THE VIRGINIA TRANSPORTATION

Commonwealth Transportation BoardVirginia Department of Transportation

Virginia Department of Rail and Public Transportation

2015 – 2020

REVISED FINAL

RICHMOND DISTRICT

Page 2: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

This Page Is Intentionally Left Blank

700 11/12/2014

Page 3: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL

FY2015-2020 Six-Year Improvement Program RICHMOND DISTRICT

FY2019 FY2020FY2018FY2017FY2016FY2015Fund Source Name

Funding Allocation Summary (000's)

RICHMOND DISTRICT

System Totals

Interstate

CTB Formula

$12,439$15,131$11,807$8,064$7,958$0Bridge - State $55,399

0 0 0 1,750 0 0High Priority - State 1,750

0 0 37,350 5,079 2,258 1,464Paving - Federal 46,151

0 0 9,338 1,270 565 366Paving - Soft Match 11,538

0 0 0 15,561 12,162 2,198Paving - State 29,921

NHPP

0 0 0 0 0 6,400BOA - NHPP Federal 6,400

0 0 0 0 0 1,600BOA - NHPP Soft Match 1,600

0 0 1,175 570 2,876 2,442Bridge - Federal 7,064

0 0 294 143 719 611Bridge - Soft Match 1,766

0 0 3,794 13,319 0 3,550Statewide - Federal 20,663

0 0 422 1,480 0 887Statewide - Soft Match 2,789

RSTP (STP Regional)

0 1,600 1,000 0 1,280 1,240MPO - Federal 5,120

0 400 250 0 320 310MPO - State Match 1,280

STP

0 0 8,121 0 0 0Statewide - Federal 8,121

0 0 2,030 0 0 0Statewide - Soft Match 2,030

$12,439$17,131$75,581$47,235$28,138$21,068Total $201,592

Primary

CMAQ

$3,440$4,094$2,624$1,343$890$417MPO - Federal $12,810

860 1,024 656 336 223 104MPO - State Match 3,202

CTB Formula

3,308 487 4,531 1,759 5,012 0Bridge - State 15,097

0 0 51 0 0 0High Priority - State 51

0 0 0 0 120 60ITS - State 180

0 0 0 2,634 618 1,256Paving - Federal 4,508

0 0 0 659 154 314Paving - Soft Match 1,127

0 0 0 4,656 14,871 0Paving - State 19,528

Highway Safety Improvements

0 0 0 2,025 2,025 5,427Federal 9,477

0 0 0 225 225 603Soft Match 1,053

NHPP

3,221 1,376 0 0 414 957Bridge - Federal 5,967

805 344 0 0 104 239Bridge - Soft Match 1,492

0 0 0 0 0 674Statewide - Federal 674

0 0 0 0 0 169Statewide - Soft Match 169

RSTP (STP Regional)

2,012 5,520 8,800 7,052 4,475 5,351MPO - Federal 33,210

503 1,380 2,200 1,763 1,119 1,338MPO - State Match 8,302

STP

5,569 3,332 2,988 1,932 3,282 682Bridge - Federal 17,786

1,392 833 747 483 821 171Bridge - Soft Match 4,446

0 0 252 8 1,814 755Statewide - Federal 2,829

0 0 63 2 454 189Statewide - Soft Match 707

$21,109$18,390$22,913$24,877$36,619$18,706Total $142,615

11/12/2014 701

Page 4: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL

FY2015-2020 Six-Year Improvement Program RICHMOND DISTRICT

FY2019 FY2020FY2018FY2017FY2016FY2015Fund Source Name

Funding Allocation Summary (000's)

RICHMOND DISTRICT - cont.

System Totals

CMAQ

$0$560$2,160$1,874$2,341$958MPO - Federal $7,892

0 140 540 468 585 240MPO - State Match 1,973

CTB Formula

4,291 5,532 1,885 2,962 0 0Bridge - State 14,670

0 95 0 0 0 0High Priority - State 95

1,089 1,133 1,051 1,039 638 117Unpaved - State 5,067

Highway Safety Improvements

0 0 1,080 135 2,070 135Federal 3,420

0 0 120 15 230 15Soft Match 380

Local Project Contributions

0 0 0 0 0 10,035Local 10,035

Residue Parcel Revenue

0 0 0 0 0 59State 59

Revenue Sharing Funds

0 0 0 0 0 9,110Local Match 9,110

0 0 0 0 0 9,110State Match 9,110

RSTP (STP Regional)

4,244 1,577 1,833 2,597 4,303 2,817MPO - Federal 17,372

1,061 394 458 649 1,076 704MPO - State Match 4,343

STP

5,041 3,248 4,586 5,461 3,367 2,980Bridge - Federal 24,682

1,260 812 1,146 1,365 842 745Bridge - Soft Match 6,171

2,309 2,264 2,234 1,953 2,074 1,558BROS - Federal 12,393

577 566 559 488 519 390BROS - Soft Match 3,098

Telecommunications

1,877 1,877 1,877 1,877 1,877 1,877State 11,261

$21,750$18,199$19,529$20,883$19,921$40,850Total $141,132

Urban

CMAQ

$2,763$2,151$1,800$3,480$3,461$2,681MPO - Federal $16,336

691 538 450 870 865 670MPO - State Match 4,084

CTB Formula

0 0 0 0 2,000 0High Priority - State 2,000

Revenue Sharing Funds

0 0 0 0 0 13,023Local Match 13,023

0 0 0 0 0 13,023State Match 13,023

RSTP (STP Regional)

3,412 4,452 1,548 2,140 2,938 1,567MPO - Federal 16,056

853 1,113 387 535 734 392MPO - State Match 4,014

STP

0 0 0 0 0 129Bridge - Federal 129

0 0 0 0 0 32Bridge - Soft Match 32

$7,718$8,254$4,185$7,025$9,999$31,516Total $68,697

Enhancement

Revenue Sharing Funds

$0$0$0$0$0$180Local Match $180

0 0 0 0 0 180State Match 180

Secondary

702 11/12/2014

Page 5: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL

FY2015-2020 Six-Year Improvement Program RICHMOND DISTRICT

FY2019 FY2020FY2018FY2017FY2016FY2015Fund Source Name

Funding Allocation Summary (000's)

RICHMOND DISTRICT - cont.

System Totals

TAP

1,121 1,121 1,121 1,121 1,121 1,123MPO - Federal 6,727

0 0 0 0 0 1,000Statewide - Federal 1,000

$1,121$1,121$1,121$1,121$1,121$2,483Total $8,086

Transit

CMAQ

$28$28$28$428$428$742MPO - Federal $1,682

7 7 7 107 107 185MPO - State Match 420

$35$35$35$535$535$927Total $2,102

Other

CMAQ

$1,360$757$979$466$470$2,561MPO - Federal $6,593

340 189 245 116 118 640MPO - State Match 1,648

CTB Formula

0 0 0 0 375 150ITS - State 525

Highway Safety Improvements

4,453 3,116 2,489 5,267 3,713 1,656Federal 20,694

495 346 277 585 413 184Soft Match 2,299

Prescoping Funds

1,130 1,105 1,082 1,058 1,818 919State 7,113

RSTP (STP Regional)

4,532 1,050 1,018 2,410 1,203 488MPO - Federal 10,701

1,133 263 255 603 301 122MPO - State Match 2,675

$13,443$6,827$6,343$10,506$8,411$6,720Total $52,249

Grand Total $77,615$69,956$129,705$112,182$104,743$122,270 $616,472

11/12/2014 703

Page 6: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

This Page Is Intentionally Left Blank

704 11/12/2014

Page 7: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Interstate

MPO Area

RichmondInterstate

PROGRAM/SYSTEM

I-64 - WIDEN FROM 4 TO 6 LANES AND

IMPROVE RTE 623 INTERCHNG

PROJECT

UPC NO.:

ROUTE:

70542

FO0064

Federal Requirement for Access Approval on Route 288 Intchg.REPORT NOTE:

Underway

SCHEDULE

1,413

ESTIMATED COST (000's)

JURISDICTION:

I-64STREET NAME:

PERichmond District-wide

Underway 35,816CNFROM: 0.99 MI W RTE 623 (WB - RTE 622, EB - RTE

623) TO: 0.38 MI W RTE 295 IN SHORT PUMP

(POUNCEY TRACT RD) (4.5200 MI)

DESCRIPTION: RW

8578,8579,8580,8581,8635,8639,9778,9779,9780,9781,26461,26462,2667159,61,73,74,81,86,95,96,96,97,100PROJECT LENGTH: 4.5200 MI STRUCTURE NO.: SUFFICIENCY RATING:

SCOPE OF WORK: Reconstruction w/ Added Capacity TO 37,229

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 4,305Bond Proceeds: CPR Bonds

1,407 0 0 0 0 0 0CTB Formula: Bridge - State

0 0 0 0 0 0 860CTB Formula: High Priority - Federal

0 0 0 0 0 0 215CTB Formula: High Priority - Soft Match

0 0 0 0 1,750 0 0CTB Formula: High Priority - State

0 0 0 0 0 0 6,718Interstate: Federal

0 0 0 0 0 0 1,222Interstate: State Match

0 0 0 0 0 6,400 0NHPP: BOA - NHPP Federal

0 0 0 0 0 1,600 0NHPP: BOA - NHPP Soft Match

0 0 0 0 0 928 8,907NHPP: Statewide - Federal

0 0 0 0 0 232 2,227NHPP: Statewide - Soft Match

0 0 0 0 0 0 457Soft Match: Federal

0 0 0 0 1,750 1,407 9,160 24,912Total

MPO Area

RichmondInterstate

PROGRAM/SYSTEM

RTE 64 - REPLACE BRIDGES OVER RTE 156

PROJECT

UPC NO.:

ROUTE:

97565

FO0064

Revised schedule required.REPORT NOTE:

Underway

SCHEDULE

2,000

ESTIMATED COST (000's)

JURISDICTION:

STREET NAME:

PEHenrico County

FY2017 15,386CNFROM: APPROACHES & BRIDGE OVER RTE 156 TO:

(2.60 MI W RTE 295)

DESCRIPTION: RW

30233 -1PROJECT LENGTH: _ STRUCTURE NO.: SUFFICIENCY RATING:

SCOPE OF WORK: Bridge Replacement w/o Added Capacity TO 17,386

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

1,250 0 10,131 3,005 3,000 0 0CTB Formula: Bridge - State 0

MPO Area

NonMPOInterstate

PROGRAM/SYSTEM

I-64 WB RESTORE EXIST. PAVE

PROJECT

UPC NO.:

ROUTE:

104496

FO0064

SCHEDULE ESTIMATED COST (000's)

JURISDICTION:

STREET NAME:

PEGoochland County

Underway 2,765CNFROM: GOOCHLAND/LOUISA COUNTY LINE TO: 0.41

MI. W. RTE. 606 (WALTON RD.) (3.3500 MI)

DESCRIPTION: RW

PROJECT LENGTH: 3.3500 MISCOPE OF WORK: Resurfacing TO 2,765

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

2,765 0 0 0 0 0 0CTB Formula: Paving - State 0

11/12/2014 705

Page 8: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Interstate

MPO Area

NonMPOInterstate

PROGRAM/SYSTEM

I-64 EB REHAB EXISTING PAVEMENT

PROJECT

UPC NO.:

ROUTE:

104498

FO0064

SCHEDULE ESTIMATED COST (000's)

JURISDICTION:

STREET NAME:

PEGoochland County

Underway 1,760CNFROM: 0.36 MI. E. RTE. 522 (CROSS COUNTRY RD.)

TO: 2.51 MI. E. RTE. 522 (CROSS COUNTRY RD.)

(2.1500 MI)

DESCRIPTION: RW

PROJECT LENGTH: 2.1500 MISCOPE OF WORK: Resurfacing TO 1,760

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 422 0CTB Formula: Paving - Federal

0 0 0 0 0 106 0CTB Formula: Paving - Soft Match

1,232 0 0 0 0 0 0CTB Formula: Paving - State

0 0 0 0 0 1,232 528 0Total

MPO Area

RichmondInterstate

PROGRAM/SYSTEM

I-64 EB REHAB EXISTING PAVEMENT

PROJECT

UPC NO.:

ROUTE:

104499

FO0064

SCHEDULE ESTIMATED COST (000's)

JURISDICTION:

STREET NAME:

PENew Kent County

Underway 17,319CNFROM: 0.13 mi. E. Airport Rd. TO: James City CL

(15.6900 MI)

DESCRIPTION: RW

PROJECT LENGTH: 15.6900 MISCOPE OF WORK: Resurfacing TO 17,319

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 2,400 242 0CTB Formula: Paving - Federal

0 0 0 0 600 60 0CTB Formula: Paving - Soft Match

8,165 0 0 0 5,851 0 0CTB Formula: Paving - State

0 0 0 0 8,851 8,165 302 0Total

MPO Area

RichmondInterstate

PROGRAM/SYSTEM

RTE 64 - REPLACE BRIDGES OVER RTE 33

(NINE MILE RD)

PROJECT

UPC NO.:

ROUTE:

105141

FO0064

Revised schedule required.REPORT NOTE:

SCHEDULE ESTIMATED COST (000's)

JURISDICTION:

I-64STREET NAME:

PEHenrico County

FY2014 9,535CNFROM: APPROACHES & BRIDGES OVER RTE 33 TO:

(0.80 MI E RTE 156) (0.8300 MI)

DESCRIPTION: RW

30208,30209 -1PROJECT LENGTH: 0.8300 MI STRUCTURE NO.: SUFFICIENCY RATING:

SCOPE OF WORK: Bridge Replacement w/o Added Capacity TO 9,535

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

282 0 0 0 0 0 0CTB Formula: Bridge - State

2,876 0 0 1,175 570 2,442 179NHPP: Bridge - Federal

719 0 0 294 143 611 45NHPP: Bridge - Soft Match

0 0 0 0 0 0 160STP: Bridge - Federal

0 0 0 0 0 0 40STP: Bridge - Soft Match

0 0 0 1,469 713 3,877 3,053 424Total

706 11/12/2014

Page 9: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Interstate

MPO Area

NonMPOInterstate

PROGRAM/SYSTEM

I-85 RESTORE EXIST. PAVE NB/SB

PROJECT

UPC NO.:

ROUTE:

104465

FO0085

SCHEDULE ESTIMATED COST (000's)

JURISDICTION:

STREET NAME:

PERichmond District-wide

Underway 22,265CN

FROM: MM 6.70 TO: MM 37.56 (30.8600 MI)DESCRIPTION: RW

PROJECT LENGTH: 30.8600 MISCOPE OF WORK: Restoration and Rehabilitation TO 22,265

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

800 0 0 5,137 1,098 0 301CTB Formula: Paving - Federal

200 0 0 1,284 275 0 33CTB Formula: Paving - Soft Match

0 0 0 0 5,126 45 0CTB Formula: Paving - State

0 0 0 1,459 5,710 0 0NHPP: Statewide - Federal

0 0 0 162 634 0 0NHPP: Statewide - Soft Match

0 0 0 8,043 12,843 1,000 45 334Total

MPO Area

Tri-CitiesInterstate

PROGRAM/SYSTEM

I-85 RESTORE EXIST. PAVE NB/SB

PROJECT

UPC NO.:

ROUTE:

104466

FO0085

SCHEDULE ESTIMATED COST (000's)

JURISDICTION:

STREET NAME:

PEDinwiddie County

Underway 44,197CN

FROM: MM 40.32 TO: MM 61.44 (21.1200 MI)DESCRIPTION: RW

PROJECT LENGTH: 21.1200 MISCOPE OF WORK: Restoration and Rehabilitation TO 44,197

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

658 0 0 23,733 0 800 268CTB Formula: Paving - Federal

165 0 0 5,933 0 200 30CTB Formula: Paving - Soft Match

0 0 0 1,834 1,435 0 0NHPP: Statewide - Federal

0 0 0 204 159 0 0NHPP: Statewide - Soft Match

0 0 0 7,023 0 0 0STP: Statewide - Federal

0 0 0 1,756 0 0 0STP: Statewide - Soft Match

0 0 0 40,482 1,595 823 1,000 297Total

MPO Area

RichmondInterstate

PROGRAM/SYSTEM

RTE 95 - BRIDGE REHABILITATION

PROJECT

UPC NO.:

ROUTE:

18944

FO0095

Complete

SCHEDULE

6,841

ESTIMATED COST (000's)

JURISDICTION:

Interstate 95STREET NAME:

PERichmond District-wide

Underway 92,400CN

UnderwayFROM: 0.20 miles south of Lombardy Intersection TO:

0.02 miles north of Upham Brook (5.3200 MI)

DESCRIPTION: 387RW

9836,9837,21443,21445,21447,21449,21451,21453,21455,21457,2149861,64,66,74,75,77,81,85PROJECT LENGTH: 5.3200 MI STRUCTURE NO.: SUFFICIENCY RATING:

SCOPE OF WORK: Bridge Rehab w/o Added Capacity TO 99,628

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 7,317Bonus OA: Federal

0 0 0 0 0 0 813Bonus OA: State Match

0 0 0 0 0 0 76,854Interstate: Federal

0 0 0 0 0 0 13,950Interstate: State Match

0 0 0 0 0 0 583NHPP: Statewide - Federal

0 0 0 0 0 0 111NHPP: Statewide - Soft Match

0 0 0 0 0 0 0 99,628Total

11/12/2014 707

Page 10: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Interstate

MPO Area

RichmondInterstate

PROGRAM/SYSTEM

RTE 95 - INTERCHANGE MODIFICATION

PROJECT

UPC NO.:

ROUTE:

58920

FO0095

MPO Project PE & RW only. See ARRA UPC 94855 for CN phase.REPORT NOTE:

Complete

SCHEDULE

661

ESTIMATED COST (000's)

JURISDICTION:

Lewistown Rd.STREET NAME:

PEHanover County

CN

UnderwayFROM: 0.064 Mi. W. Int. Rte. 743 TO: 0.367 Mi. E. Int.

Rte. 743 (0.4310 MI)

DESCRIPTION: 1,081RW

PROJECT LENGTH: 0.4310 MISCOPE OF WORK: Reconstruction w/o Added Capacity TO 1,742

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 348Non-Formula: State Match

0 0 0 0 0 0 1,394RSTP (STP Regional): Federal

0 0 0 0 0 0 0 1,742Total

MPO Area

Tri-CitiesInterstate

PROGRAM/SYSTEM

RTE 95 - INTERCHANGE IMPROVEMENT/

ROUNDABOUT

PROJECT

UPC NO.:

ROUTE:

85623

FO0095

Revised schedule required.REPORT NOTE:

Underway

SCHEDULE

1,404

ESTIMATED COST (000's)

JURISDICTION:

TEMPLE AVESTREET NAME:

PEColonial Heights

FY2014 14,395CN

FY2014FROM: 0.041 MI W HAMILTON AVE TO: 0.069 MI E

EXISTING I-95 RAMP (0.3690 MI)

DESCRIPTION: 4,250RW

PROJECT LENGTH: 0.3690 MISCOPE OF WORK: Safety TO 20,049

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 4,941Bond Proceeds: CPR Bonds

0 0 0 0 0 0 7,864Interstate: Federal

0 0 0 0 0 0 1,619Interstate: State Match

0 0 0 0 0 2,622 1,600NHPP: Statewide - Federal

0 0 0 0 0 656 400NHPP: Statewide - Soft Match

0 0 0 0 0 0 347Soft Match: Federal

0 0 0 0 0 0 3,278 16,771Total

708 11/12/2014

Page 11: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Interstate

MPO Area

RichmondInterstate

PROGRAM/SYSTEM

RTE 802 - REPLACE BRIDGE OVER 95, MOD

RAMPS & AIRPARK RD

PROJECT

UPC NO.:

ROUTE:

90347

FO0095

MPO project.REPORT NOTE:

Underway

SCHEDULE

2,074

ESTIMATED COST (000's)

JURISDICTION:

LEWISTOWN ROADSTREET NAME:

PEHanover County

FY2015 22,693CN

UnderwayFROM: 0.252 MILES WEST INT. I-95 TO: 0.431 MILES

EAST INT. I-95 (0.6830 MI)

DESCRIPTION: 5,341RW

29524 -1PROJECT LENGTH: 0.6830 MI STRUCTURE NO.: SUFFICIENCY RATING:

SCOPE OF WORK: Bridge Replacement w/o Added Capacity TO 30,108

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

3,331 0 0 8,602 3,000 0 0CTB Formula: Bridge - State

0 0 0 0 0 0 125Non-Formula: State Match

0 0 0 0 0 0 7,459RSTP (STP Regional): Federal

1,040 0 1,600 1,000 0 1,040 0RSTP (STP Regional): MPO - Federal

260 0 400 250 0 260 0RSTP (STP Regional): MPO - State Match

0 0 0 0 0 0 1,740RSTP (STP Regional): State Match

0 0 2,000 9,852 3,000 4,631 1,300 9,324Total

MPO Area

RichmondInterstate

PROGRAM/SYSTEM

ARRA - HANOVER 95 RAMP IMPROVEMENTS

FOR LEWISTOWN (743)

PROJECT

UPC NO.: 94855

FOARRA09

PE & RW on UPC 58920;REPORT NOTE:

FROM: 0.061 MI W INT RTE 743 TO: 0.367 MI E INT RTE

743 (0.4290 MI)

DESCRIPTION:

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 3,188American Recovery and Reinvestment Act:

Urbanized Area > 200K

MPO Area

Multiple MPOsInterstate

PROGRAM/SYSTEM

I-95 NB ONLY RESTORE EXIST. PAVE

PROJECT

UPC NO.:

ROUTE:

104489

FO0095

SCHEDULE ESTIMATED COST (000's)

JURISDICTION:

STREET NAME:

PEChesterfield County

Underway 4,313CNFROM: Rte. 620 (Woods Edge Rd.) TO: Rte. 10 (West

Hundred Rd.) (3.5700 MI)

DESCRIPTION: RW

PROJECT LENGTH: 3.5700 MISCOPE OF WORK: Resurfacing TO 4,313

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 781 0 1,426CTB Formula: Paving - Federal

0 0 0 0 195 0 158CTB Formula: Paving - Soft Match

0 0 0 0 0 1,753 0CTB Formula: Paving - State

0 0 0 0 976 0 1,753 1,584Total

11/12/2014 709

Page 12: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Interstate

MPO Area

Tri-CitiesInterstate

PROGRAM/SYSTEM

I95/85 SB INTERCHANGE SAFETY

IMPROVEMENTS (PE ONLY)

PROJECT

UPC NO.:

ROUTE:

104956

FO0095

MPO Project. Complete estimate and schedule required.REPORT NOTE:

SCHEDULE ESTIMATED COST (000's)

JURISDICTION:

I95STREET NAME:

PEPetersburg

CN

FROM: I85 TO: WAGNER ROAD (2.3500 MI)DESCRIPTION: RW

PROJECT LENGTH: 2.3500 MISCOPE OF WORK: Safety TO 0

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 160RSTP (STP Regional): MPO - Federal

0 0 0 0 0 0 40RSTP (STP Regional): MPO - State Match

-200 0 0 0 0 0 0 200Total

MPO Area

RichmondInterstate

PROGRAM/SYSTEM

RTE 95 - OVERLAP IMPROVEMENTS

PROJECT

UPC NO.:

ROUTE:

105055

FO0095

HB2 ADJUSTMENT

Revised schedule required.REPORT NOTE:

FY2014

SCHEDULE

9,928

ESTIMATED COST (000's)

JURISDICTION:

STREET NAME:

PERichmond

FY2017 49,842CN

FY2016FROM: I95/64 TO: I95/I64DESCRIPTION: 2,230RW

PROJECT LENGTH: _SCOPE OF WORK: Reconstruction w/o Added Capacity TO 62,000

REQ'D AFTER

2020*FY2020* FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

80 0 0 0 0 0 0RSTP (STP Regional): MPO - Federal

20 0 0 0 0 0 0RSTP (STP Regional): MPO - State Match

61,900 0 0 0 0 100 0 0Total

MPO Area

RichmondInterstate

PROGRAM/SYSTEM

RTE 95 - INTERCHANGE ALTERNATIVES

ANALYSIS AT RTE 54

PROJECT

UPC NO.:

ROUTE:

106215

NFO0095

MPO Project.REPORT NOTE:

FY2015

SCHEDULE

450

ESTIMATED COST (000's)

JURISDICTION:

I-95STREET NAME:

PEAshland

CNFROM: AT RTE 54 INTERCHANGE TO: AT RTE 54

INTERCHANGE

DESCRIPTION: RW

PROJECT LENGTH: _SCOPE OF WORK: Other TO 450

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

160 0 0 0 0 200 0RSTP (STP Regional): MPO - Federal

40 0 0 0 0 50 0RSTP (STP Regional): MPO - State Match

0 0 0 0 0 200 250 0Total

710 11/12/2014

Page 13: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Interstate

MPO Area

RichmondInterstate

PROGRAM/SYSTEM

RTE 95 - INSTALL BARRIER SERVICE

PROJECT

UPC NO.:

ROUTE:

106536

NFO0095

NEW PROJECT

FY2015

SCHEDULE

40

ESTIMATED COST (000's)

JURISDICTION:

0095STREET NAME:

PEChesterfield County

FY2015 275CNFROM: 1.00 MI S RTE 613 (WILLIS RD) INTERCHANGE

TO: 1.23 MI S RTE 613 (WILLIS RD) INTERCHANGE

(0.2300 MI)

DESCRIPTION: RW

PROJECT LENGTH: 0.2300 MISCOPE OF WORK: Safety TO 315

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 216Highway Safety Improvements: Federal

0 0 0 0 0 0 24Highway Safety Improvements: State Match

74 0 0 0 0 0 0 241Total

MPO Area

RichmondInterstate

PROGRAM/SYSTEM

RTE 195 - BRIDGE REPLACEMENT OVER RTE

76, CSX, RAMP S

PROJECT

UPC NO.:

ROUTE:

93087

FO0195

Underway

SCHEDULE

3,751

ESTIMATED COST (000's)

JURISDICTION:

STREET NAME:

PERichmond

FY2017 17,639CNFROM: RTE 195 - BRIDGE REPLACEMENT OVER RTE

76, CSX, RAMP S TO: (0.7 MI W RTE 146) (0.8300 MI)

DESCRIPTION: RW

PROJECT LENGTH: 0.1000 MISCOPE OF WORK: Bridge Replacement w/o Added Capacity TO 21,390

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

1,688 12,439 5,000 200 2,064 0 0CTB Formula: Bridge - State 0

MPO Area

RichmondInterstate

PROGRAM/SYSTEM

RTE 295 - UPGRADE/REPLACE SIGNS - PHASE

1

PROJECT

UPC NO.:

ROUTE:

102708

NFO0295

Complete

SCHEDULE

63

ESTIMATED COST (000's)

JURISDICTION:

STREET NAME:

PERichmond District-wide

Underway 1,262CNDESCRIPTION: RW

PROJECT LENGTH: _SCOPE OF WORK: Safety TO 1,326

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 1,575Open Container Funds: Statewide -249

11/12/2014 711

Page 14: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Interstate

MPO Area

RichmondInterstate

PROGRAM/SYSTEM

RTE 295 - UPGRADE/REPLACE SIGNS - PHASE

2

PROJECT

UPC NO.:

ROUTE:

102954

NFO0295

Complete

SCHEDULE

207

ESTIMATED COST (000's)

JURISDICTION:

STREET NAME:

PERichmond District-wide

Underway 2,409CN

FROM: MP 27.5 TO: MP 41.0 (13.5000 MI)DESCRIPTION: RW

PROJECT LENGTH: 13.5000 MISCOPE OF WORK: Safety TO 2,615

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 3,150Open Container Funds: Statewide -535

MPO Area

RichmondInterstate

PROGRAM/SYSTEM

RTE 295 - UPGRADE/REPLACE SIGNS

PROJECT

UPC NO.:

ROUTE:

102955

NFO0295

Complete

SCHEDULE

127

ESTIMATED COST (000's)

JURISDICTION:

STREET NAME:

PERichmond District-wide

Underway 1,898CN

FROM: MP 41 TO: MP 53 (12.0000 MI)DESCRIPTION: RW

PROJECT LENGTH: 12.0000 MISCOPE OF WORK: Safety TO 2,025

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 3,275Open Container Funds: Statewide -1,250

MPO Area

Multiple MPOsInterstate

PROGRAM/SYSTEM

I-295 RESTORE EXIST. PAVE NB/SB

PROJECT

UPC NO.:

ROUTE:

104467

FO0295

SCHEDULE ESTIMATED COST (000's)

JURISDICTION:

STREET NAME:

PERichmond District-wide

Underway 26,115CN

FROM: MM 20.82 TO: MM 8.46 (12.3600 MI)DESCRIPTION: RW

PROJECT LENGTH: 12.3600 MISCOPE OF WORK: Restoration and Rehabilitation TO 26,115

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

800 0 0 8,480 800 0 268CTB Formula: Paving - Federal

200 0 0 2,120 200 0 30CTB Formula: Paving - Soft Match

0 0 0 0 4,584 400 0CTB Formula: Paving - State

0 0 0 0 6,174 0 0NHPP: Statewide - Federal

0 0 0 0 686 0 0NHPP: Statewide - Soft Match

0 0 0 1,099 0 0 0STP: Statewide - Federal

0 0 0 275 0 0 0STP: Statewide - Soft Match

0 0 0 11,973 12,444 1,000 400 297Total

712 11/12/2014

Page 15: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Interstate

MPO Area

RichmondInterstate

PROGRAM/SYSTEM

RTE 618 (MEADOWVILLE RD) - ADD BRIDGE AT

RTE 295

PROJECT

UPC NO.:

ROUTE:

105057

FO0295

HB2 ADJUSTMENT

FY2018

SCHEDULE

1,000

ESTIMATED COST (000's)

JURISDICTION:

MEADOWVILLE ROADSTREET NAME:

PEChesterfield County

FY2020 12,500CN

OVER RTE 295DESCRIPTION: RW

PROJECT LENGTH: _SCOPE OF WORK: Bridge, New Construction TO 13,500

REQ'D AFTER

2020*FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 0Accounts Receivable: Local 13,500

MPO Area

RichmondInterstate

PROGRAM/SYSTEM

POCAHONTAS PARKWAY - T895 - VDOT

OVERSIGHT

PROJECT

UPC NO.: 92609

NFOBudget Item

FROM: Route 895 TO: Pocahontas ParkwayDESCRIPTION:

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 150Accounts Receivable: Local

0 0 0 0 0 0 150Total

MPO Area

NonMPOInterstate

PROGRAM/SYSTEM

RICHMOND - COMMITTED INTERSTATE

PAVING FUNDS - BALANCE ENTRY

PROJECT

UPC NO.: T13515

NFOBalance Entry

FROM: various TO: variousDESCRIPTION:

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 500 0 0 0NHPP: Statewide - Federal

0 0 0 56 0 0 0NHPP: Statewide - Soft Match

0 0 556 0 0 0 0Total

11/12/2014 713

Page 16: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Primary

MPO Area

RichmondPrimary

PROGRAM/SYSTEM

IMPROVE TRAFFIC OPERATIONS

PROJECT

UPC NO.:

ROUTE:

58911

NFO

MPO Project - Revised schedule required.REPORT NOTE:

FY2020

SCHEDULE

2,100

ESTIMATED COST (000's)

JURISDICTION:

STREET NAME:

PEHenrico County

CNFROM: THRU SIGNALIZATION, TURN LANES AND ITS

ADVANCES TO: AT VARIOUS LOCATIONS

DESCRIPTION: RW

PROJECT LENGTH: 0.0000 MISCOPE OF WORK: Safety TO 2,100

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 876CMAQ: Federal

0 0 0 0 0 0 206CMAQ: State Match

1,019 0 0 0 0 0 0 1,081Total

MPO Area

RichmondPrimary

PROGRAM/SYSTEM

ARRA BRIDGE DESIGN-BUILD CONTRACT

PROJECT

UPC NO.: 92701

NFOARRA09

DESCRIPTION:

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 4,884American Recovery and Reinvestment Act:

Flexible

0 0 0 0 0 0 187(X) Maintenance Funds: Statewide

0 0 0 0 0 0 5,071Total

MPO Area

Tri-CitiesPrimary

PROGRAM/SYSTEM

ARRA HOPEWELL/PRINCE GEORGE 36

CORRIDOR IMPROVEMENTS

PROJECT

UPC NO.: 93209

NFOARRA09

FROM: 0.260 MI W RT144 TO: JEFFERSON PARK RD.

(RTE 630) (0.9420 MI)

DESCRIPTION:

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 9,877American Recovery and Reinvestment Act:

Flexible

0 0 0 0 0 0 60Primary Formula: State

0 0 0 0 0 0 9,937Total

714 11/12/2014

Page 17: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Primary

MPO Area

RichmondPrimary

PROGRAM/SYSTEM

2014 PLANT MIX SCHEDULE ASHLAND NORTH

RESIDENCY (PRIMARY)

PROJECT

UPC NO.:

ROUTE:

104476

NFO

SCHEDULE ESTIMATED COST (000's)

JURISDICTION:

STREET NAME:

PEHanover County

Underway 5,231CN

FROM: VARIOUS TO: VARIOUSDESCRIPTION: RW

PROJECT LENGTH: 0.0000 MISCOPE OF WORK: Resurfacing TO 5,231

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 986 0 0CTB Formula: Paving - Federal

0 0 0 0 247 0 0CTB Formula: Paving - Soft Match

2,877 0 0 0 1,121 0 0CTB Formula: Paving - State

0 0 0 0 0 0 0(X) Maintenance Funds: Statewide

0 0 0 0 2,354 2,877 0 0Total

MPO Area

RichmondPrimary

PROGRAM/SYSTEM

2014 PLANT MIX SCHEDULE CHESTERFIELD

RESIDENCY (PRIMARY)

PROJECT

UPC NO.:

ROUTE:

104482

NFO

SCHEDULE ESTIMATED COST (000's)

JURISDICTION:

STREET NAME:

PEChesterfield County

Underway 5,128CN

FROM: VARIOUS TO: VARIOUSDESCRIPTION: RW

PROJECT LENGTH: 0.0000 MISCOPE OF WORK: Resurfacing TO 5,128

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

618 0 0 0 368 369 0CTB Formula: Paving - Federal

154 0 0 0 92 92 0CTB Formula: Paving - Soft Match

3,435 0 0 0 0 0 0CTB Formula: Paving - State

0 0 0 0 0 0 0(X) Maintenance Funds: Statewide

0 0 0 0 460 4,207 461 0Total

MPO Area

NonMPOPrimary

PROGRAM/SYSTEM

ADA COMPLIANCE

PROJECT

UPC NO.:

ROUTE:

106351

NFO

SCHEDULE ESTIMATED COST (000's)

JURISDICTION:

STREET NAME:

PERichmond District-wide

FY2015 500CN

FROM: various TO: variousDESCRIPTION: RW

PROJECT LENGTH: _SCOPE OF WORK: Facilities for Pedestrians and Bicycles TO 500

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 572Bond Proceeds: CPR Bonds -72

11/12/2014 715

Page 18: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Primary

MPO Area

RichmondPrimary

PROGRAM/SYSTEM

RTE 1 - BR REPLACEMENT & MOD LTL @

DSCR

PROJECT

UPC NO.:

ROUTE:

15988

NFO0001

Revised schedule required.REPORT NOTE:

Underway

SCHEDULE

2,731

ESTIMATED COST (000's)

JURISDICTION:

JEFFERSON DAVIS HIGHWAYSTREET NAME:

PEChesterfield County

FY2014 15,833CN

UnderwayFROM: Intersection w/ Rte. 145 (Chester Road) TO: 0.351

Miles North of Rte. 145 (Chester Road) (0.3510 MI)

DESCRIPTION: 1,823RW

28526 -2PROJECT LENGTH: 0.3510 MI STRUCTURE NO.: SUFFICIENCY RATING:

SCOPE OF WORK: Bridge Replacement w/o Added Capacity TO 20,387

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 1,328Bridge Replacement: Federal

0 0 0 0 0 0 664Concession Funds: State

1,681 0 0 0 0 0 0CTB Formula: Bridge - State

0 0 0 51 0 0 0CTB Formula: High Priority - State

0 0 0 0 0 0 5,908NHPP: Bridge - Federal

0 0 0 0 0 0 1,477NHPP: Bridge - Soft Match

0 0 0 0 0 0 389Primary Formula: Federal

0 0 0 0 0 0 255Primary Formula: State

0 0 0 0 0 0 97Primary Formula: State Match

0 0 0 0 0 0 1,410Priority Transportation Funds: State

0 0 0 0 0 0 103Residue Parcel Revenue: State

0 0 0 0 0 0 317Revenue Sharing Funds: Local Match

0 0 0 0 0 0 317Revenue Sharing Funds: State Match

0 0 0 0 0 0 332Soft Match: Federal

102 0 0 812 882 100 0STP: Bridge - Federal

26 0 0 203 220 25 0STP: Bridge - Soft Match

1,814 0 0 252 8 755 120STP: Statewide - Federal

454 0 0 63 2 189 30STP: Statewide - Soft Match

0 0 0 1,381 1,112 4,077 1,069 12,748Total

MPO Area

Tri-CitiesPrimary

PROGRAM/SYSTEM

RTE 1 - INTERSECTION IMPROVEMENT

PROJECT

UPC NO.:

ROUTE:

73268

NFO0001

MPO Project.REPORT NOTE:

Underway

SCHEDULE

530

ESTIMATED COST (000's)

JURISDICTION:

Boydton Plank RoadSTREET NAME:

PEDinwiddie County

FY2015 1,408CN

UnderwayFROM: On Rte 226, 0.041 Mile East of Rte 600 TO:

Intersection Rte 1 (0.1350 MI)

DESCRIPTION: 922RW

PROJECT LENGTH: 0.1350 MISCOPE OF WORK: Reconstruction w/o Added Capacity TO 2,860

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 1,950RSTP (STP Regional): Federal

0 0 0 0 0 0 910RSTP (STP Regional): State Match

0 0 0 0 0 0 0 2,860Total

716 11/12/2014

Page 19: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Primary

MPO Area

Tri-CitiesPrimary

PROGRAM/SYSTEM

RTE 1 - INSTALL NB RTL

PROJECT

UPC NO.:

ROUTE:

90367

NFO0001

MPO Project.REPORT NOTE:

Underway

SCHEDULE

135

ESTIMATED COST (000's)

JURISDICTION:

JEFFERSON DAVIS HIGHWAYSTREET NAME:

PEChesterfield County

FY2015 341CN

FY2015FROM: 0.10 MI S RTE 620 (WOODS EDGE RD) TO:

RTE 620 (WOODS EDGE RD) (0.1000 MI)

DESCRIPTION: 300RW

PROJECT LENGTH: 0.1000 MISCOPE OF WORK: Safety TO 776

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 293CMAQ: Federal

0 0 0 0 214 0 108CMAQ: MPO - Federal

0 0 0 0 53 0 31CMAQ: MPO - State Match

0 0 0 0 0 0 77CMAQ: State Match

0 0 0 0 267 0 0 509Total

MPO Area

Tri-CitiesPrimary

PROGRAM/SYSTEM

RTE 1 SOUTH - BRIDGE REPLACEMENT OVER

CSX RW

PROJECT

UPC NO.:

ROUTE:

93094

NFO0001

Complete

SCHEDULE

850

ESTIMATED COST (000's)

JURISDICTION:

BOYDTON PLANK ROAD S.STREET NAME:

PEDinwiddie County

Underway 5,526CN

UnderwayFROM: 0.19 MI. NORTH RTE. 657 W. TO: 0.61 MI.

