transmission line protection using pott scheme a …
TRANSCRIPT
TRANSMISSION LINE PROTECTION USING POTT SCHEME
A Project
Presented to the faculty of the Department of Electrical and Electronic Engineering
California State University, Sacramento
Submitted in partial satisfaction of
the requirements for the degree of
MASTER OF SCIENCE
in
Electrical and Electronic Engineering
by
Adewunmi Oluwademilade Taiwo
SPRING
2019
ii
© 2019
Adewunmi Oluwademilade Taiwo
ALL RIGHTS RESERVED
iii
TRANSMISSION LINE PROTECTION USING POTT SCHEME
A Project
by
Adewunmi Oluwademilade Taiwo
Approved by:
__________________________________, Committee Chair
Mahyar Zarghami
__________________________________, Second Reader
Tracy Toups
____________________________
Date
iv
Student: Adewunmi Oluwademilade Taiwo
I certify that this student has met the requirements for format contained in the University
format manual, and that this project is suitable for shelving in the Library and credit is to
be awarded for the project.
___________________, Graduate Coordinator ___________________
Preetham Kumar Date
Department of Electrical and Electronic Engineering
v
Abstract
of
TRANSMISSION LINE PROTECTION USING POTT SCHEME
by
Adewunmi Oluwademilade Taiwo
Statement of Problem
Permissive Overreaching Transfer Trip (POTT) is a scheme that enables fast
tripping of breakers at the local and remote end of a protected equipment. POTT schemes
are typically used for high voltage line protection against faults in areas with coordination
and power stability issues. Three-phase fault is the most severe type of fault that can
occur and fast tripping at high voltages is paramount for personnel safety, to avoid
equipment destruction, and fires. POTT schemes require a secure form of
communication between both relays (local and remote).
Sources of Data
For this project, I followed guidelines provided by Pacific Gas and Electric
(PG&E) Transmission Line Protection Manual and Relay Application Guideline. I used
Aspen software package to model the power system (transmission lines and buses). I also
performed analyses such as fault-duty study, relay-setting testing, and coordination study
using Aspen. I used Mathcad to create relay-setting using PG&E guidelines. In general,
the settings depend on the fundamentals of POTT scheme, the fault-duty study, and the
vi
current transformer (CT) and voltage/potential transformer (PT) ratios. I used Microsoft
Visio to model other diagrams and figures required to better explain how the POTT
scheme works.
Conclusions Reached
POTT scheme is an effective scheme for fast tripping. It requires a secure form of
communication between both relays (local and remote) protecting the equipment. Using
relevant manuals, guidelines and papers, I modelled and set relays to protect a 230kV line
using a POTT scheme. I also provided Phase distance and Ground overcurrent settings
for SEL-411L relays.
_______________________, Committee Chair
Mahyar Zarghami
_______________________
Date
vii
ACKNOWLEDGEMENTS
I must show my utmost gratitude to the System Protection group at PG&E for the
opportunity to learn from them, to use their system, and to follow their protection
guidelines. This project would not be possible without the help of Protection engineers in
the West Sacramento office.
To my mom Adejoke Taiwo, thank you for your love, patience and for sacrificing
a lot to help me understand the fundamentals of mathematics. I would not be an engineer
today without you. To my dad Adekunle Taiwo, thank you for your constant love, advice,
and encouragement to purse my career goal.
I would like to thank God for the wisdom, knowledge, strength and favor to be
where I am today. In God I found strength to persevere against all odds.
Finally, I would like to thank my project advisor Mahyar Zarghami of the
Electrical and Electronics Department at California State University, Sacramento. He has
helped me greatly to achieve academic success.
viii
TABLE OF CONTENTS
Page
Acknowledgements………………………………………………………………..........vii
List of Tables………………………………………………………………………...….. x
List of Figures ………………………………………………………………………..... xi
Chapter
1. INTRODUCTION ....................................................................................................1
2. WHAT IS A FAULT AND WHY DO WE NEED PROTECTION? .........................3
Fault on Power System .........................................................................................3
Symmetrical Faults ...................................................................................3
Unsymmetrical Faults ...............................................................................4
Why Do We Need Protection Against Faults? ......................................................5
3. THE SYSTEM SET UP ...........................................................................................8
The System ...............................................................................................8
Important Components for System Protection ...........................................9
4. LINE PROTECTION ............................................................................................. 12
Overcurrent Protection............................................................................ 13
Distance Protection ................................................................................. 14
5. POTT SCHEME TRANSMISSION LINE PROTECTION..................................... 16
Working Principle of Pott Scheme ..................................................................... 16
In Section Fault ...................................................................................... 18
ix
Out of Section Fault................................................................................ 18
Advantages of POTT Scheme ................................................................. 19
Disadvantages of POTT Scheme............................................................. 20
6. RELAY SETTINGS ............................................................................................... 21
Transformer Ratios and Line Impedance ............................................................ 21
Selecting Current Transformer Ratio (CTR) ........................................... 21
Selecting Potential Transformer Ratio (PTR) .......................................... 22
Line Impedance ...................................................................................... 23
Phase and Ground Relay Settings ....................................................................... 24
Phase Distance Settings .......................................................................... 24
Ground Directional Overcurrent Settings ................................................ 27
Substation A ........................................................................................ 27
Substation B ........................................................................................ 32
7. SIMIULATION RESULTS .................................................................................... 36
In Section Fault ...................................................................................... 36
Out of Section Fault................................................................................ 42
8. CONCLUSION ...................................................................................................... 46
Appendix A. ................................................................................................................. 48
Appendix B. ................................................................................................................. 52
References ..................................................................................................................... 56
x
LIST OF TABLES
Tables Page
1. System Attributes ………………………………………..……………………. 22
2. Transmission Line Attributes …………………………………………………. 23
3. Phase Distance protection settings for local and remote relays ……….……… 25
4. Ground Directional Overcurrent relay settings summary for Relay A …….…. 31
5. Ground Directional Overcurrent relay settings summary for Relay B ………. 34
xi
LIST OF FIGURES
Figures Page
1. Types of Symmetrical Faults ................................................................................4
2. Types of Unsymmetrical Faults ............................................................................5
3. System Setup .......................................................................................................8
4. Zones of Protection Illustration .......................................................................... 15
5. Permissive Overreaching Transfer Trip Scheme ................................................. 17
6. In-section fault on protected line ........................................................................ 18
7. Out-of-section fault on protected line ................................................................. 19
8. Mho Circle of Phase Distance relay .................................................................... 26
9. Inverse Overcurrent Relay Curve (U1) for relays at Sub A ................................. 31
10. Very Inverse Overcurrent Relay Curve (U3) for relays at Sub B ......................... 35
11. Aspen Oneliner Simulation of applied SLG fault ................................................ 36
12. SEL SynchroWave file of Line relay at Sub A for in-section SLG Fault ............. 37
13. SEL SynchroWave file of Line relay at Sub B for in-section SLG Fault ............. 38
14. Aspen Oneliner Simulation of applied LL fault .................................................. 39
15. SEL SynchroWave file of Line relay at Sub A for in-section LL Fault ............... 40
16. SEL SynchroWave file of Line relay at Sub B for in-section LL Fault ................ 41
17. SEL SynchroWave file of Line relay at Sub A for out-of-section LL Fault ......... 43
18. SEL SynchroWave file of Line relay at Sub B for out-of-section LL Fault ......... 44
1
1. INTRODUCTION
Our electric power system comprises of several components to enable the
generation, transmission, and distribution of power. The AC power system is typically a
three-phase system, in which three sinusoidal voltages with the same amplitude and 120°
of phase-shift are generated. This power is then transmitted over long distances using
high voltage power lines and cables and is further distributed to customers using low
voltage power lines.
