Status of the LHC ProjectL.Evans - C.WyssRiunione CSN1 INFNNapoli, 21 Settembre 2005

Page 2: Status of the LHC Project L.Evans - C.Wyss Riunione CSN1 INFN Napoli, 21 Settembre 2005

CERN L.Evans & C.Wyss INFN CSN1 Napoli September 20052

L.R. Evans – EDMS Document No. 521217

SPC

3

• length of newly tested part ~ 2.5 km

• over 400 magnets

beam tests23./24.10.04

6./7.11.04

TI 2

TI 8

TI 2 upstream part commissioning (w/o beam) possible as of Q2/2005

beam tests 8.9.03

SPSLHC

AB/BT equipment in PS complex

MQI chamber

13:39 beam at the end of TI 8, some 2.5 km away, at first attempt

General situation

TI 8 commissioning / V.Mertens / TCC, 29.10.2004

Page 3: Status of the LHC Project L.Evans - C.Wyss Riunione CSN1 INFN Napoli, 21 Settembre 2005

CERN L.Evans & C.Wyss INFN CSN1 Napoli September 20053

Beam parameters obtained from the central frequency measurements, averaged over the data obtained from the

horizontal and vertical planes.

Page 4: Status of the LHC Project L.Evans - C.Wyss Riunione CSN1 INFN Napoli, 21 Settembre 2005

CERN L.Evans & C.Wyss INFN CSN1 Napoli September 20054

Results of TI8 test

Page 5: Status of the LHC Project L.Evans - C.Wyss Riunione CSN1 INFN Napoli, 21 Settembre 2005

CERN L.Evans & C.Wyss INFN CSN1 Napoli September 20055

End of civil engineering works in Point 5 (1st February 2005)

Page 6: Status of the LHC Project L.Evans - C.Wyss Riunione CSN1 INFN Napoli, 21 Settembre 2005

CERN L.Evans & C.Wyss INFN CSN1 Napoli September 20056

Superconducting cable 1

Page 7: Status of the LHC Project L.Evans - C.Wyss Riunione CSN1 INFN Napoli, 21 Settembre 2005

CERN L.Evans & C.Wyss INFN CSN1 Napoli September 20057

Superconducting cable 2

Page 8: Status of the LHC Project L.Evans - C.Wyss Riunione CSN1 INFN Napoli, 21 Settembre 2005

CERN L.Evans & C.Wyss INFN CSN1 Napoli September 20058

Dipole cold masses

Page 9: Status of the LHC Project L.Evans - C.Wyss Riunione CSN1 INFN Napoli, 21 Settembre 2005

CERN L.Evans & C.Wyss INFN CSN1 Napoli September 20059

Number of quenches to reach 8,33 Tat the first cooldown (560 dipoles)

0102030405060708090

100110120130140150160170180190200210220230

Number of quenches to reach 8.33T

Nu

mb

er o

f c

ryo

-d

ipo

les 01 02 03

Page 10: Status of the LHC Project L.Evans - C.Wyss Riunione CSN1 INFN Napoli, 21 Settembre 2005

CERN L.Evans & C.Wyss INFN CSN1 Napoli September 200510

LHC Dipoles: integrated field

10.07

10.09

10.11

10.13

10.15

0 100 200 300 400 500 600 700

Magnet progressive number

Int tr

ansf

func

(Tm

/kA

)

-40

-20

0

20

40

Units

Firm 1

Firm 2

Firm 3

AT-MAS

Cold mass

upper limit for single magnet (3 sigma)

lower limit for single magnet (3 sigma)

Page 11: Status of the LHC Project L.Evans - C.Wyss Riunione CSN1 INFN Napoli, 21 Settembre 2005

CERN L.Evans & C.Wyss INFN CSN1 Napoli September 200511

Dipole field quality: average b3

-10

-5

0

5

10

0 100 200 300 400 500 600 700

Magnet progressive number

b3

inte

gra

l (u

nits

)

