sanjiv shah underground excavations at chep
TRANSCRIPT
-
8/17/2019 Sanjiv Shah Underground Excavations at CHEP
1/77
UNDERGROUND EXCAVATIONS AT
CHAMELIYA HYRDOELECTRIC PROJECT:
CASE STUDY
DR. SANJIV SHAH
SHAH CONSULT INTERNATIONAL (P.) LTD.
-
8/17/2019 Sanjiv Shah Underground Excavations at CHEP
2/77
PROJECT DETAILS
-
8/17/2019 Sanjiv Shah Underground Excavations at CHEP
3/77
LOCATION
Hydroelectric project:
Darchula District,
Far-western Development
Region
960 km from Kathmandu
Transmission line:
Darchula, Baitadi, Dadeldhura,
Doti & Kailali Districts
131 km long, 132 kV
-
8/17/2019 Sanjiv Shah Underground Excavations at CHEP
4/77
SALIENT FEATURES
Installed capacity: 30 MW
Scheme: PROR, with six hours daily peaking
Design discharge: 36 m3/s
Gross head: 103.7 m
Net head: 94 m
Average annual energy: 184.2 GWh
-
8/17/2019 Sanjiv Shah Underground Excavations at CHEP
5/77
PROJECT LAYOUT
-
8/17/2019 Sanjiv Shah Underground Excavations at CHEP
6/77
PRINCIPAL COMPONENTS
Dam Concrete gravity, 54 m high, 2 radial gatesStilling Basin Horizontal, 54 m long, 17 m wide
Diversion Tunnel 210 m long, 4.2 m dia., inverted D-shaped
Intake Two side intakes, orifice type, 3 x 8 m each
Desanding Basin Two underground basins, 105 x 12 x 25 m each
Headrace Tunnel 4.067 km, horseshoe shape, 5.2 and 4.2 m dia.
Surge Shaft Restricted orifice 8 m dia., 48 m high
Vertical Shaft 72 m high, 3.9 m dia., concrete lined
Penstock Tunnel Concrete/steel lined, 384 m long, 3.7~2.5~1.8 m dia.
Powerhouse Semi-underground, 37.5 x 23.5 x 27.4 m
Tailrace Box culvert, 703 m
Turbine Francis, 2 x 15 MW
Switchyard Outdoor conventional, 57 m x 47 m
Transmission Line 132 kV, 131 km single phase to Attariya
-
8/17/2019 Sanjiv Shah Underground Excavations at CHEP
7/77
PROJECT REALITIES
CHEP: 30 MW project, but complicated civil structures
Highest concrete gravity dam in Nepal (54 m high vs. 43 m at
KGAA and 52 m at MMHEP)
Two underground desanding basins (vs. three at MMHEP)
4 km headrace tunnel through probably the poorest ground
conditions encountered in Nepali hydropower projects
Several underground structures (surge shaft, vertical shaft,horizontal penstock tunnel) in poor rock
162 m high powerhouse back-slope (only other example in
Nepal: desanding basin slope at KGAA)
-
8/17/2019 Sanjiv Shah Underground Excavations at CHEP
8/77
CHRONOLOGY
1991 Project identified by NEA
1993 Potential confirmed by JICA’s master plan study
1996 Feasibility study through SADF/NIDC
1997 - 98 Upgraded feasibility study by NEADec 2001 Detailed design and tender documents
Jan 10, 2007 Mobilization of civil contractor
May 2007 Start of major civil works
Jun 1, 2008 Start of headrace tunnel excavationDec 2, 2009 First river diversion
Apr 27, 2010 First concrete pour in dam
Jun 15, 2010 First concrete pour in powerhouse
May 12, 2012 Headrace tunnel breakthrough
-
8/17/2019 Sanjiv Shah Underground Excavations at CHEP
9/77
PRESENT STATUS
-
8/17/2019 Sanjiv Shah Underground Excavations at CHEP
10/77
DIVERSION DAM
-
8/17/2019 Sanjiv Shah Underground Excavations at CHEP
11/77
DIVERSION DAM
-
8/17/2019 Sanjiv Shah Underground Excavations at CHEP
12/77
INTAKE
-
8/17/2019 Sanjiv Shah Underground Excavations at CHEP
13/77
DESANDING BASIN
-
8/17/2019 Sanjiv Shah Underground Excavations at CHEP
14/77
HRT CONFLUENCE
-
8/17/2019 Sanjiv Shah Underground Excavations at CHEP
15/77
HRT CONCRETE LINING
-
