Maintenance Works at Mobil Al tona Refnery October and November 2011 From early October to mid-November 2011, Mobil Altona Renery will be temporarily shut down so that we can complete an extensive maintenance program, commonly known as a ‘turnaround’. Mobil is committed to saely and reliably operating the Altona Renery at all times, and the turnaround is a key part o our scheduled maintenance program or the Rener y . We have spe nt the last two yea rs careully planning or the turnaround to ensure that impacts on the environment and local community are minimised, that we maintain a reliable uel supply or Victoria rom other sources, and that all work is completed saely and without incident.  This turnaround gives us the oppo rtunity to inspect the Renery and complete any r equired maintenance and equipment upgrades, including a number o eciency measures to reduce energy use and greenhouse gas emissions.  T ogether with other maintenance improvements since 2008, the work being carried out during the turnaround is the culmination o a $250 million investment in the Altona Renery by Mobil. This investment will ensure that we can continue to provide hal o Victoria’ s uel needs rom a sae, reliable and ecient renery here in Altona. We have contracted Transeld Services Ltd to manage the tur naround. T ranseld Services are highly experienced and have conducted previous maintenance works at the Renery . While our planning seeks to minimise impact on our neighbourhood, nearby residents may notice some increased faring, or changes to odours or noise patterns while the Rener y is initially shut down in early October and then again during the start-up activities in mid-November.  There will also be an incr ease in vehicle and pedestrian trac around the site as an additional 5 50 people will be working at the Renery during this period. I you have any questions, please call our 24-hour Community Hotline on 1800 659 527.

Upload: aoe1831

Post on 02-Apr-2018

222 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Turnaround Factsheet

7/27/2019 Turnaround Factsheet

http://slidepdf.com/reader/full/turnaround-factsheet 1/3

Maintenance Works at Mobil Altona Refnery 

October and November 2011

From early October to mid-November 2011, Mobil Altona Renery will be temporarily shut down so that we

can complete an extensive maintenance program, commonly known as a ‘turnaround’.Mobil is committed to saely and reliably operating the Altona Renery at all times, and the turnaround is a

key part o our scheduled maintenance program or the Renery. We have spent the last two years careully

planning or the turnaround to ensure that impacts on the environment and local community are minimised,

that we maintain a reliable uel supply or Victoria rom other sources, and that all work is completed saely

and without incident.

 This turnaround gives us the opportunity to inspect the Renery and complete any required maintenance

and equipment upgrades, including a number o eciency measures to reduce energy use and greenhouse

gas emissions.

 Together with other maintenance improvements since 2008, the work being carried out during the

turnaround is the culmination o a $250 million investment in the Altona Renery by Mobil. This investment

will ensure that we can continue to provide hal o Victoria’s uel needs rom a sae, reliable and ecient

renery here in Altona.

We have contracted Transeld Services Ltd to manage the turnaround. Transeld Services are highly

experienced and have conducted previous maintenance works at the Renery.

While our planning seeks to minimise impact on our neighbourhood, nearby residents may notice some

increased faring, or changes to odours or noise patterns while the Renery is initially shut down in early

October and then again during the start-up activities in mid-November. There will also be an increase in vehicle and pedestrian trac around the site as an additional 550 people

will be working at the Renery during this period.

I you have any questions, please call our 24-hour

Community Hotline on 1800 659 527.

Page 2: Turnaround Factsheet

7/27/2019 Turnaround Factsheet

http://slidepdf.com/reader/full/turnaround-factsheet 2/3

Overview o turnaround activities.

Timing You may notice

Phase 1

Shutdown 

(early October)

Increased faring

Release o steam

Noise rom steaming vessels

Dierent odours

Phase 2

Maintenance 

(early October – early

November)

Changes to normal noise patterns as plant

operation noise reduces and power tool

noise increases

Dierent odours rom vessels being

cleaned

Phase 3

Start-up

(early-mid November)

Increased faring

Release o steamNoise rom steaming vessels

Dierent odours

What works are taking place?

During the turnaround we will extensively inspect equipment and complete any required maintenance

work, as well as equipment upgrades, that are consistent with our long term equipment strategies aimed at

improving reliability and perormance.

In act, this turnaround will be the rst time we have had an opportunity to get inside some o our majorvessels since the renery was recongured with the Clean Fuels Venture in 2006. It gives us the opportunity

to get a better and detailed understanding o how the various units have been perorming.

Why does this work need to take place?

Mobil’s objective is to operate Altona Renery to world class standards o reliability and perormance. In

order to achieve this, we have an integrated, long-term strategy or maintenance and reliability. The strategy

uses best practices to dene specic actions and plans or parts o the renery, which include

both on-line programmed maintenance, as well as periodic plant shutdowns (or

turnarounds) or more extensive work.

Planning or this turnaround began two years ago. The turnaround will allow usto inspect equipment that is normally in continuous operation, undertake routine

maintenance and install improvements that will enhance perormance and

achieve energy savings.

What is the impact on the community?

 A comprehensive management plan has been developed to minimise

impact on the local community, including shutdown sequencing

to manage faring. Some additional faring may be noticeable

during the shut-down and start-up phases o the work, and

there may be dierences in odours and noise due to thedierent maintenance activities. We have notied the

local community o the works, highlighting some o the

dierences that may be noticeable during the dierent

phases o the maintenance program.

Page 3: Turnaround Factsheet

7/27/2019 Turnaround Factsheet

http://slidepdf.com/reader/full/turnaround-factsheet 3/3

What is the timing o these works?

 The turnaround will be completed in three stages rom early October to mid-November:

1. Shutdown phase – early to mid-October. Community may notice faring,

steam, noise rom steam vessels and dierent odours.

2. Maintenance phase – early October to early November. Community may notice dierent noise

patterns due to reduced plant operation noise and increased use o power tools, and some unusual

odours rom vessels being cleaned.

3. Start-up phase – early to mid-November. Community may notice faring, steam, noise rom steam

vessels and dierent odours.

 An environmental management plan has been developed to minimise impact on the local community and

environment as much as possible during each stage o the turnaround.

How many people are working at the Refnery during this period?

 There are an additional 550 people on-site at the Altona Renery while these works are being completed,

providing a signicant boost to employment and spending in the western suburbs.

Who is completing the work?Mobil has engaged the services o Transeld to assist with the turnaround. Transeld are highly experienced

in this type o work and have previously completed other maintenance activities at the Renery.

Will this aect Victoria’s uel supply?

We have careully planned this turnaround over the last two years, to ensure that the work is completed on

time and on budget without impacting on uel supplies to our customers. Additional sources o uel have

been secured and signicant work has also been carried out at the Mobil Yarraville Terminal to ensure that

increased marine shipments o uel into Melbourne during the Altona turnaround can be handled eectively.

How much are these works costing?

 This turnaround is part o an ongoing program totalling over $250 million investment in the Altona Renerysince 2008.

How do you know that this maintenance is needed?

Mobil has an ongoing plan or scheduled maintenance works to ensure the saety and reliability o the Altona

Renery. Planning or this scheduled shutdown began two years ago as part o our long term maintenance

strategy or the Renery. Shutting down the Renery will allow us to inspect equipment

normally in continuous operation, undertake routine maintenance, and install

eciency improvements.

Shutting down the whole Renery like this is inrequent, (this is the rst time

that the entire Renery is being shut down) but is necessary as part o ascheduled maintenance program to ensure continued sae and reliable

operations.