s02v02p01 - app...expenditures forecast of $875 million, plus the 10 percent contingency, for a...
TRANSCRIPT
An EDISON INTERNATIONAL® Company
(U 338-E)
2015 General Rate Case APPLICATION
Workpapers
GenerationSPVP, Fuel Cell, Catalina SCE-02 Volume 10
N ovem ber 2013
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
Workpaper - Southern California Edison / 2015 GRC - APPLICATION1
I.
SOLAR PHOTOV OLTAIC PROGRAM
A. SCE’s Solar Photovoltaic Program Forecast
1. Introduction and Overview of the Solar Photovoltaic Program (SPVP)
SCE’s Solar Photovoltaic Program (SPVP) is a Commission-approved initiative to install
solar photovoltaic panels in SCE’s service territory, primarily on commercial rooftop space.1- This
program will be in effect through 2015 and, as per the original application, involved the installation of
up to 250 MW of solar generating facilities by SCE. The program was modified in Decision D.12-02-
035, reducing the program installation to 125 MW, with no less than 115 MW of solar generation
facilities absent additional authorization.2 This decision also increased the allowable ground mount
installations from 10 percent of total capacity to 20 percent. The program was further reduced to no less
than 91 MW DC (68 MW AC) in D.13-05-033, which will be accomplished in 2013 with the installation
of the final solar rooftop project.
Solar photovoltaic panels convert sunlight directly into electricity using a semiconductor
material. They use no water to generate electricity and have no moving parts. Photovoltaic (PV) panels
generate direct current (DC) electricity, and electrical devices called inverters convert the output to
alternating current (AC) electricity for export to SCE’s electrical distribution system. Each 1.35 MW of
DC yields approximately 1 MW of AC. The Commission found that this easily deployable technology
“can help advance California’s broad goal of developing renewable energy and specifically help make
progress toward the state’s emphasis on developing distributed rooftop solar PV projects.”3
The SPVP projects range primarily in size from 1 to 2 MW each and are installed on
commercial and industrial rooftop space in SCE’s service territory.4 These projects fill an existing gap
in the solar industry market for solar installations of this size and will encourage the development of
more distributed generation projects within this range.5 As originally envisioned, SCE developed these
4 SCE’s Application in A.08-03-015 states that “SCE envisions the individual Solar PV Program installations to be in the 1 to 2 MW range. As the program proceeds, however, some installations may be larger or smaller than this range due to
1
Exhibit No. SCE-02 / Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
2Workpaper - Southern California Edison / 2015 GRC - APPLICATION
1 facilities over the five-year construction program life, initially targeting approximately 50 MW annually,
2 and with no more than ten percent of the program consisting of ground-mounted solar PV. This build
3 out plan was modified to 25 MW per year and the ground-mount limit increased to twenty percent with
4 the adoption of D.12-02-035.6
5 During 2008-2012, SCE constructed a total of 24 sites, all of which were delivering
6 energy to the grid by December 31, 2012. In 2013, SCE has one additional site under construction
7 which is expected to be completed by the third quarter of 2013. A summary of all the sites is included in
8 Table I-1 below.
6 D.12-02-035, Attachment 1, p.2See workpapers p. 114
2
Exhibit No. SCE-02 / Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION3
Table I-1 SPVP Sites 2008-2013
SPVP Site OnlineDate
CAISOCOD
MW AC MW DC [3 ] Inverters
SPVP001 - Fontana[4] 8/7/2008 11/26/2008 2.00 2.44 4SPVP002 - Chino 9/24/2009 12/10/2009 1.00 1.22 2SPVP003 - Rialto 7/19/2010 3/1/2011 1.00 1.22 2SPVP005 - Redlands 12/27/2010 11/24/2012 2.50 3.40 5SPVP006 - Ontario 1/10/2011 8/25/2011 2.00 2.55 4SPVP007 - Redlands 12/29/2010 11/24/2012 2.50 3.20 5SPVP008 - Ontario 12/30/2010 8/25/2011 2.00 2.85 4SPVP009 - Ontario 1/10/2011 8/25/2011 1.00 1.41 2SPVP010 - Fontana 5/18/2011 1/8/2013 1.50 2.25 3SPVP011 - Redlands 11/10/2011 Pending[2] 3.50 5.02 7SPVP012 - Ontario 12/29/2010 8/25/2011 0.50 0.77 1SPVP013 - Redlands 9/15/2011 Pending[2] 3.50 4.93 7SPVP015 - Fontana 12/19/2011 1/15/2013 3.50 4.69 7SPVP016 - Redlands 5/18/2011 Pending[2] 1.50 1.75 3SPVP017 - Fontana 12/14/2011 Pending[2] 3.50 4.50 7SPVP018 - Fontana 5/23/2011 11/24/2012 1.50 1.94 3SPVP022 - Redlands 11/15/2010 8/25/2011 2.00 3.09 4SPVP023 - Fontana 5/12/2011 1/16/2013 2.50 3.86 5SPVP026 - Rialto 8/26/2011 Pending[2] 6.00 8.60 12SPVP027 - Rialto 11/27/2012 Pending[2] 2.00 2.62 4SPVP028 - San Bernardino
12/20/2011 Pending[2] 3.50 4.86 7
SPVP032 - Ontario 12/22/2011 Pending[2] 1.50 1.74 3SPVP033 - Ontario 12/12/2011 Pending[2] 1.00 1.27 2SPVP042 - Porterville 12/28/2010 11/24/2012 5.00 6.77 10SPVP044 - Perris 9/14/2012 Pending[2] 8.00 10.15 16SPVP048 - Redlands Pending[1] Pending 5.00 6.77 10
25 SPVP Sites 67.50 91.42
[1] SPVP 048 is currently under construction
[2] Projects are complete and online, but are pending CAISO review of SCE’s application for COD status
[3] Unless otherwise specified, the energy output in this filing follows the common convention within the PV industry, which is to refer to output as PV panel DC output.
[4] Located on the same rooftop as SPVP015, the sites share a CAISO meter. In the list above, we count these two projects as one site.
3
Exhibit No. SCE-02 / Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
Workpaper - Southern California Edison / 2015 GRC - APPLICATION
We forecast the Test Year 2015 Operation and Maintenance (O&M) expenses to be
$4.298 million ($2012) and the Capital Expenditures for 2013-2017 to be $38.909 million (nominal
dollars). These expenditures are necessary to continue providing reliable service at low cost, while
complying with applicable laws and regulations, and maintaining safe operations for employees and the
public. This testimony supports the reasonableness of SCE’s forecasts.
2. Regulatory History
a) Decision Establishing SPVP
On June 18, 2009, the Commission issued D.09-06-049 authorizing SCE to
install, operate, and maintain up to 250 MW of utility-owned solar photovoltaic (PV) generating
facilities. D.09-06-049 also doubled the size of the program by adding an additional 250 MW
Independent Power Producer (IPP) component, whereby SCE must hold solicitations to procure up to
250 MW of distributed generation bids from IPPs under power purchase agreements.7
SCE proposed in Application (A.) 08-03-015 to install the utility-owned portion
of the program, at a base cost of $875 million (2008 dollars) in direct capital expenditures, or $3.50/W
with a 10 percent contingency. In D.09-06-049, the Commission found reasonable SCE’s direct capital
expenditures forecast of $875 million, plus the 10 percent contingency, for a total reasonableness cap of
$962.5 million.8 See workpapers pp. 106a-cb) Decision Modifying SPVP
On February 11, 2011, SCE filed a Petition for Modification requesting the
program be reduced to no more than 125 MW.9 SCE stated program objectives had been achieved (e.g.,
bolster the 1-2 MW solar PV market) and program goals can continue to be realized in the reduced
program at better cost savings to SCE customers. The Commission agreed that a program reduction
would preserve the intent of the solar program while also reducing costs for customers, thus partially
granting SCE’s Petition for Modification through D.12-02-035.10 As a result, SCE’s solar program was
modified to 125 MW (with no less than 115 MW absent additional authorization), and increasing
D.09-06-045, Ordering Paragraph 2
D.09-06-049, (mimeo), pp. 44-45.
A.08-03-015.
—| See workpapers pp. 104-105
See workpapers pp. 97-989
10See workpapers pp. 106d-f
D.12-02-035, Findings of Fact, pp. 29-30. D.12-02-035 denies SCE’s request to allocate the 250 MW removed from the UOG and IPP portions of the program to a new solicitati on called “IPP Revised,” which aimed for procurement of lower cost solar facilities.
See workpapers pp. 112-113
4
Exhibit No. SCE-02 / Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
Workpaper - Southern California Edison / 2015 GRC - APPLICATION5
See workpapers pp. 106g-i
ground-mount installations to twenty percent (equivalent to 25 MW) to accommodate for SCE’s existing
obligations.
In D.12-02-035, the Commission reduced not only the program size, but
proportionately reduced the cost caps previously found reasonable in D.09-06-049. The O&M expense
cap was reduced to approximately $20.655 million (2008 dollars), and the direct capital expenditures
cap reduced to $481.25 million (2008 dollars, with $437.5 million in direct capital plus a 10 percent
contingency). The total costs continue to be based on $3.50/W ($3.85/W including the 10 percent
contingency), with costs in excess of $3.85/W subj ect to a reasonableness review.11
On July 27, 2012, SCE filed a second Petition for Modification, requesting the
program be reduced to 91 MW. SCE stated additional changes that took place in the market justified a
further reduction in the utility owned generation portion of the program. SCE stated that program goals
had been successfully achieved and that customers would realize a greater cost savings with the program
reduction.12 In D.13-05-033, the Commission agreed with SCE’s assessment that market changes
between the first and second Petition for Modification filings warranted a further reduction in the utility-
owned portion of the SPVP program, and thus established that the utility-owned portion of the SPVP
program be capped at 91 MW.13 As well, the Commission made conforming changes to the O&M and
capital estimates to reflect the program reduction. The reasonable cost estimates over the program
period was reduced to approximately $15.037 million (2008 dollars) in O&M expenses, and $350.35
million (2008 dollars) in direct capital expenditures ($318.5 million direct capital plus a 10 percent
contingency). These total costs continue to be based on $3.50/W ($3.85/W including contingency), with
costs in excess of $3.85/W subject to a reasonableness review.14
5
Exhibit No. SCE-02 / Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
Workpaper - Southern California Edison / 2015 GRC - APPLICATION
II.
SPVP CAPITAL FORECAST
A. Capital Forecast
SCE is not requesting additional capital for construction of any solar PV sites (expected to
conclude in 2013) beyond the amounts authorized in D.09-06-049, and as modified by D.12-02-035 and
D.13-05-033. Table II-2 below shows the summary capital expenditures for 2013 - 2017.
See workpapers p. 88Table II-2
Capital Expenditure Forecast 2013 - 2017(Nominal $Millions)
Year 2013 2014 2015 2016 2017 TotalForecast Capital
Expenditures $31.50 $0.425 $1.035 $0.269 $5.68 $38.909
For 2013, the capital forecast includes finishing the construction of the final utility-
owned SPVP site (SPVP 048), the installations of the Electrical Fault Protection System and the
Emerson Monitoring and Control system on the entire utility-owned SPVP fleet, as well as retrofitting
the sites for personnel safety mitigation. The SPVP 048 is a 6.77 MW DC plant located in Redlands,
CA, and is expected to be completed in the third quarter of 2013. The Electrical Fault Protection System
is an automated protection system that shuts down an inverter if adverse power flows are detected in
order to prevent fires and other failures that would damage the buildings or cause harm to the people
who occupy them. The Emerson Monitoring and Control system is an upgrade to the current system that
will add monitoring and reporting functions to all the sites. SCE will use the Emerson system to
monitor, control, and maintain the SPVP sites. Personnel safety mitigation activities include
identification and marking pathways of travel, identification and marking the parameter boundaries, sky
light protection, ladder access railing, and bridges and platform to cover cable trays.
The capital forecast for years 2014-2016 is significantly lower than previous years with
the conclusion of the construction program and installation of the aforementioned systems. The capital
forecast for these years reflects equipment such as inverters, transformers, and other capital designated
replacement components. There is a substantial increase in forecast capital spending in 2017 because
SCE anticipates a significant number of inverters to be replaced in that year. Inverter manufacturers
state that an inverter lifespan is between 7-10 years. Given SCE’s experience with SPVP 001 and 002,
the lifespan is expected to be on the shorter end of the range, at seven years. Since the majority of
6
Exhibit No. SCE-02 / Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
1
2
3
4
5
6
7
8
9
10
11
12
13
14
Workpaper - Southern California Edison / 2015 GRC - APPLICATION7
SCE’s utility-owned sites were built in 2010, the additional capital in 2017 is planned for the expected
influx of inverter replacements.
B. 2008-2012 Recorded and Authorized Capital and Forecast Expenditures
In compliance with Ordering Paragraph 7 of D.12-11-051 (SCE’s 2012 GRC decision), SCE is
submitting the following Figure II-1 below, which summarizes SPVP recorded capital expenditures
during 2008 through 2012. This figure also shows forecast expenditures for 2013 through 2017, and the
2012 forecast authorized by the Commission in the 2012 GRC.
See workpapers p. 89Figure II-1
Solar Recorded And Authorized Capital And Forecast Expenditures($000 Nominal)
As shown above in Figure II-1, SCE’s forecast for 2014-2017 is substantially less than recorded
expenditures during 2008-2012. This is primarily due to the expected conclusion of SPVP construction
at the end of 2013. As mentioned above, the 2014-2017 forecasts consist primarily of capital
replacements parts necessary to maintain the solar facilities. The 2013 forecast includes capital budgets
approved in D.09-06-049 and as modified through D.12-02-035 and D.13-05-033 to complete
construction of the final solar site, installation of the Electrical Fault Protection and Emerson systems on
the entire solar fleet, as well as fitting applicable sites for personnel safety mitigation.
7
Exhibit No. SCE-02 / Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
1
2
3
4
5
6
7
8
9
10
11
Workpaper - Southern California Edison / 2015 GRC - APPLICATION
SCE’s recorded 2012 expenditures are lower than the amount authorized in the 2012 GRC,
primarily due to the cancellation of two SPVP proj ects, College of the Desert and Delano. Due to
significant interconnection upgrade costs, SCE decided that building at those sites was not in the best
interest of SCE ratepayers and subsequently cancelled the projects. SCE’s 2012 capital expenditures
were lower also due to SCE’s filing of a second Petition for Modification with the Commission on July
27, 2012, requesting that the utility-owned portion of the program be reduced to 91 MW.15 After filing
its petition, SCE was less aggressive in searching for new sites that would fill the gap created by the
College of the Desert and Delano cancellations, however SCE continued to search for potential
replacement projects should the second Petition for Modification be denied. On May 23, 2013, the
second Petition for Modification was approved by the Commission, and the utility-owned portion of the
SPVP program concluded at 91 MW.
15 Southern California Edison Company’s (U 338-E) Petition for Modification of Decision No. 12-02-035.
See workpapers p. 106g-i
8
Exhibit No. SCE-02 / Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
Workpaper - Southern California Edison / 2015 GRC - APPLICATION9
III.
SPVP O&M FORECAST
A. O&M 2015 Test Year Forecast
Since construction of new facilities concludes in 2013, SCE’s Test Year 2015 forecast consists
o f the ongoing operations and maintenance of the utility-owned solar fleet. SCE will operate and
maintain 25 solar project sites at the completion of the construction phase of the program for a total of
91 MW. Each site will be unique and have differing types and quantities of solar power plant equipment
based on the size of each site and the manufacturer of the equipment.
Test Year 2015 O&M estimates are based on previously established cost per MW for the SPVP
sites for all operations and maintenance activities and include labor and materials necessary for
maintaining the plant and lease expenses. Except for site leases, there is not sufficient O&M history on
the SPVP sites to utilize a forecasting method base d only on recorded data, therefore the O&M forecast
relies more on budgeted forecasts that are based on recorded history. Figure III-2 summarizes the SPVP
Labor and Non-Labor O&M recorded costs from 2008 through 2012, and the Test Year (TY) 2015
forecast of $4.298 million.
9
Exhibit No. SCE-02 / Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
1
2
3
4
5
6
7
8
9
10
11
12
Workpaper - Southern California Edison / 2015 GRC - APPLICATION
<------------------- Forecast >
As shown above in Figure III-2, labor expenses have increased gradually from 2008
through 2012 reflecting the construction and maintenance efforts for the SPVP projects, and are
expected to further increase in 2013. The labor reduces in 2014 and 2015 to a level appropriate for the
ongoing maintenance of the completed SPVP sites. Non-labor expenses increased substantially in 2011
through 2012 reflecting the expense-related construction non-labor components as well as the
maintenance non-labor components including roof leases, and are expected to further increase in 2013.
The non-labor reduces in 2014 and 2015 to the level appropriate for ongoing maintenance and roof
leases for the 91 MW of SPVP capacity.
1. O&M Forecast Components
In preparation for this 2015 GRC, SCE reassessed O&M activities as identified in the
2012 GRC and, based on program experience, SCE defined a new set of activities that give a more
accurate portrayal of O&M activities going forward. These O&M activities can be broken down into
10
Exhibit No. SCE-02 / Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
Workpaper - Southern California Edison / 2015 GRC - APPLICATION11
three areas, (a) Inspections and Maintenance, (b) Miscellaneous Expenses, and (c) Site Leases.16 These
O&M categories more accurately capture O&M ac tivities for the SPVP plants given O&M experience
from 2010-2012 and correctly categorize how O&M budgets will be planned in future years.
a) Inspections and Maintenance
Project O&M includes the inspections and maintenance of components of the
SPVP facilities such as the Supervisory Control and Data Acquisition (SCADA) system, switchgears,
transformers, and so on. Embedded within the inspections and maintenance of different components of
an SPVP facility is the forecast expenditure for lab or, non-capitalized spare parts and miscellaneous
expenses. SCE’s forecast cost for the Inspection and Maintenance for items (1)-(5) below is $19,240 per
MW DC ($2012), and was calculated based on an itemized forecast of future expenditures.
Beginning in 2014, existing Power Production Department staff who operate and
maintain other SCE utility-owned facilities will perform the inspections and maintenance for the SPVP
facilities. These activities require approximately 5 .5 full time employees (FTE), including roles such as
project manager and supervisor, Instrument/Control and Electrical (ICE) technicians, operator, and
engineering support. The labor cost associated with these personnel is embedded within the project-
specific O&M forecast described below. Inspection and Maintenance expenses are recorded in FERC
Account 549. Descriptions for different types of inspection and maintenance activities are listed in
detail below.
(1) SCADA Inspection and Maintenance
The SCADA gathers, records and transmits data about the performance of
each SPVP site and presents the data to the operator in the form of a Human Machine Interface (HMI).
The SCADA presents the operator with valuable and necessary information to insure safe and reliable
operation of the plants. Since these systems are computer-based, they require routine maintenance
including troubleshooting, software upgrades, security enhancements, virus and malware prevention,
etc.
16 Of the items identified in SPVP’s original and updated testimony in A.08-03-015, Array Cleaning and Inspection now falls into item (e), “Other Equipment Inspection and Maintenance,” Inverter Misc. Maintenance is now defined as item (d), “Inverter Inspection and Maintenance,” DAS Monitoring has been expanded to item (a), “SCADA Inspection and Maintenance,” and Roof Leases remained as is and listed as item (f). Items (c) and (d) were newly defined so as to capture all major components of the SPVP sites.
11
Exhibit No. SCE-02 / Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
Workpaper - Southern California Edison / 2015 GRC - APPLICATION
(2) Switchgear Inspection and Maintenance
The switchgear and main circuit breaker act as the point of “demarcation”
between the Solar Plant and the SCE electrical grid. The switchgear has meters (to measure the amount
of energy flowing into/out of the site), breakers (which control power flow and allow for isolation), and
replays (which provide circuit protection) of the plant equipment prior to it reaching the SCE
Distribution Grid. These systems require routine maintenance including inspection, cleaning, testing
and repair.
(3) Transformer Inspection and Maintenance
The transformer is used to change voltage levels. SCE’s electrical grid
has many voltages that are used depending on how far energy needs to be transmitted. Higher voltages
allow more energy to be sent on the same size wires with lower losses due to the natural resistances of
the wire. The inverters at the SCE sites produce 208 volts of AC power. Our typical transmission line
from the SPVP solar rooftop sites, to the customers, is 12,000 volts. The transformer steps up the
inverter output voltage from the 208 volts to 12,000 volts, so it can be sent to the customer.
(4) Inverter Inspection and Maintenance
The inverter is the primary energy conversion device on the site. This
device takes the Direct Current from the panels and converts it to Alternating Current for use by
customers.
(5) Rooftop Inspections and Maintenance
As needed, to investigate roof leaks, noises, disturbances with warehouse
occupants, SCE conducts rooftop inspections and maintenance. If the warehouse owner or occupant
discovers an abnormality with their rooftop, SCE is responsible to send a crew to survey the rooftop
where SPVP equipment is installed. SCE may also be responsible to remove portions of an SPVP
facility to appropriately survey the rooftop. If damages are discovered resulting from an SPVP facility,
then it is SCE’s responsibility to repair said damages.
b) Miscellaneous Expenses
The Miscellaneous expense category generally refers to preventative action,
facility maintenance (i.e., safety paint, vegetation management), and repairs for all manufactured
equipment. The sites have multiple pieces of equipment that require periodic attention in order to
maximize the usefulness of the assets. Examples of other expense include, but are not limited to, wire
12
Exhibit No. SCE-02 / Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
Workpaper - Southern California Edison / 2015 GRC - APPLICATION13
and cabling, racking, equipment rental and repairs, transportation, training, and facility maintenance
(i.e., paint, fencing, vegetation management).
Miscellaneous expenses also include array inspection and cleaning, as identified
in the SPVP program application A.08-03-015. After conducting the initial cleaning for SPVP 001, SCE
determined that at the time it was costly and not effective to justify continue array cleaning as originally
planned. There were three main reasons that led to this conclusion. One, array cleaning was more
costly than anticipated; local regulations required the use of deionized water and capture of used water.
Two, the amount of soiling is greater than expected and would require cleaning more frequently to
materially increase solar production. Three, array cleaning requires a site to be shut down, which means
SCE would lose production output during the time the site was shut down. Therefore, the benefit of
increased kWh resulting from the cleaner panels is diminished due to the loss of production due the
shutdown of sites during the cleaning. As a result, SCE concluded natural processes such as wind and
rainfall would do an adequate job of array cleaning. In the future, should it become advantageous and
cost effective to conduct array cleaning as outlined in A.08-03-015, SCE may elect to conduct regular
array cleanings.
SCE’s forecast cost for Miscellaneous Expenses for the activities described above
is $3,440 per MW DC ($2012), and was calculated based on an estimate of forecast expenditures. Also
included in Miscellaneous Expenses are Added Facility Charges, which are fixed payments that SPVP
pays to SCE T&D for interconnecting the SPVP sites to the grid. SCE’s Test Year 2015 forecast for
Added Facility Charges is $1,648 ($2012) per MW, and was calculated based on historical costs.
Miscellaneous Expenses and Added Facility Charges expense record in FERC Account 549.
c) Site Leases
Site leases on all rooftop sites and the single ground mount site (SPVP 042) are
fixed lease payments that escalate on their anniversary in conjunction with general Consumer Price
Index escalation rates. New site construction will conclude with the completion of SPVP 048 in the
third quarter of 2013. SCE’s forecast for Site Leases is $22,901 per MW ($2012), and was calculated
based on the scheduled lease payments for all the sites. Site Leases expense is recorded in FERC
Account 550.
B. Development of O&M Forecast by FERC Account
Historical O&M data from 2009-2012 includes expenses in excess of that required for the 2015
Test Years due to expenses that relate to new site construction through 2013. Beginning in 2014, during
13
Exhibit No. SCE-02 / Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
Workpaper - Southern California Edison / 2015 GRC - APPLICATION
the Test Year 2015, and for the years going forward, utility-owned SPVP sites will be operated and
maintained like all other utility-owned generation facilities in the Power Production Department. As
such, O&M expenditures in Test Year 2015 are based on the previously approved cost per MW, which
encompasses the forecasted maintenance expenses. Table III-3 below shows the previously approved
cost per MW and the correlation to our 2015 GRC O&M forecast.
See workpapers pp. 18a-bTable III-3
SPVP O&M Cost per M W
2012 GRC $/MW Forecast (2009$)
2012 GRC$/MW
91 MW Cost (2012$M)
Revised Allocation $/MW 2015 GRC
91 MW Cost (2012$M)
ActivityArray Cleaning/Inspection 8,000 8,702 0.792Inverter Misc. Inspection 5,100 5,548 0.505DAS Monitoring 1,200 1,305 0.119Total Plant Maintenance 14,300 15,556 1.416 24,330 2.214Roof Lease Costs 30,000 32,442 2.952 22,901 2.084
In the 2012 GRC it was believed that roof lease costs would approach $30,000 per MW. The
costs at this time are approximately $23,000/MW, which would likely have been higher if SCE
continued the program past the current 91 MW. O&M expenses for maintenance were forecast at
approximately $16,000/MW in the 2012 GRC, but the experience to date indicates a higher expense of
about $24,300/MW. The total expense forecast for the 2012 GRC and the 2015 GRC per MW of
installed solar capacity remains essentially the same at approximately $47,200/MW. As noted above in
Section 1, the O&M activities have slightly changed from those envisioned when the program began.
However, the costs are in line with the original forecast as shown in Chapter IV SPVP Reasonableness
Review below.
1. FERC Account 549 - Miscellaneous and Other Power Generation Expenses
a) Description of Account
FERC Account 549 includes the cost of labor and expenses incurred in the
operation and maintenance of SPVP sites. The Test Year 2015 SPVP O&M expense forecast is $24,330
per MW DC ($2012). The Labor forecast for this account is $0.555 million and the Non-Labor forecast
is $1.659 million, providing a total TY forecast of $2.214 million. The 2008 through 2012 recorded
expense history and our forecasts for 2013 through 2015 for this account are summarized in Figure III-3
below.
14
Exhibit No. SCE-02 / Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
1
2
3
4
5
6
7
8
9
10
11
12
13
Workpaper - Southern California Edison / 2015 GRC - APPLICATION15
See workpapers pp. 1-18 and 18b
Figure III-3 SPVP FERC Account 549
Recorded 2008-2012/Forecast 2013-2015(2012 $000)
b) Development of Test Year Forecast
Upon Commission approval of the program in June 2009, SCE began ramping up
the staffing efforts to adequately support the project growth schedule for 2009 and future years. The
increased labor costs through 2012 are reflective of the increased number of personnel required to meet
the increased SPVP project installation schedule. Program staffing during the construction phase will
remain high until construction is completed at the end of 2013. Staffing will decline at the end of 2013
to that necessary for continued maintenance.
The increasing Non-labor costs for 2010 through 2012, and forecast for 2013
reflect the increased number of projects that were installed during those years, and the associated O&M
activities required for project maintenance. In 2013 the costs include installation of systems including
the Electrical Fault Protection System, and the Emerson Monitoring and Control system, required for
safe and reliable operation of SPVP facilities. O&M costs associated with site maintenance will reduce
to a maintenance required level, which is significantly lower than during the construction period.
15
Exhibit No. SCE-02 / Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
Workpaper - Southern California Edison / 2015 GRC - APPLICATION
SCE developed its 2015 expense forecast primarily based on the previously
planned cost per MW for the SPVP development. As discussed above, the previously planned O&M
expense of approximately $16,000 requires revising up to $24,300/MW, but that is offset by the
reduction from the roof lease cost. In FERC 549 for both Labor and Non-Labor expense, the 2012
expense serves as an appropriate base estimate for our 2015 forecast, with a forecast reduction
adjustment for the 2015 TY. In D. 04-07-022 and D. 89-12-057, the CPUC stated that if costs have
shown a trend in a certain direction over three or more years, the last recorded year is an appropriate
base estimate. Labor expenses have been increasing for five years from 2008-2012, so we used 2012
recorded as the starting base estimate, but we adjusted the 2012 base downward to reflect our belief that
there will be reduced staff in 2015 given that construction of new facilities will conclude in 2013. Non
labor expenses fluctuated significantly from 2008-2012, but this was also due to the timing of the
construction of new facilities as well as the online dates for the various projects, as opposed to
unpredictable factors (such as weather) suggested by the CPUC in D. 04-07-022 and D. 89-12-057 that
would support the use of an average of recorded years as the test year methodology. Since all projects
except SPVP048 were online by the end of 2012, SCE used the 2012 non-labor recorded expense as its
starting base estimate but reduced the expense to the level necessary for the continued site maintenance
forecasted for 2015.
2. FERC Account 550 - Rents
a) Description of Account
This account includes all rents of property of others used, occupied, or operated in
connection with SPVP projects. The Test Year 2015 SPVP O&M expense forecast is $22,901 per MW
DC ($2012). This account does not contain Labor expense. The Non-Labor forecast for this account is
$2.084 million for the 2015 TY forecast. The 2008 through 2012 recorded expense history and our
forecasts for 2013 through 2015 for this account are summarized in Figure III-4 below.
16
Exhibit No. SCE-02 / Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
1
2
3
4
5
6
7
8
9
10
11
12
Workpaper - Southern California Edison / 2015 GRC - APPLICATION17
See workpapers pp. 19-36 and 36a
Figure III-4 SPVP FERC Account 550
Recorded 2008-2012/Forecast 2013-2015(2012 $000)
2.400 ------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
. 11112008 2009 2010 2011 2012 2013 2014 2015
□ Labor (std escl) ■ N on-Labor (std escl) □ O ther (not escl)
Labor o o o o o o o o
Non-Labor 0 172 155 756 2.127 2,034 2,034 2,084
Other 0 0 0 0 0 0 0 0
Total 0 172 155 756 2,127 2,084 2,084 2,084
<-------------------------Forecast--------------------------->
b) Development of Test Year Forecast
SCE developed its 2015 exp ense forecast primarily based on the previously
planned cost per MW for the SPVP development. As discussed above, the previously planned Roof
Lease expense of approximately $30,000 requires revising down to $22,901 /MW. In FERC 550 for
Non-Labor expense we utilize a Last Recorded Year with a forecast decrease adjustment for the 2015
TY. In D. 04-07-022 and D. 89-12-057, the CPUC stated that if costs have shown a trend in a certain
direction over three or more years, the last recorded year is an appropriate base estimate. Lease Non
labor expenses have been increasing each year, which provides a base for estimating the test year 2015.
To this base we add an increase adjustment of six months lease for one site that reflected only six
months of 2012 recorded expense.
Costs in this account are expected to remain constant for 2013-2015 and for years
going forward, as these lease costs are fixed and only increase annually with escalation.
17
Exhibit No. SCE-02 / Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
Workpaper - Southern California Edison / 2015 GRC - APPLICATION
IV.
SPVP REASONABLENESS REVIEW
A. Reasonableness Review Requirement
In D.09-06-049, the Commission found that the reasonableness review of SPVP’s capital
expenditures and O&M costs should be conducted in the GRC proceeding, and review of SCE’s
operation of the facilities should be conducted in the Energy Resource Recovery Account (ERRA)
proceeding. In D.09-06-049, the Commission found reasonable SCE’s cost estimates (in 2008 dollars)
of $41.31 million in O&M and $875.0 million in direct capital expenditures over the 2008 through 2014
program period, and authorized SCE to establish the Solar Photovoltaic Program Balancing Account
(SPVPBA) to record capital costs and O&M expense associated with the SPVP.17 As discussed by Mr.
Snow in Exhibit SCE-10, Volume 1, Part 2, SCE is proposing to eliminate the SPVPBA in this
proceeding and to recover the SPVP rate base and O&M costs in Test Year 2015 GRC base rates.
In accordance with D.09-06-049, this testimony presents for Commission review the capital
expenditures and O&M expenses associated with installation of the 24 completed SPVP sites
(84.65 MW DC).
1. Reasonableness Threshold
In A.08-03-015, SCE provided an estimate of megawatts installed and associated direct
capital expenditures that would be incurred during the five year SPVP. As indicated in SCE’s direct
testimony, Year 0 estimated a time frame from April 2008 to December 2008 for installation of the first
projects totaling 5 MW, and capital expenditures of $25 million.
Table IV-4 summarizes target capital cost of the SPVP and associated installation
schedule as provided in direct testimony to A.08-05-013.18
^ — See workpapers pp. 97-9817 D.06-09-049, (mimed), pp. 44, 45.
18 Please see SCE’s Rebuttal Testimony filed in A.08-03-0 15 on October 3, 2008, Confidential Attachment 1 for details on how target capital cost was developed.
^ — See Confidential workpapers pp. 1-23
18
Exhibit No. SCE-02 / Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
1
2
3
4
5
6
7
8
9
10
11
Workpaper - Southern California Edison / 2015 GRC - APPLICATION19
Table IV-4Summary o f Capital Costs o f Solar P V Program
(2008$)
Year Capital (Million$) MW Installed Estimated Time Frame
0 $25 5 April '08 to Dec '08
1 $174 50 2009
2 $174 50 2010
3 $174 50 2011
4 $174 50 2012
5 $154 45 2013
Total $875 250
The capital cost schedule in Table IV-4 assumed a Commission decision would be issued
on the SPVP in 2008; however D.09-06-049 did not approve the SPVP until June 18, 2009. The timing
of issuance of D.09-06-049 moved Year 0 of the SPVP installation to 2009. Given this delayed
installation schedule, the reasonableness review threshold as provided in SCE’s application testimony is
applied on a program year basis, rather than a calendar year basis.
Conclusion of Law in D.09-06-049 states that a “ [r]eview of all SPVP costs should be
conducted in SCE’s GRC proceeding.”19 SCE’s target cost for the Solar PV Program is $875.0 million,
or $3.50/W DC.20 The reasonableness threshold is $962.5 million ($ 2008), or $3.85/W DC ($2008),
which is the base case amount plus a reasonable 10 percent contingency.21 If SCE’s direct capital
expenditures are less, on a $/W basis than the reasonableness threshold, then those capital expenditures
will be deemed to be reasonable.
19
Exhibit No. SCE-02 / Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
Workpaper - Southern California Edison / 2015 GRC - APPLICATION
The cap for direct capital expenditures has reduced to correspond to revised program
installed MW goals approved by the Commission. D.12-02-035 issued February 16, 2012, reduced the
SPVP program by half for the 2008-2012 program period, thus reducing the direct capital expenditures
to $481.25 million ($2008) ($427.5 million ($2008) plus a 10 percent contingency).22 D.13-05-033
issued May 23, 2012, further reduced the program cap to 91 MW, thus concurrently reducing the capital
expenditure cap to $350.35 million ($2008) ($318.5 million ($2008) plus a 10 percent contingency.23
In all three program build out structures, the direct capital expenditure limit remained
$3.85/W ($2008) ($3.50/W ($2008) plus a 10 percent contingency), with the requirement that the cost
cap be subject to a reasonableness review.24
The reasonableness threshold is based on installed watt of direct current (DC) electricity.
Solar photovoltaic panels generate DC electricity, and inverters convert the output to alternate current
(AC) electricity for export to SCE’s electrical distribution system. Each MW AC is equivalent to 1.35
MW DC.
Table IV-5 identifies Reasonableness Thresholds for Direct Solar PV Program Capital
Costs on an installed $/W basis.
See workpapers p. 11022 D. 12-02-035, Conclusion 4.4 (p.27).
23 D. 13-05-033, Conclusion 6.3 (p.16).
24 D.09-06-049, Conclusions of Law 10 (p.57); D.12-02-035, Conclusion 4.4 (p.27); D.13-05-033, Conclusion 6.3 (p.16).
See workpapers p. 118
See workpapers pp. 103, 110 and 118
20
Exhibit No. SCE-02 / Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
1
2
3
4
5
6
7
8
9
10
11
12
13
Workpaper - Southern California Edison / 2015 GRC - APPLICATION21
Table IV-5Reasonableness Review Threshold For Direct Solar P V Program Capital Costs25
(2008$)
Expenditures Incurred During
$/W
Year 0 5.50Year 1 3.83Year 2 3.83Year 3 3.83Year 4 3.83Year 5 3.76
Though the Solar PV Program estimates a base case total installed cost of $3.50 per watt,
the average cost of installation will vary from year to year. As indicated in SCE’s testimony in the
SPVP application, the capital costs would be higher in the early years but decrease as SCE’s experience
increases.26
In its SPVP application, SCE estimated the costs incurred during the start-up phase of the
program (listed as year “0”) to be $25 million ($ 2008) for up to 5 MW of installed PV generation,
which produces an average installed cost of $5.50/W ($ 2008) for that year. This estimate was based
upon discussions with solar industry experts, and vendor quotes, combined with a forecasted schedule
for installation of SPVP projects. Please refer to Rebuttal Testimony (A.08-03-015) Workpapers for
data on original capital cost estimate. See Confidential workpapers pp. 1-232. ^ SPVP Costs are below the Reasonableness Threshold
SCE’s actual capital expenditures for the start-up phase of SPVP, Year “0” were at the
reasonableness threshold of $5.50/W DC. SCE incurred $20.4 million in capital expenditures for the
See workpapers pp. 123, 125 and 126
25 These threshold amounts will be escalated to nominal year amounts for use in reasonableness review. Consistent with SCE’s testimony in A.08-03-015, because direct capital expenditures will be recorded in nominal dollars during each year of the project, the $/W values will be adjusted for general price inflation between 2008 and later years. SCE proposed to adjust the constant 2008 dollars to nominal dollars by multiplying the $/W costs in 2008 dollars by the ratio of the Gross Domestic Product Price Index for the calendar year being reviewed to the Gross Domestic Product Price Index for 2008.
26 SCE’s Application Testimony, p. 43.
21
Exhibit No. SCE-02 / Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
Workpaper - Southern California Edison / 2015 GRC - APPLICATION
See workpapers pp. 123, 125 and 126
first 3.71 MW DC of SPVP installations, or $5.50/W DC installed. These expenditures are deemed
reasonable pursuant to D.09-06-049.
Year “ 1” SPVP construction began ramping up with the build of 27.04 MW DC. Capital
expenditures are higher than the reasonableness threshold of $3.83/W DC. SCE incurred $118.8 million
in capital expenditures for the additional MW, which translates to $4.39/W DC.
Year “2” SPVP construction increased significantly resulting in 41.19 MW DC of new
build. Capital expenditures are lower than the reasonableness threshold of $3.83/W DC. SCE incurred
$154.6 million in capital expenditures for the additional MW, which translates to $3.76/W.
Year “3” SPVP construction began to taper off with the construction of 12.77 MW.
Capital expenditures are lower than the reasonableness threshold of $3.83/W DC. SCE incurred $30.3
million in capital expenditures for the additional MW, which translates to $2.37/W.
Although Years 0 and 1 capital expenditures were at or higher than the established cost
cap for SPVP direct capital expenditures in those particular years, remaining years are considerably
lower. The cumulative total for the SPVP program in 2008 dollars shows that capital expenditures at
this point in the program are in fact lower than the program cost cap of $3.85/W ($2008). The
cumulative total of capital expenditures in for years 2008-2012 is $316.4 million ($2008), therefore SCE
is below the cost cap at $3.74/W ($2008).
3. Capital
Capital expenditures can be categorized into two expenditures types: (1) Hardware
Expenditures, and (2) Installation Labor. Descriptions of the categories are included below.
a) Hardware Expenditures
Hardware expenditures represent SCE’s costs to procure the solar panels and
other project-related equipment (such as racks to mount the panels, inverters, data acquisition
equipment, circuit breakers and fuse boxes, metering, and transformers to increase the panel output
voltage to levels utilized in the electrical distribution system).
(1) Solar Panel
SCE utilized solar panels from three manufacturers, First Solar, Sunpower,
and Trina. First Solar FS series two rigid thin film modules were utilized for SPVP 001, 002 and 003.