Under normal conditions, the power system is considered safe, but there are
events that can threaten the safety of the system. A fault in the power system can cause
dangerous and unsafe conditions. When a fault occurs, the voltage and current in the
system is disturbed. We tend to see a depression in voltage and sudden spike in current
which is as a result of decrease in impedance at the fault location. A sudden and sustained
spike in current can have devastating effects such as destruction of power equipment.
This can be avoided by tripping the faulted equipment.
Tripping of power equipment is the process of disconnecting the equipment from
the power sources and isolating the fault. This is accomplished using combined action of
circuit breakers, relays, potential transformers, current transformers, and in some case
communication channels. It is important to understand that when we have high voltages,
a sudden depression and huge spike in current can be very devastating. Therefore, fast
tripping to isolate the fault is crucial. Pilot schemes enable fast tripping.
2
Pilot schemes are communication-assisted schemes between the local and remote
relays to protect a power system equipment. There are several pilot schemes but for the
purpose of this project we focus on POTT scheme.
Permissive Overreaching Transfer Tripping (POTT) is a type of pilot scheme that
requires a secure communication channel to enable fast tripping. This permissive tripping
is done by both local and remote relays. When a relay sees a fault in its zone of
protection, it sends out a permission signal through communication channels to other
relays protecting the line telling them to trip instantaneously if they also see a fault in the
forward direction. A permissive trip will only occur when all relays protecting the line
agree that the fault is on the protected line (in-section) and not on another line (out-of-
section).
3
2. WHAT IS A FAULT AND WHY DO WE NEED PROTECTION?
Fault on Power System
The electric power system operates with all equipment carrying the normal
allocated load current and voltages [2]. The system under normal conditions operates
within predetermined limits which can be disrupted by a disturbance. A fault is a
disturbance in an electric circuit that affects the normal delivery of power. A short circuit
fault causes a sudden spike in current and depression in voltage as a result of a low
impedance path created between phases or phase(s) to ground. The flow of high fault
current through the faulted equipment can cause catastrophic damages. Short circuit
currents can be classified into:
Symmetrical Faults
Unsymmetrical Faults
Symmetrical Faults
A fault involving all three phases is a symmetrical fault. Three phase fault occurs
when three equal fault impedance is applied to the three phases. Since the three phases
are balanced and equal fault impedance is applied, the resulting fault currents and
voltages on all phases are balanced. A symmetrical fault is the most severe fault that can
occur because it involves all three phases. There are two types of symmetrical faults;
three phase to ground (3LG), and three phase fault.
4
(a) Three-phase to ground fault (b) Three-phase fault
Figure 1: Types of Symmetrical Faults
Unsymmetrical Faults
Unlike symmetrical faults, unsymmetrical faults do not involve all three phases.
Unsymmetrical faults causes an unbalance in the system. This can occur as a result of
lighting, animal interference, wind, temperature, tree branches and so much more. This
makes unsymmetrical faults more common. There are three types of unsymmetrical
faults:
Single Line to Ground (SLG) Fault
Line to Line (LL) Fault
Double Line to Ground (LLG) fault
(a) Single Line to Ground fault (b) Line to Line Fault
5
(c) Double Line to Ground Fault
Figure 2: Types of Unsymmetrical Faults
Why Do We Need Protection Against Faults?
As explained in previous sections, a fault causes high current flowing through the
faulted equipment and decreased bus voltages. What does this mean to an equipment?
Electrical components in the power system are rated based on the maximum current such
equipment can withstand before they are damaged. Take for example, a three phase 100
MVA 60 Hz system, with a 230 kV transmission line which uses a 477 Hawk 26/7 ASCR
conductor with a current ampacity of 655 A. The normal current flowing through the
system is calculated at 251 A. A three phase to ground fault occurs on the line with a
fault current of 11,500 A. This is 17.5 times the rated current that can flow through the
conductor. As a result, this fault can cause a fire that can destroy properties in its vicinity.
Protection against faults prevents catastrophic events from happening. It gives us
the ability to quickly isolate the faulted component from the rest of the system. With the
6
faulted component isolated, no current flows through it, thus eliminating the risk of
equipment damage and stabilizes the power system.
When it comes to power system protection, we are concerned about the following
attributes:
Reliability
o Security
o Dependability
Selectivity
Speed
Simplicity
Economics
Reliability focuses on the ability of the protection scheme to operate properly. We
say the protection system is secure when breakers do not trip when they should not, and
dependable when breakers trip when they are expected to. Selectivity is the ability to trip
the minimal amount of protection devices to clear a fault. Selectivity is done to endure
that there’s no miscoordination of the protective devices. Miscoordination is when the
backup protection operates faster than the primary protection. When this happens,
unaffected equipment (i.e. transformer, lines) are isolated from the power system. This
causes unnecessary loss of power delivery.
When it comes to protection speed, the faster the better. This is important to
minimize the damaging effect of a fault and to ensure system stability. Keeping the
protection scheme simple and easy to follow is important to ensure that any engineer or
technician can determine what went wrong when the scheme does not work as expected.
7
Economics plays a major part when deciding what protection scheme to apply. In other
words, do not go for an expensive scheme when a cheaper one works just as fine.
8
3. THE SYSTEM SET UP
The System
This project focuses on the protection of a 230kV transmission line using a POTT
scheme. Figure 3 shows the single-line diagram of the protected line connected between
Substation A and Substation B.
Substation A has two step-down transformers from 230kV to 115kV. This
substation is fed from three sources, 230kV substations E, G and F and feeds five 230kV
substations B, D, H, I, and J. Substation B has two step-down transformers from 230kV
to 115kV. This substation is fed from 4 sources, 230kV substations A, D, K and B and
feeds two 230kV substations C and L.
For this project, let us call the protected line “Sub A – Sub B 230kV Line”. The
transmission line is an electrical conductor cable that enables the flow of power from one
point to another. There are several types of electrical cable used in power transmission
Figure 3: System Setup
9
such as: All Aluminum Conductor (AAC), All Aluminum Alloy Conductor (AAAC),
Aluminum Conductor Steel Reinforced (ACSR) etc. This transmission line is 28.5 miles
long. The line conductor type is ACSR which is great for long distances because of the
steel reinforcement.
Important Components for System Protection
For line protection using POTT scheme, we need a current transformer (CT),
potential/voltage transformer (PT), line relays, line circuit breaker, and communication
channel.
