trfrfdn-20 mva(runnisaidpur)
TRANSCRIPT
20MVA Transf fdn Page 1
CLIENT POWER GRID CORPORATION OF INDIA LIMITED SHYAMA POWER (I) LTDPROJECT BIHAR SUB TRANSMISSION SYSTEM, PHASE II, PART II DESIGN NO.- 1000SUBSTATION 132/33kV Runnisaidpur S/S
Design of Transformer Foundation
Transformer Detail
Equipment Type : 20 MVA(3 Phase)Length, L 5.9 mWidth, B 3.2 mHeight from PL, H 4.5 mWeight, W 50850 Kgs
Ref drg no. EM10/D10401 (R-1) - GA of 20MVA Transformerof EMCO Ltd.
General inputs :Basic wind Speed, Vb 47 m/sRisk coefficient, k1 1.07Terrain ht & str size factor, k2 1.00Topogrphy factor, k3 1.00Design wind speed, Vz 50.29 m/sDesign wind pressure, Pz 1.517 KN/m2Seismic Zone 4Zero period acceleration value , Z 0.24
2.5g
Importance factor , I 1.5Response Reduction factor , R 3Damping 5%Ah 0.15
(R/I)
Base Shear, Vb = Ah x W 7627.50 KgsNet safe Bearing capacity 68.67 KN/m2 =7*9.81Bulk density of soil, n 18.39 KN/m3 =1.875*9.81
0Cohesion, C 34.34 KN/m2 =3.5*9.81Depth of water table 4.5 mself wt of grating 70 Kg/m2Live load on grating 300 kg/m2Thickness of gravel topping over grating 0.1 mwt of gravel topping 240 Kg/m2Partial factor of safety 2.2
Spectral acceleration coeffient for soil , Sa
= (Z/2)* (Sa/g)
Angle of repose, f 0
20MVA Transf fdn Page 2
CLIENT POWER GRID CORPORATION OF INDIA LIMITED SHYAMA POWER (I) LTDPROJECT BIHAR SUB TRANSMISSION SYSTEM, PHASE II, PART II DESIGN NO.- 1000SUBSTATION 132/33kV Runnisaidpur S/S
1. Design of Transformer main Block
Size of transformer mass block 2.35 m x 3.15 m
300
2000 1700
300
500 2350 5003350
Horizontal Force due to Wind, 40.29 KN =1.52 x 5.9 x 4.5
Add 20% for projections 48.35 KNMoment at PL, Mw 108.78 KN-m =48.35 x 4.5/2
Horiz. Force due to Seismic Load, 74.83 KN =7627.5 x 9.81/1000
Moment at PL, Ms 168.36 KN-m =74.83 x 4.5/2
Design Loads at Plinth LevelVertical Equipment Load 498.84 KN =50850 x 9.81/1000
Horizontal Shear 74.83 KNMoment 168.36 KN-m
Transformer Block300
Wall
3150 2300 1700
500
300150
400 5250 4350 400150
4150
When clear gap between wall and main block exceeds 2.0m, provide grating support column at a distance of 2.0 m from main block,Grating Area = 13.88 m2 =(5.25+4.35-3.15)/2x2.35+2.0x3.15
Grating Load due to dead weight 971.51 Kg = 70 x 13.88
20MVA Transf fdn Page 3
CLIENT POWER GRID CORPORATION OF INDIA LIMITED SHYAMA POWER (I) LTDPROJECT BIHAR SUB TRANSMISSION SYSTEM, PHASE II, PART II DESIGN NO.- 1000SUBSTATION 132/33kV Runnisaidpur S/S
Load due to gravel topping 3330.90 Kg = 240 x 13.88
20MVA Transf fdn Page 4
CLIENT POWER GRID CORPORATION OF INDIA LIMITED SHYAMA POWER (I) LTDPROJECT BIHAR SUB TRANSMISSION SYSTEM, PHASE II, PART II DESIGN NO.- 1000SUBSTATION 132/33kV Runnisaidpur S/S
Combined concentric Load 42.21 KN = (971.51 + 3330.9) x 9.81/1000
Load due to live load on grating 40.85 KN = 300 x 13.88 x 9.81/1000
Total wt due to Grating and others 83.05 KN
Check for Bearing pressure
