use of 3d technologies for managing utilities · use of 3d technologies for managing utilities...
TRANSCRIPT
Use of 3D Technologies for Managing Utilities
Research Contract DTFH61-12-C-00025
Federal Highway Administration
Cesar Quiroga, Ph.D., P.E. Senior Research Engineer, Texas A&M Transportation Institute
Traditional 2D Plan View
Use of 3D Technologies for Managing Utilities 2
3D Model Including Utilities
Use of 3D Technologies for Managing Utilities 3
Utility Process and 3D Workflows
• Comprehensive development agreements (CDAs) – Concession development agreements
• Developer is responsible for all utility investigations
– Design-build projects • TxDOT conducts QLB (and some QLA) utility investigations
– Contract provision to support the use of 3D models • 3D model of existing surface AND underground features
(drainage structures, bridge and wall foundations, and utilities) • 3D design features for existing and proposed elements of work • Software that enables interactive 3D visualizations
Use of 3D Technologies for Managing Utilities 4
Utility Process and 3D Workflows
• Design-bid-build projects – TxDOT conducts QLB (and some QLA) utility
investigations, but not consistently – Transition from 2D to 3D
• Business case • Plan on how to train TxDOT staff on the process to build 3D
models internally • Focus on basic functionality, not sophisticated rendering • Roadway surface and drainage features • Utilities: Broken lines shown on surface if Z data are not
available
Use of 3D Technologies for Managing Utilities 5
FHWA Research Objectives
• Feasibility of having SHAs as the central repository of utility data within the state highway right-of-way
• Potential benefits of having accurate utility data available during project development and delivery
• Barriers for collecting and managing utility location data, as well as strategies to overcome those barriers
• Cost to manage 3D utility location data and mark utilities with RFID technology
Use of 3D Technologies for Managing Utilities 6
2D Utility Mapping • Utility location services: X, Y • Test holes at specified locations: Z (X, Y if surveyed) • ASCE/CI 38-02 Standard Guideline:
– QLD: Review of existing records: X, Y – QLC: Survey of visible appurtenances: X, Y – QLB: Geophysical methods for underground utilities: X, Y – QLA: Exposed utilities at specified locations: X, Y, Z
• Test holes • Valves • Manholes • Vaults • Building basement walls
Use of 3D Technologies for Managing
Utilities 7
Locations with QLA Data
Use of 3D Technologies for Managing Utilities 8
Test hole Test hole Valve
Manhole
Assumed Curved Pipe Alignment
Use of 3D Technologies for Managing Utilities 9
Test hole Test hole Valve
Manhole
Assumed Straight Pipe Alignment
Use of 3D Technologies for Managing Utilities 10
Test hole Test hole Valve
Manhole
Assumed Horizontal Interpolation
Use of 3D Technologies for Managing Utilities 11
Test hole Test hole Valve
Manhole
GPR and EMI Arrays
GPR array EMI array
Use of 3D Technologies for Managing Utilities 12
3D Imagery – GPR Array
3D imagery Interpreted pipe locations
Use of 3D Technologies for Managing Utilities 13
3D Imagery – EMI Array
Use of 3D Technologies for Managing Utilities 14
Zoomed-in view, all levels shown
Zoomed-in view, with one level hidden
3D Model of Existing Facilities
Use of 3D Technologies for Managing Utilities 15
Case Studies
• California: Data model, 3D modeling, 3D utility inventory • Connecticut: Guidelines for use of 3D in projects • Florida: Radar tomography for 3D utility mapping • Iowa: 3D for design and grading and paving AMG • North Carolina: data collection costs, 3D visualization • Texas: 3D for design and construction, utility conflict • Virginia: RFID for utility monitoring and inventory • Washington State: 3D for design and visualization • Wisconsin: 3D utility data collection
Use of 3D Technologies for Managing Utilities 16
California – Port of Los Angeles
• $42M Berths 144-145 Backland Improvement Project • 21 acres of container terminal backland improvements • Design while existing berth was in operation
– Limited utility investigation capability – Existing utility records and info from utility companies
• Utility conflict management during construction – GPR-based utility inventory + test holes – 3D of existing and proposed utility installations – Effective web-based communication with designer
Use of 3D Technologies for Managing Utilities 17
Use of 3D Technologies for Managing Utilities 18
Use of 3D Technologies for Managing Utilities 19
California – Port of Los Angeles
• Lessons learned: – Importance of quality inventory of existing utilities to
manage conflicts during construction – Focus on the basics, i.e., 3D design with no frills – Highly cost effective, will continue to use 3D for future
construction projects • Already used 3D for AMG earthwork • Would like to include utilities (both existing and proposed) • Need for standard library of 3D components
