substation layout

58
SUBSTATION LAYOUT, SWITCHING SCHEMES AND GENERAL ARRANGEMENT 16.02.2009 (15:45 TO 17:15) MANOJ KUMAR, MANAGER (S/S), MOGA [email protected] [email protected] Mob. : 09417215560

Upload: 386

Post on 01-Nov-2014

680 views

Category:

Documents


45 download

DESCRIPTION

Substation layout

TRANSCRIPT

Page 1: Substation Layout

SUBSTATION LAYOUT, SWITCHING SCHEMES AND GENERAL ARRANGEMENT

16.02.2009 (15:45 TO 17:15)

MANOJ KUMAR, MANAGER (S/S), MOGA

[email protected]

[email protected]

Mob. : 09417215560

Page 2: Substation Layout

General ArrangementA Designer perspective, but fine

tuned at site Placement of switchyard Control Room placement Fire fighting pump house placement DG set placement LT station placement

(ACDB, DCDB, Battery Bank & Battery Charges)

Identification of roads & rail tracks Identification of boundary wall and

fencing Identification of approach roads Space for colony and other

infrastructures

Page 3: Substation Layout

Switchyard Layout

Single Line Diagram Bus Switching Scheme Normal rating with temperature

rise, Short time current rating Rating & insulation levels of the

equipments Bay numbering

Page 4: Substation Layout

General Arrangement

LAYOUT (PLAN & SECTION) OF SWITCHYARD

PLANNING ASPECTS:

• Switching scheme to be adopted.• Type of Layout (D or I)• Details of feeders requirements. • Future/anticipated expansion of the substation .• Available size of plot .

Page 5: Substation Layout

Major factors deciding a layout …

Standard factors Electrical clearances Heights of different levels & electric field

Variable factors Shape of land & feeder orientation

Bus bar arrangement Type of isolator used Arrangement of lightning protection

Location of control room building, FFPH

Roads and rail tracks

Page 6: Substation Layout

General Arrangement Following factors determine the switchyard area

Conventional (AIS) OR GIS

D Type OR I Type Layout

Automation (SAS) OR without Automation

Page 7: Substation Layout

GA:- Area occupied by one Dia in D & I Layout

8662.5 sqm=2.14 acre (27m bay width)

7969.5sqm=1.969 acre (24m bay width)

3504 sqm = 0.865 acre (24m bay width)

Page 8: Substation Layout
Page 9: Substation Layout

Layout (Plan & Sections)…

Selection of conductor for main bus, Transfer bus, Jack bus, equipment interconnection

AAC conductorACSR conductorAAAC conductorAluminium pipe

Space for a bay (bay width)Phase to phase clearancePhase to earth clearanceSection Clearance

….under worst condition

Page 10: Substation Layout

Minimum Clearances for Layout (at altitude <1000m above mean sea

level)…Voltage Level

(Rated)Ph-Ph

(mm)

Ph-E

(mm)

Sectional

Clearance (mm)

765 kV 7600 4900 10300

400 kV 4000 3500 6500

220 kV 2100 2100 5000

132 kV 1300 1300 4000

110 kV 1100 1100 3800

66 kV 630 630 3500

33 kV 320 320 2800

Altitude corrections w.r.t clearances, insulation levels, creepage and oil temperature rise of the equipment shall be considered for altitudes more than 1000 m above mean sea level.

Page 11: Substation Layout

Design Calculation for Layout …

Sag tension calculation & Sag tension Chart w.r.t initial static tension, maximum temperature rise etc.

Short circuit force calculation and determination of spacer span as per IEC:865

Direct Stroke Lightning Protection (DSLP) CalculationBy Lightning MastsBy Overhead earthwires

Design of earthing systemTouch & step potential controlGrid resistance as low as possibleLocation of fencing

