training plan and skill matrix

1
Name Position Srl No. Instruction Manual Trainee's current Level Level of Trainer Name of Trainer Dt. of Training Trainer Sign. Trainee Sign. Site Operational Familiarization 1 3 3 3 3 3 IM/SC 2 3 3 3 3 3 Cmpl Mngr 3 2 2 3 3 3 IM/SC 4 1 1 3 3 3 IM/SC 5 3 3 3 3 3 IM/SC 6 3 3 3 3 3 IM/SC 7 1 1 1 1 1 PM + IM/SC 8 3 3 2 2 2 IM/SC 9 2 2 2 3 3 IM/SC Warehouse Operations Awareness 1 3 3 1 WS/IM 2 3 3 1 1 1 WS/IM 3 3 3 1 1 1 WS/IM SC SCM LM IM WS Training Requirement List of skills Yard Operation and cleaning Waste Beans and recycling Skill Matrix - Supply Chain Team Initial visit to warehouse and production site, lab Oversee a collection/delivery Newport Street Operation Shift plan, Rotas, Break times, key holding Introduction to the team Trip around the site, health and saftery awareness, breaks Familiarise with log in, It system, Outlook Understaning the Costa's operational structure, channels Familiarise with Green Coffee, origins, warehouses Familiarise with packing supplier and packaging material. 3 3 3 1 1 1 WS/IM 4 3 3 1 1 1 WS/IM 5 3 3 2 2 2 WS/IM 6 3 3 2 2 2 WS/IM 7 3 3 2 2 2 WS/IM Understanding of physical stock movement at Roastery 1 3 3 2 1 1 IM/SC/WS 2 3 3 2 1 1 IM/SC/WS 3 3 3 2 1 1 IM/SC/WS 4 3 3 2 1 1 IM/SC/WS 5 3 3 2 2 1 IM/SC/WS 6 3 3 2 1 1 IM/SC/WS 7 3 3 2 1 1 IM/SC/WS 8 3 3 2 1 1 IM/SC/WS 9 3 3 2 1 1 IM/SC/WS 10 3 3 2 2 1 IM/SC/WS 11 3 3 2 2 1 IM/SC/WS Understanding of Stock Movement on Nav 1 Ship and receive trasnfer order from Roastery to K&N/PTS 1 2 3 2 IM/LM 2 1 2 3 2 IM/LM 3 1 2 3 2 IM/LM 4 1 2 3 2 IM/LM 5 Transfer finished good from production to Arches Ship and receive trasnfer order for Green Coffee Transfer Green coffee from Arches to Production Transfer packaging from Arches to production Green Coffee Inbound Process, paperwork, FIFO Packaging, pallets and Consumables Inbound, paperwork, FIFO Green Coffee movement from Arch to Production, paperwork Packaging from Arch to Production Finished goods from Production to Arch Quarantine stock from production to Arch, paperwork Finished good collection from arches, process, slots, paperwork Quarantine stock, non-compliance and return to supplier Weekly and Monthly stock count Document scanning and filling Return to supplier Fork lift opeartion, maintenance, parking and check list Item location in arches with relevant paperwork, cleaning rotas Arch humidity and temperature check list and cleaning Used pallets and Hessian bags movement Waste Beans and recycling 5 1 2 3 2 IM/LM 6 1 2 3 2 IM/LM 7 1 2 3 2 IM/LM 8 1 2 3 2 IM/LM 9 1 2 3 2 IM/LM 10 1 2 3 2 IM/LM 11 1 2 3 2 1 IM/LM 12 1 2 3 2 IM/LM 13 1 2 3 2 IM/LM 14 1 2 3 2 IM/LM 15 1 2 3 2 IM/LM 16 1 2 3 2 IM/LM Understanding of advanced Nav 1 1 1 PM/SA/IM 2 1 1 PM/SA/IM 3 1 1 PM/SA/IM 4 1 1 PM/SA/IM Supply Chain Operations and understanding 1 3 2 1 LM/SCM 2 3 2 1 LM/SCM 3 2 2 1 LM/SCM 4 2 2 1 LM/SCM Stock managment and optimization, material planning Consumption Report Analysis Stock Non-Confirmity Understaning, VSOP KANBAN opeartion in the warehouse Transfer finished good from production to Arches Transfer Quarantine items from production to arches Creating and mordifying a BOM Creating a new version of BOM Creating a new process routing Receive a purchase order Mordifying a process routing Rasing of Transfer order for Green Coffee Raising of Transfer order for channels Ship and receive a sales order Rasing and amend a purchase Order Ship and receive a PO for L&Y Raise and receive a return order Cancel a posted purchase order receipt Purchase receipt and invoice tracing Duplicate old purchase order 4 2 2 1 LM/SCM 5 3 3 3 Line Manager 6 3 2 1 PM/LM 7 1 1 1 PM/LM Planning and Managemnet 1 3 3 LG/SCM 2 3 1 LG/SCM 3 3 2 LG/SCM 4 3 3 2 LG/SCM 5 3 2 LG/SCM 6 3 1 Cmpl Manager 7 3 1 LG/SCM Key SC Cmpl Mngr IM 3 - Subject Matter Expert LM 2- Good Undersatnding SCM 1- Elementary Knowledge PM 0- Knowledge Gap WS Compliance Manager Stock Controller Warehouse Supervisor Production Manager Supply Chain Manager Logistics Manager Inventory Manager Introduction to management of overall logistics operation Monthly forecast reporting Product Tracebility Report Stock adjustment using item journal and physical stock count Regular management of L&Y Management of supplier accounts and relationship building Sporadic health and safety checks wrt logisctics operation Performance Review and Objectives introduction Yearly Capacity Planning - Roastery and L&Y Weekly Production planning KANBAN opeartion in the warehouse

