Status of the LHC Project L.Evans - C.Wyss Riunione CSN1 INFN Napoli, 21 Settembre 2005. Beam parameters obtained from the central frequency measurements, averaged over the data obtained from the horizontal and vertical planes. Results of TI8 test. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Status of the LHC Project L.Evans - C.Wyss Riunione CSN1 INFN Napoli, 21 Settembre 2005

Status of the LHC ProjectL.Evans - C.WyssRiunione CSN1 INFNNapoli, 21 Settembre 2005

Page 2: Status of the LHC Project L.Evans - C.Wyss Riunione CSN1 INFN Napoli, 21 Settembre 2005

CERN L.Evans & C.Wyss INFN CSN1 Napoli September 20052

L.R. Evans – EDMS Document No. 521217

SPC

3

• length of newly tested part ~ 2.5 km

• over 400 magnets

beam tests23./24.10.04

6./7.11.04

TI 2

TI 8

TI 2 upstream part commissioning (w/o beam) possible as of Q2/2005

beam tests 8.9.03

SPSLHC

AB/BT equipment in PS complex

MQI chamber

13:39 beam at the end of TI 8, some 2.5 km away, at first attempt

General situation

TI 8 commissioning / V.Mertens / TCC, 29.10.2004

Page 3: Status of the LHC Project L.Evans - C.Wyss Riunione CSN1 INFN Napoli, 21 Settembre 2005

CERN L.Evans & C.Wyss INFN CSN1 Napoli September 20053

Beam parameters obtained from the central frequency measurements, averaged over the data obtained from the

horizontal and vertical planes.

Page 4: Status of the LHC Project L.Evans - C.Wyss Riunione CSN1 INFN Napoli, 21 Settembre 2005

CERN L.Evans & C.Wyss INFN CSN1 Napoli September 20054

Results of TI8 test

Page 5: Status of the LHC Project L.Evans - C.Wyss Riunione CSN1 INFN Napoli, 21 Settembre 2005

CERN L.Evans & C.Wyss INFN CSN1 Napoli September 20055

End of civil engineering works in Point 5 (1st February 2005)

Page 6: Status of the LHC Project L.Evans - C.Wyss Riunione CSN1 INFN Napoli, 21 Settembre 2005

CERN L.Evans & C.Wyss INFN CSN1 Napoli September 20056

Superconducting cable 1

Page 7: Status of the LHC Project L.Evans - C.Wyss Riunione CSN1 INFN Napoli, 21 Settembre 2005

CERN L.Evans & C.Wyss INFN CSN1 Napoli September 20057

Superconducting cable 2

Page 8: Status of the LHC Project L.Evans - C.Wyss Riunione CSN1 INFN Napoli, 21 Settembre 2005

CERN L.Evans & C.Wyss INFN CSN1 Napoli September 20058

Dipole cold masses

Page 9: Status of the LHC Project L.Evans - C.Wyss Riunione CSN1 INFN Napoli, 21 Settembre 2005

CERN L.Evans & C.Wyss INFN CSN1 Napoli September 20059

Number of quenches to reach 8,33 Tat the first cooldown (560 dipoles)

0102030405060708090

100110120130140150160170180190200210220230

Number of quenches to reach 8.33T

Nu

mb

er o

f c

ryo

-d

ipo

les 01 02 03

Page 10: Status of the LHC Project L.Evans - C.Wyss Riunione CSN1 INFN Napoli, 21 Settembre 2005

CERN L.Evans & C.Wyss INFN CSN1 Napoli September 200510

LHC Dipoles: integrated field

10.07

10.09

10.11

10.13

10.15

0 100 200 300 400 500 600 700

Magnet progressive number

Int tr

ansf

func

(Tm

/kA

)

-40

-20

0

20

40

Units

Firm 1

Firm 2

Firm 3

AT-MAS

Cold mass

upper limit for single magnet (3 sigma)

lower limit for single magnet (3 sigma)

Page 11: Status of the LHC Project L.Evans - C.Wyss Riunione CSN1 INFN Napoli, 21 Settembre 2005