NORTH RTE. 657 W. (0.5900 MI)

DESCRIPTION: 223RW

29850 -1PROJECT LENGTH: 0.5900 MI STRUCTURE NO.: SUFFICIENCY RATING:

SCOPE OF WORK: Bridge Replacement w/o Added Capacity TO 6,599

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 80Bond Match: State Bond Match

0 0 0 0 0 0 453Bridge Replacement: Federal

0 0 0 0 0 0 33Soft Match: Federal

2,785 0 0 1,235 426 380 0STP: Bridge - Federal

696 0 0 309 107 95 0STP: Bridge - Soft Match

0 0 0 1,544 533 3,482 475 566Total

MPO Area

RichmondPrimary

PROGRAM/SYSTEM

RTE 1 - IMPROVE INTERSECTION

PROJECT

UPC NO.:

ROUTE:

101021

NFO0001

MPO Project. Excess funds to be redistributed by MPO.REPORT NOTE:

Complete

SCHEDULE

1,095

ESTIMATED COST (000's)

JURISDICTION:

Jefferson Davis HighwaySTREET NAME:

PEChesterfield County

Underway 3,084CN

UnderwayFROM: 0.18 Mi. S. Int. Route 1/Route 618 TO: 0.25 Mi. N.

Int. Route 1/Route 618 (0.4400 MI)

DESCRIPTION: 858RW

PROJECT LENGTH: 0.4400 MISCOPE OF WORK: Safety TO 5,036

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 1,180Local Project Contributions: Local

0 0 0 0 0 0 800RSTP (STP Regional): Federal

0 0 0 0 0 1,600 800RSTP (STP Regional): MPO - Federal

0 0 0 0 0 400 200RSTP (STP Regional): MPO - State Match

0 0 0 0 0 0 200RSTP (STP Regional): State Match

-144 0 0 0 0 0 2,000 3,180Total

11/12/2014 717

Page 20: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Primary

MPO Area

NonMPOPrimary

PROGRAM/SYSTEM

RTE 1 - ADD TRAFFIC SIGNAL AND TURN

LANES

PROJECT

UPC NO.:

ROUTE:

104661

NFO0001

Underway

SCHEDULE

1,000

ESTIMATED COST (000's)

JURISDICTION:

JFFERSON DAVIS HIGHWAYSTREET NAME:

PEChesterfield County

FY2017 4,500CN

FY2015FROM: 0.154 MI S RTE 620 (WOODS EDGE RD) TO:

0.082 MI N RTE 619 (HAPPY HII RD) (0.3870 MI)

DESCRIPTION: 1,500RW

PROJECT LENGTH: 0.3870 MISCOPE OF WORK: Safety TO 7,000

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

2,025 0 0 0 2,025 1,350 900Highway Safety Improvements: Federal

225 0 0 0 225 150 100Highway Safety Improvements: Soft Match

0 0 0 0 2,250 2,250 1,500 1,000Total

MPO Area

RichmondPrimary

PROGRAM/SYSTEM

RTE 1 - UPGRADE SIGNAL TO PROVIDE

PEDESTRIAN ACCOMMODATION

PROJECT

UPC NO.:

ROUTE:

104665

NFO0001

Underway

SCHEDULE

200

ESTIMATED COST (000's)

JURISDICTION:

BROOK ROADSTREET NAME:

PEHenrico County

FY2017 500CN

FY2015FROM: 0.14 MI N VILLA PARK DR TO: 0.152 MI S VILLA

PARK DR (0.2920 MI)

DESCRIPTION: 150RW

PROJECT LENGTH: 0.2920 MISCOPE OF WORK: Safety TO 850

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 450 315Highway Safety Improvements: Federal

0 0 0 0 0 50 35Highway Safety Improvements: Soft Match

0 0 0 0 0 0 500 350Total

MPO Area

NonMPOPrimary

PROGRAM/SYSTEM

RTE 5 - VIRGNIA CAPITAL TRAIL - SHERWOOD

FOREST PHASE

PROJECT

UPC NO.:

ROUTE:

81562

NFO0005

VA Capital Trail Project.REPORT NOTE:

Underway

SCHEDULE

1,496

ESTIMATED COST (000's)

JURISDICTION:

Virginia Capital TrailSTREET NAME:

PECharles City County

Underway 11,364CN

UnderwayFROM: 2.26 Miles East of the Charles City Courthouse

TO: 0.4 miles west of the Chickahominy River (10.4000

MI)

DESCRIPTION: 239RW

29455,29456,29457,29458,29459,29460,29473,29474,29475,29476,29477,29478,29479,29480-1PROJECT LENGTH: 10.4000 MI STRUCTURE NO.: SUFFICIENCY RATING:

SCOPE OF WORK: Facilities for Pedestrians and Bicycles TO 13,099

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 674 0NHPP: Statewide - Federal

0 0 0 0 0 169 0NHPP: Statewide - Soft Match

0 0 0 0 0 0 10,068Open Container Funds: Statewide

0 0 0 0 0 0 138State: State Match

0 0 0 0 0 0 2,050Transportation Enhancement Funds:

Federal

0 0 0 0 0 0 843 12,256Total

718 11/12/2014

Page 21: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Primary

MPO Area

RichmondPrimary

PROGRAM/SYSTEM

RTE 5 - VIRGINIA CAPITAL TRAIL - NEW

MARKET HEIGHTS PHASE

PROJECT

UPC NO.:

ROUTE:

86279

NFO0005

VA Capital Trail Project. PE only; RW phase on UPC 93199; CN phase on UPC 102793.REPORT NOTE:

Underway

SCHEDULE

1,510

ESTIMATED COST (000's)

JURISDICTION:

Virginia Capital TrailSTREET NAME:

PERichmond District-wide

CN

FY2012FROM: Long Bridge Road TO: Rte 658 - Kimages Rd

(10.5000 MI)

DESCRIPTION: 0RW

PROJECT LENGTH: 10.5000 MISCOPE OF WORK: Safety TO 1,510

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 1,581Open Container Funds: Statewide -71

MPO Area

RichmondPrimary

PROGRAM/SYSTEM

RTE 5 - VIRGINIA CAPITAL TRAIL - VARINA

PHASE

PROJECT

UPC NO.:

ROUTE:

86280

NFO0005

VA Capital Trail Project.REPORT NOTE:

Underway

SCHEDULE

2,323

ESTIMATED COST (000's)

JURISDICTION:

VIRGINIA CAPITAL TRAIL - VARINA PHASESTREET NAME:

PEHenrico County

Underway 10,154CN

UnderwayFROM: FR 0.52 MI W ALMOND CR TO 0.10 MI E WOOD

MILL RD TO: FR 0.16 MI W FOURMILE CR TO 0.14 MI W

LONG BRIDGE RD (8.0850 MI)

DESCRIPTION: 1,009RW

PROJECT LENGTH: 8.0850 MISCOPE OF WORK: Facilities for Pedestrians and Bicycles TO 13,486

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 440Open Container Funds: Bike/Ped

0 0 0 0 0 0 12,368Open Container Funds: Statewide

0 0 0 0 0 0 135State: State Match

0 0 0 0 0 0 542Transportation Enhancement Funds:

Federal

0 0 0 0 0 0 0 13,486Total

MPO Area

RichmondPrimary

PROGRAM/SYSTEM

VIRGINIA CAPITAL TRAIL - RICHMOND EAST

PROJECT

UPC NO.:

ROUTE:

86429

NFO0005

VA Capital Trail Project. Revised schedule required.REPORT NOTE:

Underway

SCHEDULE

200

ESTIMATED COST (000's)

JURISDICTION:

VIRGINIA CAPITAL TRAILSTREET NAME:

PERichmond District-wide

FY2014 1,144CN

FROM: Ash Street TO: Henrico County Line (0.5800 MI)DESCRIPTION: RW

PROJECT LENGTH: 0.5000 MISCOPE OF WORK: Facilities for Pedestrians and Bicycles TO 1,344

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 463Open Container Funds: Statewide

0 0 0 0 0 0 970Primary Formula: Federal/State

-89 0 0 0 0 0 0 1,433Total

11/12/2014 719

Page 22: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Primary

MPO Area

RichmondPrimary

PROGRAM/SYSTEM

RTE 5 - VIRGINIA CAPITAL TRAIL- CHARLES

CITY COURTHOUSE EAST

PROJECT

UPC NO.:

ROUTE:

91931

NFO0005

VA Capital Trail Project. Complete estimate and schedule requiredREPORT NOTE:

Underway

SCHEDULE

292

ESTIMATED COST (000's)

JURISDICTION:

Virginia Capital TrailSTREET NAME:

PECharles City County

Underway 0CN

FY2011FROM: 0.10 Mile South of Intersection Rte 5 & Rte 644

TO: 2.26 Mile East of Charles City Courthouse (2.3640 MI)

DESCRIPTION: 0RW

29451,29452,29453,29454 -1PROJECT LENGTH: 2.3640 MI STRUCTURE NO.: SUFFICIENCY RATING:

SCOPE OF WORK: Facilities for Pedestrians and Bicycles TO 292

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 470Open Container Funds: Statewide -178

MPO Area

RichmondPrimary

PROGRAM/SYSTEM

RTE 5 - VIRGINIA CAPITAL TRAIL - PARK

PHASE

PROJECT

UPC NO.:

ROUTE:

103665

NFO0005

VA Capital Trail Project.REPORT NOTE:

Underway

SCHEDULE

628

ESTIMATED COST (000's)

JURISDICTION:

Virginia Capital TrailSTREET NAME:

PEHenrico County

Underway 6,957CN

UnderwayFROM: 0.10 MI E WOODMILL DR TO: 0.22 MI W ROCKY

HILL FARM DR (3.5000 MI)

DESCRIPTION: 125RW

PROJECT LENGTH: 3.5000 MISCOPE OF WORK: Facilities for Pedestrians and Bicycles TO 7,710

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 7,710Open Container Funds: Statewide 0

MPO Area

RichmondPrimary

PROGRAM/SYSTEM

RTE 6 - IMPROVE INTERSECTION

PROJECT

UPC NO.:

ROUTE:

101034

NFO0006

HB2 ADJUSTMENT

MPO Project. Balance of funds to be provided for by MPO.REPORT NOTE:

Underway

SCHEDULE

2,400

ESTIMATED COST (000's)

JURISDICTION:

PATTERSON AVENUESTREET NAME:

PEHenrico County

FY2019 6,600CN

FY2017FROM: 0.27 MI W RTE 7518 (PARHAM RD) TO: 0.42 MI

E RTE 7518 (PARHAM RD) (0.6900 MI)

DESCRIPTION: 5,000RW

PROJECT LENGTH: 0.6900 MISCOPE OF WORK: Safety TO 14,000

REQ'D AFTER

2020*FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 50Bond Proceeds: CPR Bonds

0 1,600 2,400 0 0 0 0CMAQ: MPO - Federal

0 400 600 0 0 0 0CMAQ: MPO - State Match

0 0 0 0 0 0 1,920RSTP (STP Regional): Federal

0 0 0 0 0 0 480RSTP (STP Regional): State Match

6,550 2,000 3,000 0 0 0 0 2,450Total

720 11/12/2014

Page 23: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Primary

MPO Area

RichmondPrimary

PROGRAM/SYSTEM

RTE 10 - UPGRADE SIGNALS - 4 INT

PROJECT

UPC NO.:

ROUTE:

77071

NFO0010

MPO Project.REPORT NOTE:

Complete

SCHEDULE

98

ESTIMATED COST (000's)

JURISDICTION:

Iron Bridge RoadSTREET NAME:

PEChesterfield County

Underway 316CNFROM: Beach Road (Rte 655) TO: Chesterfield Meadows

Road (Rte 929) (0.6402 MI)

DESCRIPTION: RW

PROJECT LENGTH: 0.6402 MISCOPE OF WORK: Safety TO 414

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 160CMAQ: Federal

0 0 0 0 0 0 40CMAQ: State Match

0 0 0 0 0 0 115(X) Maintenance Funds: Federal

0 0 0 0 0 0 99(X) Maintenance Funds: Statewide

0 0 0 0 0 0 0 415Total

MPO Area

RichmondPrimary

PROGRAM/SYSTEM

ARRA - CHESTERFIELD - RTE 10 - WIDEN TO

SIX LANES

PROJECT

UPC NO.: 94857

FOARRA09

PE on UPC 80529, ARRA UPC 94857, ARRA-C UPC 95574REPORT NOTE:

FROM: I-95 TO: WARE BOTTOM SPRINGS ROAD

(1.0100 MI)

DESCRIPTION:

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 10,394American Recovery and Reinvestment Act:

Urbanized Area > 200K

0 0 0 0 0 0 286CMAQ: Federal

0 0 0 0 0 0 15CMAQ: State Match

0 0 0 0 0 0 245Demonstration Funds: Federal

0 0 0 0 0 0 11,000Local Project Contributions: Local

0 0 0 0 0 0 436Non-Formula: State Match

0 0 0 0 0 0 640Primary Formula: Federal

0 0 0 0 0 0 585Primary Formula: State

0 0 0 0 0 0 160Primary Formula: State Match

0 0 0 0 0 0 2,058RSTP (STP Regional): Federal

0 0 0 0 0 0 78RSTP (STP Regional): State Match

0 0 0 0 0 0 716SAFETEA-LU Earmarks: Federal

0 0 0 0 0 0 179SAFETEA-LU Earmarks: State Match

0 0 0 0 0 0 26,793Total

11/12/2014 721

Page 24: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Primary

MPO Area

RichmondPrimary

PROGRAM/SYSTEM

RTE 10 - MAJOR WIDENING

PROJECT

UPC NO.:

ROUTE:

101020

FO0010

HB2 ADJUSTMENT

MPO Project. Revised schedule required. Balance to be provided by MPO.REPORT NOTE:

Underway

SCHEDULE

2,100

ESTIMATED COST (000's)

JURISDICTION:

WEST HNDRD/Meadowville/OLD BERMUDA HNDRD/RvrsBndSTREET NAME:

PEChesterfield County

FY2019 35,860CN

FY2015FROM: 1.73 mi. W of Rte. 618 (OLD BERMUDA

HUNDRED RD) TO: 0.27 mi. E of Rte. 618 (OLD

BERMUDA HUNDRED ROAD) (2.0000 MI)

DESCRIPTION: 7,250RW

PROJECT LENGTH: 2.0000 MISCOPE OF WORK: Reconstruction w/ Added Capacity TO 45,210

REQ'D AFTER

2020*FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 6,412Bond Proceeds: CPR Bonds

0 0 0 0 0 0 8Non-Formula: State Match

0 0 0 0 0 0 589RSTP (STP Regional): Federal

0 0 0 8,000 3,300 0 0RSTP (STP Regional): MPO - Federal

0 0 0 2,000 825 0 0RSTP (STP Regional): MPO - State Match

0 0 0 0 0 0 139RSTP (STP Regional): State Match

23,937 0 0 10,000 4,125 0 0 7,148Total

MPO Area

RichmondPrimary

PROGRAM/SYSTEM

RTE 10 - WIDEN TO 6 LANES

PROJECT

UPC NO.:

ROUTE:

102952

NFO0010

MPO Project.REPORT NOTE:

Underway

SCHEDULE

800

ESTIMATED COST (000's)

JURISDICTION:

WEST HUNDRED ROADSTREET NAME:

PEChesterfield County

FY2018 4,200CN

FY2016FROM: RTE 1 TO: RTE 95 (0.3500 MI)DESCRIPTION: 3,000RW

PROJECT LENGTH: 0.3500 MISCOPE OF WORK: Reconstruction w/ Added Capacity TO 8,000

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 2,000Revenue Sharing Funds: Local Match

0 0 0 0 0 0 2,000Revenue Sharing Funds: State Match

1,200 0 0 0 1,600 0 400RSTP (STP Regional): MPO - Federal

300 0 0 0 400 0 100RSTP (STP Regional): MPO - State Match

0 0 0 0 2,000 1,500 0 4,500Total

722 11/12/2014

Page 25: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Primary

MPO Area

RichmondPrimary

PROGRAM/SYSTEM

RTE 10 - UPGRADE CROSSWALKS

PROJECT

UPC NO.:

ROUTE:

102957

NFO0010

MPO Project. Revised schedule required.REPORT NOTE:

Underway

SCHEDULE

127

ESTIMATED COST (000's)

JURISDICTION:

WEST HUNDRED ROADSTREET NAME:

PEChesterfield County

FY2014 600CNFROM: RTE 616 (OSBORNE RD) TO: CHESTERTOWNE

RD (1.0000 MI)

DESCRIPTION: RW

PROJECT LENGTH: 1.0000 MISCOPE OF WORK: Facilities for Pedestrians and Bicycles TO 727

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 304CMAQ: Federal

0 0 0 0 0 0 160CMAQ: MPO - Federal

0 0 0 0 0 0 40CMAQ: MPO - State Match

0 0 0 0 0 0 76CMAQ: State Match

0 0 0 0 0 0 100Revenue Sharing Funds: Local Match

0 0 0 0 0 0 100Revenue Sharing Funds: State Match

-52 0 0 0 0 0 0 779Total

MPO Area

RichmondPrimary

PROGRAM/SYSTEM

RTE 10 - PROVIDE BICYCLE

ACCOMMODATIONS

PROJECT

UPC NO.:

ROUTE:

104662

NFO0010

Underway

SCHEDULE

200

ESTIMATED COST (000's)

JURISDICTION:

IRONBRIDGE ROADSTREET NAME:

PEChesterfield County

FY2015 2,300CNFROM: RTE 749 (WOMACK RD) TO: 0.134 MI W RTE 1

(JEFFERSON DAVIS HWY) (2.4600 MI)

DESCRIPTION: RW

PROJECT LENGTH: 2.4600 MISCOPE OF WORK: Safety TO 2,500

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 2,070 180Highway Safety Improvements: Federal

0 0 0 0 0 230 20Highway Safety Improvements: Soft Match

0 0 0 0 0 0 2,300 200Total

MPO Area

RichmondPrimary

PROGRAM/SYSTEM

RT 10 - WIDENING

PROJECT

UPC NO.:

ROUTE:

104889

NFO0010

MPO Project. Balance of funds to be provided for by MPO.REPORT NOTE:

FY2019

SCHEDULE

1,300

ESTIMATED COST (000's)

JURISDICTION:

IRONBRIDGE ROADSTREET NAME:

PEChesterfield County

FY2024 8,700CN

FY2021FROM: WHITEPINE ROAD TO: FRITH LANE (1.3500 MI)DESCRIPTION: 2,000RW

PROJECT LENGTH: 1.3500 MISCOPE OF WORK: Reconstruction w/ Added Capacity TO 12,000

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 1,040 0 0 0 0RSTP (STP Regional): MPO - Federal

0 0 260 0 0 0 0RSTP (STP Regional): MPO - State Match

10,700 0 1,300 0 0 0 0 0Total

11/12/2014 723

Page 26: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Primary

MPO Area

NonMPOPrimary

PROGRAM/SYSTEM

RTE 13 - REPLACE BRIDGE

PROJECT

UPC NO.:

ROUTE:

105108

NFO0013

Revised schedule requiredREPORT NOTE:

Underway

SCHEDULE

500

ESTIMATED COST (000's)

JURISDICTION:

Old Bucking Ham RoadSTREET NAME:

PEPowhatan County

FY2017 972CN

FY2016DESCRIPTION: 322RW

PROJECT LENGTH: _SCOPE OF WORK: Bridge Replacement w/o Added Capacity TO 1,794

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 218 439 396 200 182 0STP: Bridge - Federal

0 54 110 99 50 46 0STP: Bridge - Soft Match

0 272 549 495 250 0 228 0Total

MPO Area

RichmondPrimary

PROGRAM/SYSTEM

REALIGN INTERSECTION OF RTE 33 & RTE 54

PROJECT

UPC NO.:

ROUTE:

18948

NFO0033

MPO Project.REPORT NOTE:

Complete

SCHEDULE

1,140

ESTIMATED COST (000's)

JURISDICTION:

MOUNTAIN RDSTREET NAME:

PEHanover County

Underway 2,894CN

UnderwayFROM: 0.337 MILE WEST RELOC. RTE 54 TO: 0.174

MILE EAST RELOC. RTE 54 (0.5110 MI)

DESCRIPTION: 1,562RW

PROJECT LENGTH: 0.5110 MISCOPE OF WORK: Safety TO 5,596

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 2,094CMAQ: Federal

0 0 0 0 0 0 853CMAQ: State Match

0 0 0 0 0 0 574Non-Formula: State Match

0 0 0 0 0 0 8Primary Formula: State

0 0 0 0 0 0 2,713RSTP (STP Regional): Federal

0 0 0 0 0 0 104RSTP (STP Regional): State Match

-750 0 0 0 0 0 0 6,346Total

724 11/12/2014

Page 27: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Primary

MPO Area

RichmondPrimary

PROGRAM/SYSTEM

RTE 33 - INTERSECTION IMPROVEMENT AT

RTE 623

PROJECT

UPC NO.:

ROUTE:

56181

FO0033

MPO Project. Excess funds to be redistributed by MPO.REPORT NOTE:

Underway

SCHEDULE

1,610

ESTIMATED COST (000's)

JURISDICTION:

STREET NAME:

PEHanover County

FY2017 4,788CN

UnderwayFROM: 0.05 MI S RTE 623 (ASHLAND RD) TO: 0.05 MI N

RTE 623 (ASHLAND RD) (0.1000 MI)

DESCRIPTION: 1,250RW

PROJECT LENGTH: 0.1000 MISCOPE OF WORK: Reconstruction w/ Added Capacity TO 7,648

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 5CMAQ: Federal

0 0 494 1,180 0 0 0CMAQ: MPO - Federal

0 0 124 295 0 0 0CMAQ: MPO - State Match

0 0 0 0 0 0 1CMAQ: State Match

0 0 0 0 0 0 1,914Primary Formula: Federal

0 0 0 0 0 0 2,750Primary Formula: State

0 0 0 0 0 0 478Primary Formula: State Match

0 0 0 0 0 0 502Priority Transportation Funds: State

-95 0 618 1,475 0 0 0 5,650Total

MPO Area

Tri-CitiesPrimary

PROGRAM/SYSTEM

RTE 36 - IMPROVEMENTS AT FT. LEE

ENTRANCE

PROJECT

UPC NO.:

ROUTE:

104697

NFO0036

MPO Project.REPORT NOTE:

Underway

SCHEDULE

210

ESTIMATED COST (000's)

JURISDICTION:

OAKLAWN BOULEVARDSTREET NAME:

PEPrince George County

FY2016 911CN

FY2015FROM: SIEGE RD TO: 19TH ST (0.5700 MI)DESCRIPTION: 750RW

PROJECT LENGTH: 0.5700 MISCOPE OF WORK: Reconstruction w/o Added Capacity TO 1,871

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 1,778Demonstration Funds: Federal

75 0 0 0 0 0 0RSTP (STP Regional): MPO - Federal

19 0 0 0 0 0 0RSTP (STP Regional): MPO - State Match

0 0 0 0 0 93 0 1,778Total

MPO Area

NonMPOPrimary

PROGRAM/SYSTEM

RTE 40 - RECONSTRUCT SIDEWALK AND

PAVING

PROJECT

UPC NO.:

ROUTE:

104276

NFO0040

Underway

SCHEDULE

5

ESTIMATED COST (000's)

JURISDICTION:

S MAIN STREETSTREET NAME:

PEBlackstone

FY2017 93CNFROM: BAPTIST CHURCH @ IRVIN ST TO: CHURCH ST

(0.0800 MI)

DESCRIPTION: RW

PROJECT LENGTH: 0.0800 MISCOPE OF WORK: Safety TO 98

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 49Revenue Sharing Funds: Local Match

0 0 0 0 0 0 49Revenue Sharing Funds: State Match

0 0 0 0 0 0 0 98Total

11/12/2014 725

Page 28: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Primary

MPO Area

NonMPOPrimary

PROGRAM/SYSTEM

RTE 46 - BRIDGE REPLACEMENT

PROJECT

UPC NO.:

ROUTE:

18949

NFO0046

Complete

SCHEDULE

928

ESTIMATED COST (000's)

JURISDICTION:

Christanna HighwaySTREET NAME:

PEBrunswick County

Underway 6,350CN

UnderwayFROM: 0.283 mi South of Meherrin River TO: 0.342 mi

North of Meherrin River (0.6250 MI)

DESCRIPTION: 266RW

3582,27387 -2,91PROJECT LENGTH: 0.6250 MI STRUCTURE NO.: SUFFICIENCY RATING:

SCOPE OF WORK: Bridge Replacement w/o Added Capacity TO 7,544

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 835Bond Match: State Bond Match

0 0 0 0 0 0 2,863Bridge Replacement: Federal

0 0 0 0 0 0 971Federal STP: Federal

0 0 0 0 0 0 670Primary Formula: Federal

0 0 0 0 0 0 200Primary Formula: Federal/State

0 0 0 0 0 0 313Primary Formula: State

0 0 0 0 0 0 167Primary Formula: State Match

0 0 0 0 0 0 61Priority Transportation Funds: State

0 0 0 0 0 0 22Residue Parcel Revenue: State

0 0 0 0 0 0 123Soft Match: Federal

0 0 0 0 0 0 1,054STP: Statewide - Federal

0 0 0 0 0 0 263STP: Statewide - Soft Match

0 0 0 0 0 0 0 7,544Total

MPO Area

NonMPOPrimary

PROGRAM/SYSTEM

RTE 46 - REPLACE BRIDGE OVER NOTTOWAY

RIVER (SPILLWAY)

PROJECT

UPC NO.:

ROUTE:

93093

NFO0046

Underway

SCHEDULE

1,100

ESTIMATED COST (000's)

JURISDICTION:

BRUNSWICK ROADSTREET NAME:

PEBrunswick County

FY2017 10,564CN

FY2015FROM: 1.326 MI N RTE 615 (CEDAR CREEK RD) TO:

0.266 MI S RTE 645 (JONESBORO RD) (0.8920 MI)

DESCRIPTION: 450RW

29538 -1PROJECT LENGTH: 0.8920 MI STRUCTURE NO.: SUFFICIENCY RATING:

SCOPE OF WORK: Bridge Replacement w/o Added Capacity TO 12,114

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 63Bond Match: State Bond Match

0 0 0 0 0 0 382Bridge Replacement: Federal

0 2,239 487 0 0 0 0CTB Formula: Bridge - State

0 0 0 0 0 0 498NHPP: Bridge - Federal

0 0 0 0 0 0 125NHPP: Bridge - Soft Match

0 0 0 0 0 0 33Soft Match: Federal

180 5,008 1,000 283 139 20 0STP: Bridge - Federal

45 1,252 250 71 35 5 0STP: Bridge - Soft Match

0 8,499 1,737 354 174 225 25 1,100Total

726 11/12/2014

Page 29: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Primary

MPO Area

RichmondPrimary

PROGRAM/SYSTEM

RTE 54 - IMPROVE INTERSECTION

PROJECT

UPC NO.:

ROUTE:

104275

NFO0054

Underway

SCHEDULE

141

ESTIMATED COST (000's)

JURISDICTION:

E PATRICK HENRY ROADSTREET NAME:

PEHanover County

FY2016 1,170CN

FY2015AT WOODSIDE LNDESCRIPTION: 330RW

PROJECT LENGTH: _SCOPE OF WORK: Safety TO 1,641

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 141Local Project Contributions: Local

0 0 0 0 0 0 750Revenue Sharing Funds: Local Match

0 0 0 0 0 0 750Revenue Sharing Funds: State Match

0 0 0 0 0 0 0 1,641Total

MPO Area

NonMPOPrimary

PROGRAM/SYSTEM

RTE 58 - OUTSTANDING R/W & CN

PROJECT

UPC NO.: 68973

NFOProject Report Req'd

FROM: DISTRICTWIDE (UPC'S 9879, 9880, 9882, 9883,

11314, 13734, TO: 13835, 16093, 10178, 15538, 50434 &

50435)

DESCRIPTION:

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 1,234Bond Proceeds: Rt 58 Bond CDP Funds

MPO Area

RichmondPrimary

PROGRAM/SYSTEM

RTE 60 - UPGRADE SIGNALS AT VARIOUS

LOCATIONS

PROJECT

UPC NO.:

ROUTE:

101019

NFO0060

Complete

SCHEDULE

127

ESTIMATED COST (000's)

JURISDICTION:

MIDLOTHIAN TURNPIKESTREET NAME:

PEChesterfield County

Underway 625CN

UnderwayFROM: 0.054 MI,. W. STONEBRIDGE PLAZA AVE TO:

0.114 MI. E. STONEBRIDGE PLAZA AVE (0.1670 MI)

DESCRIPTION: 167RW

PROJECT LENGTH: 0.1670 MISCOPE OF WORK: Safety TO 919

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 885Highway Safety Improvements: Federal

0 0 0 0 0 0 98Highway Safety Improvements: State Match

-64 0 0 0 0 0 0 983Total

11/12/2014 727

Page 30: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Primary

MPO Area

RichmondPrimary

PROGRAM/SYSTEM

RTE 60 - WIDEN TO 6 LANES

PROJECT

UPC NO.:

ROUTE:

102959

NFO0060

MPO Project. Excess funds to be redistributed by MPO.REPORT NOTE:

Underway

SCHEDULE

1,750

ESTIMATED COST (000's)

JURISDICTION:

MIDLOTHIAN TURNPIKESTREET NAME:

PEChesterfield County

FY2017 12,785CN

FY2015FROM: Rte. 727 (ALVERSER DR) TO: Rte. 677 (OLD

BUCKINGHAM RD) (1.2500 MI)

DESCRIPTION: 2,400RW

5014,5015 86,96PROJECT LENGTH: 1.2500 MI STRUCTURE NO.: SUFFICIENCY RATING:

SCOPE OF WORK: Reconstruction w/ Added Capacity TO 16,935

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 6,451Revenue Sharing Funds: Local Match

0 0 0 0 0 0 6,451Revenue Sharing Funds: State Match

1,600 0 0 0 0 1,200 480RSTP (STP Regional): MPO - Federal

400 0 0 0 0 300 120RSTP (STP Regional): MPO - State Match

-67 0 0 0 0 2,000 1,500 13,502Total

MPO Area

RichmondPrimary

PROGRAM/SYSTEM

RTE 60 - ADD DUAL LEFT TURN LANES AT RTE

645 (BRANCHWAY RD)

PROJECT

UPC NO.:

ROUTE:

103576

NFO0060

MPO Project.REPORT NOTE:

Complete

SCHEDULE

120

ESTIMATED COST (000's)

JURISDICTION:

MIDLOTHIAN TURNPIKESTREET NAME:

PEChesterfield County

Underway 733CNFROM: 0.043 MI EAST OF HUGUENOT RD. (RTE. 147)

TO: 0.147 MI EAST OF HUGUENOT RD. (RTE. 147)

(0.1040 MI)

DESCRIPTION: RW

PROJECT LENGTH: 0.1040 MISCOPE OF WORK: Safety TO 853

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 400CMAQ: MPO - Federal

0 0 0 0 0 0 100CMAQ: MPO - State Match

0 0 0 0 0 0 31Non-Formula: State Match

0 0 0 0 0 0 282RSTP (STP Regional): Federal

0 0 0 0 0 0 40RSTP (STP Regional): State Match

0 0 0 0 0 0 0 853Total

MPO Area

RichmondPrimary

PROGRAM/SYSTEM

I64 CORR TECH US 60, SIGNAL COMM CAM -

JAMES CTY TO HENRICO

PROJECT

UPC NO.:

ROUTE:

105444

NFO0060

Underway

SCHEDULE

180

ESTIMATED COST (000's)

JURISDICTION:

STREET NAME:

PERichmond District-wide

CNFROM: Richmond Corp Limits TO: James City CL

(29.3300 MI)

DESCRIPTION: RW

PROJECT LENGTH: 29.3300 MISCOPE OF WORK: Safety TO 180

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

120 0 0 0 0 60 0CTB Formula: ITS - State 0

728 11/12/2014

Page 31: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Primary

MPO Area

RichmondPrimary

PROGRAM/SYSTEM

RTE 60 CORRIDOR EAST SPECIAL AREA PLAN

- POWHATAN CO

PROJECT

UPC NO.:

ROUTE:

106217

NFO0060

MPO Project.REPORT NOTE:

FY2015

SCHEDULE

150

ESTIMATED COST (000's)

JURISDICTION:

ANDERSON HIGHWAYSTREET NAME:

PEPowhatan County

CNFROM: RTE 678 (ROCKY OAK RD) TO: CHESTERFIELD

CO LN (6.6100 MI)

DESCRIPTION: RW

PROJECT LENGTH: _SCOPE OF WORK: Other TO 150

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 120 0RSTP (STP Regional): MPO - Federal

0 0 0 0 0 30 0RSTP (STP Regional): MPO - State Match

0 0 0 0 0 0 150 0Total

MPO Area

RichmondPrimary

PROGRAM/SYSTEM

RTE 73 - INSTALL SIDEWALK AND CURB AND

GUTTER

PROJECT

UPC NO.:

ROUTE:

100561

NFO0073

Underway

SCHEDULE

90

ESTIMATED COST (000's)

JURISDICTION:

Parham RoadSTREET NAME:

PEHenrico County

FY2015 509CNFROM: 0.208 mi. WEST OF INT. WITH VILLA PARK DR

TO: 0.041 mi. EAST OF INT. WITH VILLA PARK DR

(0.2490 MI)

DESCRIPTION: RW

PROJECT LENGTH: 0.2490 MISCOPE OF WORK: Safety TO 599

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 539Highway Safety Improvements: Federal

0 0 0 0 0 0 60Highway Safety Improvements: State Match

0 0 0 0 0 0 0 599Total

MPO Area

RichmondPrimary

PROGRAM/SYSTEM

ELECTRONIC TOLL CUSTOMER SERV. &

VIOLATION ENFORCEMENT SYS.