Page 12: Substation Layout

Bay widths & levels…

Voltage Level

Bay width

First Level

Second Level

Third level

BIL

kVp

SIL

kVp

765 kV 38m 14m 27m 39m 2100 1550

400 kV 27/24m 8m 15m 22m 1550 1050

220 kV 18/16m 5.9m 11.7m 16.2m 1050 650

132 kV 12m 4.6m 7.5m 10.8m 650 NA

66 kV 7.6m 4m 6m 9.5m 325 NA

Ligtning Impulse : 1.2/50 micro secSwitching Impulse: 250/2500 micro sec

Page 13: Substation Layout

To understand Single Line diagram & Layout plan drawing…

Page 14: Substation Layout

To understand Layout Section drawing…

Page 15: Substation Layout

STANDARD CLASSIFICATION OF TOWERS

Tower Type

Height First Level

Height Second Level

Peak Angle of Deviation

End /Middle

TA 15 m NIL 7.5m ±30 deg End

TB 15 m NIL 7.5m ±30 deg Middle

TC 15 m NIL NIL 0 deg End

TD 15 m NIL NIL 0 deg Middle

TE 15 m NIL 7.5m 0 deg End

TF 15 m NIL 7.5m 0 deg Middle

TG 22 m NIL 7.5 m ±30 deg End

TH 22 m NIL 7.5 m ±30 deg Middle

TI 22 m NIL 7.5 m 0 deg End

TJ 22 m NIL 7.5 m 0 deg Middle

TK 15 m 7 m 7.5 m 0 deg Corner/ 2beams

TL 15 m 7 m 7.5 m 0 deg Middle/ 3beams

TM 15 m 7 m 7.5 m ±30 deg Corner/ 2beams

TN 15 m 7 m 7.5 m ±30 deg Middle/ 3beams

Wind Zone : 47m/Sec 400kV

Page 16: Substation Layout

NON-STANDARD TOWERS (MOGA)

Tower Type Description

400kVTG Beam at 15 m with peak 23m

TSP Beam at 23m with peak 30 m

G5 Beam at 15m (Twin Moose)

GSP Beam at 23m

220kVTA Beam at 11m

TB Beam at 11m & 17.5m

TC Beam at 11m & 17.5m with peak 22m

G1 Beam at 11m (Single Moose)

G2 Beam at 11m (Twin Moose)

G3 Beam at 17.5m (Single Moose)

Page 17: Substation Layout

Typical dimensions between equipments…

400 kV 220 kV 132 kV 66 kV

CB&ISO 10.5 m 6.5 m 3.75m 3 m

ISO&CT 7 m 4 m 2.5 m 2 m

CB&CT 7 m 3m+road+5 m 2.5 m 2 m

Gantry Tower &ISO

6 m 3.5 m 1.8 m 1.8 m

SA &PI& CVT 6 m 3.5 m 2.5 m 2 m

LA & SR 7 m - - -

Road & SR 15 m - - -

Page 18: Substation Layout

Control Room Building

Placement of Control, Relay & Protection

Panels PLCC Panels AC Distribution Board DC Distribution Board Batteries (220V, 48V) Battery Chargers Lighting Transformers Lighting Distribution Boards Rooms of Station-in Charge &

staff Miscellaneous

Page 19: Substation Layout

Fire Fighting Pump House

Placement of AC driven main pump DG driven stand-by pump Jockey Pump Air Vessels AC Distribution Board cum pump control panels Fire Water Tank

Page 20: Substation Layout

Miscellaneous

Placement of LT Station (ACDB, DCDB, Battery Bank &

Battery Chargers) Diesel Generator Set with AMF Panel Security hut Office Buildings Other residential buildings

Page 21: Substation Layout

Gas Insulated Substation (GIS)

GIS in POWERGRID POWERGRID is constructing 132kV, 220 kV

& 400 kV GIS substation Construction of 800 kV GIS is under

considerationTechnical Advantage of GIS All equipments are compact in size and

enclosed in SF6 gas with metallic enclosure

Area requirement of GIS is approx. 20% of conventional AIS

Lesser structures & foundation works; Hence less execution time

Costlier than AIS

Page 22: Substation Layout

Bus Bar Switching SchemesBus Bar Switching Schemes……Factors dictating choice of bus switching scheme

1) Reliability

No Power interruption during Bus fault

2) CB Maintenance

No Power interruption during CB maintenance. Taking out CB for maintenance shall be easy

3) Bus Bar Maintenance

No Power interruption during Bus bar maintenance

Page 23: Substation Layout

Bus Bar Switching SchemesBus Bar Switching Schemes……4) Simplicity of protection arrangements

Protection arrangements shall be simple for easy commissioning and regular checking

5) Ease of Extension

Extension of Bus bar necessary to take care of future expansion. Power interruption during such extension works.

