s02v02p01 - app · 2013. 11. 25. · 2015 general rate case application workpapers results of...
TRANSCRIPT
An EDISON INTERNATIONAL® Company
(U 338-E)
2015 General Rate Case APPLICATION
Workpapers
Results of Operations (RO)Requested Revenue Requirements, Ratemaking, Forecasts of Sales, Other Operating Revenue, Cost Escalation, Post-Year Ratem aking SCE-10 Volume 01, Chapter X
N ovem ber 2013
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
Workpaper - Southern California Edison / 2015 GRC - APPLICATION1
X.
POST-TEST YEAR RATEMAKING
This chapter presents SCE’s proposal to extend our current Post-Test Year Ratemaking (PTYR)
mechanism. This mechanism is intended to provide additional revenues, as necessary, to cover our costs
of doing business in calendar years 2016 and 2017, including our program to step-up capital investment
to meet growing demand and to replace aging utility infrastructure. Our current PTYR mechanism was
adopted in SCE’s 2003 General Rate Case and extended, with modifications, in SCE’s 2006, 2009, and
2012 General Rate Cases.100
SCE currently operates under ratemaking that incorporates a revenue balancing account
mechanism known as the Base Revenue Requirement Balancing Account (BRRBA). This account is
discussed in Chapter II of Volume 1 of this exhibit. Under this mechanism, rates are designed to recover
the authorized revenue requirement with any variation in recorded revenues (either higher or lower)
tracked in a balancing account for subsequent recovery from, or refund to, retail customers.
Consequently, during the period in which the revenue requirement is in effect, any additional revenues
that result from customer growth or increased usage per customer are returned to customers as a rate
decrease, rather than being available to offset SCE’s cost increases. Thus, it is necessary to provide for
an increase in the annual revenue requirement to recover cost increases caused by increased capital
spending. Such increased spending may include new facilities to meet load growth or replace aging
infrastructure,101 and the impact of price inflation on operating expenses.102 In this manner, SCE is
provided a fair opportunity to earn its authorized return on equity. SCE is proposing a ratemaking
formula that results in the projected revenue requirement increases for 2016 and 2017 that are shown in
Chapters II and III of Volume 1 of this exhibit. SCE proposes to update its revenue requirement
100 D.04-07-022 (mimeo), pp. 266-281. D.06-05-016 (mimeo), pp. 290-309. D.09-03-025, (mimeo), pp. 302-307. D.12-11-051, (mimeo), pp. 599-609.
101 SCE’s rates reflect the embedded cost o f existing facilities, which are partly depreciated. Because plant is valued at original cost (without adjustment for inflation) less accumulated depreciation, new facilities that are added to accommodate load growth will cost more than the average value (for ratemaking purposes) o f existing plant. When older facilities are replaced with new ones, the associated cost is typically much higher that what is included in rates for the original facilities.
102 As explained more fully in section B.1 below, SCE’s post-test year ratemaking mechanism does not include any offset for additional O&M expense resulting from new customers. This feature, which is consistent with previous attrition mechanisms authorized by the Commission, and SCE’s current PTYR mechanism, is an implicit productivity adjustment.
110
Exhibit No. SCE-10 / Results of Operations / Vol. 01 / Ch. XWitness: P. Hunt
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
Workpaper - Southern California Edison / 2015 GRC - APPLICATION
projections based on updated price inflation forecasts that will be made in annual filings prior to 2016
and 2017. SCE’s PTYR mechanism will recover O&M cost changes that result from input price
changes outside of SCE’s control and capital-related cost changes that result from SCE’s capital
expenditure program. As explained later in this exhibit, SCE’s mechanism does not track or recover
O&M cost changes that result from other factors, except to the extent that those factors are captured by
SCE’s proposed Z-factor mechanism. In addition, capital expenditures in the post test year period that
are not anticipated in SCE’s capital expenditure program as projected in this rate case will result in cost
increases that the PTYR mechanism will not recover.
Under our PTYR mechanism proposal we may seek recovery of costs imposed on SCE as a
result of Commission actions. SCE’s proposed post-test year ratemaking mechanism is based on events
known and reasonably anticipated as of the date this testimony is being prepared. Subsequent
Commission actions or other events may require SCE to propose changes to this mechanism.
A. Background
1. Rate Case Plan
Under the Rate Case Plan, as modified by Commission Resolution ALJ-151 and
D.89-01-040,103 energy utilities file GRC applications every three years. The Attrition Revenue
Requirement Adjustment mechanism was adopted by the Commission104 in the early 1980s to
compensate utilities for the increased costs that occurred between test years and has since been a regular
part of utility ratemaking.105 Over approximately this same period, the Commission utilized an Electric
Revenue Adjustment Mechanism (ERAM) or similar balancing account mechanisms to remove the
incentive for SCE to promote electricity sales at the expense of conservation and demand reduction
programs.
Annual cost increases can be caused by inflation and plant additions used to maintain and
provide service. Without a means to recognize these increases in rates, SCE will not have a reasonable
103 D.89-01-040, 30 CPUC 2d 576.
104 In D.92549, issued in conjunction with Edison’s 1981 GRC application, the Commission adopted Staff’s recommendation to implement stepped rate changes for 1982, citing Staff’s argument that “the use o f stepped rates would provide a more stable earnings pattern.” 5 CPUC 2d 39, 80.
105 In D.96-09-092, the Commission adopted a five-year performance based ratemaking mechanism that provided annual increases in SCE’s distribution rates based on a measure of inflation less a productivity factor, and allowed SCE to retain additional revenues that resulted from sales and customer growth. In anticipation of adopting a PBR mechanism, the CPUC did not authorize an attrition mechanism in SCE’s 1995 test year GRC.
111
Exhibit No. SCE-10 / Results of Operations / Vol. 01 / Ch. XWitness: P. Hunt
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
Workpaper - Southern California Edison / 2015 GRC - APPLICATION3
opportunity to earn its authorized rate of return after the test year, as evidenced by the projections
presented in Chapters II and III of Volume 1 of this exhibit. Since the BRRBA prevents SCE from
retaining the incremental revenue from sales that are above projected levels, SCE must have an explicit
ratemaking mechanism to permit it to recover increased costs.
financial cost changes. Operational cost changes due to price increases in the goods and services that we
employ in our operations and the level of capital assets required to operate our business are addressed by
the PTYR mechanism proposed in this exhibit. Financial costs, such as the cost of long-term debt and
preferred equity, are not addressed by the PTYR mechanism.