PROJECT

UPC NO.: 80330

NFOProject Report Req'd

AT THE POWHITE PARKWAY EXTENSIONDESCRIPTION:

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 1,047IFRO: State

11/12/2014 729

Page 32: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Primary

MPO Area

NonMPOPrimary

PROGRAM/SYSTEM

BRIDGE REPLACEMENT RTE 92 OVER

BUTCHERS CREEK (FED ID 11943)

PROJECT

UPC NO.:

ROUTE:

104955

NFO0092

Revised schedule required.REPORT NOTE:

FY2019

SCHEDULE

950

ESTIMATED COST (000's)

JURISDICTION:

STREET NAME:

PEMecklenburg County

FY2021 2,640CN

FY2020FROM: 0.03 mi.from Rte. 797 TO: 0.07 mi. from Rte. 797DESCRIPTION: 250RW

PROJECT LENGTH: _SCOPE OF WORK: Bridge Replacement w/o Added Capacity TO 3,840

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 343 692 0 0 0 0STP: Bridge - Federal

0 86 173 0 0 0 0STP: Bridge - Soft Match

2,546 429 865 0 0 0 0 0Total

MPO Area

Tri-CitiesPrimary

PROGRAM/SYSTEM

RTE 106 - INTERSECTION IMPROVEMENTS

PROJECT

UPC NO.:

ROUTE:

105110

NFO0106

MPO Project. Revised schedule required.REPORT NOTE:

Underway

SCHEDULE

120

ESTIMATED COST (000's)

JURISDICTION:

COURTHOUSE ROADSTREET NAME:

PEPrince George County

FY2018 294CN

FY2017FROM: RTE 616 (LAUREL SPRINGS ROAD) TO: RTE

616 (LAUREL SPRINGS ROAD)

DESCRIPTION: 200RW

PROJECT LENGTH: 0.0000 MISCOPE OF WORK: Safety TO 615

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 96RSTP (STP Regional): Federal

0 492 0 0 0 0 0RSTP (STP Regional): MPO - Federal

0 123 0 0 0 0 0RSTP (STP Regional): MPO - State Match

0 0 0 0 0 0 24RSTP (STP Regional): State Match

-120 615 0 0 0 0 0 120Total

MPO Area

Tri-CitiesPrimary

PROGRAM/SYSTEM

RTE 106 - ROUNDABOUT LIGHTING AND

IMPROVEMENTS

PROJECT

UPC NO.:

ROUTE:

105170

NFO0106

State Funds - AC for future federal conversion.REPORT NOTE:

Underway

SCHEDULE

85

ESTIMATED COST (000's)

JURISDICTION:

COURTHOUSE ROADSTREET NAME:

PEPrince George County

FY2015 200CN

FROM: AT INT RTE 634 TO: AT INT RTE 634DESCRIPTION: RW

PROJECT LENGTH: 0.0000 MISCOPE OF WORK: Safety TO 285

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 582Primary Formula: State -297

730 11/12/2014

Page 33: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Primary

MPO Area

RichmondPrimary

PROGRAM/SYSTEM

RTE 106 - ARTERIAL ACCESS MANAGEMENT

PLAN

PROJECT

UPC NO.:

ROUTE:

106216

NFO0106

MPO Project.REPORT NOTE:

FY2015

SCHEDULE

130

ESTIMATED COST (000's)

JURISDICTION:

EMMAUS CHURCH ROADSTREET NAME:

PENew Kent County

CN

FROM: RTE 64 TO: 1.0 MI S RTE 64 (1.0000 MI)DESCRIPTION: RW

PROJECT LENGTH: 1.0000 MISCOPE OF WORK: Other TO 130

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 104 0RSTP (STP Regional): MPO - Federal

0 0 0 0 0 26 0RSTP (STP Regional): MPO - State Match

0 0 0 0 0 0 130 0Total

MPO Area

NonMPOPrimary

PROGRAM/SYSTEM

RTE 137 - REPLACE BRIDGE

PROJECT

UPC NO.:

ROUTE:

87617

NFO0137

Complete

SCHEDULE

123

ESTIMATED COST (000's)

JURISDICTION:

Dundas RoadSTREET NAME:

PELunenburg County

Underway 941CNFROM: 0.062 MI S. Int. RTE 645 TO: 0.023 MI S Int RTE

645 (0.0390 MI)

DESCRIPTION: RW

30043 98PROJECT LENGTH: 0.0390 MI STRUCTURE NO.: SUFFICIENCY RATING:

SCOPE OF WORK: Bridge Replacement w/o Added Capacity TO 1,064

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 115Bond Match: State Bond Match

0 0 0 0 0 0 461Minimum Guarantee: Federal

0 0 0 0 0 0 672Primary Formula: Federal

0 0 0 0 0 0 168Primary Formula: State Match

-353 0 0 0 0 0 0 1,417Total

MPO Area

Tri-CitiesPrimary

PROGRAM/SYSTEM

RTE 144 (TEMPLE AVE) - TURN LANE AT

DIMMOCK PKWY

PROJECT

UPC NO.:

ROUTE:

97691

NFO0144

MPO Project.REPORT NOTE:

Complete

SCHEDULE

105

ESTIMATED COST (000's)

JURISDICTION:

TEMPLE AVENUESTREET NAME:

PEColonial Heights

Underway 467CNFROM: 0.02 Miles West OF DIMMOCK PKWY

intersection TO: 0.13 Miles East DIMMOCK PKWY

intersection (0.1500 MI)

DESCRIPTION: RW

PROJECT LENGTH: 0.1500 MISCOPE OF WORK: Resurfacing TO 572

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 328CMAQ: Federal

0 0 0 0 0 0 80CMAQ: MPO - Federal

0 0 0 0 0 0 20CMAQ: MPO - State Match

0 0 0 0 0 0 82CMAQ: State Match

0 0 0 0 0 0 62Local Project Contributions: Local

0 0 0 0 0 0 0 572Total

11/12/2014 731

Page 34: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Primary

MPO Area

Tri-CitiesPrimary

PROGRAM/SYSTEM

RTE 144 (TEMPLE AVE) - EXTEND TURN LANE

AT CONDUIT RD

PROJECT

UPC NO.:

ROUTE:

98882

NFO0144

MPO Project. Revised schedule required.REPORT NOTE:

Underway

SCHEDULE

65

ESTIMATED COST (000's)

JURISDICTION:

TEMPLE AVENUESTREET NAME:

PEColonial Heights

FY2014 343CNFROM: 0.05 Miles EAST OF CONDUIT RD TO: 0.17 Miles

EAST CONDUIT RD (0.2200 MI)

DESCRIPTION: RW

PROJECT LENGTH: 0.2200 MISCOPE OF WORK: Safety TO 408

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 92CMAQ: Federal

0 0 0 0 0 0 268CMAQ: MPO - Federal

0 0 0 0 0 0 67CMAQ: MPO - State Match

0 0 0 0 0 0 23CMAQ: State Match

-42 0 0 0 0 0 0 450Total

MPO Area

Tri-CitiesPrimary

PROGRAM/SYSTEM

RTE 144 (TEMPLE AVE) - SIGNAL

COORDINATION

PROJECT

UPC NO.:

ROUTE:

98883

NFO0144

MPO Project.REPORT NOTE:

Underway

SCHEDULE

100

ESTIMATED COST (000's)

JURISDICTION:

TEMPLE AVENUESTREET NAME:

PEColonial Heights

FY2018 395CN

FROM: RTE 1 TO: ECL COLONIAL HEIGHTS (2.0000 MI)DESCRIPTION: RW

PROJECT LENGTH: 2.0000 MISCOPE OF WORK: Safety TO 495

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 284 32 80 0CMAQ: MPO - Federal

0 0 0 71 8 20 0CMAQ: MPO - State Match

0 0 0 355 40 0 100 0Total

MPO Area

Tri-CitiesPrimary

PROGRAM/SYSTEM

RTE 144 - ADD TURN LANE

PROJECT

UPC NO.:

ROUTE:

98994

NFO0144

MPO Project.REPORT NOTE:

Complete

SCHEDULE

419

ESTIMATED COST (000's)

JURISDICTION:

HARROWGATE ROADSTREET NAME:

PEChesterfield County

Underway 1,126CN

UnderwayFROM: 0.062 MI S RTE 1141 (SOUTH ST) TO: 0.095 MI N

RTE 1141 (SOUTH ST) (0.2260 MI)

DESCRIPTION: 254RW

PROJECT LENGTH: 0.1570 MISCOPE OF WORK: Safety TO 1,798

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 168CMAQ: Federal

400 0 0 0 341 321 208CMAQ: MPO - Federal

100 0 0 0 85 80 52CMAQ: MPO - State Match

0 0 0 0 0 0 42CMAQ: State Match

0 0 0 0 427 500 401 470Total

732 11/12/2014

Page 35: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Primary

MPO Area

RichmondPrimary

PROGRAM/SYSTEM

RTE 144 - CONSTRUCT CURB, GUTTER &

SIDEWALK

PROJECT

UPC NO.:

ROUTE:

104291

NFO0144

Revised schedule requiredREPORT NOTE:

Underway

SCHEDULE

100

ESTIMATED COST (000's)

JURISDICTION:

HARROWGATE ROADSTREET NAME:

PEChesterfield County

FY2015 181CN

FY2014FROM: INT. OF RTE 1508 (SCHOOL STREET) TO: 08

MI N OF THE INT. OF RTE 1508 (SCHOOL STREET)

(0.0800 MI)

DESCRIPTION: 10RW

PROJECT LENGTH: 0.0800 MISCOPE OF WORK: Safety TO 291

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 300Revenue Sharing Funds: Local Match

0 0 0 0 0 0 300Revenue Sharing Funds: State Match

-309 0 0 0 0 0 0 600Total

MPO Area

RichmondPrimary

PROGRAM/SYSTEM

RTE 147 - HUGUENOT BRIDGE -

REPLACEMENT

PROJECT

UPC NO.:

ROUTE:

16519

NFO0147

State Funds - AC for future federal conversion.REPORT NOTE:

Complete

SCHEDULE

5,668

ESTIMATED COST (000's)

JURISDICTION:

Huguenot RoadSTREET NAME:

PEHenrico County

Underway 46,290CN

UnderwayFROM: 0.20 MILE SOUTH RIVERSIDE ROAD TO: 0.20

MILE WEST RIVER ROAD (0.9560 MI)

DESCRIPTION: 2,289RW

26545 82PROJECT LENGTH: 0.9560 MI STRUCTURE NO.: SUFFICIENCY RATING:

SCOPE OF WORK: Bridge Replacement w/ Added Capacity TO 54,246

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 106Accounts Receivable: Local

0 0 0 0 0 0 2,030Bond Match: State Bond Match

0 0 0 0 0 0 14,929Bridge Replacement: Federal

0 0 0 0 0 0 2,613Concession Funds: State

0 0 0 0 0 0 387Federal STP: Federal

0 0 0 0 0 0 6,372NHPP: Bridge - Federal

0 0 0 0 0 0 1,593NHPP: Bridge - Soft Match

0 0 0 0 0 0 5,583NHPP: Statewide - Federal

0 0 0 0 0 0 1,396NHPP: Statewide - Soft Match

0 0 0 0 0 0 6,515Primary Formula: Federal

0 0 0 0 0 0 9,790Primary Formula: State

0 0 0 0 0 0 1,629Primary Formula: State Match

0 0 0 0 0 0 410Residue Parcel Revenue: State

0 0 0 0 0 0 1,299Soft Match: Federal

-403 0 0 0 0 0 0 54,650Total

11/12/2014 733

Page 36: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Primary

MPO Area

RichmondPrimary

PROGRAM/SYSTEM

RTE 147 (HUGUENOT ROAD) - SPOT WIDENING

PROJECT

UPC NO.:

ROUTE:

90346

NFO0147

MPO project - excess funds to be redistributed by MPO.REPORT NOTE:

Underway

SCHEDULE

874

ESTIMATED COST (000's)

JURISDICTION:

HUGUENOT ROADSTREET NAME:

PEChesterfield County

FY2015 1,420CN

UnderwayFROM: ROUTE 60 (MIDLOTHIAN TURNPIKE) TO: ROUTE

727 (KOGER CENTER BLVD.) (0.4100 MI)

DESCRIPTION: 1,245RW

PROJECT LENGTH: 0.4100 MISCOPE OF WORK: Reconstruction w/ Added Capacity TO 3,539

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 3,215RSTP (STP Regional): Federal

0 0 0 0 0 0 804RSTP (STP Regional): State Match

-480 0 0 0 0 0 0 4,019Total

MPO Area

RichmondPrimary

PROGRAM/SYSTEM

RTE 147 - SHOULDER WIDENING

PROJECT

UPC NO.:

ROUTE:

93216

NFO0147

Complete

SCHEDULE

90

ESTIMATED COST (000's)

JURISDICTION:

Huguenot RoadSTREET NAME:

PEChesterfield County

Underway 843CNFROM: SR 5400 Polo Parkway TO: SR 633 Forest Hill

Ave (2.5000 MI)

DESCRIPTION: RW

PROJECT LENGTH: 2.5000 MISCOPE OF WORK: Safety TO 933

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 851Highway Safety Improvements: Federal

0 0 0 0 0 0 95Highway Safety Improvements: State Match

-12 0 0 0 0 0 0 946Total

MPO Area

RichmondPrimary

PROGRAM/SYSTEM

RTE 155 - SAFETY SHOULDER & BICYCLE

ACCOMMODATION

PROJECT

UPC NO.:

ROUTE:

67939

NFO0155

MPO project.REPORT NOTE:

Complete

SCHEDULE

992

ESTIMATED COST (000's)

JURISDICTION:

Courthouse RoadSTREET NAME:

PENew Kent County

Underway 1,669CN

UnderwayFROM: 0.685 Mi South of Boulevard Rd (Route 629) TO:

0.876 Mi North of Route 60 WBL (Pocahontas Trail)

(1.6950 MI)

DESCRIPTION: 1,680RW

PROJECT LENGTH: 1.6950 MISCOPE OF WORK: Safety TO 4,341

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 271Non-Formula: State Match

0 0 0 0 0 0 0Primary Formula: State

0 0 0 0 0 0 2,866RSTP (STP Regional): Federal

0 0 0 0 0 20 762RSTP (STP Regional): MPO - Federal

0 0 0 0 0 5 191RSTP (STP Regional): MPO - State Match

0 0 0 0 0 0 446RSTP (STP Regional): State Match

-220 0 0 0 0 0 26 4,536Total

734 11/12/2014

Page 37: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Primary

MPO Area

RichmondPrimary

PROGRAM/SYSTEM

RTE 155 - COURTHOUSE TO COURTHOUSE

CONNECTOR - PE ONLY

PROJECT

UPC NO.:

ROUTE:

92652

NFO0155

MPO Project. Revised schedule required. Balance of funds to be provided for by MPO.REPORT NOTE:

Underway

SCHEDULE

1,359

ESTIMATED COST (000's)

JURISDICTION:

North Courthouse RoadSTREET NAME:

PENew Kent County

FY2019 3,936CN

FY2015FROM: RTE 1047 (OLD FORGE ROAD) TO: RTE 249

(NEW KENT COUNTY HIGHWAY) (5.1200 MI)

DESCRIPTION: 2,275RW

PROJECT LENGTH: 5.1200 MISCOPE OF WORK: Safety TO 7,570

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 119Non-Formula: State Match

0 0 0 0 0 0 4Primary Formula: State

0 0 0 0 0 0 1,053RSTP (STP Regional): Federal

0 0 0 0 0 0 140RSTP (STP Regional): State Match

6,253 0 0 0 0 0 0 1,317Total

MPO Area

RichmondPrimary

PROGRAM/SYSTEM

RTE 155 - SHARED-USE PATH

PROJECT

UPC NO.:

ROUTE:

97688

NFO0155

MPO Project. Revised schedule required. Excess funds to be redistributed by MPO.REPORT NOTE:

Underway

SCHEDULE

180

ESTIMATED COST (000's)

JURISDICTION:

COURTHOUSE ROADSTREET NAME:

PECharles City County

FY2017 545CN

FY2016FROM: RTE 5 TO: RTE 602 (LOTT CARY RD) (1.4400 MI)DESCRIPTION: 188RW

PROJECT LENGTH: 1.4400 MISCOPE OF WORK: Safety TO 913

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 200RSTP (STP Regional): Federal

0 400 400 0 0 0 81RSTP (STP Regional): MPO - Federal

0 100 100 0 0 0 20RSTP (STP Regional): MPO - State Match

0 0 0 0 0 0 50RSTP (STP Regional): State Match

-439 500 500 0 0 0 0 351Total

MPO Area

RichmondPrimary

PROGRAM/SYSTEM

RTE 155 - CONSTRUCT TRAIL

PROJECT

UPC NO.:

ROUTE:

106296

NFO0155

MPO Project.REPORT NOTE:

FY2020

SCHEDULE

400

ESTIMATED COST (000's)

JURISDICTION:

COURTHOUSE ROADSTREET NAME:

PECharles City County

CNFROM: RTE 602 (LOTT CARY RD) TO: NEW KENT CO

LN

DESCRIPTION: RW

PROJECT LENGTH: _SCOPE OF WORK: Facilities for Pedestrians and Bicycles TO 400

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 320 0 0 0 0 0RSTP (STP Regional): MPO - Federal

0 80 0 0 0 0 0RSTP (STP Regional): MPO - State Match

0 400 0 0 0 0 0 0Total

11/12/2014 735

Page 38: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Primary

MPO Area

Tri-CitiesPrimary

PROGRAM/SYSTEM

RTE 156 - INTERSECTION IMPROVEMENT

PROJECT

UPC NO.:

ROUTE:

97635

NFO0156

Complete

SCHEDULE

302

ESTIMATED COST (000's)

JURISDICTION:

PRINCE GEORGE DRIVESTREET NAME:

PEPrince George County

Underway 844CN

UnderwayFROM: 0.145 MI SOUTH RTE 616 N TO: 0.092 MI.

NORTH RTE 616 N (0.2370 MI)

DESCRIPTION: 240RW

PROJECT LENGTH: 0.2370 MISCOPE OF WORK: Reconstruction w/o Added Capacity TO 1,385

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 8CMAQ: Federal

0 0 0 0 0 0 250CMAQ: MPO - Federal

0 0 0 0 0 0 63CMAQ: MPO - State Match

0 0 0 0 0 0 2CMAQ: State Match

0 0 0 0 0 0 256(S) Federal Formula STP: Federal

0 0 0 0 0 0 64(S) Federal Formula STP: State Bond Match

0 0 0 0 0 0 93Revenue Sharing Funds: Local Match

0 0 0 0 0 0 93Revenue Sharing Funds: State Match

0 0 0 0 0 0 479(S) Secondary Formula: Federal/State

0 0 0 0 0 0 28(S) Secondary Formula: State

0 0 0 0 0 0 545(S) Telecommunications: State

-498 0 0 0 0 0 0 1,883Total

MPO Area

RichmondPrimary

PROGRAM/SYSTEM

RTE 157 - STUDY ONLY

PROJECT

UPC NO.:

ROUTE:

101023

NFO0157

HB2 ADJUSTMENT

Underway

SCHEDULE

2,000

ESTIMATED COST (000's)

JURISDICTION:

SPRINGFIELD ROADSTREET NAME:

PEHenrico County

N/A 0CN

N/AFROM: NUCKOLS RD TO: RTE 33 (STAPLES MILL RD)

(2.0400 MI)

DESCRIPTION: 0RW

PROJECT LENGTH: 2.0400 MISCOPE OF WORK: Preliminary Engineering TO 2,000

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 1,296Bond Proceeds: CPR Bonds

0 0 0 0 0 0 204Residue Parcel Revenue: State

500 0 0 0 0 0 0 1,500Total

736 11/12/2014

Page 39: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Primary

MPO Area

RichmondPrimary

PROGRAM/SYSTEM

RTE 249 - CONSTRUCT ROUNDABOUT

PROJECT

UPC NO.:

ROUTE:

52414

NFO0249

MPO Project.REPORT NOTE:

Underway

SCHEDULE

485

ESTIMATED COST (000's)

JURISDICTION:

NEW KENT HIGHWAYSTREET NAME:

PENew Kent County

FY2015 1,499CN

UnderwayFROM: 0.09 MI W RTE 612 TO: 0.115 MI E RTE 612

(0.1780 MI)

DESCRIPTION: 760RW

PROJECT LENGTH: 0.1780 MISCOPE OF WORK: Safety TO 2,744

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 393Non-Formula: State Match

0 0 0 0 0 0 1,895RSTP (STP Regional): Federal

0 0 0 0 0 300 0RSTP (STP Regional): MPO - Federal

0 0 0 0 0 75 0RSTP (STP Regional): MPO - State Match

0 0 0 0 0 0 81RSTP (STP Regional): State Match

0 0 0 0 0 0 374 2,369Total

MPO Area

RichmondPrimary

PROGRAM/SYSTEM

RTE 250 - 4 LANE

PROJECT

UPC NO.:

ROUTE:

52448

NFO0250

MPO Project. PE & RW only. See ARRA UPC 94854 for CN phase.REPORT NOTE:

Underway

SCHEDULE

1,287

ESTIMATED COST (000's)

JURISDICTION:

Broad Street RoadSTREET NAME:

PEGoochland County

CN

UnderwayFROM: 0.226 MILE WEST INTERSECTION ROUTE 621

TO: 0.133 MILE EAST INTERSECTION ROUTE 623

WEST (0.8610 MI)

DESCRIPTION: 3,379RW

PROJECT LENGTH: 0.8610 MISCOPE OF WORK: Reconstruction w/ Added Capacity TO 4,666

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 610Non-Formula: State Match

0 0 0 0 0 0 28Non-Formula: Statewide

0 0 0 0 0 0 276Primary Formula: State

0 0 0 0 0 0 3,399RSTP (STP Regional): Federal

0 0 0 0 0 0 240RSTP (STP Regional): State Match

0 0 0 0 0 0 113RSTP (STP Regional): Statewide

0 0 0 0 0 0 0 4,666Total

11/12/2014 737

Page 40: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Primary

MPO Area

NonMPOPrimary

PROGRAM/SYSTEM

RTE 250 (BROAD STREET RD)- ACCELERATION

LANE AT RTE 632

PROJECT

UPC NO.:

ROUTE:

81242

NFO0250

Revised estimate required.REPORT NOTE:

Complete

SCHEDULE

155

ESTIMATED COST (000's)

JURISDICTION:

BROAD STREET ROADSTREET NAME:

PEGoochland County

Underway 381CN

UnderwayFROM: 0.055 Mi. E. Rte. 632 TO: 0.197 Mi. E. Rte. 632

(0.2410 MI)

DESCRIPTION: 351RW

PROJECT LENGTH: 0.2410 MISCOPE OF WORK: Safety TO 887

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 35Discretionary Grants: State Match

0 0 0 0 0 0 693Highway Safety Improvements: Federal

0 0 0 0 0 0 42Highway Safety Improvements: State Match

0 0 0 0 0 0 100Primary Formula: State

17 0 0 0 0 0 0 870Total

MPO Area

RichmondPrimary

PROGRAM/SYSTEM

ARRA - GOOCHLAND 250 WIDEN TO 4 LANES

(MANAKIN TO HOCKETT)

PROJECT

UPC NO.: 94854

NFOARRA09

PE and RW on UPC 52448REPORT NOTE:

FROM: 0.226 MILE WEST INTERSECTION ROUTE 621

TO: 0.133 MILE EAST INTERSECTION ROUTE 623

WEST (0.8610 MI)

DESCRIPTION:

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 4,434American Recovery and Reinvestment Act:

Urbanized Area > 200K

0 0 0 0 0 0 73Non-Formula: State Match

0 0 0 0 0 0 342Primary Formula: Federal

0 0 0 0 0 0 60Primary Formula: State

0 0 0 0 0 0 85Primary Formula: State Match

0 0 0 0 0 0 293RSTP (STP Regional): Federal

0 0 0 0 0 0 5,287Total

MPO Area

RichmondPrimary

PROGRAM/SYSTEM

RTE 250 - UPGRADE SIGNAL & ADD

SIDEWALK AT BETHLEHEM RD

PROJECT

UPC NO.:

ROUTE:

98381

NFO0250

Complete

SCHEDULE

95

ESTIMATED COST (000's)

JURISDICTION:

BROAD STREETSTREET NAME:

PEHenrico County

Underway 306CN

UnderwayFROM: 0.01 MI. WEST OF BETHLEHEM RD. TO: 0.07

MI. EAST OF BETHLEHEM RD. (0.0800 MI)

DESCRIPTION: 99RW

PROJECT LENGTH: 0.0600 MISCOPE OF WORK: Safety TO 500

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 471Highway Safety Improvements: Federal

0 0 0 0 0 0 52Highway Safety Improvements: State Match

0 0 0 0 0 0 0Primary Formula: State

0 0 0 0 0 0 1Safety Funds: Hazard Elimination

-24 0 0 0 0 0 0 524Total

738 11/12/2014

Page 41: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Primary

MPO Area

RichmondPrimary

PROGRAM/SYSTEM

RTE 250 - RECONSTRUCT MEDIAN AT

TUCKERNUCK DR

PROJECT

UPC NO.:

ROUTE:

98382

NFO0250

Complete

SCHEDULE

58

ESTIMATED COST (000's)

JURISDICTION:

BROAD STREETSTREET NAME:

PEHenrico County

Underway 65CNFROM: 0.14 MI. WEST OF TUCKERNUCK DR. TO: 0.05

MI. WEST OF TUCKERNUCK DR. (0.0900 MI)

DESCRIPTION: RW

PROJECT LENGTH: 0.0900 MISCOPE OF WORK: Safety TO 123

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 167Highway Safety Improvements: Federal

0 0 0 0 0 0 19Highway Safety Improvements: State Match

-63 0 0 0 0 0 0 186Total

MPO Area

RichmondPrimary

PROGRAM/SYSTEM

RTE 250 - UPGRADE SIGNAL & ADD LIGHTING

AT WEST END DR

PROJECT

UPC NO.:

ROUTE:

98383

NFO0250

Complete

SCHEDULE

80

ESTIMATED COST (000's)

JURISDICTION:

BROAD STREETSTREET NAME:

PEHenrico County

Underway 359CN

UnderwayFROM: 0.11 MI. WEST OF WEST END DR. TO: 0.02 MI.

EAST OF WEST END DR. (0.0900 MI)

DESCRIPTION: 39RW

PROJECT LENGTH: 0.0900 MISCOPE OF WORK: Safety TO 478

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 464Highway Safety Improvements: Federal

0 0 0 0 0 0 52Highway Safety Improvements: State Match

-38 0 0 0 0 0 0 516Total

MPO Area

RichmondPrimary

PROGRAM/SYSTEM

BROAD ST RD/RTE 288 INTERCHANGE

FEASIBILITY STUDY

PROJECT

UPC NO.:

ROUTE:

104090

NFO0250

MPO Project.REPORT NOTE:

Underway

SCHEDULE

200

ESTIMATED COST (000's)

JURISDICTION:

BROAD STREET ROADSTREET NAME:

PEGoochland County

CN

FROM: HENRICO COUNTY LINE TO: MILLS ROADDESCRIPTION: RW

PROJECT LENGTH: _SCOPE OF WORK: Preliminary Engineering TO 200

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 160RSTP (STP Regional): MPO - Federal

0 0 0 0 0 0 40RSTP (STP Regional): MPO - State Match

0 0 0 0 0 0 0 200Total

11/12/2014 739

Page 42: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Primary

MPO Area

RichmondPrimary

PROGRAM/SYSTEM

RTE 250 - PROVIDE PEDESTRIAN

ACCOMMODATIONS

PROJECT

UPC NO.:

ROUTE:

104666

NFO0250

Underway

SCHEDULE

200

ESTIMATED COST (000's)

JURISDICTION:

BROAD STREETSTREET NAME:

PEHenrico County

FY2016 800CN

N/AFROM: RICHMOND CITY LIMITS TO: I-64 INTERCHANGE

(1.9500 MI)

DESCRIPTION: 0RW

PROJECT LENGTH: 1.9500 MISCOPE OF WORK: Safety TO 1,000

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 720 180Highway Safety Improvements: Federal

0 0 0 0 0 80 20Highway Safety Improvements: Soft Match

0 0 0 0 0 0 800 200Total

MPO Area

RichmondPrimary

PROGRAM/SYSTEM

RTE 288 - INTERCHANGE MODIFICATION AT

RTE 145

PROJECT

UPC NO.:

ROUTE:

90349

NFO0288

MPO Project. Excess funds to be redistributed by MPO.REPORT NOTE:

Complete

SCHEDULE

448

ESTIMATED COST (000's)

JURISDICTION:

World War II Veterans Memorial HighwaySTREET NAME:

PEChesterfield County

Underway 1,984CNFROM: RTE 288 TO: RTE 145 WB (Chester Road)

(0.2810 MI)

DESCRIPTION: RW

PROJECT LENGTH: 0.2810 MISCOPE OF WORK: New Construction Roadway TO 2,431

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 2,096CMAQ: Federal

0 0 0 0 0 0 524CMAQ: State Match

-189 0 0 0 0 0 0 2,621Total

MPO Area

RichmondPrimary

PROGRAM/SYSTEM

RTE. 288 NB - PATCH AND OVERLAY -

CHESTERFIELD CO

PROJECT

UPC NO.:

ROUTE:

104491

NFO0288

SCHEDULE ESTIMATED COST (000's)

JURISDICTION:

STREET NAME:

PEChesterfield County

Underway 7,440CNFROM: RTE. 654 (BAILEY BRIDGE RD.) TO: RTE. 76

(POWHITE PARKWAY) (3.7600 MI)

DESCRIPTION: RW

PROJECT LENGTH: 3.7600 MISCOPE OF WORK: Resurfacing TO 7,440

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 400 0CTB Formula: Paving - Federal

0 0 0 0 0 100 0CTB Formula: Paving - Soft Match

3,405 0 0 0 3,536 0 0CTB Formula: Paving - State

0 0 0 0 0 0 0(X) Maintenance Funds: Statewide

0 0 0 0 3,536 3,405 500 0Total

740 11/12/2014

Page 43: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Primary

MPO Area

RichmondPrimary

PROGRAM/SYSTEM

RTE 288 - IMPROVE INTERCHANGE AT RTE 360

(PE ONLY)

PROJECT

UPC NO.:

ROUTE:

104862

NFO0288

HB2 ADJUSTMENT

Underway

SCHEDULE

2,000

ESTIMATED COST (000's)

JURISDICTION:

RTE 288STREET NAME:

PEChesterfield County

CNFROM: INTERCHANGE AREA AT RTE 360 (HULL ST)

TO: INTERCHANGE AREA AT RTE 360 (HULL ST)

(0.0100 MI)

DESCRIPTION: RW

PROJECT LENGTH: 0.0100 MISCOPE OF WORK: Reconstruction w/ Added Capacity TO 2,000

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 1,000Bond Proceeds: CPR Bonds

0 0 0 0 0 0 400NHPP: Statewide - Federal

0 0 0 0 0 0 100NHPP: Statewide - Soft Match

500 0 0 0 0 0 0 1,500Total

MPO Area

RichmondPrimary

PROGRAM/SYSTEM

RTE 301 - REPLACE BRIDGE

PROJECT

UPC NO.:

ROUTE:

105107

NFO0301

Revised schedule requiredREPORT NOTE:

Underway

SCHEDULE

650

ESTIMATED COST (000's)

JURISDICTION:

Hanover Courthouse RoadSTREET NAME:

PEHanover County

FY2019 2,260CN

FY2017DESCRIPTION: 360RW

PROJECT LENGTH: _SCOPE OF WORK: Bridge Replacement w/o Added Capacity TO 3,270

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

800 1,068 0 0 0 0 0CTB Formula: Bridge - State

215 0 360 262 285 0 0STP: Bridge - Federal

54 0 90 65 71 0 0STP: Bridge - Soft Match

0 1,068 450 327 356 1,068 0 0Total

MPO Area

Tri-CitiesPrimary

PROGRAM/SYSTEM

RTE. 327 (HAYDEN ST) - REMOVE BRIDGE

PROJECT

UPC NO.:

ROUTE:

87618

NFO0327

Complete

SCHEDULE

235

ESTIMATED COST (000's)

JURISDICTION:

Hayden StreetSTREET NAME:

PEChesterfield County

Underway 779CN

UnderwayFROM: 0.010 MI West OF CARTER G. WOODSON AVE

TO: 0.054 MI EAST OF CARTER G. WOODSON AVE

(0.0640 MI)

DESCRIPTION: 431RW

23270 50PROJECT LENGTH: 0.0640 MI STRUCTURE NO.: SUFFICIENCY RATING:

SCOPE OF WORK: Bridge Replacement w/o Added Capacity TO 1,444

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 764Primary Formula: Federal

0 0 0 0 0 0 225Primary Formula: Federal/State

0 0 0 0 0 0 379Primary Formula: State

0 0 0 0 0 0 191Primary Formula: State Match

-115 0 0 0 0 0 0 1,559Total

11/12/2014 741

Page 44: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Primary

MPO Area

RichmondPrimary

PROGRAM/SYSTEM

RTE 360 WIDENING

PROJECT

UPC NO.:

ROUTE:

13551

NFO0360

MPO Project. Excess funds to be redistributed by MPO.REPORT NOTE:

Underway

SCHEDULE

1,373

ESTIMATED COST (000's)

JURISDICTION:

Mechanicsville TurnpikeSTREET NAME:

PEHanover County

FY2018 9,692CN

UnderwayFROM: INT w/Wynbrook Lane (Rt 1133) TO: 0.2 Miles

East of Lee Davis Road (0.7700 MI)

DESCRIPTION: 3,247RW

PROJECT LENGTH: 0.7700 MISCOPE OF WORK: Safety TO 14,313

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 656CMAQ: Federal

0 0 1,200 800 432 0 0CMAQ: MPO - Federal

0 0 300 200 108 0 0CMAQ: MPO - State Match

0 0 0 0 0 0 164Primary Formula: State

0 0 0 0 0 0 1,809RSTP (STP Regional): Federal

0 0 3,440 800 352 800 1,195RSTP (STP Regional): MPO - Federal

0 0 860 200 88 200 299RSTP (STP Regional): MPO - State Match

0 0 0 0 0 0 452RSTP (STP Regional): State Match

-42 0 5,800 2,000 980 0 1,000 4,575Total

MPO Area

RichmondPrimary

PROGRAM/SYSTEM

RTE 360 - WIDENING FROM 4 TO 6 & 8 LANES

PROJECT

UPC NO.:

ROUTE:

17768

NFO0360

Underway

SCHEDULE

2,455

ESTIMATED COST (000's)

JURISDICTION:

MECHANICSVILLE TURNPIKESTREET NAME:

PEHanover County

FY2015 5,055CN

UnderwayFROM: RTE 295N BRIDGE TO: RTE 1133 (WYNBROOK

LN) (0.6340 MI)

DESCRIPTION: 1,893RW

PROJECT LENGTH: 0.6340 MISCOPE OF WORK: Reconstruction w/ Added Capacity TO 9,403

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 425Bond Match: State Bond Match

0 0 0 0 0 0 989Concession Funds: State

0 0 0 0 0 0 1,620Federal STP: Federal

0 0 0 0 0 0 1,592Minimum Guarantee: Federal

0 0 0 0 0 0 1,930Primary Formula: Federal

0 0 0 0 0 0 3,687Primary Formula: State

0 0 0 0 0 0 483Primary Formula: State Match

0 0 0 0 0 0 2,223RSTP (STP Regional): Federal

0 0 0 0 0 0 556RSTP (STP Regional): State Match

-4,101 0 0 0 0 0 0 13,504Total

742 11/12/2014

Page 45: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Primary

MPO Area

RichmondPrimary

PROGRAM/SYSTEM

ROUTE 360 - BRIDGE REPLACEMENT

PROJECT

UPC NO.:

ROUTE:

17959

NFO0360

State Funds - AC for future federal conversion.REPORT NOTE:

Complete

SCHEDULE

1,077

ESTIMATED COST (000's)

JURISDICTION:

Mechanicsville TurnpikeSTREET NAME:

PERichmond District-wide

Underway 12,801CN

UnderwayFROM: 0.498 Mi. West of Hanover/Henrico Line TO: 0.164

Mi. East of Hanover/Henrico Line (0.6620 MI)

DESCRIPTION: 937RW

28896,28897,28898,28899 -2PROJECT LENGTH: 0.6620 MI STRUCTURE NO.: SUFFICIENCY RATING:

SCOPE OF WORK: Bridge Replacement w/o Added Capacity TO 14,815

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 40Bond Match: State Bond Match

0 0 0 0 0 0 6,212Bond Proceeds: CPR Bonds

0 0 0 0 0 0 260Bridge Replacement: Federal

6 0 0 0 0 0 0CTB Formula: Bridge - State

414 0 0 0 0 957 3,937NHPP: Bridge - Federal

104 0 0 0 0 239 984NHPP: Bridge - Soft Match

0 0 0 0 0 0 323Primary Formula: Federal

0 0 0 0 0 0 1,233Primary Formula: State

0 0 0 0 0 0 81Primary Formula: State Match

0 0 0 0 0 0 25Soft Match: Federal

0 0 0 0 0 523 1,196 13,096Total

MPO Area

RichmondPrimary

PROGRAM/SYSTEM

RTE 360 - INTERSECTION RELOCATION

PROJECT

UPC NO.:

ROUTE:

18962

NFO0360

State Funds - AC for future federal conversion. Revised estimate required.REPORT NOTE:

Underway

SCHEDULE

1,044

ESTIMATED COST (000's)

JURISDICTION:

STREET NAME:

PEHanover County

FY2015 2,625CN

UnderwayFROM: 0.012 MI S RTE 360 TO: 0.333 MI S RTE 360

(0.3200 MI)

DESCRIPTION: 5,243RW

PROJECT LENGTH: 0.3200 MISCOPE OF WORK: Relocation TO 8,912

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 291Bond Match: State Bond Match

0 0 0 0 0 0 2,321Concession Funds: State

0 0 0 0 0 0 3,498Minimum Guarantee: Federal

0 0 0 0 0 0 477Primary Formula: Federal

0 0 0 0 0 0 203Primary Formula: State

0 0 0 0 0 0 119Primary Formula: State Match

0 0 0 0 0 0 647Priority Transportation Funds: State

1,357 0 0 0 0 0 0 7,555Total

11/12/2014 743

Page 46: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Primary

MPO Area

RichmondPrimary

PROGRAM/SYSTEM

RTE 360 - WIDENING FROM 4 TO 6 LANES

PROJECT

UPC NO.:

ROUTE:

18963

FO0360

Revised estimate requiredREPORT NOTE:

Underway

SCHEDULE

3,123

ESTIMATED COST (000's)

JURISDICTION:

STREET NAME:

PEHanover County

CNFROM: 0.2 MILE EAST LEE DAVIS ROAD TO: WALNUT

GROVE ROAD

DESCRIPTION: RW

PROJECT LENGTH: 0.0000 MISCOPE OF WORK: Reconstruction w/ Added Capacity TO 3,123

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 20Bond Match: State Bond Match

0 0 0 0 0 0 81Federal STP: Federal

0 0 0 0 0 0 179Minimum Guarantee: Federal

0 0 0 0 0 0 240Primary Formula: Federal

0 0 0 0 0 0 85Primary Formula: State

0 0 0 0 0 0 60Primary Formula: State Match

2,458 0 0 0 0 0 0 665Total

MPO Area

RichmondPrimary

PROGRAM/SYSTEM

RTE 360 - ADD SIDEWALK

PROJECT

UPC NO.:

ROUTE:

93386

NFO0360

Revised schedule required.REPORT NOTE:

Underway

SCHEDULE

175

ESTIMATED COST (000's)

JURISDICTION:

HULL STREETSTREET NAME:

PEChesterfield County

FY2014 525CNFROM: RTE 2023 (MOCKINGBIRD LA) TO: RTE 5655

(BRAD MCNEER PKY) (0.6000 MI)

DESCRIPTION: RW

PROJECT LENGTH: 0.6000 MISCOPE OF WORK: Safety TO 700

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 873Highway Safety Improvements: Federal

0 0 0 0 0 0 97Highway Safety Improvements: State Match

-271 0 0 0 0 0 0 971Total

744 11/12/2014

Page 47: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Primary

MPO Area

RichmondPrimary

PROGRAM/SYSTEM

RTE 360 - WIDENING

PROJECT

UPC NO.:

ROUTE:

97687

NFO0360

MPO Project. Excess funds to be redistributed by MPO.REPORT NOTE:

Complete

SCHEDULE

1,300

ESTIMATED COST (000's)

JURISDICTION:

HULL STREET ROADSTREET NAME:

PEChesterfield County

Underway 9,350CN

UnderwayFROM: 0.284 MI. W. WOODLAKE VILLAGE PARKWAY

(RTE. 3600) TO: 0.431.MI. E. WOODLAKE VILLAGE

PARKWAY (RTE. 3600) (0.7150 MI)

DESCRIPTION: 1,800RW

5223,5229 81,97PROJECT LENGTH: 0.7150 MI STRUCTURE NO.: SUFFICIENCY RATING:

SCOPE OF WORK: Reconstruction w/ Added Capacity TO 12,450

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 250Revenue Sharing Funds: Local Match

0 0 0 0 0 0 250Revenue Sharing Funds: State Match

0 0 0 0 0 0 3,040RSTP (STP Regional): Federal

1,600 0 0 0 1,800 800 2,360RSTP (STP Regional): MPO - Federal

400 0 0 0 450 200 590RSTP (STP Regional): MPO - State Match

0 0 0 0 0 0 760RSTP (STP Regional): State Match

-50 0 0 0 2,250 2,000 1,000 7,250Total

MPO Area

RichmondPrimary

PROGRAM/SYSTEM

RTE 360 - UPGRADE SIGNAL

PROJECT

UPC NO.:

ROUTE:

100565

NFO0360

Revised schedule requiredREPORT NOTE:

Underway

SCHEDULE

155

ESTIMATED COST (000's)

JURISDICTION:

Mechanicsville TurnpikeSTREET NAME:

PEHanover County

FY2014 566CN

UnderwayFROM: INT. RTE 1108 AND RTE 360 BUSINESS TO: INT.

