Natural Gas Transmission So You Want To Build A

Pipeline ?

Richard Foley Division of Pipeline Certificates

Office of Energy Projects Federal Energy Regulatory

Commission

WAGPA - NARUC Workshop

Washington, DC October 31, 2011

Page 2: So You Want To Build A Pipeline

FERC

Office of Energy Projects 2

What Is FERC ?

• An Independent Regulatory Agency in the USA Federal Government

• Created by the Department of Energy Organization Act (1977)

• Federal Power Commission was the predecessor of FERC – FPC dates to 1920 establish for water power.

Page 3: So You Want To Build A Pipeline

FERC

Office of Energy Projects 3

How is FERC Organized ?

• There are 5 Commissioners’ positions • Nominated by the President, confirmed by the

Senate, President designates Chairman • Each commissioner has a 5-year fixed term,

staggered, with one term expiring each year

• The Chairman sets the monthly Commission agenda • Orders voted out by majority rule

Page 4: So You Want To Build A Pipeline

FERC

Office of Energy Projects 4

Chairman Wellinghoff (D)

External Affairs

General Counsel

Energy Market

Regulation

Executive Director

Administrative Litigation

Administrative Law Judges

Energy Projects

Secretary

Commissioner Norris (D)

Commissioner Spitzer (R)

Commissioner Moeller (R)

Commissioner LaFleur (D)

Electric Reliability

Energy Policy & Innovation

Enforcement

Page 5: So You Want To Build A Pipeline

FERC

Office of Energy Projects 5

FERC is an Independent Federal Regulatory Agency

• Political Party • No more than 3 commissioners from one

political party • President and Congress

• No review of FERC’s decisions by President, Department of Energy or other agencies

• Industry Participants • No private discussions of open cases • Restrictions on FERC employees: stock, gifts,

future employment

Page 6: So You Want To Build A Pipeline

FERC

Office of Energy Projects 6

FERC Program Offices

Office of Energy Projects Natural Gas Pipeline Construction and Abandonment Hydroelectric Projects (licensing, safety, compliance) Environmental Reviews for Natural Gas and Hydro Projects Electric Transmission Construction Office of Energy Markets and Reliability Natural Gas, Electric, and Oil Rates and Terms/Conditions of Service Office of Energy Policy & Innovation - May ‘09 Policy reforms to address emerging issues Office of Enforcement Market Monitoring and Enforcement Office of Electric Reliability Electric System Reliability & Compliance Office of Administrative Litigation FERC Trial Staff

Page 7: So You Want To Build A Pipeline

FERC

7

OEP Organizational Structure

Page 8: So You Want To Build A Pipeline

FERC

Office of Energy Projects 8

What Does FERC Regulate ?

• Natural Gas Industry • Interstate transportation rates and services • Interstate gas pipeline and liquefied natural

gas terminal construction and oversee related environmental matters

• Electric Power Industry • Interstate transmission rates and services • Wholesale energy rates and services • Corporate transactions, mergers, securities

issued by public utilities

Page 9: So You Want To Build A Pipeline

FERC

Office of Energy Projects 9

What Does FERC Regulate ? (con’t)

• Oil Pipeline Industry • Interstate transportation rates and

services of crude oil and petroleum products

• Hydroelectric Industry • Licensing of nonfederal hydroelectric

projects • Oversee related environmental matters • Inspect nonfederal hydropower projects

for safety issues

Page 10: So You Want To Build A Pipeline

FERC

Office of Energy Projects 10

In the United States, there are approximately 217,300 miles of interstate natural gas

transmission pipeline.

Source: Based on data from Ventyx Global Energy Decisions, Inc., Velocity Suite, April 2011, and EIA’s Natural Gas Pipelines.

Page 11: So You Want To Build A Pipeline

FERC

Office of Energy Projects 11

Major Interstate and Canadian Pipelines and

Gas Production Areas, Including Shale

Source: Based on data from Ventyx Global Energy Decisions, Inc., Velocity Suite, March 2011, and EIA’s Natural Gas Pipelines.