8/17/2019 Sanjiv Shah Underground Excavations at CHEP
16/77
HEADRACE TUNNEL
-
8/17/2019 Sanjiv Shah Underground Excavations at CHEP
17/77
POWERHOUSE
-
8/17/2019 Sanjiv Shah Underground Excavations at CHEP
18/77
POWERHOUSE
-
8/17/2019 Sanjiv Shah Underground Excavations at CHEP
19/77
TAILRACE
-
8/17/2019 Sanjiv Shah Underground Excavations at CHEP
20/77
SWITCHYARD
-
8/17/2019 Sanjiv Shah Underground Excavations at CHEP
21/77
UNDERGROUND STRUCTURES
-
8/17/2019 Sanjiv Shah Underground Excavations at CHEP
22/77
INVESTIGATIONS
Geological investigations between 1996 and 2001
Headrace tunnel: surface geological investigations
Limited core drilling and seismic resistivity surveys
Structure Core Drilling SeismicSurvey (m)Planned (m) Actual (m) Angle
Desanding Basin 115 50 Horizontal -
Headrace Tunnel - 35 Vertical 295
Surge Shaft 150 39.5/35.5 Vertical 115
Penstock - - - 805
-
8/17/2019 Sanjiv Shah Underground Excavations at CHEP
23/77
TUNNELS
Structure Shape L (m) Dia. (m) Lining
Diversion tunnel Inverted D 203 4.0 S
Connecting tunnel No. 1 Inverted D 127 3.4 C
Connecting tunnel No. 2 Inverted D 116 3.4 CAccess tunnel to DB Inverted D 105 4.5 S
Flushing tunnel Inverted D 132 3.0 S/C
Headrace tunnel Horse-shoe 4,067 5.2/4.6 S/C
Adit No. 1 Inverted D 305 3.5 S
Adit No. 2 Inverted D 214 3.5 S
Adit No. 3 Inverted D 284 3.5 S
Aeration tunnel Inverted D 156 3.0 S
Penstock tunnel Horse-shoe 372 3.9/3.7 C/St
-
8/17/2019 Sanjiv Shah Underground Excavations at CHEP
24/77
CAVERNS & SHAFTS
Structure L (m) W/D (m) H (m) Lining
Desanding basin No. 1 105 12 25 Concrete
Desanding basin No. 2 105 12 25 Concrete
Surge shaft 8.0 48 ConcreteVertical shaft 3.9 72 Concrete
Total linear length of excavations 6,749 m
-
8/17/2019 Sanjiv Shah Underground Excavations at CHEP
25/77
PREDICTED VS ACTUAL GEOLOGY
Geological conditions during construction significantly
different from those predicted in design
Rock mass substantially weaker, especially in lower half of
project area
Several large shear zones and faults, mostly unpredicted or
incorrectly predicted
Orientations of bedding planes and joints incorrect
Squeezing rock mass between Adit Nos. 2 and 3 not
anticipated
-
8/17/2019 Sanjiv Shah Underground Excavations at CHEP
26/77
STRUCTURES IN HEADWORKS
-
8/17/2019 Sanjiv Shah Underground Excavations at CHEP
27/77
DESANDING BASIN
-
8/17/2019 Sanjiv Shah Underground Excavations at CHEP
28/77
HEADRACE TUNNEL
-
8/17/2019 Sanjiv Shah Underground Excavations at CHEP
29/77
HEADRACE TUNNEL
-
8/17/2019 Sanjiv Shah Underground Excavations at CHEP
30/77
HEADRACE TUNNEL SUPPORTS
-
8/17/2019 Sanjiv Shah Underground Excavations at CHEP
31/77
UG STRUCTURES AROUND PH
-
8/17/2019 Sanjiv Shah Underground Excavations at CHEP
32/77
HEADRACE TUNNEL GEOLOGY
-
8/17/2019 Sanjiv Shah Underground Excavations at CHEP
33/77
ROCK TYPES
SN Region Rock
1 Connecting tunnel desanding basin,
bifurcation & initial part of HRT
Silicious dolomite
2 Adit No. 1 area Diamictite/ meta sandstone
3 Adit No. 1 D/S Black slate
4 Adit No. 1 D/S & Adit No. 2 U/S Gray dolomite
5 Adit No. 2 D/S Phyllite-Dolomite inter-bedded
6 Adit No. 2 D/S & Adit No. 3 U/S Talcosic dolomite
7 Adit No. 3 U/S Talcosic phyllite
8 Surge shaft, vertical shaft &
penstock tunnel
Limestone and gray phyllite
-
8/17/2019 Sanjiv Shah Underground Excavations at CHEP
34/77
IMPACTS OF POOR GEOLOGY
Consequences:
Higher levels of supports installed
