uat #1 & #2 protection relay setting & testing
DESCRIPTION
RELAY PROTECTIONTRANSCRIPT
UUUUAAAAT No.1 & No.2 T No.1 & No.2 T No.1 & No.2 T No.1 & No.2 Protection Relay Setting & Protection Relay Setting & Protection Relay Setting & Protection Relay Setting & TestTestTestTestinginginging
Contents
1. Setting of UAT #1 Protection Relay - - - - - - - - - - P. 3 – P13
2. UAT #1 Protection Relay Test Record Sheet - - - - - P.14 – P.21
3. Setting of UAT #2 Protection Relay - - - - - - - - - - - P. 22 – P.32
4. UAT #2 Protection Relay Test Record Sheet - - - - - P. 33 – P.40
1. Setting of UAT #1 Protection Relay
Setting of UAT-1 Protection Relay Type RET670F87T - Unit Aux. Transformer Differential Protection
1. Terminal identification
Station Name : KERAMASANBay Name: UAT-1Relay Name RET 670Relay serial NoFrequency 50 HzAux voltage 110 VDC
2. General Data
Transformer: GSUT-1, two windingRated data : Rated power 6 MVA
Voltage ratio 11 kV / 6.3 kVW1 rated current - Ir1 315 AW2 rated current - Ir2 550 AConnection Dyn11 (resistive grounding at Y winding)p.u. Impedance 0.08at Base 6
CT ratio W1 (11kV) 750 / 1 ACT ratio W2 (6.3kV) 1250 / 1 A
VT ratio W1 11 / 0.11 kVVT ratio W2/W3 6.3 / 0.11 kV
Short circuit data :
Three-phase short circuit current at 6.3kV busbar 9300 APhase to Ground short circuit current at 6.3kV busbar 11 APhase current contribution of UAT for 3-Ph fault at 6.3kV busbar 6580 Ameasured at 6.3kV sidePhase current contribution of UAT for 3-Ph fault at 6.3kV busbar 3768.5 Ameasured at 11kV side
3. Setting Considerations
Protection Scheme - Transformer 2 winding differential protection (87T) is applied as main
protection to mostly protect the transformer from internal phase to phase fault.Very small earth fault current due to resistive grounding makes REF protection will not be effective and sensitive enough to protect the transformer frominternal earth fault. Therefore, sensitive earth fault protection relay shall then be provided in the backup protection relay.
Differential current setting (Idmin)
UAT1 F87T 1/4 Keramasan
The usual practice for transformer protection is to set the bias characteristic to a value of at least twice the value of the expected spill current underthrough faults conditions. Spill current may arise from several conditions such as : - transformer phase shift and ratio error - current transformer ratio error - different CTs characteristicIdmin of 0.3 x Ibase is normally recommended to be applied.
Zero-sequence current substraction A differential protection may operate unwanted due to external earth faults in cases where the zero sequence current can flow only on one side of the power transformer
but not on the other side. This is the situation when the zero sequence currentcan not be properly transformed to the other side of the power transformerhaving a combined Y and D connection group. In such case, the zero sequencesubstraction function shall be set ON for Y winding and OFF for D winding.
4. Setting of analogue inputConfigure analogue inputs for TRM1 (-X401) :Set analogue current channels
AI1 AI2 AI3 AI4 AI5Ctprim = 750 750 750 1250 1250Ctsec = 1 A 1 A 1 A 1 A 1 ACTStarPoint = To Object To Object To Object To Object To Object
AI6 AI7 AI8 AI9Ctprim = 1250 not used not used not usedCtsec = 1 A not used not used not usedCTStarPoint = To Object not used not used not used
Set analogue voltage channelsAI10 AI11 AI12
Vtprim = not used not used not usedVtsec = not used not used not used
5. Protection Settings
5.1. Setting of the Differential function data under T2WPDIF General settings.
Winding 1 (W1) Winding 2 (W2)RatedVoltageW1 11 kV RatedVoltageW2 6.3 kVRatedCurrentW1 315 A RatedCurrentW2 550 AConnectTypeW1 D ConnectTypeW2 YTconfigForW1 No TconfigForW2 NoCT1ratingW1 750 A CT1ratingW2 1250 AZSCurrSubtrW1 Off ZSCurrSubtrW2 On
ClockNumberW2 11
UAT1 F87T 2/4 Keramasan
Note : All other setting parameters under general setting are not relevant. Use default values.
5.2. Differential Protection Setting (87T) under T2WPDIF Setting group:
Operation = OnOperation of SOTF feature
SOTFMode = OffSetting of differential current alarm
IDiffAlarm = 0.2 *IbaseSetting of time delay of differential current alarm
tAlarmDelay = 10 sSetting of minimum differential operating current
IdMin = 0.3 *IbaseSetting of cross-over point between slope 1 and slope 2
EndSection1 = 1.25 IbaseSetting of slope 2 stabilisation, Slope 1 has fixed stabilization
SlopeSection2 = 40% *IbiasSetting of cross-over point between slope 2 and slope 3
EndSection2 = 3.00 IbaseSetting of slope 2 stabilisation
SlopeSection3 = 80% *IbiasSetting of minimum differential operating current for unrestraint step
Idunre = 20.00 *IbaseSet the operation of Cross Blocking logic On-Off
OpCrossBlock = OnSet the second and fifth harmonic stabilizing level when transformers are inside the zone
I2/I1Ratio = 15%I5/I1Ratio = 25%
Set the operation of Negative sequence differential protectionNegSeqDiffEn = No
Setting of minimum negative sequence differential current levelIMinNegSeq = 0.04
Setting of the Relay operating anglesNegSeqROA = 60 deg
Set the operation of Open CT detectionOpenCTEnable = No
Note : All other setting parameters under this setting group are not relevant.