CERN L.Evans & C.Wyss INFN CSN1 Napoli September 200511

Dipole field quality: average b3

-10

-5

0

5

10

0 100 200 300 400 500 600 700

Magnet progressive number

b3

inte

gra

l (u

nits

)

Firm 1

Firm 2

Firm 3

Cold mass

upper limit for systematic

lower limit for systematic

AT-MAS & MTM

Cross-section 2 Cross-section 3

Page 12: Status of the LHC Project L.Evans - C.Wyss Riunione CSN1 INFN Napoli, 21 Settembre 2005

CERN L.Evans & C.Wyss INFN CSN1 Napoli September 200512

Arc quadrupole cold masses

Page 13: Status of the LHC Project L.Evans - C.Wyss Riunione CSN1 INFN Napoli, 21 Settembre 2005

CERN L.Evans & C.Wyss INFN CSN1 Napoli September 200513

MSCB sextupole dipole correctors

Page 14: Status of the LHC Project L.Evans - C.Wyss Riunione CSN1 INFN Napoli, 21 Settembre 2005

CERN L.Evans & C.Wyss INFN CSN1 Napoli September 200514

Cryodipole overview

Page 15: Status of the LHC Project L.Evans - C.Wyss Riunione CSN1 INFN Napoli, 21 Settembre 2005

CERN L.Evans & C.Wyss INFN CSN1 Napoli September 200515

SSS overview

Page 16: Status of the LHC Project L.Evans - C.Wyss Riunione CSN1 INFN Napoli, 21 Settembre 2005

CERN L.Evans & C.Wyss INFN CSN1 Napoli September 200516

Magnet Installation

• Installation is progressing in sectors 8-1 and 4-5. More than 100 superconducting magnets have been installed. The installation rate must now ramp up to 20 magnets per week (16 dipoles and 4 SSSs) in the next few weeks.

• At the end of October, sector 7-8 will be liberated for magnetic installation. From then on there will be no shortage of slots.

Page 17: Status of the LHC Project L.Evans - C.Wyss Riunione CSN1 INFN Napoli, 21 Settembre 2005

CERN L.Evans & C.Wyss INFN CSN1 Napoli September 200517

First cryodipole lowered on 7 March 2005

Page 18: Status of the LHC Project L.Evans - C.Wyss Riunione CSN1 INFN Napoli, 21 Settembre 2005

CERN L.Evans & C.Wyss INFN CSN1 Napoli September 200518

First SSS lowered on 19 April 2005

Page 19: Status of the LHC Project L.Evans - C.Wyss Riunione CSN1 INFN Napoli, 21 Settembre 2005

CERN L.Evans & C.Wyss INFN CSN1 Napoli September 200519

Transport in the tunnel with an optical guided

vehicle

Page 20: Status of the LHC Project L.Evans - C.Wyss Riunione CSN1 INFN Napoli, 21 Settembre 2005

CERN L.Evans & C.Wyss INFN CSN1 Napoli September 200520

Transfer on jacks

Page 21: Status of the LHC Project L.Evans - C.Wyss Riunione CSN1 INFN Napoli, 21 Settembre 2005

CERN L.Evans & C.Wyss INFN CSN1 Napoli September 200521

Preparation of interconnect

Page 22: Status of the LHC Project L.Evans - C.Wyss Riunione CSN1 INFN Napoli, 21 Settembre 2005

CERN L.Evans & C.Wyss INFN CSN1 Napoli September 200522

Interconnection of beam tubes

Page 23: Status of the LHC Project L.Evans - C.Wyss Riunione CSN1 INFN Napoli, 21 Settembre 2005

CERN L.Evans & C.Wyss INFN CSN1 Napoli September 200523

Interconnect in sector 8-1: in progress in sub-sectors C and F

Page 24: Status of the LHC Project L.Evans - C.Wyss Riunione CSN1 INFN Napoli, 21 Settembre 2005

CERN L.Evans & C.Wyss INFN CSN1 Napoli September 200524

Pre-assembly of first low-beta triplet

(hall 181)

Page 25: Status of the LHC Project L.Evans - C.Wyss Riunione CSN1 INFN Napoli, 21 Settembre 2005

