sliding pressure operation

29
16/09/2015 1 A Study in Benefits, Challenges, Design and Tuning Presented by Don Parker Provecta Process Automation Greg Alder Scientech August 2015 Implementing Sliding Pressure Operation Scientech Plant Performance Users’ Group Symposium August 2015

Upload: vesridhar

Post on 08-Dec-2015

88 views

Category:

Documents


10 download

DESCRIPTION

power plant

TRANSCRIPT

Page 1: Sliding Pressure Operation

16/09/2015 1

A Study in Benefits, Challenges, Design and Tuning

Presented by Don Parker Provecta Process Automation Greg Alder Scientech

August 2015

Implementing Sliding Pressure Operation

Scientech Plant Performance Users’ Group Symposium August 2015

Page 2: Sliding Pressure Operation

16/09/2015 2

Historical Setting: Many base-load drum boilers in 70-90s were designed for

fixed pressure, normal operation range 80-100%.

The changing operating scene:

Life extension Unregulated renewables Economic imperatives:

Wider range operation Fuel cost reduction CO2 reduction

Overview

Scientech Plant Performance Users’ Group Symposium August 2015

Page 3: Sliding Pressure Operation

16/09/2015 3

Energy Market Challenges – Pressures on Capacity and Performance

Wider, more flexible operation

Faster Ramping Improved efficiency

at low load

Scientech Plant Performance Users’ Group Symposium August 2015

Page 4: Sliding Pressure Operation

16/09/2015 4

Range and Performance Changes: 4x500MW Station (Australia)

Mill auto-bias

Scientech Plant Performance Users’ Group Symposium August 2015

Page 5: Sliding Pressure Operation

16/09/2015 5

Sliding pressure

Steam Pressure

TV Posn

100%

Steam Flow

100%

Scientech Plant Performance Users’ Group Symposium August 2015

Page 6: Sliding Pressure Operation

16/09/2015 6

Why Sliding Pressure? Benefits in Unit Heat Rate at low load

Reduced turbine throttling losses (wider valve opening)

Reduced Feed Pump Power Improved Hot RH temperature attainability

Reduced Turbine inlet temperature

variations on load changes

Economic benefits: Fuel costs reduced CO2 emissions reduced

Scientech Plant Performance Users’ Group Symposium August 2015

Page 7: Sliding Pressure Operation

16/09/2015 7

How do I quantify the benefits? How do I optimise the pressure curve? What are the potential downsides?

Fast ramping Increased drum saturation temperature changes

Greater fuel input variations – impacts on combustion and pulverizers

How is the control system changed to: Calculate additional fuel input requirements during

ramps Minimise pressure overshoot/undershoot Minimise steam temperature deviations from fuel/steam

flow imbalances during ramps

The Challenges

Scientech Plant Performance Users’ Group Symposium August 2015

Page 8: Sliding Pressure Operation

16/09/2015 8

A Complete Solution

Known Potential Efficiency Improvement Areas

PEPSE Scenario Modelling

Benefit Determination

Controls Implementation and Tuning

Scientech’s wide industry experience

Cost model (Client); Calculations (Scientech)

Provecta’s wide controls experience

Scientech’s deep knowledge and capability

UTILIZING:

Page 9: Sliding Pressure Operation

16/09/2015 9

PEPSE model example 550MW gross, drum boiler, fixed pressure Fixed and sliding pressure comparisons at half load Two pump models applied: Electric and steam-driven Two Hot RH temperature scenarios for 50%, fixed pressure

No temperature loss (ie full HRH temperature at 50%) 30 Deg F temperature loss (and recovery in sliding pressure)

Six 50% scenarios run:

1. Quantifying the Benefits

Model HRH temp loss at 50%?