5.3. All other protection functions
Operation = Off
6. Assignment of Binary Input BIM_3
UAT1 F87T 3/4 Keramasan
BIM_3.BI01 : Bucholz Trip
BIM_3.BI02 : Rapid Pressure Relay TripBIM_3.BI03 : Oil Level Low Low TripBIM_3.BI04 : Protective Relay TripBIM_3.BI05 : Oil Temperature TripBIM_3.BI06 : HV Winding Temperature TripBIM_3.BI07 : Not usedBIM_3.BI08 : Trip from Generator Protection (59BG)BIM_3.BI09 : Trip from Generator Protection (52G Mech Fail)BIM_3.BI10 : Trip from GSUT ProtectionBIM_3.BI11 : Reset Lockout
BIM_3.BI12 : Not usedBIM_3.BI13 : Not usedBIM_3.BI14 : Not usedBIM_3.BI15 : Not usedBIM_3.BI16 : Not used
7. Assignment of Binary Output BOM_4
BOM_4.BO01 : Transformer Differential Trip (T2WPDIF)
BOM_4.BO02 : Not usedBOM_4.BO03 : Trip from Generator Protection
BOM_4.BO04 : Trip from UAT Transformer's Protection (Bucholz etc)
BOM_4.BO05 : Not usedBOM_4.BO06 : Not usedBOM_4.BO07 : Not usedBOM_4.BO08 : Not usedBOM_4.BO09 : Transformer Differential Trip (T2WPDIF)
BOM_4.BO10 : Not usedBOM_4.BO11 : Trip from Generator ProtectionBOM_4.BO12 : Not usedBOM_4.BO13 : Trip from UAT Transformer's Protection (Bucholz etc)
BOM_4.BO14 : Trip from GSUT ProtectionBOM_4.BO15 : Transformer Differential Trip (T2WPDIF)
BOM_4.BO16 : Not usedBOM_4.BO17 : Trip from GSUT ProtectionBOM_4.BO18 : Trip from Generator Protection
BOM_4.BO19 : Not usedBOM_4.BO20 : Not usedBOM_4.BO21 : Not usedBOM_4.BO22 : Not usedBOM_4.BO23 : Not usedBOM_4.BO24 : Not used
UAT1 F87T 4/4 Keramasan
Setting of UAT-1 Protection Relay Type REF615F5051 - Backup OC & EF Protection
1. Terminal identification
Station Name KERAMASANBay Name: UAT-1Relay Name REF615Relay serial NoFrequency 50 HzAux voltage 110 VDC
2. General Data
Transformer: UAT-1, two windingRated data : Rated power 6 MVA
Voltage ratio 11 kV / 6.3 kVW1 rated current - Ir1 315 AW2 rated current - Ir2 550 AConnection Dyn11 (resistive grounding at Y winding)p.u. Impedance 0.08at Base 6
CT ratio W1 (11kV) 750 / 1 ACT ratio W2 (6.3kV) 1250 / 1 A
Short circuit data :Three-phase short circuit current at 6.3kV busbar 9300 APhase to Ground short circuit current at 6.3kV busbar 11 APhase current contribution of UAT for 3-Ph fault at 6.3kV busbar 6580 Ameasured at 6.3kV sidePhase current contribution of UAT for 3-Ph fault at 6.3kV busbar 3768.5 Ameasured at 11kV side
Maximum tripping time for 6.3kV outgoing feeders Instantaneous
3. Setting Considerations
Protection Scheme - Low-set phase overcurrent (51) protection at 11kV side are used as backup
protection for differential (87T) and REF (87REF) protection.To maintain selectivity against downstream protection relays, a time delay of 0.5s on top of the downstream (6.3kV outgoing feeders) protection relays maximum operating time shall be introduced.
- Instantaneous-set overcurrent (50) at 11kV side is applied to protect the transformer during short circuit condition. Time delay shall be introduced to maintain selectivityfrom the fault which occur at the other parts of the system.
UAT1 F5051 1 of 6 Keramasan
- Sensitive earth fault/SEF (50S) of this relay will be applied at 6.3kV to detectearth fault condition at 6.3kV system. To maintain selectivity against earth faultprotection relay at 6.3kV outgoing feeders, a time delay of 0.5s on top of the outgoing feeders tripping time is introduced. As the fault current is considerably small,a longer operating time is somehow still acceptable as long as not exceeding therated time of NGR (10s).
- To avoid unwanted operation of the overcurrent and earth fault protection due toinrush current during transformer startup, the inrush detection element INRPHARis activated to give a blocking signal to the overcurrent & earth fault element wheninrush current is detected.
4. Setting of analogue inputAnalog input settings, phase currents
Secondary current = 1 APrimary current = 750 A
Amplitude corr. A = 1Amplitude corr. B = 1Amplitude corr. C = 1
Nominal current = 315 A {In}Rated secondary value = 3 mV/Hz
Reverse polarity = 0 {False}
Analog input settings, residual currents
Secondary current = 1 APrimary current = 1250 AAmplitude corr. = 1
Reverse polarity = 0 {False}
5. General System SettingRated frequency = 50 Hz
Phase rotation = ABCBlocking mode = Freeze timer
Bay Name = UAT2IDMT saturation point = 50
6. Setting of Three Phase Overcurrent Function (PHxPTOC) on 11 kV side
6.1. PHIPTOC (Instantaneous) Non group settings:
Activation of the PHIPTOC functionOperation = 1 { 1=On }
Number of phases required for operate activationNum of start phase = 1 { 1=1-out-of-3 }
Reset delay timeReset delay time = 20 ms { instantaneous }
UAT1 F5051 2 of 6 Keramasan
6.2. PHIPTOC (Instantaneous) Group settings:
Start values is set at 130% of transformer short circuit current to get selectivity with faults at 6.3kV.Start Value PHHPTOC = 130% x 3768.5 A
= 4899.1 AStart Value PHHPTOC = 15.6 x In
Operate delay timeOperate delay time = 20 ms { instantaneous }
Note : All other setting parameters are not relevant. Default values can be used.