Area of fdn 13.90 m2 = 4.15 x 3.35
Moment of Inertia, I 13.00 m4 = 4.15 x 3.35^3/12
or, Zyy = 7.76 m3 = 13/(3.35/2)
Weight of concrete(fdn only) 474.39 KN= (((1.7x25) + 0.3x25)x 3.15 x 2.35)+(3.35 x 4.15 x 0.3 x25)
Load combinations: 1) DL 1056.28 KN =498.84 + 474.39 + 83.05
2) DL+moment DL 1056.28 KN =498.84 + 474.39 + 83.05
Moment 340.46 KN-m = 74.83 x (4.5 /2 + 2.3 )
SBC at toe level 85.84 KN/m2 = ( 68.67 x 1.25 )
Pressure due overburden soil 36.79 KN/m2 = 2 x 18.39
Bearing pressure developed incase 1: 39.19 KN/m2 = 1056.28 / 13.9 - 36.79
39.19 < 68.67 Hence Okcase 2: 83.05 KN/m2
= 1056.28 / 13.9 + 340.46 / 7.76 - 36.79
83.05 < 85.84 Hence Ok
Check for Overturning
Weight of concretea) Pedestal 370.13 KN = 2 x 2.35 x 3.15 x 25
b) Raft 104.27 KN = 3.35 x 4.15 x 0.3 x 25
Total vertical load 973.23 KN = 370.13 + 104.27 + 498.84
Restoring moment about toe of fdn 1467.15 KN-m = 0.9 x 973.23 x 1.675
Overturning moment 340.46 KN-m
F.O.S. against Overturning 4.31 > 2.2 Hence O.K.
Check against sliding
Maximum horizontal shear 74.83 KNCohesion, c = 34.34 KN/m2Coefficient of pressure = 1.00 = tan^2(45 + 0/ 2) Deg.
Resisting passive pressure, P = 105.46 KN/m2 = 2 x 34.34 x 1 + 18.39 x 2 x 1
Minimum area = 5.00 m2 = 2.35 x 1.7 + 3.35 x 0.3
Max. frictional resistance = 527.29 KN = 105.46 x 5
F.O.S. against Sliding = 7.05 = 527.29 / 74.83
> 2.2, Hence O.K.
REINFORCEMENT FOR BLOCK FOUNDATION ABOVE PAD
Provide Vertical Reinforcement 12@100c/c Provide Horizontal Reinforcement 10@100 c/cProvide Top Reinforcement 10@200 c/c (B/W)
For Block Foundation, reinforcement of 25Kg/m3 is provided.
20MVA Transf fdn Page 5
CLIENT POWER GRID CORPORATION OF INDIA LIMITED SHYAMA POWER (I) LTDPROJECT BIHAR SUB TRANSMISSION SYSTEM, PHASE II, PART II DESIGN NO.- 1000SUBSTATION 132/33kV Runnisaidpur S/S
Top Reinforcement 10@200 c/c (B/W)Length 3.15 mBreadth 2.35 mNo of bars along length 12No of bars along breadth 16Length of bars 72.60 mTotal weight @ 0.617 kg/m 44.79 kg
Length 3.15 mBreadth 2.35 mNo of bars along breadth 24No of bars along length 30Length of bars 216 mTotal weight @ 0.89 kg/m 192.24 kg
@100 C/CHeight 2 MNo. of bars along length 21 nos
Length of bars 227.64 mTotal weight @0.617kg/m 140.45 kg
Total Weight of bars 377.49 kg
Volume of foundation = 2 x 2.35 x 3.15 = 14.81
Reinforcement per cubic meter = 377.49 / 14.81 = 25.50
Reinforcement required at pedestal base
Net upward pressure at the base 75.55 KN/m2 = 83.05 - 0.3x 25
Partial factor of safety 2.2Moment at face of Block 9.44 KN-m/m = 75.55 x 0.5^2 / 2
Design Moment, Mu 20.78 KN-m/m = 2.2 x 9.44
Clear cover 50 mmEffective depth, d 245 mm
Area of Steel, Ast = Mu/(0.87fy(d-0.416xu), where xu/d=1.202+-(1.4446-6.67735Mu/fckbd2))^1/2Hence, xu = 12.04 mmand Ast1 = 240 mm2/mMininimum Ast for 0.12% reinf. 360 mm2/mMax spacing, 3d or 450mm = 450 mm
Provide 10 200 mm c/c at bottom = 393 mm2/m, O.K.
Provide 10 200 mm c/c at Top = 393 mm2/m, O.K.