Current Transformers (C.T.) are used to reduce high currents to a lower current
value that can be used by the relay and monitoring devices. The alternating current (AC)
that flows through the primary winding of the CTs is proportional to the current on the
secondary winding by the turns ratio the windings [1]. Typically, CTs have a turns ratio
of primary current (Ip) to secondary current of 5A (Ip/5A). CTs deliver 0 to 5A of
secondary current that is proportional to the primary current. CTs are important for the
overcurrent function of the protection relay.
Potential/Voltage Transformers (PTs) are used to reduce high voltages to lower
voltages and work as an instrument transformer. PTs step down the primary voltage to a
secondary voltage of about 0 to 120 volts. PT provide a direction reference for relays.
They are also used for distance relay protection. Using the output of a CT and a PT, the
relay can calculate the apparent line impedance which is used in distance protection.
10
Protective relays are electromechanical, or microprocessor based devices that
calculates the decision to trip circuit breakers. A relay receives input signals from the
secondary side of CTs and PTs and can open or close the circuit breaker’s contact.
Microprocessor relays are more advanced than electromechanical relays and can
perform several mathematical functions. For this project, we will be using a
microprocessor line relay. SEL-411L relays are produced by Schweitzer Engineering
Laboratories (SEL) and have advanced line differential, distance and overcurrent
protection, automation, and control capabilities.
Although this relay has very advanced capabilities, this project would focus only
on the relay settings for distance and overcurrent protection and their comparison to
POTT scheme. This report will not cover line differential protection or mirrored bits
communication available in the SEL-411L relay.
Circuit breakers are used to manually or automatically de-energize or energize
power system equipment such as transmission or distribution lines, transformers,
generator, and buses. They act based on the command signals sent by the protective
relays. The circuit breakers on power lines usually have their contacts closed using
normal operations and opened when isolating or de-energizing the line.
Communication channel is a medium by which data transfers from one point to
another. In power system protection, communication channels are used to enable fast
tripping of circuit breakers when a fault is within the specified zone of protection. For
example, for line protection, the communication channel transfers data between the relays
at both end of the lines (relays are usually at the substation).
11
Communication channels help in improving the speed, security, dependability,
and sensitivity of protective relays [2]. There several types of communication channels in
power system protection such as power line carrier (PLC), leased telephone wire, spread
spectrum radio, fiber optics, and microwave.
12
4. LINE PROTECTION
There are several types of protection schemes that focus on some of the protection
attributes discussed in the previous section. Protection schemes are chosen based on the
type of electric equipment being protected, the amount of fault current, the frequency of
faults occurring in the location of the equipment and several other factors. Two group of
protection schemes important to this project: Non-pilot and Pilot protection line
schemes.
Non-pilot protection schemes do not require communication devices. These
schemes focus on the fault current and bus voltage at the location of the local breaker.
Pilot protection schemes require communication devices between the local and remote
end of the protected equipment. Protection devices at either ends require information
from the other end to make tripping decisions. Pilot schemes are used to increase
protection speed. These schemes are considered to have instantaneous tripping.
Depending on the availability of a CT and/or PT, here are common types of
protection that can be applied to the protected line:
Overcurrent Protection
Distance Protection
13
Overcurrent Protection
Overcurrent protection uses current from a CT to determine if a fault has occurred
and if tripping is required. Overcurrent protection requires a current threshold (pickup
value) to be set in the relay. When the current seen by the relay is over the pickup value,
the relay either issues an instantaneous trip or a timed delayed trip depending on how
much current is seen. For time-overcurrent protection (TOC) the time it takes the relay to
issue a trip is determined by the selected time dial (TD) and time-overcurrent curve.
Overcurrent protection can be directional or non-directional. When it is
directional, information from PT is required for the relay to determine where the fault has
occurred if it is in the forward or reverse direction. If the fault is in the reverse direction,
the directional overcurrent relay will not issue a trip signal, to enable other protection
devices to operate.
Depending on the type of fault, we can have a Phase Overcurrent relay protection
and Ground Overcurrent relay protection. Phase overcurrent relay protection is used to
protect the electric equipment from phase faults such as three phase faults or line to line
faults. Ground Overcurrent relay protection is used to protect against ground faults such
as SLG, and LLG.
14
Distance Protection
Distance protection is a type of protection that uses the apparent impedance seen
by the relay to determine if a fault has occurred and if tripping is required. Distance
relays need current (from CT) and voltage information (from PT) to calculate the
apparent impedance [2]. If the calculated impedance is not within the prescribed zones of
protection, the relay will not issue for a trip. There can be several numbers of protection
zones, typically transmission line protection uses three or four zones.
In line (transmission or distribution), Zone 1 is set to protect the primary line.
This is typically set to cover ≤ 85% of the line length and provides the fastest protection
with no intentional time delay. Zone 1 is not set to see the full length of the line because
of PT and CT errors that make it difficult to ensure that the relay does not trip for a fault
that is not on the protected line.
Zone 2 is set to see faults that are not on the protected line but with some time
delay margin that enables the protection on the other line to trip. Zone 2 relays are
usually set as backup protection for adjacent lines. This zone is typically set to 120% of
the primary line impedance. Zone 3 can be set to see faults further than Zone 2 in the
forward direction or can be set to protect against fault in the reverse direction of the relay.
Zone 3’s application depends on the protection requirement of the line and surrounding
lines.
Like overcurrent relays, distance relays can be set to protect against phase faults
(Phase distance element) or to protect against ground faults (Ground distance element).
15
For transmission line, we typically set phase distance relay as the standard and use
ground distance relay when the need arises. Relays these days are microprocessor based
and have several protection elements in them. Elements just need to be enabled or
disabled depending on application.
Figure 4: Zones of Protection Illustration
16
5. POTT SCHEME TRANSMISSION LINE PROTECTION
Permissive Overreaching Transfer Trip (POTT) is a type of communication aided
(pilot) protection scheme. Pilot schemes are used to ensure faster clearing time
(instantaneous) and better selectivity which is often a requirement for high voltage lines
[4]. Pilot schemes are great because they ensure the following attributes [4]:
Faster tripping helps ensure that the system does not experience stability problems
as a result of the disturbance or fault.
Faster tripping ensures that there’s no coordination problems for the protected
equipment because the primary protection has no intentional delay.
Working Principle of Pott Scheme
The term “Permissive” implies that permission must be given for this scheme to
function. Using the communication medium, when a local relay detects that a fault has
occurred on the protected line, it tells the remote relay (and vice versa) that it can trip
faster (instantaneous) if the remote relay also detects a fault in the forward direction [3].
For a permissive trip to occur, all relays acting as the primary protection of the
line must agree that a fault has indeed occurred on the line [3]. This implies that both the
local and remote relays share information and would require transmitter and receiver
devices at both ends.
17
An “Overreaching” element (typically Zone 2) is set to see past the protected line
and encroaches into the adjacent lines [3]. This is done to ensure that the line is 100%
protected. Transfer Trip (‘TT”) is the signal that is sent by at least one relay to the other
relays to allow tripping when the overreaching element (RO) element picks up for a fault.
