4-1 Session 4
Session 4: Pre-Installation Considerations
FHWA Roadway Departure Technology Transfer Roadside Safety Systems Installer Training
4-2 Session 4
Course Topics
Session 3 – Guardrail Design and Site-specific Installation Considerations
Session 4 – Pre-Installation Considerations
4-3 Session 4
Session 4 Objectives
Review project plans & specifications
Visit jobsite
Schedule manpower and equipment
Identify personnel safety needs
4-4 Session 4
Session 4 Outline
Preliminary Project Analysis – Contractor
Pre-installation Review – “Review Team”
Job Site Analysis
Vehicle and Equipment Analysis
Project Personnel Safety Analysis
4-5 Session 4
Preliminary Project Analysis
Receive, read, understand, and complete the contract or work order.
Mark project plans to include estimating notes and installation ideas to complete the project within estimate and on time.
Do a value engineering analysis of existing bid items. Notify engineer of possible changes to evaluate.
If acting as a subcontractor, call the prime contractor to coordinate scheduling.
4-6 Session 4
Pre-installation Review Guidelines
The following is an example of a Pre-installation Review that one State has done. Delaware may want to consider a similar program. See Technical Brief # 2.
4-7 Session 4
Pre-installation Review Guidelines
A pre-installation review is performed to ensure an optimal installation. These reviews are conducted on all interstate, expressway and/or other projects where federal oversight is being done.
4-8 Session 4
Pre-installation Review Guidelines
The “review team” would consist of the PennDOT Inspector-in-Charge, District guardrail Mentor, FHWA Representative and Contractor’s Representative.
Prior to the review the contractor must place temporary markers to indicate the locations of all permanent traffic barrier and end treatments.
4-9 Session 4
Pre-installation Review Guidelines
Reviews will look at the following items:
Barrier Length of need
End terminal/crash cushion selection
Slopes and grading
Miscellaneous – existing barriers to be removed, other locations within the project limits that need to be addressed, areas where barriers can be reduced or eliminated.
4-10 Session 4
Pre-installation Review Follow-Up
Revisions made through existing procedures.
Information transmitted to design as lessons learned.
Summaries annually for statewide action.
4-11 Session 4
Job Site Analysis: Site Visit
Check for existing conditions that may cause potential problems for field crews:
Culverts – check fill depth
Bridges – check for correctly formed wing walls (including correct pattern & depth for inserts).
Curbing/sidewalk - • Ask whether to take grade from roadway or from
curb/sidewalk. • Discuss liability for repair of sidewalk after post
installation.
4-12 Session 4
Job Site Analysis: Site Visit
Paved slopes Saw through paving before driving posts and patch
after posts are driven with in-kind material.
Ditches/Slopes Verify correct lateral placement
Site Grading Verify adequate recovery area exists.
A minimum of 3 working days before starting project, call the utility locator.
4-13 Session 4
Job Site Analysis
Other Critical / Last Minute Details:
Ensure proper traffic control will be provided.
Be aware of local labor service for employment if additional personnel is needed.
If material is taken from inventory, load now. If material requirements change, notify material supplier and confirm delivery date, time, location.
Let the prime contractor know you are mobilizing.
4-14 Session 4
Vehicle and Equipment Analysis Vehicles Crew truck with capability to transport men, material, and tools. 2-5 ton flat bed material hauler capable to pull a trailer.
Large rotating amber beacon or strobe lights mounted to each vehicle and clearly visible for 360-degrees around the vehicle (all vehicles including construction equipment)
Note that the road is closed as there is no traffic control
4-15 Session 4
Vehicle and Equipment Analysis
Primary Equipment 25-ton, 25-ft trailer to haul material and or equipment. Remote from operating station drop hammer or vibratory post driver.
• Other attachments: post puller, pressure auger, down hole hammer rock drill. Usually mounted on a 2-ton truck.
Arrow board, channelizing devices, truck mounted attenuator and temporary traffic control signs.
4-16 Session 4
Vehicle and Equipment Analysis
Specialized Equipment Backhoe Skid steer Forklift Knuckle boom truck Grass trimmer
All vehicles and equipment are subject to scheduled inspection and maintenance procedures and documentation.
4-17 Session 4
Project Personnel Safety Analysis
5 Areas Personal Protective Equipment Personnel Safety Procedures Identification of Procedures for
Hazardous Materials Crew Briefing Verification of Special Skills Certification
4-18 Session 4
Project Personnel Safety Analysis: Personal Protective Equipment
Mandatory safety equipment (unless otherwise directed by local agency) Head protection (hard hats) Eye protection (safety glasses) Foot protection (safety toe / composite) High visibility safety apparel (retroreflective vests) First aid kit in all crew trucks & all company
locations
Optional safety equipment Hand protection (gloves) Weather-related clothing (rain suit)
4-19 Session 4
Project Personnel Safety Analysis: Personnel Safety Procedures
Pre-hire, annual, and/or random drug testing?
Equipment operation
Emergency procedures Locate nearest hospital
Evacuation plans
Accident reporting Notification of insurance Report injuries
4-20 Session 4
Project Personnel Safety Analysis: Hazardous Materials
Identification of and procedures for Hazardous Materials Hazardous Materials Handbook (zinc poisoning from
oxygen and acetylene torch). Receiving and transporting of Hazardous Materials:
galvanized material, gasoline, diesel, hydraulic fluid, antifreeze, explosives and caps.
Schedule and amount of explosives (if used). Documentation of inventory. Material Safety Data Sheets (MSDS) / discuss with crew. Disposal of Hazardous Material (Uniform Hazardous
Waste Manifest).
4-21 Session 4
Project Personnel Safety Analysis: Crew Briefing Crew briefing
Plans Estimate notes and installation ideas Jobsite conditions Pre-trip inspection of equipment/loaded material Review reporting procedures Daily safety briefing Confirm crew understands by asking questions
4-22 Session 4
Project Personnel Safety Analysis: Special Skills Certification Verification of special skills certifications
Contractor’s license
Certified Installer certification (required by some DOTs)
CDL license
Equipment Operator license/certifications - company post driving training - fork lift training - backhoe training - skid steer training
Traffic control flagging certification
4-23 Session 4
Session 4 Outcomes
Interpret Plans and Specifications.
Visit Installation Site(s).
Schedule Manpower & Equipment Needed.
Ensure Adequate and Proper Safety Measures are Followed.