Frequent collapses and debris flows
Large water inflows
Squeezing in 843 m
Frequent stoppages
Reduced rate of advancement
Planned: 2 – 2.5 m/day
Actual: 0.6 – 1.4 m/day at different faces, 0.37 m/day in
squeezing section
Delays and claims
-
8/17/2019 Sanjiv Shah Underground Excavations at CHEP
35/77
SQUEEZING IN HEADRACETUNNEL
-
8/17/2019 Sanjiv Shah Underground Excavations at CHEP
36/77
HRT EXCAVATION
Commencement of HRT excavation:
From Adit No. 2: June 2008
From Adit No. 3: August 2008
From Adit No. 1: March 2009
Drill and blast method, with full-face excavation
Initial 22 months of construction: no major problems barring a
few incidences of collapses, heavy water ingress and minor
squeezing
-
8/17/2019 Sanjiv Shah Underground Excavations at CHEP
37/77
TUNNEL SQUEEZING
Squeezing in 843 m of headrace tunnel between Adits 2 & 3
Adit No. 2:
Severe to extremely severe squeezing (20 to 40%)
Deformation of steel ribs, cracking of shotcrete
Large mud flows
Work halted for over 9 months due to monsoon and mud flow
clearance
Adit No. 3: Large deformations in crown and sidewalls
Severe to extremely severe squeezing (10 to 30%)
-
8/17/2019 Sanjiv Shah Underground Excavations at CHEP
38/77
TUNNEL SQUEEZING – ADIT 2 D/S
-
8/17/2019 Sanjiv Shah Underground Excavations at CHEP
39/77
TUNNEL SQUEEZING – ADIT 2 D/S
-
8/17/2019 Sanjiv Shah Underground Excavations at CHEP
40/77
TUNNEL SQUEEZING – ADIT 2 D/S
-
8/17/2019 Sanjiv Shah Underground Excavations at CHEP
41/77
TUNNEL SQUEEZING – ADIT 3 U/S
-
8/17/2019 Sanjiv Shah Underground Excavations at CHEP
42/77
TUNNEL SQUEEZING – ADIT 3 U/S
-
8/17/2019 Sanjiv Shah Underground Excavations at CHEP
43/77
PROBLEMS IN TUNNELING
Debris Flow Rock fall
-
8/17/2019 Sanjiv Shah Underground Excavations at CHEP
44/77
DEBRIS FLOW
Water & gravel flow Mud flow through portal
-
8/17/2019 Sanjiv Shah Underground Excavations at CHEP
45/77
MAJOR CAUSES
Overburden only between 174 and 279 m, but poor geology
Ch. 3+102.5 and 3+592.7 m
Fault zone with highly crushed rock mass of grey to white talcosic
dolomite with phyllite intercalation Bedding planes nearly parallel to tunnel (deviation ~ 11°)
Large ground water inflow
Ch. 3+659.4 and 3+945 m
Mainly composed of highly weathered talcosic phyllite with veryrare intercalation of white to grey, thinly bedded dolomite or
quartzite
Bedding planes vertical, nearly parallel to tunnel (deviation ~ 11°)
Large ground water inflow
-
8/17/2019 Sanjiv Shah Underground Excavations at CHEP
46/77
GEOLOGY BETWEEN ADITS 2 & 3
-
8/17/2019 Sanjiv Shah Underground Excavations at CHEP
47/77
GEOLOGY BETWEEN ADITS 2 & 3
-
8/17/2019 Sanjiv Shah Underground Excavations at CHEP
48/77
SEVERITY OF SQUEEZING
-
8/17/2019 Sanjiv Shah Underground Excavations at CHEP
49/77
INITIAL ATTEMPTS FOR SOLUTION
Various methods for solution attempted
Top heading and benching
Manual excavation
Fore poling
Placement of closely spaced steel ribs
Drainage
Invert strengthening (invert strut and concreting)
Implementation difficult due to poor ground conditions
Sequential excavation: misalignment of steel rib crown & legs
Invert strengthening: Not possible due to slushy conditions,
immediate sidewall squeezing & floor heaving following invert
excavation, severe buckling
-
8/17/2019 Sanjiv Shah Underground Excavations at CHEP
50/77
OPTIONS EVALUATED
• Over-excavation
• To gain sufficient time to install supports