POTT scheme requires that the RO element picks up, keys a transfer trip channel
and only trips the circuit breaker when it receives a permissive trip signal from the
remote terminal [5]. A secure communication channel is very important for this scheme
to function properly. When the communication channel is compromised, the scheme is
not effective, and we need contingency schemes (like non-pilot) in place for such
instances.
Figure 5: Permissive Overreaching Transfer Trip Scheme
18
In Section Fault
For a fault on the protected line, we would expect the POTT scheme to work as
shown in Figure 5 below. At both ends, the RO element picks up and keys the transfer
trip channel. Both relays receive permissive trip signals. With both the RO element and
permissive trip signal received, the relays will issue a POTT scheme trip for both Breaker
A and B.
Figure 6: In-section fault on protected line
Out of Section Fault
For a fault not on the protected line, we would expect the POTT scheme to work
as shown in Figure 6 below. For a fault placed on a transmission line behind Breaker A,
the RO element of the relay at Breaker B would pick up while that of Breaker A would
not. Relay B key the transfer trip channel but would not receive a permissive trip signal.
19
Relay A would receive a permissive trip signal but would not key the transfer trip
channel. Because no relay has both RO element picked up and permissive signal
received, the Breaker A and B would not trip via the POTT scheme
Figure 7: Out-of-section fault on protected line
Advantages of POTT Scheme
POTT scheme is very secure because it will not issue for false tripping when an
external fault occurs. It is easy to understand because the scheme is simple and not
complicated. It is easy to construct; POTT scheme requires a directional element that can
be set for three zones (i.e. distance protection) [4].
20
Disadvantages of POTT Scheme
POTT scheme relies on a secure communication channel. A compromised
communication channel means this scheme would not produce a pilot trip for a fault on
the protected line. Due to this concern, power line carrier is not an advised
communication channel for pure POTT scheme protection [4]
21
6. RELAY SETTINGS
Transformer Ratios and Line Impedance
For this project, we will be setting SEL-411L relays at both terminals. This relay provides
us with several protection options. For the POTT scheme protection, we will be enabling
Phase Distance and Ground Overcurrent elements.
Phase distance relays should protect the line from any type of fault. Due to the
unpredictable ground impedance that can occur during a SLG fault, phase distance
elements might not be sensitive to this fault. Ground overcurrent elements was set to
provided protection against SLG faults which is the most common fault that occurs on
power lines. To successfully set the relays, we need to determine transformer ratios for
CT and PT:
Current Transformer Ratio (CTR)
Potential Transformer Ratio (PTR)
Selecting Current Transformer Ratio (CTR)
Current transformers come from manufactures with either single ratio or multi-
ratio. When the CT has multiple ratios available, a selection can be made to best fit our
need. To avoid thermal issues with CT, CT ratio should be set higher than the maximum
emergency loading of the protected equipment (i.e. Transmission line) [4]. The CT ratio
22
selected should keep the maximum secondary fault current that can occur on the
protected equipment to a minimum value (PG&E guideline is 50 A to 100 A) [4].
Table 1: System Attributes
Line to Line Voltage (KV) 230
Maximum Loading 1378 A
This conductor has a highest California ISO (CALISO) rating of 1378A during
summer peak loading. As mentioned in previous section, the relay needs a secondary
current of about 5A therefore, the CT converts primary currents to 5 A secondary. The
available CT ratios are 300:5, 400:5, 500:5, 800:5, 1100:5, 1200:5, 1500:5, 1600:5, and
2000:5. Given this information, we will be selecting a CT ratio of 1600/5 which gives
reasonable margin to the maximum loading.
Selecting Potential Transformer Ratio (PTR)
The relay requires an input of about 120 V which means the systems high voltage
of 230kV has to be stepped down considerably to be used by the relay. With a 230kV, a
PTR ratio of 2000 will provide 115 V on the secondary side of the transformer, which is
sufficient. The system is designed to withstand a change of ± 10% in voltage.
Transmission lines do not typically have overvoltage protection because alarms would go
off during this conditions and system operators would rectify the issue.
23
Line Impedance
The line impedance was provided by PG&E’s Aspen Oneliner model of its system
and is presented in Table 2 below.
Table 2: Transmission Line Attributes
Line Length 28.5 miles
Positive Sequence Impedance (Z1) 0.00514 + j0.04101 per unit
Zero Sequence Impedance (Z1) 0.01943 + j0.13154 per unit
The given per unit impedance values are in primary bases and therefore we need
find the impedance used by the relay by converting to secondary bases as shown below:
ZBase = KVLL
2
MVAbase
= (230×103)
2
100×106 = 529 Ω
Zratio = k = PTR
CTR =
2000
(1600
5)
= 6.25
Z1,pri=ZBase× √0.005142 +0.04101 2 =21.8 Ω
Z0,pri =ZBase× √0.01943 2 +0.13154 2 = 70.34 Ω
Z1,sec=Z1,pri
k=
21.8
6.25=3.49824 Ω; Z1,ANGLE= tan-1 (
0.04101
0.00514) =82.86°
Z0,sec=Z0,pri
k=
70.34
6.25=11.25435 Ω; Z0,ANGLE= tan-1 (
0.13154
0.01943) =81.6°
24
With the above calculations, the line impedance date input to the relay is:
Z1,MAG=3.49824 Ω; Z1,ANGLE= 82.86°
Z0,MAG=11.25435 Ω; Z0,ANGLE= 81.6°
Phase and Ground Relay Settings
Using the PG&E system model on Aspen Oneliner, several fault simulations were
performed to find the maximum and minimum short circuit currents, voltages, and
impedance. The results of this simulations can be found in Appendices A and B.
Phase Distance Settings
For phase distance protection, we will be setting 3 zones of protection. Zone 1
will be set to 85% of the minimum line impedance with no intentional time delay [6].
Zone 2 will be set to overreach the line (RO element) at 120% of the maximum line
impedance with 20 cycle delay for coordination with upstream and downstream relays
[6]. Zone 2 serves as the RO pick up element for POTT scheme and would trip after a
specified time delay in a situation when the communication channel is compromised.
Z1MP = 0.85× ZP
k = 2.98 Ω sec Z1PD = 0 cycle
Z2MP = 1.2× ZP
k = 4.2 Ω sec Z2PD = 20 cycles
25
Zone 3 is set to see in the reverse direction and to equal the Zone 2 element of the
remote end. This ensures that the relay overreaches (sees farther) than the forward-
looking Zone 2 element of the remote terminal [6]. Zone 3 is set to confirm that relay is
operating properly and that the fault is indeed behind the relay. Zone 3 can also be set as
backup protection for a bus fault.
Z3MP =
RemoteZ2MP × (𝑅𝑒𝑚𝑜𝑡𝑒 𝑃𝑇𝑅𝐶𝑇𝑅𝑅𝐸𝑀𝑂𝑇𝐸
)
k = 4.2 Ω sec Z2PD = 20 cycles
Where:
ZP = Impedance of the line
Z1MP = Maximum impedance that would trigger Zone 1 protection
Z2MP = Maximum impedance that would trigger Zone 2 protection
Z3MP = Maximum impedance that would trigger Zone 3 protection
Z1PD = Time delay for Zone 1
Z2PD = Time delay for Zone 2
Z3PD = Time delay for Zone 3
Table 3: Phase Distance protection settings for local and remote relays
PT ratio 2000
CT ratio 320
Zone 1 (Forward) 2.98 Ω sec
Zone 2 (Forward) 4.2 Ω sec
Zone 3 (Reverse) 4.2 Ω sec
Zone 1 time delay 0 cycle
Zone 2 time delay 20 cycles
Zone 3 time delay 20 cycles
26
Since Phase distance uses the impedance of the line, the same settings would be
applied to relays at both ends of the line.