Fixed Pressure

Sliding Pressure

Elec MBFPs Y N/A Elec MBFPs N Steam MBFPs Y N/A Steam MBFPs N

Page 10: Sliding Pressure Operation

16/09/2015 10

Page 11: Sliding Pressure Operation

16/09/2015 11

Page 12: Sliding Pressure Operation

16/09/2015 12

Page 13: Sliding Pressure Operation

16/09/2015 13

Page 14: Sliding Pressure Operation

16/09/2015 14

Outcomes: Turbine Net Cycle Efficiency at Half Load Case 1: Fixed Pressure HRH Steam Temp 970°F Case 2: Fixed Pressure HRH Steam Temp 1000°F Both cases: Sliding Pressure HRH Steam Temp 1000°F

1. Quantifying the Benefits

MBFP Model

Case Fixed Prs Sld Prs % Improvement

Net Heat rate improvement

Electric 1 39.88

40.68 2.00 168.4 B/kWh

2 40.09 1.47 123.1

Steam 1 40.19

40.80 1.52 128.4

2 40.40 0.99 83.86

Page 15: Sliding Pressure Operation

16/09/2015 15

Cost Benefits Based on typical fuel costs $2.27/MMBTU

1. Quantifying the Benefits

MBFP Model

Case Net Heat rate improvement

Saving/hr 298MW

Sav per unit per year @ 4h/day low load (*.85)

Electric 1 168.4 B/kWh $114 $140k 2 123.1 $83 $80k

Steam 1 128.4 $87 $85k 2 83.86 $57 $55k

Page 16: Sliding Pressure Operation

16/09/2015 16

PEPSE can quantify all scenarios

Required load change rate will determine drum metal temperature change rate for any given pressure profile.

Sliding pressure setpoint will be lagged: To reflect boiler milling/heat release delay and steam energy

storage delay. Delayed pressure setpoint also minimises temperature

deviations. Ensure delayed pressure setpoint curve does not cause

turbine governor to reach maximum at fastest ramp rate.

2. Optimising the Sliding Pressure Curve

Page 17: Sliding Pressure Operation

16/09/2015 17

Main areas affected Boiler Demand (dynamic feedforward; pressure controller) Pressure setpoint Steam temperature (gain adaption and feedforwards)

Design changes

Response analysis tests

Simulation and tuning

3. Modifying the Controls

Scientech Plant Performance Users’ Group Symposium August 2015

Page 18: Sliding Pressure Operation

16/09/2015 18

Unit Coordinated Mode (BF+MW)

Boiler

MILLS

FUEL

AIR

FEEDWATER

SUPERHEATERTV

P

MWF

Overfiring

AGC

+ PI

Unit Demand

PID O2 Trim

+

+ + +

_ _

Pressure SP

Scientech Plant Performance Users’ Group Symposium August 2015

Page 19: Sliding Pressure Operation

16/09/2015 19

Load changes in Fixed and Sliding Pressure (simulations)

2000 2500 3000 3500 4000 4500 5000 550020

40

60

80

100

120

140

160

180

Press BarMW%Gov Posn %MWDFuel Flow%New P-SPBasic P-SP

Coord ModeLoad Ramp

2000 2500 3000 3500 4000 4500 5000 550020

40

60

80

100

120

140

160

180

Press BarMW%Gov Posn %MWDFuel Flow%New P-SPBasic P-SP

Coord Mode(Sliding Pressure)

Scientech Plant Performance Users’ Group Symposium August 2015

Page 20: Sliding Pressure Operation

16/09/2015 20

A 2-Degree-of-Freedom structure provides control parameters to independently manipulate both setpoint and disturbance responses.

Simpler structures do not model the expected process response into the setpoint, nor provide model-based feedforward dynamics.

Design Basis: 2-DOF Controller

Tuned for load changing

Tuned for disturbances

Page 21: Sliding Pressure Operation

16/09/2015 21

Simulation results showing the effect on pressure response (light blue) when a feedforward to fuel (green) is added to the fuel demand and the pressure setpoint is passed through a second order lag.