Page 12: So You Want To Build A Pipeline

FERC

Office of Energy Projects 12

North American Gas Paths

1. Southwest to Southeast 2. Southwest to Northeast 3. Southwest to Midwest 4. Southwest to Panhandle to Midwest 5. Southwest to Western 6. Canada to Western 7. Canada to Midwest 8. Canada to Northeast 9. Eastern Offshore Canada to Northeast 10. Rocky Mountains to Western 11. Rocky Mountains to Midwest

Page 13: So You Want To Build A Pipeline

FERC

Office of Energy Projects 13

U.S. Natural Gas Supply Basins Relative to Major Natural Gas Pipeline

Transportation Corridors

Page 14: So You Want To Build A Pipeline

FERC

Office of Energy Projects 14

FERC Helping Markets Work

Adequate Infrastructure

OEP

Effective Market Rules

OEMR

Market Oversight

OE

Competitive Market

Innovation FERC

Page 15: So You Want To Build A Pipeline

FERC

Office of Energy Projects 15

The Regulatory Process As A Balancing Act

Page 16: So You Want To Build A Pipeline

FERC

Office of Energy Projects 16

Natural Gas Act

NATURAL GAS ACT

Section 3 Import/Export

Case Specific

Case Specific

Blanket Authority

Automatic Prior Notice

Section 7(c) Interstate

Page 17: So You Want To Build A Pipeline

FERC

Office of Energy Projects 17

• Automatic Authorization • Cost of facilities is less than $ 10.6 million • Facilities are “eligible” facilities

• Prior Notice • Cost is between $ 10.6 and $ 30.2 million • 60-day notice period prior to construction • Facilities are “eligible” facilities

Natural Gas Act

• Blanket Certificate

• 45-day landowner notification / waived

Page 18: So You Want To Build A Pipeline

FERC

Office of Energy Projects 18

• Conduct a full review of proposal including engineering, rate, accounting, and market analysis

• Conduct an environmental review by preparing an Environmental Assessment or an Environmental Impact Statement

Natural Gas Act

• Case Specific Section 7(c) Certificate

Page 19: So You Want To Build A Pipeline

FERC

Office of Energy Projects 19

Imports/Exports

• Any entity that proposes to site, construct and operate or modify facilities used to import or export gas must file an application pursuant to Section 3 of the NGA and file for the issuance of a Presidential Permit.

• In order to obtain a Presidential Permit, the Commission must "consult" with the Secretaries of State and Defense prior to its issuance.

Page 20: So You Want To Build A Pipeline

FERC

Office of Energy Projects 20

Imports / Exports

• The owner of the gas must apply to the Office of Fossil Energy, Department of Energy (DOE/FE) for Section 3 authority as well.

• Jurisdictional pipelines that filed for Section 3 authorization to site, construct, and operate border facilities will not be the same party that applies for Section 3 authority from DOE/FE.

Page 21: So You Want To Build A Pipeline

FERC

Office of Energy Projects 21

North Baja Project Border Facilities

Page 22: So You Want To Build A Pipeline

FERC

Office of Energy Projects 22

Major Pipeline Construction Projects

Page 23: So You Want To Build A Pipeline

FERC

Office of Energy Projects 23

How Does FERC Evaluate All Of These Major Projects ?

What Criteria Are Used in This Evaluation ?

Project Evaluation

Page 24: So You Want To Build A Pipeline

FERC

Office of Energy Projects 24

PL99-3-000 Certificate Policy

• New Certificate Policy Statement issued on September 15, 1999.

• Clarification of Certificate Policy Statement issued on February 9, 2000.

• Clarification issued on July 26, 2000. • Policy applied to facts of each case.

Page 25: So You Want To Build A Pipeline

FERC

Office of Energy Projects 25

Prior Policy Problems

• The reliance on percentage of capacity under long-term contracts to show demand.

• The pricing of new facilities.

Page 26: So You Want To Build A Pipeline

FERC

Office of Energy Projects 26

• Foster Competition • Consider Captive Customers • Avoid Unnecessary Physical Impacts • Achieve Optimal Amount of Facilities • Encourage Complete Record • Expedite Review Time

G o a l s

PL99-3-000 Certificate Policy

Page 27: So You Want To Build A Pipeline

FERC

Office of Energy Projects 27

PL99-3-000 Certificate Policy

• Apply Threshold Cost Test • Subsidization = Incremental Rates

• No Subsidization = Rolled-in Treatment

• System improvements for existing customers = Rolled-in Treatment

Page 28: So You Want To Build A Pipeline

FERC

Office of Energy Projects 28

PL99-3-000 Certificate Policy

• Develop Record • Adverse Impacts on

• Existing Customers and Pipelines • Landowners • Communities

• Specific Benefits • Need and Market • Condemnation Impact • Initial Rate Derivation and Tariff Sheets

Page 29: So You Want To Build A Pipeline

FERC

Office of Energy Projects 29

Adverse Impacts

Needs and Benefits Record

• Balance Benefits and Impacts • Complete Traditional Environmental Process

PL99-3-000 Certificate Policy

Page 30: So You Want To Build A Pipeline

30

Balancing Interests

People Like... But They Also Want...