Figure 8: Mho Circle of Phase Distance relay
Mho circles shows the R-X boundary of the protection zones. The maximum
impedance reach for each zone, the relay characteristics angle (RCA) and the maximum
torque angle (MTA) is used to generate the Mho circles. The positive sequence
impedance angle of the line is typically set as the MTA. The RCA is used to calculate the
maximum load that could cause the relay to operate and is usually set to 90°. The
diameter of each circle is impedance boundary set for each zones. During the normal
27
operation of the system, the load impedance is usually high enough to not encroach into
the mho circles.
Ground Directional Overcurrent Settings
For ground protection, we will be setting ground overcurrent elements instead of
distance elements. This is because for high impedance in-section faults, ground distance
relays are less likely to see the fault [4]. The Ground Directional Time Overcurrent
element is set to 50% of the minimum fault current for a fault on the remote bus with all
sources, parallel lines in and the strongest local source out [5]. 50 and 51 are the IEE
standard device numbers for Instantaneous overcurrent relay and AC time overcurrent
relays respectively.
Substation A
Using the simulation results in Appendix A, the calculations below was done to
determine the appropriate directional ground times and instantaneous overcurrent
settings.
Ground Directional Timed Overcurrent settings [6]:
Using the minimum ground fault current (Min3I0), the pickup value is calculated as:
28
51G = 0.5×Min3I0
CTR = 1.59 Asec
Select 51G = 1.5 Asec
For coordination with upstream and downstream relays, we selected Inverse Overcurrent
Curve (U1). 51C = U1.
Where:
Min3I0 = Minimum ground fault current
51G = Minimum current pickup value for Ground Timed Overcurrent protection
CTR = Current Transformer Ratio
51C = Time-Overcurrent curve
The time dial is set for > 0.33 sec (20 cycles) fastest clearing of the remote bus fault. This
allows for coordination [6].
Using the SEL Curve U1 equation provided by SEL-411L instruction manual
MG = Max3I0
51P01 × CTR= 5.158
TimeGfault = 0.7 s
TDGMAXFAULT=
TimeGfault
0.0226 + 0.0104
M0.02 − 1
= 2.09
Select 51TD = 2.2
29
Where:
Max3I0 = Maximum ground fault current
MG = Multiples of pickup
TimeGfault = Desired fastest clearing time
TD_GMAX_FAULT = SEL Time Dial element
51TD = Inverse Time Overcurrent 01 Time Dial
The 51G setting serve as the RO pick up element for POTT scheme. It also serves
backup protection in a situation where the communication channel is compromised, or
the POTT scheme is cut out.
Ground Directional Instantaneous Overcurrent settings [6]:
The Ground Directional Instantaneous Current element is set to about 120% to
130% of the highest remote bus fault with no intentional time delay [6]. To get this, put a
fault on the remote bus with a strong source at the local bus or parallel line out [5].
50𝐺 = 1.2 × 𝑀𝑎𝑥3𝐼0
𝐶𝑇𝑅= 9.29 𝐴𝑠𝑒𝑐
Select 50G = 9.5 Asec 50GD = 0 cycle
30
Where:
Max3I0 = Maximum ground fault current
50G = Minimum current pickup for Ground Instantaneous Overcurrent protection
50GD = Time delay
CTR = Current Transformer Ratio
To make these relays directional, we need to provide a reference point for
polarization. Polarization provides a reference point by which the relay can tell if the
current is going in (forward) or going out (reverse). Ground directional overcurrent
relays are typically polarized using either the negative sequence voltage or the zero
sequence voltage from the remote end. Refer to Appendix A for polarization quantities.
For the Ground Directional Element settings, SEL Application guide AG2016-14
suggests the following settings [6]:
Forward Directional Overcurrent Pickup (50FP) = 0.5
Forward Directional Z2 Threshold (Z2F) = -0.3
Reserve Directional Z2 Threshold (Z2R) = 0.3
Positive-Sequence Restraint Factor, I2/I1 (a2) = 0.1
Zero-Sequence Restraint Factor, I2/I0 (k2) = 0.2
31
Table 4: Ground Directional Overcurrent relay settings summary for Relay A
CT ratio 320
Time Dial 2.2
Overcurrent Curve U1
Timed Overcurrent pick up (Asec) 1.5
Instantaneous Overcurrent pick up (Asec) 9.5
Figure 9: Inverse Overcurrent Relay Curve (U1) for relays at Sub A
10 2 3 4 5 7 100 2 3 4 5 7 1000 2 3 4 5 7 10000 2 3 4 5 7
10 2 3 4 5 7 100 2 3 4 5 7 1000 2 3 4 5 7 10000 2 3 4 5 7CURRENT (A)
SECONDS
2
3
4
5
7
10
20
30
40
50
70
100
200
300
400
500
700
1000
2
3
4
5
7
10
20
30
40
50
70
100
200
300
400
500
700
1000
.01
.02
.03
.04
.05
.07
.1
.2
.3
.4
.5
.7
1
.01
.02
.03
.04
.05
.07
.1
.2
.3
.4
.5
.7
1
TIME-CURRENT CURVES By
For No.
Comment Date
1
1. Ground relay LINE A- LINE B GROC SEL3xx/5xxMI TD=2.2
SUB A 230.kV - SUB B 230.kV L SUB A - B
CTR=1600/5 Pickup=1.5A Inst=3040A TP@ 5.0=0.7491s
32
Figure 9 above shows the inverse overcurrent relay curve (U1) which was
selected. The operating time (Y axis) is inversely proportional to the current (X axis). The
more current the relay sees the faster it issues a trip. The curve can be selected to be
steeper (inverse to extremely inverse curve). The straight section of the plot is the
minimum current that would trigger an instantaneous trip (which we selected to be 3,040
Apri or 9.5 Asec).
Substation B
Using the simulation results in Appendix B, the calculations below was done to
determine the appropriate directional ground times and instantaneous overcurrent
settings.
Ground Directional Timed Overcurrent settings [6]:
Using the minimum ground fault current (Min3I0), the pickup value is calculated as:
51G= 0.5×Min3I0
CTR = 1.59 Asec
Select 51G = 1.5 Asec
5IC = U3.