6.3. PHHPTOC (high-set) Non group settings:
Activation of the PHHPTOC functionOperation = 5 { 5=Off }
Note : All other setting parameters are not relevant. Default values can be used.
6.4. Setting of parameters for PHLPTOC (low-set) Non-group Setting
Activation of the PHLPTOC functionOperation = 1 { 1=On }
Number of phases required for activationNum of start phase = 1 out of 3
Minimum operate time for IDMT curveMin. oper. Time = 40 ms
Reset delay timeReset delay time = 20 ms
Curve parameter for programmable curveCurve parameter A, B, C, D, E = default {NA}
6.5. PHLPTOC (low-set) Group settings:Start values is set at 110% of transformer rated current.
Start Value PHLPTOC = 120% x 315 A= 378 A
Start Value PHLPTOC = 1.2 x InMultiplier for scalng the start value
Start value Mult = 1Time multiplier setting (TMS)
Time multiplier = 1 {See note below}Operate delay time
Time delay PHLPTOC = 400 ms {Not relevant for inverse type}Operating curve type
Curve PHLPTOC = IEC Extremely InverseSelection of reset curve type
Type of reset curve = 1 {Immediate}
Note : Time delayed PHLPTOC shall be set to operate in about 0.8 s at short circuit
UAT1 F5051 3 of 6 Keramasan
current to give safe margin to the transformer main protection and other unit protection at the other part of the system.Short circuit current = 3768.5 A
= 12 x Inwith start value = 1.2 x Inand set time multiplier = 1for extremely inverse curve, the operating time t is :
t = 0.814 s --> OK
7. Setting of Earth Fault Protection Function (EFxPTOC) on 6.3 kV side
7.1. EFIPTOC (Instantaneous) Non group settings:
Activation of the EFIPTOC functionOperation = 5 { 5=Off }
Note : All other setting parameters are not relevant. Default values can be used.
7.2. EFHPTOC (high-set) Non group settings:
Activation of the EFHPTOC functionOperation = 5 { 5=Off }
Note : All other setting parameters are not relevant. Default values can be used.
7.3. EFLPTOC (low-set) Non group settings:
Activation of the EFLPTOC functionOperation = 1 { 1=On }
Minimum operate time for IDMT curveMin. oper. Time = 40 ms
Reset delay timeReset delay time = 20 ms
Curve parameter for programmable curveCurve parameter A, B, C, D, E = default {NA}
Selection for used Io signalIo signal Sel = 1 {Measured Io)
7.3. EFLPTOC (low-set) Group settings:Start value for earth fault is set at 50% of maximum earth fault current.
Start Value EFLPTOC = 50% x 11 A {See note below}= 6 A
Start Value EFLPTOC = 0.02 x InMultiplier for scalng the start value
Start value Mult = 1Time multiplier setting (TMS)
Time multiplier = 0.1 {See note below}Operate delay time
UAT1 F5051 4 of 6 Keramasan
Time delay EFLPTOC = 0.9 sOperating curve type
Curve EFLPTOC = Definite timeSelection of reset curve type
Type of reset curve = 1 {Immediate}
8. Setting of Inrush Detector INRPHAR
8.1. Inrush Detector INRPHAR Group SettingRatio of the 2nd to the 1st harmonic leading to restraint
Start value = 0.15 %Operate delay time
Operate delay time = 20 ms
8.2. Inrush Detector INRPHAR Non Group Setting
Activation of the INRPHAR functionOperation = 1 { 1=On }
Reset delay timeReset delay time = 20 ms
9. All other protection functions
Operation = 5 { 5=Off }
10. Assignment of Binary Input
Binary Input Terminal -X110_
BI1 : Not usedBI2 : Not usedBI3 : Not usedBI4 : Not usedBI5 : Not usedBI6 : Not usedBI7 : Not usedBI8 : Not usedBI9 : Not usedBI10 : Not used
Binary Input Terminal -X120_
BI1
BI2
BI3
BI4 : Reset lockout
11. Assignment of Binary Output
UAT1 F5051 5 of 6 Keramasan
Binary Output Terminal -X100_
PO1 : Overcurrent Trip
(Operation of PHHPTOC, PHLPTOC)
PO2 : SEF Trip
(Operation of EFLPTOC)
SO1 : Overcurrent Trip
SO2 : SEF Trip
PO3
PO4
Binary Output Terminal -X110_
SO1 : Overcurrent Trip
SO2 : SEF Trip
SO3
SO4
UAT1 F5051 6 of 6 Keramasan
2. UAT #1 Protection Relay Test Record Sheet
Equipment :
Feeder :
1. Reference Drawing
Schematic Diagram :
Transformer Bay :
2. General Data
Manufacture : Designation :
Type : Sereal No. :
3. Commissioning Tests
3.1 Visual Check
a) Physically Good ? :
b) Relay Healthy ? :
c) Mounting and wiring completed ? :
Protection Relay Test
Unit Aux. Transformer Differential Protection Relay RET670
UAT #1
KPP-00-TPS-W-141
11kV 6.3kV UAT #1
ABB
RET670
F87T
c) Mounting and wiring completed ? :
3.2 Verifying the connections and the analog inputs
Apply input signals as needed and verify that signals are measured correctly
1
2
3
4
5
6
7
No. ProcedureInjected Values
Secondary
Measured
Values PrimaryRemarks
Inject current phase R → A101 A A
Inject current phase R → A104 A A
Inject current phase S → A105 A A
Inject current phase S → A102 A A
Inject current phase T → A103 A A
Inject current phase T → A106 A A
Inject current Neutral → A107 A A
Contractor
3.3 Deferential Protection Test
(1) Check on HV side Secondary Injection
No. Procedure Items to be verified. Remarks
1 Make sure that REF and OC / EF
function are set to off.