Vertical Reinforcement 12@100 c/c
Horizontal Reinforcement 10
m3
kg/m3 > 25 kg/m3
f bars @
f bars @
20MVA Transf fdn Page 6
CLIENT POWER GRID CORPORATION OF INDIA LIMITED SHYAMA POWER (I) LTDPROJECT BIHAR SUB TRANSMISSION SYSTEM, PHASE II, PART II DESIGN NO.- 1000SUBSTATION 132/33kV Runnisaidpur S/S
2. Design of wall foundation for rails
Shipping wt of transformer = 50850 kg= 498.84 KN
Calculation of Gravel loadL.L. on grating 2.94 KN/m2Wt of gravel 2.35 KN/m2Wt of grating 0.69 KN/m2
5.98 KN/m2Thickness of wall 0.400 mC/C distance of rail track 1.743 mLoad coming on unit length of wall 4.02 KN/m = 5.98 x ( 1.743 - 0.4)/2
Case I : When wheels run on two parallel tracks
350 1743 350
300 400 GL
21002000
200
2443
Final load combination for single wall1) DL due to equipment 124.71 KN = 498.84 / 4
124.71 KNConsidering unit length of wallVertical load 71.55 KN/m = 124.71 / 1.743
Dead wt of wall 21.00 KN/m = 0.4 x 2.1 x 25
Load from Gravel and Grating 4.02 KN/m96.57 KN/m
Factored vertical load/m, Pu 212.45 KN/m =2.2 x 96.57
Clear cover provided 50 mmEffective depth, d 344 mm
Minimum reinforcement required 0.2 % of gross areaReinforcement required 800 = 0.2/100 x 1000 x 400
Provide 12 125 mm c/c as Vert. & Horiz.Reinf. = 905 mm2/m, O.K.
Design of base pad
SBC at toe level for dead load only 68.67 KN/m2 = 68.67
Pressure due to overburden soil 36.79 KN/m2 = 2 x 18.39
Dispersed load width 6.343 m = (1743 + 2 / tan(45) x 2300)/1000
mm2/face
f bars @
20MVA Transf fdn Page 7
CLIENT POWER GRID CORPORATION OF INDIA LIMITED SHYAMA POWER (I) LTDPROJECT BIHAR SUB TRANSMISSION SYSTEM, PHASE II, PART II DESIGN NO.- 1000SUBSTATION 132/33kV Runnisaidpur S/S
Moment at base 53.67 KN-m/m = (74.83 x(4.5/2+2.3))/6.343
Volume of concrete above GL 0.24 m3/m = 2 x 0.3 x 0.4
Volume of concrete below GL 1.93 m3/m = 2 x 1.8 x 0.4 + 2.443 x 0.2
Dead load raft & wall 54.22 KN/m = (0.24 + 1.9286) x 25
Total Vertical load 141 KN/m 498.84 / 6.343 + 54.215 + 4.02 x 2
2300
1743
6343
Maximum bearing pressure developed = 20.89 KN/m2 = 140.9/2.443 - 36.79
< 68.67 KN/m2 OK.Design of base pad
Net bearing pressure 15.89 KN/m2 = 20.89 - 0.2 x 25
Moment at middle of slab 6.03 KN-m/m = 15.89 x 1.743^2 / 8
Design moment, Mu 13.27 KN-m/m = 2.2 x 6.03
Clear cover provided 50 mmEffective depth, d 145
Area of Steel, Ast = Mu/(0.87fy(d-0.416xu), where xu/d=1.202+-(1.4446-6.67735Mu/fckbd2))1/2Hence, xu = 13.23 mm
and Ast1 = 264
Mininimum Ast for 0.12% reinf. 174Max spacing, 3d or 450mm = 435 mm
Provide 10 250 mm c/c both ways at top and bottom
= 314
Check for punching against one wall
Punching perimeter 12.686 m = 2 x 6.343
Effective area for punching 1.84 m2 = 12.686 x 145/1000
Punching load 408.110 KN =498.84/2+4.02x6.343+(2.1 x0.4x6.343)x25
Punching shear stress developed 0.488= 2.2 x 408.11x 1000 /(1.84x 1000 x 1000)
< 0.25 x sqrt(fck) = 1.118 N/mm2, O.K.
45º
mm2/m
mm2/m
f bars @
mm2/m, O.K.