Model-based Sliding Pressure Control

0 200 400 600 800 1000 1200 1400 1600 1800 2000-2

0

2

4

6

8

10

0 200 400 600 800 1000 1200 1400 1600 1800 2000-1

0

1

2

3

4

5

6

7

8

9

10

Basic control structure (left) and 2-DOF structure (right).

Page 22: Sliding Pressure Operation

16/09/2015 22

Simplified pressure model:

Field Data:

Pressure Setpoint (Response Model) Dynamics

Steam flow

Steam Pressure

Integ.Grinding and Boiler energy storageHeat release delay

PT3

X

LAG IFuel Demand

Turbine CV position

Step change in fuel flow (CV fixed) Step change in Throttle Valve position

Page 23: Sliding Pressure Operation

16/09/2015 23

The sliding pressure setpoint is dynamically modified to minimise: Pressure controller over-correction Steam temperature disturbances.

Three setpoint model components:

Initial pressure change as governor moves before fuel has any impact on steam production (pressure direction reversal)

Delay to pressure changes due to energy storage in metal and waterwalls as the saturation temperature changes

Delay in heat input from the additional fuel due to milling, combustion and heat transfer processes

Pressure Setpoint Formation

Scientech Plant Performance Users’ Group Symposium August 2015

Page 24: Sliding Pressure Operation

16/09/2015 24

Pressure Setpoint Formation

Scientech Plant Performance Users’ Group Symposium August 2015

Model-based pressure setpoint

Identification tools used to determine parameters Need to ensure sufficient throttle valve ‘headroom”

for fastest ramp rate.

Governor-movementpressure response model

P-SP

Energy + InertialStorage DelayModel Model

Rate Lim

Dyn

F(t) High orderF(x)

F(t)

Unit Load Demand

Adapt

Calculated CV Posn

Page 25: Sliding Pressure Operation

16/09/2015 25

System Identification: Boiler Energy Storage

Scientech Plant Performance Users’ Group Symposium August 2015

Page 26: Sliding Pressure Operation

16/09/2015 26 Scientech Plant Performance Users’ Group Symposium August 2015

AGC or Local

Droopw ith DB

ULD

Press-SP Delay model

∆ MSP

Decoupling aand relief b

a/b

MW trim **

storageCalc CV demand compensat'n

feedfwd

delay compensationfeedfwd

** Dyn - adaptive transient overfiring

MW Demand

Transfer Tracking signals

< Capability

F(x)

Syst. Freq.

Dyn

F(x)

PID

PID

MSP

Turbine Demand

Gross MW

F(t)

F(x)

F(t)

Fuel/Air Demand

Dyn ULD

< >

Add static Setpoint curve

Delay P-SP (model based)

Add overfiring transient component

Unit Master Modifications

Page 27: Sliding Pressure Operation

16/09/2015 27

Pressure-ramp tuning – overfiring calibration Initial settings from energy storage models Set procedures followed to optimise

Load-ramp tuning – dynamic setpoint calibration

Low/mid/high range ramps Load-based adjustments around model data

Steam temperature – attemperator outlet temperature

setpoint feedforward calibration Based on steam/fuel dynamic mismatch Iterative: spray flow affects pressure response

Tuning

Page 28: Sliding Pressure Operation

16/09/2015 28

Load ramping

Scientech Plant Performance Users’ Group Symposium August 2015

Main Steam Pressure and SP

Fuel Demand

Overfiring signals

SH and RH Temps

Turbine Master

Page 29: Sliding Pressure Operation

16/09/2015 29

Low load operation is expected to become more prevalent as renewable penetration increases.

PEPSE has shown Sliding Pressure can provide significant Cost savings CO2 reduction Reduction in turbine inlet thermal cycling.

Model-based DCS design provides fast ramping with

minimal disturbances.

Use of advanced identification and tuning tools minimises optimisation time.

Conclusion