These panels convert sunlight directly into electricity utilizing layers of cadmium telluride (CDTE)
semiconductor materials. First Solar panels are rated at 72.5 watts DC under standard test conditions
and have a 25-year limited power output warranty. Sunpower and Trina panels were used for the
22
Exhibit No. SCE-02 / Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
Workpaper - Southern California Edison / 2015 GRC - APPLICATION23
remaining SPVP sites. Sunpower and Trina panels have a higher panel rating than First Solar, such that
sites with Sunpower and Trina panels produced more MW per panel.
Sunpower panels were used for ten SPVP sites.27 These panels convert
sunlight directly into electricity utilizing 96 monocrystalline modules per panel protected by tempered
glass. Sunpower panels are rated up to 305 watts DC under standard test conditions and have a 25-year
limited power output warranty. Trina panels were used for the remaining thirteen SPVP.28 These panels
convert sunlight directly into electricity utilizing 72 multicrystalline modules per panel protected by
tempered glass. Trina panels are available in various ratings ranging from 285 through 305 watts DC
under standard test conditions and have a 25-year limited power output warranty.
(2) Inverters and Balance of System
All solar PV modules, regardless of technology, generate direct-current
(DC) power. SCE must convert this DC power to alternating current (AC) power to use in its
distribution system. Inverters perform this conversion. SCE plans to utilize inverters by two different
manufacturers for future SPVP installations, Satcon Technologies and Xantrex.
Satcon PVS-500 Powergate inverters are sized to generate 500 kW AC,
and are designed to interconnect to the distribution grid. The inverters are supplied with an inter
connection voltage of three phases, 480 VAC nominal. As a result of the design for grid
interconnection, the inverters are outfitted with many system protections in place including: inverter
on/off switches, Inverter Over Current Fault protection, Line Frequency Controls, etc. If any of these
system protections detect a deviation from a safe range operation, safety controls will automatically
isolate the system, or parts of the system, from the grid.
The Xantrex GT500kW Grid-Tied Photovoltaic inverter is a three phase
power conversion system that is designed to generate 500kW AC.
Solar PV systems also include conduit, wire, and combiner boxes, called
Balance of System (BOS) components. In order to allow the solar array to achieve the proper operating
voltage of a nominal 600 volts DC, modules must be wired in series (imagine multiple batteries in a
flashlight) into strings. The strings are then terminated in parallel using specially designed
27 SPVP 005, 007, 011, 013, 015, 016, 017, 026, 028, and 044.
28 SPVP 006, 008, 009, 010, 012, 018, 022, 023, 027, 032, 033, 042, and 048.
23
Exhibit No. SCE-02 / Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
Workpaper - Southern California Edison / 2015 GRC - APPLICATION
combiner/fuse boxes that provide over-current protection to the series strings, before sending the
combined DC power to the inverter.
(3) PV Module Mounting Systems
SPVP systems re quire racks on which to attach the panels. Racking
systems vary and can be scalable, ballast and non-ballast-railed, have penetrating and non-penetrating
designs, and different wind rated to capacities.
(4) SCADA System
The Supervisory Control & Data Acquisition System (SCADA) gathers,
records and transmits data about the performance of each SPVP site and presents the data to the operator
in the form of a Human Machine Interface (HI). The SCADA System presents the operator with
valuable and necessary information to insure safe and reliable operation of the plants. The SCADA
System includes weather sensory equipment that will enable SCE to evaluate impact of weather
conditions experienced on the quantity of power output. Additionally, the Data Processing Gateway
(DPG) receives data from the SCADA System which is transmitted to the CAISO and SCE Generation
Control Center. Data provided to these entities inc lude operational data on a real time basis. The
SCADA System also archives historical data related to the operation of the SPVP sites in databases
which allow for trend analysis as well as alarm and event historical analysis.
(5) Interconnection Equipment
Interconnection Equipment includes equipment necessary for
interconnecting the SPVP projects to the SCE distribution grid. SPVP projects will connect at low
voltages (less than 4 kV) and medium voltages (greater than 4 kV). Standard equipment used for
interconnection includes: transformers; switchgear; meters; fuses; breakers; pad mounted switches; and
standard switchgear protective relays. The interconnection equipment required for each voltage level is
determined on a project specific basis.
b) Installation Expenditures
(1) Scope
Installation consists of SCE’s expenditures to install the Generating
Facility Equipment on the project site including: Site Selection, Engineering, Permitting, Installation
and Commissioning, Project Management and Oversight.
24
Exhibit No. SCE-02 / Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
Workpaper - Southern California Edison / 2015 GRC - APPLICATION25
(2) Description of Installation Activities
(a) Site Selection
The site selection process includes performing initial analysis of a
building’s potential to qualify for inclusion in the SPVP, including rooftop surveys and site walks with
building owners. Some preliminary engineering activities may occur during the site selection process to
determine if a potential roof is compatible with the requirements of a solar energy project.
(b) Engineering
Once a suitable site has been selected, engineering activities begin.
Engineering activities include: reviewing the buildings structural drawings, marking the site to identify
array layout, and creating drawings that clearly define requirements for installation of the solar projects.
(c) Installation and Commissioning
Installation activities include the actual act of placing the racks on
the rooftops, mounting the panels to the racks, and installing all of the Balance of System components.
Once all Installation activities have been completed, Commissioning begins. Commissioning is the
process of turning on the system, testing and notation taking, and troubleshooting any problems.
(d) Project Management and Oversight
Project Mana gement and Oversight activities include overview of
all activities from Engineering to Commissioning projects in accordance with all applicable laws and
regulations, in accordance with SCE’s internal policies, and meet deadlines and budget requirements.
4. Operation & Maintenance Expenses
As previously discussed, SPVP incurs expenses related to Operations and Maintenance
on a project and program specific basis. Project O&M expenses include the activities necessary for
maintaining plant equipment and lease expenses for each project site. SCE contracted with US-Most to
monitor, operate, and maintain SPVP sites. US-Most is an engineering, technology, consulting, and
construction company that focus on renewable energy for Utility and Federal markets. The US-Most
team has extensive operations and maintenance experience in the solar industry, as well as other
renewable energy technologies including wind and geothermal. US-Most monitored, operated, and
maintained the sites beginning in 2009 and continued in 2012. Going forward, SCE plans to conduct
such activities in-house as construction ends. A detailed description of the activities that make up
Project and Program O&M is discussed in the Proj ect O&M Forecast Costs portion of the SPVP
25
Exhibit No. SCE-02 / Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
Workpaper - Southern California Edison / 2015 GRC - APPLICATION
Forecast Testimony. Please refer to that portion of testimony for a detailed description of each activity
associated with Project O&M.
a) Recorded Program and Project Operations and Maintenance Expenses
Expenses for Project and Program O&M recorded in the SPVPBA from 2008 -
2012 totaled $ 22.8 million. These costs are lower than the projected amount identified in D.13-05-033
for a 91 MW DC program.
b) Recorded Roof Lease Costs
Roof lease expenses recorded in the SPVPBA from 2008 - 2012 totaled $2.8
million. These costs are for commercial roof leases that SCE entered into with building owners to
locate, construct, and operate SPVP projects.
Recorded roof lease costs are higher than expected for the SPVP program for a
variety of reasons. When SCE started the SPVP program, the idea of leasing roof space for PV panel
installations was a novel concept. There was no re al market reference pricing in existence because the
SPVP differed from most large-scale rooftop PV deployments in that it was for large roof building that
would not otherwise qualify for net energy metering. Roof space owners then had the opportunity to set
the market price for lease payments. Additionally, the Independent Power Producer (IPP) component of
the SPVP instilled a new competition for roof space in high solar-potential areas, inflating leasing costs.
See workpapers p. 124
26
Exhibit No. SCE-02 / Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
Workpaper - Southern California Edison / 2015 GRC - APPLICATION27
See workpapers pp. 150a-b
V.
SCE'S FUEL CELL PROJECT
A. Introduction and Overview of the Fuel Cell Project
As discussed in the testimony in Exhibit SCE-10, Volume 1, SCE requests that the Commission
terminate the current memorandum account treatment of the Fuel Cell Program and transfer recovery of
these costs to base rates. Therefore, in this testimony, SCE presents a background of SCE’s Fuel Cell
Program, which was approved by the Commission in D.10-04-028, and SCE requests that the
Commission approve SCE’s 2015 O&M test year forecast of $0.669 million for two fuel cell sites.
A fuel cell converts a source fuel, such as natural gas, into electrical current through an
electrochemical reaction. Fuel cell technology generates electricity more efficiently than other
similarly-sized combustion technologies, resulting in lower emissions of greenhouse gases, and because
fuel cells do not burn natural gas, minimal emissions of nitrogen oxide, sulfur dioxide, and particulate
matter. Fuel cells have been designated as “Ultra-Clean” by the California Air Resources Board
(CARB) and exceed all 2007 CARB standards.
SCE’s fuel cell project at University of California Santa Barbara (UCSB) was completed in 2012
and utilizes an electric-only fuel cell technology. The project at California State University San
Bernardino (CSUSB) is expected to be completed in before the end of 2013 and utilizes a combined heat
and power fuel cell technology. The fuel cell system at CSUSB is designed to operate at close to 70
percent total system efficiency by utilizing the fuel cell’s exhaust heat to supplement CSUSB’s hot
water heating system. A description of the selection of the fuel cell sites can be found in SCE’s Fuel
Cell Program direct testimony in A.09-04-018.29
1. Regulatory History
install, operate, and maintain three utility-owned fuel cells (UCSB, CSUSB, and California State
University Long Beach (CSULB)). Decision No. 10-04-028 authorized SCE recovery of $19.1 million
a) Decision Establishing the Fuel Cell Program
On April 14, 2010, the Commission issued D.10-04-028 authorizing SCE to
in capital and $8.9 million in O&M, exclusive of fuel.
See workpapers pp. 151-16029 See A.09-04-018, Exhibit SCE-01, p. 9-15.
27
Exhibit No. SCE-02 / Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
Workpaper - Southern California Edison / 2015 GRC - APPLICATION
See workpapers p. 150d
Subsequently, SCE concluded that it should not go forward with the third
installation at CSULB and provided testimony supporting its decision in the 2012 GRC.30 Fuel Cell
Energy (FCE) petitioned to modify D.10-04-028 to clarify that SCE should seek an alternate host site for
the third^nstallation. Although SCE and DRA opposed FCE’s petition, the CPUC determined in D.12-
04-011 that SCE attempt to identify an alternate site within one year. The CPUC further authorized SCE
to develop and complete a third fuel cell installation at an alternate site, should the project be able to be
completed within the budget limits and conditions established in D.10-04-028. Following detailed
feasibility studies at two sites previously identified in the initial development activities for the fuel cell
program, SCE has determined that a third fuel cell installation cannot be completed33 within the
parameters of D.10-04-028, and consequently will not pursue a third fuel cell installation.
b) Creation of the Fuel Cell Program Memorandum Account
Decision No.10-04-028, Ordering Paragraph No. 4.b states that SCE shall record
actual capital and O&M costs in a Fuel Cell Program Memorandum Account (FCPMA). The balance
shall be transferred monthly to the generation sub-account of Base Revenue Requirement Balancing
Account (BRRBA), as long as the amounts are no higher than the estimates approved in the decision.
Actual capital expenditures less than or equal to $19.1 million are deemed reasonable. Actual O&M
expenses less than or equal to $8.9 million over the ten year life of the program are also deemed
reasonable. The CPUC currently reviews SCE’s FCPMA expenses annually in SCE’s Energy Resource
Recovery Account (ERRA) Review of Operations proceedings.
2. Request to Eliminate the FCPMA
In Exhibit SCE-10, Volume 1, SCE requests that the Commission terminate the current
memorandum account treatment of the Fuel Cell Program and transfer recovery of these costs to base
rates.32 By doing so, the Commission will be able to review 2015 and future Fuel Cell Program costs in
the GRC proceedings and not in the ERRA. The CPUC denied SCE’s similar request in SCE’s 2012
GRC decision33 due to delays and modifications in the program, as well as the relatively short amount of
time since the memorandum account had been established. SCE has more experience with the program
See workpapers pp. 161-16430 Exhibit SCE-84, Update Testimony (October 24, 2011).
31 See Workpapers titled “Report of Southern California Edison Company Regarding Efforts to Identify an Alternative Fuel Cell Site Pursuant to Decision 12-04-011,” dated May 30, 2013.
32 See testimony of Mr. Snow in Exhibit SCE-10, Volume 1. See W O fkpapefS p p . 165-170
28
Exhibit No. SCE-02 / Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION29
now, having completed one fuel cell project, nearing completion of the second, and has entered into
long-term service agreements for maintenance. Thus, SCE believes it can forecast with relative
certainty test year O&M expenses.
Because SCE’s request in this application relates to approval of 2015 test year costs, the
reasonableness of 2012-2014 O&M and capital costs recorded in the FCPMA will continue to be
reviewed in SCE’s ERRA proceeding.
3. Capital Expenditures Forecast
Figure V-5 is shown below, in compliance with D.12-11-051 Ordering Paragraph 7.
See workpapers pp. 147-150
9
10
Figure V-5 Fuel Cell Program
Recorded, Authorized and Forecast Capital Expenditures
The fuel cell project at UCSB was completed in 2012 and the fuel cell project at CSUSB
will be online in 2013. SCE’s forecast of 2013 capital expenditures for the CSUSB fuel cell project is
Continued from the previous page33 D.12-11-051, p. 592.
29
Exhibit No. SCE-02 / Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
1
2
3
4
1
5
6
7
8
9
10
11
Workpaper - Southern California Edison / 2015 GRC - APPLICATION
less than $1 million with no additional capital expenditures forecast beyond 201334. Per D.12-11-051
Conclusions of Law 60, the reasonableness of the capital expenditures recorded in the FCPMA will be
addressed in SCE’s 2014 ERRA review proceeding.
4. Operation & Maintenance (O&M) Forecast
ee workpapers pp. 129-146"I Figure V-6 Fuel Cell Program
Recorded and Adjusted 2008-2012/Forecasted 2013-2015 FERC Account 549
(Constant 2012$)
a) Description of Account
SCE records Fuel Cell Program O&M expenses in FERC Account 549. FERC
Account 549 includes the O&M cost of labor, material used, and expenses incurred in the operation of
the Fuel Cell Program.
b) Recorded and Forecast Costs
The itemized forecast for FERC Account 549, as shown in Figure V-6 consists of
labor and non-labor. The labor portion of the forecast is the market reference point for a Manager -
34 WBS Element CG0-00-GP-PS-000070.
30
Exhibit No. SCE-02 / Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
Workpaper - Southern California Edison / 2015 GRC - APPLICATION31
Program Contract 3. This Full Time Equivalent (FTE) will provide project management and program
contract oversight necessary to support the ongoing safe, compliant, and reliable operation of the fuel
cells. The FTE will interface with the host univers ities, including outage scheduling, and will oversee
numerous vendor service agreements.
The non-labor portion of the forecasts includes ten year Long Term Service
Agreements (LTSA) with the manufacturers of each fuel cell for ongoing maintenance of each unit.
Also included in the non-labor forecast are telecommunications and data services, interconnection
facilities charges, water treatment system service a greement, site maintenance service agreements, and
air quality permit certification and renewal.
c) Development of Test Year Estimate for Account 549
SCE’s Fuel Cell Program has no recorded O&M expenses until 2012, and 2012
did not include a full year of costs to use as a starting point from which to develop a forecast estimate;
therefore SCE chose the Itemized Forecast method for the Fuel Cell Program labor and non-labor. Since
the UCSB project was not operational until September 2012, the 2012 O&M recorded data does not
represent an entire calendar year and does not include any costs associated with the LTSA for this
project. As mentioned earlier, the fuel cell project at CSUSB is not expected to be operational until
2013, and therefore the 2012 O&M recorded data does not include any costs for the CSUSB project.
Because of this, the most appropriate O&M forecasting methodology is an Itemized Forecast. Table V-
6 identifies 2012 recorded Fuel Cell Program O&M costs and the 2013 - 2015 forecast, by project,
along with SCE program management labor for both sites.
Table V-6SCE Fuel Cell Program: 2012-2015 O&M
Calendar year 2012 dollars
2012Recorded
2013Forecast
2014Forecast
2015Forecast
UC Santa Barbara $863 $39,020 $85,576 $88,229
CSU San Bernardino $0 $228,155 $432,030 $467,800
SCE Labor $5,483 $112,500 $112,500 $112,500Total Fuel Cell Program $6,346 $379,675 $630,106 $668,529
31
Exhibit No. SCE-02 / Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
Workpaper - Southern California Edison / 2015 GRC - APPLICATION
VI.
CATALINA GENERATION
A. Introduction
SCE provides electric service to the approximately 5,000 permanent residents and 750,000
annual visitors of Santa Catalina Island, which is located approximately twenty-seven miles off the
California coast. SCE’s service territory covers the entire Island, and includes the cities of Avalon and
Two Harbors, as well as rural areas located in Catalina’s rugged interior.
Currently, six diesel engine generators located at SCE’s Pebbly Beach Generating Station
(PBGS) in the city of Avalon provide power generation to Catalina residents and visitors. Diesel fuel
for the generators is delivered from refineries on the mainland to Catalina in tanker trucks, which are
transported to Catalina by barge. The fuel is then transferred to storage tanks, which in turn feed the
various engines as needed. The control operators and plant equipment operators at the station monitor
electrical load as it fluctuates throughout the day to ensure the generators meet the customer demand.
Generated electricity flows to a substation and then is distributed through three circuits (Hi Line,
Interior, and Wrigley) at 12 kilovolts (kV). Through numerous transformers located close to customers,
the 12 kV electricity is stepped down to service voltages for general use. Catalina is a closed electrical
system; electricity generated and distributed on Catalina is isolated and self-contained, and cannot be
obtained from the mainland.
SCE’s total generation capacity totals 12 megawatts (MW), which includes six diesel generators
(9.4 MW), twenty-three 65 kilowatt (KW) micro turbines (1.5 MW), and one energy storage battery (1.0
MW). Generation exhaust emissions are heavily regulated by the South Coast Air Quality Management
District (SCAQMD), and extensive air emissions monitoring and control equipment has been installed to
meet operating permit requirements.
1. Forecast O&M Expenses and Capital Expenditures
The following tables provide Catalina Generation’s O&M expense and capital forecasts,
which are described and supported in this chapter.
32
Exhibit No. SCE-02 / Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
Workpaper - Southern California Edison / 2015 GRC - APPLICATION33
Table VI-7 Catalina Generation
Summary o f2013-2015 O&M Forecast(Constant 2012 $000)
Account Activity 2015549.140 Catalina Generation Expenses $4,594
Total O&M Expenses $4,594
Table VI-8 Catalina Generation
Summary o f2013-2017 Capital Expenditures Forecast(Nominal $000) ]
________________Activity____________________2213________ 2214________ 2015________ 2016________ 2017________ TotalPBGS Generation Automation Installation $800 $3,505 $0 $0 $0 $4,305Projects less than $1 Million_____________ $1,680______ $1,960__________$420_________$310_________ $60______ $4,430
Total Expenditures $2,480______ $5,465__________$420_________$310_________ $60______ $8,735
2. Comparison of 2012 GRC Request, Authorized, and Recorded
In the 2012 GRC, SCE requested Catalina Generation O&M expenses of $5.149 million
and was authorized $4.913 million. SCE recorded O&M expenses of $4.194 million.
Expenses were lower than authorized in 2012 for several reasons. First, there were no
unplanned generation outages in 2012. Second, some planned maintenance work was rescheduled to
2013. Lastly, costs incurred for replacement of catalysts were lower than anticipated as a result of some
scheduling delays.
B. O&M Expenses
1. Catalina Generation O&M Expenses
Catalina Generation’s O&M expenses include all costs related to Catalina’s generation
assets. The expenses incurred for SCE’s electric distribution assets on Catalina Island are recorded in
the appropriate chapters within T&D’s testimony. FERC Account 549.140 includes the expenses related
to operating, maintaining, and repairing SCE’s Catalina Generation assets, the auxiliary apparatus and
systems, including the emergency generator, compressed air, emission control and monitoring systems,
pumps, diesel fuel storage tanks, compressors, and ventilation equipment, and the supervision and
management costs for generation personnel. This account also includes various miscellaneous expenses,
33
See workpapers pp. 187-188
Exhibit No. SCE-02 / Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
Workpaper - Southern California Edison / 2015 GRC - APPLICATION
including ordering and handling diesel fuel oil, spare parts, general and administrative support staff,
urgent automotive repair, tools, and hazardous waste documentation and compliance reporting.
Table VI-9 Catalina Generation O&M Expenses
FERC Account 549.140 Recorded and Adjusted 2008-2012/Forecast 2013-2015
(Constant 2012 $000)
Recorded Forecast2008 2009 2010 2011 2012 2013 2014 2015
Labor $1,744 $1,584 $1,984 $2,034 $2,230 $1,915 $1,915 $1,915Non-Labor $2,357 $3,421 $3,369 $2,286 $1,964 $2,679 $2,679 $2,679
Total $4,100 $5,005 $5,353 $4,319 $4,194 $4,594 $4,594 $4,594
Ratio of Labor to Total 43% 32% 37% 47% 53% 42% 42% 42%
Basis of Forecast: Five-Year AverageBasis of Labor/Non-Labor Split: Five-Year Average
a) Cost Forecast
Expenses in this account significantly fluctuate from year to year depending on
the extent of maintenance and repair work required for the generation assets and related equipment.
Costs have varied over the years for three primary reasons;
1) Catalina’s Gas, Water and Electric utilities share staff and expenses: Catalina
is the hub for all three of SCE’s utilities on the island. The amount of work
required for the different types of equipment vary from year to year. Annual
workloads can vary significantly for a variety of reasons. For instance,
fluctuations can result from different maintenance schedules for equipment,
responses to emergency or inspections, or emerging situations such as storms.
As a result, in one year, electric O&M costs may be down, while the costs
recorded to Gas and Water O&M may increase.
2) Capital projects: Personnel on Catalina are called upon to work on both
capital and O&M projects, doing everything from design work, to project
management, to daily supervision of the work. As projects wind up or down,
34
See workpapers pp. 171-186
Exhibit No. SCE-02 / Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
Workpaper - Southern California Edison / 2015 GRC - APPLICATION35
the recorded O&M costs will either decrease or increase, as time is charged to
a capital work order.
3) Maintenance of Generation Equipment: The generators on Catalina undergo
scheduled and unscheduled maintenance activities. For example, in 2009,
SCE performed maintenance on its emission control equipment, and in 2010,
SCE performed major overhauls on four of its six diesel generators. With the
addition of the micro-turbines, these costs will tend to fluctuate even more
than they have in the past.
The variability in workload over the years affects both labor and non-labor
collectively. For instance, SCE personnel may be performing routine maintenance on one generator,
and experience problems with another generator at the same time, and have to call in contract resources.
SCE may also be working on a gas or water matter , and similarly have to bring in contract resources to
handle a temporary increase in workload due to unscheduled maintenance on one of the generators or
turbines. Since most of this fluctuation cannot be predicted very well (for instance, it depends on
weather and unpredictable equipment problems), SCE has determined that a five-year average is the best
methodology to forecast costs for 2015.
35
Exhibit No. SCE-02 / Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
Workpaper - Southern California Edison / 2015 GRC - APPLICATION
C. Capital Expenditures
1. PBGS Generation Automation Project
Figure VI-7 PBGS Generation Automation Project
Recorded 2008-2012/Forecast 2013-2017(Nominal and Constant 2012 $000)
See workpapers p. 190
2008 2009 2010 2011 2012 2013 2014 2015 2016 2017Nominal $ $23 $201 $963 $2,591 $1,853 $800 $3,505 $- $- $-2012 Constant $ $28 $232 $1,059 $2,777 $1,853 $775 $3,321 $- $- $-
Nominal $ -2012 Constant $
The PBGS Generation Automation project was approved in the 2012 GRC. The project,
which was originally expected to be completed by year-end 2012, has been delayed slightly, but
significant work has been performed ($5.6 million through 2012) and the project is expected to be
completed in 2014. The project was delayed until the work scope specified in the 2009 Settlement
Agreement between SCAQMD and SCE for NOx control was fully understood. This delay allowed the
generation automation design to be integrated with several other Catalina projects, including the new
NaS battery, Micro Turbines installation, and the Control Room Betterment, Main Building Betterment,
and Security Betterment projects. All of these systems must work in parallel, and the Automation
system design needed to be integrated with peer sy stems that were being subsequently installed.
The project cost has also increased from $4.6 million (in the 2012 GRC) to $9.9 million,
due to unforeseen complexities, which include inte rference removal, design, programming, equipment
purchase, construction, and commissioning costs. The commissioning period has been extended from 4
months to 14 months because Catalina operations allow only one unit to be shut down at a time for
36
Exhibit No. SCE-02 / Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
Workpaper - Southern California Edison / 2015 GRC - APPLICATION37
engine control modification, final connections, and commissioning. The longer commissioning period
increases the costs of contractors, construction management, and engineering support. The actual cost
o f major equipment has been about three times the original estimate, and the costs of programming and
construction have been higher than originally estimated after they were put out for competitive bidding.
SCE’s Supervisory Control and Data Acquisition (SCADA) enhancement project will
automate the monitoring and control of the generation system and provide real time data on the
maintenance and operations activities of this system. This installation will provide one integrated
control system that can dispatch controlling actions using various options that are system knowledge-
based. The control system uses programmed knowledge of systems to make controlling decisions
regarding the optimization of the island’s electrical system.
Installing the SCADA system for Catalina generation will:
• Improve the labor-intensive process of starting the generating units
• Reduce the station operating complexity
• Maximize the air quality benefits of the micro turbines and NaS battery use
• Improve diesel generator fuel economy
• Reduce diesel engine NOx emis sions to help meet SCAQMD emission requirements
• Improve plant system safety and reliability
• Provide automatic dispatch capability
a) Cost Forecast
Figure VI-7 shows the estimated costs for the SCADA project. Cost estimates are
based on work scope developed from an engineering assessment, budgetary quotations from vendors,
and published reference book for cost estimating like “R.S. Means.” Detailed cost analysis is provided
in the Catalina capital workpaper titled “PBGS Generation Automation Project.”
\ , ,
\ — See workpapers p. 190
37
Exhibit No. SCE-02 / Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
1
2
3
4
5
6
7
8
9
10
11
12
Workpaper - Southern California Edison / 2015 GRC - APPLICATION
2. Projects Less Than $1 Million
Figure VI-8Various Catalina Generation Projects Less Than $1 Million
Forecast 2013-2017(Nominal and Constant 2012 $000)
$2,500
2013 2014 2015 2016 2017Nominal $ $1,680 $1,960 $420 $310 $602012 Constant $ $1,627 $1,857 $389 $280 $53
Nominal $ ^ ^ ^ 2 0 1 2 Constant $
Catalina Generation also has severa l projects that are forecast to cost less than $1 million.
Figure VI-8 captures the estimated costs for these projects, which include:
• Antenna Consolidation/Platform Installation
• SCR Catalyst Replacement
• Diesel Unit 8 Zero-T Overhaul
• Diesel Unit 15 Zero-T Overhaul
• Plant Asphalt and Concrete Rep lacement
• Diesel Engine Water Treatment Program
• Perimeter Fencing Replacement
• Corrosion Control Program
• Sequence of Events Recorder
38
Exhibit No. SCE-02 / Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION39
1 • Fuel Meter System Upgrade
2 • Diesel Engine Vibration Continuous Monitoring System
3 • Diesel Engine House Enclosures
4 D. Recorded Capital Expenditures Compared to Previous GRC Authorized
5 In compliance with Ordering Paragraph 7 of D.12-11-051, Figure VI-9 below summarizes
6 Catalina Generation’s recorded capital expenditures during 2008 through 2012, as well as forecast
7 expenditures for 2013 through 2017, and the 2009 and 2012 forecasts adopted by the Commission in our
8 2009 GRC25 and 2012 GRC.33
Figure VI-9 Catalina Generation
Recorded, Authorized and Forecast Expenditures
See workpapers pp. 187-189
35 D.09-03-025
36 D.12-11-051
39
Exhibit No. SCE-02 / Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
2015 General Rate Case - APPLICATION INDEX OF WORKPAPERS
EXHIBIT SCE-02, Vol. 10
DOCUMENT PAGE(S)Solar Photovoltaic ProgramO&M Workpapers for FERC Account 549 1-18Response to DRA-Verbal-010 Q.C.01 18aSolar Program O&M Forecast 18bO&M Workpapers for FERC Account 550 19-36Solar Program O&M Forecast 36aO&M Workpapers for FERC Account 546 37-46O&M Workpapers for FERC Account 548 47-56O&M Workpapers for FERC Account 551 57-66O&M Workpapers for FERC Account 553 67-76O&M Workpapers for FERC Account 554 77-86Capital Expenditure Workpapers 87-92Excerpts from D.09-06-049 93-106Excerpts from A.08-03-015 106a-cExcerpt fromA.08-03-015, Petition for Modification 106d-fExcerpt fromA.08-03-015, Second Petition for Modification 106g-iExcerpt from D.12-11-051, Ordering Paragraph 7 106jExcerpts from D.12-02-035 107-114Excerpts from D.13-05-033 115-120Recorded Cost Reasonableness 121-128Fuel Cell ProgramO&M Workpapers for FERC Account 549 129-146Capital Expenditure Workpapers 147-150Excerpts from D.10-04-028 150a-dA.09-04-018 Fuel Cell Program Testimony Excerpt 151-160A.10-11-015 2012 GRC Update Testimony- SCE 84 161-164A.09-02-013 A.09-04-018 Fuel Cell - Report of Southern California Edison Company (U 338-E) Regarding Efforts to Identify an Alternative Fuel Cell Site Pursuant to Decision 12-04-011
165-170
CatalinaFERC Account 549.140 - Operations and Maintenance of Generation Facilities 171-186
Catalina Generation Capital Workpapers 187-189PBGS Generation Automation Project Capital Forecast 190FERC Account 546.140 191-198FERC Account 548.140 199-206FERC Account 551.140 207-214FERC Account 552.140 215-222FERC Account 553.140 223-230ERC Account 554.140 231-238
Workpaper - Southern California Edison / 2015 GRC - APPLICATION1
Exhibit SCE-02, Volume 10 WORKPAPERS
Solar Photovoltaic Program
O&M FERC Account 549
Witness: Rudy Perez
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
2Workpaper - Southern California Edison / 2015 GRC - APPLICATION
Beginning of Workpapers for:
FERC Account: 549 Miscellaneous Other Power Generation Expenses
A ctiv ity: 549 - SOLAR PHOTOVOLTAIC PROGRAM
Witness: Rodolfo L Perez
Forecast Method
Chosen
2012$ (000)
Recorded
2012
Forecast
2015
Labor Last Recorded Year Adj. 1,731 555
Non-Labor Last Recorded Year Adj. 3,038 1,659
O ther N/A 0 0
Total 4,769 2,214
Description of Activity:
This activity includes the cost of program labor and expenses incurred in the operation and m aintenance of S o lar Photovoltaic
Program (S P V P ) projects.
Final Cost Centers included in this activity (S ee Appendix A for additional detail):
F525699 F527623 F527624 F527625 F527626 F527649 F527651 F528076 F528080 F528084
F528336
Exhibit No. SCE-02 / Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION3
F E R C A c c o u n t : 5 4 9 M is c e lla n e o u s O th e r P o w e r G e n e ra t io n E x p e n s e s
A c tiv ity : 5 4 9 - S O L A R P H O T O V O L T A IC P R O G R A M
W itn e s s : R o d o lfo L P e re z
D E T E R M IN A T IO N O F R E C O R D E D /A D J U S T E D
I R e c o rd e d P erio d
$ (000)
2008 2009 2010 2011 2012
F E R C F o r m 1 R e c o rd e d (N o m in a l $)
Labor 0 0 0 3 146
N on-Labor 0 113 77 11,590 1,749
O ther 0______________0______________ 0______________0_____________0
Total 0 113 77 11,593 1,895
A d ju s tm e n ts - (N o m in a l $ ) - s e e A p p e n d ix B fo r a d d itio n a l d e ta il
Labor 102 474 964 1,488 1,585
Non-Labor 348 798 759 1,306 1,289
O ther 0 0 0 0 0
Total 450 1,272 1,723 2,794 2,874
R e c o rd e d /A d ju s te d (N o m in a l $)
Labor 102 474 964 1,491 1,731
Non-Labor 348 911 836 12,896 3,038
Other 0 0 0 0 0
Total 450 1,385 1,800 14,387 4,769
E sca la tio n :
Labor 1.1414 1.1070 1.0701 1.0327 1.0000
Non-Labor 1.0881 1.0814 1.0642 1.0254 1.0000
O ther 1.0000 1.0000 1.0000 1.0000 1.0000
R e c o rd e d /A d ju s te d (C o n s ta n t 2 0 1 2 $ )
Labor
Non-Labor
Other Total
116
379
0495
525
985
01 510
1,032
890
01,922
1.540
13.223
014,763
1,731
3.038
04.769
16 ,000
14 .000
12.000
10,000
8,000
6,000
4 .0 0 0
2.000
0
R e c o rd e d A d ju s te d 2 0 0 8 -2 0 1 2 (2 0 1 2 $ )
m200 8 200 9 2010 2011 2012
□ L a b o r (s td escl) ■ N o n -L abo r (s td esc l) □ Cither (no t escl)
Exhibit No. SCE-02 / Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
4Workpaper - Southern California Edison / 2015 GRC - APPLICATION
FERC Account: 549 Miscellaneous Other Power Generation Expenses
Activ ity: 549 - SOLAR PHOTOVOLTAIC PROGRAM
Witness: Rodolfo L Perez
Forecasting Methods - Summary o f Results o f all Methods Studied - 2012$ (000)
2 Recorded Years (2011 - 2012):Results of Averaging (A2)
COoCM 2014 | 2015 | sd** | Chosen_abor 1,635 1,635 1,635 96 no''Jon-Labor 8,131 8,131 8,131 5,093 noOther 0 0 0 0 noTotal 9,766 9,766 9,766 n/a n/a
3 Recorded Years (2010 -2012):Results of Linear Trending (T3)
LaborNon-LaborOtherTotal
2013 2014 2015 r2 * Chosen2,1347,865
0
2,4838,939
0
2,83310,014
0
0.94 no0.03 no0.00 no
9,999 11,422 12,847 n/a n/a
2013Results of Averaging (A3)
| 2014 ' '2015 sd* Chosen1,4345,717
0
1,4345,717
0
1,4345,717
0
295 no5,380 no
0 no7,151 7,151 7,151 n/a n/a
4 Recorded Years (2009 - 2012):Results of Linear Trending (T4)
LaborNon-LaborOtherTotal
2013 2014 2015 r2 * Chosen2,2399,157
0
2,65111,006
0
3,06412,855
0
0.97 no
0.17 no0.00 no
11,396 13,657 15,919 n/a n/a
2013Results of Averaging (A4)
sd** | Chosen2014 20151,207 1,2074,534 4,534
0 0
1,2074,534
0
469 no5,090 no
0 no5,741 5,741 5,741 n/a n/a
5 Recorded Years (2008 - 2012):Results of Linear Trending (T5) Results of Averaging (A5)
LaborNon-LaborOtherTotal
CO
oCM 2014 | 2015 | r2* I Chosen 2013 | 2014 | 2015 | sd** | Chosen2,262 2,686 3,111 0.98 no 989 989 989 605 no8,970 10,726 12,481 0.26 no 3,703 3,703 3,703 4,846 no
0 0 0 0 . 0 0 no 0 0 0 0 no11,232 13,412 15,592 n/a n/a 4,692 4,692 4,692 n/a n/a
Other Methods:
Last Recorded Year (LRY)
LaborNon-LaborOtherTotal
2013 2014 20151,7313,038
0
1,7313,038
0
1,7313,038
0
| ChoseTTItemized Forecast (IF)
yesyesno
4,769 4,769 4,769 n/a
2013 2014 2015 i r Chosen
nonon/a
Forecast Adjustments:Base Forecast Method Adjustments*
LaborNon-LaborOtherTotal
Method 2013 | 2014 | 2015 | 2013 | 2014 | 2015 | |LRY 1,731 1,731 1,731 377 (1,176) (1,176)LRY 3,038 3,038 3,038 2,498 (1,379) (1,379)N/A 0 0 0 0 0 0
4,769 4,769 4,769 2,875 (2,555) (2,555)
r2 = R Squared (Based on recorded years data)
sd = standard deviation (Based on recorded years data)
See Appendix B Fo r Additional Detail
Exhibit No. SCE-02 / Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION5
FERC Account: 549 Miscellaneous Other Power Generation Expenses
Activ ity: 549 - SOLAR PHOTOVOLTAIC PROGRAM
Witness: Rodolfo L Perez
Results:
Labor
Non-Labor
Other
Total
Forecasting Results
M ethod Selected 2013 | 201 4 | 201 5 | |
Last Recorded Y ear Adj. 2 ,108 555 555
Last Recorded Y ear Adj. 5 ,536 1 ,659 1,659
N/A 0 0 0
7,644 2 ,2 1 4 2 ,214
Analysis o f Forecasting Methods
Analysis of Linear Trending Method:In D. 0 4 -07 -022 and D. 89 -12 -057 , the C P U C stated that if costs have shown a trend in a certain direction over three or more
years, the last year recorded is an appropriate base estim ate. Labor costs have been increasing each year, which provides
our base for estimating Test Year 2015. Non-labor costs have not shown a trend. S ee analysis of last recorded year below.
Analysis of Averaging Method:In D. 0 4 -07 -022 and D. 89 -12 -057 , the C P U C stated that for those accounts which have significant fluctuations in recorded
expenses from year to year, an average of recorded expenses is appropriate. Recorded labor costs in this account have not
fluctuated significantly from year to year, so an average is not an appropriate forecast. Non-labor costs fluctuated in
201 0 -2 0 1 2 , however, the averaging method results in a forecast amount that is higher than the expected costs needed in this
account. S e e analysis of last recorded year below.
Analysis of Last Recorded Year (2012):In D. 0 4 -07 -022 and D. 89 -12 -057 , the C P U C stated that if costs have shown a trend in a certain direction over three or more
years, the last year recorded is an appropriate base estim ate. Labor costs have been increasing each year, which provides
our base for estimating Test Year 2015. To the labor base w e add increased costs in 201 3 for forecast construction activities, and decreased costs in 201 4 -2 015 . Non-labor costs utilize the last recorded year as the most reasonable basis to forecast
our expected expense level. To the non-labor base w e add increased costs in 2013 for forecast construction activities, and
decreases in 2014 and 201 5 to account for decreased materials costs.
Analysis of Itemized Forecast Method:Not applicable.