N/mm2
20MVA Transf fdn Page 7
CLIENT POWER GRID CORPORATION OF INDIA LIMITED SHYAMA POWER (I) LTDPROJECT BIHAR SUB TRANSMISSION SYSTEM, PHASE II, PART II DESIGN NO.- 1000SUBSTATION 132/33kV Runnisaidpur S/S
3. Design of transformer pit wall
150
300 FGL
550
750400 0
200
950
Load calculation
1) Gravel load 2.35
2) Grating load 0.69
3) L.L. 2.94
5.98
Coeff. of earth pressure, K0 1.00 1 - sin(0)
1 + Sin (0)
Soil pressure at the bottom of wall 13.80 = 1 x ( 0.75 x 18.39)
Surcharge 2000
= 19.62
Earth pressure due to surcharge,q0 19.62 = 1 x 19.62
750
0
0.00 KN/m2 13.80 KN/m2 19.62Water pressure Earth Pressure at rest Lateral pressure due to surcharge
55010.12 0.00
200
13.80 0.00
Earth Pressure at rest Water pressure
KN/m2
KN/m2
KN/m2
KN/m2
KN/m2
KN/m2
KN/m2
KN/m2
KN/m2
20MVA Transf fdn Page 8
CLIENT POWER GRID CORPORATION OF INDIA LIMITED SHYAMA POWER (I) LTDPROJECT BIHAR SUB TRANSMISSION SYSTEM, PHASE II, PART II DESIGN NO.- 1000SUBSTATION 132/33kV Runnisaidpur S/S
Check for OverturningWeight of concrete per metre of wall lengtha) Pedestal 3.19 KN/m = 0.85 x 0.15 x 25
b) Raft 4.75 KN/m = 0.95 x 0.2 x 25
Weight of overburden soil per metre of wall length 8.09 KN/m = (0.95 - 0.15) x 0.55 x 18.39
Weight due to surcharge 7.85 KN/m = 19.62 x 0.4
Total Oil Weight 7.20 KN/m =14100 x9.81/1000/9.6/2
Total vertical load 36.77 KN/m =3.19+4.75+8.09+5.98x0.95+7.85+7.2
Restoring moment about toe of fdn 15.72 KN-m/m = 0.9 x 36.77 x 0.95 /2
Overturning momentMoment from soil side of pit 6.81 KN-m/m =19.62x0.75^2/2+13.8x0.75^2/6+0x0^2/6
Moment from other side of pit 0.23 KN-m/m =10.12x(0.2)^2/2+(13.8-10.12)x(0.2)^2/6
Net overturning moment 6.58 KN-m/mF.O.S. against Overturning 2.39 >2.2, Hence O.K.
Check against sliding
Maximum horizontal shear 19.89 KN/m =19.62x0.75+13.8x0.75/2
Cohesion, c = 34.34Coefficient of Friction = 1.00
Resisting passive pressure, P = 82.47 =2 x 34.34 x 1+18.39*0.75*1
Minimum area = 0.75 m2/m = 0.2 + 0.55
Max. frictional resistance = 61.85 KN/m = 82.47 x 0.75
F.O.S. against Sliding = 3.11 = 61.85 / 19.89
> 2.2, Hence O.K.
Design of wallClear cover provided 50 mmPartial factor of safety 2.2Effective depth, d 95 mm
Soil pressure at the bottom of wall 10.12 = 1 x 0.55 x 18.39
550
00.00 KN/m2 10.12 KN/m2 19.62 KN/m2
Water pressure Earth Pressure at rest Lateral pressure due to surcharge
Design Moment, Mu 7.65 KN-m/m = 2.2 x ( 0.5 x 10.12 / 3 + 19.62/2 ) x 0.55^2
Area of Steel, Ast = Mu/(0.87fy(d-0.416xu), where xu/d=1.202+-(1.4446-6.67735Mu/fckbd2))^1/2Hence, xu = 11.80 mm
and Ast1 = 235
Minimum Ast in wall 0.2% = 300
Ast / face = 150Provide 10 200 mm c/c as Vert. Reinf.
= 393
KN/m2
= tan2(45 + 0/ 2) Deg.
KN/m2
KN/m2
mm2/m
mm2/m
mm2/mf bars @
mm2/m, O.K.
20MVA Transf fdn Page 9
CLIENT POWER GRID CORPORATION OF INDIA LIMITED SHYAMA POWER (I) LTDPROJECT BIHAR SUB TRANSMISSION SYSTEM, PHASE II, PART II DESIGN NO.- 1000SUBSTATION 132/33kV Runnisaidpur S/S
Design of internal wall face(Considering water inside & no earth outside during construction stage)
850
8.50 KN/m2 0Top of raft
Moment at the base due to water 1.02 KN-m/m = 0.5 x 0.85 x 10 x 0.85 x ( 0.85/3+0)
Design Moment, Mu 2.25 KN-m/m = 2.2 x 1.02
Area of Steel, Ast = Mu/(0.87fy(d-0.416xu), where xu/d=1.202+-(1.4446-6.67735Mu/fckbd2))^1/2Hence, xu = 3.3 mm
and Ast1 = 67
Minimum Ast in wall 0.2% = 300
Ast / face = 150Provide 10 200 mm c/c as Vert. Reinf.
