Page 1: Session 4: Pre-Installation Considerations · Session 4 . 4-5 . Preliminary Project Analysis Receive, read, understand, and complete the contract or work order. Mark project plans

4-1 Session 4

Session 4: Pre-Installation Considerations

FHWA Roadway Departure Technology Transfer Roadside Safety Systems Installer Training

Page 2: Session 4: Pre-Installation Considerations · Session 4 . 4-5 . Preliminary Project Analysis Receive, read, understand, and complete the contract or work order. Mark project plans

4-2 Session 4

Course Topics

Session 3 – Guardrail Design and Site-specific Installation Considerations

Session 4 – Pre-Installation Considerations

Page 3: Session 4: Pre-Installation Considerations · Session 4 . 4-5 . Preliminary Project Analysis Receive, read, understand, and complete the contract or work order. Mark project plans

4-3 Session 4

Session 4 Objectives

Review project plans & specifications

Visit jobsite

Schedule manpower and equipment

Identify personnel safety needs

Page 4: Session 4: Pre-Installation Considerations · Session 4 . 4-5 . Preliminary Project Analysis Receive, read, understand, and complete the contract or work order. Mark project plans

4-4 Session 4

Session 4 Outline

Preliminary Project Analysis – Contractor

Pre-installation Review – “Review Team”

Job Site Analysis

Vehicle and Equipment Analysis

Project Personnel Safety Analysis

Page 5: Session 4: Pre-Installation Considerations · Session 4 . 4-5 . Preliminary Project Analysis Receive, read, understand, and complete the contract or work order. Mark project plans

4-5 Session 4

Preliminary Project Analysis

Receive, read, understand, and complete the contract or work order.

Mark project plans to include estimating notes and installation ideas to complete the project within estimate and on time.

Do a value engineering analysis of existing bid items. Notify engineer of possible changes to evaluate.

If acting as a subcontractor, call the prime contractor to coordinate scheduling.

Page 6: Session 4: Pre-Installation Considerations · Session 4 . 4-5 . Preliminary Project Analysis Receive, read, understand, and complete the contract or work order. Mark project plans

4-6 Session 4

Pre-installation Review Guidelines

The following is an example of a Pre-installation Review that one State has done. Delaware may want to consider a similar program. See Technical Brief # 2.

Page 7: Session 4: Pre-Installation Considerations · Session 4 . 4-5 . Preliminary Project Analysis Receive, read, understand, and complete the contract or work order. Mark project plans

4-7 Session 4

Pre-installation Review Guidelines

A pre-installation review is performed to ensure an optimal installation. These reviews are conducted on all interstate, expressway and/or other projects where federal oversight is being done.

Page 8: Session 4: Pre-Installation Considerations · Session 4 . 4-5 . Preliminary Project Analysis Receive, read, understand, and complete the contract or work order. Mark project plans

4-8 Session 4

Pre-installation Review Guidelines

The “review team” would consist of the PennDOT Inspector-in-Charge, District guardrail Mentor, FHWA Representative and Contractor’s Representative.

Prior to the review the contractor must place temporary markers to indicate the locations of all permanent traffic barrier and end treatments.

Page 9: Session 4: Pre-Installation Considerations · Session 4 . 4-5 . Preliminary Project Analysis Receive, read, understand, and complete the contract or work order. Mark project plans

4-9 Session 4

Pre-installation Review Guidelines

Reviews will look at the following items:

Barrier Length of need

End terminal/crash cushion selection

Slopes and grading

Miscellaneous – existing barriers to be removed, other locations within the project limits that need to be addressed, areas where barriers can be reduced or eliminated.

Page 10: Session 4: Pre-Installation Considerations · Session 4 . 4-5 . Preliminary Project Analysis Receive, read, understand, and complete the contract or work order. Mark project plans

4-10 Session 4

Pre-installation Review Follow-Up

Revisions made through existing procedures.

Information transmitted to design as lessons learned.

Summaries annually for statewide action.

Page 11: Session 4: Pre-Installation Considerations · Session 4 . 4-5 . Preliminary Project Analysis Receive, read, understand, and complete the contract or work order. Mark project plans

4-11 Session 4

Job Site Analysis: Site Visit

Check for existing conditions that may cause potential problems for field crews:

Culverts – check fill depth

Bridges – check for correctly formed wing walls (including correct pattern & depth for inserts).

Curbing/sidewalk - • Ask whether to take grade from roadway or from

curb/sidewalk. • Discuss liability for repair of sidewalk after post

installation.

Page 12: Session 4: Pre-Installation Considerations · Session 4 . 4-5 . Preliminary Project Analysis Receive, read, understand, and complete the contract or work order. Mark project plans

4-12 Session 4

Job Site Analysis: Site Visit

Paved slopes Saw through paving before driving posts and patch

after posts are driven with in-kind material.

Ditches/Slopes Verify correct lateral placement

Site Grading Verify adequate recovery area exists.

A minimum of 3 working days before starting project, call the utility locator.

Page 13: Session 4: Pre-Installation Considerations · Session 4 . 4-5 . Preliminary Project Analysis Receive, read, understand, and complete the contract or work order. Mark project plans

4-13 Session 4

Job Site Analysis

Other Critical / Last Minute Details:

Ensure proper traffic control will be provided.