– Better to resolve utility conflicts during design
Use of 3D Technologies for Managing Utilities 20
Texas – TxDOT
• Grand Parkway Project in Houston • $1.1 billion for segments F-1, F-2, and G
Use of 3D Technologies for Managing Utilities 21
Texas – TxDOT
• 3D utility model and utility conflict resolution: – Review all previous utility information, including QLB data – Collect additional QLB and QLA data
• New utility installations on the ground after bidding
– Strengthen utility permitting process • PE signature and seal required • Field inspection and surveying required
– Build 3D utility model and integrate into main 3D model – Conduct ‘hard’ and ‘soft’ clash detections – Use UCM approach from SHRP 2 R15B
Use of 3D Technologies for Managing Utilities 22
Washington State – WSDOT
• Process to develop 3D utility model: – Calculate spot utility elevations from data gathered at
points such as vaults, valves, basements, and records – Use SMEs to estimate depths between spot locations – Develop 3D utility model – Collect QLA data at critical locations – Update 3D utility model as needed
Use of 3D Technologies for Managing Utilities 23
Washington State – WSDOT
• Maintain the utility data current during PDP: – Review all city construction permits
• Check for utility conditions that do not need a permit
– Review all One Call tickets – Contact utility owners and request information on
any changes – Walk the project and scan for evidence of new
construction – Conduct QLB investigation at locations with changes
Use of 3D Technologies for Managing Utilities 24
Project Impacts
Use of 3D Technologies for Managing Utilities 25
Cost/Benefit Item Project Impact
Costs of 3D modeling/BIM Additional upfront cost Minor project cost impact
Difficult to separate cost to develop 3D models
Minor project cost impact
Benefits of 3D modeling/BIM Reduction in construction change orders
75% fewer change orders
Project cost savings 4-15% of total project cost
Project Impacts
Use of 3D Technologies for Managing Utilities 26
Cost/Benefit Item Project Impact
Costs of conventional QLB/QLA utility investigations
Cost to gather QLB and QLA data
0.2-3% of total project cost
Benefits of conventional QLB/QLA utility investigations
Coverage and detection 80-90% of utility facilities
Project cost savings 4% of total project cost
Costs of using advanced geophysics to generate 3D inventory of utilities
Cost to gather data 0.1-2% of total project cost
Benefits of using advanced geophysics to generate 3D inventory of utilities
Additional utility features detected and mapped
Depends on local conditions
Depth identification Significant benefit
Project cost savings Up to 4% of total project cost
Implementation Goals
Facilitate the development of
reliable repositories of utility facility
data
Highlight the benefits of
reliable, accurate utility data
during project development and delivery
Address barriers for collecting
and managing utility location
data
Document the cost and ROI of
collecting, using, and maintaining 3D utility data
Provide strategic support to
implementable strategies
Use of 3D Technologies for Managing Utilities 27
Goal 1 Goal 2 Goal 3 Goal 4 Goal 5
Overarching Goal: Manage Utilities within the Highway Right-of-Way Effectively
Implementation Strategies
Use of 3D Technologies for Managing Utilities 28
•Use utility data model •Strengthen utility permitting requirements •Update SHA policies and procedures
Goal 1: Facilitate the development of reliable
repositories of utility facilities
•Conduct webinars to highlight benefits of reliable utility inventories
Goal 2: Highlight the benefits of reliable, accurate
utility data during project development and delivery
•Use standards-based utility data collection and reporting protocols • Include mechanisms to update database in response to changes • Integrate 3D utility conflict management process
Goal 3: Address barriers for collecting and managing
utility location data
•Develop catalog of projects that manage utilities in 3D •Promote the use of RFID technology to mark utilities •Assess total cost of damage to underground utilities
Goal 4: Document the cost and ROI of collecting, using, and maintaining 3D utility
data
Implementation Strategies •Develop robust, reference 3D utility data model •Develop robust data exchange standard for utilities •Develop library of 3D components for utility installations •Develop manual for effective utility investigations • Improve coordination between SHAs and the One Call process •Develop tool to quantify utility location risk levels
Goal 5: Provide strategic support to implementable
strategies
Use of 3D Technologies for Managing Utilities 29
Thank You!
• Additional information: – Cesar Quiroga, Ph.D., P.E. – Email: [email protected] – Phone: (210) 321-1229
Use of 3D Technologies for Managing Utilities 30