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
6Workpaper - Southern California Edison / 2015 GRC - APPLICATION
FERC Account: 549 Miscellaneous Other Power Generation Expenses
Activ ity: 549 - SOLAR PHOTOVOLTAIC PROGRAM
Witness: Rodolfo L Perez
Recorded 2008-2012 / Forecast 2013-2015 2012$ (000)
16,000
14.000
12.000
10,000
8,000
6,000
4.000
2.000
02008 2009 2010 2011 2012 2013 2014 2015
□ L ab o r (s td esc l) ■ N o n -L abo r (s td e sc l) □ O the r (no t esc l)
:m m
*
|_____________________________________________________Recorded Period$ (0 0 0 )
F o re ca s t E xp e n se s (c o n s ta n t 2012$) 2008 | 2009 I 2010 | 2011 | 2012 2013 | 2014 | 2015Labor (s tan dard esca la tion ) 116 525 1,032 1,540 1,731 2,108 555 555
N o n-L abo r (s tandard esca la tion ) 379 985 890 13,223 3 ,038 5,536 1,659 1,659
O ther (no t e sca la tab le ) 0 0 0 0 0 0 0 0
Total 495 1,510 1,922 14,763 4 ,769 7,644 2 ,214 2,214
Labor P rio r ye a r Total 1,731 2 ,108 555
C h ange 377 (1,553) 0
Total 1,731 2,108 555 555
N o n-L abo r P rio r ye a r Total 3,038 5 ,536 1,659
C h ange 2.498 (3.877) 0
Total 3 ,038 5,536 1,659 1,659
O th e r P rio r ye a r Total 0 0 0
C h ange 0 0 0
Total 0 0 0 0
Total C h a n g e |
Labor 377 (1,553) 0
N o n-L abo r 2,498 (3,877) 0
O th e r 0 0 0
Total N /A 2,875 (5,430) 0
Exhibit No. SCE-02 / Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION7
FERC Account: 549 Miscellaneous Other Power Generation Expenses
Activ ity: 549 - SOLAR PHOTOVOLTAIC PROGRAM
Witness: Rodolfo L Perez
This page shows the changes in Labor, Non-Labor, and Other expenditures forecast during 2013 through 2015, including reasons for the addition of personnel (labor), increased office supplies required due to an increase in activity (non-labor).
2012 -2013
Labor: 377
Increased labor expense due to increased construction phase activities.
Non-Labor: 2,498
Increased non-labor expense due to increased construction phase activities.
Other: 0
Not applicable.
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
8Workpaper - Southern California Edison / 2015 GRC - APPLICATION
FERC Account: 549 Miscellaneous Other Power Generation Expenses
Activ ity: 549 - SOLAR PHOTOVOLTAIC PROGRAM
Witness: Rodolfo L Perez
This page shows the changes in Labor, Non-Labor, and Other expenditures forecast during 2013 through 2015, including reasons for the addition o f personnel (labor), increased office supplies required due to an increase in activity (non-labor).
2013 -2014
Labor: (1,553)
Transition from capital installation to operation and maintenance phase of project.
Non-Labor: (3,877)
Decreased material costs due to completion of installation.
Other: 0
Not applicable.
Exhibit No. SCE-02 / Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION9
FERC Account: 549 Miscellaneous Other Power Generation Expenses
Activ ity: 549 - SOLAR PHOTOVOLTAIC PROGRAM
Witness: Rodolfo L Perez
This page shows the changes in Labor, Non-Labor, and Other expenditures forecast during 2013 through 2015, including reasons for the addition o f personnel (labor), increased office supplies required due to an increase in activity (non-labor).
20 1 4 -2015 _______________
Labor: 0
Not applicable.
Non-Labor: 0
Not applicable.
Other: 0
Not applicable.
Exhibit No. SCE-02 / Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
10Workpaper - Southern California Edison / 2015 GRC - APPLICATION
THIS PAGE INTENTIONALLY LEFT BLANK
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION11
FERC Account:
A ctiv ity:
Witness:
549 Miscellaneous Other Power Generation Expenses
549 - SOLAR PHOTOVOLTAIC PROGRAM
Rodolfo L Perez
APPENDIX A
Detail Description of Final Cost Centers Included in This Activity
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
12Workpaper - Southern California Edison / 2015 GRC - APPLICATION
FERC Account: 549 Miscellaneous Other Power Generation Expenses
Activity: 549 - SOLAR PHOTOVOLTAIC PROGRAM
Witness: Rodolfo L Perez
Description of Final Cost Centers included in this activity:
F525699 PROJECT DEVELOPMENT - SOLAR PHOTOVOLTAIC PROGRAM - MISCELLANEOUSOPERATION AND MAINTENANCE EXPENSESThis final cost center records the Project Development Solar Photovoltaic Program (SPVP) miscellaneous Operation and Maintenance (O&M) expenses such as material, contract and other costs incurred in connection with the SPVP.
F527623 SOLAR PV OPERATIONS 546 SUPERVISION & ENGINEERINGIncludes labor and expenses incurred in the general supervision and direction of the operation of rooftop solar photovoltaic systems at SPVP Sites 2, 3, 5, 6, 7, 8, 9, 11, 12, 13, 16, 22 and 26.Activities include: labor and expenses for operations manager and supervisors, Engineering & Technical Service labor and expenses, and Power Production Department Home Office engineering expenses.
F527624 SOLAR PV OPERATIONS 549 MISCELLANEOUS GENERATION EXPENSESIncludes labor and expenses that are not readily assignable to other operating accounts at SPVP Sites 2, 3, 5, 6, 7, 8, 9, 11, 12, 13, 16, 22 and 26. Activities include: management and administrative labor; general clerical support; labor relations costs, office supplies, safety and training expenses, first aid supplies, etc.
F527625 SOLAR PV MAINTENANCE 551 SUPERVISION & ENGINEERINGIncludes labor and expenses incurred in the general supervision and direction of the maintenance of rooftop solar photovoltaic systems at SPVP Sites 2, 3, 5, 6, 7, 8, 9, 11, 12, 13, 16, 22 and 26.Activities include: labor and expenses for maintenance manager and supervisors; NERC-CIP engineering costs; and hazardous material control.
F527626 SOLAR PV MAINTENANCE 554 MISCELLANEOUS GENERATION EXPENSESIncludes the cost of labor, materials and expenses incurred in the maintenance of rooftop solar photovoltaic systems at SPVP Sites 2, 3, 5, 6, 7, 8, 9, 11, 12, 13, 16, 22 and 26. Activities include: balance of plant systems; vehicle costs, station consumables, compressed air systems, fire systems, training for operations and maintenance, etc.
F527649 SOLAR PV - 548 OPERATIONS EXPENSESIncludes labor, materials used and expenses incurred in operating rooftop solar photovoltaic systems at SPVP Sites 2, 3, 5, 6, 7, 8, 9, 11, 12, 13, 16, 22 and 26. Activities include: operations craft labor and expenses, environmental compliance costs, permits and fees, and other expenses related to generation.
F527651 SOLAR PV MAINTENANCE 553 MAINTENANCE OF GENERATION & ELECTRICAL EQUIPMENTIncludes the cost of labor, materials and expenses incurred in the maintenance of rooftop solar photovoltaic systems at SPVP Sites 2, 3, 5, 6, 7, 8, 9, 11, 12, 13, 16, 22 and 26. Activities include: labor and expenses for maintenance craft labor; maintenance materials, contractor costs, maintenance of auxiliary electrical systems, calibration and maintenance, electrical distribution, etc.
F528076 SOLAR PV SITE 5 MAINTENANCE 553 MAINTENANCE GENERATION-ELECTRICAL EQUIPMENTIncludes the cost of labor, materials and expenses incurred in the maintenance of rooftop solar photovoltaic systems at SPVP Sites 2, 3, 5, 6, 7, 8, 9, 11, 12, 13, 16, 22 and 26. Activities include: labor and expenses for maintenance craft labor; maintenance materials, contractor costs, maintenance of auxiliary electrical systems, calibration and maintenance, electrical distribution, etc.
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION13
FERC Account: 549 Miscellaneous Other Power Generation Expenses
Activity: 549 - SOLAR PHOTOVOLTAIC PROGRAM
Witness: Rodolfo L Perez
Description of Final Cost Centers included in this activity:
F528080 SOLAR PV MAINTENANCE 553 MAINTENANCE GENERATION-ELECTRICAL EQUIPMENTIncludes the cost of labor, materials and expenses incurred in the maintenance of rooftop solar photovoltaic systems at SPVP Sites 2, 3, 5, 6, 7, 8, 9, 11, 12, 13, 16, 22 and 26. Activities include: labor and expenses for maintenance craft labor; maintenance materials, contractor costs, maintenance of auxiliary electrical systems, calibration and maintenance, electrical distribution, etc.
F528084 SOLAR PV SITE 5 OPERATIONS 546 SUPERVISION-ENGINEERINGIncludes labor and expenses incurred in the general supervision and direction of the operation of rooftop solar photovoltaic systems at SPVP Sites 2, 3, 5, 6, 7, 8, 9, 11, 12, 13, 16, 22 and 26. Activities include: labor and expenses for operations manager and supervisors, Engineering & Technical Service labor and expenses, and Power Production Department Home Office engineering expenses.
F528336 SOLAR PV SITE 2 MAINTENANCE 553 GENERATION-ELECTRICAL EQUIPMENTIncludes the cost of labor, materials and expenses incurred in the maintenance of rooftop solar photovoltaic systems at SPVP Sites 2, 3, 5, 6, 7, 8, 9, 11, 12, 13, 16, 22 and 26. Activities include: labor and expenses for maintenance craft labor; maintenance materials, contractor costs, maintenance of auxiliary electrical systems, calibration and maintenance, electrical distribution, etc.
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
14Workpaper - Southern California Edison / 2015 GRC - APPLICATION
FERC Account: 549 Miscellaneous Other Power Generation Expenses
Activ ity: 549 - SOLAR PHOTOVOLTAIC PROGRAM
Witness: Rodolfo L Perez
Recorded/Adjusted (Constant 2012$) By Final Cost Center$ (000)
2008 2009 2010 2011 2012
F525699 PROJECT DEVELOPMENT - SOLAR PHOTOVOLTAIC PROGRAM - MISCELLANEOUS OPERATION AND MAINTENANCE EXPENSES
495 1,510 1,922 14,574 4,078
F527623 SOLAR PV OPERATIONS 546 SUPERVISION & ENGINEERING
0 0 0 3 1
F527624 SOLAR PV OPERATIONS 549 MISCELLANEOUS GENERATION EXPENSES
0 0 0 10 45
F527625 SOLAR PV MAINTENANCE 551 SUPERVISION & ENGINEERING
0 0 0 119 132
F527626 SOLAR PV MAINTENANCE 554 MISCELLANEOUS GENERATION EXPENSES
0 0 0 0 77
F527649 SOLAR PV - 548 OPERATIONS EXPENSES 0 0 0 7 27
F527651 SOLAR PV MAINTENANCE 553 MAINTENANCE OF GENERATION & ELECTRICAL EQUIPMENT
0 0 0 48 408
F528076 SOLAR PV SITE 5 MAINTENANCE 553 MAINTENANCEGENERATION-ELECTRICAL EQUIPMENT
0 0 0 0 1
F528080 SOLAR PV MAINTENANCE 553 MAINTENANCEGENERATION-ELECTRICAL EQUIPMENT
0 0 0 0 1
F528084 SOLAR PV SITE 5 OPERATIONS 546 SUPERVISION-ENGINEERING
0 0 0 0 (2)
F528336 SOLAR PV SITE 2 MAINTENANCE 553 GENERATION-ELECTRICAL EQUIPMENT
0 0 0 0 1
Total 495 1,510 1,922 14,761 4,769
* * Due to rounding, totals m ay not tie to o ther workpaper pages.
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION15
FERC Account:
Activ ity:
Witness:
549 Miscellaneous Other Power Generation Expenses
549 - SOLAR PHOTOVOLTAIC PROGRAM
Rodolfo L Perez
APPENDIX B
Detail of Total Company Adjustments to Recorded
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
16Workpaper - Southern California Edison / 2015 GRC - APPLICATION
FERC Account: 549 Miscellaneous Other Power Generation Expenses
A ctiv ity : 549 - SOLAR PHOTOVOLTAIC PROGRAM
Witness: Rodolfo L Perez
Detail o f Total Company Adjustm ents to Recorded Expenses
|Adjs - (Nominal $) $ (000)2008 2009 2010 2011 2012 2013 2014 2015
Labor 102 474 964 1,488 1,585 377 (1,176) (1,176)Non-Labor 348 798 759 1,306 1,289 2,498 (1,379) (1,379)Other 0 0 0 0 0 0 0 0
Total 450 1,272 1,723 2,794 2,874 2,875 (2,555) (2,555)
Company Wide Adjustment 1 GRC-JAB-CW-NONUTILCR
This adjustment reverses the non-utility affiliate credits related to expenses recorded in one or more of the final cost centers included in this activity and charged to non-utility affiliates. These adjustments are appropriate because all recorded non-utility affiliate credits were refunded to customers through the Base Revenue Requirement Balancing Account (BRRBA) pursuant to D.99-10-057. If these adjustments were not made, non-utility affiliate credits would be refunded to customers twice: (1) through adjustments to the BRRBA; and (2) through reductions to rates.
0 0 0 0 17 0 0LaborNon-LaborOtherTotal 18
Organizational Unit Adjustment 1 GRC-MJP.CPT-OUX-OTHER A&G TO SOLAR
Transfer from Other A&G FERC accounts 920/921 and 923 to FERC account 549 for expenses related to the Solar Photovoltaic activity where they are forecast.
LaborNon-LaborOther
102348
0
474831
0
964759
0
1,4121,214
0
1,222974
0
000
000
000
Total 450 1,305 1,723 2,626 2,196 0 0 0
Organizational Unit Adjustment 2 GBU-CPT-OU-SPVP ROLL UP TO 549
This adjustment transfers Solar costs from FERC 546, 548, 551, 553, and 554 to FERC 549 Operations.
Labor 0 0 0 81 343 0 0 0Non-Labor 0 0 0 92 303 0 0 0Other 0 0 0 0 0 0 0 0
Total 0 0 0 173 646 0 0 0
Organizational Unit Adjustment 3
This adjustment transfers equipment leases from FERC 550 to FERC 549.
GBU-CPT-OU-SPVP-EQUIPMENT LEASES TO 549
LaborNon-LaborOtherTotal
0110
11
Exhibit No. SCE-02 / Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
o o 0 0 0 0 0
0 0 0 0 0 0 0
Workpaper - Southern California Edison / 2015 GRC - APPLICATION17
FERC Account: 549 Miscellaneous Other Power Generation Expenses
A ctiv ity : 549 - SOLAR PHOTOVOLTAIC PROGRAM
Witness: Rodolfo L Perez
Detail o f Total Company Adjustm ents to Recorded Expenses
|Adjs - (Nominal $) $ (000)2008 2009 2010 2011 2012 2013 2014 2015
Organizational Unit Adjustment 4
This adjustment transfers labor expenses from FERC 550 to FERC 549.
GBU-CPT-OU-SPVP - LABOR CORRECTION
LaborNon-LaborOtherTotal
(5)00
(5)
Organizational Unit Adjustment 5
This adjustment removes one time expenses related to O&M from the Solar Photovoltaic Program.
GBU-CPT-OU-OTM ADJ
LaborNon-LaborOtherTotal
0(33)
0(33)
Organizational Unit Adjustment 6
This future year adjustment is for changes to solar projects.
GBU-CPT-OU-FYA SPVP FUTURE ADJ
Labor 0 0 0 0 0 377 (1,176) (1,176)Non-Labor 0 0 0 0 0 2,498 (1,379) (1,379)Other 0 0 0 0 0 0 0 0Total 0 0 0 0 0 2,875 (2,555) (2,555)
3 0
Exhibit No. SCE-02 / Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
18Workpaper - Southern California Edison / 2015 GRC - APPLICATION
End of Workpapers for:
FERC Account: 549 Miscellaneous Other Power Generation Expenses
A ctiv ity: 549 - SOLAR PHOTOVOLTAIC PROGRAM
Witness: Rodolfo L Perez
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION18a
Southern California Edison 2015 GRC A.13-11-XXX
DATA REQUEST SET DRA-Verbal-010
To: DRA Prepared by: Anthony Kurpakus
Title: Manager Dated: 08/22/2013
Received Date: 08/22/2013
Question C.01:
Originator: Peter Morse
Solar, SCE 02, Volume 10
C.1. Provide additional explanation for the derivation of $24,310/MW forecast shown in the column titled "Revised Allocation" in Table III.3. (confidential testimony, p 14)
Response to Question C.01: Should be DC
In Table III-3, the $24,310/MW is based on the 2015 Test Year SPVP O&M, not including the Roof Lease costs. It is calculated by using the 2015 O&M forecast divided by the Solar AC Megawatt capacity. The calculation from the table is: $2.212 M, times 1 Million , divided by 91 MW, equals $24,308 /MW ($2.212M*1,000,000/91MW =$24,308/MW). The difference between the calculated $24,308/MW and the $24,310 from the table is due to rounding. Additional information has been provided to show the derivation of the 2015 test year expense forecast. See the attached fde, "Solar 2015 GRC O&M Detail".
□
Exhibit No. SCE-02 / Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Exhibit No. SCE-02 / Generation / Vol. 10 Witnesses: R. Perez, J. Rumble and A. Edeson
00 cr
SOLA
R P
HO
TOV
OLT
AIC
PR
OG
RA
M
FOR
ECA
ST O
&M
BY
ACT
IVIT
Y -
2015
GR
CA
LL C
OST
S SH
OW
N I
N $
2012
FER
C A
ccou
nt
Des
crip
tion
2015
For
ecas
t Ex
pens
eFo
reca
st A
ssum
ptio
nsCo
st B
asis
FER
CSS
OLe
ases
2,08
4,45
1Le
ases
incr
ease
with
GR
C e
scal
atio
nB
ased
on
exis
ting
leas
e ag
reem
ents
FER
CS
49M
aint
enan
ce L
abor
554,
800
5.5
Em
ploy
ee F
TEB
ased
on
fore
cast
labo
r re
quire
men
ts
FER
CS
49E
quip
men
t/Spa
re P
arts
/Con
sum
able
sS
06,0
00S
pare
s, e
lect
rical
par
ts,
etc.
Est
imat
e o
f SCE
fiel
d pe
rson
nel b
ased
on
reco
rded
cos
ts a
nd
expe
rienc
e, e
xtra
pola
ted
to fu
ll nu
mbe
r o
f in
stal
latio
ns
FER
CS
49C
ontr
act S
ervi
ces
186,
000
2 C
ontr
act
hire
s an
d m
ater
ials
for
Inve
rter
M
aint
enan
ceB
ased
on
2012
rec
orde
d co
sts
and
fore
cast
of
mat
eria
ls
FER
CS
49In
vest
igat
ions
and
Rep
airs
164,
000
Roo
f sur
veys
& I
nspe
ctio
n, e
ngin
eerin
gE
stim
ate
of S
CE fi
eld
pers
onne
l bas
ed o
n ex
perie
nce,
extr
apol
ated
to fu
ll nu
mbe
r o
f in
stal
latio
ns
FER
CS
49T
estin
g26
5,00
0T
herm
ogra
phy,
DG
A, M
ete
r re
cert
.E
stim
ate
of S
CE fi
eld
pers
onne
l bas
ed o
n ex
perie
nce,
ex
trap
olat
ed to
full
num
ber
of
inst
alla
tions
FER
CS
49M
oni
tori
ng
and
Rep
ortin
g75
,000
Ver
izon
te
lem
etr
y sy
stem
Bas
ed o
n fo
reca
sted
cos
ts f
or
full
num
ber
of
inst
alla
tions
FER
CS
49A
dded
Fac
ility
Cos
ts15
0,00
0T&
D I
nter
conn
ectio
nB
ased
on
reco
rded
cos
ts,
extr
apol
ated
to fu
ll nu
mbe
r of
in
stal
latio
ns
FER
CS
49T
elec
omm
unic
atio
ns46
,000
Tel
ecom
, IS
PB
ased
on
2012
rec
orde
d co
sts,
ext
rapo
late
d to
full
num
ber
of
inst
alla
tions
FER
CS
49E
quip
men
t R
enta
ls25
,000
Man
lifts
, to
ilets
, tra
ilers
Est
imat
e o
f SCE
fiel
d pe
rson
nel b
ased
on
expe
rienc
e,
extr
apol
ated
to fu
ll nu
mbe
r o
f in
stal
latio
ns
FER
CS
49T
rans
port
atio
n60
,000
SCE
truc
ks,
equi
pmen
tB
ased
on
fore
cast
req
uire
men
t fo
r ve
hicl
es a
nd fu
el
FER
CS
49T
rain
ing
5,00
0T
rain
ing
for
mai
nten
ance
& o
pera
tion
SCE
estim
ate
base
d on
exp
erie
nce,
adj
uste
d fo
r nu
mbe
r of
FT
E
FER
CS
49La
ndsc
apin
g an
d S
ecur
ity M
anag
emen
t27
,000
Gro
und
syst
ems,
fenc
ing
Bas
ed o
n fo
reca
sted
cos
ts f
or
full
num
ber
of
inst
alla
tions
FER
CS
49O
ther
cos
ts15
0,00
0T
heft,
van
dalis
m,
etc.
Bas
ed o
n fo
reca
sted
cos
ts f
or
full
num
ber
of
inst
alla
tions
Tota
l4,
298,
251
SPV
P Fo
reca
st20
15FE
RC 5
49La
bor
554,
800
Non
-Lab
or1,
659,
000
Sub
-tot
al2,
213,
800
FERC
550
Leas
es2,
084,
451
Tota
l4,
298,
251
See
Fig
ure
111-
3, P
age
IS T
estim
ony
See
Fig
ure
ill-4
, P
age
17 T
estim
ony
Workpaper - Southern California Edison / 2015 GRC - APPLICATION
Workpaper - Southern California Edison / 2015 GRC - APPLICATION19
Exhibit SCE-02, Volume 10 WORKPAPERS
Solar Photovoltaic Program
O&M FERC Account 550
Witness: Rudy Perez
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
20Workpaper - Southern California Edison / 2015 GRC - APPLICATION
Beginning of Workpapers for:
FERC Account: 550 Rents
A ctiv ity : 550 - SOLAR PHOTOVOLTAIC PROGRAM
Witness: Rodolfo L Perez
Forecast Method Chosen
2012$ (000)
Recorded2012
Forecast2015
Labor N/A 0 0Non-Labor Last Recorded Year Adj. 2,127 2,084Other N/A 0 0Total 2,127 2,084
Description of Activity:
This activity shall include all rents of property of others used, occupied, or operated in connection with Solar Photovoltaic Program (SPVP) projects.
Final Cost Centers included in this activity (See Appendix A for additiona l detail):
F525698 F527650
Exhibit No. SCE-02 / Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION21
FERC Account: 550 Rents
A ctiv ity : 550 - SOLAR PHOTOVOLTAIC PROGRAM
Witness: Rodolfo L Perez
DETERMINATION OF RECORDED/ADJUSTED
Recorded Period$ (000)
2008 2009 2010 2011 2012FERC Form 1 Recorded (Nominal $)
Labor 0 0 0 (5) 3Non-Labor 0 159 146 737 2,138Other 0_________ 0__________0__________0_________ 0Total 0 159 146 732 2,141
Adjustments- (Nominal $) - see Appendix B for additional detailLabor 0 0 0 5 (3)Non-Labor 0 0 0 0 (11)Other 0 0 0 0 0Total 0 0 0 5 (14)
Recorded/Adjusted (Nominal $)Labor 0 0 0 0 0Non-Labor 0 159 146 737 2,127Other 0 0 0 0 0Total 0 159 146 737 2,127
Escalation:Labor 1.1414 1.1070 1.0701 1.0327 1.0000
Non-Labor 1.0881 1.0814 1.0642 1.0254 1.0000
Other 1.0000 1.0000 1.0000 1.0000 1.0000
Recorded Adjusted 2008-2012 (2012$)
2,400
2,000
1,600
1,200
800
400
02008 2009 2010 2011 2012
□ Labor (std escl) Non-Labor (std escl) □ Other (not escl)
Exhibit No. SCE-02 / Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
22Workpaper - Southern California Edison / 2015 GRC - APPLICATION
FERC Account: 550 Rents
A ctiv ity: 550 - SOLAR PHOTOVOLTAIC PROGRAM
Witness: Rodolfo L Perez
Forecasting Methods - Summary o f Res ults o f all Methods Studied - 2012$ (000)
2 Recorded Years (2011 - 2012):Results of Averaging (A2)
COoCM ^r
oCM 2015 | sd** | ChosenLabor 0 0 0 0 noNon-Labor 1,441 1,441 1,441 686 noOther 0 0 0 0 noTotal 1,441 1,441 1,441 n/a n/a
3 Recorded Years (2010 - 2012):Results of Linear Trending (T3) Results of Averaging (A3)
COoCM ^r
oCM 2015 | r2* | Chosen 2013 | 2014 | 2015 | sd** | ChosenLabor 0 0 0 0.00 no 0 0 0 0 noNon-Labor 2,984 3,970 4,956 0.95 no 1,013 1,013 1,013 825 noOther 0 0 0 0.00 no 0 0 0 0 no
Total 2,984 3,970 4,956 n/a n/a 1,013 1,013 1,013 n/a n/a
4 Recorded Years (2009 - 2012):Results of Linear Trending (T4) Results of Averaging (A4)
LaborNon-LaborOtherTotal
COoCM r̂oCM 2015 | r2* | Chosen
COoCM r̂oCM 2015 | sd** | Chosen0 0 0 0.00 no 0 0 0 0 no
2,419 3,065 3,712 0.81 no 803 803 803 802 no0 0 0 0.00 no 0 0 0 0 no
2,419 3,065 3,712 n/a n/a 803 803 803 n/a n/a
5 Recorded Years (2008 - 2012):Results of Linear Trending (T5) Results of Averaging (A5)
LaborNon-LaborOtherTotal
COoCM ^roCM 2015 | r2* | Chosen
COoCM ^roCM 2015 | sd** | Chosen0 0 0 0.00 no 0 0 0 0 no
2,093 2,577 3,061 0.76 no 642 642 642 786 no0 0 0 0.00 no 0 0 0 0 no
2,093 2,577 3,061 n/a n/a 642 642 642 n/a n/a
Other Methods:
Last Recorded Year (LRY) Itemized Forecast (IF)
LaborNon-LaborOtherTotal
COoCM ^roCM 2015 1 | Chosen
COoCM ^roCM 2015 | | Chosen0 0 0 no 0 0 0 no
2,127 2,127 2,127 yes 0 0 0 no0 0 0 no 0 0 0 no
2,127 2,127 2,127 n/a 0 0 0 n/a
Forecast Adjustm ents:Base Forecast Method Adjustments*
LaborNon-LaborOtherTotal
Method
COoCM ^roCM 2015 |
COoCM ^roCM 2015 | |N/A 0 0 0 0 0 0LRY 2,127 2,127 2,127 (43) (43) (43)N/A 0 0 0 0 0 0
2,127 2,127 2,127 (43) (43) (43)
* r2 = R Squared (Based on recorded years data)
** sd = standard deviation (Based on recorded years data)
*** See Appendix B F o r Additional Detail
Exhibit No. SCE-02 / Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION23
FERC Account: 550 Rents
A ctiv ity : 550 - SOLAR PHOTOVOLTAIC PROGRAM
W itness: Rodolfo L Perez
Results:
Forecasting Results
Method Selected 2013 | 2014 | 2015 | |Labor N/A 0 0 0Non-Labor Last Recorded Year Adj. 2,084 2,084 2,084Other N/A 0 0 0Total 2,084 2,084 2,084
Analysis o f Forecasting Methods
Analysis of Linear Trending Method:In D. 04-07-022 and D. 89-12-057, the CPUC stated that if costs have sh own a trend in a certain direction over three or more years, the last year recorded is an appropriate base estimate. Non-labor costs have been increasing each year, which provides a base for estimating the test year 2015. To this base we decreased costs for 2013, reflecting the decreased costs for roof leases.
Analysis of Averaging Method:In D. 04-07-022 and D. 89-12-057, the CPUC stated that for those accounts which have significant fluctuations in recorded expenses from year to year, an average of recorded expenses is approp riate. Recorded costs in this account have not fluctuated significantly from year to year, so an average is not an appropriate forecast.
Analysis of Last Recorded Year (2012):In D. 04-07-022 and D. 89-12-057, the CPUC stated that if recorded expenses in an account have been relatively stable for three or more years, the last recorded year is an appropriate base estimate. Costs in this account have not been stable, but use of this method is applicable because there is a historical trend of increasing costs. To this base we decreased expenses for non-repeating leases expenses.
Analysis of Itemized Forecast Method:Not applicable.
Exhibit No. SCE-02 / Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
24Workpaper - Southern California Edison / 2015 GRC - APPLICATION
FERC Account: 550 Rents
A ctiv ity : 550 - SOLAR PHOTOVOLTAIC PROGRAM
W itness: Rodolfo L Perez
Recorded 2008-2012 / Forecast 2013-2015 2012$ (000)
2,400
2,000
1,600
1,200
800
400
0llll
2008 2009 2010 2011 2012 2013 2014 2015
□ Labor (std escl) Non-Labor (std escl) □ Other (not escl)
1 Recorded Period$ (000)
Forecast Expenses (constant 2012$) 2008 | 2009 | 2010 | 2011 | 2012 2013 | 2014 | 2015Labor (standard escalation) 0 0 0 0 0 0 0 0Non-Labor (standard escalation) 0 172 155 756 2,127 2,084 2,084 2,084Other (not escalatable) 0 0 0 0 0 0 0 0Total 0 172 155 756 2,127 2,084 2,084 2,084
Labor Prior year Total 0 0 0Change 0 0 0Total 0 0 0 0
Non-Labor Prior year Total 2,127 2,084 2,084ChangeTotal
(43) 0 02,127 2,084 2,084 2,084
Other Prior year Total 0 0 0Change 0 0 0Total 0 0 0 0
Total ChangeLabor 0 0 0Non-Labor (43) 0 0Other 0 0 0Total N/A (43) 0 0
Exhibit No. SCE-02 / Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION25
FERC Account: 550 Rents
A ctiv ity : 550 - SOLAR PHOTOVOLTAIC PROGRAM
Witness: Rodolfo L Perez
This page shows the changes in Labor, Non-Labor, and Other expenditures forecast during 2013 through 2015, including reasons for the addition of personnel (labor), increased office supplies required due to an increase in activity (non-labor).
2012 - 2013
Labor: 0
Not applicable.
Non-Labor: (43)
Non-labor expense decreases due to non-repeating lease expenses.
Other: 0
Not applicable.
Exhibit No. SCE-02 / Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
26Workpaper - Southern California Edison / 2015 GRC - APPLICATION
FERC Account: 550 Rents
A ctiv ity : 550 - SOLAR PHOTOVOLTAIC PROGRAM
W itness: Rodolfo L Perez
This page shows the changes in Labor, Non-Labor, and Oth er expenditures forecast during 2013 through 2015, including reasons for the addition of personne l (labor), increased office supplies required due to an increase in activity (non-labor).
2013 - 2014
Labor: 0
Not applicable.
Non-Labor: 0
Not applicable.
Other: 0
Not applicable.
Exhibit No. SCE-02 / Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION27
FERC Account: 550 Rents
A ctiv ity: 550 - SOLAR PHOTOVOLTAIC PROGRAM
Witness: Rodolfo L Perez
This page shows the changes in Labor, Non-Labor, and Oth er expenditures forecast during 2013 through 2015, including reasons for the addition of personnel (labor), increased office supplies required due to an increase in activity (non-labor).
2014 - 2015_______________
Labor: 0
Not applicable.
Non-Labor: 0
Not applicable.
Other: 0
Not applicable.
Exhibit No. SCE-02 / Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
28Workpaper - Southern California Edison / 2015 GRC - APPLICATION
THIS PAGE INTENTIONALLY LEFT BLANK
Exhibit No. SCE-02 / Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION29
FERC Account
A ctiv ity:
W itness:
550 Rents
550 - SOLAR PHOTOVOLTAIC PROGRAM
Rodolfo L Perez
APPENDIX A
D e t a i l D e s c r i p t i o n o f F i n a l C o s t C e n t e r s
I n c l u d e d in T h r s A c t i v i t y
Exhibit No. SCE-02 / Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
30Workpaper - Southern California Edison / 2015 GRC - APPLICATION
FERC Account: 550 Rents
Activity: 550 - SOLAR PHOTOVOLTAIC p r o g r a m
Witness: Rodolfo L Perez
Description of Final Cost Centers included in this activity:
F525698 PROJECT DEVELOPMENT - SOLAR PHOTOVOLTAIC PROGRAM - LEASESThis final cost center records the Project Development Solar Photovoltaic program lease expenses.
F527650 SOLAR PV MAINTENANCE 550 RENTSIncludes all rents of property of others used, occupied, or operated in connection with rooftop solar photovoltaic systems at SPVP Sites 2, 3, 5, 6, 7, 8, 9, 11, 12, 13, 16, 22 and 26.
Exhibit No. SCE-02 / Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION31
FERC Account
Activ ity:
Witness:
Recorded/Adjusted (Cons tant 2012$) By Final Cost Center
$ (000)2008 2009 2010 2011 2012
550 Rents
550 - SOLAR PHOTOVOLTAIC PROGRAM
Rodolfo L Perez
F525698 PROJECT DEVELOPMENT - SOLAR 0 172 155 756 2,127PHOTOVOLTAIC PROGRAM - LEASES
F527650 SOLAR PV MAINTENANCE 550 RENTS 0 0 0 0 0
Total 0 172 155 756 2,127
* * Due to rounding, totals m ay not tie to o the r workpaper pages.
Exhibit No. SCE-02 / Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
32Workpaper - Southern California Edison / 2015 GRC - APPLICATION
THIS PAGE INTENTIONALLY LEFT BLANK
Exhibit No. SCE-02 / Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION33
FERC Account
A ctiv ity:
Witness:
550 Rents
550 - SOLAR PHOTOVOLTAIC PROGRAM
Rodolfo L Perez
APPENDIX B
D e t a i l o f T o t a l C o m p a n y
A d j u s t m e n t s t o R e c o r d e d
Exhibit No. SCE-02 / Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
34Workpaper - Southern California Edison / 2015 GRC - APPLICATION
FERC Account: 550 Rents
A ctiv ity : 550 - SOLAR PHOTOVOLTAIC PROGRAM
W itness: Rodolfo L Perez
Detail o f Total Company Adj ustments to Recorded Expenses
| Adjs - (Nominal $) $ (000)2008 2009 2010 2011 2012 2013 2014 2015
Labor 0 0 0 5 (3) 0 0 0Non-Labor 0 0 0 0 (11) (43) (43) (43)Other 0 0 0 0 0 0 0 0
Total 0 0 0 5 (14) (43) (43) (43)
Organizational Unit Adjustment 1 GBU-CPT-OU-FYA SPVP FUTURE ADJ
This future year adjustment is a reduction to the forecast due to n on-repeating lease expenses.
Labor 0 0 0 0 0 0 0 0Non-Labor 0 0 0 0 0 (43) (43) (43)Other 0 0 0 0 0 0 0 0
Total 0 0 0 0 0 (43) (43) (43)
Organizational Unit Adjustment 2 GBU-CPT-OU-SPVP - LABOR CORRECTION
This adjustment transfers labor expenses from FERC 550 to FERC 549.
Labor 0 0 0 5 (3) 0 0 0Non-Labor 0 0 0 0 0 0 0 0Other 0 0 0 0 0 0 0 0
Total 0 0 0 5 (3) 0 0 0
Organizational Unit Adjustment 3 GBU-CPT-OU-SPVP-EQUIPMENT LEASES TO 549
This adjustment transfers equipment leases from FERC 550 to FERC 549.
Labor 0 0 0 0 0 0 0 0Non-Labor 0 0 0 0 (11) 0 0 0Other 0 0 0 0 0 0 0 0
Total 0 0 0 0 (11) 0 0 0
Exhibit No. SCE-02 / Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION35
End of Workpapers for:
FERC Account: 550 Rents
A ctiv ity : 550 - SOLAR PHOTOVOLTAIC PROGRAM
Witness: Rodolfo L Perez
Exhibit No. SCE-02 / Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Exhibit No. SCE-02 / Generation / Vol. 10 Witnesses: R. Perez, J. Rumble and A. Edeson
00 Ul
0)
SOLA
R P
HO
TOV
OLT
AIC
PRO
GR
AM
FO
REC
AST
O&
M B
Y A
CTIV
ITY
- 20
15 G
RC
ALL
CO
STS
SHO
WN
IN
$20
12
FERC
Acc
ount
Des
crip
tion
2015
For
ecas
t Ex
pens
eFo
reca
st A
ssum
ptio
nsCo
st B
asis
FER
CSS
OLe
ases
2,08
4,45
1Le
ases
inc
reas
e w
ith G
RC
esc
alat
ion
Bas
ed o
n ex
istin
g le
ase
agre
emen
ts
FERC
S49
Mai
nten
ance
Lab
or55
4,80
05.
5 E
mpl
oyee
FTE
Bas
ed o
n fo
reca
st la
bor
requ
irem
ents
FERC
S49
Equ
ipm
ent/S
pare
Par
ts/C
onsu
mab
les
S06
,000
Spa
res,
ele
ctric
al p
arts
, et
c.E
stim
ate
of S
CE fi
eld
pers
onne
l ba
sed
on r
ecor
ded
cost
s an
d ex
perie
nce,
ext
rapo
late
d to
full
num
ber
of
inst
alla
tions
FERC
S49
Con
trac
t Ser
vice
s18
6,00
02
Con
trac
t hi
res
and
mat
eria
ls fo
r In
vert
er
Mai
nten
ance
Bas
ed o
n 20
12 r
ecor
ded
cost
s an
d fo
reca
st o
f m
ater
ials
FERC
S49
Inve
stig
atio
ns a
nd R
epai
rs16
4,00
0R
oof s
urve
ys &
Ins
pect
ion,
eng
inee
ring
Est
imat
e of
SCE
fiel
d pe
rson
nel
base
d on
exp
erie
nce,
ex
trap
olat
ed t
o fu
ll nu
mbe
r o
f in
stal
latio
ns
FERC
S49
Test
ing
265,
000
The
rmog
raph
y, D
GA,
Met
er r
ecer
t.E
stim
ate
of S
CE fi
eld
pers
onne
l ba
sed
on e
xper
ienc
e,
extr
apol
ated
to
full
num
ber
of
inst
alla
tions
FERC
S49
Mo
nito
ring
and
Rep
ortin
g75
,000
Ver
izon
te
lem
etr
y sy
stem
Bas
ed o
n fo
reca
sted
cos
ts fo
r fu
ll nu
mbe
r o
f ins
talla
tions
FERC
S49
Add
ed F
acili
ty C
osts
150,
000
T&D
Int
erco
nnec
tion
Bas
ed o
n re
cord
ed c
osts
, ex
trap
olat
ed to
full
num
ber
of
inst
alla
tions
FERC
S49
Tel
ecom
mun
icat
ions
46,0
00T
elec
om,
ISP
Bas
ed o
n 20
12 r
ecor
ded
cost
s, e
xtra
pola
ted
to fu
ll nu
mbe
r of
in
stal
latio
ns
FERC
S49
Equ
ipm
ent
Ren
tals
25,0
00M
anlif
ts, t
oile
ts, t
raile
rsE
stim
ate
of S
CE fi
eld
pers
onne
l ba
sed
on e
xper
ienc
e,
extr
apol
ated
to
full
num
ber
of
inst
alla
tions
FERC
S49
Tra
nspo
rtat
ion
60,0
00SC
E tr
ucks
, eq
uipm
ent
Bas
ed o
n fo
reca
st r
equi
rem
ent f
or
vehi
cles
and
fuel
FERC
S49
Tra
inin
g5,
000
Tra
inin
g fo
r m
aint
enan
ce &
ope
ratio
nSC
E es
timat
e ba
sed
on e
xper
ienc
e, a
djus
ted
for
num
ber
of
FTE
FERC
S49
Land
scap
ing
and
Sec
urity
Man
agem
ent
27,0
00G
roun
d sy
stem
s, f
enci
ngB
ased
on
fore
cast
ed c
osts
for
full
num
ber
of i
nsta
llatio
ns
FERC
S49
Oth
er c
osts
150,
000
The
ft, v
anda
lism
, et
c.B
ased
on
fore
cast
ed c
osts
fo
r fu
ll nu
mbe
r o
f ins
talla
tions
Tota
l4,
298,
251
SPV
P Fo
reca
st20
15FE
RC 5
49La
bor
554,
800
Non
-Lab
or1,
659,
000
Sub
-tot
al2,
213,
800
FERC
550
Leas
es2,
084,
451
Tota
l4,
298,
251
See
Figu
re 1
11-3
, Pag
e IS
Tes
timon
y
See
Figu
re il
l-4,
Pag
e 17
Tes
timon
y
Workpaper - Southern California Edison / 2015 GRC - APPLICATION
Workpaper - Southern California Edison / 2015 GRC - APPLICATION36
THIS PAGE INTENTIONALLY LEFT BLANK
Exhibit No. SCE-02 / Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
37Workpaper - Southern California Edison / 2015 GRC - APPLICATION
E xhib it SCE-02, Volume 10 WORKPAPERS
Solar Photovoltaic Program
O & M FERC Account 546
Witness: Rudy Perez
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION38
Beginning of Workpapers for:
FERC Account: 546 Operation Supervision and Engineering
Activ ity: 546 - SOLAR PHOTOVOLTAIC PROGRAM
Witness: Rodolfo L Perez
Forecast Method Chosen
2012$ (000)
Recorded2012
Forecast2015
Labor N/A 0 0Non-Labor N/A 0 0Other N/A 0 0Total 0 0
Description of Activity:
This activity package has zero dollars; all costs have been transferred to other activities.