6) Cost

Optimal techno-economic solution

Page 24: Substation Layout

Bus Switching SchemesBus Switching Schemes……

Single Main Bus Scheme Single Main Bus Scheme

– – with sectionaliser & without with sectionaliser & without sectionalisersectionaliser

Single Main & Transfer Bus Scheme Single Main & Transfer Bus Scheme Double Main Bus Scheme Double Main Bus Scheme Double Main with by-pass isolator Double Main with by-pass isolator

Bus schemeBus scheme Double Main & Transfer Bus SchemeDouble Main & Transfer Bus Scheme One & Half Breaker Bus SchemeOne & Half Breaker Bus Scheme Double bus two breaker SchemeDouble bus two breaker Scheme Ring Bus Scheme Ring Bus Scheme

Page 25: Substation Layout

Simplest and Simplest and cheapest bus bar cheapest bus bar schemescheme

Maintenance and Maintenance and extensions of bus extensions of bus bars are not bars are not possible without possible without shutdown of the shutdown of the substation.substation.

Operation & Operation & maintenance of bus maintenance of bus bar is easybar is easy.

SINGLE BUS SCHEMESINGLE BUS SCHEME

Page 26: Substation Layout
Page 27: Substation Layout

Similar to the single bus Similar to the single bus scheme except the scheme except the sectionalising breaker or sectionalising breaker or isolator.isolator.

By keeping the By keeping the sectionaliser open one sectionaliser open one section can be in service section can be in service and the other can be taken and the other can be taken for maintenance or for maintenance or extension.extension.

If a bus section breaker is If a bus section breaker is provided busbar protection provided busbar protection can detect fault on any can detect fault on any section and trip the section and trip the breakers connected to that breakers connected to that section and isolate it.section and isolate it.

SINGLE BUS WITH SECTIONALISERSINGLE BUS WITH SECTIONALISER

Page 28: Substation Layout

Individual CB can be taken Individual CB can be taken out for maintenance on-load out for maintenance on-load at a time.at a time.

The transfer bus coupler The transfer bus coupler acts as the breaker for the acts as the breaker for the circuit under by pass.circuit under by pass.

Individual circuits have a Individual circuits have a bypass isolator to connect bypass isolator to connect to the transfer bus and this to the transfer bus and this isolator will be closed isolator will be closed during bypass operation of during bypass operation of that particular circuit.that particular circuit.

SINGLE MAIN AND TRANSFER SINGLE MAIN AND TRANSFER SCHEMESCHEME

Page 29: Substation Layout

Load will be distributed on both the Load will be distributed on both the buses and the bus coupler shall be buses and the bus coupler shall be normally closed.normally closed.

For maintenance & extension of For maintenance & extension of any one of the buses the entire any one of the buses the entire load will be transferred to the load will be transferred to the other bus.other bus.

On load transfer of a circuit from On load transfer of a circuit from one bus to the other bus is possible one bus to the other bus is possible through bus isolators provided the through bus isolators provided the bus coupler is closed and thereby bus coupler is closed and thereby two buses are at the same two buses are at the same potential.potential.

On load bypassing of any circuit for On load bypassing of any circuit for breaker maintenance is not breaker maintenance is not possiblepossible.

DOUBLE BUS SCHEMEDOUBLE BUS SCHEME

Page 30: Substation Layout

DOUBLE BUS WITH BY-PASS SCHEMEDOUBLE BUS WITH BY-PASS SCHEME

Page 31: Substation Layout

This bus arrangement provides the facilities This bus arrangement provides the facilities of a double bus arrangement & a main and of a double bus arrangement & a main and transfer bus arrangement.transfer bus arrangement.

The bus to which the transfer bus isolator is The bus to which the transfer bus isolator is connected can be used as a transfer bus connected can be used as a transfer bus also.also.