B. Need for Revenue Requirement Increases
This section explains why we anticipate that revenue requirement increases will be required
during 2016 and 2017.
1. Inflation and Productivity
since the late 1970s and 1980s, inflation still results in higher costs for the inputs that we use to provide
service to our customers.106 The labor and non-labor escalation rates presented in Part 4 of Volume 1 of
this exhibit document the operation and maintenance (O&M) inflation expected from 2012 through
2017. We will also incur higher costs for capital equipment to replace worn out equipment and to build
facilities to serve new customers.
costs, but generally productivity improvements are not sufficient to avoid cost increases, particularly
when we cannot keep the revenue increases from output (kWh sales, kW demand) increases. In
addition, our revenue requirements will increase as a result of the costs associated with serving new
customers. These two factors make a post-test year ratemaking mechanism necessary to provide SCE a
fair opportunity to recover its costs.
Under a revenue balancing account, we do not retain any incremental revenue from
growth in usage or new customers to offset the increased costs of operation that result from these
106 Perhaps the most notable example that consumers will recognize is that the price o f gasoline has increased by almost 133 percent from 2004 and almost 67 percent from 2009. (Based on the Producer Price Index for gasoline, not seasonally
2. Operational Cost Changes
After the test year, SCE’s earned rate of return is directly affected by operational and
Despite the dramatic decrease in price inflation in the U. S. economy that has occurred
In the past, our productivity performance has acted as a partial offset to our increased
adjusted.)
112
Exhibit No. SCE-10 / Results of Operations / Vol. 01 / Ch. XWitness: P. Hunt
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
Workpaper - Southern California Edison / 2015 GRC - APPLICATION
influences. Under the attrition mechanisms previously authorized by the Commission and SCE’s current
PTYR mechanism, it has been assumed that increased O&M costs from customer and usage growth are
offset by productivity gains that will be achieved during the attrition years.107 These mechanisms
generally have permitted recovery of O&M cost increases due to input price escalation (O&M labor
escalation and O&M non-labor escalation) during attrition or post-test year periods, but have not
permitted recovery of O&M cost increases due to other factors. Limiting recovery of O&M cost
increases in this way results in an implicit expectation that productivity gains will offset O&M cost
increases from other sources. (Appendix B provides a mathematical analysis of this question.) This is
why our PTYR mechanism adjusts our test year O&M expense levels for escalation and
Commission-mandated and government-mandated changes, but does not include an explicit productivity
offset to these adjustments.
2. Enhancing SCE’s Financial Standing
SCE has returned to financial health and investment grade status, but SCE has not
returned to the financial stature that it enjoyed before the California energy crisis. SCE’s credit ratings
are below mid-2000 levels, before the energy crisis began. A reasonable regulatory mechanism that will
allow SCE to recover its revenue requirement during 2016 and 2017 will reinforce SCE’s return to
financial health.108
If SCE can achieve higher credit ratings than it currently possesses, customers will
benefit from reduced financing costs. The Commission should extend SCE’s post-test year ratemaking
mechanism to support SCE’s financial standing. The post-test year ratemaking mechanism should
provide that capital-related costs will be recovered as investments are made and enter rate base and also
allow timely recovery of reasonable cost increases in operation and maintenance costs that result from
cost inflation.
SCE cannot afford a post-test year ratemaking mechanism that allows it to recover costs
only associated with average historical levels of capital additions. Nor can SCE afford a post-test year
ratemaking mechanism that increases its authorized revenue requirement in one year but avoids any
increase in another. SCE’s capital expenditures are at historically high levels and those capital
107 D.04-07-022 (mimeo), pp. 273-274.
108 Before the energy crisis, SCE was A-rated by both Moody’s and Standard & Poor’s (corporate or issuer credit rating). While SCE is again A-rated by Moody’s, SCE is only BBB-rated (BBB+) by Standard & Poor’s.
113
Exhibit No. SCE-10 / Results of Operations / Vol. 01 / Ch. XWitness: P. Hunt
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
Workpaper - Southern California Edison / 2015 GRC - APPLICATION5
expenditures will result in substantial revenue requirement increases after the 2015 test year. The
Commission should continue the positive steps that it took in SCE’s prior GRC applications to ensure
that SCE’s authorized revenue requirement will be sufficient to permit it to make the capital investments
that are necessary to maintain and expand its system, and serve its customers.109 As discussed in more
detail below, the post-test year ratemaking mechanism adopted in the 2009 GRC contained significant
flaws. It does not serve as a model for this case.
C. Features of our Proposed Mechanism
We propose a PTYR mechanism with the following features:
• An annual advice letter providing notice of the revenue requirement change for the following
year.
• O&M escalation using the GRC escalation rate methodology, updated at the time of the
advice letter filing.
• Capital-related cost increases using SCE’s Board-approved capital budget, updated for
changes in SCE’s authorized cost of capital.
• A mechanism to address major exogenous changes in SCE’s costs.
These features are discussed in more detail in the following sections.
1. Annual PTYR Mechanism Advice Letter
SCE will file an annual PTYR mechanism advice letter by November 1, 2015 for 2016
post-test year ratemaking and November 1, 2016 for 2017 post-test year ratemaking, consistent with
current procedure. This advice letter will specify the revenue requirement adjustment for O&M
escalation and changes in capital-related costs.
2. O&M Escalation
Chapter VII of Volume 1 of this exhibit describes SCE’s methodology for determining
escalation rates for labor and non-labor O&M expense. SCE proposes to use the same methodology,
with some adjustments as discussed below, to determine O&M escalation rates to calculate the O&M
expense adjustments for 2016 and 2017.
109 The use o f an actual capital additions budget, as specified in the 2003 GRC decision, is superior to the escalation of test year capital additions, as adopted in the 2006 and 2012 GRC decisions, or the escalation of SCE’s revenue requirement, as adopted in the 2009 GRC decision.