Final Cost Centers included in this activity (See Appendix A for additional detail):
F527623 F528084
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
39Workpaper - Southern California Edison / 2015 GRC - APPLICATION
FERC Account: 546 Operation Supervision and Engineering
A ctiv ity : 546 - SOLAR PHOTOVOLTAIC PROGRAM
Witness: Rodolfo L Perez
D E T E R M IN A T IO N O F R E C O R D E D /A D J U S T E D
R e c o rd e d P erio d
$ (0 0 0 )
2 0 0 8 2 0 0 9 2 0 1 0 2011 2 0 1 2
F E R C F o rm 1 R e c o rd e d (N o m in a l $)
Labor 0 0 0 3 (1)
Non-Labor 0 0 0 0 0
O ther 0 0 0 0 0
Total 0 0 0 3 (1)
A d ju s tm e n ts - (N o m in a l $)
Labor
s e e A p p e n d ix B fo r a d d it io n a l d e ta il
0 0 0 (3) 1
Non-Labor 0 0 0 0 0
O ther 0 0 0 0 0
Total 0 0 0 (3) 1
R e c o rd e d /A d ju s te d (N o m in a l $)
Labor 0 0 0 0 0
Non-Labor 0 0 0 0 0
O ther 0 0 0 0 0
Total 0 0 0 0 0
E sca la tio n
Labor 1.1414 1.1070 1.0701 1.0327 1.0000
Non-Labor 1.0881 1.0814 1.0642 1.0254 1.0000
O ther 1.0000 1.0000 1.0000 1.0000 1.0000
R e c o rd e d /A d ju s te d (C o n s ta n t 2 0 1 2 $ )
Labor 0 0 0 0 0
Non-Labor 0 0 0 0 0
O ther 0 0 0 0 0
Total 0 0 0 0 0
R e c o rd e d A d ju s te d 2 0 0 8 -2 0 1 2 (2 0 1 2 $ )
6
4
2
0
-2
-4
2 0 0 8 2 0 0 9 2 0 1 0 2 01 1 2 0 1 2
□ L a b o r (std e sc l) ■ N o n -L a b o r (s td e sc l) □ O th e r (n o t e s c l)
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION40
THIS PAGE INTENTIONALLY LEFT BLANK
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
41Workpaper - Southern California Edison / 2015 GRC - APPLICATION
FERC Account:
Activ ity:
Witness:
546 Operation Supervision and Engineering
546 - SOLAR PHOTOVOLTAIC PROGRAM
Rodolfo L Perez
APPENDIX A
Detail Description of Final Cost Centers Included in This Activity
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION42
FERC Account: 546 Operation Supervision and Engineering
Activ ity: 546 - SOLAR PHOTOVOLTAIC PROGRAM
Witness: Rodolfo L Perez
Recorded/Adjusted (Constant 2012$) By Final Cost Center$ (000)
2008 2009 2010 2011 2012
F527623 SOLAR PV OPERATIONS 546 0 0 0 0 0SUPERVISION & ENGINEERING
F528084 SOLAR PV SITE 5 OPERATIONS 546 0 0 0 0 0SUPERVISION-ENGINEERING
Total
* * Due to rounding, totals m ay not tie to o ther workpaper pages.
0 0 0 0 0
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
43Workpaper - Southern California Edison / 2015 GRC - APPLICATION
FERC Account:
Activ ity:
Witness:
546 Operation Supervision and Engineering
546 - SOLAR PHOTOVOLTAIC PROGRAM
Rodolfo L Perez
APPENDIX B
Detail of Total Company Adjustments to Recorded
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION44
FERC Account: 546 Operation Supervision and Engineering
A ctiv ity: 546 - SOLAR PHOTOVOLTAIC PROGRAM
Witness: Rodolfo L Perez
Detail o f Total Company Adjustm ents to Recorded Expenses
|Adjs - (Nominal $) $ (000)2008 2009 2010 2011 2012 2013 2014 2015
Labor 0 0 0 (3) 1 0 0 0Non-Labor 0 0 0 0 0 0 0 0Other 0 0 0 0 0 0 0 0
Total 0 0 0 (3) 1 0 0 0
Organizational Unit Adjustment 1 GBU-CPT-OU-SPVP ROLL UP TO 549
This adjustment transfers Solar costs from FERC 546, 548, 551, 553, and 554 to FERC 549 Operations.
Labor 0 0 0 (3) 1 0 0 0Non-Labor 0 0 0 0 0 0 0 0Other 0 0 0 0 0 0 0 0
Total 0 0 0 (3) 1 0 0 0
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
45Workpaper - Southern California Edison / 2015 GRC - APPLICATION
End of Workpapers for:
FERC Account: 546 Operation Supervision and Engineering
A ctiv ity: 546 - SOLAR PHOTOVOLTAIC PROGRAM
Witness: Rodolfo L Perez
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION46
THIS PAGE INTENTIONALLY LEFT BLANK
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
47Workpaper - Southern California Edison / 2015 GRC - APPLICATION
Exhibit SCE-02, Volume 10 WORKPAPERS
Solar Photovoltaic Program
O&M FERC Account 548
Witness: Rudy Perez
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION48
Beginning of Workpapers for:
FERC Account: 548 Generation Expenses
Activ ity: 548 - SOLAR PHOTOVOLTAIC PROGRAM
Witness: Rodolfo L Perez
Forecast Method Chosen
2012$ (000)
Recorded2012
Forecast2015
Labor N/A 0 0Non-Labor N/A 0 0Other N/A 0 0Total 0 0
Description of Activity:
This activity package has zero dollars; all costs have been transferred to other activities.
Final Cost Centers included in this activity (See Appendix A for additional detail):
F527649
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
49Workpaper - Southern California Edison / 2015 GRC - APPLICATION
FERC Account: 548 Generation Expenses
A ctiv ity : 548 - SOLAR PHOTOVOLTAIC PROGRAM
Witness: Rodolfo L Perez
D E T E R M IN A T IO N O F R E C O R D E D /A D J U S T E D
! R e c o rd e d P e rio d
$ (0 0 0 )
2 0 0 8 2 0 0 9 2 0 1 0 2011 2 0 1 2
F E R C F o rm 1 R e c o rd e d (N o m in a l $ )
Labor 0 0 0 7 26
N on-Labor 0 0 0 0 1
O the r 0______________0______________0_____________ 0_____________ 0
Total 0 0 0 7 27
A d ju s tm e n ts - (N o m in a l $) - s e e A p p e n d ix B fo r a d d it io n a l d e ta il
Labor 0 0 0 (7) (26)
Non-Labor 0 0 0 0 (1)
O ther 0 0 0 0 0
Total 0 0 0 (7) (27)
R e c o rd e d /A d ju s te d (N o m in a l $)
Labor 0 0 0 0 0
Non-Labor 0 0 0 0 0
O ther 0 0 0 0 0
Total 0 0 0 0 0
E sca la tio n :
Labor 1.1414 1.1070 1.0701 1.0327 1.0000
Non-Labor 1.0881 1.0814 1.0642 1.0254 1.0000
O ther 1.0000 1.0000 1.0000 1.0000 1.0000
R e c o rd e d /A d ju s te d (C o n s ta n t 2 0 1 2 $ )
Labor
N on-Labor
O ther
Total
R e c o rd e d A d ju s te d 2 0 0 8 -2 0 1 2 (2 0 1 2 $ )
2008 2009 2010 2011 2012
□ Labor (std escl) ■ Non-Labor (std escl) □ Other (not escl)
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION50
THIS PAGE INTENTIONALLY LEFT BLANK
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
51Workpaper - Southern California Edison / 2015 GRC - APPLICATION
FERC Account
Activ ity:
Witness:
548 Generation Expenses
548 - SOLAR PHOTOVOLTAIC PROGRAM
Rodolfo L Perez
APPENDIX A
Detail Description of Final Cost Centers Included in This Activity
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION52
FERC Account: 548 Generation Expenses
Activ ity: 548 - SOLAR PHOTOVOLTAIC PROGRAM
Witness: Rodolfo L Perez
Recorded/Adjusted (Constant 2012$) By Final Cost Center$ (000)
2008 2009 2010 2011 2012
F527649 SOLAR PV - 548 OPERATIONS EXPENSES 0 0 0 0 0
Total 0 0 0 0 0
* * Due to rounding, totals m ay not tie to o ther workpaper pages.
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
53Workpaper - Southern California Edison / 2015 GRC - APPLICATION
FERC Account:
Activ ity:
Witness:
548 Generation Expenses
548 - SOLAR PHOTOVOLTAIC PROGRAM
Rodolfo L Perez
APPENDIX B
Detail of Total Company Adjustments to Recorded
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION54
FERC Account: 548 Generation Expenses
A ctiv ity: 548 - SOLAR PHOTOVOLTAIC PROGRAM
Witness: Rodolfo L Perez
Detail o f Total Company Adjustm ents to Recorded Expenses
|Adjs - (Nominal $) $ (000)2008 2009 2010 2011 2012 2013 2014 2015
Labor 0 0 0 (7) (26) 0 0 0Non-Labor 0 0 0 0 (1) 0 0 0Other 0 0 0 0 0 0 0 0
Total 0 0 0 (7) (27) 0 0 0
Organizational Unit Adjustment 1 GBU-CPT-OU-SPVP ROLL UP TO 549
This adjustment transfers Solar costs from FERC 546, 548, 551, 553, and 554 to FERC 549 Operations.
Labor 0 0 0 (7) (26) 0 0 0Non-Labor 0 0 0 0 (1) 0 0 0Other 0 0 0 0 0 0 0 0
Total 0 0 0 (7) (27) 0 0 0
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
55Workpaper - Southern California Edison / 2015 GRC - APPLICATION
End of Workpapers for:
FERC Account: 548 Generation Expenses
Activ ity:
W itness:
548 - SOLAR PHOTOVOLTAIC PROGRAM
Rodolfo L Perez
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION56
THIS PAGE INTENTIONALLY LEFT BLANK
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
57Workpaper - Southern California Edison / 2015 GRC - APPLICATION
Exhibit SCE-02, Volume 10 WORKPAPERS
Solar Photovoltaic Program
O&M FERC Account 551
Witness: Rudy Perez
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION58
Beginning of Workpapers for:
FERC Account: 551 Maintenance Supervision and Engineering
Activ ity: 551 - SOLAR PHOTOVOLTAIC PROGRAM
Witness: Rodolfo L Perez
Forecast Method Chosen
2012$ (000)
Recorded2012
Forecast2015
Labor N/A 0 0Non-Labor N/A 0 0Other N/A 0 0Total 0 0
Description of Activity:
This activity package has zero dollars; all costs have been transferred to other activities.
Final Cost Centers included in this activity (See Appendix A for additional detail):
F527625
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
59Workpaper - Southern California Edison / 2015 GRC - APPLICATION
FERC Account: 551 Maintenance Supervision and Engineering
A ctiv ity : 551 - SOLAR PHOTOVOLTAIC PROGRAM
Witness: Rodolfo L Perez
D E T E R M IN A T IO N O F R E C O R D E D /A D J U S T E D
I R e c o rd e d P e rio d
$ (0 0 0 )
2 0 0 8 2 0 0 9 2 0 1 0 2011 2 0 1 2
F E R C F o rm 1 R e c o rd e d (N o m in a l $ )
Labor 0 0 0 58 114
N on-Labor 0 0 0 58 18
O the r 0______________0_____________ 0______________ 0_____________0
Total 0 0 0 116 132
A d ju s tm e n ts - (N o m in a l $) - s e e A p p e n d ix B fo r a d d it io n a l d e ta il
Labor 0 0 0 (58) (114)
Non-Labor 0 0 0 (58) (18)
O ther 0 0 0 0 0
Total 0 0 0 (116) (132)
R e c o rd e d /A d ju s te d (N o m in a l $)
Labor 0 0 0 0 0
Non-Labor 0 0 0 0 0
O ther 0 0 0 0 0
Total 0 0 0 0 0
E sca la tio n :
Labor 1.1414 1.1070 1.0701 1.0327 1.0000
Non-Labor 1.0881 1.0814 1.0642 1.0254 1.0000
O ther 1.0000 1.0000 1.0000 1.0000 1.0000
R e c o rd e d /A d ju s te d (C o n s ta n t 2 0 1 2 $ )
Labor
N on-Labor
O ther
Total
R e c o rd e d A d ju s te d 2 0 0 8 -2 0 1 2 (2 0 1 2 $ )
2008 2009 2010 2011 2012
□ Labor (std escl) ■ Non-Labor (std escl) □ Other (not escl)
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION60
THIS PAGE INTENTIONALLY LEFT BLANK
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
61Workpaper - Southern California Edison / 2015 GRC - APPLICATION
FERC Account:
Activ ity:
Witness:
551 Maintenance Supervision and Engineering
551 - SOLAR PHOTOVOLTAIC PROGRAM
Rodolfo L Perez
APPENDIX A
Detail Description of Final Cost Centers Included in This Activity
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION62
FERC Account: 551 Maintenance Supervision and Engineering
Activ ity: 551 - SOLAR PHOTOVOLTAIC PROGRAM
Witness: Rodolfo L Perez
Recorded/Adjusted (Constant 2012$) By Final Cost Center$ (000)
2008 2009 2010 2011 2012
F527625 SOLAR PV MAINTENANCE 551 SUPERVISION & ENGINEERING
0 0 0 0 0
Total 0 0 0 0 0
* * Due to rounding, totals m ay not tie to o ther workpaper pages.
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
63Workpaper - Southern California Edison / 2015 GRC - APPLICATION
FERC Account:
Activ ity:
Witness:
551 Maintenance Supervision and Engineering
551 - SOLAR PHOTOVOLTAIC PROGRAM
Rodolfo L Perez
APPENDIX B
Detail of Total Company Adjustments to Recorded
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION64
FERC Account: 551 Maintenance Supervision and Engineering
A ctiv ity: 551 - SOLAR PHOTOVOLTAIC PROGRAM
Witness: Rodolfo L Perez
Detail o f Total Company Adjustm ents to Recorded Expenses
|Adjs - (Nominal $) $ (000)2008 2009 2010 2011 2012 2013 2014 2015
Labor 0 0 0 (58) (114) 0 0 0Non-Labor 0 0 0 (58) (18) 0 0 0Other 0 0 0 0 0 0 0 0
Total 0 0 0 (116) (132) 0 0 0
Organizational Unit Adjustment 1 GBU-CPT-OU-SPVP ROLL UPTO 549
This adjustment transfers Solar costs from FERC 546, 548, 551, 553, and 554 to FERC 549 Operations.
Labor 0 0 0 (58) (114) 0 0 0Non-Labor 0 0 0 (58) (18) 0 0 0Other 0 0 0 0 0 0 0 0
Total 0 0 0 (116) (132) 0 0 0
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
65Workpaper - Southern California Edison / 2015 GRC - APPLICATION
End of Workpapers for:
FERC Account: 551 Maintenance Supervision and Engineering
A ctiv ity: 551 - SOLAR PHOTOVOLTAIC PROGRAM
Witness: Rodolfo L Perez
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION66
THIS PAGE INTENTIONALLY LEFT BLANK
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
67Workpaper - Southern California Edison / 2015 GRC - APPLICATION
E xhib it SCE-02, Volume 10 WORKPAPERS
Solar Photovoltaic Program
O & M FERC Account 553
Witness: Rudy Perez
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION68
Beginning of Workpapers for:
FERC Account: 553 Maintenance of Generating and Electric Plant
Activ ity: 553 - SOLAR PHOTOVOLTAIC PROGRAM
Witness: Rodolfo L Perez
Forecast Method Chosen
2012$ (000)
Recorded2012
Forecast2015
Labor N/A 0 0Non-Labor N/A 0 0Other N/A 0 0Total 0 0
Description of Activity:
This activity package has zero dollars; all costs have been transferred to other activities.
Final Cost Centers included in this activity (See Appendix A for additional detail):
F527651 F528076 F528080 F528336
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
69Workpaper - Southern California Edison / 2015 GRC - APPLICATION
FERC Account: 553 Maintenance of Generating and Electric Plant
A ctiv ity : 553 - SOLAR PHOTOVOLTAIC PROGRAM
Witness: Rodolfo L Perez
D E T E R M IN A T IO N O F R E C O R D E D /A D J U S T E D
|_____________________________________________________________ R e c o rd e d P e rio d _________________
$ (000)
2008 2009 2010 2011 2012
F E R C F o rm 1 R e c o rd e d (N o m in a l $ )
Labor 0 0 0 13 186
N on-Labor 0 0 0 34 225
O the r 0_____________ 0______________ 0______________0_____________0
Total 0 0 0 47 411
A d ju s tm e n ts - (N o m in a l $) - s e e A p p e n d ix B fo r a d d it io n a l d e ta il
Labor 0 0 0 (13) (186)
Non-Labor 0 0 0 (34) (225)
O ther 0 0 0 0 0
Total 0 0 0 (47) (411)
R e c o rd e d /A d ju s te d (N o m in a l $)
Labor 0 0 0 0 0
Non-Labor 0 0 0 0 0
O ther 0 0 0 0 0
Total 0 0 0 0 0
E sca la tio n :
Labor 1.1414 1.1070 1.0701 1.0327 1.0000
Non-Labor 1.0881 1.0814 1.0642 1.0254 1.0000
O ther 1.0000 1.0000 1.0000 1.0000 1.0000
R e c o rd e d /A d ju s te d (C o n s ta n t 2 0 1 2 $ )
Labor
N on-Labor
O ther
Total
R e c o rd e d A d ju s te d 2 0 0 8 -2 0 1 2 (2 0 1 2 $ )
2008 2009 2010 2011 2012
□ L ab o r (s td esc l) ■ N o n -L abo r (s td e sc l) □ O the r (no t esc l)
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION70
THIS PAGE INTENTIONALLY LEFT BLANK
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
71Workpaper - Southern California Edison / 2015 GRC - APPLICATION
FERC Account:
Activ ity:
Witness:
553 Maintenance of Generating and Electric Plant
553 - SOLAR PHOTOVOLTAIC PROGRAM
Rodolfo L Perez
APPENDIX A
Detail Description of Final Cost Centers Included in This Activity
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION72
FERC Account: 553 Maintenance of Generating and Electric Plant
Activ ity: 553 - SOLAR PHOTOVOLTAIC PROGRAM
Witness: Rodolfo L Perez
Recorded/Adjusted (Constant 2012$) By Final Cost Center$ (000)
2008 2009 2010 2011 2012
F527651 SOLAR PV MAINTENANCE 553 MAINTENANCE OF GENERATION & ELECTRICAL EQUIPMENT
0 0 0 0 0
F528076 SOLAR PV SITE 5 MAINTENANCE 553 MAINTENANCEGENERATION-ELECTRICAL EQUIPMENT
0 0 0 0 0
F528080 SOLAR PV MAINTENANCE 553 MAINTENANCEGENERATION-ELECTRICAL EQUIPMENT
0 0 0 0 0
F528336 SOLAR PV SITE 2 MAINTENANCE 553 GENERATION-ELECTRICAL EQUIPMENT
0 0 0 0 0
Total 0 0 0 0 0
* * Due to rounding, totals m ay not tie to o ther workpaper pages.
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
73Workpaper - Southern California Edison / 2015 GRC - APPLICATION
FERC Account:
Activ ity:
Witness:
553 Maintenance of Generating and Electric Plant
553 - SOLAR PHOTOVOLTAIC PROGRAM
Rodolfo L Perez
APPENDIX B
Detail of Total Company Adjustments to Recorded
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION74
FERC Account: 553 Maintenance of Generating and Electric Plant
A ctiv ity: 553 - SOLAR PHOTOVOLTAIC PROGRAM
Witness: Rodolfo L Perez
Detail o f Total Company Adjustm ents to Recorded Expenses
|Adjs - (Nominal $) $ (000)2008 2009 2010 2011 2012 2013 2014 2015
Labor 0 0 0 (13) (186) 0 0 0Non-Labor 0 0 0 (34) (225) 0 0 0Other 0 0 0 0 0 0 0 0
Total 0 0 0 (47) (411) 0 0 0
Organizational Unit Adjustment 1 GBU-CPT-OU-SPVP ROLL UPTO 549
This adjustment transfers Solar costs from FERC 546, 548, 551, 553, and 554 to FERC 549 Operations.
Labor 0 0 0 (13) (186) 0 0 0Non-Labor 0 0 0 (34) (225) 0 0 0Other 0 0 0 0 0 0 0 0
Total 0 0 0 (47) (411) 0 0 0
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
75Workpaper - Southern California Edison / 2015 GRC - APPLICATION
End of Workpapers for:
FERC Account: 553 Maintenance of Generating and Electric Plant
Activ ity:
W itness:
553 - SOLAR PHOTOVOLTAIC PROGRAM
Rodolfo L Perez
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION76
THIS PAGE INTENTIONALLY LEFT BLANK
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
77Workpaper - Southern California Edison / 2015 GRC - APPLICATION
Exhibit SCE-02, Volume 10 WORKPAPERS
Solar Photovoltaic Program
O & M FERC Account 554
Witness: Rudy Perez
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION78
Beginning of Workpapers for:
FERC Account: 554 Maintenance of Miscellaneous Other Power Generation Plant
Activ ity: 554 - SOLAR PHOTOVOLTAIC PROGRAM
Witness: Rodolfo L Perez
Forecast Method Chosen
2012$ (000)
Recorded2012
Forecast2015
Labor N/A 0 0Non-Labor N/A 0 0Other N/A 0 0Total 0 0
Description of Activity:
This activity package has zero dollars; all costs have been transferred to other activities.
Final Cost Centers included in this activity (See Appendix A for additional detail):
F527626
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
79Workpaper - Southern California Edison / 2015 GRC - APPLICATION
FERC Account: 554 Maintenance of Miscellaneous Other Power Generation Plant
A ctiv ity : 554 - SOLAR PHOTOVOLTAIC PROGRAM
Witness: Rodolfo L Perez
D E TER M INA TIO N O F REC O R D ED /A D JU STED
Recorded Period
$ (0 0 0 )
2 0 0 8 2 0 0 9 2 0 1 0 2011 2 0 1 2
FERC Form 1 Recorded (N om inal $)Labor 0 0 0 0 18
Non-Labor 0 0 0 0 59
O ther 0 0 0 0 0
Total 0 0 0 0 77
A d justm ents- (Nom inal $)
Labor
see Appendix B fo r add itional detail0 0 0 0 (18)
Non-Labor 0 0 0 0 (59)
O ther 0 0 0 0 0
Total 0 0 0 0 (77)
Recorded/A d justed (Nom inal $)
Labor 0 0 0 0 0
Non-Labor 0 0 0 0 0
O ther 0 0 0 0 0
Total 0 0 0 0 0
E sca la tio n
Labor 1.1414 1.1070 1.0701 1.0327 1.0000
Non-Labor 1.0881 1.0814 1.0642 1.0254 1.0000
O ther 1.0000 1.0000 1.0000 1.0000 1.0000
R ecorded/A djusted (C onstan t 2012$)
Labor 0 0 0 0 0
Non-Labor 0 0 0 0 0
O ther 0 0 0 0 0
Total 0 0 0 0 0
Recorded A d justed 2008-2012 (2012$)
6
4
2
0
-2
-4
2008 2009 2010 2011 2012
□ Labor (std esc l) ■ N o n -L abo r (s td esc l) □ O the r (n o t e sc l)
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION80
THIS PAGE INTENTIONALLY LEFT BLANK
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
81Workpaper - Southern California Edison / 2015 GRC - APPLICATION
FERC Account:
Activ ity:
Witness:
554 Maintenance of Miscellaneous Other Power Generation Plant
554 - SOLAR PHOTOVOLTAIC PROGRAM
Rodolfo L Perez
APPENDIX A
Detail Description of Final Cost Centers Included in This Activity
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION82
FERC Account: 554 Maintenance of Miscellaneous Other Power Generation Plant
Activ ity: 554 - SOLAR PHOTOVOLTAIC PROGRAM
Witness: Rodolfo L Perez
Recorded/Adjusted (Constant 2012$) By Final Cost Center$ (000)
2008 2009 2010 2011 2012
F527626 SOLAR PV MAINTENANCE 554 MISCELLANEOUS GENERATION EXPENSES
0 0 0 0 0
Total 0 0 0 0 0
** Due to rounding, totals may not tie to other workpaper pages.
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
83Workpaper - Southern California Edison / 2015 GRC - APPLICATION
FERC Account:
Activ ity:
Witness:
554 Maintenance of Miscellaneous Other Power Generation Plant
554 - SOLAR PHOTOVOLTAIC PROGRAM
Rodolfo L Perez
APPENDIX B
Detail of Total Company Adjustments to Recorded
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION84
FERC Account: 554 Maintenance of Miscellaneous Other Power Generation Plant
A ctiv ity: 554 - SOLAR PHOTOVOLTAIC PROGRAM
Witness: Rodolfo L Perez
Detail o f Total Company Adjustm ents to Recorded Expenses
|Adjs - (Nominal $) $ (000)2008 2009 2010 2011 2012 2013 2014 2015
Labor 0 0 0 0 (18) 0 0 0Non-Labor 0 0 0 0 (59) 0 0 0Other 0 0 0 0 0 0 0 0
Total 0 0 0 0 (77) 0 0 0
Organizational Unit Adjustment 1 GBU-CPT-OU-SPVP ROLL UP TO 549
This adjustment transfers Solar costs from FERC 546, 548, 551, 553, and 554 to FERC 549 Operations.
Labor 0 0 0 0 (18) 0 0 0Non-Labor 0 0 0 0 (59) 0 0 0Other 0 0 0 0 0 0 0 0
Total 0 0 0 0 (77) 0 0 0
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
85Workpaper - Southern California Edison / 2015 GRC - APPLICATION
End of Workpapers for:
FERC Account: 554 Maintenance of Miscellaneous Other Power Generation Plant
A ctiv ity: 554 - SOLAR PHOTOVOLTAIC PROGRAM
Witness: Rodolfo L Perez
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION86
THIS PAGE INTENTIONALLY LEFT BLANK
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
87Workpaper - Southern California Edison / 2015 GRC - APPLICATION
Exhibit SCE-02, Volume 10 WORKPAPERS
Solar Photovoltaic Program
Capital Expenditures
Witness: Rudy Perez
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION88
Southern California Edison Company
CA PITAL W O R K P A P E R S - 2015 G R C
O P E R A T IN G U N IT SU M M A R Y
(Nominal $000)
Operating Unit Summary: GEN - Solar PV
(1) OPERATING UNIT FORECAST CAPITAL EXPENDITURES: 2015 GRC
Item Testimony DescriptionForecast Capital Expenditures
2013 2014 2015 2016 2017 Total
1 Generation 31,500 0 C 0 0 31,500
2 Projects and Blanket Work Orders Under $1 Million 0 425 1,035 269 5,680 7,409
Total 31,500 425 1,035 269 5,680 38,909
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
89Workpaper - Southern California Edison / 2015 GRC - APPLICATION
S outhern C a lifo rn ia Ed ison C om pany
C A P ITA L W O R K P A P E R S - 2015 G R C
OPERATING UNIT SUMMARY
(Nominal $000)
Operating Unit Summary: G EN - So lar PV
(2) O PERA TIN G UNIT R E C O R D E D AND AU TH O RIZED C A P ITA L AND F O R E C A S T E X P EN D ITU R ES: 2015 GRC
DescriptionRecorded and Authorized Capital Expenditures Forecast Capital Expenditures
2008 2009 2010 2011 2012 2013 2014 2015 2016 2017
Authorized Expenditures 0 87,991
Recorded & Forecast Expenditures 11,159 9,316 121,315 161,619 32,186 31,500 425 1,035 269 5,680
Total Expenditure 335,594 38,909
Recorded, Authorized and Forecast Expenditures Graph
180,000
160.000
140.000
120.000
t)0,000
80,000
60,000
40.000
20.000
02008 2009 2010 2011 2012 2013 2014 2015 2016 2017
R e c o rd e d | j A u th o r iz e d F o reca s t
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION90
Southern California Edison Company
CAPITAL W O R K P A P E R S - 2015 G R C
P R O JE C T DETAIL W O R K S H E E T : SO LA R C O N S TR U C T IO N
Organizational Unit Summary: GEN - Solar PV Testimony Summary: SCE-02, Volume 10 Major Program: Generation Category: Gen - Solar Detail: Solar Construction Database ID: 1145 / RO Model ID: 13
1. WITNESS
2. PROJECT DETAILProgram Group
Program
P in #
W B S Element
3. PROJECT TYPE
Rudy Perez
P P D SP V P
S P E C IF IC -S C
6556
C G 0-00-P P -S C -000001
Select one
Compliance: Safety, Environmental, Licenses
Replacem ents in Kind
Upgrades
Blanket: FE, Tools, Spare Parts, Lab, Computer Equip
Select one
Customer Growth
Load Growth
Reliability
Capitalized Software
Various (See Below)
4. ASSET TYPE
5. CLOSE DATE
6. RIIM ELIGIBLE
Solar PV
12/1 /2013
N/A
20 1 5 GRC - C a p i t a l E x p e n d i t u r e s F o r e c a s t
25,000
20,000
15,000
10,000
2013 2014 2015 2016 2017
7. COST ESTIMATES (NOMINAL $000)
Yr SC E $
2013 31,500
2014 0
2015 0
2016 0
2017 0
Total 31,500
X
7(a). SYSTEM SHORT TEXT
7 (b). DETAILED DESCRIPTION
8. SCOPE
9. JUSTIFICATION
PP D S P V P Construction
Solar Photovoltaic Program (S P V P ) Construction - Capital expenditures in 2013 reflect the capital required to complete the construction of the S P V P final solar site, Redlands distribution center (RD C) 10.
Conclusion of the build out of the S P V P program, which includes installation of the Electrical Fault Protection System and the Emmerson Comm and and Control systems on all the S P V P facilities.
Capital is required to finish construction of S P V P Utility owned generation's (U O G ) final site and fulfill the Commission's build-out requirements per Decision 13-05-033. The Electrical Fault Protection and Em merson Comm and and Control systems are needed to ensure that the S P V P sites are operated, monitored, and maintained safely and effectively throughout their life.
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
91Workpaper - Southern California Edison / 2015 GRC - APPLICATION
Southern California Edison Company
CAPITAL W O R K P A P E R S - 2015 G R C
P R O JE C T DETAIL W O R K S H E E T : SP A R E PA RTS BLANKET
Organizational Unit Summary: GEN - Solar PV Testimony Summary: SCE-02, Volume 10Major Program: Projects and Blanket Work Orders Under $1 MillionCategory: BlanketDetail: Spare Parts BlanketDatabase ID: 1146 / RO Model ID: 14
1. WITNESS2. PROJECT DETAIL
Program Group
Program
P in #
W B S Element
3. PROJECT TYPE
Rudy Perez
P P D S P V
BLAN KET S P V
7132
C G 0-00-P P -S P-000004
Select one
Compliance: Safety, Environmental, Licenses
Replacem ents in Kind
Upgrades
Blanket: FE, Tools, Spare Parts, Lab, Computer Equip
Select one
X
Customer Growth
Load Growth
Reliability
Capitalized Software
Various (See Below)
4. ASSET TYPE
5. CLOSE DATE
6. RIIM ELIGIBLE
Solar PV
Blanket
N/A
7. COST ESTIMATES (NOMINAL $000)
Yr SC E $
2013 0
2014 425
2015 1,035
2016 269
2017 5,680
Total 7,409
20 15 GRC - C a p i t a l E x p e n d i t u r e s F o r e c a s t
6 000
5.000
4000
3 000
2000
1000
02013 2014 2015 2016 2017
7(a). SYSTEM SHORT TEXT
7 (b). DETAILED DESCRIPTION
8. SCOPE
9. JUSTIFICATION
PPD Solar Photovoltaic 044-S pare Parts
S o la r Pho tovo lta ic (S P V ) 044 -S pare Parts - C ap ita l expend itu res in 2014 through 2017 reflect expend itu res ca tegorized as cap ita l under SCE accounting sys tem s; these expend itu res inc lude the rep lacem ent o f parts, p rim arily inverters and tran s fo rm ers utilized fo r pow er contro l in S P V system s.
Purchase o f cap ita l rep lacem ent parts, p rim arily inverte rs and tran s fo rm ers fo r O &M o f the SP VP utility ow ned genera tion (UO G ) fac ilities .
C ap ita l rep lacem ent pa rts are required to m ainta in the S o la r P ho tovo lta ic P rogram (SPV P) s ites in w orking cond ition . W ith o u t spare parts to replace fa iled com pone n ts , s ites w ould de terio ra te and not opera te at rated capacity .
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION92
THIS PAGE INTENTIONALLY LEFT BLANK
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
93Workpaper - Southern California Edison / 2015 GRC - APPLICATION
Exhibit SCE-02, Volume 10 WORKPAPERS
Solar Photovoltaic Program
D .09-06-049
Witness: Rudy Perez
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION94
THIS PAGE INTENTIONALLY LEFT BLANK
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
95Workpaper - Southern California Edison / 2015 GRC - APPLICATION
COM /JB2/ avs Date of Issuance 6/2^2009
Decision 09-06-049 June 18, 2009
BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA
Application of Southern California EdisonCompany (U338E) for Authority to Implement Application 08-03-015and Recover in Rates the Cost of its Proposed (Filed March 27,2008)Solar Photovoltaic (PV) Program.
DECISION ADDRESSING A SOLAR PHOTOVOLTAIC PROGRAM FOR SOUTHERN CALIFORNIA EDISON COMPANY
387876 - 1 -
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION96
A.08-03-015 COM/JB2/ avs
energy system."12 More recently, the California Air resources Board adopted a
scoping plan that specifically identified a target of 33% renewables by 2020 as a
key strategy that will help the state achieve its 2020 greenhouse gas emission
reduction goal. Consistent with these principles, and given the magnitude of the
state's renewable objectives, we find that the SPVP is a reasonable step to
encourage development of more distributed renewable resources in the one to
two MW range. The SPVP projects can be located near load, thus avoiding the
need to build new transmission facilities and help reduce local congestion. The
ability to deploy this technology quickly also can help advance California's
broad goal of developing renewable energy and specifically help make progress
tow ard the state's emphasis on developing distributed rooftop solar PV projects
while other options are being considered. Although we agree with the intent of
the SPVP, as discussed below, several modifications to the proposed SPVP are
necessary in order to allow more competition consistent with Commission
policies. The following sections address these issues.
4. Discussion of the Adopted Plan
4.1. Summary
In order to determine w hether to adopt the proposed program or a
modified proposal, we consider Commission policies applicable to this
application and the relevant statute.
12 Energy Action Plan I, p. 8
- 1 1 -
ExhibitNo. SCE-02/ Generation/ Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
97Workpaper - Southern California Edison / 2015 GRC - APPLICATION
A.08-03-015 COM/JB2/ avs
incentives. Because of all these differences, the SPVP will not be counted
towards the CSI target.
Furthermore, to ensure there is no conflict between the CSI and the SPVP,
we adopt DRA's proposal and direct SCE to target project sites for the SPVP that
do not have sufficient on-site load to participate in the CSI program.
Solar Alliance supports this concept, but suggests we require a statement from
roof space owners acknowledging that they know and understand the benefits
offered through the CSI, but have chosen to lease their roof space for wholesale
power production instead.52 This requirement w ould provide clarity to the
process and may prevent future disputes. We find it appropriate and
incorporate it in the adopted SPVP.
We also decline to adopt Greenlining's proposal to require information on
supplier diversity and low-income enrollment as part of the adopted SPVP. The
Commission has separate processes for monitoring and examining utility
supplier diversity and also ensuring that the utilities comply w ith low-income
utility service requirements. The adopted SPVP is not the appropriate vehicle for
such review.
5. Cost Recovery
SCE expects to incur approximately $41.31 million (2008$) in O&M and
$875.0 million (2008$) in direct capital expenditures over the 2008 through
2014 program period, and requests that the Commission find reasonable up to
$962.5 million (2008$)in direct capital expenditures during the 2008 through
52 Solar Alliance comments at pp. 4-5.
-44 -
Exhibit No. SCE-02/ Generation/ Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION98
A.08-03-015 COM /JB2/avs
2014 program period.53 SCE has also requested authority to establish the
Solar PV Program Balancing Account (SPVPBA) to record the difference
between: (1) the actual incremental O&M and capital-related revenue
requirement and; (2) the recorded Solar PV Program-related revenue. We find
these cost estimates reasonable.
DRA in comments to the PD recommends an annual review of SCE's plant
operation via a Tier 3 advice letter.54 DRA also suggests that SCE's lease costs
above $21,000/MW/Year (20% over SCE's estimate) and SCE's annual O&M
costs above $33,000/Year (20% over SCE's estimate) be disallowed.55 As
discussed below, we will review SCE's operation of SPVP (including SCE's
maintenance practices and performance of the facilities) in its ERRA proceeding,
and review all program costs (including O&M costs) in SCE's GRC. We direct
that SCE's lease costs and SCE's annual O&M costs be subject to reasonableness
review in SCE's GRC.
6. Scope and Timing of Reasonableness Review
6.1. Parties’ Positions
Greenlining argues that "the SPVP is a more costly and less certain means
of achieving progress toward the Million Solar Roofs goal, as compared to CSI,
and will not result in savings to Edison's ratepayers."56 Greenlining is concerned
that in contrast to the CSI, where the ratepayers only fund incentives given to
53 The $962.5 million includes a 10% adder.54 DRA Comments at p. 2.
55 Ibid.
56 Greenlining Opening Brief at p. 7.
- 4 5 -
ExhibitNo. SCE-02/ Generation/ Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
99Workpaper - Southern California Edison / 2015 GRC - APPLICATION
A.08-03-015 COM/JB2/ avs
performance based on what it knew or should have known at the time.58 SCE
argues that if as part of this review, the Commission finds that the SPVP did not
operate in a prudent manner, the Commission could disallow recovery of the
replacement power costs (i.e., the replacement power costs w ould be borne by
SCE's shareholders rather than customers). SCE argues that no form of cost
sharing or additional incentives are necessary because the review process in
ERRA will create adequate incentives for prudent system performance.59
6.2. DiscussionSCE's claimed primary potential benefit of the SPVP is that this project
w ould provide additional MWs of renewable energy. However, several parties
contend that as proposed, there is no guarantee that any of the projected power
will be actually delivered. Parties are therefore concerned that the ratepayers
will be paying for an investment that may never produce the expected benefits,
and they encourage us to consider some protection in case the expected benefits
from the investments paid by ratepayers are never realized.