During the time a circuit is under bypass, the During the time a circuit is under bypass, the bus coupler will act as the breaker for the bus coupler will act as the breaker for the bypassed circuit.bypassed circuit.

DOUBLE BUS WITH BY-PASS SCHEMEDOUBLE BUS WITH BY-PASS SCHEME

Page 32: Substation Layout
Page 33: Substation Layout

In this bus scheme, in In this bus scheme, in addition to the two main addition to the two main buses there will be a buses there will be a separate transfer bus also. separate transfer bus also.

Since separate transfer bus Since separate transfer bus is available there will be no is available there will be no need of transferring the need of transferring the load from one bus to the load from one bus to the other bus unlike in a double other bus unlike in a double main cum transfer bus main cum transfer bus arrangement.arrangement.

Other features are similar Other features are similar to the one described in to the one described in double bus with by pass double bus with by pass arrangement.arrangement.

DOUBLE MAIN AND TRANSFER DOUBLE MAIN AND TRANSFER SCHEMESCHEME

Page 34: Substation Layout

In this scheme, two circuit In this scheme, two circuit have three breakers, the have three breakers, the middle breaker ties the two middle breaker ties the two circuits and hence is called the circuits and hence is called the tie breaker. tie breaker.

Breaker or bus maintenance is Breaker or bus maintenance is possible without any shut possible without any shut down of the feederdown of the feeder

Even if both the buses are out Even if both the buses are out of service, power can be of service, power can be transferred from one feeder to transferred from one feeder to another feeder through tie another feeder through tie breakerbreaker

BREAKER AND HALF SCHEMEBREAKER AND HALF SCHEME

Page 35: Substation Layout

Each feeder is controlled Each feeder is controlled by two breakers.by two breakers.

This arrangement is This arrangement is comparatively costlier comparatively costlier than other scheme and than other scheme and hence followed in very hence followed in very important circuit only. important circuit only.

In this arrangement In this arrangement breaker maintenance for breaker maintenance for any feeder circuit is easily any feeder circuit is easily possible without any possible without any shutdownshutdown..

DOUBLE BUS TWO BREAKER SCHEMEDOUBLE BUS TWO BREAKER SCHEME

Page 36: Substation Layout

As long as the ring is As long as the ring is closed load has two closed load has two sources of supply and any sources of supply and any circuit breaker can be circuit breaker can be taken out of service taken out of service without affecting the without affecting the supply.supply.

Extension of ring scheme Extension of ring scheme is difficult.is difficult.

No bus bar protection No bus bar protection requiredrequired..

RING BUS SCHEMERING BUS SCHEME

Page 37: Substation Layout

Bus Switching Selection Bus Switching Selection considerations…considerations…

ReliabilityReliability Operation Flexibility Operation Flexibility Ease of MaintenanceEase of Maintenance Short Circuit Level LimitationShort Circuit Level Limitation Simplicity of Protection Simplicity of Protection

ArrangementArrangement Ease of Future expansionEase of Future expansion Land availabilityLand availability Cost Cost

Page 38: Substation Layout

A Case Study

Of

MOGA SUBSTATION

Page 39: Substation Layout

800 / 400 / 220 KV MOGA SUBSTATION

1065 MVA(4 ICTs & 3 Reactors)

800 KV KMTL-249.212 km

(Loc 602-730)

800 KV KMTL-151.343 km

(Loc 581-710)

400 KV D/C JMTL52.232 km

(Loc 510-647)

400 KV D/C MHTL & MFTL120.465 km(Loc 1- 321)

TRANSMISSION NETWORK OF MOGA SUBSTATION

220 KV D/C PSEB Jagraon-I&II

(35km)

400 KV D/C MOGA -Bhiwadi 352 km (under const.)

NRSSS-V

+ under const : 2 Nos. 63 MVAR Bhiwadi Line

React(NRSSS-V)+ Proposed : 765/400kV

System and LILO of PSEB Nakodar Line

220 KV D/C PSEB MOGA-I&II(400mtr)

220 KV D/C PSEB MOGA-III &IV

(400 mtr)