2 Connect the test set for injection of 3
phase current to the current terminals
of RET670 which are connected to the
CT's on HV side of transformer
3 Increase the current in phase L1 until
the protection operates and check
L1
a) the operating current (Iop) a) Iop : A
b) Trip contacts operation b) Trip contact :
Operate / Not operate
c) Alarm contact operation c) Alarm contact :
a) Iop : A
b) Trip contacts operation b) Trip contact :
Operate / Not operate
4 Increase the current in phase L2 until
the protection operates and check
L2 For stable condition,
Trip not operated
a) the operating current (Iop)
Operate / Not operate
For stable condition,
Trip not operated
a) the operating current (Iop) a) Iop : A
b) Trip contacts operation b) Trip contact :
Operate / Not operate
c) Alarm contact operation c) Alarm contact :
Operate / Not operate
c) Alarm contact operation c) Alarm contact :
Operate / Not operate
Operate / Not operate
5 Increase the current in phase L3 until
the protection operates and check
L3
Contractor
(2) Check on LV side Secondary Injection
No. Procedure Items to be verified. Remarks
c) Alarm contact operation c) Alarm contact :
Operate / Not operate
1 Connect the test set for injection of 3
phase current to the current terminals
of RET670 which are connected to the
CT's on LV side of transformer
3 Increase the current in phase L2 until
the protection operates and check
L2
Operate / Not operate
2 Increase the current in phase L1 until
the protection operates and check
L1
a) the operating current (Iop) a) Iop : A
b) Trip contacts operation b) Trip contact :
Operate / Not operate
c) Alarm contact operation c) Alarm contact :
a) the operating current (Iop) a) Iop : A
b) Trip contacts operation b) Trip contact :
Operate / Not operate
4 Increase the current in phase L3 until L3
c) Alarm contact operation c) Alarm contact :
Operate / Not operate
4 Increase the current in phase L3 until
the protection operates and check
L3
a) the operating current (Iop) a) Iop : A
b) Trip contacts operation b) Trip contact :
Operate / Not operate
Contractor
3.4 6.3kV Restricted EF Protection Test
(1) Secondary Injection
No.
4. Remarks :
Procedure Items to be verified. Remarks
1 Make sure that Differential protection
and OC/EF function are set to off.
2 Connect the test set for injection of
neutral current to the current terminals
of RET670 to which the NCT 20kV is
connected
3 Increase the current in until the
protection operates and check
L1
a) the operating current (Iop) a) Iop : A
b) Trip contacts operation b) Trip contact :
Operate / Not operate
c) Alarm contact operation c) Alarm contact :
Operate / Not operate
Contractor
Equipment :
Feeder :
1. Reference Drawing
Schematic Diagram :
Transformer Bay :
2. General Data
Manufacture : Designation :
Type : Sereal No. :
3. Commissioning Tests
3.1 Visual Check
a) Physically Good ? :
b) Relay Healthy ? :
c) Mounting and wiring completed ? :
Protection Relay Test
Backup OC & EF Protection Relay REF615
UAT #1
KPP-00-TPS-W-141
11kV 6.3kV UAT
ABB
RET615
F5051
1VHR91059397
c) Mounting and wiring completed ? :
3.2 Verifying the connections and the analog inputs
Apply input signals as needed and verify that signals are measured correctly
1
2
3
4
No. ProcedureInjected Values
Secondary
Measured
Values PrimaryRemarks
Inject current phase T A A
Inject current phase N A A
Inject current phase R A A
Inject current phase S A A
Contractor
3.3 Testing of the phase overcurrent protection
The test is performed as a secondary test, by injecting current to the current energizing
inputs with the setting values used during normal operation
No.
2 Inject the current (Ii) in phase L2
Procedure Items to be verified. Remarks
1 Inject the current (Ii) in phase L1
Ii = 2.5 * I > * rated current input Start of stage I > :
.I > setting : * In
Ii = 2.5 * I > * rated current input Start of stage I > :
.I > setting : * In Trip of stage I > :
.t > setting :
s
Operation time :
s
Trip of stage I > :
.t > setting :
s
Operation time :
s
3 Inject the current (Ii) in phase L3
Ii = 2.5 * I > * rated current input Start of stage I > :
.I > setting : * In Trip of stage I > :
.t > setting :
s
Operation time :
s4 Inject the current (Ii) in phase L1
Ii = 8 * I >>> * rated current input Start of stage I >>> :
.I >>> setting : * In Trip of stage I >>> :
.t >>> setting :
s
Operation time :
s5 Inject the current (Ii) in phase L2
Ii = 8 * I >>> * rated current input Start of stage I >>> :
.I >>> setting : * In Trip of stage I >>> :
.t >>> setting :
s
Operation time :
s6 Inject the current (Ii) in phase L3
5 Inject the current (Ii) in phase L2
Ii = 8 * I >>> * rated current input Start of stage I >>> :
.I >>> setting : * In Trip of stage I >>> :
.t >>> setting :
s
Operation time :
s
Contractor
3.4 Testing of the earth fault protection
The test is performed as a secondary test, by injecting current to the current energizing
inputs with the setting values used during normal operation
No.
4. Remarks :
Start of stage I > :
.I0 > setting : * In Trip of stage I > :
.