As a general matter, the Commission has an ongoing duty to ensure that
utility investments result in infrastructure that is used and useful. In the context
of utility owned generation, we have long-standing policies and procedures in
place under which utility projects are reviewed to make sure that approved
investments are being made in a reasonable m anner and that the resulting
facilities actually fulfill their stated purpose. As SCE points out, in the context of
utility generation projects, this review is done in the utilities' annual Energy
58 SCE Opening Brief at p. 29.
59 SCE Opening Brief at p. 29.
- 4 7 -
ExhibitNo. SCE-02/ Generation/ Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION100
A.08-03-015 COM/JB2/ avs
Resources Recovery Account proceedings. We see no compelling reason why in
the context of the SPVP we should stray from this existing process. While the
program is itself new there is nothing about the UOG portion of the program,
nor anything parties have presented, to suggest that the ERRA proceeding and
the after the fact reasonableness review of operations conducted therein is
insufficient to protect ratepayer interests. As SCE notes, should the Commission
find in the ERRA proceeding that SCE did not live up to its responsibilities or did
not prudently maintain and operate the solar facilities built pursuant to this
program, the Commission can disallow recovery of certain costs.
We decline to adopt TURN'S framework for sharing cost overruns between
ratepayers and shareholders in the event that installation costs exceed $3.85 a
watt. Reasonableness of capital costs, O&M costs and other UOG expenses are
typically addressed in a utility's GRC. We see no reason why review of SPVP
costs should be different than for other utility owned resources. However, as
discussed above, we will use the ERRA proceeding to review SCE's operation of
the SPVP plant.
In addition, to help the Commission better understand the impacts of this
program, and the comparative costs and benefits of UOG and IPP solar PV
generation, the Commission will monitor this program on an ongoing basis. As
part of this review, we will examine, among other measures, the result of the
competitive solicitation and the number of market participants competing for
access to the one to two MW market. We will also monitor the prices received
under the PPA portion of the program as well as the costs SCE incurs under the
UOG portion of the program. This will provide for a broader comparison
between utility owned renewable generation and generation projects that result
from the competitive solicitation. Because SCE's GRC occurs only every
- 4 8 -
ExhibitNo. SCE-02/ Generation/ Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
101Workpaper - Southern California Edison / 2015 GRC - APPLICATION
A.08-03-015 COM/JB2/ avs
three years, in order for the Commission to have timely data to evaluate this
program and consistent with the requirements of Pub. Util. Code § 2775.5, SCE
shall file an annual compliance report in this proceeding. SCE shall consult with
Energy Division to develop the format and content of the report. The
information provided in these reports shall be reviewed by Energy Division and
shall be reflected in the Commission's reports to the legislature on the RPS
program.
The first report shall be filed on July 1, 2010. The report shall include, at a
minimum, the following:
• All solicitations issued for PPA contracts;
• A description of all bids received from the PPA solicitations, including name of bidder, location of bid, bid price, and description of proposed facility (generating capacity, type of technology, host customer, host tenant, and on-site load). SCE should indicate the winning bids;
• The total electrical output for all SPVP systems under PPS contract that are currently selling electricity to SCE, for each m onth of the previous year.
• A calculation of the LCOE for each SCE-owned facility that is completed and interconnected to the grid. SCE should accompany this calculation w ith workpapers showing actual amounts for all cost and electrical output entries that are used to calculate LCOE;
• Electrical output by m onth for the previous year for each SCE-owned facility that is completed and interconnected to the grid; and
• A description of all facilities for which work has been initiated or completed in the previous year, including: capital and O&M expenses; generating capacity; description of the site (host customer, host tenant, lease cost and on-site load); progress toward completion.
- 49 -
ExhibitNo. SCE-02/ Generation/ Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION102
A.08-03-015 COM/JB2/ avs
Resolution E-4182 authorized SCE to establish a m em orandum account to
record the incremental O&M and capital-related revenue requirement associated
w ith the first $25 million of direct capital expenditures in the SPVP (SPVPMA).
Ordering Paragraph 4 states that the Commission will address rate recovery of
the amounts recorded in the SPVPMA when it acts on SCE's SPVP application.
SCE shall transfer the balance in the SPVPMA to the SPVPBA for future rate
recovery after the Commission reviews the balance in the ERRA proceeding.
7. Rate of Return Issues
7.1. Parties’ Position
SCE requests that its investment earn 100 basis points above its authorized
ROR. SCE claims that D.06-05-039 allows the Commission to authorize this
increase for utility-owned renewable generation.60 SCE first m ade its request as
follows:
"As authorized in D.06-05-039, SCE calculated the rate of return on rate base using SCE's current authorized rate of return of 8.75%, plus 1%, since this new plant will be utility-owned renewable generation."61
SCE later in its rebuttal testimony noted that its proposal meets the
requirements of § 454.3(c), because it will develop a segment of the market that
currently lacks production.62
DRA and TURN oppose SCE's request on the basis that it does not meet
any one of the requirements of § 454.3, although TURN in its opening brief notes
that the minimum 50 basis points could be justified, albeit "under the most
60 Exhibit SCE-1 at p. 55.
61 Id at p. 54.
- 5 0 -
ExhibitNo. SCE-02/ Generation/ Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
103Workpaper - Southern California Edison / 2015 GRC - APPLICATION
A.08-03-015 COM /JB2/avs
7. The energy generated from the SPVP projects should be counted toward
SCE's RPS goal.
8. The UOG portion of the SPVP should be subject to cost of service
regulation.
9. Review of all SPVP costs should be conducted in SCE's GRC proceeding
and review of SPVP performance and SCE's operation of the facilities should be
conducted in SCE's annual ERRA proceeding.
10. Costs above $3.85/W should be subject to a reasonableness review.
11. SCE should be authorized to establish a balancing account to record the
difference between the SPVP's actual and recorded expenses and revenues.
12. The Commission should monitor the SPVP on an ongoing basis to assess
the progress and impacts of the program on the wholesale distributed solar
energy market. A full review of the SPVP should occur in SCE's GRC
proceeding.
13. The adopted SPVP does not meet the criteria of Pub. Util. Code § 454.3 for
an increase of 100 basis points.
14. Within 30 days of the effective date of this decision, SCE should file an
advice letter w ith the Energy Division delineating the criteria for selection of the
bids, and containing a draft standard 20-year PPA contract for use in the RFO.
15. SCE should file an annual compliance report as described in Section 6.2 of
this decision. The first report should be due on July 1, 2010, and subsequent
reports filed on July 1 every year thereafter. The filing of the compliance report
does not re-open the proceeding.
16. A.08-03-015 should be closed.
- 5 7 -
ExhibitNo. SCE-02/ Generation/ Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION104
A.08-03-015 COM/JB2/ avs
O R D E R
IT IS ORDERED that:
1. Southern California Edison Company's solar photovoltaic program is
modified as follows:
• 250 megawatt of utility-owned distributed generation (about 50 megawatt annually). Southern California Edison Company to own, install, operate and maintain distributed solar photovoltaic projects primarily in the one to two megawatts, located in Southern California Edison Company's service territory on existing commercial rooftops. Projects cost target at $3.50/Watt w ith a 10% contingency.
• 250 megawatt of distributed generation owned by independent power producers (about 50 megawatt annually) to be solicited at least once per year. Bids capped at Southern California Edison Company's estimated levelized costs of electricity. An Independent Evaluator should be secured to oversee the solicitation for the first two years of the program and thereafter if a utility affiliate participates in that process. Contracts will be based on standard 20-year power purchase agreement contracts.
• A five-year program.
• Cost of service treatment for utility-owned generation portion of the program.
• No increase in authorized rate of return.
• Costs in excess of $3.85 per watt subject to a reasonableness review.
2. Within 30 days of the effective date of this decision, Southern California
Edison Company shall file an Advice Letter w ith the Energy Division delineating
the criteria and process for evaluating offers received and containing a draft
- 5 8 -
ExhibitNo. SCE-02/ Generation/ Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
105Workpaper - Southern California Edison / 2015 GRC - APPLICATION
A.08-03-015 COM/JB2/ avs
standard 20-year power purchase agreement contract for use in the request for
offer.
3. Southern California Edison Company shall transfer the balance in the
Solar Photovoltaic Program M emorandum Account to the Solar Photovoltaic
Program Balancing Account for future rate recovery after Commission's review
of the balance in the energy resource recovery account reasonableness
proceeding.
4. Southern California Edison Company shall file an annual compliance
report in this proceeding as described in Section 6.2 of this decision. The first
report shall be filed on July 1, 2010, and subsequent reports filed on July 1
thereafter. The filing of the compliance report does not re-open the proceeding.
5. Application 08-03-015 is closed.
This order is effective today.
Dated June 18,2009, at San Francisco, California.
MICHAEL R. PEEVEY President
DIAN M. GRUENEICH JOHN A. BOHN RACHELLE B. CHONG TIMOTHY ALAN SIMON
Commissioners
I reserve the right to file a concurrence.
/ s / Dian M. Grueneich Commissioner
- 5 9 -
ExhibitNo. SCE-02/ Generation/ Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION106
THIS PAGE INTENTIONALLY LEFT BLANK
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
106aWorkpaper - Southern California Edison / 2015 GRC - APPLICATION
Att D R A Verbal 008 G01 Page 1
BEFORE THE PUBLIC UTILITIES COMMISSION OF THE F I L E DSTATE OF CALIFORNIA 03-27-08
08:49 AM
Application of Southern California Edison Company (U 338-E) for Authority to Implement and Recover in Rates the Cost of its Proposed Solar Photovoltaic (PV) Program.
A
A0803015
APPLICATION OF SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E) FOR AUTHORITY TO IMPLEMENT AND RECOVER IN RATES THE COST OF ITS
PROPOSED SOLAR PHOTOVOLTAIC (PV) PROGRAM
DOUGLAS K. PORTER CAROL A. SCHMID-FRAZEE ANNETTE GILLIAM
Attorneys forSOUTHERN CALIFORNIA EDISON COMPANY
2244 Walnut Grove Avenue Post Office Box 800 Rosemead, California 91770 Telephone: (626) 302-1337Facsimile: (626) [email protected]
Exhibit No. SCE-02 / Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Dated: March 27, 2008
Workpaper - Southern California Edison / 2015 GRC - APPLICATION106b
Att D R A Verbal 008 G01 Page 2
BEFORE THE PUBLIC UTILITIES COMMISSION OF THE
STATE OF CALIFORNIA
Application of Southern California Edison Company (U 338-E) for Authority to Implement and Recover in Rates the Cost of its Proposed Solar Photovoltaic (PV) Program.
A.08-03-
APPLICATION OF SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E) FOR AUTHORITY TO IMPLEMENT AND RECOVER IN RATES THE COST OF
ITS PROPOSED SOLAR PHOTOVOLTAIC (PV) PROGRAM
I.
SUMMARY OF REQUEST
Pursuant to Rule 3.2 of the California Public Utilities Commission (Commission or
CPUC) Rules of Practice and Procedure, Southern California Edison Company (SCE) hereby
submits this application requesting the Commission to:
(1) Find it reasonable for SCE to implement a Solar Photovoltaic (PV) Program that
would consist of up to 250 megawatts (MW)l of utility-owned solar PV
generating facilities of approximately 1 to 2 MW2 each over the next five years;
(2) Establish ratemaking for SCE’s Solar PV Program, specifically including:
1 U n less o therw ise specified , any reference to energy ou tpu t in th is filing fo llow s the com m on convention w ithin the P V industry , w hich is to refe r to ou tpu t as P V panel d irec t curren t (dc) output. A dditionally , SCE proposes using installed dc ou tpu t in reasonab leness rev iew s because installa tion occurs in dc panels. T he conversion facto r o f 0.90 w ill be used to convert from M W dc to M W alternating curren t (ac) based on sam ple calculations using the C a lifo rn ia E nergy C om m ission ’s ac M W to conversion (i.e., m ultip ly M W dc by 0.90 to obtain M W C E C -ac Rating).
2 SCE envisions the ind iv idual Solar P V Program installa tions to be in the 1 to 2 M W range. A s the programproceeds, how ever, som e installa tions m ay be larger o r sm aller than th is range due to ro o f size o r c ircu it loadingconsiderations.
1
Exhibit No. SCE-02 / Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
106cWorkpaper - Southern California Edison / 2015 GRC - APPLICATION
Att D R A Verbal 008 G01 Page 3
Table III-1Solar P V Program Estimated Base Case Capital Costs
(2008$ 000)
YearCapital
(Million $)MW
Installed Estimated Time Frame
0 $25 5 2008
1 $174 50 2009
2 $174 50 2010
3 $174 50 2011
4 $174 50 2012
5 $154 45 2013
Total $875 250
The Solar PV Program base case direct capital cost forecast is $875 million. The
average cost of the solar PV facilities should be about $3.50/W.12 At present, the average cost of
solar PV facilities above 900 kilowatts (kW) range from $6.56-7.08/W. SCE anticipates
achieving lower costs than the present average through economies of scale and improvements in
technology and efficiency.
b) O&M Costs
As noted previously, O&M costs consist of three components: (1) roof lease
payments; (2) other O&M costs; and (3) SCE staffing costs. With regard to the roof lease
payments, this is a new opportunity for the large rooftop owners. So, it is difficult to estimate
expected leasing rates. However, SCE anticipates that the maximum price paid for these roof
12 O n average, the reasonab leness th resho ld is 10% h igher than the base case estim ate o r about $3 .85/W . The reasonab leness th resho ld is h igher than th is am oun t in early years o f the Solar P V P rogram and low er in lateryears, as show n in T able IV -2 below .
13
Exhibit No. SCE-02 / Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION106d
Att D R A Verbal 008 G01 Page 4
BEFORE THE PUBLIC UTILITIES COMMISSION OF THE F I L E DSTATE OF CALIFORNIA 02-11-11
04:59 PM
Application of Southern California Edison )Company (U 338-E) for Authority to Implement )and Recover in Rates the Cost of its Proposed )Solar Photovoltaic (PV) Program _ )
Application 08-03-015
SOUTHERN CALIFORNIA EDISON COMPANY’S (U 338-E) PETITION FOR MODIFICATION OF DECISION 09-06-049
PUBLIC VERSION
DOUGLAS K. PORTER ANGELICA M. MORALES
Attorneys forSOUTHERN CALIFORNIA EDISON COMPANY
2244 Walnut Grove Avenue Post Office Box 800 Rosemead, California 91770 Telephone: 626-302-6160Facsimile: 626-302-6962E-mail:[email protected]
Exhibit No. SCE-02 / Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Dated: February 11, 2011
1772791
106eWorkpaper - Southern California Edison / 2015 GRC - APPLICATION
Att D R A Verbal 008 G01 Page 5
for utility-owned generation (“UOG”) and 250 MW of the Solar PV Program was to be owned, installed,
operated, and maintained by Independent Power Producers (“IPPs”).3
SCE is the nation’s leader in purchasing renewable energy on behalf of its customers. In fact, in
2009, SCE purchased roughly 80% of all solar power generated in the United States. From this experience,
SCE has witnessed firsthand the benefits that can accrue to customers because of greater competition.
Therefore, in order to permit greater competition among bidders and thus reduce the overall Solar PV
Program costs for SCE’s customers, the instant Petition requests that the Commission restructure SCE’s
existing 500 MW Solar PV Program in two ways:
1.) Reassign 250 MW to a separate competitive solicitation within the Solar PV Program that will
not be subject to the current parameters of the IPP portion (“IPP Revised”);4 and,
2.) Reduce the current UOG and original IPP portions of the Program respectively to an amount of
no more than 125 MW each.
Thus, if the Commission adopts this Petition, the 500 MW5 Program will be designated as follows:
1) no more than 125 MW as UOG;6 2) 125 MW for IPPs under the original solicitation process;7 and, 3)
250 MW for an IPP Revised solicitation.
Based on the success of the existing Solar PV Program and other procurement mechanisms, SCE
believes that the revisions proposed in this Petition will significantly reduce the costs of the Solar PV
Program going forward. The Commission has recognized that SCE’s Solar PV Program and its other
procurement efforts “suggest[] that the market for smaller scale projects appears robust with a significant
number of competing sellers.”8 Indeed, in a recent solicitation, outside of the Solar PV Program, SCE
3 D.09-06-049, Ordering Paragraph No. 1, p. 58.4 Among other things, SCE specifically recommends that the Commission designate the IPP Revised portion of the Solar PV
Program for distributed solar PV of up to 20 MW, without any limitation on ground-mounted installations.5 500 MW is an approximate number of projects installed. Final installed MW will depend on the engineering design
specifications of projects.6 SCE proposes that the Commission reduce the UOG portion of the Solar PV Program to “no more than” 125 MWs in order to
accommodate SCE’s existing obligations. The final UOG build out will depend on project specific engineering design specifications, but will be no more than 125 MW.
7 See D.09-06-049 and Resolution E-4299.8 D.10-12-048, p. 17 (decision adopting a Commission-approved procurement process for large investor-owned utilities- the
Renewable Auction Mechanism (“RAM”)).
2
Exhibit No. SCE-02 / Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION106f
Att D R A Verbal 008 G01 Page 6
procured 259 MW(ac), most of which was solar PV,9 at more competitive prices than received for bids in
the Solar PV Program.10 Current renewable energy trends have shown a significant market response for
solar PV systems. SCE’s entrance into the solar PV market through implementation of the Program has
encouraged development of solar generated electric power by, among other things, increasing the options
available for installing and operating commercial solar PV. Therefore, due to recent developments in the
solar market, including the results achieved through the Solar PV Program, the Commission should modify
D.09-06-049 as recommended in this Petition.
The Solar PV Program objectives remain achievable in a reduced-size UOG Program or have
already been satisfied. Indeed, SCE’s knowledge transfer related to PV technology is well underway and
has already resulted in positive industry changes.11 Moreover, solar power procured in the revised Program
would be consistent with the State’s goal of aggressively expanding the renewable industry in an
economically efficient manner. SCE believes it is in its customers’ best interests to revise the process
whereby it procures solar PV generation through its existing Solar PV Program. SCE’s current estimate
shows that revising the Solar PV Program as recommended in this Petition could result in a Present Value of
Revenue Requirements (PVRR) savings of approximately $300 million to all of SCE’s customers (as
compared to the cost of continuing the existing Program). This result is based on the assumption of
continued market availability at current price indications.12 Given that the Commission’s objectives have
been or appear likely to be met at reduced overall cost through the revised Program, modifying the Decision
is reasonable, justified, and in the public interest.13 Accordingly, the Commission should grant the Petition
and approve the modified Program as set forth in this Petition.
9 Subsequent to executing contracts from this solicitation, one contract has since terminated. The remaining 20 contracts are for 239 MW(ac) all from solar PV projects.
10 SCE procured these MW through its voluntary Renewable Standard Contract (“RSC”) Program solicitation. SCE is nolonger authorized to utilize its RSC Program for procurement of projects up to 20 MW in size. See D.10-12-048, Conclusionof Law No. 5, pp. 86-87 (“The IOUs should be required to use RAM exclusively for the procurement of system-side renewable projects up to 20 MW in size with the exception o f other Commission-approved programs such as the utility solar photovoltaic programs already authorized by the Commission and annual RPS solicitations; IOUs should not use voluntary programs that target the same market segment or bilateral negotiations.”) (Emphasis added.)
11 See Declaration of M. Nelson, ^ 3-14, attached as Appendix B.12 See Declaration of B. Hodges at ^ 6, attached as Appendix C.13 See D.10-10-029, p. 19 and Appendix A to D.10-10-029, p. 1 (granting SCE’s Petition for Modification of a power purchase
agreement (“PPA”) approved in D.08-09-041 on the basis that the requested changes were “reasonable, justified and in theContinued on the next page
3
Exhibit No. SCE-02 / Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
106gWorkpaper - Southern California Edison / 2015 GRC - APPLICATION
Att D R A Verbal 008 G01 Page 7
BEFORE THE PUBLIC UTILITIES COMMISSION OF T ffll L E D07-27-12
STATE OF CALIFORNIA 04:59 PM
Application of Southern California Edison Company (U 338-E) for Authority to Implement and Recover in Rates the Cost of its Proposed Solar Photovoltaic (PV) Program.
Application 08-03-015
(Filed March 27, 2008)
SOUTHERN CALIFORNIA EDISON COMPANY’S (U 338-E) PETITION FOR MODIFICATION OF DECISION NO. 12-02-035
DOUGLAS K. PORTER GLORIA M. ING
Attorneys forSOUTHERN CALIFORNIA EDISON COMPANY
2244 Walnut Grove Avenue Post Office Box 800 Rosemead, California 91770 Telephone: (626) 302-1999Facsimile: (626) 302-3990E-mail:[email protected]
Dated: July 27, 2012
LIM S-310-1452
Exhibit No. SCE-02 / Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION106h
Att D R A Verbal 008 G01 Page 8
BEFORE THE PUBLIC UTILITIES COMMISSION OF THE
STATE OF CALIFORNIA
Application of Southern California Edison )Company (U 338-E) for Authority to Implement ) Application 08-03-015and Recover in Rates the Cost of its Proposed )Solar Photovoltaic (PV) Program. ) (Filed March 27, 2°°9)
SOUTHERN CALIFORNIA EDISON COMPANY’S (U 338-E)PETITION FOR MODIFICATION OF DECISION NO. 12-02-035
I.
INTRODUCTION
Pursuant to Rule 16.4 of the California Public Utilities Commissions’ (“CPUC” or
“Commission”) Rules of Practice and Procedure and the direction in the June 13, 2012 letter from the
CPUC’s Energy Division denying SCE’s Advice Letter 2724-El Southern California Edison Company
(“SCE”) submits this Petition for Modification of Decision No. 12-02-035.
A. SCE’s Request in this Petition for Modification
In this Petition, SCE requests modification to Decision No. 12-02-035:
(1) SCE requests that the Commission permit SCE to reduce the utility-owned generation
(“UOG”) portion of the Solar Photovoltaic Program (“SPVP”) from 125 MW to 91 MW,2
which is based on SCE’s current UOG commitments of approximately 7 MW of Solar
Photovoltaic (“SPV”) ground-mount projects that have been energized and 84 MW of SPV
rooftop projects that have been energized, are in construction, or are expected to be built.
1 A copy o f the June 13, 2012 letter is attached as A ttachm en t A.2 A pprox im ate ly 72 M W o f the 91 M W are from SPV pro jects th a t have energized . T he balance o f 19 M W relate to SPV
pro jects th a t are e ither in construction o r are expected to be built. T he actual M W in S C E ’s U O G portion o f the SPVP m ay thus vary sligh tly w hen the 19 M W o f pro jects energize due to final design constraints.
1
Exhibit No. SCE-02 / Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
106iWorkpaper - Southern California Edison / 2015 GRC - APPLICATION
Att D R A Verbal 008 G01 Page 9
(2) SCE also proposes that the megawatts it does not procure through the UOG portion of the
SPVP be added to SCE’s megawatt requirement in the Renewable Auction Mechanism
(“RAM”) program, such that the 34 DC MW from the SPVP be reassigned to RAM (which
would be the equivalent of 31 AC MW in RAM), similar to the CPUC’s reassignment in
Decision No. 12-02-035.3
(3) As discussed in Section I.B, SCE requests that the Commission under Rule 16.4(h) issue an
immediate order staying SCE’s obligations under Decision No. 12-02-035 to develop a 125
MW UOG SPVP, pending disposition of this Petition for Modification. SCE also requests
that the Commission expedite its decision on this Petition for Modification.
The Commission in Decision No. 12-02-035 has already permitted the reduction of the UOG SPVP to
reflect SCE’s February 2011 SPVP commitments. As of July 2012, SCE’s commitments have again
changed, which has prompted the need for relief from the Commission through this Petition.
Fundamentally, SCE submits that the UOG portion of the SPVP has been successful with
approximately 84 MW of solar rooftops already energized, under construction, or expected to be built, in
addition to approximately 7 MW of ground mount SPV facilities that have been energized. When SCE
proposed the SPVP in 2008, the SPV market was much smaller in California than it is today and was not
competitive with other renewable generating sources such as wind and geothermal sources. Since 2008,
the market has transformed and SPV is now a competitive technology, with SCE having over 2000 MW
of SPV contracts executed.
Further, continuing circumstances have made it difficult and less economical to build SPV
projects through the UOG portion of the SPVP when SCE could buy renewable energy, generated from
SPV technology, at a lower cost through other programs. Since the inception of the SPVP, SCE has
been receiving competitive offers of SPV bids primarily through the Renewable Standard Contract
(“RSC”) program and the RAM, which are preferable alternatives to the UOG portion of the SPVP. As
3 D ecision N o. 12-02-035, m im eo pp. 22-24. In accordance w ith foo tno te 23 o f D ecision N o. 12-02-035, SCE has used a 0.9 conversion facto r to convert the D C M W from the U O G portion o f the SPV P to A C M W in the RAM .
2
Exhibit No. SCE-02 / Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION106j
Att D R A Verbal 008 G01 Page 10
A.10-11-015 A L J/M D 2/lil/gd2/jt2
extent consistent w ith the foregoing discussion, findings of fact, and conclusions
of law.
6. Southern California Edison Company shall continue the Authorized Base
Revenue Requirement Balancing Account.
7. Because the Commission and the public should be able to track the
progress of previously authorized large capital projects from one general rate
case to the next, for Generation and Transmission and Distribution Business Unit
capital expenditures in excess of $1 million, Southern California Edison
Company shall submit with its direct testimony in its next general rate case,
tables which provide historical and forecast California Public Utilities
Commission jurisdictional amounts by sub-categories, as follows:
(1) The table for each business unit shall provide five years (2008-2012) of recorded costs, 2012 authorized capital spending, and Southern California Edison Company's 2013, 2014, and 2015 capital requests by organization within these business units.
(2) For the Generation table, the data shall be presented by generation source categories; for the Transmission and Distribution table, the data should be presented by organization (e.g.,Infrastructure Replacement, Capital Maintenance, etc.).
8. W ith Southern California Edison Company's (SCE) next general rate case
application, SCE shall provide an explanation of the workload analysis used to
develop estimated labor increases.
9. W ith Southern California Edison Company's (SCE) next general rate case
application, SCE shall provide a summary of San Onofre Nuclear Generating
Station-Safety Culture programs, achievements, and three years of recorded
expenses.
10. Southern California Edison Company (SCE) shall establish a San Onofre
Nuclear Generating Station M emorandum Account (SONGSMA), effective
- 881 -
Exhibit No. SCE-02 / Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
107Workpaper - Southern California Edison / 2015 GRC - APPLICATION
Exhibit SCE-02, Volume 10 WORKPAPERS
Solar Photovoltaic Program
D .12-02-035
Witness: Rudy Perez
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION108
THIS PAGE INTENTIONALLY LEFT BLANK
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
109Workpaper - Southern California Edison / 2015 GRC - APPLICATION
ALJ/ MEB/ avs Date of Issuance 2/23/2012
Decision 12-02-035 February 16, 2012
BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA
Application of Southern California EdisonCompany (U338E) for Authority to Implement Application 08-03-015and Recover in Rates the Cost of its Proposed (Filed March 27,2008)Solar Photovoltaic (PV) Program.
DECISION PARTIALLY GRANTING SOUTHERN CALIFORNIA EDISON COMPANY’S PETITION FOR MODIFICATION OF
DECISION 09-06-049 (SPVP) AND MAKING CONFORMING CHANGES TO DECISION 10-12-048 (RAM)
575888 - 1 -
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION110
A.08-03-015 ALJ/MEB/avs
4. Conclusion
We approve the petition to the extent provided herein, and deny it in
every other respect. Specifically, we modify D.09-06-049 and D.10-12-048 to
accomplish the following:
1. Reduce the 250 MW UOG portion to no more than125 MW, with the maximum amount of ground-mounted facilities increased from 10% to 20% (25 MW), but other parameters unchanged; require SCE to file an advice letter for authorization if UOG procurement will be less than 115 MW by the end of year five.
2. Reduce the 250 MW IPP portion to no more than 125 MW, w ith the maximum amount of ground-mounted facilities increased from 10% to 20% (25 MW), but other parameters unchanged; require SCE to file an advice letter for authorization if IPP procurement will be less than 115 MW by the end of year five.
3. Procure the remaining amount of SPVP through 225 MW of RAM, w ith an increase in SCE's total RAM allocation from 498.4 MW to 723.4 MW. (SCE has applied 144 MW procured via its 2010 RSC program to RAM, leaving a net initial RAM procurement of 354.4 MW, or net adjusted579.4 MW when increased by the 225 MW transferred here.) All other RAM parameters and protocols are unchanged (e.g., projects up to 20 MW; any eligible renewable technology; commercial operation within18 months from Commission approval of the PPA, subject to a one-time six m onth extension).
4. Reduce the reasonable cost estimates for 125 MW of UOG over the 2008 to 2014 program period to approximately $20,655 million (2008 dollars) in O&M expenses, and $481.25 million (2008 dollars) in direct capital expenditures ($427.5 million (2008 dollars) direct capital plus a10% contingency). These costs are based on $3.50 per W att ($3.85 per W att including contingency), w ith costs in excess of $3.85 per W att subject to a reasonableness review.If SCE develops less that 125 MW of UOG, the reasonable
- 2 7 -
ExhibitNo. SCE-02/ Generation/ Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
111Workpaper - Southern California Edison / 2015 GRC - APPLICATION
A.08-03-015 ALJ/MEB/avs
total cost estimates are based on the number of Watts times $3.50 per Watt ($3.85 per Watt including contingency), w ith costs in excess of $3.85 per W att subject to a reasonableness review.
Because this decision only changes the SPVP and RAM programs going
forward, we do not need to change the language in D.09-06-049 or D.10-12-048.
Rather, to implement the changes adopted today, we only need to modify each
program effective today. We do that by adopting appendices attached to this
order that summarize each program, as modified.
Finally, we also direct SCE to file and serve a Tier 2 advice letter to specify
the amount of each product it will solicit in each remaining RAM auction for the
225 MW of capacity added to RAM via today's order, along w ith identifying the
resulting amount of each product in its new RAM total of 723.4 MW.
5. Comments on Proposed Decision
The proposed decision of the Administrative Law Judge (ALJ) in this
matter was mailed to the parties in accordance with Section 311 of the Public
Utilities Code and comments were allowed under Rule 14.3 of the Commission's
Rules of Practice and Procedure. Comments were filed on January 31,2012 by
eight parties (SCE, DRA, IEP, SEIA, Silverado Power, Clean Coalition, Basic
Crafts Alliance, and Southern California District Council of Laborers). Reply
comments were filed on February 6, 2012 by two parties (SCE, and the Coalition
of California Utility Employees). As required by our rules, comments must focus
on factual, legal, or technical errors and, in citing such errors, m ust make specific
references to the record. Comments which fail to do so, or which merely reargue
positions taken in the proceeding, are given no weight (Rule 14.3.) We similarly
give no weight to new facts first asserted in comments. Specific contract clauses
- 2 8 -
ExhibitNo. SCE-02/ Generation/ Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION112
A.08-03-015 ALJ/MEB/avs
and labor issues are not within the scope of the petition for modification, and we
decline to address them here.27
We make limited changes based on comments. For example, we clarify
that the contract we expect parties to use for the additional 225 MW solicited via
RAM is the RAM contract in effect at the time of contracting (not the contract
used for the first RAM solicitation "frozen" over time even if changes to the
RAM contract are later m ade by the Commission). We clarify that the 20%
limitation on ground-mounted facilities in the remaining UOG and IPP portions
of SPVP is up to a total of 50 MW (25 MW each in the UOG and IPP portions).
We adjust the capacity transferred to RAM from the 250 MW cited in the
proposed decision to 225 MW here to reflect the conversion from DC to AC
output. We also more clearly state the MW for the remaining three RAM
auctions (see Attachment 2).
6. Assignment of Proceeding
Mark J. Ferron is the assigned Commissioner and Maryam Ebke is the
assigned ALJ in this proceeding.
Findings of Fact
1. Since SPVP was approved in 2009, solar PV costs have fallen, the economic
dow nturn has slowed development opportunities, and other programs have
been created or modified that provide support for the one to two MW market
segment, including rooftop solar PV facilities.
2. Modifications to SPVP are necessary to offer the best opportunity to secure
savings for ratepayers resulting from falling PV costs, and may be designed to
complement changes in other conditions and programs.
27 Specific SPVP contract issues are addressed in draft Resolution E-4453.
- 2 9 -
ExhibitNo. SCE-02/ Generation/ Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
113Workpaper - Southern California Edison / 2015 GRC - APPLICATION
A.08-03-015 ALJ/MEB/avs
3. SPVP, as modified, neither cancels SPVP nor completely disrupts the
market.
4. SPVP, as modified, still targets 200 MW for rooftop solar PV in the one to
two MW size range.
5. The economic dow nturn has reduced the economic availability of rooftops.
6. SPVP, as modified, increases competitive pressure on rooftop owners and
rooftop PV plants to reduce costs to compete with ground-mounted PV and
other renewable facilities.
7. Reducing the UOG and IPP portions of SPVP (from 250 MW each to no
more than 125 MW each, but at least 115 MW each absent additional
authorization) provides the best opportunity to capture savings while continuing
to secure several advantages of SPVP, including the maintenance of large enough
UOG and IPP pieces to permit reasonable data collection.
8. The current trend of industry price reductions, and SCE's recent successes
in bringing down costs, support a directly proportional reduction in the costs
previously found reasonable by the Commission for the UOG portion of SPVP.
9. The Commission, upon its adoption of SPVP, considered and dismissed a
range of ratemaking proposals to address limiting costs, sharing costs, or setting
performance requirements, and nothing new on these matters is presented here.
10. Increasing the percentage from 10% (in the original SPVP) to 20% (in the
UOG and IPP portions of SPVP as modified) maintains the same allowance for
up to 50 MW ground-mounted facilities, thereby permitting SCE to
accommodate existing obligations.
11. Retaining SPVP, as modified, at 500 MW promotes a reasonable degree of
continuity and consistency w ith market expectations created by the original
SPVP.
- 3 0 -
ExhibitNo. SCE-02/ Generation/ Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION114
A.08-03-015 ALJ/MEB/avs
2. Utility-Owned Generation
SCE is authorized to own, develop, install, maintain and operate up to 125 MW (but no less than 115 MW absent additional authorization) of solar PV projects in the one to two MW range, located in SCE's service area, primarily on rooftops, over a five year program (about 25 MW annually, although SCE is encouraged to accelerate the development if practical and not adverse to program costs).Project costs are subject to cost of service ratemaking treatment, and are capped at $3.50 per Watt w ith a 10% contingency. Costs in excess of $3.85 per Watt are subject to reasonableness review. No more than 20% (25 MW) may be ground- m ounted facilities, and the bulk of SPVP projects m ust be in range of one to two MW. SCE shall develop 125 MW, or as close to 125 MW as reasonable. SCE shall explain in periodic SPVP reports why it is not on target to achieve 125 MW of UOG if that is the case, and explain w hat steps it is taking to achieve 125 MW. SCE shall, no later than 180 days before the end of the five year SPVP program, file a Tier 2 advice letter for authorization if UOG procurement will be less than 115 MW by the end of year five.
3. Independent Power Producer
SCE is authorized to procure via competitive solicitation up to 125 MW (but no less than 115 MW absent additional authorization) of solar PV generation owned by independent power producers. The solicitations shall be at least once per year. The generation shall primarily be from rooftop solar PV projects in the one to two MW range, located in SCE's service area, over a five year program (about 25 MW annually, although SCE is encouraged to accelerate the procurement if practical and not adverse to program costs). Bids are capped at SCE's estimated levelized cost of electricity ($0.26 per kilowatthour). No more than 20% (25 MW) may be ground-mounted facilities, and the bulk of SPVP projects m ust be in range of one to two MW. SCE shall procure 125 MW, or as close to 125 MW as reasonable. SCE shall explain in periodic SPVP reports w hy it is not on target to achieve 125 MW of IPP if that is the case, and explain w hat steps it is taking to achieve 125 MW. SCE shall, no later than 180 days before the end of the five year SPVP program, file a Tier 2 advice letter for authorization if IPP procurement will be less than 115 MW by the end of year five.
- 2 -
ExhibitNo. SCE-02/ Generation/ Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
115Workpaper - Southern California Edison / 2015 GRC - APPLICATION
Exhibit SCE-02, Volume 10 WORKPAPERS
Solar Photovoltaic Program
D.13-05-033
Witness: Rudy Perez
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION116
THIS PAGE INTENTIONALLY LEFT BLANK
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
117Workpaper - Southern California Edison / 2015 GRC - APPLICATION
COM/ MF1 / acr/ jt2 Date of Issuance 6/3/2013
Decision 13-05-033 May 23, 2013
BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA
Application of Southern California Edison Company (U338E) for Authority toImplement and Recover in Rates the Cost Application 08-03-015of its Proposed Solar Photovoltaic (PV) (Filed March 27, 2008)Program.
DECISION PARTIALLY GRANTING SOUTHERN CALIFORNIA EDISON COMPANY’S PETITION FOR MODIFICATION OF DECISION 12-02-035
(SOLAR PHOTOVOLTAIC PROGRAM)
1. Summary
This decision partially grants Southern California Edison Company's
(SCE) petition for modification of Decision (D.) 12-02-035 regarding the Solar
Photovoltaic Program (SPVP).
The SPVP, adopted in 2009 (D.09-06-049), is a 500 megawatt (MW) solar
photovoltaic generation program, w ith 250 MW utility-owned generation (UOG)
and 250 MW owned by independent power producers (IPP). As modified by
D.12-02-035, the total program remains at 500 MW, but w ith no more than
125 MW designated for utility ownership, no more than 125 MW designated for
IPP ownership, and 250 MW transferred to the Renewable Auction Mechanism
(RAM) program.
SCE now petitions to reduce the utility ownership portion from 125 MW to
91 MW, with the 34 MW differential transferred to the RAM program. We grant
the petition as to the reduction of the UOG portion of the SPVP and the
reallocation of the 34 MW to RAM. As modified, the UOG portion of the
66060035 - 1 -
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION118
A.08-03-015 C O M /M F l/acr/jt2
6. Conclusion
We approve the petition to the extent provided herein, and deny it in
every other respect. Specifically, we modify D.09-06-049, D.10-12-048 and
D.12-02-035 to accomplish the following:
1. Reduce the 125 MW UOG portion to no more than 91 MW, with the other parameters unchanged; require SCE to file a Tier 2 advice letter for authorization if UOG procurement will be less than 91 MW by the end of year five.
2. Procure the remaining amount of UOG SPVP through the 34 DC MW (31 MW AC) of RAM procurement, with an increase in SCE's total RAM allocation from 723.4 MW to754.4 MW. All other RAM parameters and protocols are unchanged.
3. Reduce the reasonable cost estimates for 91 MW of UOG over the 2008 to 2014 program period to approximately $15,036 million (2008 dollars) in O&M expenses, and $350.35 million (2008 dollars) in direct capital expenditures ($318.5 million (2008 dollars) direct capital plus a 10% contingency). These costs are based on $3.50 per watt ($3.85 per w att including contingency), with costs in excess of $3.85 per w att subject to a reasonableness review. If SCE develops less that 91 MW of UOG, the reasonable total cost estimates are based on the number of watts times $3.50 per w att ($3.85 per w att including contingency), w ith costs in excess of $3.85 per w att subject to a reasonableness review.