765 KV S/C Bhiwani - MOGA

Page 40: Substation Layout

Layout of Moga Substation A Case Study

D Type Layout (Residential area is more than switchyard area)

DE Tower of 400kV D/C Hisar Line located in 220 kV Switchyard obstructing future expansion of 220 kV S/Y

Location of Dead End Tower from Take off Gantry: Dead End Tower of 220kV Jagraon Line of PSEB was shifted from 30m to 100m outside boundary wall

Gantry is designed for 200m span with angle deviation ±30 deg both in vertical & horizontal plane

Page 41: Substation Layout

LAYOUT OF COLONY & SUBSTATION COMPLEX

Page 42: Substation Layout

Layout of Moga Substation: A Case Study

Bhiwadi Bays Extn works at Moga: Problems identified and changes proposed as per site conditions

Take-off gantry of Bhiwadi Line shifted by 9m to reduce angle on gantry from 15 deg to 9 deg

Matching of towers TG (Standard vs Non-standard)

Dead End Tower of 400kV Moga-Bhiwadi Line was shifted as per site condition facilitating 765kV interconnection

Foundation for CT in Tie Bay falling over already constructed cable trench

No scope kept for Stone spreading, construction of approach roads for bays, incl old KMTL bays

Re-orientation of rail track in reactor foundation

LM marked in the engg. drawing but not existing

Page 43: Substation Layout

Layout of Moga Substation A Case Study

Re-locating 50 MVAR Bus Reactor Bay numbering in random order including Tie

Bay T1 & T2 Isolators 400kV D/C Moga -Jalandhar Line in one Dia Provision of SVC 33kV, 25 MVAR Tertiary Reactors Shifting of Bus CVTs Conversion of 5 CT to 3 CT protection scheme Re-locating 245kV CT to enhance availability

Page 44: Substation Layout

B. ADDITIONAL LAND ACQUIRED : 33 Acers

FOR 800 KV SWITCHYARD

C. ADDITIONAL LAND BEING : 32.3 Acres

ACQUIRED FOR 765KV SUBSTATION (2X1500 MVA, 765/400KV ICT, 2x240MVAR BUS REACTOR,

1X240 MVAR LINE REACTOR & TSS OF TALWANDI SABO OF PSEB)

A. TOTAL AREA : 70.25 Acers1. 400 KV SWITCHYARD : 31.60 Acres

2. TOWNSHIP BUILT-UP AREA : 13.77 Acres

3. TOWNSHIP OPEN AREA : 24.88 Acres

Page 45: Substation Layout

ICT-I BAY220 kV PSEB-I I I

220 kV PSEB-IV

220 kV PSEB-I

220 kV PSEB-I I

400 KV BUS-I

400 KV BUS-I I

220 KV BUS-I

220 KV BUS-I I

220 KV TRANSFER BUS

ICT-I I BAY

ICT-I I I BAY

250 MVAICT-I

250 MVAICT-I I

250 MVAICT-I I I

400 KV KISHENPUR-I I

400 KV JALANDHAR-I I

400 KV JALANDHAR-I

400 KV KISHENPUR-I

400 KV

FATEHABAD

400 KV

HISAR

BUS COUPLER

220 kV TBC BAY Switchyard Fencing

CO

NT

RO

L

RO

OM

SINGLE LINE DIAGRAM OF 400 / 220 KV MOGA SUBSTATION (WITH FUTURE PLAN)

