Subcontractor Management An introduction

Norman Housden

Optimatrix

Page 2: Subcontractor Management - OptiMatrixoptimatrix.co.uk/wp-content/.../Subcontractor-management-guidlines.pdf · • Subcontractor management ... Whilst not covered directly it must

Copyright protected 2011 Confidential - Optimatrix 2

Index

• Introduction

• SCM – A team event.

• Subcontractor Manager - Responsibilities

• Subcontractor source and selection.

• Subcontractor engagement.

• Subcontractor Negotiation.

• SME interface with Subcontractor.

• Subcontractor Performance.

• Documentation – Version control.

Optimatrix

Page 3: Subcontractor Management - OptiMatrixoptimatrix.co.uk/wp-content/.../Subcontractor-management-guidlines.pdf · • Subcontractor management ... Whilst not covered directly it must

Copyright protected 2011 Confidential - Optimatrix 3

Introduction • Subcontractor management is a team effort that relies on many disciplines spanning all phases of

the contract life.

• The Subcontractor manager has responsibility to ensure that each discipline undertakes, and completes on

schedule, relevant assigned activity and that nothing falls through the cracks.

• Well-written and managed subcontracts, regardless of size, result in success on the prime contract, a satisfied

customer, and a positive relationship with the subcontractor.

• Effective management of Subcontractors relies on effective Relationship Management (understanding the

Subcontractor drivers and constraints).

Optimatrix

Page 4: Subcontractor Management - OptiMatrixoptimatrix.co.uk/wp-content/.../Subcontractor-management-guidlines.pdf · • Subcontractor management ... Whilst not covered directly it must

Copyright protected 2011 Confidential - Optimatrix 4

HR

Gov

Cost Mod

el

Finance

Exp & Sec

Comm

M A

Risk

Bid Mngnt

Legal

Systems Eng

Sub Contractor Management

Prime

Gov System

Eng

HR

Legal Commercial

Finance

Subcontractor

lead

Sub 5

Gov System

Eng

HR

Legal Commercial

Finance Subcontractor

lead

Sub 4

Gov System

Eng

HR

Legal Commercial

Finance Subcontractor

lead

Sub 6

Gov System

Eng

HR

Legal Commercial

Finance

Subcontractor

lead

Sub 1

Gov System

Eng

HR

Legal Commercial

Finance Subcontractor

lead

Sub 3

Gov System

Eng

HR

Legal Commercial

Finance

Subcontractor

lead

Sub 2

Optimatrix

Page 5: Subcontractor Management - OptiMatrixoptimatrix.co.uk/wp-content/.../Subcontractor-management-guidlines.pdf · • Subcontractor management ... Whilst not covered directly it must

Copyright protected 2011 Confidential - Optimatrix 5

Subcontractor Managers Responsibilities

• Prime interface between Prime and Subcontractor.

• Develops and maintains Subcontractor source and selection plan.

• Develops and maintains Subcontractor engagement plan.

• Co-ordinates and manages the SME interface with Subcontractor.

• Monitors and manages Subcontractor performance.

• Ensures, as appropriate, flow-down of end-customer terms and conditions.

• Ensures flow-up of negotiated A’s, D’s, R’s & E’s. (Assumptions; Dependencies; Risk's and Exclusions)

• Identifies and mitigates all risks associated to the subcontractor.

Optimatrix

Page 6: Subcontractor Management - OptiMatrixoptimatrix.co.uk/wp-content/.../Subcontractor-management-guidlines.pdf · • Subcontractor management ... Whilst not covered directly it must

Copyright protected 2011 Confidential - Optimatrix 6

Subcontractor source and selection

•The Subcontractor manager co-ordinates the Subcontractor source and selection plan.

• Identifies and engages SME Stakeholders.

• With SME input identifies potential Subcontractors.

• Establishes initial contact and qualifies interest.

• Establishes relevant NDA.

• Develops (from SME input) and co-ordinates issue of formal RFI documentation, including:

• Overview.

• High level requirement documents, (outline SOW including statements on required annex’s A,D,R

&E, CDRL’s , Compliancy matrix etc.).

• Statement on applicable T’s& C’s (those which Prime will negotiate on).

• Statement on Billing and Payment policy.

• RFI response schedule.

• Communication Channels (for requirement clarification – SPOC prinicples).

• Co-ordinates and disseminates all clarification questions and responses.