114
Exhibit No. SCE-10 / Results of Operations / Vol. 01 / Ch. XWitness: P. Hunt
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
Workpaper - Southern California Edison / 2015 GRC - APPLICATION
a) Latest Global Insight Escalation Rates Will Be Used
SCE’s annual revenue change advice letter will be filed by November 1 of 2015
and 2016 for the following year. SCE will employ the latest IHS Global Insight escalation rates that are
available on October 1 of the year in which these filings are made. These will be from the “Control”
projection if HIS Global Insight publishes more than one projection.
b) Escalation Rates Will Be “Trued Up” to Actual, But Previous Forecast
Errors Will Not Be Recovered or Refunded
This provision applies to the O&M escalation adjustment for 2017. In the
November 2016 advice letter filing, SCE will compute the authorized level of O&M expense for 2017
by applying compound escalation factors from 2015 through 2016 to the authorized level of O&M
expense for 2015. These escalation factors will be the latest available, so that actual escalation will
become incorporated as it becomes known. This procedure will ensure that the 2015 O&M escalation
adjustment captures all of the latest information for escalation from the test year forward.
The 2017 authorized level of O&M expense will be calculated as the 2015 level
multiplied by an escalation factor for 2016 and an escalation factor for 2017, based on the latest Global
Insight escalation rates available by October 1, 2016. The escalation factor for 2016 will not be the
factor employed in the November 2015 advice letter for 2016 post-test year ratemaking, but the factor
based on the latest information. However, there will be no true-up to the 2016 authorized level of O&M
expense resulting from updates to the escalation factor for 2016.
c) Other Differences from Escalation Rates Calculated Through the Test Year
The labor O&M escalation rates for 2013 and 2014 incorporated union wage
increases and target wage increases for non-represented employees, as discussed in Chapter VII of
Volume 1 of this exhibit. For the annual advice letters, union wage increases and target wage increases
for non-represented employees granted prior to the adoption of a Phase 1 decision in this application will
be incorporated in the labor escalation rates used in the 2016 and 2017 PTYR advice letters.
d) Projected Labor and Non-Labor Escalation Rates for 2016 and 2017
SCE’s projected labor and non-labor escalation rates for 2016 and 2017, based on
the information available at this time, are presented in Chapter Vii of Volume 1 of this exhibit.
115
Exhibit No. SCE-10 / Results of Operations / Vol. 01 / Ch. XWitness: P. Hunt
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
Workpaper - Southern California Edison / 2015 GRC - APPLICATION7
It is important that the escalation rates embedded in SCE’s PTYR mechanism be
industry-specific or company-specific, as SCE’s proposed escalation rates are.110 Use of a general
inflation index such as the Consumer Price Index (CPI) or Gross Domestic Product Chain-Weighted
Price Index (GDPPI) should be avoided. The CPI tracks prices paid by consumers and excludes large
categories of SCE’s costs. In addition, it excludes health care costs paid by employers.111 The GDPPI
covers the entire U.S. economy and thus is far too broad to be an accurate measure of SCE’s input price
inflation.
e) Benefit Escalation Rates
Testimony in Exhibit SCE-06, Volume 2, Part 1 discusses SCE’s benefit program
costs for the test year and benefit cost escalation in selected areas for 2016 and 2017. For medical costs,
escalation is projected to be eight percent in 2016 and 2017. These projected escalation rates should be
applied directly to medical program costs and PBOP (Post Retirement Benefits Other Than Pensions)
costs without any updating when the PTYR advice letters are filed. It is reasonable to apply these
escalation rates to PBOP costs, since PBOP costs are dominated by medical costs.
For other benefit categories, SCE will use the escalation rates shown in Table X-
39 below. Cross-references for these escalation rates are shown in the workpapers.
Table X-39 Benefit Escalation Rates
LineNo. Category 2016 2017 Comments1. Medical Programs - 926 8.00% 8.00% Medical escalation rate2. Dental Programs - 926 4.50% 4.50% Dental escalation rate3. Vision Service Plan - 926 2.00% 2.00% VSP escalation rate4. Disability Programs - 926 2.66% 2.65% Labor escalation rate5. Group Life Insurance - 926 0.00% 0.00% Life escalation rate6. Misc. Benefit Programs - 926 3.03% 2.90% A&G nonlabor rate after 20157. Executive Benefits - 926 2.66% 2.65% Labor escalation rate8. 401(k) 2.66% 2.65% Labor escalation rate
110 This matter is discussed in more detail in the cost escalation testimony presented in Chapter VII o f Volume 1 of this exhibit.
111 D.04-07-022 (mimeo), p. 278.
116
Exhibit No. SCE-10 / Results of Operations / Vol. 01 / Ch. XWitness: P. Hunt
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
Workpaper - Southern California Edison / 2015 GRC - APPLICATION
3. Capital-Related Cost Increases
As discussed in more detail in other parts of this application, we are engaged in a
multi-year program of construction expenditures to meet system load growth, and to expand replacement
of aging infrastructure. (See Exhibit SCE-03, Volumes 1 and 3-5.) Our proposed PTYR mechanism
includes capital costs associated with a budget-based forecast of capital expenditures, but we also
propose that the associated revenue requirements be subject to refund if our capital spending budgets are
not fully implemented.112
Our projected capital additions, including cost of removal, for 2016-2017 are shown in
the following table.
Table X-40 Proposed Capital Additions, 2016-2017
($ millions)See WP's, pp. 3-4.
LineNo. 2016 2017
1. 3,827.1 3,896.3
(These amounts include gross capital additions plus cost of removal.)
SCE is not proposing that its capital additions for test year 2015 be covered by this type
of “one-way balancing account” mechanism. This is because when the Commission is considering and
deciding our test year request, we are close to the in-service dates for our capital projects. The customer
is protected because any variance between forecast and recorded capital additions is explained in our
next GRC application.