63 MVARLINE

REACTOR

63 MVARLINE

REACTO

R

25 MVARTer. Reactor-I

25 MVARTer. Reactor-I I

1 MVA33/0.433 kV

Bhiwadi-I

41489A

41489AE

41389T2

41389T2E

41352

41389T1E

41389T1

1000-500/1A

41289BE

41289B

41289A

41289AE

41252

41289L

41289LE

41289R

41289RE

4189LE

4189L

4389T14189B

4189BE

4152

4189AE1

4189A

4389T1E

4352

4389T2

4389T2E 4289BE

4289B

4252

4289A

4289AE1

4289L

4289LE

41589R

41589RE 41652

41552

41589B

41589BE

41589AE

41589A

41589L

41589LE

41689T1

41689T1E

41689T2E

41689T2

4989A

4189AE2

4289AE2

4989AE

4989B

4989BE

4952 41052

411524989C

4989CE

41189T1

41189T1E 41189T2E

41089BE

41089B

41089A41089AE

41089C41089C

E

41889A 41889AE

41852

41889B

41889BE

48524889T2

4889T2E

4889T1

4889T1E

4552

4589A

4589AE

4589BE

4589B

4589L

4589LE41889CE

41889C

4689A

4689B

4689C

2152

2252

2752 2352 2852 2452 2552 2652 2952

2189A

2189B

2189C

2289A 2289B 2789A

2789B

2789C

2789L

2389A

2389B

2389T

2889A

2389C

2889B

2889C

2889L

2489A

2489B

2489C

2489L

2589A

2589B

2589C

2589L

2689A

2689B

2689T

2689C

2989A

2989B

2989C

2989T

2189E1

2189E2

2289E1 2789E1

2789E2

2789E3

2389E1

2389E2

2389E3

2889E1

2889E2

2889E3

2489E1

2489E2

2489E3

2589E1

2589E2

2589E3

2689E1

2689E2

2689E3

2989E1

2989E2

2989E3

1000-500/1A

1000-500/1A

1000-500/1A

1000-500/1A

1000-500/1A 1000-

500/1A

1000-500/1A

1000-500/1A

1000-500/1A

1000-500/1A

1000-500/1A

1000-500/1A

1000-500/1A

1000-500/1A

1000-500/1A

1000-500/1A

1000-500/1A

1000-500/1A

1000-500/1A

1000-500/1A

1000-500/1A

1000-500/1A

1000-500/1A

1000-500/1A

4489A

4489AE

4452

4489BE

4489B4789T2 4752

4652

4789T2E

4789T1E

4789T1

4689AE

4689BE

4689CE

1000-500/1A

1000-500/1A

1000-500/1A

Bhiwadi-II

220 kV Jagraon-I

ICT-I V BAY

41452

1000-500/1A

41489BE

41489B

50 MVAR BUS

REACTOR

41489RE

41489R

315 MVA ICT-IV

Spare

220 kV Jagraon-II

41789A

41789AE

63 MVARLINE

REACTO

R

63 MVARLINE

REACTO

R

41952

42052

42189A

42189AE41989A

E41989A

41989BE

41989B

42089T1

42089T2

42089T2E42089T1E

41989L

41989LE

42089R

42089RE

41789B

41789BE

41752

41789L

41789LE

41789R

41789RE

21052 21152 21252

21089A

21089B

21089C

21089T

21089E1

21089E2

21089E3

1000-500/1A

1000-500/1A

1000-500/1A21189C

21189E3

21189E2

21189A

21189B21189E

1

21289A

21289B21289E

1

21289C

21289E3

21289T

21289E2

21189T

Page 46: Substation Layout
Page 47: Substation Layout

Small Scale industry

Small Scale industry

House

TO BE DI SMENTELED

Page 48: Substation Layout

Small Scale industry

Small Scale industry

House

TO BE DISMENTELED

Page 49: Substation Layout

Small Scale industry

Small Scale industry

House

TO BE DISMENTELED

Page 50: Substation Layout

ICT-I BAY220 kV PSEB-III

220 kV PSEB-IV

220 kV PSEB-I

220 kV PSEB-II

220 KVICT- IV

400 KV BUS-I

400 KV BUS-II

220 KV BUS-I

220 KV BUS-II

220 KV TRANSFER BUS

ICT-II BAY ICT-III BAY

250 MVAICT-I

250 MVAICT-II

250 MVAICT-III

50 MVAR BUS

REACTOR

400 KV KISHENPUR-II

400 KV BHIWADI-I

400 KV BHIWADI-II

400 KV JALANDHAR-II

400 KV JALANDHAR-I

400 KV KISHENPUR-I

SPARE

220 kV PSEB-VI

400 KV HISAR-II

400 KV HISAR-I

250 MVAICT-IV

220 kV PSEB-V

BUS COUPLER

220 kV TBC BAY

Existing 400 kV

D/C Dead End

Tower

Switchyard Fencing

CO

NT

RO

L

RO

OM

MOGA SUBSTATION AUGMENTATION OF EXISTING TRANSFORMATION CAPACITY - INSTALLATION OF ICT-IV AND ASSOCIATED BAYS

LOCATION OF

BHIWADI – I & II

( PROPOSED )

