Rule 24 Data ProcessA Simple Example

June 24, 2013

Page 2: Rule 24 Data Process A Simple Example June 24, 2013

Page 2

Introduction

In this example we start with a DRP that is registered with the CPUC and has a DRP service agreement.

We will follow a single, individually metered service account, a 300kW Supermarket, from first contact by a DRP to meter data delivery to CAISO. Our example will illustrate the steps involved and use of forms as well the key players.

Then we will follow another single, individually metered service account, a 300kW Supermarket, from first contact by a DRP to meter data delivery to CAISO.

Our example will ultimately illustrate the challenges to provide the necessary information required.

Page 3: Rule 24 Data Process A Simple Example June 24, 2013

Page 3

The CAISO’s PDR process

• Defined Roles– DRP

• And DRP SC

– UDC– LSE– CAISO

• Undefined Roles– MDMA– Consolidating MDMA

Page 4: Rule 24 Data Process A Simple Example June 24, 2013

Page 4

The Proposed DR process

Page 5: Rule 24 Data Process A Simple Example June 24, 2013

Page 5

D. 12-11-025 Ordering Paragraph 12D. 12-11-025 Ordering Paragraph 12

Pacific Gas and Electric Company, San Diego Gas & Electric Company, and Southern California Edison Company, as the Meter Data Management Agent, are responsible for providing the actual Settlement Quality Meter Data to the demand response provider’s Scheduling Coordinator to facilitate final data submission in accordance with the CAISO tariff.

Page 6: Rule 24 Data Process A Simple Example June 24, 2013

Page 6

The Challenge

RQMD

SQMD

Page 7: Rule 24 Data Process A Simple Example June 24, 2013

Page 7

Meter Data

IOU

30 MW

ESP B

10 MW

ESP A

10 MW

LSE A

MDMA1

MDMA 1SA 1SA 2

SA n

Service Accounts by LSE by MDMAService account information is aggregated as defined by CAISO’s Demand Response System. The MDMA as an actor does not have access to this information.

MDMA 1SA 1SA 2

SA n

MDMA 2SA 1SA 2

SA n

LSE A LSE B LSE C

LSE B

MDMA1

LSE C

MDMA2

RQMD is a routine processthat MDMAs perform.

PDR

XYZ

SQMD requires meter data plus registration data. MDMAs provide the meter data, but do not yet have access to the DRS registration data.

Page 8: Rule 24 Data Process A Simple Example June 24, 2013

Page 8

For ExampleFor Example

• DRP (Muir’s DRP Co)– Signs up a supermarket– Registers the supermarket in Resource B – Registration B1

• Processes– UDC CISR form– CAISO Demand Response System (DRS)

• UDC “ok”• LSE “ok”• CAISO “ok”

– Meter Data• MDMA1

– RQMD– SQMD

Page 9: Rule 24 Data Process A Simple Example June 24, 2013

Page 9

Example continuedExample continued

• DRP (Muir’s DRP Co)– Signs up another supermarket

• MDMA2

– Also registers the supermarket in Resource B – New Registration B2

• Processes– UDC CISR form– CAISO DRS

• UDC “ok”• LSE “ok”• CAISO “ok”

– Meter Data• MDMA2

– RQMD– No SQMD (different MDMAs)

Page 10: Rule 24 Data Process A Simple Example June 24, 2013

Page 10

Here we go with the Example

• Meet Muir’s DRP Company

CPUC RegisteredAll other agreements in place

Page 11: Rule 24 Data Process A Simple Example June 24, 2013

Page 11

Muir Co signs “Fantastic Basket Supermarket”

Page 12: Rule 24 Data Process A Simple Example June 24, 2013

Page 12

Muir Co completes Enrollment

UDC CISR Form

CAISO DRS Form

Page 13: Rule 24 Data Process A Simple Example June 24, 2013

Page 13

Approvals

• UDC approves

• LSE approves

• CAISO approves

• DRP all set

Page 14: Rule 24 Data Process A Simple Example June 24, 2013

Page 14

Meter Data

IOU

30 MW

ESP B

10 MW

ESP A

10 MW

LSE A

MDMA1

MDMA 1SA 1

Service Account by MDMA 1For one service account Revenue Quality Meter Data (RQMD) is the same as Settlement Quality Meter Data (SQMD).

LSE A

RQMD

PDR

XYZ

Muir Co establishes Registration B1, containing one SA (Fantastic Basket). In this case SQMD = RQMD.

Page 15: Rule 24 Data Process A Simple Example June 24, 2013

Page 15

CAISO’s DRS Registration process

Page 16: Rule 24 Data Process A Simple Example June 24, 2013

Page 16

Muir Co signs “Play Foods Grocers”

Page 17: Rule 24 Data Process A Simple Example June 24, 2013

Page 17

Muir Co completes Enrollment

UDC CISR Form

CAISO DRS Add Form

Page 18: Rule 24 Data Process A Simple Example June 24, 2013

Page 18

Approvals

• UDC approves

• LSE approves

• CAISO approves

• DRP all set

Page 19: Rule 24 Data Process A Simple Example June 24, 2013

Page 19

Meter Data

IOU

30 MW

ESP B

10 MW

ESP A

10 MW

LSE A

MDMA1

MDMA 1SA 1

Service Accounts by LSE by MDMA

MDMA 2SA 1

LSE A LSE B LSE C

LSE B

MDMA1

LSE C

MDMA2

RQMD

PDR

XYZ

For an MDMA to keep track of the registration changes, it will need access to the CAISO’s DRS.

The addition of “Play Foods” requires a new registration B2. Here the RQMD is not the same as SQMD.

Page 20: Rule 24 Data Process A Simple Example June 24, 2013

Page 20

SQMD Process (?)

IOU

30 MW

ESP B

10 MW

ESP A

10 MW

LSE A

MDMA1

MDMA 1SA 1

Service Accounts by LSE by MDMA

MDMA 2SA 1

LSE A LSE B LSE C

LSE B

MDMA1

LSE C

MDMA2

RQMD

PDR

XYZ

There is a need to consolidate the RQMD information from the MDMAs as defined by the registrations from the DRS to produce the SQMD. This could be done by the DRP or a consolidating MDMA.

The DRS information is critical for producing the SQMD necessary for supporting each registration. There may be times where there are multiple registrations requiring SQMD for the same DR resource.