• Develops (from SME input) acceptance / scoring criteria. (scoring matrix).

• Co-ordinates review panel of SME stakeholders, and manages down select process.

• Communicates selection panel decision.

• Manages RFP issue to selected Subcontractors

Optimatrix

Page 7: Subcontractor Management - OptiMatrixoptimatrix.co.uk/wp-content/.../Subcontractor-management-guidlines.pdf · • Subcontractor management ... Whilst not covered directly it must

Copyright protected 2011 Confidential - Optimatrix 7

Subcontractor source and selection (cont.)

•Develops specific Subcontractor RFP plan.

• Establish business worth to the subcontractor (core, % of turnover, new market entry etc).

• Undertakes due diligence – (D&B etc).

• Develops (from SME input) and co-ordinates issue of formal RFP documentation, including:

• Overview.

• Decomposed requirement documents, (initial SOW including required all annex’s (A,D,R &E, CDRL’s ,

Compliancy matrix etc.).

• Applicable T’s& C’s (those which Prime will negotiate on).

• Billing and Payment plan.

• Commercial response Schedule.

• Co-ordinates and disseminates all clarification questions and responses.

• Co-ordinates Subcontractor Audits / Presentations (as appropriate).

• Develops (From SME input) Acceptance / Scoring criteria. (scoring matrix).

• Co-ordinates review panel of SME stakeholders, and manages down select process.

• Communicates selection panel decision.

Whilst specific Subcontractors will be selected to proceed, the information gathered and assessments undertaken

of non-selected Subcontractors should be maintained in a Subcontractor database, as initial reference for future

sourcing activity or should a need arise to replace the selected Subcontractor.

Optimatrix

Page 8: Subcontractor Management - OptiMatrixoptimatrix.co.uk/wp-content/.../Subcontractor-management-guidlines.pdf · • Subcontractor management ... Whilst not covered directly it must

Copyright protected 2011 Confidential - Optimatrix 8

Subcontractor engagement

•Develops specific Subcontractor engagement plan.

• Co-ordinate relevant TA, MOU, MOA.

• Where applicable co-ordinate export licence activity (TAA; ITAR; EAR ; F680 etc)

• Establishes organisational hierarchy charts – Peer review and escalation

• Develops Subcontract management schedule – All gates and deliverables to be included (this schedule

must align to Prime requirements, however needs to realistically accommodate subcontractors needs.).

• Establish Actions Log – For the daily management of all actions that are sub – schedule level or are on the

schedule but require specific activity.

• Develops meeting calendar - To include PMR; Commercial; Technical and Finance.

• Within the Project database establish file structure for all Subcontractor management documents – including

SOW, T’s & C’s, CDRL’s and SRDL's. (see Document and version Control).

Optimatrix

Page 9: Subcontractor Management - OptiMatrixoptimatrix.co.uk/wp-content/.../Subcontractor-management-guidlines.pdf · • Subcontractor management ... Whilst not covered directly it must

Copyright protected 2011 Confidential - Optimatrix 9

Subcontractor Negotiation

It must be remembered that every interface, however innocuous, is a potential negotiation with a

subcontractor. As such all project team members must ensure that they do not unwittingly enable the

subcontractor the opportunity to manipulate any aspect of the terms or requirements through informal

agreement. Simple guidelines should be followed:

• Internally identify the key individuals in Prime organisation, who have relevant authority for specific

negotiation areas (e.g. T’s & C’s = Commercial lead). These leads are responsible for:

• Establishing the Primes baseline.

• Gap analysis, from Subcontractors position.

• Identify drivers / lever’s to change Subcontractors position.

• With SCM develop combined Negotiation Plan.

• Identify the Subcontractor personnel with authority to negotiate.

• Identify escalation route.

• Schedule specific meetings to negotiate, (as opposed to technical reviews or planning meetings).

• Appoint lead (single) negotiator.

• Develop meeting strategy (targets, acceptable, concessions available).

• Avoid (where possible),providing Subcontractor with knowledge of outside issues, as these could

be used by them. (i.e. customer / governance time schedules).

• On key requirements, if agreement cannot be reached “park” the point and proceed with other

elements, return later in the negotiation at a suitable point where the Subcontractor has identified a

concession the Prime is able to concede, barter.

• Close the meeting when all items have been discussed. Document all areas of agreement and outstanding issues. Schedule follow up meeting providing sufficient time to assess the position.

