© 2014 Karen Martin & Mike Osterling
Value Stream Mapping CharterScope Accountable Parties Logistics
Value Stream Executive Sponsor
Demand RateFacilitator
Trigger
First Step
Last Step
Current State Problems & Business Needs Mapping Team1 Function Name Contact Information
2 1
3 2
4 3
5 4
Measurable Target Condition 5
1 6
2 7
3 8
4 9
5 10
Benefits to Customers & Business On-Call Support1 Function Name Contact Information
2 1
3 2
4 3
5 4
Relevant Data Agreement1 Executive Sponsor Value Stream Champion Facilitator
2
3 Signature: Signature: Signature:
4 Date: Date: Date:
Event Dates & TimesSpecific
Conditions Value Stream
Champion
Base-camp Location
Logistics Coordinator
Meals Provided
Boundaries & Limitations Briefing Attendees
** required *optional
Briefing Dates &TimesImprovement
Timeframe
![Page 2: Value Stream Mapping Charter KMMO v14](https://reader036.vdocuments.us/reader036/viewer/2022072002/563db8e1550346aa9a97d4a0/html5/thumbnails/2.jpg)
© 2014 Karen Martin & Mike Osterling
Value Stream Mapping CharterScope Accountable Parties Logistics
Value Stream Value stream being improved Executive Sponsor Required: typically VP or C-level
Demand Rate How many times is this done per wk, qtr, mo, or yr?Facilitator
Trigger What initiates the process?
First Step Task on first process blockNot always needed
Last Step Task on last process block
What is the team NOT authorized to change?
Typically 3-6 months
Current State Problems & Business Needs Mapping Team1 What's driving the need for improvement? Function Name Contact Information
2 1 Leadership-heavy
3 2
4 3
5 4
Measurable Target Condition 5
1 Reduce <defined metric> from X to Y (Z% improvement). 6
2 Increase <defined metric> from X to Y (Z% improvement). 7
3 8
4 9
5 10
Benefits to Customers & Business On-Call Support1 How will the business, internal and external customers, and Function Name Contact Information
2 internal and external suppliers benefit from value stream improvement? 1 SMEs that may not be needed full time
3 2
4 3
5 4
Relevant Data Agreement1 What data is required to understand relevant current state issues. Executive Sponsor Value Stream Champion Facilitator
2 Examples: work volume & volume variation, process quality &
3 effectiveness, market trends, customer satisfaction, employee Signature: Signature: Signature:
4 engagement, financials, lead time, safety records, etc. Date: Date: Date:
Event Dates & Times
3 days typically; consecutive is best; 6 hrs per day minimum; 7 or 8 hrs is bestSpecific
Conditions What circumstances are included and excluded? (e.g., type of customer, geographic location, etc.)
Value Stream Champion
If needed—often director or manager level
Required: skilled, objective person leading the activity
Base-camp Location
On-site, ample wall space, quiet/private location
Logistics Coordinator
Meals Provided
Always a nice touch; keeps the team from wandering
Boundaries & Limitations Briefing Attendees
** required *optional
List the the people that are required to attend the briefings (**) and those whose attendance is optional (*).
Briefing Dates & Times
Aids in consensus building and organizational learning. Typically the last hour of the day.
Improvement Time Frame
![Page 3: Value Stream Mapping Charter KMMO v14](https://reader036.vdocuments.us/reader036/viewer/2022072002/563db8e1550346aa9a97d4a0/html5/thumbnails/3.jpg)
© 2014 Karen Martin & Mike Osterling
Value Stream Mapping CharterScope Accountable Parties Logistics
Value Stream Capital equipment Executive Sponsor Allen Ward
Nancy Little
Demand Rate 1,000 per yearFacilitator Dave Parks Surf's Up - Room A
Trigger Customer submits RFQ
First Step Sales reviews the RFQDave Parks Continential breakfast & lunch
Last Step Production ships product
Current State Problems & Business Needs Mapping Team1 Desire to stay ahead of the competition & deepen customer loyalty. Function / Title Name Contact Information
2 Forecasted growth of 15% for next fiscal year. 1 Sales, Director Sean Michaels
3 Unclear & incorrect information flowing through value stream. 2 IT, Director Diana Marie
4 Lead time for RFQ turnaround = 2 weeks; PO to software dev = 5 weeks 3 Finance, Controller Dave Gerald
5 (Competition's RFQ LT is 1 wk and PO to delivery is 4 wks) 4 Scrum Master Ryan Austin
Goals & Measurable Target Conditions 5 Engineering, Vice President Nancy Little
1 Reduce RFQ lead time by a minimum of 50%. 6 Manufacturing, Director Ambreen Motiwala
2 Reduce PO to software development lead time by a minimum of 50%. 7 Customer Service, Manager Danny Tran
3 Improve quality of information flowing throughout value stream. 8 Customer (contract manufacturer) JR Hunt
4 9
5 10
Benefits to Customers & Business On-Call Support1 Faster delivery; less hassle; less cost. Function Name Contact Information
2 Better working relationships between sales, estimating & engineering. 1 Planning / Purchasing, Planner Lourdes Dwyer
3 Freed capacity to absorb additional business w/o increasing staff. 2 Production Supervisor Tom St. James
4 3
5 4
Relevant Data Agreement1 Sales effectiveness: RFQ conversion rate. Executive Sponsor Value Stream Champion Facilitator
2 Financial: Estimate-to-actual cost comparison.
3 Operational: LT in segments (RFQ to quote; PO to development). Signature: Signature: Signature:
4 Date: Date: Date:
Event Dates & Times
July 24-26, 20138:00 am - 5:00 pmSpecific
Conditions Engineer to order, requires both hardware & software customization
Value Stream Champion
Base-camp Location
Logistics Coordinator
Meals Provided
Boundaries & Limitations
No new software; only minor changes to existing IT systems; no additional staff; no budget changes Briefing Attendees
** required *optional
** Allen W (COO), Joe M (CIO), Sal T (VP Sales)* Bruce R (VP Ops), Carlos P (HR), Su T (CFO), Bill M (VP CS)
Briefing Dates & Times
July 24, 25, & 264:00-5:00 pmImprovement Time
FrameFuture state design is fully realized by December 31, 2013.
![Page 4: Value Stream Mapping Charter KMMO v14](https://reader036.vdocuments.us/reader036/viewer/2022072002/563db8e1550346aa9a97d4a0/html5/thumbnails/4.jpg)
Order Now!
Karen Martin, Author and President The Karen Martin Group, Inc.
858.677.6799
Mike Osterling, Author and PresidentOsterling Consulting, Inc.
619.572.3632www.ksmartin.com www.mosterling.com