Firm 1

Firm 2

Firm 3

Cold mass

upper limit for systematic

lower limit for systematic

AT-MAS & MTM

Cross-section 2 Cross-section 3

Page 12: Status of the LHC Project L.Evans - C.Wyss Riunione CSN1 INFN Napoli, 21 Settembre 2005

CERN L.Evans & C.Wyss INFN CSN1 Napoli September 200512

Arc quadrupole cold masses

Page 13: Status of the LHC Project L.Evans - C.Wyss Riunione CSN1 INFN Napoli, 21 Settembre 2005

CERN L.Evans & C.Wyss INFN CSN1 Napoli September 200513

MSCB sextupole dipole correctors

Page 14: Status of the LHC Project L.Evans - C.Wyss Riunione CSN1 INFN Napoli, 21 Settembre 2005

CERN L.Evans & C.Wyss INFN CSN1 Napoli September 200514

Cryodipole overview

Page 15: Status of the LHC Project L.Evans - C.Wyss Riunione CSN1 INFN Napoli, 21 Settembre 2005

CERN L.Evans & C.Wyss INFN CSN1 Napoli September 200515

SSS overview

Page 16: Status of the LHC Project L.Evans - C.Wyss Riunione CSN1 INFN Napoli, 21 Settembre 2005

CERN L.Evans & C.Wyss INFN CSN1 Napoli September 200516

Magnet Installation

• Installation is progressing in sectors 8-1 and 4-5. More than 100 superconducting magnets have been installed. The installation rate must now ramp up to 20 magnets per week (16 dipoles and 4 SSSs) in the next few weeks.

• At the end of October, sector 7-8 will be liberated for magnetic installation. From then on there will be no shortage of slots.

Page 17: Status of the LHC Project L.Evans - C.Wyss Riunione CSN1 INFN Napoli, 21 Settembre 2005

CERN L.Evans & C.Wyss INFN CSN1 Napoli September 200517

First cryodipole lowered on 7 March 2005

Page 18: Status of the LHC Project L.Evans - C.Wyss Riunione CSN1 INFN Napoli, 21 Settembre 2005

CERN L.Evans & C.Wyss INFN CSN1 Napoli September 200518

First SSS lowered on 19 April 2005

Page 19: Status of the LHC Project L.Evans - C.Wyss Riunione CSN1 INFN Napoli, 21 Settembre 2005

CERN L.Evans & C.Wyss INFN CSN1 Napoli September 200519

Transport in the tunnel with an optical guided

vehicle

Page 20: Status of the LHC Project L.Evans - C.Wyss Riunione CSN1 INFN Napoli, 21 Settembre 2005

CERN L.Evans & C.Wyss INFN CSN1 Napoli September 200520

Transfer on jacks

Page 21: Status of the LHC Project L.Evans - C.Wyss Riunione CSN1 INFN Napoli, 21 Settembre 2005

CERN L.Evans & C.Wyss INFN CSN1 Napoli September 200521

Preparation of interconnect

Page 22: Status of the LHC Project L.Evans - C.Wyss Riunione CSN1 INFN Napoli, 21 Settembre 2005

CERN L.Evans & C.Wyss INFN CSN1 Napoli September 200522

Interconnection of beam tubes

Page 23: Status of the LHC Project L.Evans - C.Wyss Riunione CSN1 INFN Napoli, 21 Settembre 2005

CERN L.Evans & C.Wyss INFN CSN1 Napoli September 200523

Interconnect in sector 8-1: in progress in sub-sectors C and F

Page 24: Status of the LHC Project L.Evans - C.Wyss Riunione CSN1 INFN Napoli, 21 Settembre 2005

CERN L.Evans & C.Wyss INFN CSN1 Napoli September 200524

Pre-assembly of first low-beta triplet

(hall 181)

Page 25: Status of the LHC Project L.Evans - C.Wyss Riunione CSN1 INFN Napoli, 21 Settembre 2005

CERN L.Evans & C.Wyss INFN CSN1 Napoli September 200525

Page 26: Status of the LHC Project L.Evans - C.Wyss Riunione CSN1 INFN Napoli, 21 Settembre 2005