Due Process Expedited Process

Smaller Government Effective Government

Less Regulation Assurance of Fair Markets

Market-dictated OutcomesProtection from Market

Dysfunctions, Unexpected Risk,and Unjust Rates

Protection for the Environment andProperty Interests

Ample Supplies ofLow-cost Energy

Page 31: So You Want To Build A Pipeline

31

Dual Paths of Review

Application Filed

Non-Environmental Review

Environmental Review

Draft Order Prepared Commission Action

Page 32: So You Want To Build A Pipeline

32

Certificate Process Overview

Application Filed

Order Issued

Non-Environmental Review and Analysis • Engineering – GQI, storage, hydraulic flow • Tariff – rates, terms & conditions of service • Policy – precedents, rules, regulations • Accounting

Environmental Review and Analysis • Biological – fish, wildlife, vegetation • Cultural – historic preservation • Land use – recreation, aesthetics • Soils and geologic • Air and noise – quality, loudness • Socioeconomic impacts • System alternatives

Parallel Processing Paths

Page 33: So You Want To Build A Pipeline

FERC

Office of Energy Projects 33

The Environmental Process

FERC’s Environmental Review Process Makes a Special Effort to be Accessible to All Affected Parties, Especially Landowners.

Page 34: So You Want To Build A Pipeline

FERC

Office of Energy Projects 34

Opportunities for Public Involvement

The FERC Process: • Issue Notice of the

Application • Project Sponsor Sends

Landowner Notification Package

• Issue Notice of Intent to Prepare the NEPA Document (i.e., scoping)

• Hold Scoping Meetings

Public Input:

• File an Intervention; register for e-subscription

• Contact the project sponsor w/questions, concerns; contact FERC

• Send letters expressing concerns about environmental impact

• Attend scoping meetings

Page 35: So You Want To Build A Pipeline

FERC

Office of Energy Projects 35

Opportunities for Public Involvement

The FERC Process: • Issue Notice of

Availability of the DEIS

• Hold Public Meetings on DEIS

• Issue a Commission Order

Public Input: • Comments on the

adequacy of DEIS • Attend public

meetings to give comments on DEIS

• Intervene / request for Rehearing

Page 36: So You Want To Build A Pipeline

FERC

Office of Energy Projects 36

Traditional vs. Pre-Filing Process

Announce Open

Season

Announce Open

Season

Develop Study

Corridor

Develop Study

Corridor

Conduct Scoping

Conduct Scoping

0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28

Review Draft Resource Reports & Prepare DEIS

Issue Draft EIS

Issue Draft EIS

File At

FERC

Issue Order

Issue Order

File At

FERC

Prepare Resource Reports

Prepare Resource Reports

Issue Final EIS

Issue Final EIS

(months)

Traditional - Applicant

Traditional - FERC

Pre-Filing - Applicant

Pre-Filing - FERC

Page 37: So You Want To Build A Pipeline

FERC

Office of Energy Projects 37

Timeline for Pre-Filing Process

(months)

Start PF

Review

0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

Review Draft Resource Reports

& Prepare Prelim. DEIS

Issue Draft EIS

File At

FERC

Issue Order

Prepare Draft Resource Reports

Issue Final EIS

Applicant’s Activities

FERC’s Activities

Determine Application Complete

Submit PF

letter

Page 38: So You Want To Build A Pipeline

FERC

Office of Energy Projects 38

Benefits of Pre-Filing

• More interactive NEPA process, no shortcuts

• Earlier, more direct involvement by FERC, other agencies, landowners

• Goal of “no surprises”

• Time savings realized only if we are working together with stakeholders

• FERC staff is an advocate of the Process, not the Project!