CERN L.Evans & C.Wyss INFN CSN1 Napoli September 200525

Page 26: Status of the LHC Project L.Evans - C.Wyss Riunione CSN1 INFN Napoli, 21 Settembre 2005

CERN L.Evans & C.Wyss INFN CSN1 Napoli September 200526

UA47: Quench protection & Power converters

Page 27: Status of the LHC Project L.Evans - C.Wyss Riunione CSN1 INFN Napoli, 21 Settembre 2005

CERN L.Evans & C.Wyss INFN CSN1 Napoli September 200527

Page 28: Status of the LHC Project L.Evans - C.Wyss Riunione CSN1 INFN Napoli, 21 Settembre 2005

CERN L.Evans & C.Wyss INFN CSN1 Napoli September 200528

Cryogenics overview

Page 29: Status of the LHC Project L.Evans - C.Wyss Riunione CSN1 INFN Napoli, 21 Settembre 2005

CERN L.Evans & C.Wyss INFN CSN1 Napoli September 200529

2400 W @ 1,8 K in the UX85 cavern

1.8K refrigeration units1st Pump-down in final LHC configuration

0.00

0.05

0.10

0.15

0.20

0.25

0.30

0.35

0.40

0.45

0.50

7:12 8:24 9:36 10:48 12:00

Time

Su

cti

on

Pre

ss

ure

[B

]

0

500

1000

1500

2000

2500

Co

oli

ng

Po

we

r [

W]

Suction Pressure

Set point

1.8K Cooling Power

P8 - 7 April 2005

Installed mode 2400 W @ 1.8 K

Pump-down 15 mbar

Page 30: Status of the LHC Project L.Evans - C.Wyss Riunione CSN1 INFN Napoli, 21 Settembre 2005

CERN L.Evans & C.Wyss INFN CSN1 Napoli September 200530

Repair of QRL modules

Page 31: Status of the LHC Project L.Evans - C.Wyss Riunione CSN1 INFN Napoli, 21 Settembre 2005

CERN L.Evans & C.Wyss INFN CSN1 Napoli September 200531

Repair of special QRL elements at

CERN

Page 32: Status of the LHC Project L.Evans - C.Wyss Riunione CSN1 INFN Napoli, 21 Settembre 2005

CERN L.Evans & C.Wyss INFN CSN1 Napoli September 200532

Cryogenic distribution line

Page 33: Status of the LHC Project L.Evans - C.Wyss Riunione CSN1 INFN Napoli, 21 Settembre 2005

CERN L.Evans & C.Wyss INFN CSN1 Napoli September 200533

QRL

Page 34: Status of the LHC Project L.Evans - C.Wyss Riunione CSN1 INFN Napoli, 21 Settembre 2005

CERN L.Evans & C.Wyss INFN CSN1 Napoli September 200534

Reinstallation of QRL in 7-8

• Sub-sectors A and B (600 m) have been cooled down on Wednesday 14th September.

• After the cold tests, the inner triplet will be installed, cooled down and powered whilst the rest of the line is being installed.

Page 35: Status of the LHC Project L.Evans - C.Wyss Riunione CSN1 INFN Napoli, 21 Settembre 2005

First cooldown of 600 m cryogenic LHC line sector 13-14 September 2005

He in

He outTh.screenlineLHe

linePump. line

20 K line

Page 36: Status of the LHC Project L.Evans - C.Wyss Riunione CSN1 INFN Napoli, 21 Settembre 2005

CERN L.Evans & C.Wyss INFN CSN1 Napoli September 200536

Conclusions

• Main objectives:– terminate installation in February 2007– first collisions in summer 2007

• The industrial production of standard components is compatible with this objective.

• The ramping up of QRL activities and magnet installation is critical to maintain this schedule.

• Additional actions have been implemented to ensure proper QRL production and installation rates.

• The installation and interconnection of cryomagnets have started in the tunnel.

• The commissioning of technical systems will take place in two adjacent sectors in parallel.

• Main next actions:– partial test of sector 7-8 in autumn 2005– commissioning test of the two first sectors (7-8 and 8-1) in summer

2006– find external collaborators to help with commissioning.

=> many thanks to INFN for its support !