= 393
Horizontal reinforcement
Providing pt = 0.2 %
Minimum Ast in wall 0.2% = 300
Ast / face 150Provide 8 250 mm c/c per face
= 201W3
Design of base slab
Wt of soil outside the pit,w1 4.05 KN/mWt of soil inside the pit,w2 0.0 KN/mNet design moment, Mu 5.85 KN-m/m Soil 0
= 0.5 x 13.8 x 0.75^2 / 3 + 19.62 x 0.75^2/2-(4.05-0)*0.475/2 550 W1
Wt of wall & gravel 13.92 KN/m soil W2
Design vertical load, Pu 17.97 KN/m 200
Pressure due to overburden soil 13.80 400
= 0.75 x 18.39
Bearing pressure 44.01 475
= 17.97 / 0.95 + 5.85 x 6 / 0.95^2 - 13.8
SBC at toe level 49.05> 44.01 Hence Ok
Net bearing pressure 39.01 = 44.01 - 0.2 x 25
Design moment, Mu 6.87 KN-m/m = 2.2 x 39.01 x 0.4 ^2 / 2
Effective depth, d 146 mmArea of Steel, Ast = Mu/(0.87fy(d-0.416xu), where xu/d=1.202+-(1.4446-6.67735Mu/fckbd2))^1/2Hence, xu = 6.67 mm
and Ast1 = 133
Minimum Ast in slab 0.12% = 240
Ast / face = 120Provide 8 300 mm c/c per face
mm2/m
mm2/m
mm2/mf bars @
mm2/m, O.K.
mm2/m
mm2/mf bars @
mm2/m, O.K.
KN/m2
KN/m2
KN/m2
KN/m2
mm2/m
mm2/m
mm2/mf bars @
20MVA Transf fdn Page 10
CLIENT POWER GRID CORPORATION OF INDIA LIMITED SHYAMA POWER (I) LTDPROJECT BIHAR SUB TRANSMISSION SYSTEM, PHASE II, PART II DESIGN NO.- 1000SUBSTATION 132/33kV Runnisaidpur S/S
= 167 mm2/m, O.K.
20MVA Transf fdn Page 10
CLIENT POWER GRID CORPORATION OF INDIA LIMITED SHYAMA POWER (I) LTDPROJECT BIHAR SUB TRANSMISSION SYSTEM, PHASE II, PART II DESIGN NO.- 1000SUBSTATION 132/33KV Runnisaidpur S/S
Transformer load 50850 kgLoad for Pulling Block 5% of 50850 = 2542.50 kg 25Size of Pulling Block 1.00 m x 1.00 m
300GL
2000
200
300 1000 300
1600Weight of concretewt of concrete above GL = 0.3 x 1 x 1 x 25 7.50 KNwt of concrete below GL = (1.8 x 1 x 1 + 0.2 x 1.6 x 1.6)x25 57.80 KNTotal wt of concrete 65.30 KNWeight of soil = 1.8 x (1.6 x 1.6 - 1 x 1) x 18.39 51.65 KNTotal weight due to soil= 51.65 KN
Coefficient of Passive pressure = (1 + Sin 0)/(1-Sin 0) = 1.00Passive pressure = 1 x 1.8 x 18.39 = 33.11 KN/m2Moment due to Passive pressure = 1 /2 x 33.11 x 1.8 x 1.8/3 = 17.88 KNm
Passive pressure = 1 x 0.2 x 18.39 3.68 KN/m2Moment due to Passive pressure = 1 /2 x 3.68 x 0.2 x 0.2/3 = 0.02 KNm
Applied Moment = 25 x 2.3 = 57.50 KNmResultant moment = 57.5 - 17.88 - 0.02 = 39.60 KNmTotal Vertical load = 65.3 + 51.65 = 116.95 KNResisting moment = 116.95 x 1.6/2 = 93.56 KNmFOS = 93.56/39.6 = 2.36 > 2.2
Reinforcement calculation
Total Vertical load 52.50 KNHoriz. Force in y-direction,SFy 25 KNMoment about major axis ,Mx = 25 x 2.1 52.5 KNmShear parallel to base channel, SFx 0 KN