Because this decision only changes the SPVP and RAM programs going
forward, we do not need to change the language in D.09-06-049, D.10-12-048 and
D.12-02-035. Rather, to implement the changes adopted today, we only need to
modify each program effective today. We do that by adopting appendices
attached to this order that summarize each program, as modified.
- 1 6 -
ExhibitNo. SCE-02/ Generation/ Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
119Workpaper - Southern California Edison / 2015 GRC - APPLICATION
A.08-03-015 C O M /M F l/acr/jt2
7. Comments on Alternate Proposed Decision
On April 23, 2013, the alternate proposed decision of Commissioner Florio
in this matter was mailed to the parties in accordance w ith Section 311 of the
Public Utilities Code and comments were allowed under Rule 14.3 of the
Commission's Rules of Practice and Procedure. On May 13, 2013, opening
comments on the alternate proposed decision were filed by DRA, SCE,
Independent Energy Producers and SEIA. Clean Coalition filed reply comments
on May 17, 2013. The length of Clean Coalition's reply comments were not in
compliance w ith Commission's Rules and therefore only a portion was
considered. On May 20, 2013, reply comments were filed. As required by our
rules, comments must focus on factual, legal, or technical errors and, in citing
such errors, must make specific references to the record. Comments which fail to
do so, or which merely reargue positions taken in the proceeding, are given no
weight (Rule 14.3.) We have reviewed the comments and determined that there
is a need to make one change to the alternate proposed decision. Clean Coalition
indicated that the RAM program no longer allows projects under 3 MW. The
alternate proposed decision has been changed to reflect this.
8. Assignment of ProceedingMark J. Ferron is the assigned Commissioner and Maryam Ebke is the
assigned Administrative Law Judge in this proceeding.
Findings of Fact1. Since the SPVP was approved in 2009, Solar PV costs have fallen and other
programs have been created or modified that provide support for the one to
two MW market segment, including rooftop Solar PV facilities.
- 1 7 -
ExhibitNo. SCE-02/ Generation/ Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION120
A.08-03-015 C O M /M F l/acr/jt2
2. Modifications to SPVP are necessary to offer the best opportunity to secure
savings for ratepayers resulting from falling PV costs, and may be designed to
complement changes in other conditions and programs.
3. SPVP, as modified, neither cancels the SPVP nor completely disrupts the
market.
4. SPVP, as modified, still targets a minimum of 173 MW for rooftop Solar PV
in the one to two MW size range.
5. SPVP, as modified, increases competitive pressure on rooftop owners and
rooftop PV developers to reduce costs to compete w ith ground-m ounted PV and
other renewable facilities.
6. The current trend of industry price reductions, and SCE's recent successes
in bringing down costs, supports a directly proportional reduction in the costs
previously found reasonable by the Commission for the UOG portion of SPVP.
7. Consolidating 34 MW DC (equal to 31 MW AC) of SPVP w ith RAM will
reduce developer confusion and enhance administrative efficiency.
8. Using RAM protocols promotes simplicity, efficiency and continuity.
9. Nothing presented here justifies reconsidering recently adopted
solicitation parameters, or consideration of other solicitation parameters in a new
advice letter.
Conclusions of Law
1. Petitioner reasonably justifies why the petition was not filed within
12 months of the effective date of the decision proposed to be modified.
2. The Commission should reasonably, responsibly, and appropriately
respond to market and industry changes, including changes that permit SPVP
modifications to enhance downward pressure on costs and prices for all
renewable projects across a range of sizes and technologies, and should take
- 1 8 -
ExhibitNo. SCE-02/ Generation/ Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
121Workpaper - Southern California Edison / 2015 GRC - APPLICATION
Exhibit SCE-02, Volume 10 WORKPAPERS
Solar Photovoltaic Program
Recorded Cost Reasonableness
Witness: Rudy Perez
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION122
THIS PAGE INTENTIONALLY LEFT BLANK
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
123Workpaper - Southern California Edison / 2015 GRC - APPLICATION
SPVP Recorded Cost Reasonableness 2008-2012 Capital $
2008 - 2012 SPVP Capital Cost:
2008 2009 2010 2011 2012 Total
Nom inal $ $11,162,901 $9,315,688 $121,525,252 $161,523,768 $32,196,409 $335,724,018M W Com pleted 2.45 1.26 27.04 41.19 12.77 84.71Nom inal $ Per
W att $3.96
2008 2009 2010 2011 2012 Total
Cap is $3.85
2 008$ $11,162,901 $9,233,445 $118,857,219 $154,679,215 $30,299,695 $324,232,475MW Com pleted 2.45 1.26 27.04 41.19 12.77 84.712008 $ Per W att $4.56 $7.33 $4.39 $3.76 $2.37 $3.83
Year 0 Year 1 Year 2 Year 3$20,396,346
3.715.50
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION124
S P V P Recorded Cost Reasonableness
2008 -2012 O & M $
YearO &M recorded ($) - Exclude
LeaseOperating Lease Recorded ($) Non-Operating Lease TOTAL O&M
2008 $450,712 $0 $450,7122009 $1,452,857 $126,311 $1,579,1682010 $1,822,317 $122,472 $1,944,7892011 $14,385,463 $681,745 $55,161 $15,122,3692012 $4,712,263 $1,877,386 $250,000 $6,839,649Grand Total $22,823,611 $2,807,915 $305,161 $25,936,687
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
125Workpaper - Southern California Edison / 2015 GRC - APPLICATION
SPVP Recorded Cost Reasonableness Escalation
Used in order to change nom inal dollars to 2008 dollars.
Note: JPGDP Escalation Factor
2008 2009 2010 2011 2012 2013 2014 2015
1.000 1.009 1 .022 1.044 1.063 1.077 1 .096 1.113
2008 1.00000 1.00891 1.02245 1.04425 1.06260 1.07680 1.09603
2009 0 .99117 1.00000 1.01342 1.03503 1.05322 1.06730 1.08635
2010 0 .97805 0 .98676 1.00000 1.02132 1.03927 1.05316 1.07196
2011 0 .95763 0 .96615 0.97912 1.00000 1.01757 1.03117 1.04958
2012 0 .94109 0.94947 0.96221 0 .98273 1.00000 1.01337 1.03146
2013 0 .92868 0 .93695 0.94952 0.96977 0.98681 1.00000 1.01785
2014 0 .91239 0.92051 0.93287 0 .95276 0 .96950 0 .98246 1.00000
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION126
ijj d
E=
C-a>
GJ
CO+-» ?*>O
O ~
i ■ a .
1cc
u
0Oh
>
at
in ^ ^ LTi <»g p-T m rN 2S id O’! rfi« « S ̂ n
■ 8 .
in in r i in o y? oo o
- - — yy
cri . qjI in sCsl
i in o>1 ID 00J '=tID oo ■sf
<Nrnrn K_ '=t
SlW ) ^
a s s 1 1■ - s ' a ? s gf£ O* W IN i5 g} £0
w v>a S
cr oo « ^ ^" in 00 00 CO».' r«l O ^S N co m o HTO 00 °0 P. Pin in i 2 2 ^^ -D> v> v> v> -IA
Ln 0*1 fN H ID Mon O'1^ in w co ' t •<!■ on rn <ro fN i_n CTi cT 5t oo
2 00*"!vo ino gs sv> O rn m si- ' ro </> co -C/> v> ~
0m fN — 100 s ■nt’ A ? 5
CP 3 in r-(fN iHr l IDs ^
fN3. s
«» 00cj TO^ -in
-int—Im
-in ^ m
, oo in . m <nw -in
fN̂t; a p mm 0000IDL-, p-*m inm 3rn CD 00 00Jh r~IN
m'i; CD■m- <n <n -m
O ID OCT> A ID
3 4 ffi.<n vv i-*
•• in ^ •<* m i \ £^ ^ K c* m rn o -m m cn m
rC ^in
fM fN
in
i w w > i - ■ ■ . w > ■ U1 in oij i n inu i o i ^Lni nmO^ ■ cdnikcn^fO(Y)r1co2 i ^ ^ i - L n rs lr,« r '< - i rH,'_ ,W ;■ to in_ a\ P. ^ o ' t id p coi m in o ^ in rs h rn m^ N f n « ) ( M H i n \ o m >r m m m Is; j in in n r~| to- - - - - - - ‘ • m h-m
ID VO 00 r-T m' vd
-in
§ " sS o ' in
s00Or**a
s go - w £
« a,-i *N rn O p
• m o rn <n rv id• nj cm*
12 m in cn rn°1 P* UD UD VOin pJ <n cn5 CT H yj ■tf> rn CD on
O <-vi oo o cnrn p h p in o~- o on o ^ g g j' P“» on o t}n m p̂ vj- in
to m m pP P in °°.■=;!• TO m ij-in h cji ium id
a s a 3 5* *5 5?
rn -in id -m -m m “
5c ’ - - oo. M IN 'tH inH an inT-*p^?J; m - in - in r ' i- in ^ fn . '" m m -t> m vn
s§
§ £ in inr-irsim^tLniDr^ooo^o o o o o o o o oo o o o o o o o o
CHlMmDiniONCOOl H H H H H H H H H Ho o o o o o o o o o o o o o o o o o o o o o o
i n fNm <3- •=: 0 0 cij- in r* 00
in i/-.
00
m
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
127Workpaper - Southern California Edison / 2015 GRC - APPLICATION
S P V P Recorded Cost Reasonableness
M W by Site and by Year
M W Comoletion Bv Site
SPVP Number Site Status 2008 2009 2010 2011 2012 Total001 SG 1 Complete 2.45 2.45002 SG 7 Peaker and Solar Division 1.26 1.26003 SG 7 Peaker and Solar Division 1.2621 1.2621005 SG 7 Peaker and Solar Division 3.3962 3.3962006 SG 7 Peaker and Solar Division 2.5502 2.5502007 SG 7 Peaker and Solar Division 3.1978 3.1978008 SG 7 Peaker and Solar Division 2.8465 2.8465009 SG 7 Peaker and Solar Division 1.4104 1.4104010 SG 1 Complete 2.2508 2.2508O il SG 7 Peaker and Solar Division 5.0176 5.0176012 SG 7 Peaker and Solar Division 0.7728 0.7728013 SG 7 Peaker and Solar Division 4.928 4.928015 SG 1 Complete 2.25 2.25016 SG 7 Peaker and Solar Division 1.7488 1.7488017 SG 1 Complete 4.4979 4.4979018 SG 1 Complete 1.9417 1.9417022 SG 7 Peaker and Solar Division 3.0912 3.0912023 SG 1 Complete 3.864 3.864026 SG 7 Peaker and Solar Division 8.6016 8.6016027 SG 4 Complete 2.62 2.62028 SG 1 Complete 4.8563 4.8563032 SG 1 Complete 1.7066 1.7066033 SG 1 Complete 1.2719 1.2719042 SG 1 Complete 6.7684 6.7684044 SG 1 Complete 10.15 10.15048 SG 2 In-Construction 6.77
TOTAL 2.45 1.26 27.04 41.19 12.77 91.48
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION128
THIS PAGE INTENTIONALLY LEFT BLANK
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
129Workpaper - Southern California Edison / 2015 GRC - APPLICATION
E xhib it SCE-02, Volume 10 WORKPAPERS
Fuel Cell Program
O & M FERC Account 549
Witness: Jonathan Rumble
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION130
Beginning of Workpapers for:
FERC Account: 549 Miscellaneous Other Power Generation Expenses
A ctiv ity: 549 -FUEL CELL
Witness: Jonathan L. Rumble
Forecast Method
Chosen
2012$ (000)
Recorded
2012
Forecast
2015
Labor Itemized Forecast 5 113
Non-Labor Itemized Forecast 1 556
O ther N/A 0 0
Total 6 669
Description of Activity:
The Fuel Cell Program w as approved in D .10-04-028 to install utility owned fuel cells on the University of California and
California State University campuses.
Final Cost Centers included in this activity (S ee Appendix A for additional detail):
F528939
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
131Workpaper - Southern California Edison / 2015 GRC - APPLICATION
FERC Account: 549 Miscellaneous Other Power Generation Expenses
A ctiv ity : 549 - FUEL CELL
Witness: Jonathan L. Rumble
DETER M INA TIO N O F R E C O R D ED /A D JU STED
I Recorded Period$ (000)
2008 2009 2010 2011 2012
FERC Form 1 Recorded (Nom inal $)Labor 0 0 0 0 0
Non-Labor 0 0 0 0 0
O ther 0 0 0 0 0
Total 0 0 0 0 0
A d justm ents- (N om inal $) - see Appendix B fo r additional detail
Labor 0 0 0 0 5
Non-Labor 0 0 0 0 1
O ther 0 0 0 0 0
Total 0 0 0 0 6
R ecorded/A djusted (Nom inal $)
Labor 0 0 0 0 5
Non-Labor 0 0 0 0 1
O ther 0 0 0 0 0
Total 0 0 0 0 6
E sca la tio n :
Labor 1.1414 1.1070 1.0701 1.0327 1.0000
Non-Labor 1.0881 1.0814 1.0642 1.0254 1.0000
O ther 1.0000 1.0000 1.0000 1.0000 1.0000
Recorded/A d justed (C onstan t 2012S)
Labor 0 0 0 0 5
Non-Labor 0 0 0 0 1
Other 0___________ 0___________ 0___________ 0__________ ^Total 0 0 0 0 6
Recorded A d justed 2008-2012 (2012$)
6 -----------------------------------------------------------------------5 -------------------------------------------------------------------------------------------------
4 -------------------------------------------------------------------------------------------------
3 -------------------------------------------------------------------------------------------------
2 -----------------------------------------------------------------------
1 ------------------------------------------------------------
0 , , ---------2008 2009 2010 2011 2012
□ Labor (std escl) ■ Non-Labor (std escl) □ Other (not escl)
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION132
FERC Account: 549 Miscellaneous Other Power Generation Expenses
Activity: 549 - FUEL CELL
Witness: Jonathan L. Rumble
Forecasting Methods - Summary of Results of all Methods Studied - 2012$ (000)
2 Recorded Years (2011 - 2012):Results of Averaging (A2)
COoCM 2014 | 2015 | sd** | ChosenLabor 3 3 3 3 noNon-Labor 1 1 1 1 noOther 0 0 0 0 noTotal 4 4 4 n/a n/a
3 Recorded Years (2010 -2012):Results of Linear Trending (T3) Results of Averaging (A3)
LaborNon-LaborOtherTotal
2013 2014 2015 r2 * Chosen1220
0.75 no0.75 no0.00 no
14 n/a n/a
2013 2014 2015 sd* Chosenno
n/a n/a
4 Recorded Years (2009 - 2012):Results of Linear Trending (T4) Results of Averaging (A4)
LaborNon-LaborOtherTotal
COoCM 2014 | 2015 | r2* I Chosen 2013 | 2014 | 2015 | sd** | Chosen5 7 8 0.60 no 1 1 1 2 no1 1 2 0.60 no 0 0 0 0 no0 0 0 0.00 no 0 0 0 0 no6 8 10 n/a n/a 1 1 1 n/a n/a
5 Recorded Years (2008 - 2012):Results of Linear Trending (T5) Results of Averaging (A5)
2013 I 2014 | 2015 | r2* I Chosen
COoCM r̂oCM 2015 | sd** | ChosenLabor 4 5 6 0.50 no 1 1 1 2 noNon-Labor 1 1 1 0.50 no 0 0 0 0 noOther 0 0 0 0.00 no 0 0 0 0 noTotal 5 6 7 n/a n/a 1 1 1 n/a n/a
Other Methods:
Last Recorded Year (LRY) Itemized Forecast (IF)
COoCM 2014 | 2015 | | Chosen 2013 | 2014 | 2015 | | Chosen_abor 5 5 5 no 113 113 113 yesSion-Labor 1 1 1 no 267 518 556 yesOther 0 0 0 no 0 0 0 no
Total 6 6 6 n/a 380 631 669 n/a
Forecast Adjustments:Base Forecast Method Adjustments***
Method 2013 | 2014 | 2015 | 2013 | 2014 | 2015 | |Labor IF 113 113 113 0 0 0Non-Labor IF 267 518 556 0 0 0Other N/A 0 0 0 0 0 0
Total 380 631 669 0 0 0
* r2 = R Squared (Based on recorded years data)** sd = standard deviation (Based on recorded years data)*** See Appendix B For Additional Detail
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
133Workpaper - Southern California Edison / 2015 GRC - APPLICATION
FERC Account: 549 Miscellaneous Other Power Generation Expenses
Activ ity: 549 - FUEL CELL
Witness: Jonathan L. Rumble
Results:
Forecasting Results
Method Selected 2013 | 2014 | 2015 | |Labor Itemized Forecast 113 113 113Non-Labor Itemized Forecast 267 518 556Other N/A 0 0 0Total 380 631 669
Analysis o f Forecasting Methods
Analysis of Linear Trending Method:SCE's Fuel Cell Program has very little O&M recorded data to use as a starting point from which to develop a forecast estimate. Since the UCSB site was not operational until September 2012, the 2012 O&M recorded data does not represent an entire year and does not include any costs associated with the manufacturer's long term service agreement for this project.The fuel cell project at CSUSB is expected to be operational in 2013, therefore the 2012 O&M recorded data does not include any costs for the CSUSB site. Because of this, the most appropriate O&M forecasting methodology is an itemized forecast.
Analysis of Averaging Method:In D.04-07-022 and D.89-12-057, the CPUC stated that for those accounts have significant fluctuations in recorded expenses from year to year, and average of recorded expenses is appropriate. The Fuel Cell Program has no recorded O&M expenses until 2012, so an average is not an appropriate forecasting method.
Analysis of Last Recorded Year (2012):In D.04-07-022 and D.89-12-057, the CPUC stated that if recorded expenses in account have been relatively stable forthree or more years, the last recorded year is an appropriate base estimate. The Fuel Cell Program had no recorded O&M expenses until 2012 and 2012 did not include a full year of costs. Therefore, the last recorded year is not an applicable forecasting method.
Analysis of Itemized Forecast Method:SCE used the itemized forecast method for Fuel Cell Program labor and non-labor because SCE's Fuel Cell Program has very little O&M recorded data to use as a starting point from which to develop a forecast estimate. SCE has signed Long Term Service Agreements (LTSA) with the manufacturers of each of the fuel cell units, as well as with some other providers of services necessary to operate the fuel cells. The Fuel Cell Program has no recorded O&M expenses until 2012. Therefore, an itemized forecast is the most appropriate for labor and non-labor for FERC 549, the Fuel Cell Program.
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION134
FERC Account: 549 Miscellaneous Other Power Generation Expenses
Activ ity: 549 - FUEL CELL
Witness: Jonathan L. Rumble
1 R e c o rd e d P e rio d
$ (0 0 0 )
Forecast Expenses (constant 2012$) 2 0 0 8 | 2 0 0 9 | 2 0 1 0 | 201 1 | 2 0 1 2 2 0 1 3 | 2 0 1 4 | 2 0 1 5
Labor (s tan dard esca la tion ) 0 0 0 0 5 113 113 113
N o n-L abo r (s tandard esca la tion ) 0 0 0 0 1 267 518 556
O ther (no t e sca la tab le ) 0 0 0 0 0 0 0 0
Total 0 0 0 0 6 380 631 669
Labor Prior year Total 5 113 113
Change 108 0 0
Total 5 113 113 113
Non-Labor Prior year Total 1 267 518
Change 266 251 38
Total 1 267 518 556
O ther Prior year Total 0 0 0
Change
Total
0 0 0
0 0 0 0
Total C hange |
Labor 108 0 0
Non-Labor 266 251 38
O ther 0 0 0
Total N/A 374 251 38
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
135Workpaper - Southern California Edison / 2015 GRC - APPLICATION
FERC Account: 549 Miscellaneous Other Power Generation Expenses
Activ ity: 549 -FUELC ELL
Witness: Jonathan L. Rumble
This page shows the changes in Labor, Non-Labor, and O ther expenditures forecast during 2013 through 2015, including reasons fo r the addition o f personnel (labor), increased office supp lies required due to an increase in activity (non-labor).
2012 -2 0 1 3
Labor: 108
2013 w ill be the firs t year in which the UC Santa Barbara u n itw ill operate fo r a fu ll year, and the CSU San Bernardino unit w ill operate fo r approxim ately ha lf o f 2013, which results in increased labor costs.
Non-Labor: 266
Expenditures increases, as various O&M service contracts will go into service w ith the com m issioning of the second unit in 2013.
Other: 0
Not applicable.
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION136
FERC Account: 549 Miscellaneous Other Power Generation Expenses
Activ ity: 549 - FUEL CELL
Witness: Jonathan L. Rumble
This page shows the changes in Labor, Non-Labor, and Other expenditures forecast during 2013 through 2015, including reasons for the addition o f personnel (labor), increased office supplies required due to an increase in activity (non-labor).
2013 -2014
Labor: 0
Not applicable.
Non-Labor: 251
The increase reflects LTSA O&M for the first full year of operation for both fuel cell units.
Other: 0
Not applicable.
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
137Workpaper - Southern California Edison / 2015 GRC - APPLICATION
FERC Account: 549 Miscellaneous Other Power Generation Expenses
Activ ity: 549 - FUEL CELL
Witness: Jonathan L. Rumble
This page shows the changes in Labor, Non-Labor, and Other expenditures forecast during 2013 through 2015, including reasons for the addition o f personnel (labor), increased office supplies required due to an increase in activity (non-labor).
2014-2015
Labor: 0
Not applicable.
Non-Labor: 38
The change in non-labor represents the average of the 2015, 2016, 2017 prices for one LTSA. Three years were averaged for test year 2015 in order to reflect anticipated LTSA expenditures for the remaining years of the rate case cycle.
Other: 0
Not applicable.
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION138
THIS PAGE INTENTIONALLY LEFT BLANK
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
139Workpaper - Southern California Edison / 2015 GRC - APPLICATION
FERC Account
A ctiv ity:
Witness:
549 Miscellaneous Other Power Generation Expenses
549 - FUEL CELL
Jonathan L. Rumble
APPENDIX A
Detail Description of Final Cost Centers Included in This Activity
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION140
FERC Account: 549 Miscellaneous Other Power Generation Expenses
A c tiv ity : 549 - FUEL CELL
Witness: Jonathan L. Rumble
Description of Final Cost Centers included in this activity:
F528939 FUEL CELLSThis account includes the cost of labor, materials used and expenses incurred in the operation of Fuel Cells which are not specifically provided for or are not readily assignable to other generation expense accounts. This includes general management and administration, safety, noise and water compliance, labor relations costs, community information technology costs, reliability and efficiency expenses, training and grounds management.
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
141Workpaper - Southern California Edison / 2015 GRC - APPLICATION
FERC Account: 549 Miscellaneous Other Power Generation Expenses
Activ ity: 549 - FUEL CELL
Witness: Jonathan L. Rumble
Recorded/Adjusted (Constant 2012$) By Final Cost Center$ (000)
2008 2009 2010 2011 2012
F528939 FUEL CELLS 0 0 0 0 6
Total 0 0 0 0 6
** Due to rounding, totals may not tie to other workpaper pages.
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION142
THIS PAGE INTENTIONALLY LEFT BLANK
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
143Workpaper - Southern California Edison / 2015 GRC - APPLICATION
FERC Account:
Activ ity:
Witness:
549 Miscellaneous Other Power Generation Expenses
549 - FUEL CELL
Jonathan L. Rumble
APPENDIX B
Detail of Total Company Adjustments to Recorded
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION144
FERC Account: 549 Miscellaneous Other Power Generation Expenses
A ctiv ity : 549 - FUEL CELL
Witness: Jonathan L. Rumble
Detail o f Total Company Adjustm ents to Recorded Expenses
|Adjs - (Nominal $) $ (000)2008 2009 2010 2011 2012 2013 2014 2015
Labor 0 0 0 0 5 0 0 0Non-Labor 0 0 0 0 1 0 0 0Other 0 0 0 0 0 0 0 0
Total 0 0 0 0 6 0 0 0
Organizational Unit Adjustment 1 GRC-MJP.CPT-OUX-FUEL CELLS
To transfer expenses related to fuel cells from Other A&G to 549 - Fuel Cell.
Labor 0 0 0 0 5 0 0 0Non-Labor 0 0 0 0 1 0 0 0Other 0 0 0 0 0 0 0 0
Total 0 0 0 0 6 0 0 0
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
145Workpaper - Southern California Edison / 2015 GRC - APPLICATION
End of Workpapers for:
FERC Account: 549 Miscellaneous Other Power Generation Expenses
A ctiv ity: 549 - FUEL CELL
Witness: Jonathan L. Rumble
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION146
THIS PAGE INTENTIONALLY LEFT BLANK
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
147Workpaper - Southern California Edison / 2015 GRC - APPLICATION
Fuel Cell Program
Capital Expenditures
Witness: Jonathan Rumble
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION148
Southern California Edison Company
CAPITAL WORKPAPERS - 2015 GRC
OPERATING UNIT SUMMARY (Nominal $000)
Operating Unit Summary: GEN - Fuel Cells
(1) OPERATING UNIT FORECAST CAPITAL EXPENDITURES: 2015 GRC
Item Testimony DescriptionForecast Capital Expenditures
2013 2014 2015 2016 2017 Total
1 711 C C 0 0 711
Total 711 C C 0 0 711
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
149Workpaper - Southern California Edison / 2015 GRC - APPLICATION
Southern California Edison Company
CAPITAL W O R K P A P E R S - 2015 G RC
OPERATING UNIT SUMMARY
(Nominal $000)
Operating Unit Sum m ary: GEN - Fuel Cells
(2) OPERATING UNIT RECORDED AND AUTHORIZED CAPITAL AND FORECAST EXPENDITURES: 2015 GRC
DescriptionRecorded and Authorized Capital Expenditures Forecast Capital Expenditures
2008 2009 2010 2011 2012 2013 2014 2015 2016 2017
Authorized Expenditures 0 3,977
Recorded & Forecast Expenditures 0 0 227 5,944 5,040 711 0 0 0 0
Total Expenditure 11,211 711
7.000
6.000
5.000
4.000
3.000
2.000
1.000
0
Recorded, Authorized and Forecast Expenditures Graph
. . : - .. n
2013 2014 2015 2016
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION150
Southe rn C a lifo rn ia E d ison C om pany
C A P IT A L W O R K P A P E R S - 2015 G R C
P R O JE C T D E TA IL W O R K S H E E T
Organizational Unit Summary: GEN - Fuel Cells Testimony Summary: SCE-02, Volume 10 Major Program:Category: Facilities Infrastructure Detail:Database ID: 1647 / RO Model ID: 12
1. WITNESS2. PROJECT DETAIL
P rogram G roup
P rogram
P in #
W B S E lem ent
3. PROJECT TYPE
Jona than R um ble
FU E L C E LL
G E N E R A L - O TH E R
6965
C G 0-00-G P -P S -000070
S e lec t one
C o m plian ce : S a fe ty , Environm enta l, L icenses
R e p lace m en ts in K ind
U pgrades
B lanket: FE, T oo ls , S p are P arts, Lab, C o m pu te r Equip
S e lect one
C u s to m e r G row th
Load G row th
R e liab ility
C ap ita lized S o ftw are
V a rious (See Below )
4. ASSET TYPE
5. CLOSE DATE
6. RIIM ELIGIBLE
Fuel Cell
7 /1 /2013
N /A
7. COST ESTIMATES (NOMINAL $000)
Y r SC E $
2013 711
2014 0
2015 0
2016 0
2017 0
Tota l 711
2 0 15 GRC - C a p i ta l E x p e n d i tu r e s F o r e c a s t
400
20 0
02013 2014 2015 2016 2017
7 (a). SYSTEM SHORT TEXT Pjct Dev-Fuel Cell Pro ject
7 (b). DETAILED DESCRIPTION C a p ita l fo r cons truc tion o f th e fu e l ce ll p rogram , a s au thorized by D. 10-04-028.
8. SCOPE C ons is ts o f the cap ita l required to insta ll and com m iss ion S C E ’s fue l ce lls at C a lifo rn ia StateU nivers ity San B e rna rd ino (C SU SB ) and U nivers ity o f C a lifo rn ia Santa B arbara (UC SB).
9. JUSTIFICATION S C E ’s Fue l C e ll P rog ram , app roved by th e C o m m iss ion in D .10-04-028, supp o rts E xecu tive O rde rS-20-04, G overnor S ch w arzenegg e r’s G reen Build ing A ction Plan fo r S ta te fac ilitie s , and fu rthe rs S tate leg is la tive po lic ies fo r reducing G reenhouse G as (G H G ) em iss ion under A sse m b ly B ill (AB) 32 and utiliz ing c le ane r sources of d is tribu ted genera tion techno logy under S enate B ill (SB) 1298. Because the fue l cell fac ilit ie s are being insta lled at s ta te un ivers ities, the Fuel C ell P rogram will a lso enhance the S ta te ’s overa ll in te llectua l cap ita l regarding fue l cell techno logy . A s a u tility- ow ned asset, SCE is ga in ing expe rience in operating fue l ce lls to the d irect benefit o f S C E ’s cus tom ers . The pow er output of the fue l ce lls is de livered d irectly to S C E ’s d is tribu tion system which a lso benefits S C E ’s cus tom ers . SCE com ple ted construction , and com m iss ioned the fuel cell at UC SB in 2012. SCE expects to com p le te construction and com m iss ion the fue l cell at C S U S B in 2013 . P e r D. 10-04-028, O rde ring P a rag raph No. 4.b, S C E re co rd s ac tua l cap ita l and O & M in a Fue l C e ll P rog ram M em o ran dum A cco u n t (FC P M A ). S C E w ill inc lude th e cap ita l expend itu res and assoc ia ted cap ita l revenue requ irem ent fo r the Fuel C e ll P ro ject in its A p ril 1, 2014 ER R A rev iew p roceed ing and w ill dem onstra te tha t the cap ita l expend itu res are consis tent w ith th e requ irem ents o f D. 10-04-028.
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
150aWorkpaper - Southern California Edison / 2015 GRC - APPLICATION
C O M /M P l/lil Date o f Issuance 4/14/2Q1Q
Decision 10-04-028 April 8, 2010
BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA
Application of Pacific Gas and Electric Company for Approval and Recovery of Costs Associated w ith its Fuel Cell Project.
Application of Southern California Edison Company for Authority to Implement an d Recover in Rates the Cost of its Proposed Fuel Cell Installation Program for State Universities.
Application 09-02-013 (Filed February 20, 2009)
Application 09-04-018 (Filed April 27, 2009)
DECISION AUTHORIZING FUEL CELL PROJECTS
1. Summary
This decision approves, w ith modi fications, the applications of Pacific Gas
and Electric Company (PG&E) and Southern California Edison Company (SCE)
for approval of each utility's Fuel Cell Project to install utility-owned fuel cells on
several University of California and California State University campuses. The
decision finds it reasonable for the utilities to proceed w ith their respective Fuel
Cell Projects, as long as the projects are modified in two respects. First, PG&E
and SCE shall each reduce their project capital costs to reflect a lower
contingency percentage. Second, PG&E shall remove contingency costs and
education and outreach labor costs from its estimated non-fuel operations and
maintenance costs.
420634 - 1 -
Exhibit No. SCE-02 / Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION150b
A.09-02-013, A.09-04-018 C O M /M P l/lil
utilities may seek recovery of any difference in either a petition to modify this
decision or a separate application.
16. PG&E should correct notice defects in future applications and ensure
notice is timely given and provides all information required by Rule 3.2.
O R D E R
IT IS ORDERED that:
1. The application of Pacific Gas and Electric Company for approval of its
Fuel Cell Project, is approved as modified to reduce capital costs to $20.3 million
and reduce non-fuel operations and maintenance costs from $5.79 million to
$4.71 million to remove any contingency and to exclude costs for education and
outreach labor.
2. The application of Southern California Edison Company for approval of its
Fuel Cell Installation Program is approved as modified to reduce capital costs to
$19.1 million, to clarify that stranded costs shall be recovered in accordance w ith
Decision 08-09-012, and to prohibit Southern California Edison from using
Self-Generation Incentive Program funds for the project.
3. The ratemaking for Pacific Gas and Electric Company's Fuel Cell Project is
approved as follows:
a. Pacific Gas and Electric Company may accrue the initial revenue requirement, as adjusted in this decision based on capital costs and operations an d maintenance cost reductions, in its Utility Generation Balancing Account on the commercial operation date of the Fuel Cell Project.
b. Pacific Gas and Electric Company shall file an advice letter w ithin 90 days of this decision to establish a Fuel Cell Project M emorandum Account to track the difference between
- 39 -
Exhibit No. SCE-02 / Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
150cWorkpaper - Southern California Edison / 2015 GRC - APPLICATION
A.09-02-013, A.09-04-018 C O M /M P l/lil
estimated and actual capital costs and estimated and actual operations and maintenance costs.
c. After the commercial operation date of the Fuel Cell Project, if actual capital costs are less than $20.3 million, Pacific Gas and Electric Company shall file an advice letter to update the revenue requirem ent to reflect actual capital costs.
d. After each year of operation, Pacific Gas and Electric Company shall file an advice letter to adjust the previous year's Utility Generation Balancing Account entries to reflect actual operations and maintenance expenses, as long as they are no higher than $4.71 million for the first four years of plant operation.
e. Pacific Gas and Electric Company may seek recovery of reasonably incurred amounts above the estimated capital costs and operations and maintenance costs approved in this decision through either a petiti on for modification or a separate application.
f. Pacific Gas and Electric Company may seek recovery of fuel costs for the Fuel Cell Project through the Energy Resource Recovery Account.
4. The ratemaking for Southern California Edison Company's Fuel Cell
Installation Program is approved as follo ws:
a. Southern California Edison Company shall file an advice letter w ithin 90 days of this decision to establish a Fuel Cell Program M emorandum Accou nt.
b. Southern California Edison Company shall record actual capital costs and operation and maintenance costs in the Fuel Cell Program M emorandum Account and transfer the balance monthly to the generation sub-account of Base Revenue Requirement Balancing Account, as long as the amounts are no higher than the estimates approved in this decision. If actual capital expenditures and actual annual operations and maintenance expenses are less than approved in this decision, then the recorded direct capital expenditures and operations and maintenance expenses are reasonable.
- 40 -
Exhibit No. SCE-02 / Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION150d
A.09-02-013, A.09-04-018 C O M /M P l/lil
c. If capital costs are less than or equal to $19.1 million, and total operations and maintenance costs are less than or equal to $8.9 million, review of Southern California Edison Company's Fuel Cell Program M emorandum Account shall occur in Southern California Edison Company's annual Energy Resource Recovery Account Reasonableness proceeding. If costs exceed these amounts, Southern California Edison Company may file either a petition for modification or a separate application to seek recovery of the excess.
5. Pacific Gas and Electric Company and Southern California Edison
Company may each recover stranded costs associated w ith their respective Fuel
Cell Projects through a non-bypassable charge for a 10-year period following
commercial operation of the fuel cells, consistent w ith Commission
determinations in Decision 08-09-012.
6. Pacific Gas and Electric Company and Southern California Edison
Company shall install metering and monitoring equipm ent at each project
sufficient to provide the following projec t-specific information: electrical output
(15 m inute interval basis); thermal outpu t (15 minute interval basis); fuel
consumption (15 m inute interval basis); system electrical efficiency; and overall
system efficiency.
7. Beginning April 30, 2011 and every year thereafter, Pacific Gas and Electric
Company and Southern California Edison Company shall each submit annual
compliance reports to Energy Division providing an overview the performance
of each project deployed pursuant to this decision. The information provided in
these reports should include each project's annual capacity factor, system
availability during system peak hours, annual fuel consumption, annual
electrical output, annual thermal output, overall electrical efficiency for the year,
and overall system efficiency for the year, as well as any other information that
- 41 -
Exhibit No. SCE-02 / Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
151Workpaper - Southern California Edison / 2015 GRC - APPLICATION
Fuel Cell Program
A.09-04-018 Fuel Cell Program Testimony
Witness: Jonathan Rumble
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION152
THIS PAGE INTENTIONALLY LEFT BLANK
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
153Workpaper - Southern California Edison / 2015 GRC - APPLICATION
Application No.: Exhibit No.: Witnesses:
A.09-04-SCE-01J. Rumble G. Schoonyan D.Snow D. Pasaporte
■SOUTHERN CALIFORNIA
EDISONAn EDISON INTERNATIONAL Company
(U 338-E)
I Southern California Edison Company’s Fuel Cell Testimony
Before the
Public Utilities Commission of the State of California
Rosemead, California April 27, 2009
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
1
2
3
4
5
6
7
8
9
10
11
12
13
14
Workpaper - Southern California Edison / 2015 GRC - APPLICATION154
installation activities during the school year will be mutually disruptive for both students and
construction workers.
The table below shows the expected schedule for the Fuel Cell Program.
Table 11-1Estimated Fuel Cell Program Schedule
Date Event
April 2009 SCE files its application with the CPUC
Spring/Summer 2009 SCE issues RFPs for bids for fuel cell technology and
installation
After Fuel Cell Program
Approval by the CPUC
SCE finalizes lease agreements with selected host sites
After Fuel Cell Program
Approval by the CPUC
SCE finalizes contracts for the procurement of fuel cell
technology and for the installation of the fuel cell systems
After Fuel Cell Program
Approval by the CPUC
SCE will arrange for installation of up to three MW (total) of
fuel cell generation at State Universities
3. Selection of Facilities
SCE’s Fuel Cell Program seeks to promote the benefits of fuel cells with cogeneration
and electric-only fuel cell technology in California. Before refining its search for state-owned facilities
to utilize these specific technologies, however, SCE conducted an initial review of numerous
state-owned facilities, including universities, executive branch office buildings, developmental and
university hospitals, prisons, veterans homes, and state National Guard facilities. SCE’s initial search
focused on the following required criteria: (1) the facility must be owned by the State of California; (2)
for interconnection convenience, cost savings, and safety considerations, the facility must have a large
and continuous electrical load to ensure that energy output from the installed fuel cell is used entirely by
the host facility (reducing the overall demand on the electric grid); and (3) the selected facility would
provide a strong platform for community education.
9
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
Workpaper - Southern California Edison / 2015 GRC - APPLICATION
After a cursory review of a number of state facilities within our service territory, SCE
selected the following eleven facilities as potential candidates based on its initial search:
• California State University at Long Beach;
• California State University at San Bernardino;
• California State University at Fullerton;
• California State Polytechnic University at Pomona;
• University of California at Santa Barbara;
• University of California at Irvine;
• University of California at Irvine Medical Center;
• Fairview Developmental Center;
• Porterville Developmental Center.
• Los Alamitos - California National Guard; and
• California State Veterans’ Home at Barstow.
In the second phase of its search, SCE narrowed its search criteria to focus on a host
facility’s ability to utilize the specific fuel cell technologies being advanced by the program, i.e., fuel
cells with cogeneration and electric-only. SCE’s process for selecting final sites, which included site
visits and/or teleconferences, is discussed below in detail.
a) Fuel Cell with Potential Cogeneration Host Sites
One of the goals of the Fuel Cell Program is to demonstrate the ability of fuel
cells to operate at high efficiencies in large, utility-scale (i.e., greater than one MW) installations. To
meet this goal, SCE evaluated each site’s potential to host a fuel cell installation with cogeneration
capabilities of one MW or greater electrical capacity.
Utility-scale fuel cell systems are usually installed with cogeneration capabilities,
where the host site uses both the electricity and heat generated by the fuel cell system. The heat
exhausted from the fuel cell is typically integrated with the host site’s thermal energy systems (building
air conditioning and water heating systems), to provide supplemental heat for HVAC systems or for pre
Exhibit No. SCE-02/ Generation/ Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
Workpaper - Southern California Edison / 2015 GRC - APPLICATION156
heating feed water for boilers. Other innovative uses of waste heat include heating swimming pools or
creating C02-rich warm air for tropical plant facilities.
