sanjiv shah underground excavations at chep

Upload: saphal-lamichhane

Post on 06-Jul-2018

220 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/17/2019 Sanjiv Shah Underground Excavations at CHEP

    1/77

    UNDERGROUND EXCAVATIONS AT

    CHAMELIYA HYRDOELECTRIC PROJECT:

    CASE STUDY

    DR. SANJIV SHAH

    SHAH CONSULT INTERNATIONAL (P.) LTD.

  • 8/17/2019 Sanjiv Shah Underground Excavations at CHEP

    2/77

    PROJECT DETAILS

  • 8/17/2019 Sanjiv Shah Underground Excavations at CHEP

    3/77

    LOCATION

    Hydroelectric project:

    Darchula District,

    Far-western Development

    Region

    960 km from Kathmandu

    Transmission line:

    Darchula, Baitadi, Dadeldhura,

    Doti & Kailali Districts

    131 km long, 132 kV

  • 8/17/2019 Sanjiv Shah Underground Excavations at CHEP

    4/77

    SALIENT FEATURES

    Installed capacity: 30 MW

    Scheme: PROR, with six hours daily peaking

    Design discharge: 36 m3/s

    Gross head: 103.7 m

    Net head: 94 m

    Average annual energy: 184.2 GWh

  • 8/17/2019 Sanjiv Shah Underground Excavations at CHEP

    5/77

    PROJECT LAYOUT

  • 8/17/2019 Sanjiv Shah Underground Excavations at CHEP

    6/77

    PRINCIPAL COMPONENTS

    Dam Concrete gravity, 54 m high, 2 radial gatesStilling Basin Horizontal, 54 m long, 17 m wide

    Diversion Tunnel 210 m long, 4.2 m dia., inverted D-shaped

    Intake Two side intakes, orifice type, 3 x 8 m each

    Desanding Basin Two underground basins, 105 x 12 x 25 m each

    Headrace Tunnel 4.067 km, horseshoe shape, 5.2 and 4.2 m dia.

    Surge Shaft Restricted orifice 8 m dia., 48 m high

    Vertical Shaft 72 m high, 3.9 m dia., concrete lined

    Penstock Tunnel Concrete/steel lined, 384 m long, 3.7~2.5~1.8 m dia.

    Powerhouse Semi-underground, 37.5 x 23.5 x 27.4 m

    Tailrace Box culvert, 703 m

    Turbine Francis, 2 x 15 MW

    Switchyard Outdoor conventional, 57 m x 47 m

    Transmission Line 132 kV, 131 km single phase to Attariya

  • 8/17/2019 Sanjiv Shah Underground Excavations at CHEP

    7/77

    PROJECT REALITIES

    CHEP: 30 MW project, but complicated civil structures

    Highest concrete gravity dam in Nepal (54 m high vs. 43 m at

    KGAA and 52 m at MMHEP)

    Two underground desanding basins (vs. three at MMHEP)

    4 km headrace tunnel through probably the poorest ground

    conditions encountered in Nepali hydropower projects

    Several underground structures (surge shaft, vertical shaft,horizontal penstock tunnel) in poor rock

    162 m high powerhouse back-slope (only other example in

    Nepal: desanding basin slope at KGAA)

  • 8/17/2019 Sanjiv Shah Underground Excavations at CHEP

    8/77

    CHRONOLOGY

    1991 Project identified by NEA

    1993 Potential confirmed by JICA’s master plan study

    1996 Feasibility study through SADF/NIDC

    1997 - 98 Upgraded feasibility study by NEADec 2001 Detailed design and tender documents