Where:
Min3I0 = Minimum ground fault current
51G = Minimum current pickup value for Ground Timed Overcurrent protection
33
CTR = Current Transformer Ratio
51C = Time-Overcurrent curve
Using the SEL Curve U3 equation provided by SEL-411L instruction manual
MG = Max3I0
51P01 × CTR= 5.158
TimeGfault = 0.4 s
TDGMAXFAULT=
TimeGfault
0.0963 + 3.88
M𝐺2 − 1
= 1.95
Select 51TD = 2
Where:
Max3I0 = Maximum ground fault current
MG = Multiples of pickup
TimeGfault = Desired fastest clearing time
TD_GMAX_FAULT = SEL Time Dial element
51TD = Inverse Time Overcurrent 01 Time Dial
Ground Directional Instantaneous Overcurrent settings [6]:
The Ground Directional Instantaneous Current element is set to about 120% to
130% of the highest remote bus fault with no intentional time delay [6]. To get this, but a
fault on the remote bus with a strong source at the local bus or parallel line out.
34
50𝐺 = 1.2 × 𝑀𝑎𝑥3𝐼0
𝐶𝑇𝑅= 10.92 𝐴𝑠𝑒𝑐
Select 50G = 11 Asec 50GD = 0 cycle
Where:
Max3I0 = Maximum ground fault current
50G = Minimum current pickup for Ground Instantaneous Overcurrent protection
50GD = Time delay
CTR = Current Transformer Ratio
Table 5: Ground Directional Overcurrent relay settings summary for Relay B
CT ratio 320
Time Dial 2
Overcurrent Curve U3
Timed Overcurrent pick up (Asec) 1.5
Instantaneous Overcurrent pick up (Asec) 11
Ground directional overcurrent relays are typically polarized using either the
negative sequence voltage or the zero sequence voltage from the remote end. Refer to
Appendix B for polarization quantities.
35
Figure 10: Very Inverse Overcurrent Relay Curve (U3) for relays at Sub B
Figure 10 above shows the very inverse overcurrent relay curve (U3) which was
selected. The operating time (Y axis) is inversely proportional to the current (X axis). The
U3 curve is steeper than the U1 curve. This implies that for the same amount of current,
the time overcurrent relay using the U3 curve would trip faster than U1 curve. The
straight section of the plot is the minimum current that would trigger an instantaneous trip
(which we selected to be 3,520 Apri or 11 Asec)
10 2 3 4 5 7 100 2 3 4 5 7 1000 2 3 4 5 7 10000 2 3 4 5 7
10 2 3 4 5 7 100 2 3 4 5 7 1000 2 3 4 5 7 10000 2 3 4 5 7CURRENT (A)
SECONDS
2
3
4
5
7
10
20
30
40
50
70
100
200
300
400
500
700
1000
2
3
4
5
7
10
20
30
40
50
70
100
200
300
400
500
700
1000
.01
.02
.03
.04
.05
.07
.1
.2
.3
.4
.5
.7
1
.01
.02
.03
.04
.05
.07
.1
.2
.3
.4
.5
.7
1
TIME-CURRENT CURVES By
For No.
Comment Date
1
1. Ground relay LINE A - LINE B GROC SEL-VI TD=2
SUB B 230.kV - SUB A 230.kV L SUB A - B
CTR=320:1 Pickup=1.5A Inst=3520A TP@ 5.0=0.5159s
36
7. SIMIULATION RESULTS
In Section Fault
We will be analyzing a phase to ground fault (AG) placed at about 10% of the line
from Sub A. Without using a POTT scheme, as shown in Figure 11, the directional
instantaneous ground overcurrent line relay at Sub A would issue for the tripping of
Breaker A with no time delay. It typically takes a high voltage circuit breaker about 0.1
seconds to trip and isolate a fault.
The directional timed ground overcurrent line relay at Sub B would pick up and
issue for the tripping of Breaker B after a time delay of 0.563 second. The time delay plus
the time it takes the breaker to open results in an actual tripping time of 0.653 second.
Figure 11: Aspen Oneliner Simulation of applied SLG fault
With a POTT scheme, we can see in Figure 12 and Figure 13 that both relays’ RO
element would pick up (50G2), both would key the transfer trip channel (KEY), and both
would receive a permissive trip signal (PTRX). The line breakers clear the fault on the
37
line in about 0.1 seconds at both ends. So rather than waiting for 0.653 second to clear the
single phase to ground fault, by using a POTT scheme we can clear the fault much faster.
About half a second might seem irrelevant to us, but in the protection world, this is a
huge deal. This difference could prevent power stability issues or area blackouts due to
cascading fault events.
Figure 12: SEL SynchroWave file of Line relay at Sub A for in-section SLG Fault
38
Figure 13: SEL SynchroWave file of Line relay at Sub B for in-section SLG Fault
Next, we analyze how a POTT scheme compares to the Zone 1 (Z1) and Zone 2
(Z2) phase distance protection of the transmission line. For this analyzes, a phase to
phase fault (LL) was placed at about 10% of the line from Sub A. Without using a POTT
scheme, as shown in Figure 14, the phase distance Z1 element at Sub A would issue for
the tripping of Breaker A without a time delay. The Z2 phase distance element at Sub B
would pick up and issue for the tripping of Breaker B after a time delay of 20 cycles
(0.333 second).
39
Figure 14: Aspen Oneliner Simulation of applied LL fault
With a POTT scheme, we can see in Figure 15 and Figure 16 that both relays’ RO
element would pick up, both would key the transfer trip channel (KEY), and both would
receive a permissive trip signal (PTRX). The line breakers clear the fault on the line in
about 0.1 second at both ends. The POTT scheme supersedes the Zone 2 time delay of
0.333 second and clears the fault faster.
40
Figure 15: SEL SynchroWave file of Line relay at Sub A for in-section LL Fault
41
Figure 16: SEL SynchroWave file of Line relay at Sub B for in-section LL Fault
The POTT scheme would operate the same way for a 3LG, LL, and LLG fault.
The only difference would be the magnitude of the fault current. The when the fault is
outside the Z1 protection of the relay, the POTT scheme would supersede the preselected
Z2 time delay and would trip the circuit breaker faster.
42
Out of Section Fault
For an out of section fault as explained in section 5, we do not expect the relays to
operate via the POTT scheme. Figure 17 and Figure 18 helps us visualize what happens
when a fault is placed on Bus B and then reversed and placed on Bus A. With a phase to
phase fault (LL) occurring at Bus B, we expect the RO element to pick up at Sub A but
not at Sub B. When the reversal occurs, we expect the RO element to pick up at Sub B
but not at Sub A. Let’s analyze the waveforms below.
Figure 17 below is the waveform observed from relay A. During the first few
cycles we placed a fault on the 230kV Bus at Sub B. We observe that the RO element
(Z2P) picks up (sees the fault). The relay keys the transfer trip channel but does not
receive a permissive trip signal from relay B.
The fault is then reversed and placed on the 230kV Bus at Sub A. The RO
element does not see the fault because the fault is in the reverse direction. To confirm the
direction, we can see that the Z3P element picks up since it is looking in the reverse
direction. Relay A receives a permissive trip signal from relay B but does not key the
transfer trip channel. As a result, Breaker A does not trip for the fault.
43
Figure 17: SEL SynchroWave file of Line relay at Sub A for out-of-section LL Fault
Figure 18 below is the waveform observed from relay B. During the first few
cycles we placed a fault on the 230kV Bus at Sub B. We observe that the RO element
(Z2P) does not pick up because the fault is behind the relay. To confirm the direction, we
can see that the Z3P element picks up since it is looking in the reverse direction. The
relay receives a permissive trip signal from relay A but does not key the transfer trip
channel.