RTE 1108 AND RTE 360 BYPASS

DESCRIPTION: 50RW

PROJECT LENGTH: 0.0000 MISCOPE OF WORK: Safety TO 771

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 21Discretionary Grants: State Match

0 0 0 0 0 0 738Highway Safety Improvements: Federal

0 0 0 0 0 0 61Highway Safety Improvements: State Match

0 0 0 0 0 0 1Primary Formula: State

0 0 0 0 0 0 9Safety Funds: Hazard Elimination

-59 0 0 0 0 0 0 830Total

11/12/2014 745

Page 48: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Primary

MPO Area

RichmondPrimary

PROGRAM/SYSTEM

RTE 360 - WIDEN TO SIX LANES

PROJECT

UPC NO.:

ROUTE:

101022

NFO0360

MPO Project.REPORT NOTE:

Complete

SCHEDULE

500

ESTIMATED COST (000's)

JURISDICTION:

HULL STREET ROADSTREET NAME:

PEChesterfield County

Underway 1,509CN

UnderwayFROM: 0.093 MI EAST WARBRO ROAD (RTE 907) TO:

0.166 MI WEST GENITO ROAD (RTE 604) (0.8480 MI)

DESCRIPTION: 1,000RW

PROJECT LENGTH: 0.8480 MISCOPE OF WORK: Reconstruction w/o Added Capacity TO 3,009

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 400RSTP (STP Regional): Federal

0 0 0 0 0 407 1,600RSTP (STP Regional): MPO - Federal

0 0 0 0 0 102 400RSTP (STP Regional): MPO - State Match

0 0 0 0 0 0 100RSTP (STP Regional): State Match

0 0 0 0 0 0 509 2,500Total

MPO Area

RichmondPrimary

PROGRAM/SYSTEM

RTE 360 - INTERSECTION IMPROVEMENTS

PROJECT

UPC NO.:

ROUTE:

104886

NFO0360

MPO Project.REPORT NOTE:

FY2017

SCHEDULE

250

ESTIMATED COST (000's)

JURISDICTION:

HULL STREET ROADSTREET NAME:

PEChesterfield County

FY2021 2,300CN

FY2018FROM: 0.25 MILE WEST OF SPRING RUN ROAD TO:

0.25 MILE EAST OF SPRING RUN ROAD (0.5000 MI)

DESCRIPTION: 450RW

PROJECT LENGTH: 0.5000 MISCOPE OF WORK: Reconstruction w/o Added Capacity TO 3,000

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 1,840 0 360 200 0 0CMAQ: MPO - Federal

0 460 0 90 50 0 0CMAQ: MPO - State Match

0 2,300 0 450 250 0 0 0Total

MPO Area

RichmondPrimary

PROGRAM/SYSTEM

RTE 360 - WIDENING

PROJECT

UPC NO.:

ROUTE:

104890

NFO0360

MPO Project. Balance to be provided for by MPO.REPORT NOTE:

FY2019

SCHEDULE

800

ESTIMATED COST (000's)

JURISDICTION:

HULL STREET ROADSTREET NAME:

PEChesterfield County

FY2022 3,700CN

FY2020FROM: LONAS PARKWAY TO: CASTLE ROCK ROAD

(0.9000 MI)

DESCRIPTION: 1,000RW

PROJECT LENGTH: 0.9000 MISCOPE OF WORK: Reconstruction w/ Added Capacity TO 5,500

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 800 640 0 0 0 0RSTP (STP Regional): MPO - Federal

0 200 160 0 0 0 0RSTP (STP Regional): MPO - State Match

3,700 1,000 800 0 0 0 0 0Total

746 11/12/2014

Page 49: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Primary

MPO Area

NonMPOPrimary

PROGRAM/SYSTEM

RTE 360 - REPLACE BRIDGES

PROJECT

UPC NO.:

ROUTE:

104953

NFO0360

Revised schedule requiredREPORT NOTE:

FY2016

SCHEDULE

3,000

ESTIMATED COST (000's)

JURISDICTION:

STREET NAME:

PEAmelia County

FY2020 8,252CN

FY2018DESCRIPTION: 2,000RW

PROJECT LENGTH: _SCOPE OF WORK: Bridge Replacement w/o Added Capacity TO 13,252

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 3,221 1,376 0 0 0 0NHPP: Bridge - Federal

0 805 344 0 0 0 0NHPP: Bridge - Soft Match

0 0 840 0 0 0 0STP: Bridge - Federal

0 0 210 0 0 0 0STP: Bridge - Soft Match

6,455 4,026 2,771 0 0 0 0 0Total

MPO Area

Tri-CitiesPrimary

PROGRAM/SYSTEM

RTE 460 - ADD LEFT TURN LANE WESTBOUND

AT RTE 657

PROJECT

UPC NO.:

ROUTE:

100499

NFO0460

MPO Project. Balance to be provided for by MPO.REPORT NOTE:

Underway

SCHEDULE

250

ESTIMATED COST (000's)

JURISDICTION:

COUNTY DRIVESTREET NAME:

PEPrince George County

FY2016 1,044CN

FY2015FROM: 0.102 MI. W OF RTE. 657 (Enterprise Drive) TO:

0.163 MI. E OF RTE. 657 (Enterprise Drive) (0.2700 MI)

DESCRIPTION: 939RW

PROJECT LENGTH: 0.2700 MISCOPE OF WORK: Reconstruction w/o Added Capacity TO 2,234

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 383CMAQ: Federal

490 0 0 0 124 16 136CMAQ: MPO - Federal

123 0 0 0 31 4 34CMAQ: MPO - State Match

0 0 0 0 0 0 96CMAQ: State Match

796 0 0 0 155 613 20 649Total

MPO Area

NonMPOPrimary

PROGRAM/SYSTEM

RTE 460B - ADD ACCELERATION LANE

PROJECT

UPC NO.:

ROUTE:

104116

NFO0460

Revised schedule required.REPORT NOTE:

SCHEDULE ESTIMATED COST (000's)

JURISDICTION:

COX ROAD (RTE 460 BUS)/RTE 460 BYPASSSTREET NAME:

PENottoway County

FY2014 1,500CNFROM: 0.116 MI S RTE 460 BYPASS TO: 0.315 MI E

RTE 460 BUS (0.4260 MI)

DESCRIPTION: RW

PROJECT LENGTH: 0.4260 MISCOPE OF WORK: Safety TO 1,500

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 1,500Bond Proceeds: CPR Bonds 0

11/12/2014 747

Page 50: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Primary

MPO Area

NonMPOPrimary

PROGRAM/SYSTEM

RTE 460 BUS - BRIDGE REPLACEMENT

PROJECT

UPC NO.:

ROUTE:

18964

NFO7460

Underway

SCHEDULE

1,150

ESTIMATED COST (000's)

JURISDICTION:

COX ROADSTREET NAME:

PENottoway County

FY2015 10,445CN

UnderwayFROM: 0.421MI S Rte 641 TO: 0.123 MI N Rte 641

(0.5450 MI)

DESCRIPTION: 710RW

28704 -2PROJECT LENGTH: 0.5450 MI STRUCTURE NO.: SUFFICIENCY RATING:

SCOPE OF WORK: Bridge Replacement w/o Added Capacity TO 12,305

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

2,525 0 0 4,531 1,759 0 0CTB Formula: Bridge - State

0 0 0 0 0 0 1,913Primary Formula: Federal

0 0 0 0 0 0 1,098Primary Formula: State

0 0 0 0 0 0 478Primary Formula: State Match

0 0 0 4,531 1,759 2,525 0 3,489Total

MPO Area

RichmondPrimary

PROGRAM/SYSTEM

RTES. 145 & 632 MILL, PATCH, & OVERLAY

CHESTERFIELD CO.

PROJECT

UPC NO.:

ROUTE:

104493

NFO9999

SCHEDULE ESTIMATED COST (000's)

JURISDICTION:

CENTRALIA RD/CHALKEY RD./CHESTER RD.STREET NAME:

PEChesterfield County

Underway 1,381CN

FROM: 3 LOCATIONS TO: VARIOUS (4.4900 MI)DESCRIPTION: RW

PROJECT LENGTH: 4.4900 MISCOPE OF WORK: Restoration and Rehabilitation TO 1,381

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 331 0CTB Formula: Paving - Federal

0 0 0 0 0 83 0CTB Formula: Paving - Soft Match

967 0 0 0 0 0 0CTB Formula: Paving - State

0 0 0 0 0 0 0(X) Maintenance Funds: Statewide

0 0 0 0 0 967 414 0Total

MPO Area

RichmondPrimary

PROGRAM/SYSTEM

REPLACE SIGNALS - 3 INTERSECTIONS

PROJECT

UPC NO.:

ROUTE:

106293

NFO9999

PE & RW on UPC 104664.REPORT NOTE:

SCHEDULE ESTIMATED COST (000's)

JURISDICTION:

VARIOUSSTREET NAME:

PERichmond District-wide

FY2015 930CNFROM: HENRICO - 2 LOC ON RTE 33 TO:

CHESTERFIELD - 1 LOC ON RTE 637

DESCRIPTION: RW

PROJECT LENGTH: 0.0000 MISCOPE OF WORK: Safety TO 930

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 837 0Highway Safety Improvements: Federal

0 0 0 0 0 93 0Highway Safety Improvements: Soft Match

0 0 0 0 0 0 930 0Total

748 11/12/2014

Page 51: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Primary

MPO Area

NonMPOPrimary

PROGRAM/SYSTEM

2014 PLANT MIX SCHEDULE SOUTH HILL

RESIDENCY (PRIMARY)

PROJECT

UPC NO.:

ROUTE:

104480

NFOPM4B

SCHEDULE ESTIMATED COST (000's)

JURISDICTION:

STREET NAME:

PEMecklenburg County

Underway 5,983CN

FROM: VARIOUS TO: VARIOUSDESCRIPTION: RW

PROJECT LENGTH: 0.0000 MISCOPE OF WORK: Resurfacing TO 5,983

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 1,280 156 0CTB Formula: Paving - Federal

0 0 0 0 320 39 0CTB Formula: Paving - Soft Match

4,188 0 0 0 0 0 0CTB Formula: Paving - State

0 0 0 0 0 0 0(X) Maintenance Funds: Statewide

0 0 0 0 1,600 4,188 195 0Total

MPO Area

NonMPOPrimary

PROGRAM/SYSTEM

GENERAL R/W EXPENSES, VARIOUS

LOCATIONS DISTRICTWIDE

PROJECT

UPC NO.: 63839

NFOProject Report Req'd

DISTRICTWIDEDESCRIPTION:

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 1,167Primary Formula: State

11/12/2014 749

Page 52: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL

FY2015-2020 Six-Year Improvement Program RICHMOND DISTRICTSecondary

PROJECT PROGRAM/SYSTEM

SecondaryRICHMOND DISTRICT SSYP

DESCRIPTION:

REQUIRED ALLOCATIONS (000's)

Total available secondary allocations by locality and fund source.

Fund Source NameCounty FY2016 FY2018 FY2019 FY2020FY2017 TotalFY2015

Amelia County

CTB Formula

167 174 161 159 98 18Unpaved - State 777

Telecommunications

38 38 38 38 38 38State 228

56 136 197 199 212 205Amelia County Total 1,005

Brunswick County

CTB Formula

72 75 70 69 42 8Unpaved - State 337

Telecommunications

51 51 51 51 51 51State 309

59 94 121 121 127 124Brunswick County Total 646

Charles City County

CTB Formula

6 6 5 5 3 1Unpaved - State 26

Telecommunications

22 22 22 22 22 22State 129

22 25 27 27 27 27Charles City County Total 155

Chesterfield County

CTB Formula

30 31 29 29 18 3Unpaved - State 140

Residue Parcel Revenue

0 0 0 0 0 59State 59

Telecommunications

945 945 945 945 945 945State 5,672

1,007 963 974 974 977 975Chesterfield County Total 5,871

Dinwiddie County

CTB Formula

145 151 140 139 85 16Unpaved - State 676

Telecommunications

83 83 83 83 83 83State 497

98 168 221 223 234 228Dinwiddie County Total 1,173

Goochland County

CTB Formula

16 17 16 15 10 2Unpaved - State 75

Telecommunications

64 64 64 64 64 64State 386

66 74 80 80 81 81Goochland County Total 461

Hanover County

Telecommunications

276 276 276 276 276 276State 1,658

276 276 276 276 276 276Hanover County Total 1,658

Henrico County

0 0 0 0 0 0Henrico County Total 0

750 11/12/2014

Page 53: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL

FY2015-2020 Six-Year Improvement Program RICHMOND DISTRICTSecondary

PROJECT PROGRAM/SYSTEM

SecondaryRICHMOND DISTRICT SSYP

DESCRIPTION:

REQUIRED ALLOCATIONS (000's)

Total available secondary allocations by locality and fund source.

Fund Source NameCounty FY2016 FY2018 FY2019 FY2020FY2017 TotalFY2015

Lunenburg County

CTB Formula

230 239 222 220 135 25Unpaved - State 1,070

Telecommunications

38 38 38 38 38 38State 230

63 173 258 260 278 268Lunenburg County Total 1,300

Mecklenburg County

CTB Formula

281 293 272 268 165 30Unpaved - State 1,309

Telecommunications

77 77 77 77 77 77State 461

107 242 345 348 369 358Mecklenburg County Total 1,769

New Kent County

CTB Formula

44 46 42 42 26 5Unpaved - State 204

Telecommunications

56 56 56 56 56 56State 334

60 81 98 98 101 100New Kent County Total 538

Nottoway County

CTB Formula

62 64 59 59 36 7Unpaved - State 287

Telecommunications

36 36 36 36 36 36State 218

43 72 95 96 100 98Nottoway County Total 505

Powhatan County

CTB Formula

5 5 5 4 3 1Unpaved - State 22

Telecommunications

84 84 84 84 84 84State 502

84 86 88 88 89 88Powhatan County Total 524

Prince George County

Telecommunications

106 106 106 106 106 106State 636

106 106 106 106 106 106Prince George County Total 636

Grand Total 2,935 2,977 2,898 2,886 2,497 2,049 16,242

11/12/2014 751

Page 54: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Secondary

MPO Area

NonMPOSecondary

PROGRAM/SYSTEM

RTE 609 - BRIDGE & APPROACHES OVER

APPOMATTOX RIVER

PROJECT

UPC NO.:

ROUTE:

87943

NFO0609

Complete

SCHEDULE

920

ESTIMATED COST (000's)

JURISDICTION:

ROYALTON ROADSTREET NAME:

PEAmelia County

Underway 5,880CN

UnderwayFROM: 0.25 MI S OF AMELIA/POWHATAN CO LINE TO:

0.28 MI N OF AMELIA/POWHATAN CO LINE (0.5320 MI)

DESCRIPTION: 39RW

29424 -1PROJECT LENGTH: 0.5320 MI STRUCTURE NO.: SUFFICIENCY RATING:

SCOPE OF WORK: Bridge Replacement w/o Added Capacity TO 6,838

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 313Bond Match: State Bond Match

0 0 0 0 0 0 122Bond Proceeds: CPR Bonds

0 0 0 0 0 0 1,511Bridge Replacement: Federal

0 0 0 0 0 0 242(S) Federal Formula STP: Federal

0 0 0 0 0 0 61(S) Federal Formula STP: State Bond Match

0 0 0 0 0 0 159(S) Secondary Formula: Federal

0 0 0 0 0 0 321(S) Secondary Formula: Federal/State

0 0 0 0 0 0 40(S) Secondary Formula: State Match

0 0 0 0 0 0 65Soft Match: Federal

0 0 0 0 0 218 0STP: Bridge - Federal

0 0 0 0 0 54 0STP: Bridge - Soft Match

39 0 0 0 0 1,240 1,676STP: BROS - Federal

10 0 0 0 0 310 419STP: BROS - Soft Match

0 0 0 0 0 0 41(S) Telecommunications: State

0 0 0 0 0 49 1,821 4,968Total

MPO Area

NonMPOSecondary

PROGRAM/SYSTEM

RTE 617 - BRIDGE REPLACEMENT OVER

SAILORS CREEK

PROJECT

UPC NO.:

ROUTE:

84738

NFO0617

Complete

SCHEDULE

332

ESTIMATED COST (000's)

JURISDICTION:

SAYLERS CREEK ROADSTREET NAME:

PEAmelia County

Underway 777CNFROM: 1.450 MILE SOUTH OF RTE 618 TO: 1.497 MILE

SOUTH OF RTE 618 (0.0470 MI)

DESCRIPTION: RW

29291 81PROJECT LENGTH: 0.0470 MI STRUCTURE NO.: SUFFICIENCY RATING:

SCOPE OF WORK: Bridge Replacement w/o Added Capacity TO 1,109

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 60Bond Match: State Bond Match

0 0 0 0 0 0 240Bridge Replacement: Federal

0 0 0 0 0 0 382(S) Federal Formula STP: Federal

0 0 0 0 0 0 54(S) Federal Formula STP: State Bond Match

0 0 0 0 0 0 89(S) Secondary Formula: Federal

0 0 0 0 0 0 211(S) Secondary Formula: Federal/State

0 0 0 0 0 0 64(S) Secondary Formula: State Match

0 0 0 0 0 0 2(S) SSYP - Incidental: Federal

0 0 0 0 0 0 8(S) Telecommunications: State

0 0 0 0 0 0 0 1,109Total

752 11/12/2014

Page 55: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Secondary

MPO Area

NonMPOSecondary

PROGRAM/SYSTEM

RTE 620 - BRIDGE REPLACEMENT

PROJECT

UPC NO.:

ROUTE:

91755

NFO0620

Underway

SCHEDULE

705

ESTIMATED COST (000's)

JURISDICTION:

STONEY POINT ROADSTREET NAME:

PEAmelia County

FY2015 1,305CN

UnderwayFROM: 1.567 MI N OF RTE 621 TO: 1.642 MI N OF RTE

621 (0.0620 MI)

DESCRIPTION: 119RW

29563 -1PROJECT LENGTH: 0.0740 MI STRUCTURE NO.: SUFFICIENCY RATING:

SCOPE OF WORK: Bridge Replacement w/ Added Capacity TO 2,129

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 22Bond Match: State Bond Match

0 0 0 0 0 0 366Bridge Replacement: Federal

0 0 0 0 0 0 50(S) Federal Formula STP: Federal

0 0 0 0 0 0 12(S) Federal Formula STP: State Bond Match

0 0 0 0 0 0 365(S) Secondary Formula: Federal/State

0 0 0 0 0 0 293(S) Secondary Formula: State

0 0 0 0 0 0 70Soft Match: Federal

0 0 0 0 0 0 124(S) State Formula: Secondary - Unpaved

0 0 0 0 177 57 0STP: Bridge - Federal

0 0 0 0 44 14 0STP: Bridge - Soft Match

392 0 0 0 55 30 75STP: BROS - Federal

98 0 0 0 14 7 19STP: BROS - Soft Match

0 0 0 0 0 0 37(S) Telecommunications: State

-192 0 0 0 290 490 108 1,433Total

MPO Area

NonMPOSecondary

PROGRAM/SYSTEM

RTE 660 - RURAL RUSTIC

PROJECT

UPC NO.:

ROUTE:

104200

NFO0660

Complete

SCHEDULE

5

ESTIMATED COST (000's)

JURISDICTION:

MILLS LANESTREET NAME:

PEAmelia County

Underway 108CNFROM: RTE 704 (MILLS CT) TO: END STATE

MAINTENANCE (0.9500 MI)

DESCRIPTION: RW

PROJECT LENGTH: 0.9500 MISCOPE OF WORK: Resurfacing TO 113

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 56Revenue Sharing Funds: Local Match

0 0 0 0 0 0 56Revenue Sharing Funds: State Match

0 0 0 0 0 0 0 113Total

MPO Area

NonMPOSecondary

PROGRAM/SYSTEM

RTE 666 - RURAL RUSTIC

PROJECT

UPC NO.:

ROUTE:

104199

NFO0666

Complete

SCHEDULE

5

ESTIMATED COST (000's)

JURISDICTION:

CEDAR LANESTREET NAME:

PEAmelia County

Underway 102CNFROM: RTE 614 (DENNISVILLE RD) TO: END STATE

MAINTENANCE (0.9000 MI)

DESCRIPTION: RW

PROJECT LENGTH: 0.9000 MISCOPE OF WORK: Resurfacing TO 107

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 54Revenue Sharing Funds: Local Match

0 0 0 0 0 0 54Revenue Sharing Funds: State Match

0 0 0 0 0 0 0 107Total

11/12/2014 753

Page 56: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Secondary

MPO Area

NonMPOSecondary

PROGRAM/SYSTEM

RTE 667 - PAVE UNPAVED ROAD

PROJECT

UPC NO.:

ROUTE:

105697

NFO0667

FY2015

SCHEDULE

5

ESTIMATED COST (000's)

JURISDICTION:

HAW BRANCH LANESTREET NAME:

PEAmelia County

FY2016 140CN

FROM: 1.00 ME 681 TO: DEAD END (0.9100 MI)DESCRIPTION: RW

PROJECT LENGTH: 1.0000 MISCOPE OF WORK: Reconstruction w/o Added Capacity TO 145

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 73 0Revenue Sharing Funds: Local Match

0 0 0 0 0 73 0Revenue Sharing Funds: State Match

0 0 0 0 0 0 145 0Total

MPO Area

NonMPOSecondary

PROGRAM/SYSTEM

RTE 680 - RURAL RUSTIC

PROJECT

UPC NO.:

ROUTE:

104206

NFO0680

Complete

SCHEDULE

2

ESTIMATED COST (000's)

JURISDICTION:

MAXEY LANESTREET NAME:

PEAmelia County

Underway 54CNFROM: RTE 614 (DENNISVILLE RD) TO: END STATE

MAINTENANCE (0.4500 MI)

DESCRIPTION: RW

PROJECT LENGTH: 0.4500 MISCOPE OF WORK: Resurfacing TO 56

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 28Revenue Sharing Funds: Local Match

0 0 0 0 0 0 28Revenue Sharing Funds: State Match

0 0 0 0 0 0 0 56Total

MPO Area

NonMPOSecondary

PROGRAM/SYSTEM

RTE 683 - RURAL RUSTIC

PROJECT

UPC NO.:

ROUTE:

104210

NFO0683

Complete

SCHEDULE

5

ESTIMATED COST (000's)

JURISDICTION:

CHULA SCHOOL LANESTREET NAME:

PEAmelia County

Underway 74CNFROM: RTE 705 (MT OLIVE LN) TO: END STATE

MAINTENANCE (0.6500 MI)

DESCRIPTION: RW

PROJECT LENGTH: 0.6500 MISCOPE OF WORK: Resurfacing TO 79

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 39Revenue Sharing Funds: Local Match

0 0 0 0 0 0 39Revenue Sharing Funds: State Match

0 0 0 0 0 0 0 79Total

754 11/12/2014

Page 57: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Secondary

MPO Area

NonMPOSecondary

PROGRAM/SYSTEM

RTE 684 - PAVE UNPAVED ROAD

PROJECT

UPC NO.:

ROUTE:

105696

NFO0684

FY2015

SCHEDULE

5

ESTIMATED COST (000's)

JURISDICTION:

MORRIS LANESTREET NAME:

PEAmelia County

FY2016 98CNFROM: 658 DRUNKARD LANE TO: END LANE (0.5400

MI)

DESCRIPTION: RW

PROJECT LENGTH: 0.7000 MISCOPE OF WORK: Reconstruction w/o Added Capacity TO 103

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 52 0Revenue Sharing Funds: Local Match

0 0 0 0 0 52 0Revenue Sharing Funds: State Match

0 0 0 0 0 0 103 0Total

MPO Area

NonMPOSecondary

PROGRAM/SYSTEM

RTE 688 - PAVE UNPAVED ROAD

PROJECT

UPC NO.:

ROUTE:

105698

NFO0688

FY2015

SCHEDULE

5

ESTIMATED COST (000's)

JURISDICTION:

SHADY LANESTREET NAME:

PEAmelia County

FY2016 84CN

FROM: 616 GENITO ROAD TO: DEAD END (0.6000 MI)DESCRIPTION: RW

PROJECT LENGTH: 0.6000 MISCOPE OF WORK: Reconstruction w/o Added Capacity TO 89

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 45 0Revenue Sharing Funds: Local Match

0 0 0 0 0 45 0Revenue Sharing Funds: State Match

0 0 0 0 0 0 89 0Total

MPO Area

NonMPOSecondary

PROGRAM/SYSTEM

RTE 689 - RURAL RUSTIC

PROJECT

UPC NO.:

ROUTE:

104208

NFO0689

Complete

SCHEDULE

2

ESTIMATED COST (000's)

JURISDICTION:

FLIPPEN LANESTREET NAME:

PEAmelia County

Underway 48CNFROM: DENNISVILLE RD (RTE 614) TO: END STATE

MAINTENANCE (0.4000 MI)

DESCRIPTION: RW

PROJECT LENGTH: 0.4000 MISCOPE OF WORK: Resurfacing TO 50

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 25Revenue Sharing Funds: Local Match

0 0 0 0 0 0 25Revenue Sharing Funds: State Match

0 0 0 0 0 0 0 50Total

11/12/2014 755

Page 58: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Secondary

MPO Area

NonMPOSecondary

PROGRAM/SYSTEM

RTE 695 - RURAL RUSTIC

PROJECT

UPC NO.:

ROUTE:

104209

NFO0695

Complete

SCHEDULE

2

ESTIMATED COST (000's)

JURISDICTION:

FLINN LANESTREET NAME:

PEAmelia County

Underway 48CNFROM: RTE 607 (WEST CREEK RD) TO: END STATE

MAINTENANCE (0.4000 MI)

DESCRIPTION: RW

PROJECT LENGTH: 0.4000 MISCOPE OF WORK: Resurfacing TO 50

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 25Revenue Sharing Funds: Local Match

0 0 0 0 0 0 25Revenue Sharing Funds: State Match

0 0 0 0 0 0 0 50Total

MPO Area

NonMPOSecondary

PROGRAM/SYSTEM

RTE 704 - RURAL RUSTIC

PROJECT

UPC NO.:

ROUTE:

104201

NFO0704

Complete

SCHEDULE

2

ESTIMATED COST (000's)

JURISDICTION:

MILLS COURTSTREET NAME:

PEAmelia County

Underway 37CNFROM: RTE 660 (MILLS LN) TO: END STATE

MAINTENANCE (0.3000 MI)

DESCRIPTION: RW

PROJECT LENGTH: 0.3000 MISCOPE OF WORK: Resurfacing TO 39

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 20Revenue Sharing Funds: Local Match

0 0 0 0 0 0 20Revenue Sharing Funds: State Match

0 0 0 0 0 0 0 39Total

MPO Area

NonMPOSecondary

PROGRAM/SYSTEM

RTE 710 - RURAL RUSTIC

PROJECT

UPC NO.:

ROUTE:

104211

NFO0710

Complete

SCHEDULE

2

ESTIMATED COST (000's)

JURISDICTION:

HILLS LANESTREET NAME:

PEAmelia County

Underway 20CNFROM: RTE 683 (CHULA SCHOOL LN) TO: END STATE

MAINTENANCE (0.1500 MI)

DESCRIPTION: RW

PROJECT LENGTH: 0.1500 MISCOPE OF WORK: Resurfacing TO 22

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 11Revenue Sharing Funds: Local Match

0 0 0 0 0 0 11Revenue Sharing Funds: State Match

0 0 0 0 0 0 0 22Total

756 11/12/2014

Page 59: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Secondary

MPO Area

NonMPOSecondary

PROGRAM/SYSTEM

RTE 714 - PAVE UNPAVED ROAD

PROJECT

UPC NO.:

ROUTE:

105699

NFO0714

FY2015

SCHEDULE

5

ESTIMATED COST (000's)

JURISDICTION:

PRIDES LANESTREET NAME:

PEAmelia County

FY2016 70CNFROM: 681 PRIDESVILLE ROAD TO: DEAD END (0.5000

MI)

DESCRIPTION: RW

PROJECT LENGTH: 0.5000 MISCOPE OF WORK: Reconstruction w/o Added Capacity TO 75

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 38 0Revenue Sharing Funds: Local Match

0 0 0 0 0 38 0Revenue Sharing Funds: State Match

0 0 0 0 0 0 75 0Total

MPO Area

NonMPOSecondary

PROGRAM/SYSTEM

RTE 717 - RURAL RUSTIC

PROJECT

UPC NO.:

ROUTE:

104207

NFO0717

Complete

SCHEDULE

2

ESTIMATED COST (000's)

JURISDICTION:

HALL ROADSTREET NAME:

PEAmelia County

Underway 26CNFROM: RTE 614 (DENNISVILLE RD) TO: END STATE

MAINTENANCE (0.2000 MI)

DESCRIPTION: RW

PROJECT LENGTH: 0.2000 MISCOPE OF WORK: Resurfacing TO 28

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 14Revenue Sharing Funds: Local Match

0 0 0 0 0 0 14Revenue Sharing Funds: State Match

0 0 0 0 0 0 0 28Total

MPO Area

NonMPOSecondary

PROGRAM/SYSTEM

RTE 735 - PAVE UNPAVED ROAD

PROJECT

UPC NO.:

ROUTE:

105695

NFO0735

FY2015

SCHEDULE

5

ESTIMATED COST (000's)

JURISDICTION:

BAILEY LANESTREET NAME:

PEAmelia County

FY2016 66CNFROM: 681 CLEMENTOWN ROAD TO: DEAD END

(0.4700 MI)

DESCRIPTION: RW

PROJECT LENGTH: 0.4700 MISCOPE OF WORK: Reconstruction w/o Added Capacity TO 71

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 35 0Revenue Sharing Funds: Local Match

0 0 0 0 0 35 0Revenue Sharing Funds: State Match

0 0 0 0 0 0 71 0Total

11/12/2014 757

Page 60: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Secondary

MPO Area

NonMPOSecondary

PROGRAM/SYSTEM

RURAL ADDITION FOR BRUNSWICK COUNTY

(RS FY13)

PROJECT

UPC NO.:

ROUTE:

102923

NFO

Underway

SCHEDULE

2

ESTIMATED COST (000's)

JURISDICTION:

JOHNSON RUN ROADSTREET NAME:

PEBrunswick County

FY2015 48CNFROM: BRUNSWICK/GREENSVILLE COUNTY LINE TO:

END OF STATE MAINTENANCE (0.2000 MI)

DESCRIPTION: RW

PROJECT LENGTH: 1.2000 MISCOPE OF WORK: Reconstruction w/o Added Capacity TO 50

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 50Revenue Sharing Funds: Local Match

0 0 0 0 0 0 50Revenue Sharing Funds: State Match

0 0 0 0 0 0 1(S) Telecommunications: State

-51 0 0 0 0 0 0 101Total

MPO Area

NonMPOSecondary

PROGRAM/SYSTEM

BRIDGE ( FED ID 3658) RTE 609 OVER

NOTTOWAY RIVER

PROJECT

UPC NO.:

ROUTE:

105490

NFO0609

FY2018

SCHEDULE

314

ESTIMATED COST (000's)

JURISDICTION:

STREET NAME:

PEBrunswick County

FY2020 1,568CN

FY2019DESCRIPTION: 209RW

PROJECT LENGTH: _SCOPE OF WORK: Bridge Replacement w/ Added Capacity TO 2,090

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 500 254 80 0 0 0STP: BROS - Federal

0 125 64 20 0 0 0STP: BROS - Soft Match

1,047 625 318 100 0 0 0 0Total

MPO Area

NonMPOSecondary

PROGRAM/SYSTEM

RTE 630 - BRIDGE REPLACEMENT

PROJECT

UPC NO.:

ROUTE:

101241

NFO0630

.REPORT NOTE:

FY2017

SCHEDULE

200

ESTIMATED COST (000's)

JURISDICTION:

Waqua Creek RoadSTREET NAME:

PEBrunswick County

FY2019 1,125CN

FY2018FROM: APPROACHES AND BRIDGE OVER WAQUA

CREEK (STR 6033) TO: APPROACHES AND BRIDGE

OVER WAQUA CREEK (STR 6033) (4.0300 MI)

DESCRIPTION: 100RW

PROJECT LENGTH: 0.0000 MISCOPE OF WORK: Bridge Replacement w/o Added Capacity TO 1,425

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 740 60 40 300 0 0STP: BROS - Federal

0 185 15 10 75 0 0STP: BROS - Soft Match

0 925 75 50 375 0 0 0Total

758 11/12/2014

Page 61: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Secondary

MPO Area

NonMPOSecondary

PROGRAM/SYSTEM

RTE 642 - PAVE UNPAVED ROAD

PROJECT

UPC NO.:

ROUTE:

105700

NFO0642

FY2015

SCHEDULE

2

ESTIMATED COST (000's)

JURISDICTION:

ZERO ROADSTREET NAME:

PEBrunswick County

FY2016 48CNFROM: INTERSECTION OF RTE 643, FLAT TOCK ROAD

TO: .4 MI NORTH OF RTE 643, FLAT ROCK ROAD

(0.4000 MI)

DESCRIPTION: RW

PROJECT LENGTH: 0.4000 MISCOPE OF WORK: Reconstruction w/o Added Capacity TO 50

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 25 0Revenue Sharing Funds: Local Match

0 0 0 0 0 25 0Revenue Sharing Funds: State Match

0 0 0 0 0 0 50 0Total

MPO Area

NonMPOSecondary

PROGRAM/SYSTEM

RTE 712 - BRIDGE REPLACEMENT

PROJECT

UPC NO.:

ROUTE:

77053

NFO0712

Underway

SCHEDULE

765

ESTIMATED COST (000's)

JURISDICTION:

OLD STAGE ROADSTREET NAME:

PEBrunswick County

FY2015 3,355CN

UnderwayFROM: 1.617 MI. S. Rte. 85 TO: 1.9 MI. S. Rte. 85

(0.2830 MI)

DESCRIPTION: 96RW

PROJECT LENGTH: 0.2830 MISCOPE OF WORK: Bridge Replacement w/o Added Capacity TO 4,216

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 58Bridge Replacement: Federal

0 0 0 0 0 0 224(S) Federal Formula STP: Federal

0 0 0 0 0 0 48(S) Federal Formula STP: State Bond Match

0 0 0 0 0 0 140(S) Secondary Formula: Federal

0 0 0 0 0 0 43(S) Secondary Formula: State Match

0 0 0 0 0 0 15Soft Match: Federal

1,133 0 0 0 968 765 168STP: Bridge - Federal

283 0 0 0 242 191 42STP: Bridge - Soft Match

0 0 0 0 0 0 9(S) Telecommunications: State

-111 0 0 0 1,210 1,416 956 746Total

11/12/2014 759

Page 62: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Secondary

MPO Area

NonMPOSecondary

PROGRAM/SYSTEM

RTE 712 - APPROACHES & BRIDGE OVER

STURGEON CREEK

PROJECT

UPC NO.:

ROUTE:

85441

NFO0712

Underway

SCHEDULE

711

ESTIMATED COST (000's)

JURISDICTION:

OLD STAGE ROADSTREET NAME:

PEBrunswick County

FY2015 2,200CN

UnderwayFROM: 0.131 MI S STURGEON CR TO: 0.113 MI N

STURGEON CR (0.2200 MI)

DESCRIPTION: 144RW

29521 -1PROJECT LENGTH: 0.2440 MI STRUCTURE NO.: SUFFICIENCY RATING:

SCOPE OF WORK: Bridge Replacement w/o Added Capacity TO 3,055

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 42Bond Match: State Bond Match

0 0 0 0 0 0 666Bridge Replacement: Federal

0 0 0 0 0 0 125Soft Match: Federal

564 0 0 538 233 630 0STP: Bridge - Federal

141 0 0 135 58 158 0STP: Bridge - Soft Match

0 0 0 0 0 0 1(S) Telecommunications: State

-235 0 0 673 291 705 788 834Total

MPO Area

NonMPOSecondary

PROGRAM/SYSTEM

RTE 715 - BRIDGE REPLACEMENT

PROJECT

UPC NO.:

ROUTE:

93091

NFO0715

Underway

SCHEDULE

700

ESTIMATED COST (000's)

JURISDICTION:

STREET NAME:

PEBrunswick County

FY2018 3,514CN

FY2018At Meherrin River (0.1400 MI)DESCRIPTION: 104RW

PROJECT LENGTH: _SCOPE OF WORK: Bridge Replacement w/o Added Capacity TO 4,319

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 600 565 0 0 0 0CTB Formula: Bridge - State

219 992 294 285 80 225 0STP: Bridge - Federal

55 248 73 71 20 56 0STP: Bridge - Soft Match

535 1,840 932 356 100 273 282 0Total

MPO Area

RichmondSecondary

PROGRAM/SYSTEM

RTE 607 - MINOR WIDENING

PROJECT

UPC NO.:

ROUTE:

59166

NFO0607

MPO Project.REPORT NOTE:

Underway

SCHEDULE

500

ESTIMATED COST (000's)

JURISDICTION:

WAYSIDE ROADSTREET NAME:

PECharles City County

FY2017 1,096CN

UnderwayFROM: 0.035 Miles East Rte 639 (The New Road) TO:

0.518 Miles East Rte 639 (The New Road) (0.4830 MI)

DESCRIPTION: 535RW

PROJECT LENGTH: 0.4830 MISCOPE OF WORK: Reconstruction w/o Added Capacity TO 2,131

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 252Non-Formula: State Match

0 0 0 0 0 0 1,946RSTP (STP Regional): Federal

0 0 0 0 0 0 234RSTP (STP Regional): State Match

-301 0 0 0 0 0 0 2,433Total

760 11/12/2014

Page 63: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Secondary

MPO Area

RichmondSecondary

PROGRAM/SYSTEM

RTE 609 - RECONSTRUCTION

PROJECT

UPC NO.:

ROUTE:

85337

NFO0609

MPO Project. Revised schedule required. Balance to be provided by MPO.REPORT NOTE:

Underway

SCHEDULE

665

ESTIMATED COST (000's)

JURISDICTION:

BARNETTS ROADSTREET NAME:

PECharles City County

FY2015 823CN

FY2014FROM: RTE 602 (LOTT CARY RD) TO: RTE 603 (OLD

UNION RD) (0.2400 MI)

DESCRIPTION: 802RW

PROJECT LENGTH: 1.1900 MISCOPE OF WORK: Reconstruction w/o Added Capacity TO 2,290

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 1,779RSTP (STP Regional): Federal

0 0 0 0 0 0 445RSTP (STP Regional): State Match

66 0 0 0 0 0 0 2,224Total

MPO Area

RichmondSecondary

PROGRAM/SYSTEM

ROUTE 618 - MULTI-USE TRAIL

PROJECT

UPC NO.:

ROUTE:

102507

NFO0618

MPO Project. Excess funds to be redistributed by MPO. Revised schedule required.REPORT NOTE:

Underway

SCHEDULE

185

ESTIMATED COST (000's)

JURISDICTION:

WILCOX WHARF ROADSTREET NAME:

PECharles City County

FY2014 509CN

UnderwayFROM: ROUTE 5 TO: 0.801 MI. S. RTE 5 (0.8010 MI)DESCRIPTION: 54RW

PROJECT LENGTH: 0.8010 MISCOPE OF WORK: Facilities for Pedestrians and Bicycles TO 748

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 63Non-Formula: State Match

0 0 0 0 0 0 712RSTP (STP Regional): Federal

0 0 0 0 0 0 115RSTP (STP Regional): State Match

-142 0 0 0 0 0 0 890Total

MPO Area

Tri-CitiesSecondary

PROGRAM/SYSTEM

RTE 600 - REALIGN INTERSECTION

PROJECT

UPC NO.:

ROUTE:

101028

NFO0600

MPO Project. Excess funds to be redistributed by MPO.REPORT NOTE:

Underway

SCHEDULE

254

ESTIMATED COST (000's)

JURISDICTION:

Matoaca RoadSTREET NAME:

PEChesterfield County

FY2019 1,385CN

FY2018FROM: 0.2 MI S RTE 626 (Hickory Road) TO: 0.2 MI N

RTE 626 (Hickory Road) (0.4000 MI)

DESCRIPTION: 650RW

PROJECT LENGTH: 0.4000 MISCOPE OF WORK: Safety TO 2,290

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 91RSTP (STP Regional): Federal

17 884 537 207 0 113 0RSTP (STP Regional): MPO - Federal

4 221 134 52 0 28 0RSTP (STP Regional): MPO - State Match

0 0 0 0 0 0 23RSTP (STP Regional): State Match

-21 1,105 672 259 0 21 141 113Total

11/12/2014 761

Page 64: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Secondary

MPO Area

RichmondSecondary

PROGRAM/SYSTEM

RTE 604 - ADD SIDEWALK

PROJECT

UPC NO.:

ROUTE:

96733

NFO0604

Underway

SCHEDULE

101

ESTIMATED COST (000's)

JURISDICTION:

GENITO ROADSTREET NAME:

PEChesterfield County

FY2015 149CN

UnderwayFROM: 0.003 MI RTE 759 (STIGALL DR) TO: 0.007 MI

RTE 906 (PRICE CLUB BLVD) (0.1894 MI)

DESCRIPTION: 29RW

PROJECT LENGTH: 0.1894 MISCOPE OF WORK: Facilities for Pedestrians and Bicycles TO 280

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 286Highway Safety Improvements: Federal

0 0 0 0 0 0 32Highway Safety Improvements: State Match

-39 0 0 0 0 0 0 318Total

MPO Area

RichmondSecondary

PROGRAM/SYSTEM

RTE 604 - ADD SIDEWALK

PROJECT

UPC NO.:

ROUTE:

100560

NFO0604

Underway

SCHEDULE

151

ESTIMATED COST (000's)

JURISDICTION:

GENITO ROADSTREET NAME:

PEChesterfield County

FY2015 227CN

UnderwayFROM: 0.003 MI E RTE 759 (STIGALL DR) TO: 0.007 MI

W RTE 906 (PRICE CLUB BLVD) (0.3551 MI)

DESCRIPTION: 99RW

PROJECT LENGTH: 0.3551 MISCOPE OF WORK: Facilities for Pedestrians and Bicycles TO 477

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 439Highway Safety Improvements: Federal

0 0 0 0 0 0 49Highway Safety Improvements: State Match

-10 0 0 0 0 0 0 487Total

MPO Area

RichmondSecondary

PROGRAM/SYSTEM

RTE 604 - REPLACE BRIDGE OVER

TOMAHAWK CREEK

PROJECT

UPC NO.:

ROUTE:

101243

NFO0604

Underway

SCHEDULE

750

ESTIMATED COST (000's)

JURISDICTION:

Genito RoadSTREET NAME:

PEChesterfield County

FY2016 3,075CN

FY2015FROM: 0.651 Mi. E. Rte 668 (Woolridge Road) TO: 0.712

Mi. E. Rte 668 (Woolridge Road) (0.0610 MI)

DESCRIPTION: 112RW

30028 -1PROJECT LENGTH: 0.0610 MI STRUCTURE NO.: SUFFICIENCY RATING:

SCOPE OF WORK: Bridge Replacement w/o Added Capacity TO 3,937

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 270Bridge Replacement: Federal

0 0 0 0 0 0 68Soft Match: Federal

100 0 0 1,636 690 453 0STP: Bridge - Federal

25 0 0 409 173 113 0STP: Bridge - Soft Match

0 0 0 2,045 863 125 567 338Total

762 11/12/2014

Page 65: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Secondary

MPO Area

RichmondSecondary

PROGRAM/SYSTEM

RTE 609 - INSTALL SIDEWALK

PROJECT

UPC NO.:

ROUTE:

104288

NFO0609

Underway

SCHEDULE

100

ESTIMATED COST (000's)

JURISDICTION:

OLD CENTRALIA ROADSTREET NAME:

PEChesterfield County

FY2015 380CN

FY2015FROM: CASTLEBURY DR TO: GLEN OAKS CT (0.5000

MI)

DESCRIPTION: 20RW

PROJECT LENGTH: 0.5000 MISCOPE OF WORK: Safety TO 500

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 250Revenue Sharing Funds: Local Match

0 0 0 0 0 0 250Revenue Sharing Funds: State Match

0 0 0 0 0 0 0 500Total

MPO Area

RichmondSecondary

PROGRAM/SYSTEM

RTE 618 - RECONSTRUCT SHOULDER AND

DITCHES

PROJECT

UPC NO.:

ROUTE:

104286

NFO0618

Revised schedule required.REPORT NOTE:

Underway

SCHEDULE

400

ESTIMATED COST (000's)

JURISDICTION:

OLD BERMUDA HUNDRED ROADSTREET NAME:

PEChesterfield County

FY2015 1,800CN

FY2014FROM: RTE 95 TO: EAST OF OLD STAGE RD (0.4000

MI)

DESCRIPTION: 300RW

PROJECT LENGTH: 0.4000 MISCOPE OF WORK: Safety TO 2,500

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 1,250Revenue Sharing Funds: Local Match

0 0 0 0 0 0 1,250Revenue Sharing Funds: State Match

0 0 0 0 0 0 0 2,500Total

MPO Area

NonMPOSecondary

PROGRAM/SYSTEM

RTE 618 - RECONSTRUCTION

PROJECT

UPC NO.:

ROUTE:

105648

NFO0618

Underway

SCHEDULE

800

ESTIMATED COST (000's)

JURISDICTION:

OLD BERMUDA HUNDRED RDSTREET NAME:

PEChesterfield County

FY2020 6,400CN

FY2017FROM: OLD STAGE RD, RT 732 TO: RT 10 (2.2000 MI)DESCRIPTION: 800RW

PROJECT LENGTH: 2.2000 MISCOPE OF WORK: Reconstruction w/o Added Capacity TO 8,000

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 4,000 0Local Project Contributions: Local

0 0 0 0 0 2,000 0Revenue Sharing Funds: Local Match

0 0 0 0 0 2,000 0Revenue Sharing Funds: State Match

0 0 0 0 0 0 8,000 0Total

11/12/2014 763

Page 66: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Secondary

MPO Area

RichmondSecondary

PROGRAM/SYSTEM

RTE 636 - WIDENING & RECONSTRUCTION

PROJECT

UPC NO.:

ROUTE:

16409

NFO0636

Complete

SCHEDULE

724

ESTIMATED COST (000's)

JURISDICTION:

NASH ROADSTREET NAME:

PEChesterfield County

Underway 2,808CN

UnderwayFROM: 0.108 MILE SOUTH ROUTE 5186 (EAST FAIR

DRIVE) TO: 0.703 MILE SOUTH ROUTE 655 (BEACH

ROAD) (1.0800 MI)

DESCRIPTION: 1,150RW

PROJECT LENGTH: 1.0800 MISCOPE OF WORK: Reconstruction w/ Added Capacity TO 4,682

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 587Non-Formula: State Match

0 0 0 0 0 0 109Revenue Sharing Funds: Local Match

0 0 0 0 0 0 109Revenue Sharing Funds: State Match

0 0 0 0 0 0 3,390RSTP (STP Regional): Federal

0 0 0 0 0 0 260RSTP (STP Regional): State Match

0 0 0 0 0 0 14(S) Secondary Formula: Federal

0 0 0 0 0 0 194(S) Secondary Formula: Federal/State

0 0 0 0 0 0 240(S) Secondary Formula: State

0 0 0 0 0 0 4(S) Secondary Formula: State Match

-224 0 0 0 0 0 0 4,906Total

MPO Area

RichmondSecondary

PROGRAM/SYSTEM

RTE 636 - BRIDGE REPLACEMENT

PROJECT

UPC NO.:

ROUTE:

103469

NFO0636

Revised schedule required.REPORT NOTE:

Underway

SCHEDULE

400

ESTIMATED COST (000's)

JURISDICTION:

NASH ROADSTREET NAME:

PEChesterfield County

FY2019 2,200CN

FY2018FROM: 0.50 MI S RTE 635 (REEDY BRANCH ROAD) TO:

0.52 MI S RTE 635 (REEDY BRANCH ROAD)

(0.0020 MI)

DESCRIPTION: 400RW

PROJECT LENGTH: 0.0020 MISCOPE OF WORK: Bridge Replacement w/o Added Capacity TO 3,000

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 165 0 0 0 0CTB Formula: Bridge - State

0 0 95 0 0 0 0CTB Formula: High Priority - State

400 0 728 945 666 0 0(S) Telecommunications: State

0 0 988 945 666 400 0 0Total

MPO Area

Tri-CitiesSecondary

PROGRAM/SYSTEM

RTE 638 & 611 - CONSTRUCT ROUNDABOUT

PROJECT

UPC NO.:

ROUTE:

106197

NFO0638

FY2016

SCHEDULE

300

ESTIMATED COST (000's)

JURISDICTION:

Hopkins RoadSTREET NAME:

PEChesterfield County

FY2018 1,200CN

FY2017FROM: 0.20 Mi. North Rte. 638 TO: 0.20 Mi. South Rte.

638 (0.4000 MI)

DESCRIPTION: 150RW

PROJECT LENGTH: 0.4000 MISCOPE OF WORK: Safety TO 1,650

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

270 0 0 1,080 135 0 0Highway Safety Improvements: Federal

30 0 0 120 15 0 0Highway Safety Improvements: Soft Match

0 0 0 1,200 150 300 0 0Total

764 11/12/2014

Page 67: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Secondary

MPO Area

NonMPOSecondary

PROGRAM/SYSTEM

RTE 641 - RECONSTRUCTION

PROJECT

UPC NO.:

ROUTE:

105673

NFO0641

Underway

SCHEDULE

300

ESTIMATED COST (000's)

JURISDICTION:

BEULAH RDSTREET NAME:

PEChesterfield County

FY2019 1,800CN

FY2017FROM: KINGSLAND RD RT 611 TO: PINELEAF DR RT

3428 (0.4000 MI)

DESCRIPTION: 400RW

PROJECT LENGTH: 0.4000 MISCOPE OF WORK: Reconstruction w/o Added Capacity TO 2,500

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 1,900 0Local Project Contributions: Local

0 0 0 0 0 300 0Revenue Sharing Funds: Local Match

0 0 0 0 0 300 0Revenue Sharing Funds: State Match

0 0 0 0 0 0 2,500 0Total

MPO Area

RichmondSecondary

PROGRAM/SYSTEM

RTE 642 - ADD SIDEWALK

PROJECT

UPC NO.:

ROUTE:

96732

NFO0642

Complete

SCHEDULE

155

ESTIMATED COST (000's)

JURISDICTION:

SALEM CHURCH ROADSTREET NAME:

PEChesterfield County

Underway 420CN

UnderwayFROM: 0.030 MI South of Rte. 1903 (Chanson Road) TO:

0.17 MI North of Rte. 1903 (Chanson Road) (0.2000 MI)

DESCRIPTION: 100RW

PROJECT LENGTH: 0.2000 MISCOPE OF WORK: Facilities for Pedestrians and Bicycles TO 675

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 664Highway Safety Improvements: Federal

0 0 0 0 0 0 74Highway Safety Improvements: State Match

-62 0 0 0 0 0 0 738Total

MPO Area

RichmondSecondary

PROGRAM/SYSTEM

RTE 642 - ADD SIDEWALK

PROJECT

UPC NO.:

ROUTE:

104883

NFO0642

MPO Project. Balance to be provided by MPO.REPORT NOTE:

Underway

SCHEDULE

100

ESTIMATED COST (000's)

JURISDICTION:

SALEM CHURCH ROADSTREET NAME:

PEChesterfield County

FY2016 275CNFROM: FOX HOLLOW DR TO: SARA KAY DR (0.1100

MI)

DESCRIPTION: RW

PROJECT LENGTH: 0.1100 MISCOPE OF WORK: Safety TO 375

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

176 0 0 0 0 0 104CMAQ: MPO - Federal

44 0 0 0 0 0 26CMAQ: MPO - State Match

25 0 0 0 0 220 0 130Total

11/12/2014 765

Page 68: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Secondary

MPO Area

NonMPOSecondary

PROGRAM/SYSTEM

RTE 643 - RECONSTRUCTION

PROJECT

UPC NO.:

ROUTE:

105669

NFO0643

Underway

SCHEDULE

400

ESTIMATED COST (000's)

JURISDICTION:

JESSUP RDSTREET NAME:

PEChesterfield County

FY2019 2,500CN

FY2017FROM: RT 10 TO: PINELAND RD RT 2145 (0.3000 MI)DESCRIPTION: 500RW

PROJECT LENGTH: 0.3000 MISCOPE OF WORK: Reconstruction w/o Added Capacity TO 3,400

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 1,700 0Revenue Sharing Funds: Local Match

0 0 0 0 0 1,700 0Revenue Sharing Funds: State Match

0 0 0 0 0 0 3,400 0Total

MPO Area

RichmondSecondary

PROGRAM/SYSTEM

RTE 647 (REAMS RD) - INTERSECTION

IMPROVEMENTS

PROJECT

UPC NO.:

ROUTE:

70092

NFO0647

MPO Project. Excess funds to be redistributed by MPO.REPORT NOTE:

Complete

SCHEDULE

523

ESTIMATED COST (000's)

JURISDICTION:

REAMS ROADSTREET NAME:

PEChesterfield County

Underway 2,414CN

UnderwayFROM: 0.047 MILE WEST INTERSECTION RTE 2588

(ROSEGILL) TO: 0.062 MILE EAST INTERSECTION RTE

2588 (ROSEGILL) (0.1090 MI)

DESCRIPTION: 1,045RW

PROJECT LENGTH: 0.1090 MISCOPE OF WORK: Safety TO 3,982

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 192Non-Formula: State Match

0 0 0 0 0 0 2,598RSTP (STP Regional): Federal

0 0 0 0 0 393 180RSTP (STP Regional): MPO - Federal

0 0 0 0 0 98 45RSTP (STP Regional): MPO - State Match

0 0 0 0 0 0 458RSTP (STP Regional): State Match

0 0 0 0 0 0 289(S) Secondary Formula: Federal/State

-271 0 0 0 0 0 491 3,762Total

766 11/12/2014

Page 69: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Secondary

MPO Area

RichmondSecondary

PROGRAM/SYSTEM

RTE 649 - RECONSTRUCTION

PROJECT

UPC NO.:

ROUTE:

17179

NFO0649

Revised schedule requiredREPORT NOTE:

Complete

SCHEDULE

423

ESTIMATED COST (000's)

JURISDICTION:

NEWBYS BRIDGE RDSTREET NAME:

PEChesterfield County

Underway 1,755CN

FY2014FROM: 0.307 MI S RTE 3186 (SUSSEX DR) TO: RTE

3186 (SUSSEX DR) (0.3300 MI)

DESCRIPTION: 683RW

PROJECT LENGTH: 0.3070 MISCOPE OF WORK: Reconstruction w/o Added Capacity TO 2,861

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 27(S) Residue Parcel Revenue: State

0 0 0 0 0 0 404Revenue Sharing Funds: Local Match

0 0 0 0 0 0 404Revenue Sharing Funds: State Match

0 0 0 0 0 0 746RSTP (STP Regional): Federal

0 0 0 0 0 0 187RSTP (STP Regional): State Match

0 0 0 0 0 0 387(S) Secondary Formula: Federal/State

0 0 0 0 0 0 3(S) Secondary Formula: State

0 0 0 0 0 0 1,260(S) Telecommunications: State

-555 0 0 0 0 0 0 3,416Total

MPO Area

RichmondSecondary

PROGRAM/SYSTEM

RTE 649 - MINOR WIDENING

PROJECT

UPC NO.:

ROUTE:

104289

NFO0649

Revised schedule required.REPORT NOTE:

Underway

SCHEDULE

300

ESTIMATED COST (000's)

JURISDICTION:

NEWBY'S BRIDGE ROADSTREET NAME:

PEChesterfield County

FY2015 3,435CN

FY2014FROM: Rte. 914 (HAGOOD LN) TO: Rte. 638 (BELMONT

RD) (0.5900 MI)

DESCRIPTION: 300RW

PROJECT LENGTH: 0.7000 MISCOPE OF WORK: Safety TO 4,035

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 1,068 950Revenue Sharing Funds: Local Match

0 0 0 0 0 1,068 950Revenue Sharing Funds: State Match

0 0 0 0 0 0 2,135 1,900Total

11/12/2014 767

Page 70: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Secondary

MPO Area

RichmondSecondary

PROGRAM/SYSTEM

RTE 653 - SB RIGHT TURN LANE

IMPROVEMENT

PROJECT

UPC NO.:

ROUTE:

67967

NFO0653

MPO Project.REPORT NOTE:

Complete

SCHEDULE

906

ESTIMATED COST (000's)

JURISDICTION:

COURTHOUSE ROADSTREET NAME:

PEChesterfield County

Underway 3,086CN

UnderwayFROM: RTE 360 TO: RTE 679 CONNECTOR (0.3740 MI)DESCRIPTION: 2,365RW

PROJECT LENGTH: 0.3740 MISCOPE OF WORK: Safety TO 6,356

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 4,015CMAQ: Federal

0 0 0 0 0 0 362CMAQ: MPO - Federal

0 0 0 0 0 0 90CMAQ: MPO - State Match

0 0 0 0 0 0 620CMAQ: State Match

0 0 0 0 0 0 20Non-Formula: State Match

0 0 0 0 0 0 3(S) Residue Parcel Revenue: State

0 0 0 0 0 0 82RSTP (STP Regional): Federal

0 0 0 0 0 0 384(S) Secondary Formula: Federal/State

0 0 0 0 0 0 165(S) Secondary Formula: State

0 0 0 0 0 0 1,118(S) Telecommunications: State

-502 0 0 0 0 0 0 6,859Total

MPO Area

RichmondSecondary

PROGRAM/SYSTEM

RTE 668 - IMPROVE CURVE

PROJECT

UPC NO.:

ROUTE:

19060

NFO0668

Complete

SCHEDULE

211

ESTIMATED COST (000's)

JURISDICTION:

WOOLRIDGE ROADSTREET NAME:

PEChesterfield County

Underway 1,320CN

UnderwayFROM: 0.105 mi N of intersection with Red Fern Ct (Rte

7190) TO: 0.126 mi S of Intersection with Crown Point Rd

(Rte 3699) (0.1750 MI)

DESCRIPTION: 239RW

PROJECT LENGTH: 0.1750 MISCOPE OF WORK: Safety TO 1,770

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 63Highway Safety Improvements: Federal

0 0 0 0 0 0 7Highway Safety Improvements: State Match

0 0 0 0 0 0 1,104Local Project Contributions: Local

0 0 0 0 0 0 532Safety Funds: Hazard Elimination

0 0 0 0 0 0 63(S) Secondary Formula: Federal/State

0 0 0 0 0 0 0 1,770Total

768 11/12/2014

Page 71: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Secondary

MPO Area

NonMPOSecondary

PROGRAM/SYSTEM

RTE 672 - WIDENING (EX. 2 TO 4 LANES)

PROJECT

UPC NO.:

ROUTE:

105676

NFO0672

Underway

SCHEDULE

400

ESTIMATED COST (000's)

JURISDICTION:

ARCH RDSTREET NAME:

PEChesterfield County

FY2019 1,500CN

FY2017FROM: RT 60 TO: BRUNDIDGE RD (0.3000 MI)DESCRIPTION: 600RW

PROJECT LENGTH: 0.3000 MISCOPE OF WORK: Reconstruction w/ Added Capacity TO 2,500

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 1,135 0Local Project Contributions: Local

0 0 0 0 0 683 0Revenue Sharing Funds: Local Match

0 0 0 0 0 683 0Revenue Sharing Funds: State Match

0 0 0 0 0 0 2,500 0Total

MPO Area

RichmondSecondary

PROGRAM/SYSTEM

RTE 678 - CONSTRUCT CURB, GUTTER &

SIDEWALK

PROJECT

UPC NO.:

ROUTE:

104287

NFO0678

Underway

SCHEDULE

200

ESTIMATED COST (000's)

JURISDICTION:

PROVIDENCE ROADSTREET NAME:

PEChesterfield County

FY2015 3,000CN

UnderwayFROM: RTE 60 TO: RTE 2661 (WOODWARD DR) (0.5140

MI)

DESCRIPTION: 400RW

PROJECT LENGTH: 0.5030 MISCOPE OF WORK: Safety TO 3,600

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 1,800Revenue Sharing Funds: Local Match

0 0 0 0 0 0 1,800Revenue Sharing Funds: State Match

0 0 0 0 0 0 0 3,600Total

MPO Area

RichmondSecondary

PROGRAM/SYSTEM

RTE 711 - PAVE SHOULDER

PROJECT

UPC NO.:

ROUTE:

104884

NFO0711

MPO Project.REPORT NOTE:

Underway

SCHEDULE

130

ESTIMATED COST (000's)

JURISDICTION:

ROBIOUS ROADSTREET NAME:

PEChesterfield County

FY2017 270CN

FY2016FROM: SALISBURY DRIVE TO: JAMES RIVER ROAD

(1.2640 MI)

DESCRIPTION: 100RW

PROJECT LENGTH: 1.2640 MISCOPE OF WORK: Safety TO 500

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

296 0 0 0 0 0 104CMAQ: MPO - Federal

74 0 0 0 0 0 26CMAQ: MPO - State Match

0 0 0 0 0 370 0 130Total

11/12/2014 769

Page 72: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Secondary

MPO Area

RichmondSecondary

PROGRAM/SYSTEM

RTE 720 - WIDEN TO 4 LANES

PROJECT

UPC NO.:

ROUTE:

104290

NFO0720

Underway

SCHEDULE

400

ESTIMATED COST (000's)

JURISDICTION:

LUCKS LANESTREET NAME:

PEChesterfield County

FY2015 3,100CN

UnderwayFROM: RTE 2780 (SPIREA RD) TO: RTE 3970 (EAST

EVERGREEN PKWY) (0.5300 MI)

DESCRIPTION: 100RW

PROJECT LENGTH: 0.5300 MISCOPE OF WORK: Reconstruction w/ Added Capacity TO 3,600

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 1,800Revenue Sharing Funds: Local Match

0 0 0 0 0 0 1,800Revenue Sharing Funds: State Match

0 0 0 0 0 0 0 3,600Total

MPO Area

NonMPOSecondary

PROGRAM/SYSTEM

RTE 720 - WIDENING (EX. 2 TO 4 LANES)

PROJECT

UPC NO.:

ROUTE:

105674

NFO0720

Underway

SCHEDULE

600

ESTIMATED COST (000's)

JURISDICTION:

LUCKS LANESTREET NAME:

PEChesterfield County

FY2019 5,100CN

FY2017FROM: E. EVERGREEN PKWY RT 3970 TO: RT 288

(1.2000 MI)

DESCRIPTION: 800RW

PROJECT LENGTH: 1.2000 MISCOPE OF WORK: Reconstruction w/ Added Capacity TO 6,500

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 3,000 0Local Project Contributions: Local

0 0 0 0 0 1,750 0Revenue Sharing Funds: Local Match

0 0 0 0 0 1,750 0Revenue Sharing Funds: State Match

0 0 0 0 0 0 6,500 0Total

MPO Area

RichmondSecondary

PROGRAM/SYSTEM

RTE 754 - ADD SIDEWALK

PROJECT

UPC NO.:

ROUTE:

100559

NFO0754

Complete

SCHEDULE

117

ESTIMATED COST (000's)

JURISDICTION:

COALFIELD ROADSTREET NAME:

PEChesterfield County

Underway 207CN

UnderwayFROM: 0.015 MI NORTH OF WATKINS ELEMENTARY

SCHOOL TO: 0.007 MI SOUTH OF RTE 4671

(SYCAMORE VILLAGE DRIVE) (0.1220 MI)

DESCRIPTION: 109RW

PROJECT LENGTH: 0.1220 MISCOPE OF WORK: Facilities for Pedestrians and Bicycles TO 434

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 397Highway Safety Improvements: Federal

0 0 0 0 0 0 44Highway Safety Improvements: State Match

-7 0 0 0 0 0 0 441Total

770 11/12/2014

Page 73: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Secondary

MPO Area

Tri-CitiesSecondary

PROGRAM/SYSTEM

RTE 1107 - WIDENING

PROJECT

UPC NO.:

ROUTE:

104083

NFO1107

Complete

SCHEDULE

600

ESTIMATED COST (000's)

JURISDICTION:

EAST RIVER ROADSTREET NAME:

PEChesterfield County

Underway 6,250CN

UnderwayFROM: INT. ROUTE 36 (CHESTERFIELD AVENUE) TO:

INT. ROUTE 1106 (DUPUY ROAD) (0.7400 MI)

DESCRIPTION: 650RW

PROJECT LENGTH: 0.7400 MISCOPE OF WORK: Reconstruction w/ Added Capacity TO 7,500

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 4,750Revenue Sharing Funds: Local Match

0 0 0 0 0 0 4,750Revenue Sharing Funds: State Match

-2,000 0 0 0 0 0 0 9,500Total

MPO Area

RichmondSecondary

PROGRAM/SYSTEM

RTE 4700 - CONSTRUCT CURB, GUTTER AND

SIDEWALK

PROJECT

UPC NO.:

ROUTE:

104285

NFO4700

Underway

SCHEDULE

110

ESTIMATED COST (000's)

JURISDICTION:

DEER RUN DRIVESTREET NAME:

PEChesterfield County

FY2015 1,870CN

FY2015FROM: HULL STREET ROAD (RTE 360) TO: CHITAL

DRIVE (RTE4730) (0.5500 MI)

DESCRIPTION: 20RW

PROJECT LENGTH: 0.5500 MISCOPE OF WORK: Safety TO 2,000

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 865Local Project Contributions: Local

0 0 0 0 0 500 67Revenue Sharing Funds: Local Match

0 0 0 0 0 500 67Revenue Sharing Funds: State Match

0 0 0 0 0 0 1,000 1,000Total

MPO Area

RichmondSecondary

PROGRAM/SYSTEM

WALTON PARK LANE IMPROVEMENTS

PROJECT

UPC NO.:

ROUTE:

102945

NFO9999

Complete

SCHEDULE

100

ESTIMATED COST (000's)

JURISDICTION:

WALTON PARK LANESTREET NAME:

PEChesterfield County

Underway 360CN

UnderwayFROM: VARIOUS TO: VARIOUS (0.3200 MI)DESCRIPTION: 40RW

PROJECT LENGTH: 0.3200 MISCOPE OF WORK: Facilities for Pedestrians and Bicycles TO 500

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 633Revenue Sharing Funds: Local Match

0 0 0 0 0 0 633Revenue Sharing Funds: State Match

-765 0 0 0 0 0 0 1,265Total

11/12/2014 771

Page 74: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Secondary

MPO Area

Tri-CitiesSecondary

PROGRAM/SYSTEM

RTE 600 - ROUNDABOUT

PROJECT

UPC NO.:

ROUTE:

80993

NFO0600

MPO Project. Accruing for CNREPORT NOTE:

Underway

SCHEDULE

543

ESTIMATED COST (000's)

JURISDICTION:

FERNDALE ROADSTREET NAME:

PEDinwiddie County

FY2015 3,268CN

UnderwayFROM: On Rte 226, 0.105 Mile West of Rte 600 TO: On

Rte 226, 0.041 Mile East of Rte 600 (0.2980 MI)

DESCRIPTION: 1,096RW

PROJECT LENGTH: 0.1470 MISCOPE OF WORK: Reconstruction w/ Added Capacity TO 4,907

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 396(S) Federal Formula STP: Federal

0 0 0 0 0 0 60(S) Federal Formula STP: State Bond Match

0 0 0 0 0 0 1,660RSTP (STP Regional): Federal

1,146 0 0 0 0 272 0RSTP (STP Regional): MPO - Federal

286 0 0 0 0 68 0RSTP (STP Regional): MPO - State Match

0 0 0 0 0 0 415RSTP (STP Regional): State Match

0 0 0 0 0 0 6(S) Secondary Formula: Federal

0 0 0 0 0 0 120(S) Secondary Formula: State

0 0 0 0 0 0 40(S) Secondary Formula: State Match

83 0 0 0 83 68 186(S) Telecommunications: State

17 0 0 0 83 1,515 408 2,884Total

MPO Area

Tri-CitiesSecondary

PROGRAM/SYSTEM

BRIDGE (FED ID 6051) RTE 624 OVER WHITE

OAK CREEK

PROJECT

UPC NO.:

ROUTE:

105954

NFO0624

Revised schedule required.REPORT NOTE:

FY2018

SCHEDULE

158

ESTIMATED COST (000's)

JURISDICTION:

STREET NAME:

PEDinwiddie County

FY2019 788CN

FY2019DESCRIPTION: 105RW

PROJECT LENGTH: _SCOPE OF WORK: Bridge Replacement w/ Added Capacity TO 1,051

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 549 0 0 0 0 0CTB Formula: Bridge - State

0 309 92 0 0 0 0STP: BROS - Federal

0 77 23 0 0 0 0STP: BROS - Soft Match

0 936 115 0 0 0 0 0Total

772 11/12/2014

Page 75: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Secondary

MPO Area

NonMPOSecondary

PROGRAM/SYSTEM

RTE 703 - REPLACE BRIDGE OVER ROWANTY

CREEK

PROJECT

UPC NO.:

ROUTE:

101235

NFO0703

Underway

SCHEDULE

495

ESTIMATED COST (000's)

JURISDICTION:

CARSON ROADSTREET NAME:

PEDinwiddie County

FY2017 1,857CNFROM: APPROACHES & BRIDGE REPLACEMENT

OVER ROWANTY CR TO: 0.50 MI E RTE 667 (0.1500 MI)

DESCRIPTION: RW

29956 -1PROJECT LENGTH: 0.1500 MI STRUCTURE NO.: SUFFICIENCY RATING:

SCOPE OF WORK: Bridge Replacement w/o Added Capacity TO 2,352

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 256Bridge Replacement: Federal

0 0 0 0 0 0 64Soft Match: Federal

157 0 0 1,140 144 263 0STP: Bridge - Federal

39 0 0 285 36 66 0STP: Bridge - Soft Match

-98 0 0 1,425 180 197 328 320Total

MPO Area

Tri-CitiesSecondary

PROGRAM/SYSTEM

RTE 708 - REPLACE BRIDGE

PROJECT

UPC NO.:

ROUTE:

93092

NFO0708

Revised schedule required.REPORT NOTE:

Underway

SCHEDULE

188

ESTIMATED COST (000's)

JURISDICTION:

NAMOZINE ROADSTREET NAME:

PEDinwiddie County

FY2017 2,891CN

FY2014FROM: 0.233 MI W RTE 746 (BIRD NEST RD) TO: 0.339

MI W RTE 746 (BIRD NEST RD) (0.1060 MI)

DESCRIPTION: 94RW

PROJECT LENGTH: 0.1060 MISCOPE OF WORK: Bridge Replacement w/o Added Capacity TO 3,173

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 184Bridge Replacement: Federal

0 0 0 0 0 0 46Soft Match: Federal

324 872 699 266 93 167 0STP: Bridge - Federal

81 218 175 67 23 42 0STP: Bridge - Soft Match

-81 1,089 873 333 116 405 209 229Total

MPO Area

RichmondSecondary

PROGRAM/SYSTEM

ASHLAND ROAD / I-64 FEASIBILITY STUDY

PROJECT

UPC NO.:

ROUTE:

104089

NFO0623

MPO Project.REPORT NOTE:

Underway

SCHEDULE

200

ESTIMATED COST (000's)

JURISDICTION:

ASHLAND ROADSTREET NAME:

PEGoochland County

CN

@ 64 INTERCHANGEDESCRIPTION: RW

PROJECT LENGTH: 0.0000 MISCOPE OF WORK: Preliminary Engineering TO 200

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 160RSTP (STP Regional): MPO - Federal

0 0 0 0 0 0 40RSTP (STP Regional): MPO - State Match

0 0 0 0 0 0 0 200Total

11/12/2014 773

Page 76: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Secondary

MPO Area

RichmondSecondary

PROGRAM/SYSTEM

RTE 623 - IMPROVE INTERSECTION

PROJECT

UPC NO.:

ROUTE:

105733

NFO0623

MPO Project.REPORT NOTE:

FY2016

SCHEDULE

400

ESTIMATED COST (000's)

JURISDICTION:

HOCKETT ROADSTREET NAME:

PEGoochland County

FY2017 1,500CN

N/AFROM: RTE 1006 (HOLLY LN) TO: RTE 250/RTE 623

(ASHLAND RD) (0.5050 MI)

DESCRIPTION: 0RW

PROJECT LENGTH: 0.5050 MISCOPE OF WORK: Safety TO 1,900

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

400 0 0 0 400 400 0RSTP (STP Regional): MPO - Federal

100 0 0 0 100 100 0RSTP (STP Regional): MPO - State Match

0 0 0 0 0 0 320(S) Secondary Formula: Federal/State

0 0 0 0 0 0 80(S) Secondary Formula: State

0 0 0 0 500 500 500 400Total

MPO Area

RichmondSecondary

PROGRAM/SYSTEM

RTE 606 - ROUNDABOUT

PROJECT

UPC NO.:

ROUTE:

104875

NFO0606

MPO Project. Excess funds to be redistributed by MPO.REPORT NOTE:

Underway

SCHEDULE

200

ESTIMATED COST (000's)

JURISDICTION:

STUDLEY ROADSTREET NAME:

PEHanover County

FY2021 700CN

FY2016DESCRIPTION: 50RW

PROJECT LENGTH: _SCOPE OF WORK: Safety TO 950

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 700Local Project Contributions: Local

896 0 0 0 0 200 200RSTP (STP Regional): MPO - Federal

224 0 0 0 0 50 50RSTP (STP Regional): MPO - State Match

-1,370 0 0 0 0 1,120 250 950Total

774 11/12/2014

Page 77: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Secondary

MPO Area

RichmondSecondary

PROGRAM/SYSTEM

RTE 615 (CREIGHTON RD) - IMPROVE

INTERSECTION

PROJECT

UPC NO.:

ROUTE:

81667

NFO0615

VDOT records do not include additional previous funds. County and VODT working together to

identify funds and have them posted into the VDOT system. Balance to complete will be funded

with other funds

REPORT NOTE:

Underway

SCHEDULE

802

ESTIMATED COST (000's)

JURISDICTION:

CREIGHTON ROAD & COLD HARBOR ROADSTREET NAME:

PEHanover County

FY2016 4,790CN

UnderwayFROM: COLD HARBOR RD - FR 0.22 MI W CREIGHTON

RD TO 0.22 MI E TO: CREIGHTON RD - FR 0.38 MI S

COLD HARBOR RD TO 0.12 MI N (0.9400 MI)

DESCRIPTION: 1,789RW

PROJECT LENGTH: 0.9400 MISCOPE OF WORK: Reconstruction w/o Added Capacity TO 7,381

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 3,869CMAQ: Federal

0 0 0 0 0 0 807CMAQ: MPO - Federal

0 0 0 0 0 0 202CMAQ: MPO - State Match

0 0 0 0 0 0 967CMAQ: State Match

0 0 0 0 0 0 0(S) Secondary Formula: State

1,537 0 0 0 0 0 0 5,845Total

MPO Area

RichmondSecondary

PROGRAM/SYSTEM

BRIDGE (FED ID 9492) RTE. 617 OVER SOUTH

ANNA RIVER

PROJECT

UPC NO.:

ROUTE:

T11967

NFO0617

Revised schedule required.REPORT NOTE:

FY2018

SCHEDULE

684

ESTIMATED COST (000's)

JURISDICTION:

STREET NAME:

PEHanover County

FY2019 2,546CN

FY2019FROM: 1.1 To Rte 611 & 1.3 To 610 TO: 1.1 To Rte 611 &

1.3 To 610

DESCRIPTION: 570RW

PROJECT LENGTH: _SCOPE OF WORK: Bridge Replacement w/ Added Capacity TO 3,800

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 260 104 0 0 0 0STP: BROS - Federal

0 65 26 0 0 0 0STP: BROS - Soft Match

3,345 325 130 0 0 0 0 0Total

11/12/2014 775

Page 78: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Secondary

MPO Area

RichmondSecondary

PROGRAM/SYSTEM

RT 623 - IMPROVE INTERSECTION

PROJECT

UPC NO.:

ROUTE:

103014

NFO0623

Underway

SCHEDULE

472

ESTIMATED COST (000's)

JURISDICTION:

CEDAR LANESTREET NAME:

PEHanover County

FY2016 3,781CN

FY2015FROM: 0.18 mi W of Int. Rte 1(Wash Hwy)/Rte 623(Cedar

Ln) TO: Int. Rte 1(Wash Hwy)/Rte 623(Cedar Ln) (0.2500

MI)

DESCRIPTION: 914RW

PROJECT LENGTH: 0.1800 MISCOPE OF WORK: Reconstruction w/o Added Capacity TO 5,167

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 1,500Revenue Sharing Funds: Local Match

0 0 0 0 0 0 1,500Revenue Sharing Funds: State Match

0 0 0 0 0 1,200 400RSTP (STP Regional): MPO - Federal

0 0 0 0 0 300 100RSTP (STP Regional): MPO - State Match

0 1 0 0 0 0 0(S) Telecommunications: State

166 1 0 0 0 0 1,500 3,500Total

MPO Area

RichmondSecondary

PROGRAM/SYSTEM

RTE 623 - SHOULDER WEDGING

PROJECT

UPC NO.:

ROUTE:

104025

NFO0623

MPO Project.REPORT NOTE:

Complete

SCHEDULE

20

ESTIMATED COST (000's)

JURISDICTION:

Ashland RoadSTREET NAME:

PEHanover County

Underway 930CNFROM: RTE 623 FROM RTE 271 TO RTE 666 TO: RTE

666 FROM RTE 623 TO RTE 657 (6.1600 MI)

DESCRIPTION: RW

PROJECT LENGTH: 6.1600 MISCOPE OF WORK: Safety TO 950

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 760RSTP (STP Regional): MPO - Federal

0 0 0 0 0 0 190RSTP (STP Regional): MPO - State Match

0 0 0 0 0 0 0 950Total

MPO Area

RichmondSecondary

PROGRAM/SYSTEM

RTE 623 - SHOULDER WEDGING

PROJECT

UPC NO.:

ROUTE:

104876

NFO0623

MPO Project.REPORT NOTE:

Complete

SCHEDULE

20

ESTIMATED COST (000's)

JURISDICTION:

CEDAR LANE RDSTREET NAME:

PEHanover County

Underway 980CNFROM: RTE 666 (ASHLAND RD) TO: 0.5 MI WEST OF

RTE 1 (5.6700 MI)

DESCRIPTION: RW

PROJECT LENGTH: 5.6700 MISCOPE OF WORK: Safety TO 1,000

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 800RSTP (STP Regional): MPO - Federal

0 0 0 0 0 0 200RSTP (STP Regional): MPO - State Match

0 0 0 0 0 0 0 1,000Total

776 11/12/2014

Page 79: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Secondary

MPO Area

RichmondSecondary

PROGRAM/SYSTEM

RTE 625 - BRIDGE REPLACEMENT

PROJECT

UPC NO.:

ROUTE:

82399

NFO0625

Revised schedule required.REPORT NOTE:

Underway

SCHEDULE

664

ESTIMATED COST (000's)

JURISDICTION:

GREENWOOD ROADSTREET NAME:

PEHanover County

FY2015 1,845CN

FY2014FROM: .025 W OF HENRICO COUNTY LINE TO: .025 E

OF HANOVER COUNTY LINE (0.0500 MI)

DESCRIPTION: 207RW

29485 -1PROJECT LENGTH: 0.0500 MI STRUCTURE NO.: SUFFICIENCY RATING:

SCOPE OF WORK: Bridge Rehab w/o Added Capacity TO 2,716

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 29Bond Match: State Bond Match

0 0 0 0 0 0 265Bridge Replacement: Federal

0 0 0 0 0 0 37Soft Match: Federal

78 0 0 0 1,491 80 266STP: Bridge - Federal

20 0 0 0 373 20 67STP: Bridge - Soft Match

-10 0 0 0 1,864 98 100 664Total

MPO Area

RichmondSecondary

PROGRAM/SYSTEM

RT 627 (POLE GREEN RD) - INT IMPR @RTE

636 (WALNUT GROVE RD)

PROJECT

UPC NO.:

ROUTE:

97685

NFO0627

Underway

SCHEDULE

132

ESTIMATED COST (000's)

JURISDICTION:

POLE GREEN ROADSTREET NAME:

PEHanover County

FY2016 659CN

UnderwayFROM: 0.07 MI W RTE 636 (WALNUT GROVE ROAD)

TO: 0.14 MI E RTE 636 (WALNUT GROVE ROAD)

(0.2000 MI)

DESCRIPTION: 272RW

PROJECT LENGTH: 0.2000 MISCOPE OF WORK: Safety TO 1,064

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 400CMAQ: Federal

0 0 0 0 0 0 161CMAQ: MPO - Federal

0 0 0 0 0 0 40CMAQ: MPO - State Match

0 0 0 0 0 0 100CMAQ: State Match

0 0 0 0 0 0 150Local Project Contributions: Local

0 0 0 0 0 0 12(S) Residue Parcel Revenue: State

0 0 0 0 0 0 343(S) Telecommunications: State

-142 0 0 0 0 0 0 1,206Total

11/12/2014 777

Page 80: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Secondary

MPO Area

RichmondSecondary

PROGRAM/SYSTEM

POLE GREEN RD (RT. 627)/RURAL POINT RD

(RT. 643) INT. IMPR.