4. Treatment of Major Exogenous Cost Changes
In SCE’s current PTYR mechanism, SCE is permitted to seek recovery of costs
associated with exogenous events (“Z-Factors”) that result in a major cost impact for SCE. The existing
Z-Factor mechanism allows either SCE or the Division of Ratepayer Advocates (DRA) to submit a
Letter of Notification to the Executive Director to identify any potential Z-Factor event. There are no
current Z-factors. SCE is at risk for events that do not have a financial impact of more than $10 million.
112 We will create a “one-way” balancing account that will refund any over-estimate o f the revenue requirement associated with our post test year capital additions, including the cost o f removal. The balancing account calculation will be cumulative over the combined two-year period. This is the same as the balancing account that was adopted in our 2003 General Rate Case. D.04-07-022 (mimeo), p. 277.
117
Exhibit No. SCE-10 / Results of Operations / Vol. 01 / Ch. XWitness: P. Hunt
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
Workpaper - Southern California Edison / 2015 GRC - APPLICATION9
In addition, there is a $10 million “deductible amount” applied on a one-time basis to the first year’s
revenue requirement associated with any approved Z-Factors. Costs associated with two named
contingencies, new municipal utility formation and P.U. Code Section 463 projects, are treated as Z-
Factors but without the $10 million threshold or the $10 million deductible.113
The existing Z-Factor mechanism should be continued. Although neither SCE nor DRA
have identified any proposed Z-Factors since SCE’s 2003 GRC was decided, the Z-Factor mechanism
has nonetheless provided the assurance that a clear process is in place to deal with unanticipated major
variations in SCE’s costs.
5. The Commission Should Not Require an Application to Implement Post Test Year
Ratemaking
In authorizing post-test year ratemaking for 2004 and 2005, the Commission imposed a
requirement that if SCE’s revenue requirement increase were to exceed $150 million in either year, SCE
would be required to submit an application for that year, rather than an advice letter.114 The
Commission stated that it was unwilling to permit greater rate increases to be implemented through the
“streamlined” advice letter process.
Unlike that GRC application, however, this application contains testimony supporting
SCE’s proposed capital expenditures through 2017, not just through the test year.115 Thus, there is no
substantial component of SCE’s post-test year ratemaking mechanism that is not addressed by testimony
in this application. The Commission should not require SCE to submit a second application in 2015 or
2016 to reapprove its proposed mechanism.
D. The Post-Test Year Mechanism Adopted in SCE’s 2009 GRC Contains Two Fundamental
Analytic Errors That Shortchanged SCE’s Revenue Requirement
In SCE’s 2009 GRC, the Commission adopted a simplified post-test year mechanism that simply
increased SCE’s revenue requirement in 2010 and 2011 by specified percentages. However, that
113 The Z-factor mechanism was established in SCE’s 2003 Test Year General Rate Case. D.04-07-022 (mimeo), pp. 278-279; Finding of Fact 231, p. 346. Continuation was authorized in SCE’s 2006, 2009, and 2012 Test Year General Rate Cases. D.06-05-016 (mimeo), p. 308; Ordering Paragraph 7, p. 382. D.09-03-025, p. 306; Conclusion of Law 213, p. 390; Ordering Paragraph 5, p. 393. D.12-11-051 (mimeo), p. 609.
114 D.04-07-022 (mimeo), p. 281; Conclusion of Law 53, p. 355.
115 Further, when SCE submits its Test Year 2018 General Rate Case application, it will provide an updated forecast o f 2016and 2017 capital additions, developed at a much closer point in time (2016 instead of 2013). The Commission will beafforded another review opportunity at that time if it chooses.
118
Exhibit No. SCE-10 / Results of Operations / Vol. 01 / Ch. XWitness: P. Hunt
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
Workpaper - Southern California Edison / 2015 GRC - APPLICATION
approach contained a methodological error because the Commission’s calculations overlooked SCE’s
year-end 2008 balance of Construction Work in Progress (CWIP).116
In SCE’s 2009 GRC, as in this 2015 GRC, we proposed a method for the Commission to
authorize revenue requirements for the two attrition or post-test years (in that case 2010 and 2011, in this
case 2016 and 2017).117 Our post-test year ratemaking proposal included detailed testimony on our
capital expenditures for 2010 and 2011. However, in lieu of reviewing our entire capital forecast, the
Commission instead adopted a ratemaking method that indexed our total 2009 adopted revenue
requirement by 4.25 percent for 2010 and 4.35 percent for 2011. The post-test year revenue requirement
should provide for recovery of authorized costs and a reasonable opportunity to earn the authorized rate
of return. But the post-test year ratemaking formula adopted in our 2009 GRC contained a fundamental
methodological error118 that effectively shortchanged our authorized revenues and jeopardized SCE’s
ability to earn its authorized rate of return.
It can take many months for some capital projects to be completed and placed into service.
During that interim period, as we continue to make capital expenditures on those projects, we accrue an
Allowance for Funds Used During Construction (AFUDC), which recognizes the financing costs being
incurred during construction.119 The AFUDC accrual is eventually added to the overall cost of the asset,
along with corporate overheads, then transferred to “Plant-in-Service” and the cost recovered over its
116 See, FERC Uniform System o f Accounts for Electric Utilities, 18 CFR, Part 101, Account 107:
A. This account shall include the total o f the balances o f work orders for electric plant in process o f construction.
B. Work orders shall be cleared from this account as soon as practicable after completion of the job. Further, if a project, such as a hydroelectric project, a steam station or a transmission line, is designed to consist o f two or more units or circuits which may be placed in service at different dates, any expenditures which are common to and which will be used in the operation of the project as a whole shall be included in electric plant in service upon the completion and the readiness for service o f the first unit. Any expenditures which are identified exclusively with units o f property not yet in service shall be included in this account. ...
117 SCE’s 2009 post-test year ratemaking proposal is described in A.07-11-011, Exhibit SCE-11A, Vol. 1 and summarized in D.09-03-025 §14.
118 SCE first brought this methodological error to the Commission’s attention in SCE’s 2006 General Rate Case. See Application 04-12-014, Exhibit 87, page 8.