Page 39: So You Want To Build A Pipeline

FERC

Office of Energy Projects

Common Environmental Issues

• Wetlands and Waterbodies

• Agricultural and Residential Areas

• Archeological and Historical Resources

• Endangered Species

• Landowner Concerns

• Safety

Page 40: So You Want To Build A Pipeline

FERC

Office of Energy Projects

Construction Impacts

• Erosion and sedimentation

• Soil layer mixing

• Restrictions on and conflicts with property use

• Loss or change of habitat

• Increased or decreased accessibility

• Wildlife / habitat protection time windows

Page 41: So You Want To Build A Pipeline

FERC

Office of Energy Projects

Right-of-Way Workspace & Pipe String

Page 42: So You Want To Build A Pipeline

FERC

Office of Energy Projects

Pipe Bends & Slopes

Page 43: So You Want To Build A Pipeline

FERC

Office of Energy Projects

Side Booms – In the Ditch

Page 44: So You Want To Build A Pipeline

FERC

Office of Energy Projects

Protecting and Recovering Archeological Resources

Page 45: So You Want To Build A Pipeline

FERC

Office of Energy Projects

Construction in Populated Areas

Page 46: So You Want To Build A Pipeline

FERC

Office of Energy Projects

Residential Construction

Page 47: So You Want To Build A Pipeline

FERC

Office of Energy Projects

Open-cut River Crossing

Page 48: So You Want To Build A Pipeline

FERC

Office of Energy Projects

Dry Crossing of Stream

Page 49: So You Want To Build A Pipeline

FERC

Office of Energy Projects

Horizontal Directional Drill

Page 50: So You Want To Build A Pipeline

FERC

Office of Energy Projects

Avoiding Sensitive Resources

Page 51: So You Want To Build A Pipeline

FERC

Office of Energy Projects

Wetland Construction

Page 52: So You Want To Build A Pipeline

FERC

Office of Energy Projects

Preservation and Restoration of Stream Banks

Page 53: So You Want To Build A Pipeline

FERC

Office of Energy Projects

Construction within a Transmission Line Corridor

Page 54: So You Want To Build A Pipeline

FERC

Office of Energy Projects

Topsoil Segregation

Page 55: So You Want To Build A Pipeline

FERC

Office of Energy Projects

Erosion Control - Slope Breakers

Page 56: So You Want To Build A Pipeline

FERC

Office of Energy Projects

Slope Stabilization

Page 57: So You Want To Build A Pipeline

FERC

Office of Energy Projects

Compressor Station

Page 58: So You Want To Build A Pipeline

FERC

Office of Energy Projects 58

Major Pipeline Projects

Page 59: So You Want To Build A Pipeline

FERC

Office of Energy Projects 59

Projects Certificated

Page 60: So You Want To Build A Pipeline

FERC

Office of Energy Projects 60

Differing Purposes for Certificated Pipelines

• Typical long-line from new supply • Replacement pipeline projects • Short, high capacity pipelines to

deliver regasified LNG to grid • Short, high capacity pipelines to

deliver underground storage to grid

Page 61: So You Want To Build A Pipeline

FERC

Office of Energy Projects 61

Currently Pending Projects

Page 62: So You Want To Build A Pipeline

FERC

Office of Energy Projects 62

On The Horizon

Page 63: So You Want To Build A Pipeline

FERC

Office of Energy Projects 63

Storage

Page 64: So You Want To Build A Pipeline

A Look at Liquefied Natural Gas

(LNG)

64

FERC

Office of Energy Projects

Page 65: So You Want To Build A Pipeline

FERC

Office of Energy Projects 65

How Much Natural Gas Is Out There ?

Source: EIA World Proved Reserves of Oil and Natural Gas, Most Recent Estimates - Oil and Gas Journal

Total World Gas Reserves as of 1/1/09: 6, 254 Trillion Cubic Feet Total World Gas Reserves for 2009: 6,254 Trillion Cubic Feet Source: BP Statistical Review of World Energy June 2011- Table Proved Reserves of Natural Gas

Central & South America

4%Western Europe

2%

North America5%

Africa8%

Asia & Oceania9%

Middle East41%

Eastern Europe & Former U.S.S.R.

31%

Total World Gas Reserves for 2010: 6,609 Trillion Cubic Feet

Page 66: So You Want To Build A Pipeline

FERC

Office of Energy Projects 66

Imports What Is LNG ?

• LNG is natural gas cooled to its liquid at 259º Fahrenheit and 1/600 of its gaseous volume.

• LNG is commonly stored and shipped at slightly above atmospheric pressure – overseas by ship and locally by truck.

