saipem australia Strategic thinking on a daily basis: integration Strategic thinking on a daily basis: integration of environmental management, regulatory approvals, cultural heritage, land liaison and approvals, cultural heritage, land liaison and construction. Sue Korecki – Compliance Manager 15 th October 2013

Upload: others

Post on 14-Feb-2022

5 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: saipem australia - EIANZ

saipem australiap

Strategic thinking on a daily basis: integration Strategic thinking on a daily basis: integration of environmental management, regulatory

approvals, cultural heritage, land liaison and approvals, cultural heritage, land liaison and construction.

Sue Korecki – Compliance Manager

15th October 2013

Page 2: saipem australia - EIANZ

AIM FOR CONSTRUCTION – Utilising an example

Access into the Gladstone State Development Area (GSDA) from the Bruce Highway (KP 383.1)

saipem australiap

2

Page 3: saipem australia - EIANZ

Background: GSDA Gladstone State Development Area

‐ Declared in 1993.‐ Located 15 kms NW of Gladstone Located 15 kms NW of Gladstone. ‐ Land uses considered suitable for the Gladstone

SDA include: SDA include: port-related activities and industries necessary

t t j i d t i l d l t to support major industrial development; materials transportation infrastructure and utility

and service infrastructure; gas transportation infrastructure and other

saipem australia

compatible infrastructure.

p

3

Page 4: saipem australia - EIANZ

saipem australiap

4

Page 5: saipem australia - EIANZ

Infrastructure User Definition

means a person whom a Landowner has authorisedto use part of the GSDA for the purposes of construction, operation, maintenance, alteration, repair and replacement of Infrastructure but excludes for the avoidance of doubt a Grazierexcludes, for the avoidance of doubt, a Grazier.

saipem australiap

5

Page 6: saipem australia - EIANZ

Flow chartEnvironment ˃

Ecological Survey Incl. Weed Survey: Complete 1 year prior ˃ Build Washdown Facility: 1- 2 weeks

˃ Weed Treatment: 10-14 days

˃ Fauna Survey: 7 days

Regulatory Approvals ˃TMR Application for Road Corridor P it 20 b i dg y pp Permit: 20 business days

˃ GSDA ˃ 5 days notification - to enter the area

˃ 1 day notification - for preliminary works

˃ 15 days notification - major construction works

Cultural Heritage ˃Cultural Heritage Survey and Sign-Off ˃ Survey for ROW: prior to Construction (Company)

Survey for EWSs and ATs off ROW: 10 business ˃

Survey for EWSs and ATs off ROW: 10 business days' notice

Land Liaison ˃Landholder and Leaseholder Approvals ˃ Amendment to GSDA Licence (C-G): 4-6 weeks

saipem australia

˃Access, Conduct and Compensation Agreements (Leaseholder): 1 day - weeks

˃ Temporar Use Notice (C G) 1 2 eeksp

6

˃ Temporary Use Notice (C-G): 1-2 weeks

Page 7: saipem australia - EIANZ

Regulatory Approvals

Land Use Protocol for Gladstone State Development Area – Materials Transportation and Services pCorridor Precinct –Notifications to Leaseholders

saipem australiap

7

Page 8: saipem australia - EIANZ

Gladstone State Development Area (GSDA)

The Infrastructure User must:( ) i l 5 B i D ' i (a) give at least 5 Business Days' written notice to the Landowner and the relevant GSDA Users that the Infrastructure User GSDA Users that the Infrastructure User proposes to enter onto the Licensed Area, including details of the manner in which the gGSDA;(b) provide a list of activities, including the location, the proposed work program and the timing, proposed to be carried out on the Licensed Area

saipem australia

Licensed Area.

p

8

Page 9: saipem australia - EIANZ

GSDA

Next, the Infrastructure User must provide notice to the Landowner and all GSDA Users notice to the Landowner and all GSDA Users who occupy the relevant part of the GSDA as follows before entering onto its Licensed Area:follows before entering onto its Licensed Area: (a) provide 24 hours' notice to the Landowner and all relevant GSDA Users prior pto preliminary works, such as surveying activities; (b) 15 Business Days' notice for major construction activities.

saipem australiap

9

Page 10: saipem australia - EIANZ

Designated Access Point (DAP) – KP 383. 1 (Bruce Highway).

