status of the planning working group’s (pwg) efforts
DESCRIPTION
Status of the Planning Working Group’s (PWG) Efforts. Andrew Fusco May 12, 2006. Agenda. Purpose of the PWG 2006 NCTPC process PWG efforts to date Next steps. Purpose of the PWG. Coordinates the development of the transmission studies to support the NCTPC Establishes a base case model - PowerPoint PPT PresentationTRANSCRIPT
Status of the Planning Working Group’s (PWG) Efforts
Andrew Fusco
May 12, 2006
DRAFT 2
• Purpose of the PWG
• 2006 NCTPC process
• PWG efforts to date
• Next steps
Agenda
DRAFT 3
• Coordinates the development of the transmission studies to support the NCTPC– Establishes a base case model– Performs Resource Supply Option studies –
focused on reliability– Performs Enhanced Access studies – focused
on power supply economics– Develops cost and schedule estimates
Purpose of the PWG
DRAFT 4
NCTPC Process Flowchart
PWG evaluates reliability problems
and current transmission upgrade
plans
PWG develops and the OSC approves the reliability study
scope
PWG coordinates the study analysis,
identifies reliability problems, develops
solutions with estimates of costs
and schedules
Participants and TAG recommend scenarios and interfaces. The
OSC selects interface and scenario studies
for analysis
PWG coordinates the study analysis,
identifies access problems, develops
solutions with estimates of costs
and schedules
Reliability Planning
Enhanced Transmission Access Planning
OSC selects reliability and enhanced access solutions; checks for improved reliability through enhanced access solutions
OSC creates final draft
Collaborative Plan
Feedback and Iterative Studies
Participants and TAG review the reliability study
results
Participants’ resource planning
processes
Participants and TAG review the
enhanced access study
results
TAG feedback on final draft Collaborative
Plan
OSC approves final
Collaborative Plan
PWG develops and the OSC approves the
enhanced access study
scope
DRAFT 5 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
Enhanced Access Planning Process
Collaborative Plan Development
Develop Reliability Study Scope
Perform analysis, identify problems, and develop solutions
Review Reliability Study Results
Evaluate current reliability problems and transmission upgrade plans
Propose and select enhanced access scenarios and interface
Develop Enhanced Access Study Scope
Perform analysis, identify problems, and develop solutions
Review Enhanced Access Study Results
Reliability Planning Process
OSC publishes DRAFT Plan
TAG review and comment
Combine Reliability and Enhanced Results
2006 Overview Schedule
TAG Meetings
DRAFT 6
NCTPC Process Flowchart - REVISED
PWG evaluates reliability problems
and current transmission upgrade
plans
PWG develops and the OSC approves the reliability study
scope
PWG coordinates the study analysis,
identifies reliability problems, develops
solutions with estimates of costs
and schedules
Reliability Planning
OSC selects reliability and enhanced access solutions; checks for improved reliability through enhanced access solutions
OSC creates final draft
Collaborative Plan
Feedback and Iterative Studies
Participants and TAG review the reliability study
results
Participants’ resource planning
processes
TAG feedback on final draft Collaborative
Plan
OSC approves final
Collaborative Plan
DRAFT 7 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
Collaborative Plan Development
Develop Reliability Study Scope
Perform analysis, identify problems, and develop solutions
Review Reliability Study Results
Evaluate current reliability problems and transmission upgrade plans
Reliability Planning Process
OSC publishes DRAFT Plan
TAG review and comment
Finalize Reliability Results
2006 Overview Schedule - REVISED
TAG Meetings
DRAFT 8
PWG Efforts to Date
• First PWG meeting in September 2005• Sept – Dec: Compared reliability planning
assumptions used by Duke and PEC• Oct – Jan: Developed scope for 2006
reliability study
DRAFT 9
PWG Efforts to Date
• Dec – Jan: Provided data for base case development– Load and resource forecasts– Dispatch order for resources– Coordinated interchange– Contingency and monitored line lists
DRAFT 10
PWG Efforts to Date
• Jan – Feb: Developed merged detailed base case
• Feb – Mar: Developed potential alternative resource options for study
• Mar – Apr: Performed base case and some generator maintenance reliability screenings
• Apr: Reviewed initial reliability screenings
DRAFT 11
Next Steps
• Complete studies for Resource Supply Options
• Identify reliability problems• Develop solutions
– Develop technical solutions– Develop cost and schedule estimates for
solutions
• Recommend alternative resource options for study