119 See, FERC Uniform System of Accounts for Electric Utilities, 18 CFR, Part 101, Electric Plant Instruction 3(17):
Allowance fo r funds used during construction (Major and Non-major Utilities) includes the net cost for the period of construction of borrowed funds used for construction purposes and a reasonable rate on other funds when so used, not to exceed, without prior approval o f the Commission, allowances computed in accordance with the formula prescribed in paragraph (a) o f this subparagraph. No allowance for funds used during construction charges shall be included in these accounts upon expenditures for construction projects which have been abandoned.
119
Exhibit No. SCE-10 / Results of Operations / Vol. 01 / Ch. XWitness: P. Hunt
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
Workpaper - Southern California Edison / 2015 GRC - APPLICATION11
operating life. During the period before the asset enters service, the costs are recorded in Construction
Work in Progress (CWIP), FERC Account 107.
The Commission’s decision on our 2009 GRC “stranded” Construction Work In Progress
(CWIP) associated with authorized 2009 capital expenditures. That is, 2010 authorized revenues were
not enough to recover the authorized revenue requirement in 2010 when the 2009 CWIP balance is also
considered. Our Results of Operations (RO) model, which we are required by this Commission to rely
upon and that has also been used and endorsed by the Commission staff, includes estimates of the capital
expenditures in-service dates. Our rate base forecast thus depends on both the capital expenditure
amount and the forecast in-service dates. The rate base forecast, in turn, affects the revenue
requirement. For example, if there is a $100 million project and the annual revenue requirement is $17
million, with an in-service date of June 1, the first year’s revenue requirement would be $8.5 million.
The second year’s revenue requirement would be $17 million. The first year revenue requirement is
pro-rated, but the following year the project would be in rate base for a full year, and the revenue
requirement is for an entire year. Using this simplified example, overlaid with the 4.25 percent and 4.35
percent escalation is graphically depicted in Figure X-9 below.
120
Exhibit No. SCE-10 / Results of Operations / Vol. 01 / Ch. XWitness: P. Hunt
1
2
3
4
5
6
7
8
9
10
11
12
13
14
Workpaper - Southern California Edison / 2015 GRC - APPLICATION
Figure X-9 Illustrative Revenue Requirement Example
i i Revenue Requirement “ ♦ ■Authorized Revenues (4.25% & 4.35% )
Explaining how this error shortchanged our authorized revenues requires some background on
ratemaking. While SCE’s proposal in this GRC is to review and approve a post-test year capital
expenditure forecast, in the event the Commission chooses to use a formulaic approach to setting the
post-test year revenue requirement, at a minimum this error should not be repeated.
1. The “Stranded” Construction Work in Progress Error in the 2009 GRC Adopted
Post-Test Year Ratemaking Formulas
As described in Mr. Shimmel’s testimony in Volume 2 of this exhibit, SCE budgets
capital on an expenditure basis, which represents the company’s outlays for capital projects. Given the
capital-intensive nature of our business, which is especially so for SCE, we must estimate the level of
capital expenditures to ensure we can finance this level of investment. And while we budget by capital
expenditure, many projects require months to construct, process invoices, and eventually close the work
order. We cannot begin to recover the investments until they are providing service to SCE customers.
The common characterization of capital assets serving utility customers is that they must be “used and
useful.” While these projects are being constructed, the monthly expenses being incurred by SCE are
121
Exhibit No. SCE-10 / Results of Operations / Vol. 01 / Ch. XWitness: P. Hunt
1
2
3
4
5
6
7
89
10111213141516171819202122
23
24
25
26
27
28
29
30
Workpaper - Southern California Edison / 2015 GRC - APPLICATION13
recorded in “CWIP.” SCE, like most utilities subject to cost-of-service ratemaking, will carry a balance
in CWIP until such time as a capital asset is placed into service. This CWIP balance will carry forward
from the end of one calendar year into the next. Ratemaking that follows cost-of-service principles
would customarily recognize and link the capital expenditures authorized in year one, but closing
subsequently, to year two when establishing the revenue requirement in year two.
In SCE’s 2009 GRC, DRA witness Greg Wilson endorsed the manner in which SCE’s
Results of Operation (RO) model converts capital expenditures to capital additions:
SCE’s capital exhibits and supporting workpapers (as well as its RO computer model) are organized around capital expenditures. SCE’s capital witnesses provide testimony regarding the magnitude of the direct capital dollars that are estimated to be spent each year, not how much is actually being booked to plant. SCE relies on its RO computer model to manipulate these direct capital expenditures and calculate the corresponding capital additions. DRA has studied SCE’s RO model, and believes that it properly calculates plant additions. Therefore, DRA’s analyses and recommended direct capital adjustments are also stated in terms of capital expenditures. When analyzing data in this format, the impact of recommended adjustments to capital expenditures may not show up in the year in which they are made. For example, suppose a capital project is scheduled to begin construction in 2008, but is not scheduled to be completed until 2009. If DRA was to recommend an adjustment to the 2008 expenditures, there will not be a revenue requirement impact until 2009, when the project is completed, is booked to plant-in-service, and begins earning a return.120
Due to the timing differences between capital expenditures and capital additions, of the
total 2009 capital expenditures the Commission approved in SCE’s 2009 GRC, $1.468 billion121 ($960
million, CPUC jurisdiction) remained in CWIP as of year-end 2009. Note that this $1.468 billion 2009
CWIP balance does not depend in any way on the 2010-2011 capital expenditure forecast the
Commission declined to review, but is based entirely on the capital expenditure forecasts the
Commission did review and approve through the end of 2009.
Figure X-10 below, compares the forecast revenue requirement-holding capital spending
flat at the level authorized in 2009 for the entire three-year GRC cycle (2009-2011).
120 A.07-1-011, Exhibit DRA-13, pp. 8-9.
121 The year-end CWIP balance in SCE’s application was $1.847 billion.
122
Exhibit No. SCE-10 / Results of Operations / Vol. 01 / Ch. XWitness: P. Hunt
1
2
3
4
5
6
7
8
9
10
11
12
13
14
Workpaper - Southern California Edison / 2015 GRC - APPLICATION
Figure X-10 2009 GRC CapEx Constant
2010 & 2011(CPUC Jurisdiction)
In theory, if a utility’s capital expenditure forecast were to be held constant year after
year for an extended period of time and depreciation rates were adequate, the amount of CWIP closing
in a given year would be mostly offset by new entries and asset retirements, thus mitigating the revenue
requirement effect in the subsequent years.