2 Inject the current (Ii) in the earth fault
Procedure Items to be verified.
energizing input :
Ii = 2.5 * I0 >> * rated current input Start of stage I >> :
.I0 >> setting : * In Trip of stage I >> :
.t0 >> setting : s Operation time :
s
Remarks
1 Inject the current (Ii) in the earth fault
energizing input :
Ii = 2.5 * I0 > * rated current input
t0 > setting : s Operation time :
s
Contractor
3. Setting of UAT #2 Protection Relay
Setting of UAT-2 Protection Relay Type RET670F87T - Unit Aux. Transformer Differential Protection
1. Terminal identification
Station Name : KERAMASANBay Name: UAT-2Relay Name RET 670Relay serial NoFrequency 50 HzAux voltage 110 VDC
2. General Data
Transformer: GSUT-2, two windingRated data : Rated power 6 MVA
Voltage ratio 11 kV / 6.3 kVW1 rated current - Ir1 315 AW2 rated current - Ir2 550 AConnection Dyn11 (resistive grounding at Y winding)p.u. Impedance 0.08at Base 6
CT ratio W1 (11kV) 750 / 1 ACT ratio W2 (6.3kV) 1250 / 1 A
VT ratio W1 11 / 0.11 kVVT ratio W2/W3 6.3 / 0.11 kV
Short circuit data :
Three-phase short circuit current at 6.3kV busbar 9300 APhase to Ground short circuit current at 6.3kV busbar 11 APhase current contribution of UAT for 3-Ph fault at 6.3kV busbar 6580 Ameasured at 6.3kV sidePhase current contribution of UAT for 3-Ph fault at 6.3kV busbar 3768.5 Ameasured at 11kV side
3. Setting Considerations
Protection Scheme - Transformer 2 winding differential protection (87T) is applied as main
protection to mostly protect the transformer from internal phase to phase fault.Very small earth fault current due to resistive grounding makes REF protection will not be effective and sensitive enough to protect the transformer frominternal earth fault. Therefore, sensitive earth fault protection relay shall then be provided in the backup protection relay.
Differential current setting (Idmin)
UAT2 F87T 1/4 Keramasan
The usual practice for transformer protection is to set the bias characteristic to a value of at least twice the value of the expected spill current underthrough faults conditions. Spill current may arise from several conditions such as : - transformer phase shift and ratio error - current transformer ratio error - different CTs characteristicIdmin of 0.3 x Ibase is normally recommended to be applied.
Zero-sequence current substraction A differential protection may operate unwanted due to external earth faults in cases where the zero sequence current can flow only on one side of the power transformer
but not on the other side. This is the situation when the zero sequence currentcan not be properly transformed to the other side of the power transformerhaving a combined Y and D connection group. In such case, the zero sequencesubstraction function shall be set ON for Y winding and OFF for D winding.
4. Setting of analogue inputConfigure analogue inputs for TRM1 (-X401) :Set analogue current channels
AI1 AI2 AI3 AI4 AI5Ctprim = 750 750 750 1250 1250Ctsec = 1 A 1 A 1 A 1 A 1 ACTStarPoint = To Object To Object To Object To Object To Object
AI6 AI7 AI8 AI9Ctprim = 1250 not used not used not usedCtsec = 1 A not used not used not usedCTStarPoint = To Object not used not used not used
Set analogue voltage channelsAI10 AI11 AI12
Vtprim = not used not used not usedVtsec = not used not used not used
5. Protection Settings
5.1. Setting of the Differential function data under T2WPDIF General settings.
Winding 1 (W1) Winding 2 (W2)RatedVoltageW1 11 kV RatedVoltageW2 6.3 kVRatedCurrentW1 315 A RatedCurrentW2 550 AConnectTypeW1 D ConnectTypeW2 YTconfigForW1 No TconfigForW2 NoCT1ratingW1 750 A CT1ratingW2 1250 AZSCurrSubtrW1 Off ZSCurrSubtrW2 On
ClockNumberW2 11
UAT2 F87T 2/4 Keramasan
Note : All other setting parameters under general setting are not relevant. Use default values.
5.2. Differential Protection Setting (87T) under T2WPDIF Setting group:
Operation = OnOperation of SOTF feature
SOTFMode = OffSetting of differential current alarm
IDiffAlarm = 0.2 *IbaseSetting of time delay of differential current alarm
tAlarmDelay = 10 sSetting of minimum differential operating current
IdMin = 0.3 *IbaseSetting of cross-over point between slope 1 and slope 2
EndSection1 = 1.25 IbaseSetting of slope 2 stabilisation, Slope 1 has fixed stabilization
SlopeSection2 = 40% *IbiasSetting of cross-over point between slope 2 and slope 3
EndSection2 = 3.00 IbaseSetting of slope 2 stabilisation
SlopeSection3 = 80% *IbiasSetting of minimum differential operating current for unrestraint step
Idunre = 20.00 *IbaseSet the operation of Cross Blocking logic On-Off
OpCrossBlock = OnSet the second and fifth harmonic stabilizing level when transformers are inside the zone
I2/I1Ratio = 15%I5/I1Ratio = 25%
Set the operation of Negative sequence differential protectionNegSeqDiffEn = No
Setting of minimum negative sequence differential current levelIMinNegSeq = 0.04
Setting of the Relay operating anglesNegSeqROA = 60 deg
Set the operation of Open CT detectionOpenCTEnable = No
Note : All other setting parameters under this setting group are not relevant.