220

kV

SH

OR

T L

INE

63 MVARLINE

REACTOR

63 MVARLINE

REACTOR

220

kV

SH

OR

T L

INEA

C D

B

IPS Al BUS on BPIs

220 KV BUS-I

220 KV BUS-II

Existing Conductor Bus

Conductor BusApprox. length 50 m

Page 51: Substation Layout

ICT-I BAY

220 kV PSEB-III

220 kV PSEB-IV

220 kV PSEB-I

220 kV PSEB-II

220 KV

ICT- IV

400 KV BUS-I

400 KV BUS-II

Existing 220 KV Conductor BUS-I

Existing 220 KV Conductor BUS-II

220 KV TRANSFER BUS

ICT-II BAY ICT-III BAY

250 MVAICT-I

250 MVAICT-II

250 MVAICT-III

400 KV KISHENPUR-II

400 KV BHIWADI-I

400 KV BHIWADI-II

400 KV JALANDHAR-I

400 KV KISHENPUR-I

50 MVAR

BUS REACTORE

220 kV PSEB-VI

400 KV HISAR-II 400 KV

HISAR-I

220 kV PSEB-V

BUS COUPLER

220 kV TBC BAY

Existing 400 kV

D/C Dead End

Tower

Switchyard Fencing

MOGA SUBSTATION AUGMENTATION : ICT-IV & ASSOCIATED 220 KV BAYS, 400 KV BHIWADI-I&II LINES

LOCATION OF

BHIWADI – I & II

( PROPOSED )