CERN L.Evans & C.Wyss INFN CSN1 Napoli September 200526

UA47: Quench protection & Power converters

Page 27: Status of the LHC Project L.Evans - C.Wyss Riunione CSN1 INFN Napoli, 21 Settembre 2005

CERN L.Evans & C.Wyss INFN CSN1 Napoli September 200527

Page 28: Status of the LHC Project L.Evans - C.Wyss Riunione CSN1 INFN Napoli, 21 Settembre 2005

CERN L.Evans & C.Wyss INFN CSN1 Napoli September 200528

Cryogenics overview

Page 29: Status of the LHC Project L.Evans - C.Wyss Riunione CSN1 INFN Napoli, 21 Settembre 2005

CERN L.Evans & C.Wyss INFN CSN1 Napoli September 200529

2400 W @ 1,8 K in the UX85 cavern

1.8K refrigeration units1st Pump-down in final LHC configuration

0.00

0.05

0.10

0.15

0.20

0.25

0.30

0.35

0.40

0.45

0.50

7:12 8:24 9:36 10:48 12:00

Time

Su

cti

on

Pre

ss

ure

[B

]

0

500

1000

1500

2000

2500

Co

oli

ng

Po

we

r [

W]

Suction Pressure

Set point

1.8K Cooling Power

P8 - 7 April 2005

Installed mode 2400 W @ 1.8 K

Pump-down 15 mbar

Page 30: Status of the LHC Project L.Evans - C.Wyss Riunione CSN1 INFN Napoli, 21 Settembre 2005

CERN L.Evans & C.Wyss INFN CSN1 Napoli September 200530

Repair of QRL modules

Page 31: Status of the LHC Project L.Evans - C.Wyss Riunione CSN1 INFN Napoli, 21 Settembre 2005

CERN L.Evans & C.Wyss INFN CSN1 Napoli September 200531

Repair of special QRL elements at

CERN

Page 32: Status of the LHC Project L.Evans - C.Wyss Riunione CSN1 INFN Napoli, 21 Settembre 2005

CERN L.Evans & C.Wyss INFN CSN1 Napoli September 200532

Cryogenic distribution line

Page 33: Status of the LHC Project L.Evans - C.Wyss Riunione CSN1 INFN Napoli, 21 Settembre 2005

CERN L.Evans & C.Wyss INFN CSN1 Napoli September 200533

QRL

Page 34: Status of the LHC Project L.Evans - C.Wyss Riunione CSN1 INFN Napoli, 21 Settembre 2005

CERN L.Evans & C.Wyss INFN CSN1 Napoli September 200534

Reinstallation of QRL in 7-8

• Sub-sectors A and B (600 m) have been cooled down on Wednesday 14th September.

• After the cold tests, the inner triplet will be installed, cooled down and powered whilst the rest of the line is being installed.

Page 35: Status of the LHC Project L.Evans - C.Wyss Riunione CSN1 INFN Napoli, 21 Settembre 2005

First cooldown of 600 m cryogenic LHC line sector 13-14 September 2005

He in

He outTh.screenlineLHe

linePump. line

20 K line

Page 36: Status of the LHC Project L.Evans - C.Wyss Riunione CSN1 INFN Napoli, 21 Settembre 2005

CERN L.Evans & C.Wyss INFN CSN1 Napoli September 200536

Conclusions

• Main objectives:– terminate installation in February 2007– first collisions in summer 2007

• The industrial production of standard components is compatible with this objective.

• The ramping up of QRL activities and magnet installation is critical to maintain this schedule.

• Additional actions have been implemented to ensure proper QRL production and installation rates.

• The installation and interconnection of cryomagnets have started in the tunnel.

• The commissioning of technical systems will take place in two adjacent sectors in parallel.

• Main next actions:– partial test of sector 7-8 in autumn 2005– commissioning test of the two first sectors (7-8 and 8-1) in summer

2006– find external collaborators to help with commissioning.

=> many thanks to INFN for its support !