5.3. All other protection functions
Operation = Off
6. Assignment of Binary Input BIM_3
UAT2 F87T 3/4 Keramasan
BIM_3.BI01 : Bucholz Trip
BIM_3.BI02 : Rapid Pressure Relay TripBIM_3.BI03 : Oil Level Low Low TripBIM_3.BI04 : Protective Relay TripBIM_3.BI05 : Oil Temperature TripBIM_3.BI06 : HV Winding Temperature TripBIM_3.BI07 : Not usedBIM_3.BI08 : Trip from Generator Protection (59BG)BIM_3.BI09 : Trip from Generator Protection (52G Mech Fail)BIM_3.BI10 : Trip from GSUT ProtectionBIM_3.BI11 : Reset Lockout
BIM_3.BI12 : Not usedBIM_3.BI13 : Not usedBIM_3.BI14 : Not usedBIM_3.BI15 : Not usedBIM_3.BI16 : Not used
7. Assignment of Binary Output BOM_4
BOM_4.BO01 : Transformer Differential Trip (T2WPDIF)
BOM_4.BO02 : Not usedBOM_4.BO03 : Trip from Generator Protection
BOM_4.BO04 : Trip from UAT Transformer's Protection (Bucholz etc)
BOM_4.BO05 : Not usedBOM_4.BO06 : Not usedBOM_4.BO07 : Not usedBOM_4.BO08 : Not usedBOM_4.BO09 : Transformer Differential Trip (T2WPDIF)
BOM_4.BO10 : Not usedBOM_4.BO11 : Trip from Generator ProtectionBOM_4.BO12 : Not usedBOM_4.BO13 : Trip from UAT Transformer's Protection (Bucholz etc)
BOM_4.BO14 : Trip from GSUT ProtectionBOM_4.BO15 : Transformer Differential Trip (T2WPDIF)
BOM_4.BO16 : Not usedBOM_4.BO17 : Trip from GSUT ProtectionBOM_4.BO18 : Trip from Generator Protection
BOM_4.BO19 : Not usedBOM_4.BO20 : Not usedBOM_4.BO21 : Not usedBOM_4.BO22 : Not usedBOM_4.BO23 : Not usedBOM_4.BO24 : Not used
UAT2 F87T 4/4 Keramasan
Setting of UAT-2 Protection Relay Type REF615F5051 - Backup OC & EF Protection
1. Terminal identification
Station Name KERAMASANBay Name: UAT-2Relay Name REF615Relay serial NoFrequency 50 HzAux voltage 110 VDC
2. General Data
Transformer: UAT-2, two windingRated data : Rated power 6 MVA
Voltage ratio 11 kV / 6.3 kVW1 rated current - Ir1 315 AW2 rated current - Ir2 550 AConnection Dyn11 (resistive grounding at Y winding)p.u. Impedance 0.08at Base 6
CT ratio W1 (11kV) 750 / 1 ACT ratio W2 (6.3kV) 1250 / 1 A
Short circuit data :Three-phase short circuit current at 6.3kV busbar 9300 APhase to Ground short circuit current at 6.3kV busbar 11 APhase current contribution of UAT for 3-Ph fault at 6.3kV busbar 6580 Ameasured at 6.3kV sidePhase current contribution of UAT for 3-Ph fault at 6.3kV busbar 3768.5 Ameasured at 11kV side
Maximum tripping time for 6.3kV outgoing feeders Instataneous
3. Setting Considerations
Protection Scheme - Low-set phase overcurrent (51) protection at 11kV side are used as backup
protection for differential (87T) and REF (87REF) protection.To maintain selectivity against downstream protection relays, a time delay of 0.5s on top of the downstream (6.3kV outgoing feeders) protection relays maximum operating time shall be introduced.
- High-set overcurrent (50) at 11kV side is applied to protect the transformer during short circuit condition. Time delay shall be introduced to maintain selectivityfrom the fault which occur at the other parts of the system.
UAT2 F5051 1 of 6 Keramasan
- Sensitive earth fault/SEF (50S) of this relay will be applied at 6.3kV to detectearth fault condition at 6.3kV system. To maintain selectivity against earth faultprotection relay at 6.3kV outgoing feeders, a time delay of 0.5s on top of the outgoing feeders tripping time is introduced. As the fault current is considerably small,a longer operating time is somehow still acceptable as long as not exceeding therated time of NGR (10s).
- To avoid unwanted operation of the overcurrent and earth fault protection due toinrush current during transformer startup, the inrush detection element INRPHARis activated to give a blocking signal to the overcurrent & earth fault element wheninrush current is detected.
4. Setting of analogue inputAnalog input settings, phase currents
Secondary current = 1 APrimary current = 750 A
Amplitude corr. A = 1Amplitude corr. B = 1Amplitude corr. C = 1
Nominal current = 315 A {In}Rated secondary value = 3 mV/Hz
Reverse polarity = 0 {False}
Analog input settings, residual currents
Secondary current = 1 APrimary current = 1250 AAmplitude corr. = 1
Reverse polarity = 0 {False}
5. General System SettingRated frequency = 50 Hz
Phase rotation = ABCBlocking mode = Freeze timer
Bay Name = UAT2IDMT saturation point = 50
6. Setting of Three Phase Overcurrent Function (PHxPTOC) on 11 kV side
6.1. PHIPTOC (Instantaneous) Non group settings:
Activation of the PHIPTOC functionOperation = 1 { 1=On }
Number of phases required for operate activationNum of start phase = 1 { 1=1-out-of-3 }
Reset delay timeReset delay time = 20 ms { instantaneous }
UAT2 F5051 2 of 6 Keramasan
6.2. PHIPTOC (Instantaneous) Group settings:
Start values is set at 130% of transformer short circuit current to get selectivity with faults at 6.3kV.Start Value PHHPTOC = 130% x 3768.5 A
= 4899.1 AStart Value PHHPTOC = 15.6 x In
Operate delay timeOperate delay time = 20 ms { instantaneous }
Note : All other setting parameters are not relevant. Default values can be used.