63 MVARLINE

REACTOR

63 MVARLINE

REACTOR

A

C D

B

IPS Al pipe on BPIs

Proposed 220 KV Conductor BUS-I

Proposed 220 KV Conductor BUS-II

400 KV JALANDHAR-II

SPARE

25 MVARTer.

Reactor-I

25 MVARTer. Reactor-

II

1 MVA33/0.433

kV

Approx. 50m

CGL

ISOL:KEP

41152

41352

41252

4352

42524152 41552

41652

4952 41052 41852

4852

4552

4452

4752

4652

21522252

27522352

24522552 2652 2952

414

52

41752

42052

41952

42189A

212522115221052

250 MVAICT-IV

13

1412

3

1 2

9

11

10

15

18

8

5

17 19

20

4

7

6

91

27 3 4 5 6

2852

8

2189A 2189B2189E1

2289A2189B

2189E1

2789A 2789B

2789E1

2189E2

2189C

2789L

2789C

2789E2

2789E3

2389A2389B

2389T

2389E2

2389E1

2389C

2389E3

2889A2889B

2889E1

2/889E2

2889L2889E3

2889C

2489A2489B

2489E1

2489E22489L

2489E3

2489C

2589A 2589B

2589E1

2589E2

2589L

2589C

268

9A

268

9B

2689E1

2689E22689T

2689E3

2689C 2989C

2989T

298

9A

298

9B

2989E1

2989E2

2989E3

4989A4989AE

4989BE

4989B

411

89T

1E

41189T1

4989C

4989CE

41189T2

41189T2E

41089C41089CE

41089B

41089BE

41089A

41089AE41889A

41889AE

41189BE

41889BE

418

89C

41889CE4889T2

4889T2E4889T1E

4889T1

458

9L

4589LE

458

9A4589AE

4589A

4589AE

4489A

4489AE

448

9B

4489BE

448

9L

4489LE

4789T2

4789T2E4789T1E

4789T1

41489A41489AE

41489BE

414

89B

414

89R 41489RE

41389T1

41389T1E 41389T2E

41389T2

41289BE

41289B

41289AE41289A

4189AE1

4189AE24189A

4189BE14189B

4389T1E

4389T1

4389T2E

4189LE14189L

4189T24289L

4289LE

41289R

412

89R

E

41289LE41289L

4289AE2

4289AE24289A

4289BE1

4289B

41589A41589AE

41589BE41589B

41589R 415

89R

E 41589L

41589LE

41689T141589R

416

89T

1E

41689T2

41689T2E41789BE

41789AE41789A

41789B

41789L41789LE

41989A41989AE

41989BE41989B

41989LE

41989L

42089T2E

42089T1

42089T1E

42089T2

42189AE

4689A4689AE

4689BE

4689B

4689C4689CE

21089C

21089E3

21089L21089E2

21089E121089B

21089A

21189C

21189E3

21189L

21189E2

21189E1

21189A21189B

21289C

21289E321289T

21289E2

21289E1

21289A 21289B

CO

NT

RO

L

RO

OM

16

Page 52: Substation Layout

SINGLE LINE DIAGRAM OF 220kV DMT SCHEME

ICT-I BAY220 kV PSEB-I

400 KV BUS-I

400 KV BUS-II

220 KV BUS-I

220 KV BUS-I I

220 KV TRANSFER BUS

ICT-I I BAY

250 MVAICT-I

250 MVAICT-I I

BUS COUPLER

4989A4989AE

4989B

4989BE

4952 41052

411524989C

4989CE

41189T1

41189T1E 41189T2E

41089BE

41089B

41089A41089AE

41089C

41089CE

2152

2252

2352 2452 2652

2189A

2189B

2189C

2289A 2289B 2389A2389B

2389T

2389C

2489A

2489B

2489C

2489L

2689A

2689B

2689T

2689C

2189E1

2189E2

2289E1 2389E1

2389E2

2389E3

2489E1

2489E2

2489E3

2689E1

2689E2

2689E3

1000-500/1A

1000-500/1A 1000-500/1A

1000-500/1A

1000-500/1A

1000-500/1A

1000-500/1A

1000-500/1A

1000-500/1A

Page 53: Substation Layout

SINGLE LINE DIAGRAM OF 220kV DMT SCHEME WITH 245kV CT RELOCATED

ICT-I BAY220 kV PSEB-I

400 KV BUS-I

400 KV BUS-II

220 KV BUS-I

220 KV BUS-I I

220 KV TRANSFER BUS

ICT-I I BAY

250 MVAICT-I

250 MVAICT-I I

BUS COUPLER

4989A4989AE

4989B

4989BE

4952 41052

411524989C

4989CE

41189T1

41189T1E 41189T2E

41089BE

41089B

41089A41089AE

41089C

41089CE

2152

2252

2352 2452 2652

2189A

2189B

2189C

2289A 2289B 2389A2389B

2389T

2389C

2489A

2489B

2489C

2489L

2689A

2689B

2689T

2689C

2189E1

2189E2

2289E1 2389E1

2389E2

2389E3

2489E1

2489E2

2489E3

2689E1

2689E2

2689E3

1000-500/1A

1000-500/1A 1000-500/1A

1000-500/1A

1000-500/1A

1000-500/1A

1000-500/1A

1000-500/1A

1000-500/1A

1000-500/1A1000-500/1A

Page 54: Substation Layout
Page 55: Substation Layout

CABLE TRENCH

Section Inner Dim Racks

Section 1 - 1 1.95 m 5 both sides

Section 2 - 2 1.05 m 3 one side

Section 3 – 3 0.75 m 2 one side

Section 4 – 4 0.40 m 1 one side

Page 56: Substation Layout

ERECTION, TESTING & COMMISSIONING OF

CT & CVT (UP TO PRE-COMMISSIONING CHECKS)

17.02.2009 (11:30 TO 12:30)

MANOJ KUMAR, MANAGER (S/S), MOGA

Page 57: Substation Layout

ERECTION OF CVTERECTION OF CVT

INTRODUCTIONINTRODUCTION Devices used to get the replica of primary

voltage which shall be suitable for measuring instruments and protective relays.

No. of cores as per requirement CVTs used generally above 220kV for

economic reasons - also obviates need for separate coupling capacitor for PLCC

Page 58: Substation Layout

Pre Commissioning Tests of CT

Polarity TestMagnetization Curve TestRatio TestPrimary Current Injection TestSecondary Current Injection Test