44
Figure 18: SEL SynchroWave file of Line relay at Sub B for out-of-section LL Fault
The fault is then reversed and placed on the 230kV Bus at Sub A. The RO
element (Z2P) picks up (sees the fault). The relay keys the transfer trip channel but does
not receive a permissive trip signal. As a result, Breaker B does not trip for the fault.
Since both relays’ RO element did not pick up, key the transfer trip channel and
receive a permissive trip signal from the other end during the same cycles, the POTT
scheme did not operate for the out of section fault.
This fault test was done to mimic how the relays should operate when there’s a
close-in fault at a breaker on a parallel line. For a close in fault on a parallel line’s
45
breaker, these relays can experience a current direction reversal when the said breaker
opens to clear the fault.
For all out of section faults (3LG, LLG, LL, SLG), the POTT scheme would
operate the same and would not issue for a trip. The only difference would be that for a
SLG fault, the ground overcurrent relay would pick up rather than the phase distance
relay.
46
8. CONCLUSION
Faults on the electric equipment can have very devastating effects. Faults are
disturbances on the power system that cause changes in normal operations such as
changes in current and voltage. A huge increase in current flowing through electrical
equipment can result in overloading, fires and can threaten personnel safety. Changes in
voltage levels can result in power stability issues and system wide blackout. It is very
important that we isolate a faulted equipment from the rest of the power system and cut
off all sources feeding the fault.
Circuit breakers can be used to isolate faulted equipment from the power system.
Circuit breakers rely on relays to make calculations, determine if a fault has occurred on
the protected equipment, and to signal the breaker to isolate the equipment. Relays
depend on Current transformers, Potential transformers and user defined settings to
determine if a fault has occurred and if the breaker needs to trip the fault. A relay can
operate based on two main types of protection schemes; non-pilot and pilot schemes.
Pilot schemes are protection settings that require communication from relays on
both ends of the protected equipment. Pilot schemes are used to ensure selectivity and
fast tripping. Pilot schemes are typically implemented in areas with power stability issues
or relay coordination issues with upstream or downstream relays. POTT is a type of pilot
scheme that can be used for transmission line protection.
Permissive overreaching transfer trip (POTT) is a secured protection scheme that
enables protective circuit breakers to trip faster for a fault on the protected line
47
(conductor). POTT scheme would not issue for a trip when the fault is not on the
protected line. A relay using POTT protection must be set to have an overreaching
element that sees beyond the protected line. When the overreaching element (typically
Zone 2 protection) picks up for a fault, it keys a transfer trip channel but would not trip
the breaker unless it receives a permissive trip signal from the remote end relay.
POTT scheme depends on a very secure communication channel between the
local and remote relays. If the communication channel gets compromised, the POTT
scheme would not operate, and a backup non-pilot protection should be used.
Communication channel security should be considered before deciding on what type of
channel can be used for this scheme.
48
Appendix A
Simulations and Settings for Line Relay Substation A
1. Aspen Simulation Results
Table: Remote Bus & Line End Faults
Imin3ph≔2863•Apri 3LG @ Sub B, Sub E-Sub A 230kV Line Out
Imax3ph ≔ 4216 • Apri 3LG @ Sub B, Sub D − Sub B 230kV Line Out
ZPmin ≔ 21.9 Ωpri 3LG @ Sub B
ZPmax ≔ 21.9 Ωpri 3LG @ Sub B
Min3I0= 1016 • Apri SLG @ Sub B, Sub B − Sub C 230kV Line Out
Max3I0= 2476 • Apri SLG close in end open on Sub D - Sub B 230kV Line ,
Sub B Bank #2 Out
Iminfphase≔2412•Apri SLG @ Sub B, Sub B – Sub C 230kV Line Out
Imaxfphase = 4216•Apri SLG @ Sub B, Sub D – Sub B 230kV Line Out
Iclosein_min_3ph = 13902•Apri 3 Ph Close in fault with Sub E - Sub A 230kV Line
Out
Iclosein_min_f_phase = 13902•Apri 1 Ph-Gnd Close in fault with Sub A - Sub D 230kV
Line Out
Iclosein_min3I0 = 13166•Apri
Table: Reverse Currents
Imax3ph_rev = 3573•Apri 3LG @ Sub A, Sub D – Sub B 230kV Line out
Max3I0REV= 2905 • Apri SLG @ Sub A, Sub A – Sub D 230kV Line out
ImaxfphaseREV=3573•Apri 3LG @ Sub A, Sub D – Sub B 230kV Line out
Table: Polarizing Quantities
V0 = 7.4 •Vpri SLG @ Sub B
V2 = 9.6 • Vpri SLG LEF to Sub B
49
2. Pilot Settings
ECOMM = POTT
TX_IDPORT1 = 1
RX_IDPORT1 = 2
The pilot (POTT) forward ground overcurrent pickup is set to less than or equal to 50%
of the minimum fault value.