    Jan 10, 2007 Mobilization of civil contractor

    May 2007 Start of major civil works

    Jun 1, 2008 Start of headrace tunnel excavationDec 2, 2009 First river diversion

    Apr 27, 2010 First concrete pour in dam

    Jun 15, 2010 First concrete pour in powerhouse

    May 12, 2012 Headrace tunnel breakthrough

  • 8/17/2019 Sanjiv Shah Underground Excavations at CHEP

    9/77

    PRESENT STATUS

  • 8/17/2019 Sanjiv Shah Underground Excavations at CHEP

    10/77

    DIVERSION DAM

  • 8/17/2019 Sanjiv Shah Underground Excavations at CHEP

    11/77

    DIVERSION DAM

  • 8/17/2019 Sanjiv Shah Underground Excavations at CHEP

    12/77

    INTAKE

  • 8/17/2019 Sanjiv Shah Underground Excavations at CHEP

    13/77

    DESANDING BASIN

  • 8/17/2019 Sanjiv Shah Underground Excavations at CHEP

    14/77

    HRT CONFLUENCE

  • 8/17/2019 Sanjiv Shah Underground Excavations at CHEP

    15/77

    HRT CONCRETE LINING

  • 8/17/2019 Sanjiv Shah Underground Excavations at CHEP

    16/77

    HEADRACE TUNNEL

  • 8/17/2019 Sanjiv Shah Underground Excavations at CHEP

    17/77

    POWERHOUSE

  • 8/17/2019 Sanjiv Shah Underground Excavations at CHEP

    18/77

    POWERHOUSE

  • 8/17/2019 Sanjiv Shah Underground Excavations at CHEP

    19/77

    TAILRACE

  • 8/17/2019 Sanjiv Shah Underground Excavations at CHEP

    20/77

    SWITCHYARD

  • 8/17/2019 Sanjiv Shah Underground Excavations at CHEP

    21/77

    UNDERGROUND STRUCTURES

  • 8/17/2019 Sanjiv Shah Underground Excavations at CHEP

    22/77

    INVESTIGATIONS

    Geological investigations between 1996 and 2001

    Headrace tunnel: surface geological investigations

    Limited core drilling and seismic resistivity surveys

    Structure Core Drilling SeismicSurvey (m)Planned (m) Actual (m) Angle

    Desanding Basin 115 50 Horizontal -

    Headrace Tunnel - 35 Vertical 295

    Surge Shaft 150 39.5/35.5 Vertical 115

    Penstock - - - 805

  • 8/17/2019 Sanjiv Shah Underground Excavations at CHEP

    23/77

    TUNNELS

    Structure Shape L (m) Dia. (m) Lining

    Diversion tunnel Inverted D 203 4.0 S

    Connecting tunnel No. 1 Inverted D 127 3.4 C

    Connecting tunnel No. 2 Inverted D 116 3.4 CAccess tunnel to DB Inverted D 105 4.5 S