6.3. PHHPTOC (high-set) Non group settings:
Activation of the PHHPTOC functionOperation = 5 { 5=Off }
6.4. Setting of parameters for PHLPTOC (low-set) Non-group Setting
Activation of the PHLPTOC functionOperation = 1 { 1=On }
Number of phases required for activationNum of start phase = 1 out of 3
Minimum operate time for IDMT curveMin. oper. Time = 40 ms
Reset delay timeReset delay time = 20 ms
Curve parameter for programmable curveCurve parameter A, B, C, D, E = default {NA}
6.5. PHLPTOC (low-set) Group settings:Start values is set at 110% of transformer rated current.
Start Value PHLPTOC = 120% x 315 A= 378 A
Start Value PHLPTOC = 1.2 x InMultiplier for scalng the start value
Start value Mult = 1Time multiplier setting (TMS)
Time multiplier = 1 {See note below}Operate delay time
Time delay PHLPTOC = 400 ms {Not relevant for inverse type}Operating curve type
Curve PHLPTOC = IEC Extremely InverseSelection of reset curve type
Type of reset curve = 1 {Immediate}
Note : Time delayed PHLPTOC shall be set to operate in about 0.8 s at short circuit current to give safe margin to the transformer main protection and other
UAT2 F5051 3 of 6 Keramasan
unit protection at the other part of the system.Short circuit current = 3768.5 A
= 12 x Inwith start value = 1.2 x Inand set time multiplier = 1for extremely inverse curve, the operating time t is :
t = 0.814 s --> OK
7. Setting of Earth Fault Protection Function (EFxPTOC) on 6.3 kV side
7.1. EFIPTOC (Instantaneous) Non group settings:
Activation of the EFIPTOC functionOperation = 5 { 5=Off }
Note : All other setting parameters are not relevant. Default values can be used.
7.2. EFHPTOC (high-set) Non group settings:
Activation of the EFHPTOC functionOperation = 5 { 5=Off }
Note : All other setting parameters are not relevant. Default values can be used.
7.3. EFLPTOC (low-set) Non group settings:
Activation of the EFLPTOC functionOperation = 1 { 1=On }
Minimum operate time for IDMT curveMin. oper. Time = 40 ms
Reset delay timeReset delay time = 20 ms
Curve parameter for programmable curveCurve parameter A, B, C, D, E = default {NA}
Selection for used Io signalIo signal Sel = 1 {Measured Io)
7.3. EFLPTOC (low-set) Group settings:Start value for earth fault is set at 50% of maximum earth fault current.
Start Value EFLPTOC = 50% x 11 A {See note below}= 6 A
Start Value EFLPTOC = 0.02 x InMultiplier for scalng the start value
Start value Mult = 1Time multiplier setting (TMS)
Time multiplier = 0.1 {See note below}Operate delay time
Time delay EFLPTOC = 0.9 s
UAT2 F5051 4 of 6 Keramasan
Operating curve typeCurve EFHPTOC = Definite time
Selection of reset curve typeType of reset curve = 1 {Immediate}
8. Setting of Inrush Detector INRPHAR
8.1. Inrush Detector INRPHAR Group SettingRatio of the 2nd to the 1st harmonic leading to restraint
Start value = 0.15 %Operate delay time
Operate delay time = 20 ms
8.2. Inrush Detector INRPHAR Non Group Setting
Activation of the INRPHAR functionOperation = 1 { 1=On }
Reset delay timeReset delay time = 20 ms
9. All other protection functions
Operation = 5 { 5=Off }
10. Assignment of Binary Input
Binary Input Terminal -X110_
BI1 : Not usedBI2 : Not usedBI3 : Not usedBI4 : Not usedBI5 : Not usedBI6 : Not usedBI7 : Not usedBI8 : Not usedBI9 : Not usedBI10 : Not used
Binary Input Terminal -X120_
BI1
BI2
BI3
BI4 : Reset lockout
11. Assignment of Binary Output
UAT2 F5051 5 of 6 Keramasan
Binary Output Terminal -X100_
PO1 : Overcurrent Trip
(Operation of PHHPTOC, PHLPTOC)
PO2 : SEF Trip
(Operation of EFLPTOC)
SO1 : Overcurrent Trip
SO2 : SEF Trip
PO3
PO4
Binary Output Terminal -X110_
SO1 : Overcurrent Trip
SO2 : SEF Trip
SO3
SO4
UAT2 F5051 6 of 6 Keramasan
4. UAT #2 Protection Relay Test Record Sheet
Equipment :
Feeder :
1. Reference Drawing
Schematic Diagram :
Transformer Bay :
2. General Data
Manufacture : Designation :
Type : Sereal No. :
3. Commissioning Tests
3.1 Visual Check
a) Physically Good ? :
b) Relay Healthy ? :
c) Mounting and wiring completed ? :
RET670
Protection Relay Test
Unit Aux. Transformer Differential Protection Relay RET670
UAT #2
KPP-00-TPS-W-141
11kV 6.3kV UAT #2
ABB F87T
c) Mounting and wiring completed ? :
3.2 Verifying the connections and the analog inputs
Apply input signals as needed and verify that signals are measured correctly
1
2
3
4
5
6
7
No. ProcedureInjected Values
Secondary
Measured
Values PrimaryRemarks
Inject current phase T → A103 A A
Inject current phase R → A104 A A
Inject current phase R → A101 A A
Inject current phase S → A102 A A
Inject current Neutral → A107 A A
Inject current phase S → A105 A A
Inject current phase T → A106 A A
Contractor
3.3 Deferential Protection Test
(1) Check on HV side Secondary Injection
No. Procedure Items to be verified. Remarks
a) the operating current (Iop) a) Iop : A
b) Trip contacts operation b) Trip contact :
Operate / Not operate
1 Make sure that REF and OC / EF
function are set to off.