• LNG is odorless, colorless ; it neither explodes nor burns as a liquid.

Page 67: So You Want To Build A Pipeline

FERC

Office of Energy Projects 67

Imports What Is LNG ?

• LNG vapors are flammable only in concentrations of 5% to 15% with air and will not explode in an unconfined environment - the ignition temperature is more than 500º Fahrenheit higher than gasoline.

• In the past 40 years there have been more

than 33,000 LNG ship voyages without a significant accident or cargo spillage.

Page 68: So You Want To Build A Pipeline

FERC

Office of Energy Projects 68

A Open Market or

Proprietary At Delivery of Liquid to Terminal

LNG Suppliers

USA LNG Buyers

A B

B Open Access At

Delivery of Vapor into Interstate Pipeline

System

Liquid to Vapor Flow

68

Hackberry Decision (December 2002)

Page 69: So You Want To Build A Pipeline

FERC

Office of Energy Projects 69

Benefits of the New LNG Policy

• Stimulates development of new LNG terminals

• Accommodates various business models

• Increases gas supplies to the U.S. • Maintains FERC’s responsibility for

environmental and safety reviews.

Page 70: So You Want To Build A Pipeline

FERC

Office of Energy Projects 70

Maximum No. American LNG Deliverability Growth

0

10

20

30

40

50

60

Existing Gov't OK UnderConstruction

Gov't OK - NOConstruction

Proposed -FERC & Coast

Guard

Potential

Bcf p

er D

ay

Existing Gov't OK Under ConstructionGov't OK - NO Construction Proposed - FERC & Coast GuardPotential

Page 71: So You Want To Build A Pipeline

FERC

Office of Energy Projects 71 Source: LNG volumes from Fossil Energy.

LNG Re-Export Volumes by Terminal

Page 72: So You Want To Build A Pipeline
Page 73: So You Want To Build A Pipeline

FERC

Office of Energy Projects 73

Energy Policy Act of 2005

• LNG (Sec. 311) – FERC is lead decisional agency – Pre-filing is mandatory

• Regulations issued on October 7th

– Hackberry Policy is now codified • Project sponsor can adopt open access, but cannot be

required to be open access

• Storage with Market Based Rates approvable even if market power is present (Sec. 312)

Page 74: So You Want To Build A Pipeline

FERC

Office of Energy Projects 74

Gas Project Scheduling/Coordination

• Section 313 - Process Coordination – Revised Sections 15 and 19 of NGA

• FERC acts as lead agency; sets schedule • FERC maintains consolidated record • Streamlines judicial review

– Order No. 687 issued by FERC on October 19, 2006 – Final rule sets schedule/consolidation procedures

• When filed, applicant must ID all needed Federal authorizations • 90 days after notice date, FERC issues notice of schedule or EA • 90 days after EA or EIS is the deadline for other agencies • 30 days after deadline expiration, each agency must file a copy

of decision & index of the record for the FERC record system.

Page 75: So You Want To Build A Pipeline

FERC

Office of Energy Projects 75

Energy Policy Act of 2005

• Process Coordination (Sec. 313) – FERC is lead agency for all Section 7 & 3

filings. • Establishes processing schedule

– FERC record is the one record upon which all appeals of Federal actions are based

– Judicial Streamlining • All appeals must be heard in Federal appeals

court in the region where facility is to be located • Violation of schedule to be heard in US Court of

Appeals for the District of Columbia

Page 76: So You Want To Build A Pipeline

FERC

Office of Energy Projects 76

Energy Policy Act of 2005 Selected Activities

• LNG Pre-filing Rulemaking – Issued October 7, 2005; effective November 17, 2005

• LNG Forums with DOE and Other Agencies – Boston, LA and Astoria, Oregon

• MOU with Defense on LNG Facilities • Alaska Progress Report – Every 6 Months • Lead Agency

– Policy Statement issued September 26, 2005 – NOPR under construction

• Storage Final Rule – Issued June 19, 2006; effective July 27, 2006

Page 77: So You Want To Build A Pipeline

FERC

Office of Energy Projects 77

Learn at Home

• Good learning resource for gas pipelines & storage

• Interactive or 76 page pdf version • http://www.eia.doe.gov/pub/oil_ga

s/natural_gas/analysis_publications/ngpipeline/index.html

Page 78: So You Want To Build A Pipeline

FERC

Office of Energy Projects 78