We do not believe the Commission intended to deny continued cost recovery for the very
capital expenditures it authorized in SCE’s 2009 GRC. However, its decision forced us to temporarily
restrain certain capital investments so that over the three-year GRC cycle (2009-2011) cumulative
company spending would mirror authorized revenues. SCE was further constrained by the fact that only
a small portion of authorized GRC revenues are “fungible,” or available to be re-prioritized. In this
application, the vast majority of the proposed revenue requirement is funding either existing ratebase
(2012 authorized, plus the 2013 and 2014 capital additions), or the amount of O&M authorized in the
2012 case. If the methodological error in the 2009 decision were repeated in this case, the only practical
way SCE could adjust spending would be to adjust the timing of capital investment decisions in a
manner that ensured recorded rate base did not contribute to a higher revenue requirement than was
123
Exhibit No. SCE-10 / Results of Operations / Vol. 01 / Ch. XWitness: P. Hunt
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
Workpaper - Southern California Edison / 2015 GRC - APPLICATION15
authorized for years 2016 and 2017. That would cause us to delay capital investment in the 2015-2017
rate case cycle, delaying the delivery of corresponding benefits to our customers.
The Commission endeavors to meet its responsibility to provide utilities subject to cost-
of-service regulation a reasonable opportunity to earn their authorized rates of return.122 In fact, in our
2003 GRC, the Commission rejected the same kind of simplified approach to post-test year ratemaking
it adopted in our 2009 GRC. In that 2003 GRC, after noting its concern with relying on a utility’s
budget-based forecasts,123 the Commission also noted that focusing solely on recorded spending would
overlook the need for stepped-up spending to replace aging infrastructure.124
Based on these considerations, in our 2003 GRC the Commission adopted a post-test year
approach that allowed us to include the capital costs associated with our budget-based forecast, with the
revenue requirement subject to refund if we under-spent capital relative to the authorized forecast. We
continue to believe this 2003 GRC approach was ultimately the most fair, both to our customers and to
our investors, because it most accurately reflects our actual cost of service over the three-year GRC
cycle. I urge the Commission to return to that approach in this 2016 GRC.
But whatever course of action the Commission follows, it must not replicate the
methodology adopted in SCE’s 2009 GRC. With a growing need to expend capital on system utility
infrastructure, review and approval of reasonable post-test year expenditures is necessary for SCE to
122 See, Re Southern California Edison Co., D.04-07-022, §11.3, (mimeo), p. 271:
We start with the proposition that a utility’s opportunity to earn a fair return on the investments made to provide adequate utility service is realized with the adoption of a just and reasonable forecast test year revenue requirement.Then, to judge whether post-test year revenue adjustment provisions are appropriate, we inquire into whether there are, or will be, conditions that might undermine a utility’s opportunity to earn its authorized rate o f return after the test year. Such conditions need not be limited to those encountered 20 years ago, when the Commission was approving attrition adjustments because o f high costs o f utility debt and because the economy was unpredictable and volatile. Interest rates may be lower and the economy may be more stable now, but that does not mean there can be no other conditions that impact the utility’s ability to earn a reasonable return.
123 It should be noted that a utility’s budget represents the most accurate forecast that can be prepared by any entity, and is the single most reliable estimate that can be developed.
124 Id., p. 276:
As we have repeatedly observed in this decision, there is a fundamental problem with budget-based ratemaking that boils down to the fact that budgets are not always implemented as planned.
When older facilities are replaced with new ones, the associated costs are typically much higher than what is included in rates for the original facilities. Moreover, the effect o f this phenomenon is enhanced by the accelerated pace of planned capital spending associated with SCE’s infrastructure replacement program. ...
124
Exhibit No. SCE-10 / Results of Operations / Vol. 01 / Ch. XWitness: P. Hunt
1
2
3456
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
Workpaper - Southern California Edison / 2015 GRC - APPLICATION
have an opportunity to earn its authorized rate of return. However, in its decision on our 2009 GRC, the
Commission rejected our proposal for determining post-test year amounts, citing two reasons:
As we repeatedly observed in prior decisions, there is a fundamental problem with budget-based ratemaking that boils down to the fact that budgets are not always implemented as planned. In addition, no party other than SCE provided or analyzed detailed post-TY plant addition budget forecasts in determining increases.125
Mr. Ron Litzinger addresses the first of these reasons—the “spending flexibility”
principle of forecast test year ratemaking in his testimony in Exhibit SCE-01. As to the second reason
given for not relying on SCE’s post-test year capital forecast, while we are sympathetic to other parties’
resource constraints,126 the Commission should not ignore the evidence of the growing need to expend
capital on aged utility infrastructure and the other reasons supporting our forecasts or to adopt a post-test
year revenue requirement that precludes recovery of some of the very capital expenditures the
Commission authorized.
2. By Not Providing for Separate Escalation of the Other Operating Revenues From
Tariffed Services, the 2009 GRC’s Post-Test Year Ratemaking Mechanism
Shortchanged the Authorized Revenue Requirement
Another flaw in the 2009 adopted post-test year ratemaking mechanism was its treatment
of Other Operating Revenues (OOR). OOR arises from various services, such as late fees, in which
individual customers provide revenues to offset SCE’s revenue requirement, rather than all customers.
Because the utility recovers such costs from individual customers, the revenues from these services
offset the revenue requirement to be recovered from general ratepayers. In other words, the authorized
revenue requirement to be recovered from general ratepayers is “net” of OOR.127
125 Re Southern California Edison Co., D.09-03-025, §14, (mimeo), p. 305.
126 Should other parties in the case make valid contributions that aid the Commission in deciding this issue, their associated resource costs are recoverable through the Commission’s intervenor compensation program.
