Presentation to the February 7, 2013, Moffett Restoration Advisory Board meeting by Neil Hey of Shaw E&I and Valerie Harris of the Navy.

TRANSCRIPT

Page 1: Site 28 Supplemental Investigation

Former NAS Moffett Field

Neil Hey, PG

Shaw E & I, Inc.

&Valerie Harris, PE

Remedial Project Manager

Navy BRAC PMO West

RAB Meeting

February 7, 2013

Site 28 Supplemental Investigation

Page 2: Site 28 Supplemental Investigation

Presentation Overview

2

Project Objectives

Technical Approach

Preliminary Results

Remaining Work

Questions

Page 3: Site 28 Supplemental Investigation

3

Page 4: Site 28 Supplemental Investigation
Page 5: Site 28 Supplemental Investigation

Supplemental investigation is needed to:

1) Further delineate PCE & daughter products (TCE,DCE, & VC) in A-aquifer within & around the FormerBuilding 88 & Traffic Island source areas

2) Confirm depth & lateral continuity of A/B-aquitard inTraffic Island Area

3) Verify depth to top of B2-aquifer in Traffic IslandArea

4) Confirm whether existing well W-88-1 is screened inB2-aquifer

5) Confirm whether B2-aquifer beneath Traffic IslandArea is impacted by COCs

Project Objectives

5

Page 6: Site 28 Supplemental Investigation

Phase 1 – Semi-quantitative ScreeningSurvey

To further assess the distribution of CEs andsoil lithology in the areas of interest

Phase 2 – Monitoring Well Installations &Sampling

To fill in data gaps of the current groundwatermonitoring well network

Technical Approach

6

Page 7: Site 28 Supplemental Investigation

Navy SCAPS Rig

7

Page 8: Site 28 Supplemental Investigation

SCAPS Probe

8

From:

U.S. Army Corps of Engineers, 2002,

Cost and Performance Report for Tri-Service

SCAPS MIP, January , ERDC/EL TR-02-1

Page 9: Site 28 Supplemental Investigation

Membrane interface probe (MIP)/ Direct sample ion-trapmass spectrometer (DSITMS) detector System

Semi-quantitative COC concentration data(mg/L of calibration solution)

MIP data are only considered estimates(USACE, 2002)

<http://el.erdc.usace.army.mil/elpubs/pdf/trel02-1.pdf>

Results by MIP system are relative & should beverified by soil and groundwater samples(EPA, 2012)

<http://www.clu-in.org/characterization/technologies/mip.cfm>

MIP/DSITMS System

9

Page 10: Site 28 Supplemental Investigation

SCAPS Test Results – Former Bldg 88

10

Maximum MIP/DSITMSResponse & Groundwater

and Soil Results

PCE

~6 to 16 ft bgs(Fine-grained Sediment Interval)

GeneralGroundwaterFlow Direction

11.5 ft bgs830,000 µg/Lcs – MIP660 µg/L - GW8.8 mg/kg - Soil

11.1 ft bgs210,000 µg/Lcs – MIP440 µg/L - GW0.45 mg/kg - Soil

µg/Lcs denotes micrograms perliter of DSITMS calibration solution

Tier 2 SCAPS test location

Tier 1 SCAPS test location

Page 11: Site 28 Supplemental Investigation

SCAPS Test Results – Former Bldg 88

11

GeneralGroundwaterFlow Direction

18 ft bgs50,000 µg/Lcs – MIP78 µg/L - GW1.9 mg/kg - Soil

Maximum MIP/DSITMSResponse & Groundwater

and Soil Results

PCE

~16 to 27 ft bgs(Coarse-grained Sediment Interval)

µg/Lcs denotes micrograms perliter of DSITMS calibration solution

Tier 2 SCAPS test location

Tier 1 SCAPS test location

Page 12: Site 28 Supplemental Investigation

SCAPS Test Results – Former Bldg 88

12

GeneralGroundwaterFlow Direction Tier 2 SCAPS test location

Tier 1 SCAPS test location

Maximum MIP/DSITMSResponse & Groundwater

and Soil Results

PCE

~27 to 40 ft bgs(Fine-grained Sediment Interval)

Page 13: Site 28 Supplemental Investigation

SCAPS Test Results – Former Bldg 88

13

GeneralGroundwaterFlow Direction

Maximum MIP/DSITMSResponse & Groundwater

and Soil Results

PCE

~40 to 56 ft bgs(Coarse-grained Sediment Interval)

Tier 2 SCAPS test location

Tier 1 SCAPS test location

Page 14: Site 28 Supplemental Investigation

SCAPS Test Results – Former Bldg 88

14

GeneralGroundwaterFlow Direction

Maximum MIP/DSITMSResponse & Groundwater

and Soil Results

PCE

~56 to 70 ft bgs(Coarse & Fine-grained

Sediment)

Tier 2 SCAPS test location

Tier 1 SCAPS test location

Page 15: Site 28 Supplemental Investigation

1) SCAPS results generally correlate well with historical data

2) MIP/DSITMS detections of PCE primarily in fine-grained sediments

3) Highest MIP/DSITMS detections of TCE & DCE primarily in fine-grained sediments

4) Vinyl chloride was not detected in any of the MIP/DSITMS samples

5) Fine-grained sediments acting as a continuing source of chemicals tothe groundwater

6) MIP/DSITMS responses are over 10-times higher than collocateddiscrete depth groundwater sample results

7) Discrete depth groundwater results are 10-times lower thanestimated effective solubility limits

8) Discrete depth soil results are over 10-times lower than estimatedsoil saturation concentrations

Preliminary Findings

15

Page 16: Site 28 Supplemental Investigation

Potential Well LocationsFormer Bldg 88 Area

16

GeneralGroundwaterFlow Direction

11.5 ft bgs830,000 µg/Lcs – MIP660 µg/L - GW8.8 mg/kg - Soil

11.1 ft bgs210,000 µg/Lcs – MIP440 µg/L - GW0.45 mg/kg - Soil

New Monitoring Well

Page 17: Site 28 Supplemental Investigation

Planned SCAPS LocationsTraffic Island Area

17

GeneralGroundwaterFlow Direction

0 to 23 ft bgs

Page 18: Site 28 Supplemental Investigation

Planned SCAPS LocationsTraffic Island Area

18

GeneralGroundwaterFlow Direction

23 to 46 ft bgs

Page 19: Site 28 Supplemental Investigation

Planned SCAPS LocationsTraffic Island Area

19

GeneralGroundwaterFlow Direction

46 to 65 ft bgs

Page 20: Site 28 Supplemental Investigation

Planned Well LocationsTraffic Island Area

20

Page 21: Site 28 Supplemental Investigation

Tier 2 SCAPS at Former Bldg 88 Area – Spring 2013

Tiers 1 & 2 SCAPS at Traffic Island Area – Spring 2013

Monitoring Well Installations – Summer 2013

Groundwater Sampling – Summer & Fall 2013

Field Work Timeline

21

Page 22: Site 28 Supplemental Investigation

Questions?

22

Point of Contact:

Scott Anderson

BRAC Environmental Coordinator