In order to achieve the highest operating efficiency for a fuel cell/cogeneration
system, the host facility must have the ability to use all of the generated exhaust heat at all times.
Therefore, SCE reviewed each of the sites to determine if the facility would have consistent demand for
the fuel cell’s heat exhaust.
In addition, SCE evaluated each site’s ability to accommodate the space
requirements for large fuel cell systems “on-campus.” Systems of this size typically require up to
10,000 square feet of nearly contiguous outdoor space for the fuel cell and auxiliary equipment, as well
as room for installation, general operations, and maintenance activities. In addition to space
requirements, SCE also evaluated the ease of interconnecting the fuel cell’s mechanical systems with the
host site’s existing physical plant facilities and the ease of interconnecting the fuel cell with gas utilities,
and the site’s electrical distribution system.
Finally, SCE requested each potential host site to provide site-specific
information pertaining to its demand for exhaust heat, gas and electric utility interconnections, and area
available to host a fuel cell.
Utilizing the foregoing information, SCE narrowed its field of candidate locations
to four campuses to participate in a feasibility study (“Feasibility Study”) performed by an engineering
consultant, Black & Veatch (“B&V”). The four sites selected to participate in the study were:
• California State University at San Bernardino;
• California State Polytechnic University at Pomona;
• California State University at Long Beach; and
• California State University at Fullerton.
The Feasibility Study provided an analysis of each site’s potential to host a fuel
cell/cogeneration installation. In particular, the Feasibility Study took into account the following
considerations:
• Fuel cell operation characteristics;
11
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
Workpaper - Southern California Edison / 2015 GRC - APPLICATION
• Conceptual design - thermal system interaction;
• Conceptual design - electrical system interaction;
• Conceptual equipment arrangement and/or building requirements;
• Order of magnitude total installed cost estimates; and
• Analysis of findings.
The Feasibility Study was completed in November 2008. Based on the results,
SCE selected Cal State San Bernardino and Cal State Long Beach as the two optimal locations for
development of fuel cell/cogeneration systems. SCE selected these two sites because they offered the
potential for highest total system efficiency for fuel cell/cogeneration facilities, as well as the simplest
means of integrating the fuel cells with the mechanical operations of the site’s physical plant facilities.
Feasibility Study findings are discussed further below.
Cal State San Bernardino: SCE proposes to locate a fuel cell/cogeneration facility
at the north end of the campus, adjacent to the university’s central heating and cooling plant. The fuel
cell’s exhaust heat would be mechanically integrated with the central plant’s high temperature heating
water system and domestic hot water system, both of which serve most of the campus. Based on the
results of the Feasibility Study, SCE estimates that the overall efficiency of this fuel cell installation
could approach 72%, the highest of all sites evaluated in the study.
Cal State Long Beach: SCE proposes to locate the fuel cell cogeneration facility
at the central part of the campus, adjacent to its swimming pool complex in the southern-most part of the
surrounding athletic fields. The fuel cell’s exhaust heat would be mechanically integrated with the
heating water system that serves much o f the central campus. Based on the results of the Feasibility
Study, SCE estimates that the overall efficiency of this fuel cell installation could approach 70%, also
among the highest of any site evaluated in the study,
b) Electric Only Host Site
Another goal of the Fuel Cell Program is to demonstrate the potential capability
of various types of utility-scale fuel cell technologies. As discussed above, most utility-scale fuel cell
installations are coupled with cogeneration facilities, where the heat exhausted from the fuel cell is
12
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
Workpaper - Southern California Edison / 2015 GRC - APPLICATION158
captured and used on-site in HVAC systems or in the production of steam and hot water. As part of its
Fuel Cell Program, SCE has also chosen to demonstrate and examine the operation and benefits of a
novel design, an electric-only fuel cell system, where the heat exhaust from the fuel cell is recycled
within the fuel cell itself to generate electricity at a much higher efficiency than is standard for the
industry, potentially as high as 60%. SCE believes this effort will be worthwhile because this
technology has not yet been as well-studied as the larger fuel cell/cogeneration options. If successful,
there are many locations where this type and size of equipment could be used and potentially improve
service at a lower cost to electric customers. The commercially available electric-only fuel cell units
tend to be produced as smaller-sized modules than typical fuel cell/cogeneration units. Since they do
not need to be mechanically integrated with a host facility’s physical plant to achieve relatively high
efficiencies, they provide greater flexibility to host sites.
Accordingly, concurrent with the Feasibility Studies performed by B&V for four
potential cogeneration sites, B&V also performed a Feasibility Study for an electric-only fuel cell
installation at UC Santa Barbara, taking into account the following considerations:
• The fuel celFs operational characteristics;
• Conceptual design - electrical system interaction;
• Conceptual equipment arrangement and/or building requirements;
• Order of magnitude of total installed cost estimates; and
• Analysis of findings.
The Feasibility Study was completed in November 2008. Base upon the results of
the Feasibility Study, SCE concluded that UC Santa Barbara would be a strong host facility for an
electric-only fuel cell installation. SCE continues to work with the administration and staff at UC Santa
Barbara to identify the ideal location to place the fuel cell system to maximize the strong environmental
stewardship platform that UC Santa Barbara offers,
c) Selected Host Sites
Following the analysis provided by the Feasibility Study in November 2008, SCE
notified Cal State San Bernardino, Cal State Long Beach, and UC Santa Barbara that SCE selected each
13
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
Workpaper - Southern California Edison / 2015 GRC - APPLICATION
to participate in the Fuel Cell Program.^ The parties appear to have a general understanding regarding
the following details of SCE’s proposed Fuel Cell Program:
• SCE will own and operate the fuel cell and all supporting equipment placed on the
host site;
• SCE will be responsible for fuel costs and O&M for the fuel cell module itself;
• The host site will be responsible for any and all O&M on the equipment that will
integrate the exhaust heat from the fuel cell with the host site’s physical plant;
• The host site will provide access to the fuel cell system to SCE and related third-
parties given reasonable notice;
• Adequate promotional signage and visibility will be given to the program and
SCE’s ownership of the facilities;
• The required space for the fuel cell system will be provided to SCE through a
lease arrangement;
• The electrical power produced by the fuel cell will be metered and provided to the
host facility per its existing tariff service arrangements with SCE;
• The sites with fuel cell/cogeneration facilities will receive and utilize the heat
exhausted from the fuel cell without additional charge; and
• Host sites will be responsible for any and all costs associated with backup thermal
systems necessary to support the thermal/mechanical loads during outages of the
fuel cell.
Both SCE and the selected host sites understand that the Fuel Cell Program must
first be approved by the Commission before the program can proceed, and before detailed negotiations
can be concluded to execute lease agreements. However, preliminary discussions indicate the parties’
are committed to successfully implement the program if it is approved by the Commission. Ultimately,
— SCE has also notified the two non-selected sites of its decision. SCE indicated that it would re-consider pursuing installation at one ofthese sites if the Fuel Cell Program does not move forward at one o f the selected host sites.
14
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
Workpaper - Southern California Edison / 2015 GRC - APPLICATION160
SCE may negotiate a single agreement with the California State University system for CSU San
Bernardino and CSU Long Beach, and a separate agreement for UC Santa Barbara.
4. Selection of Turn-Key Installation Vendors
SCE will procure the fuel cell units and turn-key installation services through an open
request for proposal (“RFP”) process. There will be two distinct RFPs for each potential host site. The
first round of RFPs will be for the procurement of a fuel cell unit for each host site; the results of this
RFP will be made available to the Commission. The second round of RFPs will be for turn-key
engineering, procurement, and construction services for the procured fuel cell units at each respective
potential host site.
The first round of RFPs will specifically address the procurement of fuel cell unit
technology. Based on the responses to its solicitation, SCE will select the fuel cell technology that not
only provides the highest potential total system efficiency as measured by total utilized net electrical and
thermal output, but also the most commercially reasonable terms. SCE has chosen to issue a separate
RFP for each potential host site in order to account for the significant differences between each site’s
mechanical and electrical requirements and the work required to integrate a fuel cell system. For
example, the conceptual integration of the exhaust heat at Cal State San Bernardino requires that the fuel
cell system be integrated both with the central plant’s high temperature heating water system and
domestic hot water system. This is different from the conceptual integration of the exhaust heat at Cal
State Long Beach, which requires only that waste heat be integrated with a heating water system.
Additionally, the proposed electric-only fuel cell represents a different technology with its own siting
and integration issues. Upon selection o f fuel unit vendors for each of the three potential host sites, SCE
will update the Commission on the selection results as an addendum to this application. SCE will not
enter into any binding agreements with the fuel cell unit vendors until the approval of this application by
the Commission.
The second round of RFPs will seek bids for the engineering, procurement, and
construction of the fuel cell systems at each potential host site using the selected fuel cell unit
technology for that respective potential host site. The conceptual designs provided in the Feasibility
15
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
161Workpaper - Southern California Edison / 2015 GRC - APPLICATION
A.10-11-015 - 2012 GRC Update Testimony - SCE 84Page 10
Witness: Jonathan Rumble
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION162
THIS PAGE INTENTIONALLY LEFT BLANK
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
163Workpaper - Southern California Edison / 2015 GRC - APPLICATION
Application No.: Exhibit No.: Witnesses:
A .10-11-015SCE-84 R. Worden D.Snow P. Phelan A. Riddle P. Wong G. Bridges T. Cameron
SOUTHERN CALIFORNIA
EDISON8
An E D ISO N INTERN ATIO N AL® Company
(U 338-E)
|SCE UPDATE TESTIMONY
Before the
Public Utilities Commission of the State of California
Rosemead, California October 24, 2011
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
- Southern California Edison / 2015 GRC - APPLICATION164
IV.
FUEL CELL CAPITAL AND O&M FORECAST
This chapter presents SCE’s update to its Fuel Cell capital expenditure and expense
forecasts. In Chapter III of Exhibit SCE-02, Volume 10, SCE provided its forecast for operation
and maintenance (O&M) expenses and capital expenditures for three fuel cell installations that
SCE would own, operate, and maintain at the University of California Santa Barbara (UC Santa
Barbara), California State University San Bernardino (CSU San Bernardino), and California
State University Long Beach (CSU Long Beach)A SCE’s capital forecast was as follows: $6.3
million (2010), $12.8 million (2011), and $0 million (2012). SCE’s 2012 O&M forecast was
$105,000 in labor expenses and $785,000 in non-labor expenses A
Subsequent to SCE submitting its direct testimony, SCE determined that it would not be
going forward with the fuel cell installation at CSU Long Beach. In SCE’s Reply Brief and in
data request responses to TURN, SCE indicated that appropriate rate base adjustments for the
Fuel Cell program would be made during the update hearing phase of the GRC. Therefore, in this
update testimony; SCE has included the forecast of fuel cell capital expenditures for only the UC
Santa Barbara and CSU San Bernardino installations in its revenue requirement. Since SCE will
not be going forward with the fuel cell installation at CSU Long Beach, SCE’s revised capital
forecast is as follows: $208,119 (2010), $6.6 million (2011), and $3.8 million (2012). Further,
SCE’s revised 2012 test year O&M forecast is $90,000 for labor and $393,333 for nonlabor. The
$90,000 forecasted for 2012 O&M labor expenses and the $393,333 forecasted for 2012 O&M
nonlabor expenses represents an average of forecasted O&M expenses over
2012-2014A
— Pursuant to page B26 of the Commission’s rate case plan (D. 89-01-040), other than electric rate design changes, update testimony is limited to changes in the cost of labor based on contract negotiations, changes in non-labor escalation factors, and known changes due to governmental actions. While the fuel cell update testimony does not fit within the boundaries of page B26 of Decision No. 89-01-040, we assume that the other parties will not object to this testimony, which would result in a decrease in SCE’s 2012 O&M and capital forecasts.
— All O&M expenses are in constant 2009 dollars.
— Fuel Cell Program O&M labor forecast of $90,000 is the average of $50,000 in 2012, $110,000 in 2013, and $110,000 in 2014, forecasted labor. Fuel Cell Program O&M non-labor forecast of $393,333 is the average of $200,000 in 2012, $490,000 in 2013, and $490,000 in 2014, forecasted non-labor.
10
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
165Workpaper - Southern California Edison / 2015 GRC - APPLICATION
A.09-02-013 A.09-04-018 Fuel Cell - Report of Southern California Edison Company (U 338-E) Regarding Efforts to Identify an Alternative Fuel Cell
Site Pursuant to D. 12-04-011
Witness: Jonathan Rumble
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION166
BEFORE THE PUBLIC UTILITIES COMMISSION OF THE
STATE OF CALIFORNIA
Application of Pacific Gas and Electric Company (U39E) For Approval and Recovery of CostsAssociated with its Fuel Cell Project.___________Application of Southern California Edison Company (U338-E) for Authority to Implement and Recover in Rates the Cost of its Proposed Fuel Cell Installation Program for State Universities.
A. 09-02-013 (Filed February 20, 2009)
A. 09-04-018 (Filed April 27, 2009)
REPORT OF SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E) REGARDING EFFORTS TO IDENTIFY AN ALTERNATIVE FUEL CELL SITE PURSUANT TO
DECISION 12-04-011
DOUGLAS K. PORTER WALKER A. MATTHEWS III
Attorneys forSOUTHERN CALIFORNIA EDISON COMPANY
2244 Walnut Grove Avenue Post Office Box 800 Rosemead, California 91770 Telephone: (626) 302-6879Facsimile: (626) 302-3990E-mail: [email protected]
Dated: May 30, 2013
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
167Workpaper - Southern California Edison / 2015 GRC - APPLICATION
BEFORE THE PUBLIC UTILITIES COMMISSION OF THE
STATE OF CALIFORNIA
Application of Pacific Gas and Electric Company (U39E) For Approval and Recovery of Costs Associated with its Fuel Cell Project.Application of Southern California Edison Company (U338-E) for Authority to Implement and Recover in Rates the Cost of its Proposed Fuel Cell Installation Program for State Universities.
A. 09-02-013 (Filed February 20, 2009)
A. 09-04-018 (Filed April 27, 2009)
REPORT OF SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E) REGARDING EFFORTS TO IDENTIFY AN ALTERNATIVE FUEL CELL SITE PURSUANT TO
DECISION 12-04-011
In compliance with Decision (D.) 12-04-011 and in accordance with direction provided
by California Public Utilities Commission (Commission) staff. Southern California Edison
Company (“SCE”) serves this report to the service list for Application (A.) 09-04-018 regarding
SCE’s efforts to identify an alternative fuel cell site pursuant to D .12-04-11. Because
A. 09-04-018 is a closed proceeding, this report is not being fded with the Commission.
I.
INTRODUCTION
The California Public Utilities Commission (Commission) approved SCE’s Fuel Cell
Program in D. 10-04-028, authorizing SCE to install fuel cell facilities at the following University
of California (UC) and California State University (CSU) campuses: 1) UC Santa Barbara, 2)
CSU San Bernardino, and 3) CSU Long Beach. After SCE and CSU Long Beach were unable to
reach an agreement for a reasonable ground lease, SCE cancelled the CSU Long Beach project
and only developed facilities at UC Santa Barbara and CSU San Bernardino, in accordance with
l
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION168
D. 10-04-028. In D. 12-04-011, the Commission granted FuelCell Energy, Inc.'s (FCE) petition to
modify D .10-04-028 to require SCE to seek an alternate host site for the cancelled CSU Long
Beach project. Specifically, Ordering Paragraph (OP) 3 of D. 12-04-011 directed SCE to “make
a reasonable effort to identify an alternative site for the California State University Long Beach
fuel cell project,” within the same budget limits and conditions set in D .10-04-028. The
Commission further required SCE to complete this effort by April 19, 2013 (within a year of the
effective date of D .12-04-011). This report includes SCE’s findings regarding its efforts to
identify an alternative site.
II.
REPORT
Decision D. 12-04-011, OP 3, states, “within 12 months of the effective date of this order.
Southern California Edison Company shall make a reasonable effort to identify an alternative
site for the California State University Long Beach fuel cell project approved in Decision 10-04
028.”
SCE has made a reasonable effort within the 12 month timeframe to identify an
alternative site for the abandoned CSU Long Beach fuel cell project. Specifically, SCE updated
and reviewed information for potential fuel cell installations at California State Polytechnic
University at Pomona and CSU Fullerton, which were two sites originally shortlisted for fuel cell
development. This evaluation included, among other things, conducting site visits; meeting with
staff at each potential host sites; and assessing electrical interconnection, waste-heat integration,
and other related technical issues. Based on the results from its evaluation, SCE has concluded
that a fuel cell project could not be developed at either site within the budget limits and
2
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
169Workpaper - Southern California Edison / 2015 GRC - APPLICATION
conditions set forth in D. 10-04-028. Accordingly, SCE will not be requesting authority to
implement the project at a third site.
Respectfully submitted,
DOUGLAS K. PORTER WALKER A. MATTHEWS III
/s / Walker A. Matthews IIIBy: WALKER A. MATTHEWS III
Attorneys forSOUTHERN CALIFORNIA EDISON COMPANY
2244 Walnut Grove Avenue Post Office Box 800 Rosemead, California 91770 Telephone: (626) 302-6879Facsimile: (626) 302-3990E -mail: walker ,matthews@sce. com
Dated: May 30, 2013
3
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION170
THIS PAGE INTENTIONALLY LEFT BLANK
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
171Workpaper - Southern California Edison / 2015 GRC - APPLICATION
Beginning of Workpapers for:
FERC Account: 549 Miscellaneous Other Power Generation Expenses
A ctiv ity : 549.140 - CATALINA GENERATION - OPERATIONS AND MAINTENANCE OF GENERATIONFACILITIES
Witness: Anthony P. Edeson
Forecast Method Chosen
2012$ (000)
Recorded2012
Forecast2015
Labor Five Year Average 2,234 1,915Non-Labor Five Year Average 1,963 2,680Other N/A 0 0Total 4,197 4,595
Description of Activity:
Catalina Generation - Operations and Maintenance of Generation Facilities - Includes the cost of labor, materials used and expenses incurred in the operation and maintenance of power generating facilities on Catalina Island. Includes labor such as: general supervision; operation of prime movers, generators, and auxiliary apparatus; maintenance of generating equipment; and other miscellaneous activities. Includes non-labor such as: parts for maintaining generating equipment; miscellaneous supplies; transportation expenses; meals, traveling and incidental expenses; utilities; water for fire protection or general use; and miscellaneous small tools.
See Appendix C for Final Cost Centers included in this activity.
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION172
FERC Account: 549 Miscellaneous Other Power Generation Expenses
A ctiv ity : 549.140 - CATALINA GENERATION - OPERATIONS AND MAINTENANCE OF GENERATIONFACILITIES
Witness: Anthony P. Edeson
D E T E R M IN A T IO N O F R E C O R D E D /A D J U S T E D
I R e c o rd e d P e rio d
$ (000)
2008 2009 2010 2011 2012F E R C F o rm 1 R e c o rd e d (N o m in a l $ )
Labor 614 579 754 615 570
Non-Labor 1,063 2,047 1,620 1,385 1,141
O ther 0 0 0 0 0
Total 1,677 2,626 2,374 2,000 1,711
A d ju s tm e n ts - (N o m in a l $) - s e e A p p e n d ix B fo r a d d it io n a l d e ta il
Labor 914 851 1,099 1,354 1,664
Non-Labor 1,104 1,117 1,547 845 822
O ther 0 0 0 0 0
Total 2,018 1,968 2,646 2,199 2,486
R e c o rd e d /A d ju s te d (N o m in a l $)
Labor 1,528 1,430 1,853 1,969 2,234
Non-Labor 2,167 3,164 3,167 2,230 1,963
O ther 0 0 0 0 0
Total 3,695 4,594 5,020 4,199 4,197
E sca la tio n :
Labor 1.1414 1.1070 1.0701 1.0327 1.0000
Non-Labor 1.0881 1.0814 1.0642 1.0254 1.0000
O the r 1.0000 1.0000 1.0000 1.0000 1.0000
R e c o rd e d /A d ju s te d (C o n s ta n t 2 0 1 2 $ )
Labor 1,744 1,583 1,983 2,033 2,234
N on-Labor 2 ,358 3,422 3,370 2,287 1,963
O the r_________________________________ 0______________0______________0______________0_____________0_
Total 4 ,102 5,005 5,353 4,320 4,197
6,000
5.000
4.000
3.000
2.000
1,000
0
□ Labor (std escl) ■ Non-Labor (std escl) □ Other (not escl)
R e c o rd e d A d ju s te d 2 0 0 8 -2 0 1 2 (2 0 1 2 $ )
■ l l l l2008 2009 2010 2011 2012
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
173Workpaper - Southern California Edison / 2015 GRC - APPLICATION
FERC Account: 549 Miscellaneous Other Power Generation Expenses
A ctiv ity: 549.140 - CATALINA GENERATION - OPERATIONS AND MAINTENANCE OF GENERATIONFACILITIES
Witness: Anthony P. Edeson
Forecasting Methods - Summary o f Results o f all Methods Studied - 2012$ (000)
2 Recorded Years (2011 - 2012):Results of Averaging (A2)
2013 | 2014 | 2015 | sd** | Chosen_abor 2,134 2,134 2,134 100 no''Jon-Labor 2,125 2,125 2,125 162 noOther 0 0 0 0 noTotal 4,259 4,259 4,259 n/a n/a
3 Recorded Years (2010 - 2012):Results of Linear Trending (T3) Results of Averaging (A3)
2013 2014 | 2015 | r2* I Chosen 2013 | 2014 | 2015 | sd** | Chosen_abor 2,335 2,460 2,586 0.89 no 2,083 2,083 2,083 108 no'Jon-Labor 1,133 429 (274) 0.91 no 2,540 2,540 2,540 602 noOther 0 0 0 0.00 no 0 0 0 0 no
Total 3,468 2,889 2,312 n/a n/a 4,623 4,623 4,623 n/a n/a
4 Recorded Years (2009 - 2012):Results of Linear Trending (T4)
LaborNon-LaborOtherTotal
2013 2014 2015 r2* Chosen2,4591,395
0
2,660850
0
2,860304
0
0.900.890.00
3,854 3,510 3,164 n/a n/a
2013Results of Averaging (A4)
sd** | Chosen2014 20151,9582,760
0
1,9582,760
0
1,9582,760
0
236 no646 no
0 no4,718 4,718 4,718 n/a n/a
5 Recorded Years (2008 - 2012):Results of Linear Trending (T5) Results of Averaging (A5)
LaborNon-LaborOtherTotal
COoCM 2014 | 2015 | r2* I Chosen
COoCM 2014 | 2015 | sd** | Chosen2,345 2,488 2,631 0.79 no 1,915 1,915 1,915 228 yes2,102 1,910 1,717 0.21 no 2,680 2,680 2,680 600 yes
0 0 0 0.00 no 0 0 0 0 no4,447 4,398 4,348 n/a n/a 4,595 4,595 4,595 n/a n/a
Other Methods:
Last Recorded Year (LRY) Itemized Forecast (IF)
LaborNon-LaborOtherTotal
2013 | 2014 | 2015 | | Chosen 2013 | 2014 | 2015 | | Chosen2,234 2,234 2,234 no 0 0 0 no1,963 1,963 1,963 no 0 0 0 no
0 0 0 no 0 0 0 no4,197 4,197 4,197 n/a 0 0 0 n/a
Forecast Adjustments:Base Forecast Method Adjustments*’
LaborNon-LaborOtherTotal
Method 2013 | 2014 | 2015 | 2013 | 2014 | 2015 | |A5 1,915 1,915 1,915 0 0 0A5 2,680 2,680 2,680 0 0 0N/A 0 0 0 0 0 0
4,595 4,595 4,595 0 0 0
r2 = R Squared (Based on recorded years data) sd = standard deviation (Based on recorded years data) See Appendix B For Additional Detail
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION174
FERC Account: 549 Miscellaneous Other Power Generation Expenses
Activ ity: 549.140 - CATALINA GENERATION - OPERATIONS AND MAINTENANCE OF GENERATIONFACILITIES
Witness: Anthony P. Edeson
Results:
Forecasting Results
LaborNon-LaborOtherTotal
Analysis o f Forecasting Methods
Analysis of Linear Trending Method:In D.89-12-057, the CPUC stated that if costs have shown a trend in a certain direction over three or more years, the last year recorded is an appropriate base estimate. As described in testimony, the use of a five-year average is more appropriate because of the fluctuations in recorded costs.
Analysis of Averaging Method:In D.89-12-057, the CPUC stated that for those sub-accounts which have significant fluctuations in recorded year expenses from year to year, an average of recorded expenses is appropriate. As described in testimony, the use of a five-year average is an appropriate forecast method because of the fluctuations in recorded costs.
Analysis of Last Recorded Year (2012):In D. 89-12-057, the CPUC stated that if costs have shown a trend in a certain direction over three or more years, the last year recorded is an appropriate base estimate. Costs in this sub-account show a four-year trend, but the use of a five-year average is more appropriate for the work activities included in this sub-account.
Analysis of Itemized Forecast Method:Not applicable.
Method Selected 2013 | 2014 | 2015 | |Five Year Average 1,915 1,915 1,915Five Year Average 2,680 2,680 2,680
N/A 0 0 04,595 4,595 4,595
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
175Workpaper - Southern California Edison / 2015 GRC - APPLICATION
FERC Account: 549 Miscellaneous Other Power Generation Expenses
A ctiv ity: 549.140 - CATALINA GENERATION - OPERATIONS AND MAINTENANCE OF GENERATIONFACILITIES
Witness: Anthony P. Edeson
6,000
5.000
4.000
3.000
2.000
1,000
0
Recorded 2008-2012 / Forecast 2013-2015 2012$ (000)
■ I I 1 ■ - I I I2008 2009 2010 2011 2012 2013 2014 2015
□ Labor (std escl) ■ Non-Labor (std escl) □ Cither (not escl)
1 R e c o rd e d P e rio d
$ (0 0 0 )
Forecast Expenses (constant 2012$) 2 0 0 8 | 2 0 0 9 | 2 0 1 0 | 2011 | 2 0 1 2 2 0 1 3 | 2 0 1 4 | 2 0 1 5
Labor (standard escalation) 1,744 1,583 1,983 2,033 2 ,234 1,915 1,915 1,915
Non-Labor (standard escalation) 2,358 3,422 3,370 2,287 1,963 2,680 2,680 2,680
Other (not escalatable) 0 0 0 0 0 0 0 0
Total 4,102 5 ,005 5,353 4,320 4 ,197 4,595 4,595 4,595
Labor Prior year Total 2,234 1,915 1,915
Change (319) 0 0
Total 2 ,234 1,915 1,915 1,915
Non-Labor Prior year Total 1,963 2,680 2,680
Change 717 0 0
Total 1 ,963 2,680 2,680 2,680
O ther Prior year Total 0 0 0
Change 0 0 0
Total 0 0 0 0
Total C hange |
Labor (319) 0 0
Non-Labor 717 0 0
Other 0 0 0
Total N/A 398 0 0
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION176
THIS PAGE INTENTIONALLY LEFT BLANK
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
177Workpaper - Southern California Edison / 2015 GRC - APPLICATION
FERC Account:
Activ ity:
Witness:
549 Miscellaneous Other Power Generation Expenses
549.140 - CATALINA GENERATION - OPERATIONS AND MAINTENANCE OF GENERATION FACILITIESAnthony P. Edeson
APPENDIX A
Detail Description of Final Cost Centers Included in This Activity
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION178
FERC Account: 549 Miscellaneous Other Power Generation Expenses
Activity: 549.140 - CATALINA GENERATION - OPERATIONS AND MAINTENANCE OF GENERATIONFACILITIES
Witness: Anthony P. Edeson
Description of Final Cost Centers included in this activity:
* See Appendix C for Summary Final Cost Centers__________________
•SUMMARY MAINTENANCE OF FUEL HOLDERS, PRODUCERS AND ACCESSORIESIncludes payroll, automotive, and other costs incurred in repairing items in plant account 342.000, including storage tanks, pumps, and pipe system.
•SUMMARY MAINTENANCE OF MISCELLANEOUS POWER PLANT EQUIPMENTIncludes payroll and other costs incurred in repairing miscellaneous equipment in and about the Catalina diesel plant which is available for general use. Includes such items in plant account 346.000 as compressors, cranes, foundations, station maintenance equipment, and ventilation equipment.
•SUMMARY MAINTENANCE OF PRIME MOVERS AND GENERATORSIncludes payroll and other costs of employees and chief engineer incurred in repairing the Catalina diesel plant prime movers, generators, and accessory electric equipment.
•SUMMARY MISCELLANEOUS DIESEL PLANT EXPENSESIncludes payroll costs incurred in miscellaneous diesel plant operations not includable in the foregoing final cost centers, such as general clerical work, watchman, building service, etc. Also includes costs incurred for materials and expenses, such as miscellaneous supplies, utility costs such as telephone, gas, and water, and other miscellaneous diesel plant expenses not assignable to other final cost centers.
•SUMMARY SAFETYIncludes labor, material, contract, chargebacks and other non-labor costs incurred in providing and attending employee safety/crew meetings, first aid meetings, safety congresses, safety fairs, safety stand-downs, and fire extinguisher demonstration meetings. Also includes costs associated with audio metric testing of employees, first aid supplies, safety equipment, and associated travel time, and board and lodging.
•SUMMARY TRAINING SEAT-TIMEIncludes payroll, automotive, and other expenses incurred by employees engaged in compliance training activities or classes. Training activities may include company classes, seminars, orientation, video/DVD and web-based classes. Also includes payroll, automotive, and other expenses of employees engaged in training activities whether it be on-the-job training or off-the-job participation in department/division/district training programs.
F502476 SUPERVISION OF DIESEL PLANT OPERATIONSIncludes a portion of the total payroll and other costs of the general foreman incurred in the general supervision and direction of the operation of the Catalina diesel plant.
F502477 OPERATE PRIME MOVERS/ GENERATORSIncludes payroll and other costs incurred in operating prime movers, generators and auxiliary apparatus, and handling diesel fuel oil. Also includes handling parts, cost and treatment of water for cooling diesel engines, and cost of lubricating oil and grease.
F502480 TOOL EXPENSE CATALINA DIESELIncludes payroll, automotive, and other expenses incurred in ordering, returning, receiving, storing, issuing, repairing, and inventorying tools. Also includes the following: tool inventories; the cost of tool items of small value or short life; material costs in connection with tool repair; testing rubber goods; all other expenses directly connected with the accounting and handling of tools; the preparation and inventory of tools on trucks; and debits and/or credits for annual inventory adjustments.
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
179Workpaper - Southern California Edison / 2015 GRC - APPLICATION
FERC Account: 549 Miscellaneous Other Power Generation Expenses
Activity: 549.140 - CATALINA GENERATION - OPERATIONS a n d m a in te n a n c e o f g e n e r a t io nFACILITIES
Witness: Anthony P. Edeson
Description of Final Cost Centers included in this activity:
* See Appendix C for Summary Final Cost Centers___________________________
F502481 EMISSION CONTROL COSTSIncludes payroll, automotive, and other expenses incurred in installing and operating emission control systems for Catalina diesel generation. Includes costs for Air Quality Management Department (AQMD) permit fees.
F502482 SUPERVISION OF DIESEL PLANT MAINTENANCEIncludes a portion of the total payroll and other costs of the general foreman incurred in the general supervision and direction of the maintenance of the Catalina diesel plant.
F502958 TOXIC WASTE CATALINA DIESELIncludes payroll, automotive, and other expenses incurred in the inspection, sampling, testing, and cleaning of oil products or polychlorinated biphenyl (PCB) contamination caused by leakage and/or spillage. Includes cost of tools and special clothing used in the sampling and clean-up process.
F502976 CATALINA FUEL EXPENSEFuel expense for Catalina diesel operations.
F528318 AIR QUALITY CONTROL EQUIPMENTIncludes payroll, automotive, and other expenses incurred in installing and operating emission control systems for Catalina diesel generation. Includes costs for Air Quality Management Department (AQMD) permit fees.
F528319 MISCELLANEOUS MAINTENANCE OF BUILDING AND GROUNDSIncludes cost of labor, materials used, and expenses incurred in maintaining substationstructures and grounds. Includes such items as: heating and air conditioning equipment and filters; sanitation facilities, including plumbing, inside the structure; all lighting fixtures; fire protection equipment; elevators, cranes, hoists, etc., and the machinery for their operation; sump pumps and pits inside structures; renovating lawns, replacing shrubbery and unlandscaped properties; repairing driveways, walks, and fences; fences and gates; water tanks; and grounding fences.
F900549 MOUNTAINVIEW 8. PEAKER CORPORATE ADJUSTMENT - 546, 548, 549, 550 AND 553OPERATIONS SUPPORT AND ENGINEERINGIncludes payroll costs incurred in miscellaneous diesel plant operations not includable in the foregoing final cost centers, such as general clerical work, watchman, building service, etc. Also includes costs incurred for materials and expenses, such as miscellaneous supplies, utility costs such as telephone, gas, and water, and other miscellaneous diesel plant expenses not assignable to other final cost centers.
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION180
FERC Account: 549 Miscellaneous Other Power Generation Expenses
Activ ity: 549.140 - CATALINA GENERATION - OPERATIONS AND MAINTENANCE OF GENERATIONFACILITIES
Witness: Anthony P. Edeson
Recorded/Adjusted (Constant 2012$ By Final Cost Center
$ (0 0 0 )* See Appendix C for Summary Final Cost Centers 2008 2009 2 0 1 0 2 0 1 1 2 0 1 2
•SUMMARY MAINTENANCE OF FUEL HOLDERS, PRODUCERS AND ACCESSORIES
2 19 96 1 1 0 159
•SUMMARY MAINTENANCE OF MISCELLANEOUS POWER PLANT EQUIPMENT
71 115 33 344 376
•SUMMARY MAINTENANCE OF PRIME MOVERS AND GENERATORS
1,379 1,344 1,887 773 550
•SUMMARY MISCELLANEOUS DIESEL PLANT EXPENSES 1,072 967 1,172 890 805
•SUMMARY SAFETY 0 0 0 0 0
•SUMMARY TRAINING SEAT-TIME 0 0 0 0 0
F502476 SUPERVISION OF DIESEL PLANT OPERATIONS
166 48 6 6 282 435
F502477 OPERATE PRIME MOVERS / GENERATORS 741 764 773 771 755
F502480 TOOL EXPENSE CATALINA DIESEL 25 16 53 38 19
F502481 EMISSION CONTROL COSTS 1,079 1,638 1,134 1,067 915
F502482 SUPERVISION OF DIESEL PLANT MAINTENANCE
69 94 140 45 42
F502958 TOXIC WASTE CATALINA DIESEL 2 0 0 0 0
F502976 CATALINA FUEL EXPENSE 28 0 0 0 0
F528318 AIR QUALITY CONTROL EQUIPMENT 0 0 0 0 118
F528319 MISCELLANEOUS MAINTENANCE OF BUILDING AND GROUNDS
0 0 0 0 23
F900549 MOUNTAINVIEW& PEAKER CORPORATE ADJUSTMENT - 546, 548, 549, 550 AND 553 OPERATIONS SUPPORT AND ENGINEERING
(532) 0 0 0 0
Total 4,102 5,005 5,354 4,320 4,197
** Due to rounding, totals may not tie to other workpaper pages.
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
181Workpaper - Southern California Edison / 2015 GRC - APPLICATION
FERC Account:
Activ ity:
Witness:
549 Miscellaneous Other Power Generation Expenses
549.140 - CATALINA GENERATION - OPERATIONS AND MAINTENANCE OF GENERATION FACILITIESAnthony P. Edeson
APPENDIX B
Detail of Total Company Adjustments to Recorded
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION182
FERC Account: 549 Miscellaneous Other Power Generation Expenses
A ctiv ity : 549.140 - CATALINA GENERATION - OPERATIONS AND MAINTENANCE OF GENERATIONFACILITIES
W itness: Anthony P. Edeson
Detail o f Total Company Adjustments to Recorded Expenses
|Adjs - (Nominal $) $ (0 0 0 )2008 2009 2 0 1 0 2 0 1 1 2 0 1 2 2013 2014 2015
Labor 914 851 1,099 1,354 1,664 0 0 0Non-Labor 1,104 1,117 1,547 845 822 0 0 0Other 0 0 0 0 0 0 0 0Total 2,018 1,968 2,646 2,199 2,486 0 0 0
Organizational Unit Adjustment 1 GBU-CPT.IDP-OUX-GENOTHERPEBBLY-549
This adjustment transfers dollars which belong to Pebbly Beach from FERC 547 to FERC 549.
Labor 0 0 0 0 0 0 0 0Non-Labor 0 35 0 0 0 0 0 0Other 0 0 0 0 0 0 0 0Total 0 35 0 0 0 0 0 0
Organizational Unit Adjustment 2 TDBU-IDP-OU-REMAPP.J O ..549.140
This adjustment consolidates expenses for Catalina Diesel in activity 549.140 where they will be forecast. Costs weretransferred from FERC 546, 548, 551, 552, 553 and 554 to FERC 549.
Labor 1,019 970 1,189 1,403 1,722 0 0 0Non-Labor 1,165 1 , 2 1 2 1,618 855 736 0 0 0Other 0 0 0 0 0 0 0 0Total 2,184 2,182 2,807 2,258 2,458 0 0 0
Organizational Unit Adjustment 3 TDBU-IDP-OU-REMAPP.J O ..566.250
This consolidation adjustment re-maps the expenses from activity 549.140, 553.140, 560.281, 561.170, 562.170, and569.281 to 566.250.