50G2P = 0.5×Min3I0
CTR = 1.59 Asec
Select 50G2P = 1.5 Asec
50G2P = 480 Apri
3. Coordination Checks for Phase Distance Relay
Check of coordination with Upstream Terminals (N-1 POTT Out):
1. Lines into Sub B:
Sub B - Sub K: ok. Zone 2 only sees 1% of Sub B - Sub K line
Sub D - Sub B: ok. Zone 2 only sees 12% of Sub D - Sub B line
Sub B - Sub L: ok. Zone 2 only sees 2% of Sub B - Sub L line
Sub B - Sub C: ok. Zone 2 only sees 2% of Sub B - Sub C line
Sub M - Sub B: ok. Zone 2 only sees 3% of Sub M - Sub B line
2. Sub A Bank 1 and Bank 2
ok. Zone 2 does not see beyond instantaneous zone of Bank 1 and Bank 2
50
Check of coordination with Downstream Terminals:
Sub F - Sub A: ok. Zone 2 reach of Sub F only sees 4% of Sub A - Sub B line
Sub G - Sub A: ok. Zone 2 reach of Sub G only sees 2% of Sub A - Sub B line
Sub E - Sub A: ok. Zone 2 reach of Sub E only sees 6% of Sub A - Sub B line
Sub A - Sub D: ok. Zone 2 reach of Sub D only sees 2% of Sub A - Sub B line
Sub A - Sub H: ok. Zone 2 reach of Sub H only sees 4% of Sub A - Sub B line
Sub A - Sub I: ok. Zone 2 reach of Sub I only sees 4% of Sub A - Sub B line
Sub A - Sub J: ok. Zone 2 reach of Sub J only sees 6% of Sub A - Sub B line
4. Coordination Checks for Directional Ground Overcurrent Relays
Check of coordination with Upstream Terminals (N-1 POTT Out):
1. Lines into Sub B:
Sub B - Sub K: ok. Does not see beyond IT zone of line relay
Sub D - Sub B: ok. Does not see beyond IT zone of line relay
Sub B - Sub L: ok. Does not see beyond IT zone of line relay
Sub B - Sub C: ok. Does not see beyond IT zone of line relay
Sub M - Sub B: ok. Does not see beyond IT zone of line relay
2. Sub A Bank 1 and Bank 2
ok. Zone 2 does not see beyond instantaneous zone of Bank 1 and Bank 2
Check of coordination with Downstream Terminals:
Sub F - Sub A: ok. Does not see beyond IT zone of line relay
Sub G - Sub A: ok. Does not see beyond IT zone of line relay
51
Sub E - Sub A: ok. Does not see beyond IT zone of line relay
Sub A - Sub D: ok. Sub K line relay trips in 4 seconds for fault beyond IT zone of
Sub B line relay
Sub A - Sub H: ok. Does not see beyond IT zone of line relay
Sub A - Sub I: ok. Does not see beyond IT zone of line relay
Sub A - Sub J: ok. Does not see beyond IT zone of line relay
52
Appendix B
Simulations and Settings for Line Relay Substation B
1. Aspen Simulation Results
Table: Remote Bus & Line End Faults
Imin3ph≔2270•Apri 3LG @ Sub A, Sub B - Sub K 230kV Line Out
Imax3ph ≔ 3573 • Apri 3LG @ Sub A, Sub D - Sub B 230kV Line Out
ZPmin ≔ 21.9 Ωpri 3LG @ Sub A
ZPmax ≔ 21.9 Ωpri 3LG @ Sub A
Min3I0= 1502 • Apri SLG @ Sub A, Sub E - Sub A 230kV Line Out
Max3I0= 2912 • Apri SLG close in end open on Sub A - Sub J 230kV Line,
Sub A -Sub B 230kV Line Out
Iminfphase≔1938•Apri SLG @ Sub A, Sub E - Sub A 230kV Line Out
Imaxfphase = 3573•Apri 3LG @ Sub A, Sub D - Sub B 230kV Line Out
Iclosein_min_3ph = 9245•Apri 3 Ph Close in fault with Sub D - Sub B 230kV Line
Out
Iclosein_min_f_phase = 9570•Apri 1 Ph-Gnd Close in fault with Sub A - Sub D 230kV
Line Out
Iclosein_min3I0 = 13166•Apri
Table: Reverse Currents
Imax3ph_rev = 4216•Apri 3LG @ Sub B, Sub D - Sub B 230kV Line Out
Max3I0REV= 2123 • Apri SLG @ Sub B, Sub D - Sub B 230kV Line Out
ImaxfphaseREV= 4216•Apri 3LG @ Sub B, Sub D - Sub B 230kV Line Out
Table: Polarizing Quantities
V0 = 5.4 •Vpri SLG LEF Sub A
V2 = 11.6 • Vpri SLG LEF to Sub A
53
2. Pilot Settings
ECOMM = POTT
TX_IDPORT1 = 2
RX_IDPORT1 = 1
The pilot (POTT) forward ground overcurrent pickup is set to less than or equal to 50%
of the minimum fault value.
50G2P = 0.5×Min3I0
CTR = 2.35 Asec
Select 50G2P = 1.5 Asec
50G2P = 480 Apri
3. Coordination Checks for Phase Distance Relay
Check of coordination with Upstream Terminals (N-1 POTT Out):
1. Lines into Sub B:
Sub F - Sub A: ok. Zone 2 only sees 6% of Sub F - Sub A line
Sub G - Sub A: ok. Zone 2 only sees 1% of Sub G - Sub A line
Sub E - Sub A: ok. Zone 2 only sees 7% of Sub E - Sub A line
Sub A - Sub D: ok. Zone 2 only sees 4% of Sub A - Sub D line
Sub A - Sub H: ok. Zone 2 only sees 1% of Sub A - Sub H line
Sub A - Sub I: ok. Zone 2 only sees 6% of Sub A - Sub I line
Sub A - Sub J: ok. Zone 2 only sees 3% of Sub A - Sub J line
54
2. Sub A Bank 1 and Bank 2
ok. Zone 2 does not see beyond instantaneous zone of Bank 1 and Bank 2
Check of coordination with Downstream Terminals:
Sub B - Sub K: ok. Zone 2 reach of Sub K only sees 8% of Sub A - Sub B line
Sub D - Sub B: ok. Zone 2 reach of Sub D only sees 2% of Sub A - Sub B line
Sub B - Sub L: ok. Zone 2 reach of Sub L only sees 18% of Sub A - Sub B line
Sub B - Sub C: ok. Zone 2 reach of Sub C only sees 6% of Sub A - Sub B line
Sub M - Sub B: ok. Zone 2 reach of Sub M only sees 6% of Sub A - Sub B line
4. Coordination Checks for Directional Ground Overcurrent Relays
Check of coordination with Upstream Terminals (N-1 POTT Out):
1. Lines into Sub B:
Sub F - Sub A: ok. Does not see beyond IT zone of line relay
Sub G - Sub A: ok. Does not see beyond IT zone of line relay
Sub E - Sub A: ok. Does not see beyond IT zone of line relay
Sub A - Sub D: ok. Sub K line relay trips in 4 seconds for fault beyond IT zone of
Sub B line relay
Sub A - Sub H: ok. Does not see beyond IT zone of line relay
Sub A - Sub I: ok. Does not see beyond IT zone of line relay
Sub A - Sub J: ok. Does not see beyond IT zone of line relay
55
2. Sub A Bank 1 and Bank 2
ok. Will miscooordinate for a N-2 condition with Sub A Bank 1 &2 high side relays
when differential relays are cut out and Sub A - Sub D line is out.
Check of coordination with Downstream Terminals:
Sub B - Sub K: ok. Sub K line relay trips in 2 seconds for fault beyond IT zone of
Sub B line relay
Sub D - Sub B: ok. Does not see beyond IT zone of line relay
Sub B - Sub L: ok. Does not see beyond IT zone of line relay
Sub B - Sub C: ok. Does not see beyond IT zone of line relay
Sub M - Sub B: ok. Does not see beyond IT zone of line relay
56
REFERENCES
[1] “Current Transformer Basics and Current Transformer Theory,” Basic Electronics
Tutorials, 05-Oct-2018. [Online]. Available:
https://www.electronics-tutorials.ws/transformer/current-transformer.html.
[Accessed: 04-Feb-2019].
[2] Electrical4U, “Distance Relay or Impedance Relay Working Principle
Types,” Electrical4U, 01-Sep-2018. [Online]. Available:
https://www.electrical4u.com/distance-relay-or-impedance-relay-working-principle-
types/. [Accessed: 20-Feb-2019].
[3] “Understanding Permissive Over-Reaching Transfer Trip (POTT) Communication
Assisted Trip Schemes Video,” Valence Electrical Training Services, 06-Mar-2018.
[Online]. Available: https://relaytraining.com/understanding-permissive-over-
reaching-transfer-trip-pott-communication-assisted-trip-schemes-video/. [Accessed:
08-Mar-2019].
[4] Pacific Gas and Electric Relay App Guide
[5] Pacific Gas and Electric Transmission Protective Relay Setting Manual
[6] Pacific Gas and Electric Line Relay Setting Calculations Mathcad file