- TMR – Road Corridor Permit Approval required for access off the Bruce Highway directly onto Saipem’s g y y pROW. Lots of negotiations and a potential standstill to Construction commencing in the GSDA.

Photo: No approval yet to access from the Bruce Highway –g ytemporary signage

saipem australiap

10

Page 11: saipem australia - EIANZ

DAP – KP 383. 1

Potential Delays: look for alternatives – utilizing the MCJV DAP onto their ROW and then utilize an AT to Saipem’s ROW.

Photo: No approval yet to access from ythe Bruce Highway – vehicles parked on the side of the road.

saipem australiap

11

Page 12: saipem australia - EIANZ

DAP – KP 383. 1

Map: The different gasdifferent gas pipeline corridors and the proposedthe proposed access from MCJV ROW.

saipem australiap

12

Page 13: saipem australia - EIANZ

DAP – KP 383. 1

Cultural Heritage potentially an issue, so utilized an existing farm track (with leaseholder’s consent)

Photo: Existing farmPhoto: Existing farm track – no works required. Therefore, no CH approvalno CH approval required.

saipem australiap

13

Page 14: saipem australia - EIANZ

DAP – KP 383. 1

Gained consent from TMR

saipem australiap

14

Page 15: saipem australia - EIANZ

Environmental

Ecological Survey(a) conduct a baseline

survey of its Licensed Area;

(b) prepare a Condition Report; and

( ) i f th (c) give a copy of the survey and Condition Report to the C-G Report to the C G, prior to commencing the works.

saipem australiap

15

Page 16: saipem australia - EIANZ

Environmental

Fauna Survey – 7 days prior to y pthe works commencing

saipem australia

Sugar Gliderp

16

Page 17: saipem australia - EIANZ

Environmental

Weed survey: as a part of the Condition Report

Map: GSDA, GRT v Clean area, washarea, wash downs

* Weed Treatment

ll 10normally 10-14 days prior. Different for

saipem australia

GRT

p

17

Page 18: saipem australia - EIANZ

Environmental

Machinery and Vehicle washdown requirements; (a) Must be washed on entry into the GSDA and out (a) Must be washed on entry into the GSDA and out

from the GSDA (need a washdown at the DAP at Bruce Highway).

(b) However, machinery and vehicles coming straight from the CICSDA did not need another washdown.

Had to build a washdown on the ROW as the Temporary Use Notice (TUN) for EWS 194 from the C G was taking time

saipem australia

C-G was taking time.

p

18

Page 19: saipem australia - EIANZ

Environmental

Photos: Building and use of Wash Down Facility at KP 383

saipem australiap

19

Page 20: saipem australia - EIANZ

Cultural Heritage

pre-construction PCCC CH survey of the ROWFor EWSs (off the ROW) – 10 business days’ notice, ( ) y ,must submit a Request for Cultural Heritage ClearanceEWS must be pegged prior to initial CH survey.

Photo: NO GO ZONE for Cultural HeritageCultural Heritage

saipem australiap

20

Page 21: saipem australia - EIANZ

Land Liaison

Notification to the leaseholders/ Graziers, as per the GSDA Land Use Protocol.Extra Work Spaces:

(a) EWSs inside the GSDA corridor - Temporary Use Notices from the C-G

(b) EWSs outside the GSDA corridor –A d t t th GSDA li f th CAmendment to the GSDA licence from the C-G

(c) EWSs outside the GSDA corridor Access (c) EWSs outside the GSDA corridor – Access Conduct and Compensation Agreements with the leaseholders

saipem australia

the leaseholders

p

21

Page 22: saipem australia - EIANZ

Environmental

saipem australiap

22

Page 23: saipem australia - EIANZ

GO NO-GO

When Signed off and received from Company

construction – construction is clear to proceed.proceed.

saipem australiap

23

Page 24: saipem australia - EIANZ

AIM Complete

saipem australiap

24Photos: Construction of the GLNG Gas Transmission Pipeline