• Led to further collapses
•
Tunnel realignment• Large lateral extent of poor rock mass
• Diversion would run parallel to bedding planes under increasingoverburden, creating even greater problems in excavation
-
8/17/2019 Sanjiv Shah Underground Excavations at CHEP
51/77
ENGINEER’S DECISION
Proceed further with tunnel excavation along designed
alignment & repair tunnel after breakthrough
Reasons:
Tunnel excavation & deformation would result in significant stressrelaxation in surrounding rock mass
Breakthrough would eliminate all tunnel faces that had
repeatedly been serving as sources of large debris flows
Breakthrough would drain surrounding rock mass
-
8/17/2019 Sanjiv Shah Underground Excavations at CHEP
52/77
EXCAVATION PROCEDURE
Fore-poling to create protective shield
Sequential excavation (heading & benching)
Sealing tunnel faces after to prevent collapses or debris flows
R5 and R6 supports with steel ribs but no rock bolts
Locations of excessive squeezing: double layer of 100 mmsteel ribs with invert struts
Temporary supports
Weep holes to drain out groundwater behind crown & wall
Limited grouting at locations with crushed rock mass
-
8/17/2019 Sanjiv Shah Underground Excavations at CHEP
53/77
SQUEEZING TREATMENT DESIGN
• Various alternatives considered
• Steel lining
• 4.9 m steel liners embedded in plain or reinforced concrete
•
Could fit within deformed tunnel profile at most places, requiringminimal reshaping at places with excessive squeezing
• Transportation, assembly and quality control extremely difficult
• Exorbitant cost (approx. Rs. 2.05 billion)
• Concrete lining
• Concrete lining after reshaping deformed• Performed sequentially, extremely slow (almost two years
provided no major stoppages)
-
8/17/2019 Sanjiv Shah Underground Excavations at CHEP
54/77
SQUEEZING TREATMENT DESIGN
Engineer designed treatment plan based on case histories
(e.g. Yacambu-Quibor tunnel) and information gained through
trial sections
Tunnel categorized into three typical zones based on observed
maximum strains Circular cross-section with 5.4 m finished diameter
Supports for each zone designed using Phase 2
Reinforced shotcrete lining selected because of shorter
installation time
Steel ribs with yielding joints in zones of excessive squeezing topermit stress relaxation and ensure safe working conditions
-
8/17/2019 Sanjiv Shah Underground Excavations at CHEP
55/77
PHASE 2 ANALYSIS
Initial values of rock mass properties (GSI, mi and sci) selected from
published charts
Back analysis performed to adjust the material parameters so as to
match the computed and observed deformations
Rock mass was modeled as an elastic-perfectly plastic material
Analyses showed extensive stress relaxation around tunnel up to
distance of at least 2 to 2.5 times tunnel diameter
Supports for each zone designed using the various support facilitiesavailable in Phase 2
Stage-wise modeling performed to simulate pre-existing
deformations and supports were installed at appropriate stages
-
8/17/2019 Sanjiv Shah Underground Excavations at CHEP
56/77
DESIGN PROFILE
SQUEEZED PROFILE
TREATED PROFILE
BASIC APPROACH
-
8/17/2019 Sanjiv Shah Underground Excavations at CHEP
57/77
SQUEEZING TREATMENT DESIGN
Zone A: Squeezing extremely severe, on-going
Total length: 418 m
Over-excavation to 6.6 m dia. circular shape
Steel ribs with yielding joint
60 mm reinforced shotcrete