Upload: prabir-chattopadhyay

Post on 20-Feb-2017

188 views

Category:

Documents


5 download

TRANSCRIPT

Page 1: Training Plan and Skill Matrix

Name

Position

Srl No.Instruction

Manual

Trainee's

current

Level

Level of TrainerName of

Trainer

Dt. of

TrainingTrainer Sign.

Trainee

Sign.

Site Operational Familiarization

1 3 3 3 3 3 IM/SC

2 3 3 3 3 3 Cmpl Mngr

3 2 2 3 3 3 IM/SC

4 1 1 3 3 3 IM/SC

5 3 3 3 3 3 IM/SC

6 3 3 3 3 3 IM/SC

7 1 1 1 1 1 PM + IM/SC

8 3 3 2 2 2 IM/SC

9 2 2 2 3 3 IM/SC

Warehouse Operations Awareness

1 3 3 1 WS/IM

2 3 3 1 1 1 WS/IM

3 3 3 1 1 1 WS/IM

SC SCMLMIMWS

Training RequirementList of skills

Yard Operation and cleaning

Waste Beans and recycling

Skill Matrix - Supply Chain Team

Initial visit to warehouse and production site, lab

Oversee a collection/delivery

Newport Street Operation

Shift plan, Rotas, Break times, key holding

Introduction to the team

Trip around the site, health and saftery awareness, breaks

Familiarise with log in, It system, Outlook

Understaning the Costa's operational structure, channels

Familiarise with Green Coffee, origins, warehouses

Familiarise with packing supplier and packaging material.