    Flushing tunnel Inverted D 132 3.0 S/C

    Headrace tunnel Horse-shoe 4,067 5.2/4.6 S/C

    Adit No. 1 Inverted D 305 3.5 S

    Adit No. 2 Inverted D 214 3.5 S

    Adit No. 3 Inverted D 284 3.5 S

    Aeration tunnel Inverted D 156 3.0 S

    Penstock tunnel Horse-shoe 372 3.9/3.7 C/St

  • 8/17/2019 Sanjiv Shah Underground Excavations at CHEP

    24/77

    CAVERNS & SHAFTS

    Structure L (m) W/D (m) H (m) Lining

    Desanding basin No. 1 105 12 25 Concrete

    Desanding basin No. 2 105 12 25 Concrete

    Surge shaft 8.0 48 ConcreteVertical shaft 3.9 72 Concrete

    Total linear length of excavations 6,749 m

  • 8/17/2019 Sanjiv Shah Underground Excavations at CHEP

    25/77

    PREDICTED VS ACTUAL GEOLOGY

    Geological conditions during construction significantly

    different from those predicted in design

    Rock mass substantially weaker, especially in lower half of

    project area

    Several large shear zones and faults, mostly unpredicted or

    incorrectly predicted

    Orientations of bedding planes and joints incorrect

    Squeezing rock mass between Adit Nos. 2 and 3 not

    anticipated

  • 8/17/2019 Sanjiv Shah Underground Excavations at CHEP

    26/77

    STRUCTURES IN HEADWORKS

  • 8/17/2019 Sanjiv Shah Underground Excavations at CHEP

    27/77

    DESANDING BASIN

  • 8/17/2019 Sanjiv Shah Underground Excavations at CHEP

    28/77

    HEADRACE TUNNEL

  • 8/17/2019 Sanjiv Shah Underground Excavations at CHEP

    29/77

    HEADRACE TUNNEL

  • 8/17/2019 Sanjiv Shah Underground Excavations at CHEP

    30/77

    HEADRACE TUNNEL SUPPORTS

  • 8/17/2019 Sanjiv Shah Underground Excavations at CHEP

    31/77

    UG STRUCTURES AROUND PH

  • 8/17/2019 Sanjiv Shah Underground Excavations at CHEP

    32/77

    HEADRACE TUNNEL GEOLOGY

  • 8/17/2019 Sanjiv Shah Underground Excavations at CHEP

    33/77

    ROCK TYPES

    SN Region Rock

    1 Connecting tunnel desanding basin,

    bifurcation & initial part of HRT

    Silicious dolomite

    2 Adit No. 1 area Diamictite/ meta sandstone

    3 Adit No. 1 D/S Black slate

    4 Adit No. 1 D/S & Adit No. 2 U/S Gray dolomite

    5 Adit No. 2 D/S Phyllite-Dolomite inter-bedded

    6 Adit No. 2 D/S & Adit No. 3 U/S Talcosic dolomite

    7 Adit No. 3 U/S Talcosic phyllite

    8 Surge shaft, vertical shaft &

    penstock tunnel

    Limestone and gray phyllite

  • 8/17/2019 Sanjiv Shah Underground Excavations at CHEP

    34/77

    IMPACTS OF POOR GEOLOGY

    Consequences:

    Higher levels of supports installed

    Frequent collapses and debris flows

    Large water inflows

    Squeezing in 843 m

    Frequent stoppages

    Reduced rate of advancement

    Planned: 2 – 2.5 m/day

    Actual: 0.6 – 1.4 m/day at different faces, 0.37 m/day in

    squeezing section

    Delays and claims

  • 8/17/2019 Sanjiv Shah Underground Excavations at CHEP

    35/77

    SQUEEZING IN HEADRACETUNNEL

  • 8/17/2019 Sanjiv Shah Underground Excavations at CHEP

    36/77

    HRT EXCAVATION

    Commencement of HRT excavation:

    From Adit No. 2: June 2008

    From Adit No. 3: August 2008

    From Adit No. 1: March 2009

    Drill and blast method, with full-face excavation

    Initial 22 months of construction: no major problems barring a

    few incidences of collapses, heavy water ingress and minor

    squeezing

  • 8/17/2019 Sanjiv Shah Underground Excavations at CHEP

    37/77

    TUNNEL SQUEEZING

    Squeezing in 843 m of headrace tunnel between Adits 2 & 3

    Adit No. 2:

    Severe to extremely severe squeezing (20 to 40%)

    Deformation of steel ribs, cracking of shotcrete

    Large mud flows

    Work halted for over 9 months due to monsoon and mud flow

    clearance

    Adit No. 3: Large deformations in crown and sidewalls

    Severe to extremely severe squeezing (10 to 30%)

  • 8/17/2019 Sanjiv Shah Underground Excavations at CHEP

    38/77

    TUNNEL SQUEEZING – ADIT 2 D/S

  • 8/17/2019 Sanjiv Shah Underground Excavations at CHEP

    39/77

    TUNNEL SQUEEZING – ADIT 2 D/S

  • 8/17/2019 Sanjiv Shah Underground Excavations at CHEP

    40/77

    TUNNEL SQUEEZING – ADIT 2 D/S

  • 8/17/2019 Sanjiv Shah Underground Excavations at CHEP

    41/77

    TUNNEL SQUEEZING – ADIT 3 U/S

  • 8/17/2019 Sanjiv Shah Underground Excavations at CHEP

    42/77

    TUNNEL SQUEEZING – ADIT 3 U/S

  • 8/17/2019 Sanjiv Shah Underground Excavations at CHEP

    43/77

    PROBLEMS IN TUNNELING

    Debris Flow Rock fall

  • 8/17/2019 Sanjiv Shah Underground Excavations at CHEP

    44/77

    DEBRIS FLOW

    Water & gravel flow Mud flow through portal

  • 8/17/2019 Sanjiv Shah Underground Excavations at CHEP

    45/77

    MAJOR CAUSES

    Overburden only between 174 and 279 m, but poor geology

    Ch. 3+102.5 and 3+592.7 m

    Fault zone with highly crushed rock mass of grey to white talcosic

    dolomite with phyllite intercalation Bedding planes nearly parallel to tunnel (deviation ~ 11°)

    Large ground water inflow

    Ch. 3+659.4 and 3+945 m

    Mainly composed of highly weathered talcosic phyllite with veryrare intercalation of white to grey, thinly bedded dolomite or

    quartzite

    Bedding planes vertical, nearly parallel to tunnel (deviation ~ 11°)

    Large ground water inflow

  • 8/17/2019 Sanjiv Shah Underground Excavations at CHEP

    46/77

    GEOLOGY BETWEEN ADITS 2 & 3

  • 8/17/2019 Sanjiv Shah Underground Excavations at CHEP

    47/77

    GEOLOGY BETWEEN ADITS 2 & 3

  • 8/17/2019 Sanjiv Shah Underground Excavations at CHEP

    48/77

    SEVERITY OF SQUEEZING

  • 8/17/2019 Sanjiv Shah Underground Excavations at CHEP

    49/77

    INITIAL ATTEMPTS FOR SOLUTION

    Various methods for solution attempted

    Top heading and benching

    Manual excavation

    Fore poling

    Placement of closely spaced steel ribs

    Drainage

    Invert strengthening (invert strut and concreting)