127 See, e.g., Re Southern California Edison Co., D.91-12-076, (mimeo), p. 116: “Revenue credits are applied against utility costs in determination of net revenue requirement to be included in rates.” See also, Re Pacific Gas and Electric Co., D.99-09-031, (mimeo), p. 2: “ ...Other Operating Revenues ... functioned as an offset or reduction in the authorized 1996 GRC revenue requirement. Since the revenue requirement was reduced by this amount, it was not included for recovery in rates in the GRC decision.” See also, Re Pacific Gas and Electric Co., D.08-06-038, (mimeo), p. 8: “PG&E proposes to credit $1,000 received from the City for the easement to Other Operating Revenue. As a result o f this action, the funds will reduce the future revenue requirements from customers consistent with conventional general rate case cost-of-service ratemaking.”
125
Exhibit No. SCE-10 / Results of Operations / Vol. 01 / Ch. XWitness: P. Hunt
1
2
3
4
5
6
7
8
9
10
11
12
13
Workpaper - Southern California Edison / 2015 GRC - APPLICATION17
As I discussed above, D.09-03-025’s post-test year formula escalates the total 2009
revenue requirement (SCE’s authorized costs). This approach assumes that each of the line items
comprising the overall revenue requirement is escalated at the same rate, including the tariffed service
revenues. However, the fees SCE is allowed to charge customers for tariffed services must be explicitly
approved by the Commission and D.09-03-025 did not authorize SCE to increase any of those fees to
provide for additional revenues. In other words, the decision’s post-test year mechanism implicitly
assumed SCE would be able to increase tariffed OOR by 4.25 percent in 2010 and 4.35 percent in 2011
but did not authorize any increase in the fees that generate that OOR. In 2010 this disconnect created a
$5 million shortfall between the adopted post-test year method and the revenues from fees for tariffed
services, an amount that grew to $10 million in 2011.128
Like the stranded CWIP error I discussed above, the post-test year ratemaking
mechanism the Commission adopts in this 2015 GRC should avoid this kind of methodological
inconsistency. See WP's, p. 6
128 For supporting calculations, please see the workpapers.
126
Exhibit No. SCE-10 / Results of Operations / Vol. 01 / Ch. XWitness: P. Hunt
2015 General Rate Case - APPLICATION INDEX OF WORKPAPERS
EXHIBIT SCE-10, Volume I, Chapter X
DOCUMENT PAGE(S)Producer Price Index for Gasoline, Not Seasonally Adjusted 1-2Annual Gross Capital Additions, 2016-2017, and Cost of Removal by Functional Classification 3-4
Citations to Benefit Escalation Rates from Table X-39 52010 and 2011 OOR Shortfall 6
Workpaper - Southern California Edison / 2015 GRC - APPLICATION1
PRODUCER PRICE INDEX FOR GASOLINE, NOT SEASONALLY ADJUSTED
Exhibit No. SCE-10 / Results of Operations / Vol. 01 / Ch. XWitness: P. Hunt
Exhibit No. SCE-10 / Results of Operations / Vol. 01 / Ch. X Witness: P. Hunt
K>
Bur
eau
of L
abor
Sta
tistic
s
Pro
duce
r P
rice
Ind
ex-C
omm
oditi
es
Ori
gina
l D
ata
Val
ue
Ser
ies
Id:
WP
U05
71N
ot S
easo
nal
ly A
dju
sted
Gro
up:
Fue
ls a
nd r
elat
ed p
rodu
cts
and
pow
erIte
m:
Gas
olin
eB
ase
Dat
e:
1982
00Y
ears
: 20
03 t
o 20
13
Yea
rJa
nFe
bM
arA
pr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
2003
95.7
112.
612
0.4
100.
194
.599
.410
1.4
106.
410
9.9
102.
795
.294
.320
0410
8.1
111.
111
7.0
126.
114
0.5
129.
113
6.1
128.
313
0.9
149.
114
0.3
120.
120
0512
7.9
137.
415
4.3
162.
515
8.2
159.
517
6.5
189.
921
4.2
207.
616
4.7
169.
920
0617
9.4
162.
218
8.5
217.
722
5.2
230.
623
6.2
228.
418
5.7
169.
117
0.5
172.
920
0716
2.0
170.
219
9.8
228.
725
0.9
239.
325
2.7
216.
822
5.6
223.
425
8.4
235.
420
0824
0.0
243.
727
2.4
281.
331
7.0
332.
634
3.8
310.
131
6.1
230.
315
4.0
114.
520
0913
2.1
138.
013
5.0
151.
917
5.5
206.
818
8.1
209.
619
8.0
194.
420
8.5
203.
320
1022
3.4
205.
022
5.4
232.
023
0.2
219.
722
0.5
224.
521
9.1
229.
623
2.8
241.
020
1125
3.0
259.
029
6.2
321.
934
3.8
313.
331
3.1
297.
630
5.7
290.
028
1.7
272.
520
1228
1.8
296.
631
8.2
327.
231
2.6
296.
828
8.6
312.
033
2.1
318.
728
1.5
271.
120
1327
4.7
300.
330
3.3
297.