Zone B: Squeezing extremely severe but stable
Total length: 226 m
Over-excavation to 6.4 m dia. circular shape
40 mm thick reinforced shotcrete
Zone C: Squeezing very severe but stable
Total length: 198 m
Over-excavation to 6.3 m dia. circular shape
35 mm thick reinforced shotcrete
-
8/17/2019 Sanjiv Shah Underground Excavations at CHEP
58/77
TYPICAL DESIGNS
-
8/17/2019 Sanjiv Shah Underground Excavations at CHEP
59/77
TYPICAL YIELDING SUPPORT
-
8/17/2019 Sanjiv Shah Underground Excavations at CHEP
60/77
POE RECOMMENDATIONS
Visited site from December 8 to 11, 2013
Observations:
Tunneling performed under extremely poor geological conditions
Observed squeezing was not “classical” squeezing Engineer’s approach to complete tunnel excavation and then
treat the squeezed section correct
Closed circular section with shotcrete looked promising and
should be maintained
Yielding steel sets were a very meaningful ground supportmeasure for squeezing rock conditions
Recommendation
Added Type D support (Type A without steel rib)
-
8/17/2019 Sanjiv Shah Underground Excavations at CHEP
61/77
ORIGINAL CONDITION
-
8/17/2019 Sanjiv Shah Underground Excavations at CHEP
62/77
RE-EXCAVATION (MANUAL)
-
8/17/2019 Sanjiv Shah Underground Excavations at CHEP
63/77
RE-EXCAVATION (MACHINE)
-
8/17/2019 Sanjiv Shah Underground Excavations at CHEP
64/77
STEEL RIB INSTALLATION
-
8/17/2019 Sanjiv Shah Underground Excavations at CHEP
65/77
FIRST STAGE SHOTCRETE
-
8/17/2019 Sanjiv Shah Underground Excavations at CHEP
66/77
STEEL BAR PLACEMENT
-
8/17/2019 Sanjiv Shah Underground Excavations at CHEP
67/77
SHOTCRETING
-
8/17/2019 Sanjiv Shah Underground Excavations at CHEP
68/77
FINAL SECTION
-
8/17/2019 Sanjiv Shah Underground Excavations at CHEP
69/77
IMPLEMENTATION OF TREATMENT
• Treatment started in March 2013
• Difficult & slow process, but no major problems encountered
• 67.5% treatment complete
Zone Total (m) Complete (m) Remaining (m)
A 283.2 248.1 31.1
B 277.2 223.1 54.1
C 181.9 97.2 84.7
D 100.0 0.00 100.0
Total 842.3 569.4 273.9
-
8/17/2019 Sanjiv Shah Underground Excavations at CHEP
70/77
PROBLEMS ENCOUNTERED
-
8/17/2019 Sanjiv Shah Underground Excavations at CHEP
71/77
PROBLEMS ENCOUNTERED
-
8/17/2019 Sanjiv Shah Underground Excavations at CHEP
72/77
VERTICAL SHAFT &PENSTOCK TUNNEL
-
8/17/2019 Sanjiv Shah Underground Excavations at CHEP
73/77
HORIZONTAL PENSTOCK TUNNEL
Tunnel length: 300 m
Only 160 m provided
with steel lining
Large debris flow, about
1,700 cu. m
Indication of very poor
geological conditions
-
8/17/2019 Sanjiv Shah Underground Excavations at CHEP
74/77
VERTICAL SHAFT
Large cavity around shaft
Approx. 25 x 8 x 5 m
Crushed material
Concrete lininginadequate
Leakage
Slope instabilities
Steel lining proposed
-
8/17/2019 Sanjiv Shah Underground Excavations at CHEP
75/77
VERTICAL SHAFT
-
8/17/2019 Sanjiv Shah Underground Excavations at CHEP
76/77
PENSTOCK & SHAFT LINING
• Original design: penstock concrete and steel lined, verticalshaft concrete lined
• Revised design: steel lining required over entire length due topoor geological conditions (large cavities)
• Concrete lining without adequate rock support may burst underwater hammer
• Water leakage through cavities
• Further revision based on POE recommendations:
•
Concrete lining (“water tight”)• Geo-membrane layer to prevent water leakage
-
8/17/2019 Sanjiv Shah Underground Excavations at CHEP
77/77
THANK YOU!