Optimatrix

Page 10: Subcontractor Management - OptiMatrixoptimatrix.co.uk/wp-content/.../Subcontractor-management-guidlines.pdf · • Subcontractor management ... Whilst not covered directly it must

Copyright protected 2011 Confidential - Optimatrix 10

Subcontractor Negotiation (cont.)

• With the relevant SME’s review the open issues to identify other negotiation tactics or mitigation activity.

(Engaging escalation where appropriate)

• Review the varying scenarios of not reaching agreement on each and multiple open issues and determine

the minimum point where proceeding is viable.

• Brief Senior Management on position and action plan as necessary.

• Continue this process until such point as suitable agreement is reached or the viability to proceed

(including timescales), is compromised.

Whilst not covered directly it must be noted that an exit strategy must be developed with regard to any

Subcontractor relationship areas to be considered include:

• Termination for convenience.

• Termination for breach / anticipatory breach.

• End of project / contract end.

• Fundamental change in client project definition.

All of these aspects should be in the T’s & C’s however it is important to detail the rights and obligations of

both parties, including such things as the return of data and IP ownership of completed development.

Optimatrix

Page 11: Subcontractor Management - OptiMatrixoptimatrix.co.uk/wp-content/.../Subcontractor-management-guidlines.pdf · • Subcontractor management ... Whilst not covered directly it must

Copyright protected 2011 Confidential - Optimatrix 11

SME interface with Subcontractor Whilst the SCM should act as the SPOC (Single Point Of Contact) with the subcontractor, this cannot be

allowed to restrict the required detailed interface between the Prime SME’s and their Subcontractor

counterparts, necessary to develop the technical and commercial aspects of the Subcontract. However the

same disciplines of document control, authority and control of released information must be adhered to.

Examples are shown below:

• An Prime single point of maintenance for each and all contract related documentation is established,

(including but not exclusive to T’s & C’s; SOW; TA and Billing and Payment plan).

• Meeting plans, objectives and minutes to be documented for each meeting by the Prime meeting lead.

• SCM to add all actions to Actions Log and is responsible to manage performance .

• SME to promptly advise SCM on progress of actions (both SME & Subcontractor), when completed or date

requirement changed.

• In order to ensure clarity of requirement no customer generated information shall be provided to the

Subcontractor, unless previously agreed with the SCM.

• The organisational structure shall show the authority of SME’s against each element of the contract.

• No verbal or written agreement shall be made which remove or alter any of the Primes or flowed down

Customer requirement outside the authority of the SME. Any, which the SME is authorised to agree, must be

documented (as detailed above), in the relevant document and be notified to the SCM.

Optimatrix

Page 12: Subcontractor Management - OptiMatrixoptimatrix.co.uk/wp-content/.../Subcontractor-management-guidlines.pdf · • Subcontractor management ... Whilst not covered directly it must

Copyright protected 2011 Confidential - Optimatrix 12

Subcontractor performance

The performance of Subcontractors is obviously critical to any project. During the selection process it is

important to ascertain, where possible, evidence of both technical performance on similar business, but also

the culture and methodology of the organisation. Understanding the approval and governance requirements

and processes will enable more accurate planning, but also may provide further insight into their decision

making process and key authorities.

It should also be recognised that whilst the performance of a subcontractor prior to selection, and during bid

preparation, may show key indication of the culture and the priority they place on a particular project, it must be

remembered that the delivery phase is a different scenario and is likely to be undertaken by diverse areas of

the business. Not withstanding this it is essential that each stage is subject to the same rigour of performance

measurement and has defined resolution and mitigation routes where performance does not meet the

requirements. Dependent on the nature and phase of the contract, it is possible to use incentives or penalties,

however these, amongst other commercial remedies, must have been previously established via the

commercial SME. Key areas to consider for all phases include:

• Reporting

•Schedules – For each phase of the project a detailed schedule, including project gates and deliverables

should be established, and proactively maintained by the SCM, (this is a working document not a record

of what has happened).

• Technical reports – establish the content, format and timing, (to be included in the schedule), required.

• Quality and security certification – establish applicability and timing, (to be included in the schedule),

required.

Optimatrix

Page 13: Subcontractor Management - OptiMatrixoptimatrix.co.uk/wp-content/.../Subcontractor-management-guidlines.pdf · • Subcontractor management ... Whilst not covered directly it must

Copyright protected 2011 Confidential - Optimatrix 13

Subcontractor performance (cont.)