9
Incr
ease
fro
m 2
004
to A
pril
2013
13
2.6%
Incr
ease
fro
m 2
009
to A
pril
2013
67
.0%
Sou
rce:
Bur
eau
of L
abor
Sta
tistic
s G
ener
ated
on:
May
29,
201
3 (0
9:39
:13
PM
)
Workpaper - Southern California Edison / 2015 GRC - APPLICATION
Workpaper - Southern California Edison / 2015 GRC - APPLICATION3
ANNUAL GROSS CAPITAL ADDITIONS, 2016-2017 AND COST OF REMOVAL
BY FUNCTIONAL CLASSIFICATION
Exhibit No. SCE-10 / Results of Operations / Vol. 01 / Ch. XWitness: P. Hunt
Exhibit No. SCE-10 / Results of Operations / Vol. 01 / Ch. X Witness: P. Hunt
Sou
ther
n C
alifo
rnia
Edi
son
Tota
l C
apita
l Add
ition
s (G
ross
Add
ition
s) a
nd C
OR
- B
y S
tate
and
Ass
et-T
ype
(nom
inal
$00
0)
Ann
ual
Gro
ss A
dditi
ons
Cos
t of
Rem
oval
Func
tiona
l Cla
ss P
lant
Ste
amN
ucle
arHy
dro
Oth
er P
rodu
ctio
n
2013 25
,327
37
1,40
3 10
8,91
2 21
6,31
9
2014 34
,071
174,
216
82,0
0818
,994
2015
2768
,026
72,1
4820
,001
2016
146
50,4
0345
,027
2,56
5
2017 53
,270
169,
277
12,9
14
2013 3,50
719
,860
10,0
391,
904
2014
34,8
959,
629
7,66
82,
755
2015 2,59
19,
028
4,74
1 67
2016
13,1
196,
753
2,97
7 45
2017 7,
040
18,2
91 35To
tal G
ener
atio
n72
1,96
130
9,28
916
0,20
398
,142
235,
461
35,3
1054
,947
16,4
2722
,894
25,3
66
Tran
smis
sion
2,34
7,14
81,
185,
790
1,46
6,40
260
7,92
072
4,27
011
2,80
611
1,29
587
,002
62,5
5649
,409
Dist
ribut
ion
1,25
8,66
51,
662,
837
1,76
5,92
12,
093,
312
1,92
6,02
232
7,05
630
7,91
534
7,22
538
3,59
238
2,31
2To
tal T
&D
3,60
5,81
42,
848,
627
3,23
2,32
32,
701,
231
2,65
0,29
243
9,86
241
9,21
143
4,22
644
6,14
843
1,72
1
Gen
eral
398,
584
331,
539
370,
089
372,
458
331,
892
862
98_
__
Inta
ngib
les
216,
518
361,
246
171,
947
186,
179
221,
578
813
17-
-6
Tota
l Gen
eral
& In
tang
ible
s61
5,10
269
2,78
654
2,03
655
8,63
755
3,47
01,
675
115
--
6
Tota
l Com
pany
(GR
C)
4,94
2,87
73,
850,
702
3,93
4,56
23,
358,
010
3,43
9,22
347
6,84
747
4,27
345
0,65
346
9,04
245
7,09
2
|GR
C G
ross
Add
ition
s +
CO
R
3,82
7,05
3 3,
896,
315
|
Workpaper - Southern California Edison / 2015 GRC - APPLICATION
Exhibit No. SCE-10 / Results of Operations / Vol. 01 / Ch. X Witness: P. Hunt
BE
NE
FIT
ESC
AL
AT
ION
RA
TE
S T
AB
LE
FO
R P
OST
-TE
ST Y
EA
R R
AT
EM
AK
ING
(TA
BL
E X
-39)
,
WIT
H C
ITA
TIO
NS
TO
SO
UR
CE
S
Lin
eN
o.C
ateg
ory
2016
2017
Com
men
tsC
itat
ion
1.M
edic
al P
rogr
ams
- 926
8.00
%8.
00%
Med
ical
esc
alat
ion
rate
Exh
ibit
SCE-
06, V
olum
e 2,
Par
t 1,
p. 7
5,11
. 8-9
2.D
enta
l Pro
gram
s - 9
264.
50%
4.50
%D
enta
l esc
alat
ion
rate
Ass
umed
to e
qual
for
ecas
t den
tal t
rend
rate
for
2014
and
201
5 (E
xhib
it SC
E-06
, Vol
ume
2, P
art
1, p.
77,
11. 2
-4; W
orkp
aper
s fo
r Exh
ibit
SCE-
06,
Vol
ume
2, P
art
1, C
hapt
er V
II, B
ook
C, p
p. 7
7-80
)
3.V
isio
n Se
rvic
e Pl
an -
926
2.00
%2.
00%
VSP
esc
alat
ion
rate
Ass
umed
to e
qual
for
ecas
t VSP
tren
d ra
te f
or 2
014
and
2015
(Ex
hibi
t SC
E-06
, Vol
ume
2, P
art
1, p.
80, 1
1. 17
-18;
Wor
kpap
ers
for E
xhib
it SC
E-06
, V
olum
e 2,
Par
t 1,
Cha
pter
VII
, Boo
k C
, p.
145)
4.D
isab
ility
Pro
gram
s - 9
262.
66%
2.65
%L
abor
esc
alat
ion
rate
Exh
ibit
SCE
-10,
Vol
ume
1, C
hapt
er V
II,
Tabl
e V
II-2
0, p
. 71
5.G
roup
Life
Insu
ranc
e - 9
260.
00%
0.00
%Li
fe e
scal
atio
n ra
te
Ass
umed
to e
qual
for
ecas
t lif
e in
sura
nce
tren
d ra
te
for 2
014
and
2015
(E
xhib
it SC
E-06
, Vol
ume
2,
Part
1, p.
99,
11. 2
2-23
; Wor
kpap
ers
for E
xhib
it SC
E-06
, Vol
ume
2, P
art
1, C
hapt
er V
II, B
ook
C,
p. 2
39)
6.M
isc.
Ben
efit
Prog
ram
s - 9
263.
03%
2.90
%A
&G
non
labo
r rat
e af
ter 2
015
Exh
ibit
SCE
-10,
Vol
ume
1, C
hapt
er V
II,
Tabl
e V
II-2
1, p
. 72
7.E
xecu
tive
Ben
efits
- 92
62.
66%
2.65
%L
abor
esc
alat
ion
rate
Exh
ibit
SCE
-10,
Vol
ume
1, C
hapt
er V
II,
Tabl
e V
II-2
0, p
. 71
8.40
l(k)
2.66
%2.
65%
Lab
or e
scal
atio
n ra
teE
xhib
it SC
E-1
0, V
olum
e 1,
Cha
pter
VII
, Ta
ble
VII
-20,
p. 7
1
cn
Workpaper - Southern California Edison / 2015 GRC - APPLICATION
6Workpaper - Southern California Edison / 2015 GRC - APPLICATION
o(A (A w -n 31 3m c C V)I I I — —e ®re E > =c re « o i - I U K Q
£ H - T J t~ O o °O - a- c ° re o =£ I S i J; I ^3 (0 | o re </) 0)
Of6OLO
o Yfflc a> £Q- Q 0) ° Y £
8<Y■ o■ o
ma> Pi? roL±_ (Y. Y ~
8 2i d
o uo in cn
LLI ^
CN CO UO CO
Exhibit No. SCE-10 / Results of Operations / Vol. 01 / Ch. XWitness: P. Hunt