    Implementation difficult due to poor ground conditions

    Sequential excavation: misalignment of steel rib crown & legs

    Invert strengthening: Not possible due to slushy conditions,

    immediate sidewall squeezing & floor heaving following invert

    excavation, severe buckling

  • 8/17/2019 Sanjiv Shah Underground Excavations at CHEP

    50/77

    OPTIONS EVALUATED

    • Over-excavation

    • To gain sufficient time to install supports

    • Led to further collapses

    Tunnel realignment• Large lateral extent of poor rock mass

    • Diversion would run parallel to bedding planes under increasingoverburden, creating even greater problems in excavation

  • 8/17/2019 Sanjiv Shah Underground Excavations at CHEP

    51/77

    ENGINEER’S DECISION

    Proceed further with tunnel excavation along designed

    alignment & repair tunnel after breakthrough

    Reasons:

    Tunnel excavation & deformation would result in significant stressrelaxation in surrounding rock mass

    Breakthrough would eliminate all tunnel faces that had

    repeatedly been serving as sources of large debris flows

    Breakthrough would drain surrounding rock mass

  • 8/17/2019 Sanjiv Shah Underground Excavations at CHEP

    52/77

    EXCAVATION PROCEDURE

    Fore-poling to create protective shield

    Sequential excavation (heading & benching)

    Sealing tunnel faces after to prevent collapses or debris flows

    R5 and R6 supports with steel ribs but no rock bolts

    Locations of excessive squeezing: double layer of 100 mmsteel ribs with invert struts

    Temporary supports

    Weep holes to drain out groundwater behind crown & wall

    Limited grouting at locations with crushed rock mass

  • 8/17/2019 Sanjiv Shah Underground Excavations at CHEP

    53/77

    SQUEEZING TREATMENT DESIGN

    • Various alternatives considered

    • Steel lining

    • 4.9 m steel liners embedded in plain or reinforced concrete

    Could fit within deformed tunnel profile at most places, requiringminimal reshaping at places with excessive squeezing

    • Transportation, assembly and quality control extremely difficult

    • Exorbitant cost (approx. Rs. 2.05 billion)

    • Concrete lining

    • Concrete lining after reshaping deformed• Performed sequentially, extremely slow (almost two years

    provided no major stoppages)

  • 8/17/2019 Sanjiv Shah Underground Excavations at CHEP

    54/77

    SQUEEZING TREATMENT DESIGN

    Engineer designed treatment plan based on case histories

    (e.g. Yacambu-Quibor tunnel) and information gained through

    trial sections

    Tunnel categorized into three typical zones based on observed

    maximum strains Circular cross-section with 5.4 m finished diameter

    Supports for each zone designed using Phase 2

    Reinforced shotcrete lining selected because of shorter

    installation time

    Steel ribs with yielding joints in zones of excessive squeezing topermit stress relaxation and ensure safe working conditions

  • 8/17/2019 Sanjiv Shah Underground Excavations at CHEP

    55/77

    PHASE 2 ANALYSIS

    Initial values of rock mass properties (GSI, mi and sci) selected from

    published charts

    Back analysis performed to adjust the material parameters so as to

    match the computed and observed deformations

    Rock mass was modeled as an elastic-perfectly plastic material

    Analyses showed extensive stress relaxation around tunnel up to

    distance of at least 2 to 2.5 times tunnel diameter

    Supports for each zone designed using the various support facilitiesavailable in Phase 2