3 3 3 1 1 1 WS/IM

4 3 3 1 1 1 WS/IM

5 3 3 2 2 2 WS/IM

6 3 3 2 2 2 WS/IM

7 3 3 2 2 2 WS/IM

Understanding of physical stock movement at Roastery

1 3 3 2 1 1 IM/SC/WS

2 3 3 2 1 1 IM/SC/WS

3 3 3 2 1 1 IM/SC/WS

4 3 3 2 1 1 IM/SC/WS

5 3 3 2 2 1 IM/SC/WS

6 3 3 2 1 1 IM/SC/WS

7 3 3 2 1 1 IM/SC/WS

8 3 3 2 1 1 IM/SC/WS

9 3 3 2 1 1 IM/SC/WS

10 3 3 2 2 1 IM/SC/WS

11 3 3 2 2 1 IM/SC/WS

Understanding of Stock Movement on Nav

1 Ship and receive trasnfer order from Roastery to K&N/PTS 1 2 3 2 IM/LM

2 1 2 3 2 IM/LM

3 1 2 3 2 IM/LM

4 1 2 3 2 IM/LM

5 Transfer finished good from production to Arches

Ship and receive trasnfer order for Green Coffee

Transfer Green coffee from Arches to Production

Transfer packaging from Arches to production

Green Coffee Inbound Process, paperwork, FIFO

Packaging, pallets and Consumables Inbound, paperwork, FIFO

Green Coffee movement from Arch to Production, paperwork

Packaging from Arch to Production

Finished goods from Production to Arch

Quarantine stock from production to Arch, paperwork

Finished good collection from arches, process, slots, paperwork

Quarantine stock, non-compliance and return to supplier

Weekly and Monthly stock count

Document scanning and filling

Return to supplier

Fork lift opeartion, maintenance, parking and check list

Item location in arches with relevant paperwork, cleaning rotas

Arch humidity and temperature check list and cleaning

Used pallets and Hessian bags movement

Waste Beans and recycling

5 1 2 3 2 IM/LM

6 1 2 3 2 IM/LM

7 1 2 3 2 IM/LM

8 1 2 3 2 IM/LM

9 1 2 3 2 IM/LM

10 1 2 3 2 IM/LM

11 1 2 3 2 1 IM/LM

12 1 2 3 2 IM/LM

13 1 2 3 2 IM/LM

14 1 2 3 2 IM/LM

15 1 2 3 2 IM/LM

16 1 2 3 2 IM/LM

Understanding of advanced Nav

1 1 1 PM/SA/IM

2 1 1 PM/SA/IM

3 1 1 PM/SA/IM

4 1 1 PM/SA/IM

Supply Chain Operations and understanding

1 3 2 1 LM/SCM

2 3 2 1 LM/SCM

3 2 2 1 LM/SCM

4 2 2 1 LM/SCM

Stock managment and optimization, material planning

Consumption Report Analysis

Stock Non-Confirmity Understaning, VSOP

KANBAN opeartion in the warehouse

Transfer finished good from production to Arches

Transfer Quarantine items from production to arches

Creating and mordifying a BOM

Creating a new version of BOM

Creating a new process routing

Receive a purchase order

Mordifying a process routing

Rasing of Transfer order for Green Coffee

Raising of Transfer order for channels

Ship and receive a sales order

Rasing and amend a purchase Order

Ship and receive a PO for L&Y

Raise and receive a return order

Cancel a posted purchase order receipt

Purchase receipt and invoice tracing

Duplicate old purchase order

4 2 2 1 LM/SCM

5 3 3 3 Line Manager

6 3 2 1 PM/LM

7 1 1 1 PM/LM

Planning and Managemnet

1 3 3 LG/SCM

2 3 1 LG/SCM

3 3 2 LG/SCM

4 3 3 2 LG/SCM

5 3 2 LG/SCM

6 3 1 Cmpl Manager

7 3 1 LG/SCM

Key SC

Cmpl Mngr

IM

3 - Subject Matter Expert LM

2- Good Undersatnding SCM

1- Elementary Knowledge PM

0- Knowledge Gap WS

Compliance Manager

Stock Controller

Warehouse Supervisor

Production Manager

Supply Chain Manager

Logistics Manager

Inventory Manager

Introduction to management of overall logistics operation

Monthly forecast reporting

Product Tracebility Report

Stock adjustment using item journal and physical stock count

Regular management of L&Y

Management of supplier accounts and relationship building

Sporadic health and safety checks wrt logisctics operation

Performance Review and Objectives introduction

Yearly Capacity Planning - Roastery and L&Y

Weekly Production planning

KANBAN opeartion in the warehouse