2 Connect the test set for injection of 3
phase current to the current terminals
of RET670 which are connected to the
CT's on HV side of transformer
c) Alarm contact operation c) Alarm contact :
Operate / Not operate
4 Increase the current in phase L2 until
the protection operates and check
L2
3 Increase the current in phase L1 until
the protection operates and check
L1
For stable condition,
Trip not operated
a) the operating current (Iop) a) Iop : A
b) Trip contacts operation b) Trip contact :
Operate / Not operate
Operate / Not operate
For stable condition,
Trip not operated
a) the operating current (Iop) a) Iop : A
b) Trip contacts operation b) Trip contact :
Operate / Not operate
Operate / Not operate
c) Alarm contact operation c) Alarm contact :
c) Alarm contact operation c) Alarm contact :
Operate / Not operate
5 Increase the current in phase L3 until
the protection operates and check
L3
Contractor
(2) Check on LV side Secondary Injection
No. Procedure Items to be verified.
a) Iop : A
b) Trip contacts operation b) Trip contact :
Operate / Not operate
c) Alarm contact operation c) Alarm contact :
Remarks
1 Connect the test set for injection of 3
phase current to the current terminals
of RET670 which are connected to the
CT's on LV side of transformer
2 Increase the current in phase L1 until
the protection operates and check
L1
a) the operating current (Iop)
Operate / Not operate
3 Increase the current in phase L2 until
the protection operates and check
L2
a) the operating current (Iop) a) Iop : A
b) Trip contacts operation b) Trip contact :
Operate / Not operate
c) Alarm contact operation c) Alarm contact :
Operate / Not operate
4 Increase the current in phase L3 until L3
a) the operating current (Iop) a) Iop : A
b) Trip contacts operation b) Trip contact :
Operate / Not operate
c) Alarm contact operation c) Alarm contact :
Operate / Not operate
4 Increase the current in phase L3 until
the protection operates and check
L3
Contractor
3.4 6.3kV Restricted EF Protection Test
(1) Secondary Injection
No.
4. Remarks :
Procedure Items to be verified. Remarks
1 Make sure that Differential protection
and OC/EF function are set to off.
2 Connect the test set for injection of
neutral current to the current terminals
of RET670 to which the NCT 20kV is
connected
3 Increase the current in until the
protection operates and check
L1
a) the operating current (Iop) a) Iop : A
b) Trip contacts operation b) Trip contact :
Operate / Not operate
c) Alarm contact operation c) Alarm contact :
Operate / Not operate
Contractor
Equipment :
Feeder :
1. Reference Drawing
Schematic Diagram :
Transformer Bay :
2. General Data
Manufacture : Designation :
Type : Sereal No. :
3. Commissioning Tests
3.1 Visual Check
a) Physically Good ? :
b) Relay Healthy ? :
c) Mounting and wiring completed ? :
UAT #2
KPP-00-TPS-W-141
11kV 6.3kV UAT
ABB F5051
RET615
Protection Relay Test
Backup OC & EF Protection Relay REF615
c) Mounting and wiring completed ? :
3.2 Verifying the connections and the analog inputs
Apply input signals as needed and verify that signals are measured correctly
1
2
3
4
No. ProcedureInjected Values
Secondary
Measured
Values PrimaryRemarks
Inject current phase R A A
Inject current phase N A A
Inject current phase S A A
Inject current phase T A A
Contractor
3.3 Testing of the phase overcurrent protection
The test is performed as a secondary test, by injecting current to the current energizing
inputs with the setting values used during normal operation
No. Procedure Items to be verified. Remarks
1 Inject the current (Ii) in phase L1
Ii = 2.5 * I > * rated current input Start of stage I > :
.I > setting : * In Trip of stage I > :
.t > setting :
s
Operation time :
s2 Inject the current (Ii) in phase L2
Ii = 2.5 * I > * rated current input Start of stage I > :
.I > setting : * In Trip of stage I > :
.t > setting :
s
Operation time :
s3 Inject the current (Ii) in phase L3
Ii = 2.5 * I > * rated current input Start of stage I > :
.I > setting : * In Trip of stage I > :
.t > setting :
s
Operation time :
s4 Inject the current (Ii) in phase L1
Ii = 8 * I >>> * rated current input Start of stage I >>> :
.I >>> setting : * In Trip of stage I >>> :
.t >>> setting :
s
Operation time :
s5 Inject the current (Ii) in phase L25 Inject the current (Ii) in phase L2
Ii = 8 * I >>> * rated current input Start of stage I >>> :
.I >>> setting : * In Trip of stage I >>> :
.t >>> setting :
s
Operation time :
s6 Inject the current (Ii) in phase L3
Ii = 8 * I >>> * rated current input Start of stage I >>> :
.I >>> setting : * In Trip of stage I >>> :
.t >>> setting :
s
Operation time :
s
Contractor
3.4 Testing of the earth fault protection
The test is performed as a secondary test, by injecting current to the current energizing
inputs with the setting values used during normal operation
No.
4. Remarks :
Remarks
1 Inject the current (Ii) in the earth fault
energizing input :
Ii = 2.5 * I0 > * rated current input Start of stage I > :
.I0 > setting : * In Trip of stage I > :
.t0 > setting : s Operation time :
s2 Inject the current (Ii) in the earth fault
Procedure Items to be verified.
energizing input :
Ii = 2.5 * I0 >> * rated current input Start of stage I >> :
.I0 >> setting : * In Trip of stage I >> :
.t0 >> setting : s Operation time :
s
Contractor