Be aware of local labor service for employment if additional personnel is needed.

If material is taken from inventory, load now. If material requirements change, notify material supplier and confirm delivery date, time, location.

Let the prime contractor know you are mobilizing.

Page 14: Session 4: Pre-Installation Considerations · Session 4 . 4-5 . Preliminary Project Analysis Receive, read, understand, and complete the contract or work order. Mark project plans

4-14 Session 4

Vehicle and Equipment Analysis Vehicles Crew truck with capability to transport men, material, and tools. 2-5 ton flat bed material hauler capable to pull a trailer.

Large rotating amber beacon or strobe lights mounted to each vehicle and clearly visible for 360-degrees around the vehicle (all vehicles including construction equipment)

Note that the road is closed as there is no traffic control

Page 15: Session 4: Pre-Installation Considerations · Session 4 . 4-5 . Preliminary Project Analysis Receive, read, understand, and complete the contract or work order. Mark project plans

4-15 Session 4

Vehicle and Equipment Analysis

Primary Equipment 25-ton, 25-ft trailer to haul material and or equipment. Remote from operating station drop hammer or vibratory post driver.

• Other attachments: post puller, pressure auger, down hole hammer rock drill. Usually mounted on a 2-ton truck.

Arrow board, channelizing devices, truck mounted attenuator and temporary traffic control signs.

Page 16: Session 4: Pre-Installation Considerations · Session 4 . 4-5 . Preliminary Project Analysis Receive, read, understand, and complete the contract or work order. Mark project plans

4-16 Session 4

Vehicle and Equipment Analysis

Specialized Equipment Backhoe Skid steer Forklift Knuckle boom truck Grass trimmer

All vehicles and equipment are subject to scheduled inspection and maintenance procedures and documentation.

Page 17: Session 4: Pre-Installation Considerations · Session 4 . 4-5 . Preliminary Project Analysis Receive, read, understand, and complete the contract or work order. Mark project plans

4-17 Session 4

Project Personnel Safety Analysis

5 Areas Personal Protective Equipment Personnel Safety Procedures Identification of Procedures for

Hazardous Materials Crew Briefing Verification of Special Skills Certification

Page 18: Session 4: Pre-Installation Considerations · Session 4 . 4-5 . Preliminary Project Analysis Receive, read, understand, and complete the contract or work order. Mark project plans

4-18 Session 4

Project Personnel Safety Analysis: Personal Protective Equipment

Mandatory safety equipment (unless otherwise directed by local agency) Head protection (hard hats) Eye protection (safety glasses) Foot protection (safety toe / composite) High visibility safety apparel (retroreflective vests) First aid kit in all crew trucks & all company

locations

Optional safety equipment Hand protection (gloves) Weather-related clothing (rain suit)

Page 19: Session 4: Pre-Installation Considerations · Session 4 . 4-5 . Preliminary Project Analysis Receive, read, understand, and complete the contract or work order. Mark project plans

4-19 Session 4

Project Personnel Safety Analysis: Personnel Safety Procedures

Pre-hire, annual, and/or random drug testing?

Equipment operation

Emergency procedures Locate nearest hospital

Evacuation plans

Accident reporting Notification of insurance Report injuries

Page 20: Session 4: Pre-Installation Considerations · Session 4 . 4-5 . Preliminary Project Analysis Receive, read, understand, and complete the contract or work order. Mark project plans

4-20 Session 4

Project Personnel Safety Analysis: Hazardous Materials

Identification of and procedures for Hazardous Materials Hazardous Materials Handbook (zinc poisoning from

oxygen and acetylene torch). Receiving and transporting of Hazardous Materials:

galvanized material, gasoline, diesel, hydraulic fluid, antifreeze, explosives and caps.

Schedule and amount of explosives (if used). Documentation of inventory. Material Safety Data Sheets (MSDS) / discuss with crew. Disposal of Hazardous Material (Uniform Hazardous

Waste Manifest).

Page 21: Session 4: Pre-Installation Considerations · Session 4 . 4-5 . Preliminary Project Analysis Receive, read, understand, and complete the contract or work order. Mark project plans

4-21 Session 4

Project Personnel Safety Analysis: Crew Briefing Crew briefing

Plans Estimate notes and installation ideas Jobsite conditions Pre-trip inspection of equipment/loaded material Review reporting procedures Daily safety briefing Confirm crew understands by asking questions

Page 22: Session 4: Pre-Installation Considerations · Session 4 . 4-5 . Preliminary Project Analysis Receive, read, understand, and complete the contract or work order. Mark project plans

4-22 Session 4

Project Personnel Safety Analysis: Special Skills Certification Verification of special skills certifications

Contractor’s license

Certified Installer certification (required by some DOTs)

CDL license

Equipment Operator license/certifications - company post driving training - fork lift training - backhoe training - skid steer training

Traffic control flagging certification

Page 23: Session 4: Pre-Installation Considerations · Session 4 . 4-5 . Preliminary Project Analysis Receive, read, understand, and complete the contract or work order. Mark project plans

4-23 Session 4

Session 4 Outcomes

Interpret Plans and Specifications.

Visit Installation Site(s).

Schedule Manpower & Equipment Needed.

Ensure Adequate and Proper Safety Measures are Followed.