    Stage-wise modeling performed to simulate pre-existing

    deformations and supports were installed at appropriate stages

  • 8/17/2019 Sanjiv Shah Underground Excavations at CHEP

    56/77

    DESIGN PROFILE

    SQUEEZED PROFILE

    TREATED PROFILE

    BASIC APPROACH

  • 8/17/2019 Sanjiv Shah Underground Excavations at CHEP

    57/77

    SQUEEZING TREATMENT DESIGN

    Zone A: Squeezing extremely severe, on-going

    Total length: 418 m

    Over-excavation to 6.6 m dia. circular shape

    Steel ribs with yielding joint

    60 mm reinforced shotcrete

    Zone B: Squeezing extremely severe but stable

    Total length: 226 m

    Over-excavation to 6.4 m dia. circular shape

    40 mm thick reinforced shotcrete

    Zone C: Squeezing very severe but stable

    Total length: 198 m

    Over-excavation to 6.3 m dia. circular shape

    35 mm thick reinforced shotcrete

  • 8/17/2019 Sanjiv Shah Underground Excavations at CHEP

    58/77

    TYPICAL DESIGNS

  • 8/17/2019 Sanjiv Shah Underground Excavations at CHEP

    59/77

    TYPICAL YIELDING SUPPORT

  • 8/17/2019 Sanjiv Shah Underground Excavations at CHEP

    60/77

    POE RECOMMENDATIONS

    Visited site from December 8 to 11, 2013

    Observations:

    Tunneling performed under extremely poor geological conditions

    Observed squeezing was not “classical” squeezing Engineer’s approach to complete tunnel excavation and then

    treat the squeezed section correct

    Closed circular section with shotcrete looked promising and

    should be maintained

    Yielding steel sets were a very meaningful ground supportmeasure for squeezing rock conditions

    Recommendation

    Added Type D support (Type A without steel rib)

  • 8/17/2019 Sanjiv Shah Underground Excavations at CHEP

    61/77

    ORIGINAL CONDITION

  • 8/17/2019 Sanjiv Shah Underground Excavations at CHEP

    62/77

    RE-EXCAVATION (MANUAL)

  • 8/17/2019 Sanjiv Shah Underground Excavations at CHEP

    63/77

    RE-EXCAVATION (MACHINE)

  • 8/17/2019 Sanjiv Shah Underground Excavations at CHEP

    64/77

    STEEL RIB INSTALLATION

  • 8/17/2019 Sanjiv Shah Underground Excavations at CHEP

    65/77

    FIRST STAGE SHOTCRETE

  • 8/17/2019 Sanjiv Shah Underground Excavations at CHEP

    66/77

    STEEL BAR PLACEMENT

  • 8/17/2019 Sanjiv Shah Underground Excavations at CHEP

    67/77

    SHOTCRETING

  • 8/17/2019 Sanjiv Shah Underground Excavations at CHEP

    68/77

    FINAL SECTION

  • 8/17/2019 Sanjiv Shah Underground Excavations at CHEP

    69/77

    IMPLEMENTATION OF TREATMENT

    • Treatment started in March 2013

    • Difficult & slow process, but no major problems encountered

    • 67.5% treatment complete

    Zone Total (m) Complete (m) Remaining (m)

    A 283.2 248.1 31.1

    B 277.2 223.1 54.1

    C 181.9 97.2 84.7

    D 100.0 0.00 100.0

    Total 842.3 569.4 273.9

  • 8/17/2019 Sanjiv Shah Underground Excavations at CHEP

    70/77

    PROBLEMS ENCOUNTERED

  • 8/17/2019 Sanjiv Shah Underground Excavations at CHEP

    71/77

    PROBLEMS ENCOUNTERED

  • 8/17/2019 Sanjiv Shah Underground Excavations at CHEP

    72/77

    VERTICAL SHAFT &PENSTOCK TUNNEL

  • 8/17/2019 Sanjiv Shah Underground Excavations at CHEP

    73/77

    HORIZONTAL PENSTOCK TUNNEL

    Tunnel length: 300 m

    Only 160 m provided

    with steel lining

    Large debris flow, about

    1,700 cu. m

    Indication of very poor

    geological conditions

  • 8/17/2019 Sanjiv Shah Underground Excavations at CHEP

    74/77

    VERTICAL SHAFT

    Large cavity around shaft

    Approx. 25 x 8 x 5 m

    Crushed material

    Concrete lininginadequate

    Leakage

    Slope instabilities

    Steel lining proposed

  • 8/17/2019 Sanjiv Shah Underground Excavations at CHEP

    75/77

    VERTICAL SHAFT

  • 8/17/2019 Sanjiv Shah Underground Excavations at CHEP

    76/77

    PENSTOCK & SHAFT LINING

    • Original design: penstock concrete and steel lined, verticalshaft concrete lined

    • Revised design: steel lining required over entire length due topoor geological conditions (large cavities)

    • Concrete lining without adequate rock support may burst underwater hammer

    • Water leakage through cavities

    • Further revision based on POE recommendations:

    Concrete lining (“water tight”)• Geo-membrane layer to prevent water leakage

  • 8/17/2019 Sanjiv Shah Underground Excavations at CHEP

    77/77

    THANK YOU!