SOLARTRICITY FOR ALAMO HEIGHTS ISD, A DASH FOR SUCCESS. CPS SOLARTRICITY CPS WILL PAY 27 CENTS PER KILOWATT FOR 20 YEARS UP TO 1 MW PER CUSTOMER. CURRENTLY CPS CHARGES AHISD 7 CENTS A KILOWATT. DERATE FACTOR Expected loss from: DC wiring AC wiring Soiling Efficiency of inverter(s) - PowerPoint PPT Presentation

TRANSCRIPT

  • SOLARTRICITY FOR ALAMO HEIGHTS ISD, A DASH FOR SUCCESS

  • CPS SOLARTRICITY

    CPS WILL PAY 27 CENTS PER KILOWATT FOR 20 YEARS UP TO 1 MW PER CUSTOMER.

    CURRENTLY CPS CHARGES AHISD 7 CENTS A KILOWATT.

  • DERATE FACTOR

    Expected loss from:

    DC wiringAC wiringSoilingEfficiency of inverter(s)Efficiency of solar panel (because a panel is a current source)

    WEATHER FACTOR

    Typical climateRain daysSun daysTemperature

  • $383,000 PER YEAR POTENTIAL EARNINGS

  • MONOCRYSTALINE

    Slices from single crystalBetter production than polycrystals because crystals are more orderlyPotentially longer lifeGrown from a circle then truncated to max out panel coverage

    POLYCRYSTALINE

    Grown in a ribbon or blockFull panel coverage

    THIN FILM

    Different crystal technology such as CIGSTypically half the power level of crystals per square footMore wind resistant, multiple applications

  • Photo from articlebase.comGOAL IS FOR HIGHEST WATTAGE PER SQUARE FOOT

  • FULL GOODS SELF BALLASTED ARRAY, POLYCRYSTALINE

  • MONOCRYSTALINE

  • LADY BIRD JOHNSON MS, CIGS vapor deposition , photo courtesy of Gridpoint

  • photo from Solarpowerrocks.com

  • MULTIPLE SMALL INVERTERS

    Maintain majority of system operation if inverter fails.Off the shelf replacementEasier installation due to smaller sizeMore connections requiredMore system complexitySelection based on electrical requirements

  • LARGE INVERTERS

    Single or minimal points of connection.More capacity per inverter.Potential long lead time for parts/replacements.Inverter goes down, whole system goes down.Lower system complexity.

  • INTERCONNECTIONTouch this you die

  • ROOF REPLACEMENT at HIGH SCHOOL

  • Inverter level monitoringString level monitoring

  • CPS OFFICE FACILITY, GREEN MOUNTAIN ROAD 6AM

  • CPS OFFICE FACILITY, GREEN MOUNTAIN ROAD 6:20AM

  • CPS OFFICE FACILITY, GREEN MOUNTAIN ROAD 6:45AM

  • SOLAR MOB APPROXIMATELY 10 MINUTES BEFORE DASH

  • CPS OFFICE FACILITY, GREEN MOUNTAIN ROAD, 6:58AM

  • FRONT DOOR, CPS FACILITYGREEN SHOES

  • SIGNING APPLICATION AND GETTING QUEUE NUMBER, CPS FACILITY 7:20AM

  • Lowell Tacker, AIA, LEED APONeill Conrad Oppelt Architects, [email protected] FOR ALAMO HEIGHTS ISD, A DASH FOR SUCCESS

    Special thanks to David McFalls, PEGridpoint

    ************************