• Testing and acceptance

• Acceptance criteria must be clearly pre-defined and articulated in the SOW.

• Testing and acceptance should be clear deliverables detailed in the schedule ( even if an iterative

delivery approach is adopted).

•Issue resolution and mitigation

• SCM, with input from SME, is responsible for Subcontractor management including performance

issues, these in the most part will be undertaken in accord with the Subcontractor however there may be

instances where a more compelling approach may be necessary. In all circumstances the following

should be considered:

• Impact on the project – cost, quality and schedule.

• Remedy – route to recover with zero project impact.

• Remedy – route to recover with mitigation action.

• Cause of issue and future avoidance.

• Resolution types

• Harmonious – the resolution and recovery is amicably agreed or the impact is not deemed to

warrant further pursuit by the Prime.

• Disputed – where the Prime does not believe that the Subcontractor either fully accepts

responsibility for or does not provide acceptable resolution to the issue, the Prime may need to

utilise any of the following:

• Escalation.

• Commercial incentive or penalty.

• Contractual remedies.

Optimatrix

Page 14: Subcontractor Management - OptiMatrixoptimatrix.co.uk/wp-content/.../Subcontractor-management-guidlines.pdf · • Subcontractor management ... Whilst not covered directly it must

Copyright protected 2011 Confidential - Optimatrix 14

Subcontractor performance (cont.)

•Reporting

• Project shchedules, CDRL’s, SRDL’s and Compliancy matrices – dependent on phase of the project.

• Action log – SCM should establish and maintain daily, an action log, to manage those activities and

deliverables that are not identified in the schedule.

• KPI’s - these will change dependent on the phase of the project, however all KPI’s need to be relevant;

unambiguous; current and “owned”.

• Informal – whilst it is recognised that this form of information transfer will happen, it must be noted that

these “reporting” mechanisms, although extremely valuable to managing the subcontract, must never be

interpreted as contractually binding.

• Meetings & reviews

• PMR’s (Project Management Reviews) – formal PMR’s should be established, the frequency of these

will be dependent on the phase of the project but should be at a minimum monthly. They are to review

the overall progress of the project and cover key areas including, cost; risk; schedule; management and

programmatic issues. It is recommended that these follow a set agenda and template reports and KPI’s

are used.

• Technical – dependent on phase of the project, but should adhere to SME interface guidelines.

• Visits & Site audits - Appropriate levels of Subcontractor site visits should be conducted dependent on

the nature and phase of the project, these should adhere to SME interface guidelines and where they are

specific audits should be formally undertaken.

• Contract negotiation meetings - dependent on phase of the project, but should adhere to

Subcontractor negotiation guidelines.

Optimatrix

Page 15: Subcontractor Management - OptiMatrixoptimatrix.co.uk/wp-content/.../Subcontractor-management-guidlines.pdf · • Subcontractor management ... Whilst not covered directly it must

Copyright protected 2011 Confidential - Optimatrix 15

Documentation – Version control With all contractual relationships, the clarity of the supporting documentation is critical, as is ensuring that the route

to the final document can be traced. It is also worth noting that usually it is only when things go badly wrong are the

documents required, as such the last position to be in when trying to rely on written agreement is for it to be

incomplete, ambiguous, contradictory or even there to be multiple copies of the “truth”. To avoid this simple

guidelines should be followed.

• All Subcontractors requirements documents should be authored and maintained by the Prime authorised

personnel appropriate to the document (e.g. T’s & C’s = commercial lead). These include but are not limited to

SOW; T’s & C’s, CDRL’s; SRDL's and Schedules.

• Subcontractors must respond using the Prime documents, (developing their own documentation should be

avoided.).

• All such documents should be version controlled and use track changes, comments should be applied either

on the document or separately on a change log (if the quantity of changes is large), detailing the reason for

the change.

• Following review meetings any changes must be made within two working days and issued to the defined

distribution list.

• Meeting plans and objectives should be documented and copied to SCM prior to each meeting (SCM to store in

database).

•Meeting minutes to be issued to the Subcontractor and SCM within two days of the meeting detailing all

actions,(including due date and owner), and understandings.

• Action Log to be maintained daily and issued to defined distribution list. Date and issue controlled.

Optimatrix