= (300 + 2000 - 200)/500+1000/30 37.53 mmMoment about minor axis ,My 1.97 KNmActive moment about the base of pedestalMux = 2.2 x 52.5 115.50 KNmMuy = 2.2 x 1.97 4.34 KNm
4. Calculation for Pulling Block
Minimum eccentricity,emin
20MVA Transf fdn Page 11
CLIENT POWER GRID CORPORATION OF INDIA LIMITED SHYAMA POWER (I) LTDPROJECT BIHAR SUB TRANSMISSION SYSTEM, PHASE II, PART II DESIGN NO.- 1000SUBSTATION 132/33KV Runnisaidpur S/STotal comp. force at bottom, P = (300 + 2000 - 200)/1000 x1x1x 25 52.50 KNPu = 2.2 x 52.5 115.50 KNMinimum percentage of steel required, pt,min 0.8 %
X-sectional area of column required = 115.5 x 1000 /(0.4 x 20 + 0.67 x 415 x 0.8/100) 11296.51
Minimum area of steel required 90.37
Area of Steel(As) 1356.48
Percentage of steel, p 0.136 %Clear Cover provided 50 mmd'/D 0.05
0.006
0.007
0.01
200.0 KN-m
0.01
200.0 KN-mPuz 9422 KNPu/Puz 0.012
1Interaction ratio 0.578 + 0.022 0.599 < 1 , OK
Provide 8 250 C/C as lateral ties
Design of base slab
Self wt of raft = 1.6 x 1.6 x 0.2 x 25 = 12.80 KNwt of pedestal = 2.1 x 1 x 1 x 25 = 52.50 KNwt of soil = (1.6x1.6 - 1x1) x (1.8 x 18.39) = 51.65 KNTotal load, P = 12.8 + 52.5 + 51.65 = 116.95 KNArea of fdn = 1.6 x 1.6 = 2.56 m2Applied Moment = 25 x 2.3 = 57.50 KNmResultant moment = 57.5 - 17.88 - 0.02 = 39.60 KNmBearing pressure =116.95/2.56+39.6x 6/1.6x1.6^2 - 36.79 = 66.90 KN/m2
< 85.84 KN/m2
Net bearing pressure = 66.9 - 25 x 0.2 = 61.90 KN/m2
Design moment, Mu = 2.2 x 61.9 x 0.3^2/2 6.13 KN/mEffective depth, d 145 mmArea of Steel, Ast = Mu/(0.87fy(d-0.416xu), where xu/d=1.202+-(1.4446-6.67735Mu/fckbd2))^1/2Hence, xu = 5.98 mm
and Ast1 = 119
Minimum Ast in slab (0.12%) = 240
Ast / face 120Provide 10 300 mm c/c per face
= 262
mm2
mm2
12 nos 12f bars mm2
Pu/fckbD
p/fck
Referring to chart 44 of SP16, Mux1/fckbD2
Mux1
Referring to chart 44 of SP16, Muy1/fckbD2
Muy1
αn
f @
mm2/m
mm2/m
mm2/mf bars @
mm2/m, O.K.
20MVA Transf fdn Page 12
SHYAMA POWER (I) LTDDESIGN NO.- 1000
KN
20MVA Transf fdn Page 13
SHYAMA POWER (I) LTDDESIGN NO.- 1000
20MVA transf fdn Page 12
CLIENT POWER GRID CORPORATION OF INDIA LIMITED SHYAMA POWER (I) LTDPROJECT BIHAR SUB TRANSMISSION SYSTEM, PHASE II, PART II DESIGN NO.- 1000SUBSTATION 132/33KV Runnisaidpur S/S
Volume of transformer oil = 17200 LitresVolume of Soak Pit (Net) = 1.3x 17200 = 22360 LitresDepth of Soak Pit = 0.55 m
Surface Area of Soak Pit required = 22.36/0.55 = 40.65
Area occupied by Transformerfoundations & cooling system foundations = 3.150 x 2.350 + 2 x 0.4 x 2.775
= 9.62
Therfore, Gross area of Soak Pit required = 40.65+ 9.62 = 50.28
Inside Gross area of Soak Pit = 5.2 x 2.3 + 1.450 x 6.2+3x7 +5.8x1.45+1.4x4.4
= 56.48
5. Soak Pit Calculation:
m2
m2
m²
m2 > 50.28 m2