Labor (105) (119) (90) (49) (58) 0 0 0Non-Labor (61) (130) (71) (1 0 ) 8 6 0 0 0Other 0 0 0 0 0 0 0 0Total (166) (249) (161) (59) 28 0 0 0
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
183Workpaper - Southern California Edison / 2015 GRC - APPLICATION
FERC Account:
Activ ity:
Witness:
549 Miscellaneous Other Power Generation Expenses
549.140 - CATALINA GENERATION - OPERATIONS AND MAINTENANCE OF GENERATION FACILITIES
Anthony P. Edeson
APPENDIX C
Final Cost Centers Included in This Activity
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION184
FERC Account: 549 Miscellaneous Other Power Generation Expenses
A ctiv ity: 549.140 - CATALINA GENERATION - OPERATIONS AND MAINTENANCE OF GENERATIONFACILITIES
Witness: Anthony P. Edeson
Final Cost Centers included in this activity:
‘ Summary Final Cost Centers:
MAINTENANCE OF FUEL HOLDERS, PRODUCERS AND ACCESSORIES
F502191 F528377
MAINTENANCE OF MISCELLANEOUS POWER PLANT EQUIPMENT
F502193 F528320 F528323
MAINTENANCE OF PRIME MOVERS AND GENERATORS
F502192 F528317 F528321 F528322 F528324 F528325 F528326 F528378 F528379 F528380
MISCELLANEOUS DIESEL PLANT EXPENSES
F502478 F520683
SAFETY
F522074 F528327
TRAINING SEAT-TIME
F521281 F523365
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
185Workpaper - Southern California Edison / 2015 GRC - APPLICATION
FERC Account: 549 Miscellaneous Other Power Generation Expenses
A c tiv ity : 549.140 - CATALINA GENERATION - OPERATIONS AND MAINTENANCE OF GENERATIONFACILITIES
Witness: Anthony P. Edeson
Individual Final Cost Centers:
F502476 F502477 F502480 F502481 F502482 F502958 F502976 F528318 F528319 F900549
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION186
End of Workpapers for:
FERC Account:
Activ ity:
W itness:
549 Miscellaneous Other Power Generation Expenses
549.140 - CATALINA GENERATION - OPERATIONS AND MAINTENANCE OF GENERATION FACILITIESAnthony P. Edeson
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
187Workpaper - Southern California Edison / 2015 GRC - APPLICATION
Southern California Edison Company
CAPITAL WORKPAPERS - 2015 GRC
OPERATING UNIT SUMMARY (Nominal $000)
Operating Unit Summary: GEN - Pebbly Beach
(1) OPERATING UNIT FORECAST CAPITAL EXPENDITURES: 2015 GRC
Item Testimony DescriptionForecast Capital Expenditures
2013 2014 2015 2016 2017 Total
1 OTHER 2,480 5,465 42C 310 60 8,735
Total 2,480 5,465 42C 310 60 8,735
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION188
Southern California Edison Company
CAPITAL W O R K P A P E R S - 2015 G R C
O P E R A T IN G U N IT S U M M A R Y
(N om ina l $000)
Operating Unit Summary: G EN - Pebbly Beach
(2) O PERA TIN G UNIT R E C O R D E D AND AU TH O RIZED C A P ITA L AND F O R E C A S T E X P EN D ITU R ES: 2015 GRC
DescriptionRecorded and Authorized Capital Expenditures Forecast Capital Expenditures
2008 2009 2010 2011 2012 2013 2014 2015 2016 2017
Authorized Expenditures 3,016 3,366
Recorded & Forecast Expenditures 2,628 3,078 7,980 16,931 4,494 2,480 5,465 420 310 60
Total Expenditure 35,110 8,735
Recorded, Authorized and Forecast Expenditures Graph
2,000 - ■ m-■ ■ ■ m“ 2008 2009 2010 201 1 2012 2013 2014 2015 2016 2017
□
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
189Workpaper - Southern California Edison / 2015 GRC - APPLICATION
Southern California Edison Company
CAPITAL W O R K P A P E R S - 2015 G R C
P R O J E C T DETAIL W O R K S H E E T : VA R IO U S C A TA LIN A C A PITA L PR O JEC TS
Organizational Unit Summary: GEN - Pebbly Beach Testimony Summary: SCE-02, Volume 10 Major Program: Catalina Capital Expenditures Category: CapitalDetail: Various Catalina Capital Projects Database ID: 679 / RO Model ID: 11
Anthony Edeson1. WITNESS2. PROJECT DETAIL
Program Group
Program
P in #
W B S Element
3. PROJECT TYPE
O T H E R - TDBU
C A TA LIN A D IES EL
4049
C E T-P D -O T-C D -C A TD S L
Select one
Compliance: Safety, Environmental, Licenses
Replacem ents in Kind
Upgrades
Blanket: FE, Tools, Spare Parts, Lab, Computer Equip
Select one
Customer Growth
Load Growth
Reliability
Capitalized Software
Various (See Below)
4. ASSET TYPE
5. CLOSE DATE
6 . RIIM ELIGIBLE
Pebbly Beach
Specific Blanket
No
7. COST ESTIMATES (NOMINAL $000)
Y : SC E $
2013 2,480
2014 5,465
2015 420
2016 310
2017 60
Total 8,735
20 1 5 GRC - C a p i t a l E x p e n d i t u r e s F o r e c a s t
6,000
5.000
4.000
3.000
2 .0 0 0
1,000
0
2013 2014 2015 2016 2017
7(a). SYSTEM SHORT TEXT Catalina Diesel
7 (b). DETAILED DESCRIPTION Pebbly Beach Generation Automation System and projects less than $1 million.
8 . SCOPE S ee workpaper for details
9. JUSTIFICATION S ee workpaper for details
X
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION190
Catalina Plant Autom ation Project To Be Completed by Dec, 20142013, May - Dec
Remaining Design, Specification, Bid & PO, Complete 1 Unit
2014 Jan - Dec Construction &
Startup: 5 Units, 33 MT, NaS Battery
2013 - 2014 Cost
2012 & Prior Cost
Project Total Cost
TASK COST COST TotalA. HOME OFFICE Construction Management $30,000 $300,000 $330,000
Starup Management $20,000 $200,000 $220,000
Remaining Design $80,000 $80,000
Project Engineer $40,000 $50,000 $100,000
Engineering support fo r Construction $15,000 $80,000 $95,000
Engineering support fo r startup $15,000 $150,000 $175,000
O&M Training $100,000 $100,000
As Built and Turn Over package $50,000 $50,000 $120,000
Project Management $40,000 $50,000 $100,000
Specification. Bid. POs $50,000 $60,000
Cost & Schedule $20,000 $40,000 $60,000
Misc. $20,000 $100,000 $120,000HO Subtotal $400,000 $1,160,000 $1,560,000
B. MATERIALS Cables/trays/conduits by SCE $20,000 $80,000 $100,000
Others by SCE $100,000 $100,000
Material Subtotal $20,000 $180,000 $200,000C. CONSTRUCTION $0Construction Contractor Re bid $100,000 $500,000 $600,000Programing Contractor Negotiate w ith the contractor
(Dynaelectric) used in 2012 To Complete Programming and Conduct Startup
$100,000 $250,000 $350,000
Test Tech A $30,000 $370,000 $400,000SSID For Diesel Units. MT. Battery $15,000 $85,000 $100,000
Onsite Technical Specialist (Contingent Worker)
For Diesel Units. MT. Battery $20,000 $100,000 $120,000
Other Station Personnel For Diesel Units. MT. Battery $10,000 $50,000 $70,000
Stored Material Shipping $20,000 $20,000IMMs $2,000 $2,000
Construction Subtotal $297,000 $1,365,000 $1,660,000
TOTAL WITHOUT CONTINGENCY $717,000 $2,705,000 $3,422,000CONTINGENCY $83,000 $800,000 $883,000TOTAL $800,000 $3,505,000 $4,305,000 $5,631,000 $9,936,000
Exhibit No. SCE-02 / Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
191Workpaper - Southern California Edison / 2015 GRC - APPLICATION
Beginning of Workpapers for:
FERC Account: 546 Operation Supervision and Engineering
Activ ity: 546.140 - CATALINA DIESEL GENERATION OPERATION SUPERVISION ANDENGINEERING
Witness: Anthony P. Edeson
Forecast Method
Chosen
201 2$ (000)
Recorded
2012
Forecast
2015Labor N/A 0 0
Non-Labor N/A 0 0
Other N/A 0 0
Total 0 0
Description of Activity:
Catalina Generation Operation Supervision and Engineering - Includes the cost of labor and expenses incurred in the general
supervision and direction of the operation of other power generating station. This activity package has zero dollars; all costs
have been transferred to activity 549 .140 .
Final Cost Centers included in this activity (See Appendix A for additional detail):
F502476
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION192
FERC Account: 546 Operation Supervision and Engineering
A ctiv ity : 546.140 - CATALINA DIESEL GENERATION OPERATION SUPERVISION ANDENGINEERING
Witness: Anthony P. Edeson
D E T E R M IN A T IO N O F R E C O R D E D /A D J U S T E D
! R e c o rd e d P e rio d
$ (000)
2008 2009 2010 2011 2012F E R C F o rm 1 R e c o rd e d (N o m in a l $ )
Labor 134 53 49 272 426
N on-Labor 12 (79) 13 1 9
O the r 0______________0______________0______________ 0_____________0
Total 146 (26) 62 273 435
A d ju s tm e n ts - (N o m in a l $) - s e e A p p e n d ix B fo r a d d it io n a l d e ta il
Labor (134) (53) (49) (272) (426)
Non-Labor (12) 79 (13) (1) (9)
O ther 0 0 0 0 0
Total (146) 26 (62) (273) (435)
R e c o rd e d /A d ju s te d (N o m in a l $)
Labor 0 0 0 0 0
Non-Labor 0 0 0 0 0
O ther 0 0 0 0 0
Total 0 0 0 0 0
E sca la tio n :
Labor 1.1414 1.1070 1.0701 1.0327 1.0000
Non-Labor 1.0881 1.0814 1.0642 1.0254 1.0000
O ther 1.0000 1.0000 1.0000 1.0000 1.0000
R e c o rd e d /A d ju s te d (C o n s ta n t 2 0 1 2 $ )
Labor
N on-Labor
O ther
Total
R e c o rd e d A d ju s te d 2 0 0 8 -2 0 1 2 (2 0 1 2 $ )
2008 2009 2010 2011 2012
□ Labor (std escl) ■ Non-Labor (std escl) □ Other (not escl)
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
193Workpaper - Southern California Edison / 2015 GRC - APPLICATION
FERC Account:
Activ ity:
Witness:
546 Operation Supervision and Engineering
546.140 - CATALINA DIESEL GENERATION OPERATION SUPERVISION AND ENGINEERING
Anthony P. Edeson
APPENDIX A
Detail Description of Final Cost Centers Included in This Activity
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION194
546 Operation Supervision and Engineering
546.140 - CATALINA DIESEL GENERATION OPERATION SUPERVISION AND ENGINEERINGAnthony P. Edeson
Recorded/Adjusted (Constant 2012$) By Final Cost Center$ (0 0 0 )
2008 2009 2 0 1 0 2 0 1 1 2 0 1 2
F502476 SUPERVISION OF DIESEL PLANT OPERATIONS
0 0 0 0 0
Total 0 0 0 0 0
** Due to rounding, totals may not tie to other workpaper pages.
FERC Account:
Activity:
Witness:
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
195Workpaper - Southern California Edison / 2015 GRC - APPLICATION
FERC Account:
Activ ity:
Witness:
546 Operation Supervision and Engineering
546.140 - CATALINA DIESEL GENERATION OPERATION SUPERVISION AND ENGINEERINGAnthony P. Edeson
APPENDIX B
Detail of Total Company Adjustments to Recorded
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION196
FERC Account: 546 Operation Supervision and Engineering
A ctiv ity: 546.140 - CATALINA DIESEL GENERATION OPERATION SUPERVISION ANDENGINEERING
Witness: Anthony P. Edeson
Detail o f Total Company Adjustm ents to Recorded Expenses
|Adjs - (Nominal $) $ (0 0 0 )2008 2009 2 0 1 0 2 0 1 1 2 0 1 2 2013 2014 2015
Labor (134) (53) (49) (272) (426) 0 0 0Non-Labor ( 1 2 ) 79 (13) ( 1 ) (9) 0 0 0Other 0 0 0 0 0 0 0 0Total (146) 26 (62) (273) (435) 0 0 0
Organizational Unit Adjustment 1 TDBU-IDP-OU-CAT_ACCTADJ_546.140
This adjustment is for one time expenses for Catalina water and gas sales in 2009.
Labor 0 0 0 0 0 0 0 0Non-Labor 0 6 8 0 0 0 0 0 0Other 0 0 0 0 0 0 0 0
Total 0 6 8 0 0 0 0 0 0
Organizational Unit Adjustment 2 TDBU-IDP-OU-REMAPP_TO_549.140
This adjustment consolidates expenses for Catalina Diesel in activity 549.140 where they will be forecast. Costs were transferred from FERC 546, 548, 551, 552, 553 and 554 to FERC 549.
Labor (134) (53) (49) (272) (426) 0 0 0Non-Labor ( 1 2 ) 1 0 (13) ( 1 ) (9) 0 0 0Other 0 0 0 0 0 0 0 0Total (146) (43) (62) (273) (435) 0 0 0
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
197Workpaper - Southern California Edison / 2015 GRC - APPLICATION
End of Workpapers for:
FERC Account:
Activ ity:
W itness:
546 Operation Supervision and Engineering
546.140 - CATALINA DIESEL GENERATION OPERATION SUPERVISION AND ENGINEERING
Anthony P. Edeson
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION198
THIS PAGE INTENTIONALLY LEFT BLANK
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
199Workpaper - Southern California Edison / 2015 GRC - APPLICATION
Beginning of Workpapers for:
FERC Account: 548 Generation Expenses
Activ ity: 548.140 - CATALINA GENERATION - OPERATION OF PRIME MOVER (TURBINE)
Witness: Anthony P. Edeson
Forecast Method Chosen
201 2$ (000)
Recorded2012
Forecast2015
Labor N/A 0 0
Non-Labor N/A 0 0
Other N/A 0 0
Total 0 0
Description of Activity:
Catalina Generation - Operation of Prime Mover (Turbine) - Includes the cost of labor, materials used and expenses incurred in operating prime movers, generators and electric equipment on Catalina Island. This activity package has zero dollars; all costs have been transferred to activity 549.140.
Final Cost Centers included in this activity (See Appendix A for additional detail):
F502477 F528318
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION200
FERC Account: 548 Generation Expenses
A ctiv ity : 548.140 - CATALINA GENERATION - OPERATION OF PRIME MOVER (TURBINE)
Witness: Anthony P. Edeson
D E TER M INA TIO N O F REC O R D ED /A D JU STED
Recorded Period$ (000)
2008 2009 2010 2011 2012
FERC Form 1 Recorded (Nom inal $)Labor 606 625 666 684 725
Non-Labor 45 67 56 63 148
O ther 0 0 0 0 0
Total 651 692 722 747 873
A d justm ents- (Nom inal $) see Appendix B fo r add itional detail
Labor (606) (625) (666) (684) (725)
Non-Labor (45) (67) (56) (63) (148)
O ther 0 0 0 0 0
Total (651) (692) (722) (747) (873)
Recorded/A d justed (Nom inal $)
Labor 0 0 0 0 0
Non-Labor 0 0 0 0 0
O ther 0 0 0 0 0
Total 0 0 0 0 0
E sca la tio n :
Labor 1.1414 1.1070 1.0701 1.0327 1.0000
Non-Labor 1.0881 1.0814 1.0642 1.0254 1.0000
O ther 1.0000 1.0000 1.0000 1.0000 1.0000
R ecorded/A djusted (C onstan t 2012$)
Labor 0 0 0 0 0
Non-Labor 0 0 0 0 0
O ther 0 0 0 0 0
Total 0 0 0 0 0
Recorded A d justed 2008-2012 (2012$)
6
4
2
0
-2
-4
2008 2009 2010 2011 2012
□ Labor (std escl) ■ Non-Labor (std escl) □ Other (not escl)
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
201Workpaper - Southern California Edison / 2015 GRC - APPLICATION
FERC Account:
Activ ity:
Witness:
548 Generation Expenses
548.140 - CATALINA GENERATION - OPERATION OF PRIME MOVER (TURBINE)
Anthony P. Edeson
APPENDIX A
Detail Description of Final Cost Centers Included in This Activity
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION202
FERC Account: 548 Generation Expenses
Activ ity: 548.140 - CATALINA GENERATION - OPERATION OF PRIME MOVER (TURBINE)
Witness: Anthony P. Edeson
Recorded/Adjusted (Constant 2012$) By Final Cost Center$ (0 0 0 )
2008 2009 2 0 1 0 2 0 1 1 2 0 1 2
F502477 OPERATE PRIME MOVERS / GENERATORS
0 0 0 0 0
F528318 AIR QUALITY CONTROL EQUIPMENT 0 0 0 0 0
Total 0 0 0 0 0
** Due to rounding, totals may not tie to other workpaper pages.
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
203Workpaper - Southern California Edison / 2015 GRC - APPLICATION
FERC Account:
Activ ity:
Witness:
548 Generation Expenses
548.140 - CATALINA GENERATION - OPERATION OF PRIME MOVER (TURBINE)
Anthony P. Edeson
APPENDIX B
Detail of Total Company Adjustments to Recorded
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION204
FERC Account: 548 Generation Expenses
A ctiv ity: 548.140 - CATALINA GENERATION - OPERATION OF PRIME MOVER (TURBINE)
Witness: Anthony P. Edeson
Detail o f Total Company Adjustm ents to Recorded Expenses
|Adjs - (Nominal $) $ (0 0 0 )2008 2009 2 0 1 0 2 0 1 1 2 0 1 2 2013 2014 2015
Labor (606) (625) (6 6 6 ) (684) (725) 0 0 0Non-Labor (45) (67) (56) (63) (148) 0 0 0Other 0 0 0 0 0 0 0 0Total (651) (692) (722) (747) (873) 0 0 0
Organizational Unit Adjustment 1 TDBU-IDP-OU-REMAPP_TO_.549.140
This adjustment consolidates expenses for Catalina Diesel in activity 549.140 where they will be forecast. Costs weretransferred from FERC 546, 548, 551, 552, 553 and 554 to FERC 549.
Labor (606) (625) (6 6 6 ) (684) (725) 0 0 0Non-Labor (45) (67) (56) (63) (148) 0 0 0Other 0 0 0 0 0 0 0 0Total (651) (692) (722) (747) (873) 0 0 0
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
205Workpaper - Southern California Edison / 2015 GRC - APPLICATION
End of Workpapers for:
FERC Account: 548 Generation Expenses
A ctiv ity: 548.140 - CATALINA GENERATION - OPERATION OF PRIME MOVER (TURBINE)
Witness: Anthony P. Edeson
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION206
THIS PAGE INTENTIONALLY LEFT BLANK
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
207Workpaper - Southern California Edison / 2015 GRC - APPLICATION
Beginning of Workpapers for:
FERC Account: 551 Maintenance Supervision and Engineering
Activ ity: 551.140 - CATALINA GENERATION - SUPERVISION OF PLANT MAINTENANCE
Witness: Anthony P. Edeson
Forecast Method
Chosen
201 2$ (000)
Recorded2012
Forecast2015
Labor N/A 0 0
Non-Labor N/A 0 0
Other N/A 0 0
Total 0 0
Description of Activity:
Catalina Generation - Supervision of Plant M aintenance - Includes the cost of labor and expenses incurred in the general supervision and direction of the m aintenance of power generating facilities on Catalina Island. This activity package has zero
dollars; all costs have been transferred to activity 549 .140 .
Final Cost Centers included in this activity (See Appendix A for additional detail):
F502482
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION208
FERC Account: 551 Maintenance Supervision and Engineering
A ctiv ity : 551.140 - CATALINA GENERATION - SUPERVISION OF PLANT MAINTENANCE
Witness: Anthony P. Edeson
D E TER M INA TIO N O F REC O R D ED /A D JU STED
I Recorded Period$ (0 0 0 )
2 0 0 8 2 0 0 9 2 0 1 0 2011 2 0 1 2
FERC Form 1 Recorded (Nom inal $)
Labor 59 40 80 32 9
Non-Labor 2 46 51 12 33
O ther 0 0 0 0 0
Total 61 86 131 44 42
A d justm ents- (Nom inal $) - see Appendix B for additional detailLabor (59) (40) (80) (32) (9)
Non-Labor (2) (46) (51) (12) (33)
O ther 0 0 0 0 0
Total (61) (86) (131) (44) (42)
Recorded/A d justed (Nom inal $)
Labor 0 0 0 0 0
Non-Labor 0 0 0 0 0
O ther 0 0 0 0 0
Total 0 0 0 0 0
E sca la tio n :
Labor 1.1414 1.1070 1.0701 1.0327 1.0000
Non-Labor 1.0881 1.0814 1.0642 1.0254 1.0000
O ther 1.0000 1.0000 1.0000 1.0000 1.0000
R ecorded/A d justed (C onstan t 2012$)
Labor
Non-Labor
OtherTotal
Recorded A d justed 2008-2012 (2012$)
2008 2009 2010 2011 2012
□ Labor (std escl) ■ Non-Labor (std escl) □ Other (not escl)
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
209Workpaper - Southern California Edison / 2015 GRC - APPLICATION
FERC Account:
Activ ity:
Witness:
551 Maintenance Supervision and Engineering
551.140 - CATALINA GENERATION - SUPERVISION OF PLANT MAINTENANCE
Anthony P. Edeson
APPENDIX A
Detail Description of Final Cost Centers Included in This Activity
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION210
FERC Account: 551 Maintenance Supervision and Engineering
Activ ity: 551.140 - CATALINA GENERATION - SUPERVISION OF PLANT MAINTENANCE
Witness: Anthony P. Edeson
Recorded/Adjusted (Constant 2012$) By Final Cost Center$ (0 0 0 )
2008 2009 2 0 1 0 2 0 1 1 2 0 1 2
F502482 SUPERVISION OF DIESEL PLANT MAINTENANCE
0 0 0 0 0
Total 0 0 0 0 0
** Due to rounding, totals may not tie to other workpaper pages.
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
211Workpaper - Southern California Edison / 2015 GRC - APPLICATION
FERC Account:
Activ ity:
Witness:
551 Maintenance Supervision and Engineering
551.140 - CATALINA GENERATION - SUPERVISION OF PLANT MAINTENANCE
Anthony P. Edeson
APPENDIX B
Detail of Total Company Adjustments to Recorded
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION212
FERC Account: 551 Maintenance Supervision and Engineering
A ctiv ity: 551.140 - CATALINA GENERATION - SUPERVISION OF PLANT MAINTENANCE
Witness: Anthony P. Edeson
Detail o f Total Company Adjustm ents to Recorded Expenses
|Adjs - (Nominal $) $ (0 0 0 )2008 2009 2 0 1 0 2 0 1 1 2 0 1 2 2013 2014 2015
Labor (59) (40) (80) (32) (9) 0 0 0Non-Labor (2 ) (46) (51) (1 2 ) (33) 0 0 0Other 0 0 0 0 0 0 0 0Total (61) (8 6 ) (131) (44) (42) 0 0 0
Organizational Unit Adjustment 1 TDBU-IDP-OU-REMAPP_TO_.549.140
This adjustment consolidates expenses for Catalina Diesel in activity 549.140 where they will be forecast. Costs were transferred from FERC 546, 548, 551, 552, 553 and 554 to FERC 549.
Labor (59) (40) (80) (32) (9) 0 0 0Non-Labor (2 ) (46) (51) (1 2 ) (33) 0 0 0Other 0 0 0 0 0 0 0 0Total (61) (8 6 ) (131) (44) (42) 0 0 0
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
213Workpaper - Southern California Edison / 2015 GRC - APPLICATION
End of Workpapers for:
FERC Account: 551 Maintenance Supervision and Engineering
A ctiv ity: 551.140 - CATALINA GENERATION - SUPERVISION OF PLANT MAINTENANCE
Witness: Anthony P. Edeson
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION214
THIS PAGE INTENTIONALLY LEFT BLANK
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
215Workpaper - Southern California Edison / 2015 GRC - APPLICATION
Beginning of Workpapers for:
FERC Account: 552 Maintenance of Structures
A ctiv ity : 552.140 - CATALINA GENERATION - MAINTENANCE OF GENERATION STRUCTURES
Witness: Anthony P. Edeson
Forecast Method Chosen
2 0 1 2 $ (000)
Recorded2 0 1 2
Forecast2015
Labor N/A 0 0Non-Labor N/A 0 0Other N/A 0 0Total 0 0
Description of Activity:
Catalina Generation - Maintenance of Generation Structures - Includes the cost of labor, materials used and expenses incurred in maintenance of facilities used in other power generation such as structures and improvements and fuel holders, producers and accessories. This activity package has zero dollars; all costs have been transferred to activity 549.140.
See Appendix C for Final Cost Centers included in this activity.
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION216
FERC Account: 552 Maintenance of Structures
A ctiv ity : 552.140 - CATALINA GENERATION - MAINTENANCE OF GENERATION STRUCTURES
Witness: Anthony P. Edeson
D E T E R M IN A T IO N O F R E C O R D E D /A D J U S T E D
R e c o rd e d P e rio d
$ (0 0 0 )
2 0 0 8 2 0 0 9 2 0 1 0 2011 2 0 1 2
F E R C F o rm 1 R e c o rd e d (N o m in a l $)
Labor 0 5 33 49 77
Non-Labor 2 12 57 58 105
O ther 0 0 0 0 0
Total 2 17 90 107 182
A d ju s tm e n ts - (N o m in a l $) - s e e A p p e n d ix B fo r a d d it io n a l d e ta il
Labor 0 (5) (33) (49) (77)
Non-Labor (2) (12) (57) (58) (105)
O ther 0 0 0 0 0
Total (2) (17) (90) (107) (182)
R e c o rd e d /A d ju s te d (N o m in a l $)
Labor 0 0 0 0 0
Non-Labor 0 0 0 0 0
O ther 0 0 0 0 0
Total 0 0 0 0 0
E sca la tio n :
Labor 1.1414 1.1070 1.0701 1.0327 1.0000
Non-Labor 1.0881 1.0814 1.0642 1.0254 1.0000
O ther 1.0000 1.0000 1.0000 1.0000 1.0000
R e c o rd e d /A d ju s te d (C o n s ta n t 2 0 1 2 $ )
Labor
N on-Labor
O ther
Total
R e c o rd e d A d ju s te d 2 0 0 8 -2 0 1 2 (2 0 1 2 $ )
2008 2009 2010 2011 2012
□ L a b o r (s td e sc l) ■ N o n -L a b o r (s td e s c l) □ O th e r (n o t e sc l)
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
217Workpaper - Southern California Edison / 2015 GRC - APPLICATION
FERC Account:
Activ ity:
Witness:
552 Maintenance of Structures
552.140 - CATALINA GENERATION - MAINTENANCE OF GENERATION STRUCTURES
Anthony P. Edeson
APPENDIX A
Detail Description of Final Cost Centers Included in This Activity
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION218
FERC Account: 552 Maintenance of Structures
Activ ity: 552.140 - CATALINA GENERATION - MAINTENANCE OF GENERATION STRUCTURES
Witness: Anthony P. Edeson
Recorded/Adjusted (Constant 2012$ By Final Cost Center
$ (0 0 0 )* See Appendix C for Summary Final Cost Centers 2008 2009 2 0 1 0 2 0 1 1 2 0 1 2
•SUMMARY MAINTENANCE OF FUEL HOLDERS, PRODUCERS AND ACCESSORIES
0 0 0 0 0
F528319 MISCELLANEOUS MAINTENANCE OF BUILDING AND GROUNDS
0 0 0 0 0
Total 0 0 0 0 0
** Due to rounding, totals may not tie to other workpaper pages.
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
219Workpaper - Southern California Edison / 2015 GRC - APPLICATION
FERC Account:
Activ ity:
Witness:
552 Maintenance of Structures
552.140 - CATALINA GENERATION - MAINTENANCE OF GENERATION STRUCTURES
Anthony P. Edeson
APPENDIX B
Detail of Total Company Adjustments to Recorded
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION220
FERC Account: 552 Maintenance of Structures
A ctiv ity : 552.140 - CATALINA GENERATION - MAINTENANCE OF GENERATION STRUCTURES
W itness: Anthony P. Edeson
Detail o f Total Company Adjustments to Recorded Expenses
|Adjs - (Nominal $) $ (0 0 0 )2008 2009 2 0 1 0 2 0 1 1 2 0 1 2 2013 2014 2015
Labor 0 (5) (33) (49) (77) 0 0 0Non-Labor (2 ) (1 2 ) (57) (58) (105) 0 0 0Other 0 0 0 0 0 0 0 0Total (2 ) (17) (90) (107) (182) 0 0 0
Organizational Unit Adjustment 1 TDBU-IDP-OU-REMAPP._TO_549.140
This adjustment consolidates expenses for Catalina Diesel in activity 549.140 where they will be forecast. Costs were transferred from FERC 546, 548, 551, 552, 553 and 554 to FERC 549.
Labor 0 (5) (33) (49) (77) 0 0 0Non-Labor (2 ) (1 2 ) (57) (58) (105) 0 0 0Other 0 0 0 0 0 0 0 0Total (2 ) (17) (90) (107) (182) 0 0 0
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
221Workpaper - Southern California Edison / 2015 GRC - APPLICATION
End of Workpapers for:
FERC Account: 552 Maintenance of Structures
A ctiv ity: 552.140 - CATALINA GENERATION - MAINTENANCE OF GENERATION STRUCTURES
Witness: Anthony P. Edeson
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION222
THIS PAGE INTENTIONALLY LEFT BLANK
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
223Workpaper - Southern California Edison / 2015 GRC - APPLICATION
Beginning of Workpapers for:
FERC Account: 553 Maintenance of Generating and Electric Plant
A ctiv ity : 553.140 - CATALINA GENERATION - MAINTENANCE OF GENERATION PRIME MOVERS
Witness: Anthony P. Edeson
Forecast Method Chosen
2012$ (000)
Recorded2012
Forecast2015
Labor N/A 0 0Non-Labor N/A 0 0Other N/A 0 0Total 0 0
Description of Activity:
Catalina Generation - Maintenance of Generation Prime Movers - Includes the cost of labor, materials used and expenses incurred in maintenance of prime movers, generators, and accessory electric equipment. This activity package has zero dollars; all costs have been transferred to activity 549.140.
See Appendix C for Final Cost Centers included in this activity.
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION224
FERC Account: 553 Maintenance of Generating and Electric Plant
A ctiv ity : 553.140 - CATALINA GENERATION - MAINTENANCE OF GENERATION PRIME MOVERS
Witness: Anthony P. Edeson
D E TER M INA TIO N O F REC O R D ED /A D JU STED
Recorded Period
$ (000)
2008 2009 2010 2011 2012
FERC Form 1 Recorded (Nom inal $)Labor 211 237 343 230 311
Non-Labor 1,046 1,001 1,428 522 265
O ther 0 0 0 0 0
Total 1,257 1,238 1,771 752 576
A d justm ents- (Nom inal $) see Appendix B fo r add itional detailLabor (211) (237) (343) (230) (311)
Non-Labor (1,046) (1,001) (1,428) (522) (265)
O ther 0 0 0 0 0
Total (1,257) (1,238) (1,771) (752) (576)
Recorded/A d justed (Nom inal $)
Labor 0 0 0 0 0
Non-Labor 0 0 0 0 0
O ther 0 0 0 0 0
Total 0 0 0 0 0
E sca la tio n :
Labor 1.1414 1.1070 1.0701 1.0327 1.0000
Non-Labor 1.0881 1.0814 1.0642 1.0254 1.0000
O ther 1.0000 1.0000 1.0000 1.0000 1.0000
R ecorded/A djusted (C onstan t 2012$)
Labor 0 0 0 0 0
Non-Labor 0 0 0 0 0
O ther 0 0 0 0 0
Total 0 0 0 0 0
Recorded A d justed 2008-2012 (2012$)
6
4
2
0
-2
-4
2008 2009 2010 2011 2012
□ Labor (std escl) ■ Non-Labor (std escl) □ Other (not escl)
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
225Workpaper - Southern California Edison / 2015 GRC - APPLICATION
FERC Account:
Activ ity:
Witness:
553 Maintenance of Generating and Electric Plant
553.140 - CATALINA GENERATION - MAINTENANCE OF GENERATION PRIME MOVERS
Anthony P. Edeson
APPENDIX A
Detail Description of Final Cost Centers Included in This Activity
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION226
FERC Account: 553 Maintenance of Generating and Electric Plant
Activ ity: 553.140 - CATALINA GENERATION - MAINTENANCE OF GENERATION PRIME MOVERS
Witness: Anthony P. Edeson
Recorded/Adjusted (Constant 2012$ By Final Cost Center
$ (0 0 0 )* See Appendix C for Summary Final Cost Centers 2008 2009 2 0 1 0 2 0 1 1 2 0 1 2
•SUMMARY MAINTENANCE OF PRIME MOVERS AND GENERATORS
0 0 0 0 0
F523311 TRAINING SEAT-TIME 0 0 0 0 0
F526142 TOXIC WASTE DISPOSAL 0 0 0 0 0
Total 0 0 0 0 0
** Due to rounding, totals may not tie to other workpaper pages.
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
227Workpaper - Southern California Edison / 2015 GRC - APPLICATION
FERC Account:
Activ ity:
Witness:
553 Maintenance of Generating and Electric Plant
553.140 - CATALINA GENERATION - MAINTENANCE OF GENERATION PRIME MOVERS
Anthony P. Edeson
APPENDIX B
Detail of Total Company Adjustments to Recorded
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION228
FERC Account: 553 Maintenance of Generating and Electric Plant
A ctiv ity : 553.140 - CATALINA GENERATION - MAINTENANCE OF GENERATION PRIME MOVERS
W itness: Anthony P. Edeson
Detail o f Total Company Adjustments to Recorded Expenses
|Adjs - (Nominal $) $ (0 0 0 )2008 2009 2 0 1 0 2 0 1 1 2 0 1 2 2013 2014 2015
Labor (2 1 1 ) (237) (343) (230) (311) 0 0 0Non-Labor (1,046) (1 ,0 0 1 ) (1,428) (522) (265) 0 0 0Other 0 0 0 0 0 0 0 0Total (1,257) (1,238) (1,771) (752) (576) 0 0 0
Organizational Unit Adjustment 1 TDBU-IDP-OU-REMAPP._TO_573.250
This consolidation adjustment re-maps the expenses from activity 553.140 to 573.250.
Labor 0 0 0 0 (3) 0 0 0Non-Labor 0 0 0 0 (23) 0 0 0Other 0 0 0 0 0 0 0 0Total 0 0 0 0 (26) 0 0 0
Organizational Unit Adjustment 2 TDBU-IDP-OU-REMAPP._TO_549.140
This adjustment consolidates expenses for Catalina Diesel in activity 549.140 where they will be forecast. Costs weretransferred from FERC 546, 548, 551, 552, 553 and 554 to FERC 549.
Labor (211) (237) (343) (230) (308) 0 0 0Non-Labor (1,046) (1,001) (1,428) (522) (242) 0 0 0Other 0 0 0 0 0 0 0 0Total (1,257) (1,238) (1,771) (752) (550) 0 0 0
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
229Workpaper - Southern California Edison / 2015 GRC - APPLICATION
End of Workpapers for:
FERC Account: 553 Maintenance of Generating and Electric Plant
A ctiv ity: 553.140 - CATALINA GENERATION - MAINTENANCE OF GENERATION PRIME MOVERS
Witness: Anthony P. Edeson
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION230
THIS PAGE INTENTIONALLY LEFT BLANK
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
231Workpaper - Southern California Edison / 2015 GRC - APPLICATION
Beginning of Workpapers for:
FERC Account: 554 Maintenance of Miscellaneous Other Power Generation Plant
A ctiv ity : 554.140 - CATALINA GENERATION - MAINTENANCE OF OTHER POWER GENERATIONPLANT
Witness: Anthony P. Edeson
Forecast Method Chosen
201 2$ (000)
Recorded2012
Forecast2015
Labor N/A 0 0
Non-Labor N/A 0 0
Other N/A 0 0
Total 0 0
Description of Activity:
Catalina Generation - Maintenance of Other Power Generation Plant - Includes the cost of labor, materials used and expenses incurred in miscellaneous maintenance of power generation plant on Catalina Island. This activity package has zero dollars; all costs have been transferred to activity 549.140.
See Appendix C for Final Cost Centers included in this activity.
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION232
FERC Account: 554 Maintenance of Miscellaneous Other Power Generation Plant
A ctiv ity : 554.140 - CATALINA GENERATION - MAINTENANCE OF OTHER POWER GENERATIONPLANT
Witness: Anthony P. Edeson
D E TER M INA TIO N O F REC O R D ED /A D JU STED
! Recorded Period$ (000)
2008 2009 2010 2011 2012
FERC Form 1 Recorded (Nom inal $)Labor 9 10 18 136 177
N on-Labor 58 96 13 199 199
O the r 0______________0______________ 0_____________ 0_____________ 0
Total 67 106 31 335 376
A d justm ents- (Nom inal $) - see Appendix B for additional detail
Labor (9) (10) (18) (136) (177)
Non-Labor (58) (96) (13) (199) (199)
O ther 0 0 0 0 0
Total (67) (106) (31) (335) (376)
Recorded/A d justed (Nom inal $)
Labor 0 0 0 0 0
Non-Labor 0 0 0 0 0
O ther 0 0 0 0 0
Total 0 0 0 0 0
E sca la tio n :
Labor 1.1414 1.1070 1.0701 1.0327 1.0000
Non-Labor 1.0881 1.0814 1.0642 1.0254 1.0000
O ther 1.0000 1.0000 1.0000 1.0000 1.0000
R ecorded/A d justed (C onstan t 2012$)
Labor
N on-Labor
O ther
Total
Recorded A d justed 2008-2012 (2012$)
2008 2009 2010 2011 2012
□ Labor (std escl) ■ Non-Labor (std escl) □ Other (not escl)
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
233Workpaper - Southern California Edison / 2015 GRC - APPLICATION
FERC Account:
Activ ity:
Witness:
554 Maintenance of Miscellaneous Other Power Generation Plant
554.140 - CATALINA GENERATION - MAINTENANCE OF OTHER POWER GENERATION PLANT
Anthony P. Edeson
APPENDIX A
Detail Description of Final Cost Centers Included in This Activity
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION234
FERC Account: 554 Maintenance of Miscellaneous Other Power Generation Plant
Activ ity: 554.140 - CATALINA GENERATION - MAINTENANCE OF OTHER POWER GENERATIONPLANT
Witness: Anthony P. Edeson
Recorded/Adjusted (Constant 2012$ By Final Cost Center
$ (000)* See Appendix C for Summary Final Cost Centers 2008 2009 2010 2011 2012
•SUMMARY MAINTENANCE OF MISCELLANEOUS POWER PLANT EQUIPMENT
0 0 0 0 0
F502958 TOXIC WASTE CATALINA DIESEL 0 0 0 0 0
Total 0 0 0 0 0
** Due to rounding, totals may not tie to other workpaper pages.
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
235Workpaper - Southern California Edison / 2015 GRC - APPLICATION
FERC Account:
Activ ity:
Witness:
554 Maintenance of Miscellaneous Other Power Generation Plant
554.140 - CATALINA GENERATION - MAINTENANCE OF OTHER POWER GENERATION PLANTAnthony P. Edeson
APPENDIX B
Detail of Total Company Adjustments to Recorded
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION236
FERC Account: 554 Maintenance of Miscellaneous Other Power Generation Plant
A ctiv ity : 554.140 - CATALINA GENERATION - MAINTENANCE OF OTHER POWER GENERATIONPLANT
W itness: Anthony P. Edeson
Detail o f Total Company Adjustments to Recorded Expenses
|Adjs - (Nominal $) $ (000)2008 2009 2010 2011 2012 2013 2014 2015
Labor (9) (10) (18) (136) (177) 0 0 0Non-Labor (58) (96) (13) (199) (199) 0 0 0Other 0 0 0 0 0 0 0 0Total (67) (106) (31) (335) (376) 0 0 0
Organizational Unit Adjustment 1 TDBU-IDP-OU-REMAPP._TO_549.140
This adjustment consolidates expenses for Catalina Diesel in activity 549.140 where they will be forecast. Costs were transferred from FERC 546, 548, 551, 552, 553 and 554 to FERC 549.
Labor (9) (10) (18) (136) (177) 0 0 0Non-Labor (58) (96) (13) (199) (199) 0 0 0Other 0 0 0 0 0 0 0 0Total (67) (106) (31) (335) (376) 0 0 0
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
237Workpaper - Southern California Edison / 2015 GRC - APPLICATION
End of Workpapers for:
FERC Account:
Activ ity:
W itness:
554 Maintenance of Miscellaneous Other Power Generation Plant
554.140 - CATALINA GENERATION - MAINTENANCE OF OTHER POWER GENERATION PLANT
Anthony P. Edeson
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson
Workpaper - Southern California Edison / 2015 GRC - APPLICATION238
THIS PAGE INTENTIONALLY LEFT BLANK
Exhibit No. SCE-02/ Generation / Vol. 10Witnesses: R. Perez, J. Rumble and A. Edeson