PROJECT

UPC NO.:

ROUTE:

97686

NFO0627

Complete

SCHEDULE

108

ESTIMATED COST (000's)

JURISDICTION:

Pole Green RoadSTREET NAME:

PEHanover County

Underway 591CN

UnderwayFROM: .06 mile west of Rural Point Road TO: .09mile

east of Rural Point Road (0.1480 MI)

DESCRIPTION: 44RW

PROJECT LENGTH: 0.1480 MISCOPE OF WORK: Safety TO 743

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 203CMAQ: Federal

0 0 0 0 0 0 76CMAQ: MPO - Federal

0 0 0 0 0 0 19CMAQ: MPO - State Match

0 0 0 0 0 0 51CMAQ: State Match

0 0 0 0 0 0 75(S) Federal Formula STP: Federal

0 0 0 0 0 0 19(S) Federal Formula STP: State Bond Match

0 0 0 0 0 0 104Local Project Contributions: Local

0 0 0 0 0 0 12(S) Residue Parcel Revenue: State

0 0 0 0 0 0 125(S) Secondary Formula: Federal

0 0 0 0 0 0 31(S) Secondary Formula: State Match

0 0 0 0 0 0 28(S) Telecommunications: State

0 0 0 0 0 0 0 743Total

MPO Area

RichmondSecondary

PROGRAM/SYSTEM

RTE 638 - CONSTRUCT LTL & ADD SB REC. LN

PROJECT

UPC NO.:

ROUTE:

77121

NFO0638

MPO project.REPORT NOTE:

Underway

SCHEDULE

448

ESTIMATED COST (000's)

JURISDICTION:

Atlee RoadSTREET NAME:

PEHanover County

FY2016 1,691CN

UnderwayFROM: 0.2 MILE SOUTH OF ROUTE 301 TO:

INTERSECTION ROUTE 301 (0.2000 MI)

DESCRIPTION: 579RW

PROJECT LENGTH: 0.2000 MISCOPE OF WORK: Reconstruction w/ Added Capacity TO 2,717

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 622CMAQ: Federal

0 0 0 0 0 0 155CMAQ: State Match

0 0 0 0 0 0 958(X) Maintenance Funds: Federal

0 0 0 0 0 0 982(X) Maintenance Funds: Statewide

0 0 0 0 0 0 0 2,717Total

778 11/12/2014

Page 81: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Secondary

MPO Area

RichmondSecondary

PROGRAM/SYSTEM

RTE 638 - EXTEND ATLEE RD TO CONNECT TO

ATLEE STATION RD

PROJECT

UPC NO.:

ROUTE:

98236

NFO0638

Revised schedule required.REPORT NOTE:

Underway

SCHEDULE

1,195

ESTIMATED COST (000's)

JURISDICTION:

Atlee Road (Rte 638)STREET NAME:

PEHanover County

FY2016 11,447CN

UnderwayFROM: 0. 234 MI. NORTH OF BUCKINGHAM BRANCH

RAILROAD TO: 0. 244 MI. SOUTH OF BUCKINGHAM

BRANCH RAILROAD (0.4780 MI)

DESCRIPTION: 2,583RW

PROJECT LENGTH: 0.4780 MISCOPE OF WORK: New Construction Roadway TO 15,225

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 384Local Project Contributions: Local

0 0 0 0 0 0 28Non-Formula: State Match

0 0 0 0 0 0 101(S) Residue Parcel Revenue: State

0 0 0 0 0 0 3,461Revenue Sharing Funds: Local Match

0 0 0 0 0 0 3,461Revenue Sharing Funds: State Match

0 0 0 0 0 0 2,193RSTP (STP Regional): Federal

0 0 0 0 0 0 1,341RSTP (STP Regional): MPO - Federal

0 0 0 0 0 0 335RSTP (STP Regional): MPO - State Match

0 0 0 0 0 0 520RSTP (STP Regional): State Match

276 274 276 276 276 276 512(S) Telecommunications: State

1,234 274 276 276 276 276 276 12,335Total

MPO Area

RichmondSecondary

PROGRAM/SYSTEM

RTE 651 (GEORGETOWN RD) - BRIDGE

REPLACEMENT

PROJECT

UPC NO.:

ROUTE:

51261

NFO0651

Complete

SCHEDULE

614

ESTIMATED COST (000's)

JURISDICTION:

GEORGETOWN ROADSTREET NAME:

PEHanover County

Underway 1,786CN

UnderwayFROM: APPROACHES AND BRIDGE AT CRUMP CR

TO: (0.21 MI S RTE 325) (0.1430 MI)

DESCRIPTION: 114RW

29315 -1PROJECT LENGTH: 0.1430 MI STRUCTURE NO.: SUFFICIENCY RATING:

SCOPE OF WORK: Bridge Replacement w/o Added Capacity TO 2,514

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 236Bond Match: State Bond Match

0 0 0 0 0 0 1,160Bridge Replacement: Federal

0 0 0 0 0 0 244Priority Transportation Funds: State

0 0 0 0 0 0 369(S) Secondary Formula: Federal

0 0 0 0 0 0 92(S) Secondary Formula: State Match

0 0 0 0 0 0 54Soft Match: Federal

60 0 0 0 0 21 205STP: BROS - Federal

15 0 0 0 0 5 51STP: BROS - Soft Match

-1 0 0 0 0 76 27 2,413Total

11/12/2014 779

Page 82: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Secondary

MPO Area

RichmondSecondary

PROGRAM/SYSTEM

RTE 656 - INSTALL LEFT TURN LANE ONTO

RTE 813

PROJECT

UPC NO.:

ROUTE:

71354

NFO0656

Complete

SCHEDULE

480

ESTIMATED COST (000's)

JURISDICTION:

SLIDING HILL RDSTREET NAME:

PEHanover County

Underway 1,770CN

UnderwayFROM: 0.093 mile west of Rte 813 (Air Park Road) TO:

0.13 mile east of Rte 813 (Air Park Road) (0.2230 MI)

DESCRIPTION: 180RW

PROJECT LENGTH: 0.2230 MISCOPE OF WORK: Safety TO 2,430

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 380CMAQ: Federal

0 0 0 0 0 0 95CMAQ: State Match

0 0 0 0 0 0 774(S) Federal Formula STP: Federal

0 0 0 0 0 0 194(S) Federal Formula STP: State Bond Match

0 0 0 0 0 0 88(S) Secondary Formula: Federal

0 0 0 0 0 0 721(S) Secondary Formula: Federal/State

0 0 0 0 0 0 9(S) Secondary Formula: State

0 0 0 0 0 0 22(S) Secondary Formula: State Match

0 0 0 0 0 0 267(S) SSYP - Incidental: Federal

0 0 0 0 0 0 85(S) Telecommunications: State

-206 0 0 0 0 0 0 2,636Total

MPO Area

RichmondSecondary

PROGRAM/SYSTEM

RTE 656 - SLIDING HILL ROAD CORRIDOR (PE

ONLY)

PROJECT

UPC NO.:

ROUTE:

104957

NFO0656

Underway

SCHEDULE

500

ESTIMATED COST (000's)

JURISDICTION:

SLIDING HILL ROADSTREET NAME:

PEHanover County

CNFROM: ATLEE STATION RD TO: NEW ASHCAKE RD

(0.9500 MI)

DESCRIPTION: RW

PROJECT LENGTH: 0.9500 MISCOPE OF WORK: Reconstruction w/ Added Capacity TO 500

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 400RSTP (STP Regional): MPO - Federal

0 0 0 0 0 0 100RSTP (STP Regional): MPO - State Match

0 1 0 0 0 0 0(S) Telecommunications: State

-1 1 0 0 0 0 0 500Total

780 11/12/2014

Page 83: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Secondary

MPO Area

RichmondSecondary

PROGRAM/SYSTEM

RTE 657 - SHOULDER WEDGE & OVERLAY

PROJECT

UPC NO.:

ROUTE:

106206

NFO0657

MPO Project.REPORT NOTE:

FY2015

SCHEDULE

20

ESTIMATED COST (000's)

JURISDICTION:

ASHCAKE ROADSTREET NAME:

PEHanover County

FY2015 580CNFROM: ECL ASHLAND TO: RTE 656 (SLIDING HILL RD)

(3.4300 MI)

DESCRIPTION: RW

PROJECT LENGTH: _SCOPE OF WORK: Resurfacing TO 600

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

240 0 0 0 0 240 0RSTP (STP Regional): MPO - Federal

60 0 0 0 0 60 0RSTP (STP Regional): MPO - State Match

0 0 0 0 0 300 300 0Total

MPO Area

RichmondSecondary

PROGRAM/SYSTEM

RTE 689 - BRIDGE REPLACEMENT OVER

LITTLE RIVER

PROJECT

UPC NO.:

ROUTE:

82378

NFO0689

Underway

SCHEDULE

580

ESTIMATED COST (000's)

JURISDICTION:

TAYLORSVILLE ROADSTREET NAME:

PEHanover County

FY2015 1,213CN

UnderwayFROM: 0.20 MI. S. OF RTE 725 TO: 0.10 MI. S. OF RTE

725 (0.1000 MI)

DESCRIPTION: 84RW

29221 -2PROJECT LENGTH: 0.1000 MI STRUCTURE NO.: SUFFICIENCY RATING:

SCOPE OF WORK: Bridge Replacement w/o Added Capacity TO 1,877

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 131Bond Match: State Bond Match

0 0 0 0 0 0 912Bridge Replacement: Federal

0 0 0 0 0 0 5Federal STP: Federal

0 0 0 0 0 0 99Soft Match: Federal

240 0 0 0 171 0 0STP: Bridge - Federal

60 0 0 0 43 0 0STP: Bridge - Soft Match

243 0 0 0 116 0 225STP: BROS - Federal

61 0 0 0 29 0 56STP: BROS - Soft Match

-514 0 0 0 359 604 0 1,428Total

MPO Area

RichmondSecondary

PROGRAM/SYSTEM

BRIDGE (FED ID 9578) RTE 715 OVER NEW

FOUND RIVER

PROJECT

UPC NO.:

ROUTE:

T11964

NFO0715

Revised schedule requiredREPORT NOTE:

FY2018

SCHEDULE

289

ESTIMATED COST (000's)

JURISDICTION:

STREET NAME:

PEHanover County

FY2019 1,444CN

FY2019FROM: 0.70 Fr Rte 781 & 1.25 TO Rte 631 TO: 0.70 Fr

Rte 781 & 1.25 TO Rte 631

DESCRIPTION: 193RW

PROJECT LENGTH: _SCOPE OF WORK: Bridge Replacement w/ Added Capacity TO 1,925

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 1,540 0 0 0 0 0STP: Bridge - Federal

0 385 0 0 0 0 0STP: Bridge - Soft Match

0 1,925 0 0 0 0 0 0Total

11/12/2014 781

Page 84: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Secondary

MPO Area

RichmondSecondary

PROGRAM/SYSTEM

HENRICO COUNTY AUTOMATIC TRAFFIC

MANAGEMENT SYSTEM (ATMS)

PROJECT

UPC NO.:

ROUTE:

T11908

NFO

MPO Project.REPORT NOTE:

FY2015

SCHEDULE

800

ESTIMATED COST (000's)

JURISDICTION:

STREET NAME:

PEHenrico County

FY2018 7,213CN

VARIOUSDESCRIPTION: RW

PROJECT LENGTH: _SCOPE OF WORK: Safety TO 8,013

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

1,089 0 0 1,600 1,806 958 958CMAQ: MPO - Federal

272 0 0 400 451 240 240CMAQ: MPO - State Match

0 0 0 2,000 2,257 1,361 1,198 1,198Total

MPO Area

RichmondSecondary

PROGRAM/SYSTEM

HENRICO COUNTY TRAFFIC SIGNAL SYSTEM

PROJECT

UPC NO.:

ROUTE:

12945

NFO

MPO project.REPORT NOTE:

Underway

SCHEDULE

984

ESTIMATED COST (000's)

JURISDICTION:

STREET NAME:

PEHenrico County

CN

COUNTYWIDE TRAFFIC SIGNAL CONTROL SYSTEMDESCRIPTION: RW

PROJECT LENGTH: 0.0000 MISCOPE OF WORK: Safety TO 984

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 851CMAQ: Federal

0 0 0 0 0 0 133CMAQ: State Match

0 0 0 0 0 0 0 984Total

MPO Area

RichmondSecondary

PROGRAM/SYSTEM

COMPUTERIZED SIGNAL SYSTEM

PROJECT

UPC NO.:

ROUTE:

13553

NFO

MPO Project. Administered by Henrico County. Excess funds to be redistributed by MPO.

100% Fed CMAQ-funded project.

REPORT NOTE:

SCHEDULE ESTIMATED COST (000's)

JURISDICTION:

STREET NAME:

PEHenrico County

Underway 2,830CNFROM: VARIOUS LOCATIONS TO: HENRICO

COUNTYWIDE

DESCRIPTION: RW

PROJECT LENGTH: 0.0000 MISCOPE OF WORK: Safety TO 2,830

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 2,864CMAQ: Federal

0 0 0 0 0 0 13CMAQ: State Match

-47 0 0 0 0 0 0 2,877Total

782 11/12/2014

Page 85: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Secondary

MPO Area

RichmondSecondary

PROGRAM/SYSTEM

SADLER RD IMP FROM DOMINION BLVD TO

CEDAR BRANCH CT PH 2 CN

PROJECT

UPC NO.:

ROUTE:

T14882

NFO0000

MPO Project. Balance to be provided for by MPO.REPORT NOTE:

SCHEDULE ESTIMATED COST (000's)

JURISDICTION:

Sadler RoadSTREET NAME:

PEHenrico County

FY2020 7,200CN

FROM: Dominion Blvd TO: Cedar Branch CtDESCRIPTION: RW

PROJECT LENGTH: _SCOPE OF WORK: Reconstruction w/ Added Capacity TO 7,200

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 3,360 0 0 0 0 0RSTP (STP Regional): MPO - Federal

0 840 0 0 0 0 0RSTP (STP Regional): MPO - State Match

3,000 4,200 0 0 0 0 0 0Total

MPO Area

RichmondSecondary

PROGRAM/SYSTEM

SIDEWALK (NEW CONSTRUCTION)

PROJECT

UPC NO.:

ROUTE:

105647

NFO0000

FY2015

SCHEDULE

183

ESTIMATED COST (000's)

JURISDICTION:

WISTAR ROADSTREET NAME:

PEHenrico County

FY2016 1,150CN

FY2015FROM: 300 FEET WEST OF SHRADER ROAD TO: 200

FEET EAST OF BIRCHBROOK ROAD (1.4000 MI)

DESCRIPTION: 95RW

PROJECT LENGTH: 1.4000 MISCOPE OF WORK: Reconstruction w/ Added Capacity TO 1,428

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 707 0Revenue Sharing Funds: Local Match

0 0 0 0 0 707 0Revenue Sharing Funds: State Match

15 0 0 0 0 0 1,413 0Total

MPO Area

RichmondSecondary

PROGRAM/SYSTEM

SIDEWALK (NEW CONSTRUCTION)

PROJECT

UPC NO.:

ROUTE:

105657

NFO0000

FY2015

SCHEDULE

11

ESTIMATED COST (000's)

JURISDICTION:

PRINCE HENRY DRIVESTREET NAME:

PEHenrico County

FY2019 70CN

FY2017FROM: E. PARHAM RD TO: HUNGARY SPRING RD

(0.4500 MI)

DESCRIPTION: 15RW

PROJECT LENGTH: 0.4500 MISCOPE OF WORK: Reconstruction w/ Added Capacity TO 96

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 35 0Revenue Sharing Funds: Local Match

0 0 0 0 0 35 0Revenue Sharing Funds: State Match

26 0 0 0 0 0 70 0Total

11/12/2014 783

Page 86: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Secondary

MPO Area

RichmondSecondary

PROGRAM/SYSTEM

SIDEWALK (NEW CONSTRUCTION)

PROJECT

UPC NO.:

ROUTE:

105658

NFO0000

FY2015

SCHEDULE

13

ESTIMATED COST (000's)

JURISDICTION:

BEULAH ROADSTREET NAME:

PEHenrico County

FY2019 94CN

FY2017FROM: HUNSTMAN ROAD TO: GREEN HOLLOW LANE

(0.1200 MI)

DESCRIPTION: 15RW

PROJECT LENGTH: 0.1200 MISCOPE OF WORK: Reconstruction w/o Added Capacity TO 122

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 47 0Revenue Sharing Funds: Local Match

0 0 0 0 0 47 0Revenue Sharing Funds: State Match

28 0 0 0 0 0 94 0Total

MPO Area

RichmondSecondary

PROGRAM/SYSTEM

RTE 615 - REPLACE BRIDGE

PROJECT

UPC NO.:

ROUTE:

104274

NFO0615

Underway

SCHEDULE

1,528

ESTIMATED COST (000's)

JURISDICTION:

CREIGHTON ROADSTREET NAME:

PEHenrico County

CN

UnderwayFROM: SANDY LN TO: CITY OF RICHMOND

CORPORATE LIMITS (1.0800 MI)

DESCRIPTION: 3,000RW

PROJECT LENGTH: 1.1200 MISCOPE OF WORK: Bridge Replacement w/ Added Capacity TO 4,528

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 6,392Local Project Contributions: Local

0 0 0 0 0 0 1,495Revenue Sharing Funds: Local Match

0 0 0 0 0 0 1,495Revenue Sharing Funds: State Match

-4,854 0 0 0 0 0 0 9,382Total

MPO Area

RichmondSecondary

PROGRAM/SYSTEM

RTE 627 - MEADOWBRIDGE ROAD -

RECONSTRUCTION

PROJECT

UPC NO.:

ROUTE:

18122

NFO0627

MPO Project. Balance to be provided by MPO.REPORT NOTE:

Underway

SCHEDULE

1,685

ESTIMATED COST (000's)

JURISDICTION:

STREET NAME:

PEHenrico County

CN

UnderwayFROM: 0.41 KILOMETER WEST OF AZALEA AVENUE

TO: 0.04 KILOMETER WEST OF HENRICO/HANOVER

COUNTY LINE (2.2130 KM)

DESCRIPTION: 1,863RW

PROJECT LENGTH: 2.2130 KMSCOPE OF WORK: Reconstruction w/ Added Capacity TO 3,549

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 519Non-Formula: State Match

0 0 0 0 0 0 2,074RSTP (STP Regional): Federal

956 0 0 0 0 0 0 2,593Total

784 11/12/2014

Page 87: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Secondary

MPO Area

RichmondSecondary

PROGRAM/SYSTEM

AZALEA AVE PEDESTRIAN & SIGNAL

IMPROVEMENTS

PROJECT

UPC NO.:

ROUTE:

106299

NFO6010

MPO Project.REPORT NOTE:

FY2016

SCHEDULE

130

ESTIMATED COST (000's)

JURISDICTION:

AZALEA AVENUESTREET NAME:

PEHenrico County

FY2019 1,400CN

FY2017FROM: THRUSH LANE TO: RICHMOND-HENRICO

TURNPIKE

DESCRIPTION: 85RW

PROJECT LENGTH: _SCOPE OF WORK: Facilities for Pedestrians and Bicycles TO 1,615

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

104 0 560 560 68 0 0CMAQ: MPO - Federal

26 0 140 140 17 0 0CMAQ: MPO - State Match

0 0 700 700 85 130 0 0Total

MPO Area

RichmondSecondary

PROGRAM/SYSTEM

RTE 7555 - LABURNUM AVENUE - WIDENING

PROJECT

UPC NO.:

ROUTE:

16153

NFO7555

MPO project. Partial PE. Balance to be provided by MPOREPORT NOTE:

Underway

SCHEDULE

1,009

ESTIMATED COST (000's)

JURISDICTION:

STREET NAME:

PEHenrico County

FY2021 5,515CNFROM: ECL RICHMOND TO: CAROLINA AVENUE

(1.9900 MI)

DESCRIPTION: RW

PROJECT LENGTH: 1.9900 MISCOPE OF WORK: Reconstruction w/ Added Capacity TO 6,524

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 167Non-Formula: State Match

0 0 0 0 0 0 668RSTP (STP Regional): Federal

5,689 0 0 0 0 0 0 835Total

MPO Area

RichmondSecondary

PROGRAM/SYSTEM

RTE 9999 - INTERSECTION IMPROVEMENT

AND SIGNALIZATION

PROJECT

UPC NO.:

ROUTE:

18124

NFO9999

Henrico County Federal Escrow Project. Balance to be provided by County.REPORT NOTE:

Complete

SCHEDULE

250

ESTIMATED COST (000's)

JURISDICTION:

STREET NAME:

PEHenrico County

Underway 1,091CN

UnderwayAT MASONIC LANE, GAY AVENUE, AND BRITTLES

LANE (0.2930 MI)

DESCRIPTION: 180RW

PROJECT LENGTH: 0.2930 MISCOPE OF WORK: Safety TO 1,521

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 762Local Partnership: State

0 0 0 0 0 0 280(S) Secondary Formula: Federal

0 0 0 0 0 0 70(S) Secondary Funds: Federal/State

408 0 0 0 0 0 0 1,112Total

11/12/2014 785

Page 88: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Secondary

MPO Area

RichmondSecondary

PROGRAM/SYSTEM

RTE 9999 (THREE CHOPT ROAD) WIDEN TO 4

LANES

PROJECT

UPC NO.:

ROUTE:

50525

NFO9999

MPO project - Balance to be provided by MPO. Revised schedule required.REPORT NOTE:

SCHEDULE ESTIMATED COST (000's)

JURISDICTION:

STREET NAME:

PEHenrico County

FY2016 6,346CN

UnderwayFROM: BARRINGTON HILLS DRIVE TO: COX ROAD

(1.0800 MI)

DESCRIPTION: 900RW

PROJECT LENGTH: 0.7500 MISCOPE OF WORK: Reconstruction w/ Added Capacity TO 7,246

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 648Non-Formula: State Match

0 0 0 0 0 0 5,551RSTP (STP Regional): Federal

0 0 0 0 0 0 740RSTP (STP Regional): State Match

308 0 0 0 0 0 0 6,938Total

MPO Area

RichmondSecondary

PROGRAM/SYSTEM

THREE CHOPT ROAD - WIDENING - PE ONLY

PROJECT

UPC NO.:

ROUTE:

50528

NFO9999

MPO Project.REPORT NOTE:

Underway

SCHEDULE

2,583

ESTIMATED COST (000's)

JURISDICTION:

STREET NAME:

PEHenrico County

CNFROM: BARRINGTON HILL DRIVE TO: GASKINS ROAD

(1.5000 MI)

DESCRIPTION: RW

PROJECT LENGTH: 1.5000 MISCOPE OF WORK: Reconstruction w/ Added Capacity TO 2,583

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 395Non-Formula: State Match

0 0 0 0 0 0 2,066RSTP (STP Regional): Federal

0 0 0 0 0 0 122RSTP (STP Regional): State Match

0 0 0 0 0 0 0 2,583Total

MPO Area

RichmondSecondary

PROGRAM/SYSTEM

RTE 9999 (THREE CHOPT ROAD) WIDEN TO 4

LANES

PROJECT

UPC NO.:

ROUTE:

50529

NFO9999

MPO project - balance to be provided by MPO. Revised schedule required.REPORT NOTE:

SCHEDULE ESTIMATED COST (000's)

JURISDICTION:

STREET NAME:

PEHenrico County

FY2016 6,772CN

UnderwayFROM: COX ROAD TO: GASKINS ROAD (1.0900 MI)DESCRIPTION: 126RW

PROJECT LENGTH: 0.7500 MISCOPE OF WORK: Reconstruction w/ Added Capacity TO 6,898

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 18Non-Formula: State Match

0 0 0 0 0 0 4,138RSTP (STP Regional): Federal

0 0 0 0 0 0 1,280RSTP (STP Regional): MPO - Federal

0 0 0 0 0 0 320RSTP (STP Regional): MPO - State Match

0 0 0 0 0 0 1,016RSTP (STP Regional): State Match

126 0 0 0 0 0 0 6,772Total

786 11/12/2014

Page 89: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Secondary

MPO Area

RichmondSecondary

PROGRAM/SYSTEM

JOHN ROLFE PARKWAY - NEW

CONSTRUCTION

PROJECT

UPC NO.:

ROUTE:

53315

NFO9999

Henrico Co. - Federal Escrow Project. Balance to be redistributed by County.REPORT NOTE:

Complete

SCHEDULE

5,000

ESTIMATED COST (000's)

JURISDICTION:

John Rolfe ParkwaySTREET NAME:

PEHenrico County

Underway 12,228CN

UnderwayFROM: 0.31 Mile South of Church Road TO: 0.026 MILE

SOUTH WEST BROAD STREET (ROUTE 250) (2.6900

MI)

DESCRIPTION: 7,800RW

PROJECT LENGTH: 2.6900 MISCOPE OF WORK: New Construction Roadway TO 25,028

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 37Accounts Receivable: Local

0 0 0 0 0 0 11,132Federal Aid: Federal Escrow

0 0 0 0 0 0 4,469(S) Federal Aid: Federal/State

0 0 0 0 0 0 241(S) Federal Formula STP: Federal

0 0 0 0 0 0 7,555(S) Secondary Formula: Federal

0 0 0 0 0 0 2,294(S) Secondary Formula: Federal/State

0 0 0 0 0 0 51(S) Secondary Funds: Federal/State

-750 0 0 0 0 0 0 25,778Total

MPO Area

RichmondSecondary

PROGRAM/SYSTEM

RTE 9999 - DABBS HOUSE RD; WIDEN TO 4

LANES; FED ESCROW PROJ

PROJECT

UPC NO.:

ROUTE:

60933

NFO9999

MPO Project. Balance to be redistributed by MPO. Revised schedule required.REPORT NOTE:

Underway

SCHEDULE

1,750

ESTIMATED COST (000's)

JURISDICTION:

Dabbs House RoadSTREET NAME:

PEHenrico County

FY2017 6,472CN

FY2014FROM: NINE MILE ROAD TO: EAST RICHMOND ROAD

(0.8920 MI)

DESCRIPTION: 2,565RW

PROJECT LENGTH: 0.9200 MISCOPE OF WORK: Reconstruction w/ Added Capacity TO 10,787

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 1,091RSTP (STP Regional): Federal

800 0 1,040 800 800 0 1,956RSTP (STP Regional): MPO - Federal

200 0 260 200 200 0 489RSTP (STP Regional): MPO - State Match

0 0 0 0 0 0 273RSTP (STP Regional): State Match

0 0 0 0 0 0 4,145(S) Secondary Formula: Federal

0 0 0 0 0 0 1,036(S) Secondary Funds: Federal/State

-2,502 0 1,300 1,000 1,000 1,000 0 8,990Total

11/12/2014 787

Page 90: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Secondary

MPO Area

RichmondSecondary

PROGRAM/SYSTEM

RTE 9999 - SADLER RD; WIDEN &

RECONSTRUCT; FED ESCROW PROJ

PROJECT

UPC NO.:

ROUTE:

60934

NFO9999

PE Only.REPORT NOTE:

Underway

SCHEDULE

2,500

ESTIMATED COST (000's)

JURISDICTION:

Sadler RoadSTREET NAME:

PEHenrico County

CNFROM: DOMINION BOULEVARD TO: CEDAR BRANCH

COURT (1.8000 MI)

DESCRIPTION: RW

PROJECT LENGTH: 1.8000 MISCOPE OF WORK: Reconstruction w/o Added Capacity TO 2,500

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 1,142RSTP (STP Regional): Federal

0 0 0 0 0 0 285RSTP (STP Regional): State Match

0 0 0 0 0 0 858(S) Secondary Formula: Federal

0 0 0 0 0 0 215(S) Secondary Funds: Federal/State

0 0 0 0 0 0 0 2,500Total

MPO Area

RichmondSecondary

PROGRAM/SYSTEM

SADLER RD - RECONSTRUCTION - PHASE I

PROJECT

UPC NO.:

ROUTE:

104148

NFO9999

SCHEDULE ESTIMATED COST (000's)

JURISDICTION:

SADLER ROADSTREET NAME:

PEHenrico County

FY2017 6,995CN

FY2015FROM: DOMINION BLVD TO: SADLER GROVE RD

(1.0000 MI)

DESCRIPTION: 2,905RW

PROJECT LENGTH: 1.0000 MISCOPE OF WORK: Reconstruction w/o Added Capacity TO 9,900

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 1,178RSTP (STP Regional): Federal

720 0 0 0 400 0 0RSTP (STP Regional): MPO - Federal

180 0 0 0 100 0 0RSTP (STP Regional): MPO - State Match

0 0 0 0 0 0 295RSTP (STP Regional): State Match

0 0 0 0 0 0 4,462(S) Secondary Formula: Federal

0 0 0 0 0 0 1,116(S) Secondary Funds: Federal/State

1,449 0 0 0 500 900 0 7,051Total

MPO Area

RichmondSecondary

PROGRAM/SYSTEM

RIDGEFIELD PKWY - CONSTRUCT SIDEWALK

PROJECT

UPC NO.:

ROUTE:

104880

NFO9999

MPO Project. Revised schedule required.REPORT NOTE:

Underway

SCHEDULE

175

ESTIMATED COST (000's)

JURISDICTION:

RIDGEFIELD PARKWAYSTREET NAME:

PEHenrico County

FY2017 325CN

FY2016FROM: PUMP ROAD TO: FALCONBRIDGE DRIVE

(1.0000 MI)

DESCRIPTION: 100RW

PROJECT LENGTH: 1.0000 MISCOPE OF WORK: Facilities for Pedestrians and Bicycles TO 600

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

340 0 0 0 0 0 140CMAQ: MPO - Federal

85 0 0 0 0 0 35CMAQ: MPO - State Match

0 0 0 0 0 425 0 175Total

788 11/12/2014

Page 91: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Secondary

MPO Area

RichmondSecondary

PROGRAM/SYSTEM

JOHN ROLFE PKWY - ADD SIDEWALK

PROJECT

UPC NO.:

ROUTE:

104881

NFO9999

MPO Project.REPORT NOTE:

Underway

SCHEDULE

120

ESTIMATED COST (000's)

JURISDICTION:

JOHN ROLFE ROADSTREET NAME:

PEHenrico County

FY2017 320CN

FY2016DESCRIPTION: 100RW

PROJECT LENGTH: _SCOPE OF WORK: Facilities for Pedestrians and Bicycles TO 540

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

336 0 0 0 0 0 96CMAQ: MPO - Federal

84 0 0 0 0 0 24CMAQ: MPO - State Match

0 0 0 0 0 420 0 120Total

MPO Area

NonMPOSecondary

PROGRAM/SYSTEM

RTE 621 - REPLACE BRIDGE

PROJECT

UPC NO.:

ROUTE:

60007

NFO0621

Revised schedule required. Partial PE fundingREPORT NOTE:

Underway

SCHEDULE

530

ESTIMATED COST (000's)

JURISDICTION:

DIX DRIVESTREET NAME:

PELunenburg County

FY2016 1,491CN

FY2015FROM: BRIDGE AND APPROACHES OVER MEHERRIN

RIVER TO: (0.55 MI S RTE 602 (LONGVIEW DR)) (0.0760

MI)

DESCRIPTION: 229RW

30021 -1PROJECT LENGTH: 0.0760 MI STRUCTURE NO.: SUFFICIENCY RATING:

SCOPE OF WORK: Bridge Replacement w/ Added Capacity TO 2,250

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 177Bridge Replacement: Federal

0 0 0 0 0 0 44Soft Match: Federal

331 0 719 392 145 35 0STP: BROS - Federal

83 0 180 98 36 9 0STP: BROS - Soft Match

0 0 899 490 181 413 44 222Total

MPO Area

NonMPOSecondary

PROGRAM/SYSTEM

RTE 631 - BRIDGE REPLACEMENT

PROJECT

UPC NO.:

ROUTE:

100977

NFO0631

Revised schedule required.REPORT NOTE:

Underway

SCHEDULE

460

ESTIMATED COST (000's)

JURISDICTION:

LEE'S MILL ROADSTREET NAME:

PELunenburg County

FY2016 1,206CN

FY2015FROM: BRIDGE AND APPROACHES OVER MIDDLE

MEHERRIN RIVER TO: 0.81 MW RTE 771

(ARROWHEAD RD) (0.0360 MI)

DESCRIPTION: 64RW

30027 -1PROJECT LENGTH: 0.1550 MI STRUCTURE NO.: SUFFICIENCY RATING:

SCOPE OF WORK: Bridge Replacement w/ Added Capacity TO 1,730

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 150Bridge Replacement: Federal

0 0 0 0 0 0 37Soft Match: Federal

85 0 0 871 212 0 65STP: BROS - Federal

21 0 0 218 53 0 16STP: BROS - Soft Match

1 0 0 0 0 1 0(S) Telecommunications: State

-1 0 0 1,088 265 108 1 269Total

11/12/2014 789

Page 92: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Secondary

MPO Area

NonMPOSecondary

PROGRAM/SYSTEM

RTE 712 - RECONSTRUCTION AND BRIDGE

REPLACEMENT

PROJECT

UPC NO.:

ROUTE:

1491

NFO0712

Underway

SCHEDULE

540

ESTIMATED COST (000's)

JURISDICTION:

WALLACES BRIDGESTREET NAME:

PELunenburg County

FY2015 1,942CN

UnderwayFROM: 1.08 MILES EAST OF ROUTE 622 TO: 1.27

MILES WEST OF ROUTE 658 (0.0760 MI)

DESCRIPTION: 128RW

28720 -2PROJECT LENGTH: 0.0760 MI STRUCTURE NO.: SUFFICIENCY RATING:

SCOPE OF WORK: Bridge Replacement w/o Added Capacity TO 2,610

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 30Bond Match: State Bond Match

0 0 0 0 0 0 122Bridge Replacement: Federal

0 0 0 0 0 0 57(S) Federal Formula STP: Federal

0 0 0 0 0 0 0(S) Federal Formula STP: State Bond Match

0 0 0 0 0 0 101(S) Secondary Formula: Federal

0 0 0 0 0 0 509(S) Secondary Formula: Federal/State

0 0 0 0 0 0 234(S) Secondary Formula: State

0 0 0 0 0 0 39(S) Secondary Formula: State Match

0 0 0 0 0 0 0Soft Match: Federal

0 0 0 0 0 0 637(S) State Formula: Secondary - Unpaved

409 0 0 0 0 217 0STP: BROS - Federal

102 0 0 0 0 54 0STP: BROS - Soft Match

0 0 0 0 0 35 81(S) Telecommunications: State

-18 0 0 0 0 511 307 1,811Total

MPO Area

NonMPOSecondary

PROGRAM/SYSTEM

RTE 718 - BRIDGE REPLACEMENT

PROJECT

UPC NO.:

ROUTE:

97690

NFO0718

Underway

SCHEDULE

17

ESTIMATED COST (000's)

JURISDICTION:

MANSON ROADSTREET NAME:

PELunenburg County

CNFROM: APPROACHES & BRIDGE OVER BEAVER

POND CR TO: (0.9 MI. RTE. 612) (0.2000 MI)

DESCRIPTION: RW

29533 -1PROJECT LENGTH: 0.2000 MI STRUCTURE NO.: SUFFICIENCY RATING:

SCOPE OF WORK: Bridge Replacement w/o Added Capacity TO 17

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 3Bond Match: State Bond Match

0 0 0 0 0 0 14Bridge Replacement: Federal

0 0 0 0 0 0 0 17Total

790 11/12/2014

Page 93: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Secondary

MPO Area

NonMPOSecondary

PROGRAM/SYSTEM

RTE 621 - BRIDGE REPLACEMENT

PROJECT

UPC NO.:

ROUTE:

91144

NFO0621

Underway

SCHEDULE

535

ESTIMATED COST (000's)

JURISDICTION:

COUNTRY CLUB ROADSTREET NAME:

PEMecklenburg County

FY2015 1,621CN

UnderwayFROM: 0.684 MI N. OF RTE 778 (TAYLOR ROAD) TO:

0.779 MI N. OF RTE 778 (TAYLOR ROAD) (0.0950 MI)

DESCRIPTION: 76RW

30022 -1PROJECT LENGTH: 0.0760 MI STRUCTURE NO.: SUFFICIENCY RATING:

SCOPE OF WORK: Bridge Replacement w/o Added Capacity TO 2,232

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 73Bridge Replacement: Federal

0 0 0 0 0 0 582(S) Federal Formula STP: Federal

0 0 0 0 0 0 145(S) Federal Formula STP: State Bond Match

0 0 0 0 0 0 74(S) Secondary Formula: Federal

0 0 0 0 0 0 19(S) Secondary Formula: State Match

0 0 0 0 0 0 18Soft Match: Federal

464 0 0 0 452 60 0STP: Bridge - Federal

116 0 0 0 113 15 0STP: Bridge - Soft Match

0 0 0 0 0 19 82(S) Telecommunications: State

0 0 0 0 565 580 94 993Total

MPO Area

NonMPOSecondary

PROGRAM/SYSTEM

RTE 633 - BRIDGE REPLACEMENT

PROJECT

UPC NO.:

ROUTE:

93090

NFO0633

Underway

SCHEDULE

113

ESTIMATED COST (000's)

JURISDICTION:

STREET NAME:

PEMecklenburg County

FY2017 1,132CN

FY2016 (0.1900 MI)DESCRIPTION: 57RW

PROJECT LENGTH: _SCOPE OF WORK: Bridge Replacement w/o Added Capacity TO 1,302

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

52 0 627 148 89 0 124STP: BROS - Federal

13 0 157 37 22 0 31STP: BROS - Soft Match

0 0 784 185 112 65 0 155Total

MPO Area

NonMPOSecondary

PROGRAM/SYSTEM

RTE 601 - BRIDGE REPLACEMENT

PROJECT

UPC NO.:

ROUTE:

99006

NFO0601

Underway

SCHEDULE

666

ESTIMATED COST (000's)

JURISDICTION:

Flat Rock RoadSTREET NAME:

PENottoway County

FY2016 1,527CN

UnderwayAPPROACHES & BRIDGE OVER WHETSTONE CR

(0.0800 MI)

DESCRIPTION: 100RW

12834 26PROJECT LENGTH: _ STRUCTURE NO.: SUFFICIENCY RATING:

SCOPE OF WORK: Bridge Replacement w/o Added Capacity TO 2,293

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 120Bridge Replacement: Federal

0 0 0 0 194 0 0CTB Formula: Bridge - State

0 0 0 0 0 0 30Soft Match: Federal

292 0 0 522 237 15 492STP: BROS - Federal

73 0 0 131 59 4 123STP: BROS - Soft Match

0 0 0 653 491 365 19 765Total

11/12/2014 791

Page 94: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Secondary

MPO Area

NonMPOSecondary

PROGRAM/SYSTEM

RTE 618 - BRIDGE REPLACEMENT

PROJECT

UPC NO.:

ROUTE:

101238

NFO0618

Underway

SCHEDULE

550

ESTIMATED COST (000's)

JURISDICTION:

Indian Oak RoadSTREET NAME:

PENottoway County

FY2019 1,778CN

FY2018FROM: 1.028 MI S RTE 613 (TURKEY ISLAND RD) TO:

1.042 MI S RTE 613 (TURKEY ISLAND RD) (0.0140 MI)

DESCRIPTION: 200RW

PROJECT LENGTH: 0.0140 MISCOPE OF WORK: Bridge Replacement w/o Added Capacity TO 2,528

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 600 824 0 0 0 0CTB Formula: Bridge - State

0 0 483 0 0 0 0STP: Bridge - Federal

0 0 121 0 0 0 0STP: Bridge - Soft Match

0 0 60 40 300 0 0STP: BROS - Federal

0 0 15 10 75 0 0STP: BROS - Soft Match

0 600 1,503 50 375 0 0 0Total

MPO Area

NonMPOSecondary

PROGRAM/SYSTEM

RTE 665 - ADD SIDEWALK

PROJECT

UPC NO.:

ROUTE:

105650

NFO0665

FY2015

SCHEDULE

11

ESTIMATED COST (000's)

JURISDICTION:

NOTTOWAY AVENUESTREET NAME:

PENottoway County

FY2016 94CN

FY2015FROM: BLACKSTONE CORP LIMITS TO: END STATE

MAINT (0.2300 MI)

DESCRIPTION: 6RW

PROJECT LENGTH: 0.2300 MISCOPE OF WORK: Reconstruction w/ Added Capacity TO 111

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 55 0Revenue Sharing Funds: Local Match

0 0 0 0 0 55 0Revenue Sharing Funds: State Match

0 0 0 0 0 0 111 0Total

MPO Area

NonMPOSecondary

PROGRAM/SYSTEM

RTE 609 - BRIDGE REPLACEMENT (R/W)

PROJECT

UPC NO.:

ROUTE:

95072

NFO0609

SCHEDULE ESTIMATED COST (000's)

JURISDICTION:

Giles Bridge RoadSTREET NAME:

PEPowhatan County

CN

UnderwayFROM: 0.26 MI S OF AMELIA/POWHATAN COUNTY

LINE TO: 0.30 MI N OF AMELIA/POWHATAN COUNTY

LINE (0.5600 MI)

DESCRIPTION: 33RW

PROJECT LENGTH: 0.5600 MISCOPE OF WORK: Bridge Replacement w/o Added Capacity TO 33

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 13Bond Match: State Bond Match

0 0 0 0 0 0 54Bridge Replacement: Federal

-34 0 0 0 0 0 0 67Total

792 11/12/2014

Page 95: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Secondary

MPO Area

NonMPOSecondary

PROGRAM/SYSTEM

ROUTE 622 - REALIGN INTERSECTION

PROJECT

UPC NO.:

ROUTE:

103116

NFO0622

Underway

SCHEDULE

400

ESTIMATED COST (000's)

JURISDICTION:

DORSET ROADSTREET NAME:

PEPowhatan County

FY2016 1,500CN

FY2015FROM: AT ROUTE 677 (BATTERSON ROAD) TO: AT

ROUTE 677 (BATTERSON ROAD)

DESCRIPTION: 100RW

PROJECT LENGTH: 0.0000 MISCOPE OF WORK: Reconstruction w/o Added Capacity TO 2,000

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 2,500Revenue Sharing Funds: Local Match

0 0 0 0 0 0 2,500Revenue Sharing Funds: State Match

-3,000 0 0 0 0 0 0 5,000Total

MPO Area

RichmondSecondary

PROGRAM/SYSTEM

RTE 676 - EXTEND EXISTING ROAD

PROJECT

UPC NO.:

ROUTE:

104213

NFO0676

SCHEDULE ESTIMATED COST (000's)

JURISDICTION:

URBINE ROADSTREET NAME:

PEPowhatan County

CN

FROM: STAVE MILL ROAD TO: ROUTE 60 (0.5000 MI)DESCRIPTION: RW

PROJECT LENGTH: 0.5000 MISCOPE OF WORK: New Construction Roadway TO 0

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 1,000Revenue Sharing Funds: Local Match

0 0 0 0 0 0 1,000Revenue Sharing Funds: State Match

-2,000 0 0 0 0 0 0 2,000Total

MPO Area

NonMPOSecondary

PROGRAM/SYSTEM

ROUTE 681 - BRIDGE REPLACEMENT OVER

APPOMATTOX RIVER

PROJECT

UPC NO.:

ROUTE:

101246

NFO0681

Revised schedule required.REPORT NOTE:

FY2017

SCHEDULE

500

ESTIMATED COST (000's)

JURISDICTION:

CLEMENTON ROADSTREET NAME:

PEPowhatan County

FY2019 3,871CN

FY2018Rte 681 Over Appomattox River (VA Str 6910) (0.2700 MI)DESCRIPTION: 200RW

PROJECT LENGTH: 0.2700 MISCOPE OF WORK: Bridge Replacement w/o Added Capacity TO 4,571

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 546 0 0 0 0 0CTB Formula: Bridge - State

0 500 347 100 248 0 0STP: BROS - Federal

0 125 87 25 62 0 0STP: BROS - Soft Match

2,532 1,171 434 125 310 0 0 0Total

11/12/2014 793

Page 96: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Secondary

MPO Area

NonMPOSecondary

PROGRAM/SYSTEM

RTE 684 - REPLACE BRIDGE

PROJECT

UPC NO.:

ROUTE:

93089

NFO0684

Revised schedule required.REPORT NOTE:

Underway

SCHEDULE

600

ESTIMATED COST (000's)

JURISDICTION:

Cartersville RdSTREET NAME:

PEPowhatan County

FY2020 2,862CN

FY2018FROM: 0.89 MI W RTE 600 / 621 TO: 1.06 MI W RTE 600

/ 621 (0.1700 MI)

DESCRIPTION: 103RW

PROJECT LENGTH: 0.1700 MISCOPE OF WORK: Bridge Replacement w/o Added Capacity TO 3,565

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 1,997 0 0 0 0 0CTB Formula: Bridge - State

0 0 793 0 0 0 0STP: Bridge - Federal

0 0 198 0 0 0 0STP: Bridge - Soft Match

170 0 0 41 250 0 0STP: BROS - Federal

43 0 0 10 62 0 0STP: BROS - Soft Match

0 1,997 991 52 312 213 0 0Total

MPO Area

RichmondSecondary

PROGRAM/SYSTEM

RTE 711 - WIDEN TO 4 LANES

PROJECT

UPC NO.:

ROUTE:

86442

NFO0711

Revised schedule required.REPORT NOTE:

Underway

SCHEDULE

2,404

ESTIMATED COST (000's)

JURISDICTION:

HUGUENOT TRAILSTREET NAME:

PEPowhatan County

FY2016 16,079CN

UnderwayFROM: 0.370 MI. EAST OF RTE. 288 TO: 0.142 MI.

EAST OF THE POWHATAN / CHESTERFIELD COUNTY

LINE (1.2000 MI)

DESCRIPTION: 2,110RW

29606 -1PROJECT LENGTH: 1.2000 MI STRUCTURE NO.: SUFFICIENCY RATING:

SCOPE OF WORK: Reconstruction w/ Added Capacity TO 20,593

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 570Bond Proceeds: CPR Bonds

0 0 3,978 1,885 2,767 0 0CTB Formula: Bridge - State

0 0 0 0 0 0 166Non-Formula: State Match

0 0 0 0 0 0 671RSTP (STP Regional): Federal

0 0 0 0 0 0 2RSTP (STP Regional): State Match

0 0 0 0 0 0 126(S) Secondary Formula: Federal

0 0 0 0 0 0 32(S) Secondary Formula: State Match

88 0 0 721 963 63 0STP: Bridge - Federal

22 0 0 180 241 16 0STP: Bridge - Soft Match

0 0 0 0 0 0 758STP: Statewide - Federal

0 0 0 0 0 0 190STP: Statewide - Soft Match

7,157 0 3,978 2,785 3,971 109 78 2,514Total

794 11/12/2014

Page 97: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Secondary

MPO Area

NonMPOSecondary

PROGRAM/SYSTEM

RTE 711 - REPLACE BRIDGE

PROJECT

UPC NO.:

ROUTE:

104954

NFO0711

FY2019

SCHEDULE

1,200

ESTIMATED COST (000's)

JURISDICTION:

HUGUENOT TRAILSTREET NAME:

PEPowhatan County

FY2022 3,360CN

FY2020DESCRIPTION: 400RW

PROJECT LENGTH: _SCOPE OF WORK: Bridge Replacement w/o Added Capacity TO 4,960

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 1,638 980 0 0 0 0STP: Bridge - Federal

0 409 245 0 0 0 0STP: Bridge - Soft Match

1,688 2,047 1,225 0 0 0 0 0Total

MPO Area

RichmondSecondary

PROGRAM/SYSTEM

RTE 714 - CONSTRUCT NEW ROAD

PROJECT

UPC NO.:

ROUTE:

104212

NFO0714

Revised schedule required.REPORT NOTE:

FY2014

SCHEDULE

300

ESTIMATED COST (000's)

JURISDICTION:

WINTERFIELD ROADSTREET NAME:

PEPowhatan County

FY2016 1,300CN

FROM: ROUTE 714 TO: ROUTE 711 (0.4500 MI)DESCRIPTION: RW

PROJECT LENGTH: 0.4500 MISCOPE OF WORK: New Construction Roadway TO 1,600

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 800Revenue Sharing Funds: Local Match

0 0 0 0 0 0 800Revenue Sharing Funds: State Match

0 0 0 0 0 0 0 1,600Total

MPO Area

RichmondSecondary

PROGRAM/SYSTEM

RTE 1343 - NEW ROADWAY CONSTRUCTION

PROJECT

UPC NO.:

ROUTE:

8216

NFO1343

Complete

SCHEDULE

1,246

ESTIMATED COST (000's)

JURISDICTION:

Carter Gallier BoulevardSTREET NAME:

PEPowhatan County

Underway 2,595CN

FY2015FROM: Intersection Luck Stone Entrance TO: Intersection

Route 60 (State Police Crossover) (0.5500 MI)

DESCRIPTION: 1,772RW

PROJECT LENGTH: 0.5500 MISCOPE OF WORK: New Construction Roadway TO 5,613

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 385Non-Formula: State Match

0 0 0 0 0 0 3,321RSTP (STP Regional): Federal

0 0 0 0 440 0 0RSTP (STP Regional): MPO - Federal

0 0 0 0 110 0 0RSTP (STP Regional): MPO - State Match

0 0 0 0 0 0 446RSTP (STP Regional): State Match

0 0 0 0 0 0 127(S) Secondary Formula: Federal/State

0 0 0 0 0 0 14(S) Secondary Formula: State

83 0 0 83 83 0 0(S) Telecommunications: State

523 0 0 83 633 83 0 4,292Total

11/12/2014 795

Page 98: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Secondary

MPO Area

Tri-CitiesSecondary

PROGRAM/SYSTEM

RTE 630 - ADD LEFT TURN LANE

PROJECT

UPC NO.:

ROUTE:

82849

NFO0630

MPO Project. Balance of funds to be provided by MPO. Revised schedule required.REPORT NOTE:

Underway

SCHEDULE

25

ESTIMATED COST (000's)

JURISDICTION:

BULL HILL ROADSTREET NAME:

PEPrince George County

FY2020 249CN

FROM: 0.10 MI S RTE 460 TO: RTE 460 (0.1000 MI)DESCRIPTION: RW

PROJECT LENGTH: 0.1000 MISCOPE OF WORK: Safety TO 274

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 53CMAQ: Federal

0 0 0 0 0 0 13CMAQ: State Match

208 0 0 0 0 0 0 66Total

MPO Area

Tri-CitiesSecondary

PROGRAM/SYSTEM

RTE 630 - ROUNDABOUT

PROJECT

UPC NO.:

ROUTE:

87941

NFO0630

Revised schedule required.REPORT NOTE:

Underway

SCHEDULE

60

ESTIMATED COST (000's)

JURISDICTION:

JEFFERSON PARK ROADSTREET NAME:

PEPrince George County

FY2013 77CN

UnderwayAT AVENUE A - FT LEE (0.2000 KM)DESCRIPTION: 56RW

PROJECT LENGTH: 0.2000 KMSCOPE OF WORK: Safety TO 192

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 116Priority Transportation Funds: State

0 0 0 0 0 0 121Special Grant Projects: Federal

-45 0 0 0 0 0 0 238Total

MPO Area

Tri-CitiesSecondary

PROGRAM/SYSTEM

RTE 645 - WIDENING

PROJECT

UPC NO.:

ROUTE:

105131

NFO0645

MPO Project. Balance to be provided by MPO.REPORT NOTE:

Underway

SCHEDULE

200

ESTIMATED COST (000's)

JURISDICTION:

PUDDLEDOCK ROADSTREET NAME:

PEPrince George County

FY2022 3,369CN

FY2020FROM: RTE 144 (TEMPLE AVE) TO: PETERSBURG

CITY LIMITS (0.5283 MI)

DESCRIPTION: 1,500RW

PROJECT LENGTH: 0.5283 MISCOPE OF WORK: Reconstruction w/ Added Capacity TO 5,069

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

85 0 0 825 557 0 423RSTP (STP Regional): MPO - Federal

21 0 0 206 139 0 106RSTP (STP Regional): MPO - State Match

2,706 0 0 1,032 696 107 0 528Total

796 11/12/2014

Page 99: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Secondary

MPO Area

NonMPOSecondary

PROGRAM/SYSTEM

DISTRICT SECONDARY ALLOCATIONS

PROJECT

UPC NO.: T1079

NFOSecondary Allocation

BALANCE OF SECONDARY FUNDS FOR PROJECTS NOT IN SYIP.REPORT NOTE:

DESCRIPTION:

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

Principal Fund Source:

0 0 0 0 0 428(S) Federal Formula STP: Federal: Federal

Formula STP - Secondary : Henrico

(CNF675)

0

0 0 0 0 0 0 428(S) Federal Formula STP: Federal

0 0 0 0 0 167(S) Federal Formula STP: State Bond Match:

Federal Formula - Secondary Bond Match :

Henrico (CNB653)

0

0 0 0 0 0 0 167(S) Federal Formula STP: State Bond Match

0 0 0 0 0 0(S) Residue Parcel Revenue: State: Residue

Parcel - Henrico County (CNS620)

0

0 0 0 0 0 0 0(S) Residue Parcel Revenue: State

0 0 0 0 0 1,025(S) Secondary Formula: Federal: Secondary

Formula - Bridge : Henrico (CNF669)

0

0 0 0 0 0 811(S) Secondary Formula: Federal: Secondary

Formula - EB(MG) : Henrico (CNF668)

0

0 0 0 0 0 577(S) Secondary Formula: Federal: Secondary

Formula - IM to STP : Henrico (CNF626)

0

0 0 0 0 0 193(S) Secondary Formula: Federal: Secondary

Formula - STP : Henrico (CNF667)

0

0 0 0 0 0 0 2,607(S) Secondary Formula: Federal

0 0 0 0 0 1,264(S) Secondary Formula: Federal/State:

Federal/State - Henrico (CNS601)

0

0 0 0 0 0 0 1,264(S) Secondary Formula: Federal/State

0 0 0 0 0 4,439(X) Secondary Formula: State: Secondary

Formula - State : Henrico

0

0 0 0 0 0 0 4,439(X) Secondary Formula: State

0 0 0 0 0 714(S) Secondary Formula: State Match:

Secondary Formula - Match : Henrico

(CNB670)

0

0 0 0 0 0 0 714(S) Secondary Formula: State Match

0 0 0 0 0 0 9,619Total

MPO Area

NonMPOSecondary

PROGRAM/SYSTEM

ADA COMPLIANCE

PROJECT

UPC NO.:

ROUTE:

106352

NFO

SCHEDULE ESTIMATED COST (000's)

JURISDICTION:

STREET NAME:

PERichmond District-wide

FY2015 473CN

FROM: various TO: variousDESCRIPTION: RW

PROJECT LENGTH: _SCOPE OF WORK: Facilities for Pedestrians and Bicycles TO 473

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 496Bond Proceeds: CPR Bonds -23

11/12/2014 797

Page 100: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Secondary

MPO Area

Tri-CitiesSecondary

PROGRAM/SYSTEM

ARRA - TRI-CITIES RESURFACING - CN ONLY

PROJECT

UPC NO.: 94858

NFOARRA09

ARRA CN for PE project UPC 95041REPORT NOTE:

FROM: VARIOUS LOCATIONS IN CHESTERFIELD,

DINWIDDIE, TO: PETERSBURG, PRINCE GEORGE &

HOPEWELL (10.5000 MI)

DESCRIPTION:

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 2,344American Recovery and Reinvestment Act:

Urbanized Area > 200K

MPO Area

RichmondSecondary

PROGRAM/SYSTEM

DISTRICTWIDE - HIGH FRICTION CORRIDOR

PAVEMENT TREATMENTS

PROJECT

UPC NO.:

ROUTE:

104699

NFO9999

Complete

SCHEDULE

80

ESTIMATED COST (000's)

JURISDICTION:

STREET NAME:

PERichmond District-wide

Underway 1,776CN

FROM: VARIOUS TO: VARIOUSDESCRIPTION: RW

PROJECT LENGTH: _SCOPE OF WORK: Safety TO 1,856

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 1,772High Risk Rural: Federal

0 0 0 0 0 0 197High Risk Rural: State Match

-113 0 0 0 0 0 0 1,969Total

MPO Area

RichmondSecondary

PROGRAM/SYSTEM

DISTRICTWIDE - HIGH FRICTION CORRIDOR

PAVEMENT

PROJECT

UPC NO.:

ROUTE:

106239

NFO9999

Underway

SCHEDULE

150

ESTIMATED COST (000's)

JURISDICTION:

STREET NAME:

PERichmond District-wide

FY2016 2,000CN

FROM: VARIOUS TO: VARIOUSDESCRIPTION: RW

PROJECT LENGTH: _SCOPE OF WORK: Safety TO 2,150

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

1,800 0 0 0 0 135 0Highway Safety Improvements: Federal

200 0 0 0 0 15 0Highway Safety Improvements: Soft Match

0 0 0 0 0 2,000 150 0Total

798 11/12/2014

Page 101: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Urban

MPO Area

RichmondUrban

PROGRAM/SYSTEM

RTE 1 - WIDEN TO 6 LANES

PROJECT

UPC NO.:

ROUTE:

8651

NFO0001

PE only. Revised schedule required. Project linked to UPC 13463.REPORT NOTE:

Underway

SCHEDULE

545

ESTIMATED COST (000's)

JURISDICTION:

ROUTE 1STREET NAME:

PEAshland

FY2022 1,543CN

UnderwayFROM: 0.008 MILE NORTH OF ASHCAKE ROAD TO:

0.015 MILE SOUTH OF PLEASANT ROAD (0.4240 MI)

DESCRIPTION: 1,700RW

PROJECT LENGTH: 0.4240 MISCOPE OF WORK: Reconstruction w/ Added Capacity TO 3,788

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 15Federal Formula STP: Federal

0 0 0 0 0 0 0Federal Formula STP: State Bond Match

0 0 0 0 0 0 2Local Project Contributions: Urban - Local

Match

0 0 0 0 0 0 10State Formula: Urban - Local Match

0 0 0 0 0 0 86Urban Formula: Federal

0 0 0 0 0 0 435Urban Formula: State

0 0 0 0 0 0 22Urban Formula: State Match

3,217 0 0 0 0 0 0 571Total

MPO Area

RichmondUrban

PROGRAM/SYSTEM

RTE 1 - IMPROVE INTERSECTION AT RTE 54

PROJECT

UPC NO.:

ROUTE:

13463

NFO0001

Project linked to UPC 8651. MPO project.REPORT NOTE:

Underway

SCHEDULE

751

ESTIMATED COST (000's)

JURISDICTION:

NORTH & SOUTH WASHINGTON HWYSTREET NAME:

PEAshland

FY2015 3,158CN

UnderwayFROM: 0.119 MI. S. OF INT. W/ RTE 54 TO: 0.086 MI. N.

OF INT. W/ RTE 54 (0.2070 MI)

DESCRIPTION: 2,500RW

PROJECT LENGTH: 0.2050 MISCOPE OF WORK: Safety TO 6,409

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 366CMAQ: Federal

400 0 0 0 0 200 3,115CMAQ: MPO - Federal

100 0 0 0 0 50 779CMAQ: MPO - State Match

0 0 0 0 0 0 3Federal Formula STP: Federal

0 0 0 0 0 0 1Federal Formula STP: State Bond Match

0 0 0 0 0 0 3Local Project Contributions: Urban - Local

Match

0 0 0 0 0 0 49Non-Formula: State

0 0 0 0 0 0 450Proffers: State

0 0 0 0 0 0 195RSTP (STP Regional): Federal

0 0 0 0 0 0 15State Formula: Urban - Local Match

0 0 0 0 0 0 63Urban Formula: Federal

0 0 0 0 0 0 168Urban Formula: Federal/State

0 0 0 0 0 0 736Urban Formula: State

0 0 0 0 0 0 14Urban Formula: State Match

-299 0 0 0 0 500 250 5,958Total

11/12/2014 799

Page 102: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Urban

MPO Area

RichmondUrban

PROGRAM/SYSTEM

RTE 1 - INTERSECTION IMPROVEMENT

PROJECT

UPC NO.:

ROUTE:

105677

NFO0001

FY2015

SCHEDULE

66

ESTIMATED COST (000's)

JURISDICTION:

WASHINGTON HIGHWAYSTREET NAME:

PEAshland

FY2019 614CN

FY2017FROM: .17 MI NORTH THE VITAMIN SHOPPE WAY TO:

.15 MI SOUTH OF THE VITAMIN SHOPPE WAY (0.3200

MI)

DESCRIPTION: 20RW

PROJECT LENGTH: 0.3200 MISCOPE OF WORK: Reconstruction w/o Added Capacity TO 700

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 350 0Revenue Sharing Funds: Local Match

0 0 0 0 0 350 0Revenue Sharing Funds: State Match

0 0 0 0 0 0 700 0Total

MPO Area

NonMPOUrban

PROGRAM/SYSTEM

N. AMELIA AVENUE - REPLACE BRIDGE DECK

PROJECT

UPC NO.:

ROUTE:

100809

NFO

Complete

SCHEDULE

408

ESTIMATED COST (000's)

JURISDICTION:

NORTH AMELIA AVENUESTREET NAME:

PEBlackstone

Underway 1,409CNFROM: 0.03 mi N. Rte 460 (Chruch Street) TO: 0.073 mi

N. Rte 460 (Church Street) (0.0430 MI)

DESCRIPTION: RW

22419 68PROJECT LENGTH: 0.0430 MI STRUCTURE NO.: SUFFICIENCY RATING:

SCOPE OF WORK: Bridge Rehab w/o Added Capacity TO 1,817

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 16Bond Match: State Bond Match

0 0 0 0 0 0 246Bridge Replacement: Federal

0 0 0 0 0 0 100Federal Formula STP: Federal

0 0 0 0 0 0 25Federal Formula STP: State Bond Match

0 0 0 0 0 0 595Federal STP: Federal

0 0 0 0 0 0 0Local Project Contributions: Urban - Local

Match

0 0 0 0 0 0 194Soft Match: Federal

0 0 0 0 0 0 0State Formula: Urban - Local Match

0 0 0 0 0 129 485STP: Bridge - Federal

0 0 0 0 0 32 121STP: Bridge - Soft Match

0 0 0 0 0 0 77STP: BROS - Federal

0 0 0 0 0 0 19STP: BROS - Soft Match

0 0 0 0 0 0 107STP: Statewide - Federal

0 0 0 0 0 0 27STP: Statewide - Soft Match

0 0 0 0 0 0 4Urban Formula: Federal

0 0 0 0 0 0 19Urban Formula: State

0 0 0 0 0 0 1Urban Formula: State Match

-380 0 0 0 0 0 161 2,036Total

800 11/12/2014

Page 103: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Urban

MPO Area

NonMPOUrban

PROGRAM/SYSTEM

SOUTH MAIN STREET, PHASE III

PROJECT

UPC NO.:

ROUTE:

90175

NFO0040

Local Priority 2. Complete & revised schedule required.REPORT NOTE:

Underway

SCHEDULE

253

ESTIMATED COST (000's)

JURISDICTION:

South Main streetSTREET NAME:

PEBlackstone

CN

FROM: Tenth Street TO: SCL (1.0000 MI)DESCRIPTION: RW

PROJECT LENGTH: 1.0000 MISCOPE OF WORK: Reconstruction w/o Added Capacity TO 253

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 8Federal Formula STP: Federal

0 0 0 0 0 0 2Federal Formula STP: State Bond Match

243 0 0 0 0 0 0 10Total

MPO Area

NonMPOUrban

PROGRAM/SYSTEM

NOTTOWAY AVE - ADD SIDEWALK

PROJECT

UPC NO.:

ROUTE:

105651

NFOU000

FY2015

SCHEDULE

41

ESTIMATED COST (000's)

JURISDICTION:

NOTTOWAY AVENUESTREET NAME:

PEBlackstone

FY2016 350CN

FY2015FROM: N AMELIA ST TO: CORP LIMITS (0.3800 MI)DESCRIPTION: 11RW

PROJECT LENGTH: 0.3800 MISCOPE OF WORK: Reconstruction w/o Added Capacity TO 402

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 201 0Revenue Sharing Funds: Local Match

0 0 0 0 0 201 0Revenue Sharing Funds: State Match

0 0 0 0 0 0 402 0Total

MPO Area

Tri-CitiesUrban

PROGRAM/SYSTEM

CITY OF COLONIAL HEIGHTS - FORMULA CITY

PAYMENT

PROJECT

UPC NO.: T7749

NFOTown/City-wide

DESCRIPTION:

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0Urban Formula: State

0 0 0 0 0 0Urban Formula: State Match

0 0 0 0 0 0Total

11/12/2014 801

Page 104: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Urban

MPO Area

Tri-CitiesUrban

PROGRAM/SYSTEM

BRANDERS BRIDGE ROAD AND ROUTE 1 -

INTERSECTION IMPROVEMENT

PROJECT

UPC NO.:

ROUTE:

99194

NFO

MPO Project. Locally Administered. Revised schedule required.REPORT NOTE:

FY2017

SCHEDULE

35

ESTIMATED COST (000's)

JURISDICTION:

Branders Bridge RoadSTREET NAME:

PEColonial Heights

FY2018 210CN

FROM: west of Route 1 TO: Route 1 (0.1000 MI)DESCRIPTION: RW

PROJECT LENGTH: 0.1000 MISCOPE OF WORK: Resurfacing TO 245

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 196 0 0 0 0CMAQ: MPO - Federal

0 0 49 0 0 0 0CMAQ: MPO - State Match

0 0 245 0 0 0 0 0Total

MPO Area

Tri-CitiesUrban

PROGRAM/SYSTEM

ROUTE 1 AND WESTOVER AVENUE

INTERSECTION

PROJECT

UPC NO.:

ROUTE:

100501

NFO

MPO Project. Locally Administered.REPORT NOTE:

FY2019

SCHEDULE

125

ESTIMATED COST (000's)

JURISDICTION:

Westover AvenueSTREET NAME:

PEColonial Heights

FY2020 656CN

FY2020FROM: Route 1 TO: .2 miles east of Route 1 (0.2000 MI)DESCRIPTION: 19RW

PROJECT LENGTH: 0.2000 MISCOPE OF WORK: Safety TO 800

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 525 115 0 0 0 0CMAQ: MPO - Federal

0 131 29 0 0 0 0CMAQ: MPO - State Match

0 656 144 0 0 0 0 0Total

MPO Area

Tri-CitiesUrban

PROGRAM/SYSTEM

DUPUY AVE - MINOR WIDENING

PROJECT

UPC NO.:

ROUTE:

101287

NFO

MPO Project. Locally Administered.REPORT NOTE:

Underway

SCHEDULE

480

ESTIMATED COST (000's)

JURISDICTION:

DUPUY AVENUESTREET NAME:

PEColonial Heights

FY2015 2,602CN

FY2014FROM: WCL COLONIAL HTS TO: 0.1 MI. WEST RTE. 1

(BOULEVARD) (0.3800 MI)

DESCRIPTION: 1,001RW

PROJECT LENGTH: 0.3800 MISCOPE OF WORK: Reconstruction w/o Added Capacity TO 4,083

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 1,091RSTP (STP Regional): Federal

81 0 0 0 0 119 1,975RSTP (STP Regional): MPO - Federal

20 0 0 0 0 30 494RSTP (STP Regional): MPO - State Match

0 0 0 0 0 0 273RSTP (STP Regional): State Match

0 0 0 0 0 101 149 3,833Total

802 11/12/2014

Page 105: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Urban

MPO Area

Tri-CitiesUrban

PROGRAM/SYSTEM

LAKEVIEW AVE - MINOR WIDENING

PROJECT

UPC NO.:

ROUTE:

101288

NFO

MPO Project. Locally Administered.REPORT NOTE:

Underway

SCHEDULE

414

ESTIMATED COST (000's)

JURISDICTION:

LAKEVIEW AVENUESTREET NAME:

PEColonial Heights

FY2015 2,550CN

FY2014FROM: BRIJIDAN LA TO: BOULEVARD (RTE 1) (0.4000

MI)

DESCRIPTION: 350RW

PROJECT LENGTH: 0.4000 MISCOPE OF WORK: Reconstruction w/o Added Capacity TO 3,314

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 331RSTP (STP Regional): Federal

83 0 0 0 0 1,368 869RSTP (STP Regional): MPO - Federal

21 0 0 0 0 342 217RSTP (STP Regional): MPO - State Match

0 0 0 0 0 0 83RSTP (STP Regional): State Match

0 0 0 0 0 104 1,710 1,501Total

MPO Area

Tri-CitiesUrban

PROGRAM/SYSTEM

WHITE SAND CT - REPAIR PAVEMENT

PROJECT

UPC NO.:

ROUTE:

104508

NFO0000

Underway

SCHEDULE

6

ESTIMATED COST (000's)

JURISDICTION:

WHITE SAND COURTSTREET NAME:

PEColonial Heights

FY2015 160CN

FROM: HERON RUN DR TO: END ST MAINT (0.1500 MI)DESCRIPTION: RW

PROJECT LENGTH: 0.1500 MISCOPE OF WORK: Restoration and Rehabilitation TO 166

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 0Local Project Contributions: Local

0 0 0 0 0 0 83Revenue Sharing Funds: Local Match

0 0 0 0 0 0 83Revenue Sharing Funds: State Match

0 0 0 0 0 0 0 166Total

MPO Area

Tri-CitiesUrban

PROGRAM/SYSTEM

CITY OF COLONIAL HEIGHTS - SRTS - NORTH

ES - SIDEWALKS

PROJECT

UPC NO.:

ROUTE:

105233

NFO0000

Locally Administered. Revised schedule required.REPORT NOTE:

Underway

SCHEDULE

20

ESTIMATED COST (000's)

JURISDICTION:

VARIOUSSTREET NAME:

PEColonial Heights

FY2017 200CN

FY2017FROM: HARGRAVE AVE TO: EASTMAN AVEDESCRIPTION: 30RW

PROJECT LENGTH: _SCOPE OF WORK: Safety TO 250

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 250Safe Routes to School: Federal

0 0 0 0 0 0 0 250Total

11/12/2014 803

Page 106: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Urban

MPO Area

Tri-CitiesUrban

PROGRAM/SYSTEM

RTE 1 - IMPROVE INT AT DUPUY AVE

PROJECT

UPC NO.:

ROUTE:

3945

NFO0001

Urban Construction Initiative project. MPO Project. Excess funds to be redistributed by MPO.REPORT NOTE:

Complete

SCHEDULE

740

ESTIMATED COST (000's)

JURISDICTION:

DUPUY AVENUE & BOULEVARDSTREET NAME:

PEColonial Heights

Underway 4,002CN

UnderwayFROM: DUPUY AVE - FR: BATTERY PLACE TO:

BOULEVARD TO: ROUTE 1 - FR: PICKWICK AVE TO:

LAFAYETTE AVE (0.3800 MI)

DESCRIPTION: 1,960RW

PROJECT LENGTH: 0.3800 MISCOPE OF WORK: Reconstruction w/o Added Capacity TO 6,702

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 1,796CMAQ: Federal

0 0 0 0 0 108 576CMAQ: MPO - Federal

0 0 0 0 0 27 144CMAQ: MPO - State Match

0 0 0 0 0 0 453CMAQ: State Match

0 0 0 0 0 0 1,715(X) Local Project Contributions: State Match

0 0 0 0 0 0 58Local Project Contributions: Urban - Local

Match

0 0 0 0 0 0 11State Formula: Urban - Local Match

0 0 0 0 0 0 1,523Urban Formula: Federal

0 0 0 0 0 0 132Urban Formula: State

0 0 0 0 0 0 175Urban Formula: State Match

-16 0 0 0 0 0 135 6,584Total

MPO Area

Tri-CitiesUrban

PROGRAM/SYSTEM

RTE 1 - ADD CENTER TURN LANE

PROJECT

UPC NO.:

ROUTE:

52434

NFO0001

Locally Administered - MPO Project. Excess funds to be redistributed by MPO.REPORT NOTE:

Complete

SCHEDULE

291

ESTIMATED COST (000's)

JURISDICTION:

BOULEVARDSTREET NAME:

PEColonial Heights

Underway 1,668CN

UnderwayFROM: WESTOVER AVE TO: WINDSOR AVE (0.1800

MI)

DESCRIPTION: 630RW

PROJECT LENGTH: 0.1800 MISCOPE OF WORK: Reconstruction w/o Added Capacity TO 2,589

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 2,007CMAQ: Federal

0 0 0 0 0 0 338CMAQ: State Match

0 0 0 0 0 0 2Local Project Contributions: Urban - Local

Match

0 0 0 0 0 0 247Minimum Guarantee: Federal

0 0 0 0 0 0 62Soft Match: Federal

0 0 0 0 0 0 1State Formula: Urban - Local Match

0 0 0 0 0 0 44Urban Formula: State

0 0 0 0 0 0 116Urban Formula: State Match

-228 0 0 0 0 0 0 2,817Total

804 11/12/2014

Page 107: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Urban

MPO Area

Tri-CitiesUrban

PROGRAM/SYSTEM

RTE 1 - ADD CENTER TURN LANE

PROJECT

UPC NO.:

ROUTE:

90374

NFO0001

MPO project. Excess funds to be redistributed by MPO. Locally AdministeredREPORT NOTE:

Complete

SCHEDULE

179

ESTIMATED COST (000's)

JURISDICTION:

BOULEVARDSTREET NAME:

PEColonial Heights

Underway 932CN

UnderwayFROM: WINDSOR AVE TO: PICKWICK AVE (0.0800 MI)DESCRIPTION: 475RW

PROJECT LENGTH: 0.0800 MISCOPE OF WORK: Reconstruction w/o Added Capacity TO 1,587

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 1,241CMAQ: Federal

0 0 0 0 0 0 179CMAQ: MPO - Federal

0 0 0 0 0 0 45CMAQ: MPO - State Match

0 0 0 0 0 0 310CMAQ: State Match

-188 0 0 0 0 0 0 1,775Total

MPO Area

Tri-CitiesUrban

PROGRAM/SYSTEM

REHABILITATE BRIDGES -VARIOUS

LOCATIONS

PROJECT

UPC NO.:

ROUTE:

105109

NFO9999

MPO Project. Locally administered. Revised schedule required.REPORT NOTE:

Underway

SCHEDULE

135

ESTIMATED COST (000's)

JURISDICTION:

VARIOUSSTREET NAME:

PEColonial Heights

FY2018 465CN

FY2017FROM: VARIOUS LOCATIONS TO: VARIOUS

LOCATIONS

DESCRIPTION: 50RW

PROJECT LENGTH: _SCOPE OF WORK: Bridge Rehab w/o Added Capacity TO 650

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 412 108 0 0 0 0RSTP (STP Regional): MPO - Federal

0 103 27 0 0 0 0RSTP (STP Regional): MPO - State Match

0 515 135 0 0 0 0 0Total

MPO Area

Tri-CitiesUrban

PROGRAM/SYSTEM

HOLLY AVE - RECONSTRUCTION

PROJECT

UPC NO.:

ROUTE:

105690

NFOU000

FY2015

SCHEDULE

6

ESTIMATED COST (000's)

JURISDICTION:

HOLLY AVENUESTREET NAME:

PEColonial Heights

FY2016 133CNDESCRIPTION: RW

PROJECT LENGTH: _SCOPE OF WORK: Reconstruction w/o Added Capacity TO 139

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 251 0Revenue Sharing Funds: Local Match

0 0 0 0 0 251 0Revenue Sharing Funds: State Match

-363 0 0 0 0 0 502 0Total

11/12/2014 805

Page 108: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Urban

MPO Area

RichmondUrban

PROGRAM/SYSTEM

RTE 271 - SIDEWALK (NEW CONSTRUCTION)

PROJECT

UPC NO.:

ROUTE:

105660

NFO0271

FY2015

SCHEDULE

125

ESTIMATED COST (000's)

JURISDICTION:

NUCKOLS RD/POUNCEY TRACT RDSTREET NAME:

PEHenrico County

FY2019 650CN

FY2017FROM: HEATHERFORD DR TO: OLD WYNDHAM DR

(1.4000 MI)

DESCRIPTION: 40RW

PROJECT LENGTH: 1.4000 MISCOPE OF WORK: Reconstruction w/ Added Capacity TO 815

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 400 0Revenue Sharing Funds: Local Match

0 0 0 0 0 400 0Revenue Sharing Funds: State Match

15 0 0 0 0 0 800 0Total

MPO Area

RichmondUrban

PROGRAM/SYSTEM

SHADY GROVE RD, OLD NUCKOLS RD - ADD

SIDEWALK

PROJECT

UPC NO.:

ROUTE:

104277

NFO9999

Underway

SCHEDULE

25

ESTIMATED COST (000's)

JURISDICTION:

SHADY GROVE ROAD and OLD NUCKOLS ROADSTREET NAME:

PEHenrico County

FY2014 113CNFROM: 500 FT S OLD NUCKOLS RD TO: 300 FT E

SHADY GROVE RD (0.1500 MI)

DESCRIPTION: RW

PROJECT LENGTH: 0.1500 MISCOPE OF WORK: Facilities for Pedestrians and Bicycles TO 138

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 25Local Project Contributions: Local

0 0 0 0 0 0 69Revenue Sharing Funds: Local Match

0 0 0 0 0 0 69Revenue Sharing Funds: State Match

-25 0 0 0 0 0 0 163Total

MPO Area

Tri-CitiesUrban

PROGRAM/SYSTEM

CATTAIL CREEK DRAINAGE CHANNEL -

IMPROVE DRAINAGE

PROJECT

UPC NO.:

ROUTE:

104278

NFO0000

FY2014

SCHEDULE

42

ESTIMATED COST (000's)

JURISDICTION:

VARIOUSSTREET NAME:

PEHopewell

FY2015 280CN

FROM: S 20TH ST (UNDER NS RR) TO: ELM STDESCRIPTION: RW

PROJECT LENGTH: _SCOPE OF WORK: Reconstruction w/o Added Capacity TO 322

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 161Revenue Sharing Funds: Local Match

0 0 0 0 0 0 161Revenue Sharing Funds: State Match

0 0 0 0 0 0 0 322Total

806 11/12/2014

Page 109: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Urban

MPO Area

Tri-CitiesUrban

PROGRAM/SYSTEM

E BROADWAY - REHABILITATE BRIDGE

PROJECT

UPC NO.:

ROUTE:

104509

NFO0000

Underway

SCHEDULE

19

ESTIMATED COST (000's)

JURISDICTION:

EAST BROADWAYSTREET NAME:

PEHopewell

FY2014 124CNFROM: GRADE CROSSING CONNECTION FROM

RIVERVIEW AVE TO: RAMSEY STREET (0.0400 MI)

DESCRIPTION: RW

PROJECT LENGTH: 0.0400 MISCOPE OF WORK: Bridge Rehab w/o Added Capacity TO 143

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 98Local Project Contributions: Local

0 0 0 0 0 0 22Revenue Sharing Funds: Local Match

0 0 0 0 0 0 22Revenue Sharing Funds: State Match

0 0 0 0 0 0 0 143Total

MPO Area

Tri-CitiesUrban

PROGRAM/SYSTEM

SOUTH 6TH AVE - REHABILITATE BRIDGE

PROJECT

UPC NO.:

ROUTE:

104510

NFO0000

Underway

SCHEDULE

12

ESTIMATED COST (000's)

JURISDICTION:

SOUTH 6TH AVENUESTREET NAME:

PEHopewell

FY2014 60CNFROM: GRADE CROSSING CONNECTION FROM SO

7TH AVE TO: LAPRADE ST (0.0500 MI)

DESCRIPTION: RW

PROJECT LENGTH: 0.0500 MISCOPE OF WORK: Bridge Rehab w/o Added Capacity TO 72

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 50Local Project Contributions: Local

0 0 0 0 0 0 11Revenue Sharing Funds: Local Match

0 0 0 0 0 0 11Revenue Sharing Funds: State Match

0 0 0 0 0 0 0 72Total

MPO Area

Tri-CitiesUrban

PROGRAM/SYSTEM

RTE 10 - IMPROVE INTERSECTION

PROJECT

UPC NO.:

ROUTE:

12955

NFO0010

MPO Project.REPORT NOTE:

Underway

SCHEDULE

330

ESTIMATED COST (000's)

JURISDICTION:

E. Randolph RoadSTREET NAME:

PEHopewell

FY2015 651CN

UnderwayFROM: 0.162 MI West Hummel Ross Road TO: 0.09 MI

East Hummel Ross Road (0.2520 MI)

DESCRIPTION: 482RW

PROJECT LENGTH: 0.2520 MISCOPE OF WORK: Safety TO 1,462

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 816CMAQ: Federal

61 0 0 0 0 341 152CMAQ: MPO - Federal

15 0 0 0 0 85 38CMAQ: MPO - State Match

0 0 0 0 0 0 136CMAQ: State Match

-184 0 0 0 0 77 427 1,143Total

11/12/2014 807

Page 110: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Urban

MPO Area

Tri-CitiesUrban

PROGRAM/SYSTEM

RTE 36 - INTERSECTION IMPROVEMENT

PROJECT

UPC NO.:

ROUTE:

100500

NFO0036

MPO Project.REPORT NOTE:

Underway

SCHEDULE

75

ESTIMATED COST (000's)

JURISDICTION:

Oaklawn BoulevardSTREET NAME:

PEHopewell

FY2017 377CNFROM: .2 miles west of Route 630 TO: .2 miles east of

Rotue 630 (0.4000 MI)

DESCRIPTION: RW

PROJECT LENGTH: 0.4000 MISCOPE OF WORK: Reconstruction w/o Added Capacity TO 451

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

40 0 0 0 257 4 58CMAQ: MPO - Federal

10 0 0 0 64 1 15CMAQ: MPO - State Match

2 0 0 0 322 50 5 73Total

MPO Area

Tri-CitiesUrban

PROGRAM/SYSTEM

CEDAR LEVEL RD - WIDENING

PROJECT

UPC NO.:

ROUTE:

90018

NFO9047

PE and RW only. Accruing funds for CN.REPORT NOTE:

Underway

SCHEDULE

400

ESTIMATED COST (000's)

JURISDICTION:

Cedar Level RoadSTREET NAME:

PEHopewell

FY2018 12,100CN

FY2014FROM: COBBLESTONE PKWY TO: UR-9036 (MILES

AVE) (0.5190 MI)

DESCRIPTION: 1,000RW

PROJECT LENGTH: 0.5190 MISCOPE OF WORK: Reconstruction w/o Added Capacity TO 13,500

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 1Federal Formula STP: Federal

0 0 0 0 0 0 53Local Project Contributions: Urban - Local

Match

0 0 0 0 0 0 1Residue Parcel Revenue: State

0 0 0 0 0 0 640RSTP (STP Regional): Federal

374 0 1,144 788 1,260 0 0RSTP (STP Regional): MPO - Federal

94 0 286 197 315 0 0RSTP (STP Regional): MPO - State Match

0 0 0 0 0 0 160RSTP (STP Regional): State Match

0 0 0 0 0 0 1,869Urban Formula: Federal

0 0 0 0 0 0 287Urban Formula: State

0 0 0 0 0 0 423Urban Formula: State Match

5,611 0 1,430 985 1,575 468 0 3,432Total

MPO Area

Tri-CitiesUrban

PROGRAM/SYSTEM

BOSTON STREET - RECONSTRUCTION

PROJECT

UPC NO.:

ROUTE:

105654

NFOU000

FY2015

SCHEDULE

14

ESTIMATED COST (000's)

JURISDICTION:

BOSTON STREETSTREET NAME:

PEHopewell

FY2016 84CNDESCRIPTION: RW

PROJECT LENGTH: _SCOPE OF WORK: Reconstruction w/o Added Capacity TO 98

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 49 0Revenue Sharing Funds: Local Match

0 0 0 0 0 49 0Revenue Sharing Funds: State Match

0 0 0 0 0 0 98 0Total

808 11/12/2014

Page 111: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Urban

MPO Area

Tri-CitiesUrban

PROGRAM/SYSTEM

LIBERTY AVENUE - RECONSTRUCTION

PROJECT

UPC NO.:

ROUTE:

105656

NFOU000

FY2015

SCHEDULE

25

ESTIMATED COST (000's)

JURISDICTION:

LIBERTY AVENUESTREET NAME:

PEHopewell

FY2016 149CNDESCRIPTION: RW

PROJECT LENGTH: _SCOPE OF WORK: Reconstruction w/o Added Capacity TO 173

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 87 0Revenue Sharing Funds: Local Match

0 0 0 0 0 87 0Revenue Sharing Funds: State Match

0 0 0 0 0 0 173 0Total

MPO Area

Tri-CitiesUrban

PROGRAM/SYSTEM

GRANBY ST - RECONSTRUCTION

PROJECT

UPC NO.:

ROUTE:

105708

NFOU000

FY2015

SCHEDULE

30

ESTIMATED COST (000's)

JURISDICTION:

GRANBY STREETSTREET NAME:

PEHopewell

FY2016 200CNDESCRIPTION: RW

PROJECT LENGTH: _SCOPE OF WORK: Reconstruction w/o Added Capacity TO 230

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 115 0Revenue Sharing Funds: Local Match

0 0 0 0 0 115 0Revenue Sharing Funds: State Match

0 0 0 0 0 0 230 0Total

MPO Area

NonMPOUrban

PROGRAM/SYSTEM

TOWN OF KENBRIDGE - SRTS - KENBRIDGE

ES - PED SIGNAL IMP.

PROJECT

UPC NO.:

ROUTE:

105234

NFO0000

Underway

SCHEDULE

14

ESTIMATED COST (000's)

JURISDICTION:

BROAD STREETSTREET NAME:

PEKenbridge

FY2017 33CNFROM: 3 LOC - FIFTH ST, SIXTH ST, TO: MAIN ST

(0.1000 MI)

DESCRIPTION: RW

PROJECT LENGTH: 0.1000 MISCOPE OF WORK: Safety TO 47

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 47Safe Routes to School: Federal 0

11/12/2014 809

Page 112: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Urban

MPO Area

Tri-CitiesUrban

PROGRAM/SYSTEM

RIVES ROAD - INTERSECTION

IMPROVEMENTS

PROJECT

UPC NO.:

ROUTE:

15832

NFO

Locally Administered. State Funds - AC for future federal conversion. Revised schedule required.REPORT NOTE:

Underway

SCHEDULE

839

ESTIMATED COST (000's)

JURISDICTION:

RIVES ROADSTREET NAME:

PEPetersburg

FY2015 3,039CN

FY2014FROM: Route 301 TO: 0.1 Mile East Rte 301 (0.3900 MI)DESCRIPTION: 1,275RW

PROJECT LENGTH: 0.3900 MISCOPE OF WORK: Reconstruction w/ Added Capacity TO 5,153

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 459Federal Formula STP: Federal

0 0 0 0 0 0 10Federal Formula STP: State Bond Match

0 0 0 0 0 0 58Local Project Contributions: Urban - Local

Match

0 0 0 0 0 0 39Residue Parcel Revenue: State

0 0 0 0 0 0 20State Formula: Urban - Local Match

0 0 0 0 0 0 1,582Urban Formula: Federal

0 0 0 0 0 0 1,360Urban Formula: State

0 0 0 0 0 0 460Urban Formula: State Match

1,165 0 0 0 0 0 0 3,988Total

MPO Area

Tri-CitiesUrban

PROGRAM/SYSTEM

DOWNTOWN TRAFFIC SIGNAL OPTIMIZATION

- VARIOUS STREETS

PROJECT

UPC NO.:

ROUTE:

77537

NFO

MPO project. Excess funds to be redistributed by MPO. Locally Administered.REPORT NOTE:

Underway

SCHEDULE

325

ESTIMATED COST (000's)

JURISDICTION:

VARIOUSSTREET NAME:

PEPetersburg

CNFROM: N Jefferson St / S Jefferson St TO Perry St AND

TO: Wythe St / Halifax St TO: Bollingbrook St/ Bank St

DESCRIPTION: RW

PROJECT LENGTH: 0.0000 MISCOPE OF WORK: Safety TO 325

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 326CMAQ: Federal

-1 0 0 0 0 0 0 326Total

810 11/12/2014

Page 113: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Urban

MPO Area

Tri-CitiesUrban

PROGRAM/SYSTEM

RTE 36 - UPGRADE SIGNAL + EXTEND LTL

PROJECT

UPC NO.:

ROUTE:

101030

NFO

MPO Project. Locally Administered. Excess funds to be redistributed by MPO.REPORT NOTE:

Underway

SCHEDULE

155

ESTIMATED COST (000's)

JURISDICTION:

WASHINGTON STREETSTREET NAME:

PEPetersburg

FY2015 598CNFROM: 0.114 MI W RTE 9038 (PUDDLEDOCK RD) TO:

0.010 MI W RTE 9038 (PUDDLEDOCK RD) (0.1040 MI)

DESCRIPTION: RW

PROJECT LENGTH: 0.1040 MISCOPE OF WORK: Safety TO 753

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 100Accounts Receivable: Local

0 0 0 0 0 0 80RSTP (STP Regional): Federal

0 0 0 0 0 0 534RSTP (STP Regional): MPO - Federal

0 0 0 0 0 0 134RSTP (STP Regional): MPO - State Match

0 0 0 0 0 0 20RSTP (STP Regional): State Match

-115 0 0 0 0 0 0 868Total

MPO Area

Tri-CitiesUrban

PROGRAM/SYSTEM

PUDDLEDOCK RD - IMPROVE INTERSECTION

PROJECT

UPC NO.:

ROUTE:

101289

NFO

MPO Project. Revised estimate required.REPORT NOTE:

Underway

SCHEDULE

100

ESTIMATED COST (000's)

JURISDICTION:

PUDDLEDOCK ROADSTREET NAME:

PEPetersburg

FY2016 422CNFROM: 0.08 MI N RTE 36 (WASHINGTON ST) TO: 0.25

MI N RTE 36 (WASHINGTON ST) (0.1700 MI)

DESCRIPTION: RW

PROJECT LENGTH: 0.1700 MISCOPE OF WORK: Reconstruction w/o Added Capacity TO 522

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 38CMAQ: MPO - Federal

0 0 0 0 0 0 10CMAQ: MPO - State Match

0 0 0 0 0 0 122Local Project Contributions: Local

0 0 0 0 0 0 2Non-Formula: State

0 0 0 0 0 0 42Non-Formula: Statewide

0 0 0 0 0 0 292RSTP (STP Regional): Federal

0 0 0 0 0 0 71RSTP (STP Regional): State Match

0 0 0 0 0 0 168RSTP (STP Regional): Statewide

-222 0 0 0 0 0 0 744Total

MPO Area

Tri-CitiesUrban

PROGRAM/SYSTEM

RTE 460 - PAVEMENT OVERLAY

PROJECT

UPC NO.:

ROUTE:

105665

NFO

SCHEDULE ESTIMATED COST (000's)

JURISDICTION:

COUNTY DRIVESTREET NAME:

PEPetersburg

FY2015 3,500CNFROM: HICKORY HILL RD TO: PETERSBURG CITY

LIMITS (2.4000 MI)

DESCRIPTION: RW

PROJECT LENGTH: _SCOPE OF WORK: Resurfacing TO 3,500

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 1,750 0Revenue Sharing Funds: Local Match

0 0 0 0 0 1,750 0Revenue Sharing Funds: State Match

0 0 0 0 0 0 3,500 0Total

11/12/2014 811

Page 114: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Urban

MPO Area

Tri-CitiesUrban

PROGRAM/SYSTEM

UPGRADE SIGNALS - VARIOUS LOCATIONS

PROJECT

UPC NO.:

ROUTE:

104868

NFO0000

MPO Project. Revised schedule required. Balance to be provided by MPO.REPORT NOTE:

FY2019

SCHEDULE

200

ESTIMATED COST (000's)

JURISDICTION:

VARIOUSSTREET NAME:

PEPetersburg

FY2020 1,400CNFROM: VARIOUS LOCATIONS TO: VARIOUS

LOCATIONS

DESCRIPTION: RW

PROJECT LENGTH: _SCOPE OF WORK: Traffic Management/Engineering TO 1,600

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 240 0 0 0 0 0CMAQ: MPO - Federal

0 60 0 0 0 0 0CMAQ: MPO - State Match

1,300 300 0 0 0 0 0 0Total

MPO Area

Tri-CitiesUrban

PROGRAM/SYSTEM

UPGRADE SIGNALS - VARIOUS LOCATIONS

PROJECT

UPC NO.:

ROUTE:

104869

NFO0000

MPO Project. Revised schedule required.REPORT NOTE:

FY2016

SCHEDULE

150

ESTIMATED COST (000's)

JURISDICTION:

VARIOUSSTREET NAME:

PEPetersburg

FY2017 300CNFROM: VARIOUS LOCATIONS TO: VARIOUS

LOCATIONS

DESCRIPTION: RW

PROJECT LENGTH: _SCOPE OF WORK: Traffic Management/Engineering TO 450

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 240 120 0 0 0CMAQ: MPO - Federal

0 0 60 30 0 0 0CMAQ: MPO - State Match

0 0 300 150 0 0 0 0Total

MPO Area

Tri-CitiesUrban

PROGRAM/SYSTEM

RTE 301 - UPGRADE SIGNALS

PROJECT

UPC NO.:

ROUTE:

101033

NFO0301

MPO Project. Excess funds to be redistributed by MPO.REPORT NOTE:

Underway

SCHEDULE

100

ESTIMATED COST (000's)

JURISDICTION:

CRATER ROADSTREET NAME:

PEPetersburg

FY2015 255CN

UnderwayFROM: 0.0220 MI NORTH OF WALNUT BLVD TO: 0.0070

MI SOUTH OF WALNUT BLVD (0.0290 MI)

DESCRIPTION: 349RW

PROJECT LENGTH: 0.0290 MISCOPE OF WORK: Safety TO 704

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 638RSTP (STP Regional): Federal

0 0 0 0 0 0 159RSTP (STP Regional): State Match

-94 0 0 0 0 0 0 797Total

812 11/12/2014

Page 115: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Urban

MPO Area

Tri-CitiesUrban

PROGRAM/SYSTEM

SOUTH CRATER ROAD AREA - SIGNAL

COORDINATION

PROJECT

UPC NO.:

ROUTE:

101039

NFO0301

MPO Project. Locally Administered. Project linked to UPC 90019.REPORT NOTE:

Underway

SCHEDULE

132

ESTIMATED COST (000's)

JURISDICTION:

South Crater RoadSTREET NAME:

PEPetersburg

FY2017 528CN

FROM: FLANK RD TO: RIVES RD (1.4000 MI)DESCRIPTION: RW

PROJECT LENGTH: 1.4000 MISCOPE OF WORK: Safety TO 660

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 400 22 106 0CMAQ: MPO - Federal

0 0 0 100 6 26 0CMAQ: MPO - State Match

0 0 0 500 28 0 132 0Total

MPO Area

Tri-CitiesUrban

PROGRAM/SYSTEM

RTE 301 - EXTEND LTL (BOTH NB & SB) S.

CRATER RD @ MORTON RD

PROJECT

UPC NO.:

ROUTE:

104870

NFO0301

MPO Project.REPORT NOTE:

FY2018

SCHEDULE

100

ESTIMATED COST (000's)

JURISDICTION:

S. CRATER RD.STREET NAME:

PEPetersburg

FY2019 450CNDESCRIPTION: RW

PROJECT LENGTH: _SCOPE OF WORK: Reconstruction w/ Added Capacity TO 550

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 360 80 0 0 0CMAQ: MPO - Federal

0 0 90 20 0 0 0CMAQ: MPO - State Match

0 0 450 100 0 0 0 0Total

MPO Area

Tri-CitiesUrban

PROGRAM/SYSTEM

RTE 301 - EXTEND SB LTL ON S. CRATER RD.

@ MED PARK BLVD.

PROJECT

UPC NO.:

ROUTE:

104878

NFO0301

MPO Project. Revised schedule required.REPORT NOTE:

FY2018

SCHEDULE

50

ESTIMATED COST (000's)

JURISDICTION:

S. CRATER RD.STREET NAME:

PEPetersburg

FY2019 285CNDESCRIPTION: RW

PROJECT LENGTH: _SCOPE OF WORK: Reconstruction w/ Added Capacity TO 335

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 228 40 0 0 0 0CMAQ: MPO - Federal

0 57 10 0 0 0 0CMAQ: MPO - State Match

0 285 50 0 0 0 0 0Total

11/12/2014 813

Page 116: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Urban

MPO Area

RichmondUrban

PROGRAM/SYSTEM

GERMAN SCHOOL ROAD - MAJOR WIDENING

PROJECT

UPC NO.:

ROUTE:

15835

NFO

CN on ARRA UPC 93530REPORT NOTE:

Underway

SCHEDULE

2,090

ESTIMATED COST (000's)

JURISDICTION:

GERMAN SCHOOL RDSTREET NAME:

PERichmond

CN

UnderwayFROM: 0.130 KILOMETER NORTH OF WARWICK ROAD

TO: 0.008 KILOMETER NORTH OF GLENWAY DRIVE

EAST (1.7240 KM)

DESCRIPTION: 3,161RW

PROJECT LENGTH: 1.7240 KMSCOPE OF WORK: Reconstruction w/ Added Capacity TO 5,251

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 76Accounts Receivable: Local

0 0 0 0 0 0 32Bond Match: State Bond Match

0 0 0 0 0 0 128Federal STP: Federal

0 0 0 0 0 0 29Local Project Contributions: Urban - Local

Match

0 0 0 0 0 0 1,040Minimum Guarantee: Federal

0 0 0 0 0 0 50State Formula: Urban - Local Match

0 0 0 0 0 0 2,811Urban Formula: Federal

0 0 0 0 0 0 500Urban Formula: State

0 0 0 0 0 0 550Urban Formula: State Match

34 0 0 0 0 0 0 5,217Total

MPO Area

RichmondUrban

PROGRAM/SYSTEM

WHITEHEAD ROAD - MAJOR WIDENING

PROJECT

UPC NO.:

ROUTE:

15954

NFO

Urban Construction Initiative Project - Matching funds provided in quarterly payment. Partial PE

only. Complete estimate and schedule required

REPORT NOTE:

SCHEDULE ESTIMATED COST (000's)

JURISDICTION:

WHITEHEAD ROADSTREET NAME:

PERichmond

CNFROM: WARWICK ROAD TO: ROUTE 360 AND

ELKHARDT ROAD (2.0000 KM)

DESCRIPTION: RW

PROJECT LENGTH: 2.0000 KMSCOPE OF WORK: Reconstruction w/ Added Capacity TO 0

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 4Local Project Contributions: Local

0 0 0 0 0 0 76(X) Local Project Contributions: State Match

0 0 0 0 0 0 337Urban Formula: Federal

-417 0 0 0 0 0 0 417Total

814 11/12/2014

Page 117: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Urban

MPO Area

RichmondUrban

PROGRAM/SYSTEM

COMMERCE ROAD IMPROVEMENTS

PROJECT

UPC NO.:

ROUTE:

15958

NFO

Urban Construction Initiative Project - Matching funds provided in quarterly payment.REPORT NOTE:

Underway

SCHEDULE

2,092

ESTIMATED COST (000's)

JURISDICTION:

COMMERCE ROADSTREET NAME:

PERichmond

FY2015 11,768CN

FY2014FROM: BELLS ROAD (SOUTH JUNCTION) TO:

BELLEMEADE ROAD (2.0000 MI)

DESCRIPTION: 600RW

PROJECT LENGTH: 2.0000 MISCOPE OF WORK: Reconstruction w/ Added Capacity TO 14,460

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 6,896Local Project Contributions: Local

0 0 0 0 0 0 1,063(X) Local Project Contributions: State Match

0 0 0 760 880 0 0RSTP (STP Regional): MPO - Federal

0 0 0 190 220 0 0RSTP (STP Regional): MPO - State Match

0 0 0 0 0 0 5,636Urban Formula: Federal

-1,184 0 0 950 1,100 0 0 13,595Total

MPO Area

RichmondUrban

PROGRAM/SYSTEM

JAHNKE ROAD - 2 LANE IMPROVEMENTS

PROJECT

UPC NO.:

ROUTE:

19035

NFO

MPO Project. Excess funds to be redistributed by MPO. Locally Administered.REPORT NOTE:

Underway

SCHEDULE

2,000

ESTIMATED COST (000's)

JURISDICTION:

JAHNKE ROADSTREET NAME:

PERichmond

FY2015 9,699CN

UnderwayFROM: BLAKEMORE RD TO: FOREST HILL AVE

(1.6000 MI)

DESCRIPTION: 2,000RW

PROJECT LENGTH: 1.6000 MISCOPE OF WORK: Reconstruction w/o Added Capacity TO 13,699

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 866CMAQ: MPO - Federal

0 0 0 0 0 0 216CMAQ: MPO - State Match

0 0 0 0 0 0 6Local Project Contributions: Urban - Local

Match

0 0 0 0 0 0 170Non-Formula: State

0 0 0 0 0 0 4,401RSTP (STP Regional): Federal

0 0 3,200 0 0 0 2,503RSTP (STP Regional): MPO - Federal

0 0 800 0 0 0 626RSTP (STP Regional): MPO - State Match

0 0 0 0 0 0 930RSTP (STP Regional): State Match

0 0 0 0 0 0 253Urban Formula: Federal

0 0 0 0 0 0 57Urban Formula: State Match

-329 0 4,000 0 0 0 0 10,029Total

11/12/2014 815

Page 118: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Urban

MPO Area

RichmondUrban

PROGRAM/SYSTEM

FOREST HILL AVENUE IMPROVEMENTS

PROJECT

UPC NO.:

ROUTE:

19036

NFO

MPO Project. Locally Administered.REPORT NOTE:

Underway

SCHEDULE

1,997

ESTIMATED COST (000's)

JURISDICTION:

FOREST HILL AVENUESTREET NAME:

PERichmond

FY2015 8,679CN

UnderwayFROM: HATHAWAY RD TO: POWHITE PARKWAY

(0.7400 MI)

DESCRIPTION: 2,025RW

PROJECT LENGTH: 0.7400 MISCOPE OF WORK: Reconstruction w/o Added Capacity TO 12,701

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 400CMAQ: MPO - Federal

0 0 0 0 0 0 100CMAQ: MPO - State Match

0 0 0 0 0 0 8Local Project Contributions: Urban - Local

Match

0 0 0 0 0 0 313Non-Formula: State

0 0 0 0 0 0 7,460RSTP (STP Regional): Federal

0 0 0 0 0 0 2,000RSTP (STP Regional): MPO - Federal

0 0 0 0 0 0 500RSTP (STP Regional): MPO - State Match

0 0 0 0 0 0 1,552RSTP (STP Regional): State Match

0 0 0 0 0 0 300Urban Formula: Federal

0 0 0 0 0 0 68Urban Formula: State Match

0 0 0 0 0 0 0 12,701Total

MPO Area

RichmondUrban

PROGRAM/SYSTEM

CITY OF RICHMOND - MAIN STREET STATION

CAPITAL FUNDS

PROJECT

UPC NO.: 64219

NFOTown/City-wide

MPO project.REPORT NOTE:

FROM: (PAYMENT FOR MAINSTREET STATION -

MONITORING OF FUNDS TO: ONLY)

DESCRIPTION:

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 12,486CMAQ: Federal

640 0 0 0 1,600 0 0CMAQ: MPO - Federal

160 0 0 0 400 0 0CMAQ: MPO - State Match

0 0 0 0 0 0 3,576CMAQ: State Match

0 0 0 0 0 0 13,705Local Project Contributions: Local

0 0 0 0 0 0 7Local Project Contributions: Urban - Local

Match

2,400 0 0 0 0 0 0RSTP (STP Regional): MPO - Federal

0 0 0 0 0 2,400 0(X) RSTP (STP Regional): MPO - Federal

(DRPT)

600 0 0 0 0 0 0RSTP (STP Regional): MPO - State Match

0 0 0 0 0 600 0(X) RSTP (STP Regional): MPO - State

Match (DRPT)

0 0 0 0 0 0 330Urban Formula: State Match

0 0 0 2,000 3,800 3,000 30,104Total

816 11/12/2014

Page 119: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Urban

MPO Area

RichmondUrban

PROGRAM/SYSTEM

CITY OF RICHMOND - TRANSPORTATION

PLAN UPDATE

PROJECT

UPC NO.:

ROUTE:

64222

NFO

MPO project. Locally Administered. Excess funds to be redistributed by MPO.REPORT NOTE:

Underway

SCHEDULE

448

ESTIMATED COST (000's)

JURISDICTION:

STREET NAME:

PERichmond

CNFROM: (PAYMENT FOR TRANSPORTATION PLAN

UPDATE - TO: MONITORING OF FUNDS ONLY)

DESCRIPTION: RW

PROJECT LENGTH: 0.0000 MISCOPE OF WORK: Preliminary Engineering TO 448

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 30Non-Formula: State

0 0 0 0 0 0 400RSTP (STP Regional): Federal

0 0 0 0 0 0 70RSTP (STP Regional): State Match

-52 0 0 0 0 0 0 500Total

MPO Area

RichmondUrban

PROGRAM/SYSTEM

CITY OF RICHMOND - MAIN STREET STATION

OPERATIONS

PROJECT

UPC NO.: 66857

NFOTown/City-wide

DESCRIPTION:

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 1,820CMAQ: Federal

0 0 0 0 0 0 163CMAQ: State Match

0 0 0 0 0 0 292(X) Local Project Contributions: State Match

0 0 0 0 0 0 2,275Total

MPO Area

RichmondUrban

PROGRAM/SYSTEM

CITY OF RICHMOND - TRAFFIC CONTROL &

SAFETY ENHANCEMENTS

PROJECT

UPC NO.:

ROUTE:

70591

NFO

MPO project. Locally Administered.REPORT NOTE:

Complete

SCHEDULE

1,805

ESTIMATED COST (000's)

JURISDICTION:

VARIOUS ROUTESSTREET NAME:

PERichmond

Underway 3,510CN

(MPO PROJECT)DESCRIPTION: RW

PROJECT LENGTH: 0.0000 MISCOPE OF WORK: Safety TO 5,315

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 300CMAQ: Federal

0 0 0 0 0 0 127Local Project Contributions: Local

0 0 0 0 0 0 216Non-Formula: State

0 0 0 0 0 0 3,910RSTP (STP Regional): Federal

0 0 0 0 0 0 761RSTP (STP Regional): State Match

0 0 0 0 0 0 0 5,315Total

11/12/2014 817

Page 120: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Urban

MPO Area

RichmondUrban

PROGRAM/SYSTEM

CITY OF RICHMOND - SIGNAL SYSTEM

ENHANCEMENT

PROJECT

UPC NO.:

ROUTE:

70593

NFO

MPO project. Locally Administered. 100% Fed CMAQ funded project. Excess funds to be

redistributed by MPO.

REPORT NOTE:

Complete

SCHEDULE

1,389

ESTIMATED COST (000's)

JURISDICTION:

VARIOUS ROUTESSTREET NAME:

PERichmond

Underway 1,288CN

FROM: North Side TO: North SideDESCRIPTION: RW

PROJECT LENGTH: 0.0000 MISCOPE OF WORK: Safety TO 2,676

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 3,251CMAQ: Federal

-574 0 0 0 0 0 0 3,251Total

MPO Area

RichmondUrban

PROGRAM/SYSTEM

CITY OF RICHMOND - FORMULA CITY

PAYMENT

PROJECT

UPC NO.: 71786

NFOReport Req'd

To be distributed in quarterly payments - Urban Construction Initiative.REPORT NOTE:

DESCRIPTION:

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0Local Project Contributions: Local

0 0 0 0 0 0SAFETEA-LU Earmarks: State Bond Match

0 0 0 0 0 0SAFETEA-LU Earmarks: State Match

0 0 0 0 0 0Urban Formula: Federal/State

0 0 0 0 0 0Urban Formula: State

0 0 0 0 0 0Urban Formula: State Match

0 0 0 0 0 0Total

MPO Area

RichmondUrban

PROGRAM/SYSTEM

CITY OF RICHMOND - PAINTING &

REHABILITATION

PROJECT

UPC NO.:

ROUTE:

72706

NFO

Urban Construction Initiative Project - Matching funds provided as part of the quarterly paymentREPORT NOTE:

Complete

SCHEDULE

218

ESTIMATED COST (000's)

JURISDICTION:

MANCHESTER BRIDGSTREET NAME:

PERichmond

Underway 8,683CNFROM: MCDONOUGH STREET TO: EAST BYRD

STREET

DESCRIPTION: RW

PROJECT LENGTH: 0.0000 MISCOPE OF WORK: Restoration and Rehabilitation TO 8,900

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 1,602(X) Local Project Contributions: State Match

0 0 0 0 0 0 7,398Urban Formula: Federal

-100 0 0 0 0 0 0 9,000Total

818 11/12/2014

Page 121: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Urban

MPO Area

RichmondUrban

PROGRAM/SYSTEM

RTE 60-CURB EXTENSIONS, ENHANCE

LIGHTING & PAVEMENT MARKINGS

PROJECT

UPC NO.:

ROUTE:

81251

NFO

Locally Administered.REPORT NOTE:

Complete

SCHEDULE

102

ESTIMATED COST (000's)

JURISDICTION:

STREET NAME:

PERichmond

Underway 224CN

Various LocationsDESCRIPTION: RW

PROJECT LENGTH: 0.0000 MISCOPE OF WORK: Safety TO 327

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 446Highway Safety Improvements: Federal

0 0 0 0 0 0 50Highway Safety Improvements: State Match

-168 0 0 0 0 0 0 495Total

MPO Area

RichmondUrban

PROGRAM/SYSTEM

GRACE STREET-UPGRADE EXIST SIGNAL,

ENHANCE PAVEMENT MARKINGS

PROJECT

UPC NO.:

ROUTE:

81252

NFO

Locally Administered.REPORT NOTE:

Complete

SCHEDULE

77

ESTIMATED COST (000's)

JURISDICTION:

W. GRACE STREETSTREET NAME:

PERichmond

Underway 451CNFROM: 250 FEET EAST OF N. BELVIDERE STREET TO:

250 FEET WEST OF N. LOMBARDY STREET

DESCRIPTION: RW

PROJECT LENGTH: 0.0000 MISCOPE OF WORK: Safety TO 528

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 466Highway Safety Improvements: Federal

0 0 0 0 0 0 52Highway Safety Improvements: State Match

0 0 0 0 0 0 11Local Project Contributions: Local

0 0 0 0 0 0 0 528Total

MPO Area

RichmondUrban

PROGRAM/SYSTEM

FRANKLIN STREET-UPGRADE EXIST SIGNAL,

ENHANCE PVMT MARKINGS

PROJECT

UPC NO.:

ROUTE:

81253

NFO

Locally Administered.REPORT NOTE:

Complete

SCHEDULE

33

ESTIMATED COST (000's)

JURISDICTION:

East FRANKLIN STREETSTREET NAME:

PERichmond

Underway 240CNFROM: 250 FEET WEST OF N. 4TH STREET TO: 250

FEET EAST OF N. 6TH STREET

DESCRIPTION: RW

PROJECT LENGTH: 0.0000 MISCOPE OF WORK: Safety TO 273

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 253Highway Safety Improvements: Federal

0 0 0 0 0 0 28Highway Safety Improvements: State Match

-8 0 0 0 0 0 0 281Total

11/12/2014 819

Page 122: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Urban

MPO Area

RichmondUrban

PROGRAM/SYSTEM

CONDUCT PLANNING & ENGINEERING FOR

MAYO BRIDGE

PROJECT

UPC NO.:

ROUTE:

82110

FO

Urban Construction Initiative Project - Match funds provided in quarterly payment & includes

SAFETEA-LU match funds.

REPORT NOTE:

Underway

SCHEDULE

1,705

ESTIMATED COST (000's)

JURISDICTION:

Mayo BridgeSTREET NAME:

PERichmond

CN

MAYO BRIDGE OVER JAMES RIVERDESCRIPTION: RW

PROJECT LENGTH: 0.0000 MISCOPE OF WORK: Preliminary Engineering TO 1,705

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 358(X) Local Project Contributions: State Match

0 0 0 0 0 0 1,433SAFETEA-LU Earmarks: Federal

-86 0 0 0 0 0 0 1,791Total

MPO Area

RichmondUrban

PROGRAM/SYSTEM

ARRA RICHMOND GERMAN SCHOOL ROAD

WIDENING/C&G/WALKS/DRAINAGE

PROJECT

UPC NO.: 93530

NFOARRA09

PE and RW on UPC 15835. ARRA Parent - UPC 93530; ARRA Child - UPC 95226.REPORT NOTE:

FROM: 0.130 KILOMETER N OF WARWICK RD TO:

0.008 KILOMETER N OF GLENWAY DR EAST (1.7240

KM)

DESCRIPTION:

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 3,337American Recovery and Reinvestment Act:

Flexible

0 0 0 0 0 0 190Local Project Contributions: Local

0 0 0 0 0 0 146Local Project Contributions: Urban - Local

Match

0 0 0 0 0 0 1,991Minimum Guarantee: Federal

0 0 0 0 0 0 123Non-Formula: State

0 0 0 0 0 0 493RSTP (STP Regional): Federal

0 0 0 0 0 0 285Soft Match: Federal

0 0 0 0 0 0 4,733Urban Formula: Federal

0 0 0 0 0 0 1,122Urban Formula: State

0 0 0 0 0 0 1,287Urban Formula: State Match

0 0 0 0 0 0 13,706Total

820 11/12/2014

Page 123: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Urban

MPO Area

RichmondUrban

PROGRAM/SYSTEM

CITY OF RICHMOND BIKE SHARED LANE

PAVEMENT MARKINGS-E/W RTE

PROJECT

UPC NO.:

ROUTE:

100490

NFO

MPO Project. Excess funds to be redistributed by MPO. Locally Administered.REPORT NOTE:

Complete

SCHEDULE

31

ESTIMATED COST (000's)

JURISDICTION:

VariousSTREET NAME:

PERichmond

Underway 5CNFROM: Westhampton Way TO: Williamsburg Road

(11.0000 MI)

DESCRIPTION: RW

PROJECT LENGTH: 11.0000 MISCOPE OF WORK: Safety TO 36

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 189CMAQ: Federal

0 0 0 0 0 0 47CMAQ: State Match

-200 0 0 0 0 0 0 237Total

MPO Area

RichmondUrban

PROGRAM/SYSTEM

CITY OF RICHMOND BIKE SHARED LANE

PVMT MARKINGS-BICYCLE RT 1

PROJECT

UPC NO.:

ROUTE:

100491

NFO

MPO Project. Excess funds to be redistributed by MPO. Locally Administered.REPORT NOTE:

Complete

SCHEDULE

37

ESTIMATED COST (000's)

JURISDICTION:

STREET NAME:

PERichmond

Underway 97CNFROM: NCL RICHMOND - Hermitage road TO: SCL

RICHMOND - Cherokee road (15.0000 MI)

DESCRIPTION: RW

PROJECT LENGTH: 15.0000 MISCOPE OF WORK: Safety TO 135

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 120CMAQ: Federal

0 0 0 0 0 0 30CMAQ: State Match

-15 0 0 0 0 0 0 150Total

MPO Area

RichmondUrban

PROGRAM/SYSTEM

CITY SIGNAL SYSTEMS SOUTH OF JAMES

RIVER

PROJECT

UPC NO.:

ROUTE:

100498

NFO

MPO Project. Excess funds to be redistributed by MPO. Locally Administered.REPORT NOTE:

Underway

SCHEDULE

1,500

ESTIMATED COST (000's)

JURISDICTION:

Chippenham parkway and othersSTREET NAME:

PERichmond

FY2015 8,500CN

FROM: James River TO: City's South limit (0.8000 MI)DESCRIPTION: RW

PROJECT LENGTH: 0.8000 MISCOPE OF WORK: Safety TO 10,000

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 934CMAQ: Federal

2,000 0 0 0 1,200 1,603 2,000CMAQ: MPO - Federal

500 0 0 0 300 401 500CMAQ: MPO - State Match

0 0 0 0 0 0 566CMAQ: State Match

-4 0 0 0 1,500 2,500 2,003 4,001Total

11/12/2014 821

Page 124: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Urban

MPO Area

RichmondUrban

PROGRAM/SYSTEM

SHOCKOE STREET REVERSAL

PROJECT

UPC NO.:

ROUTE:

101854

NFO

MPO project. Excess funds to be redistributed by MPO. Locally Administered.REPORT NOTE:

Underway

SCHEDULE

50

ESTIMATED COST (000's)

JURISDICTION:

VARIOUSSTREET NAME:

PERichmond

FY2014 568CN

FROM: 19TH ST TO: 17TH ST (0.5000 MI)DESCRIPTION: RW

PROJECT LENGTH: 0.5000 MISCOPE OF WORK: Safety TO 618

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 25Non-Formula: State

0 0 0 0 0 0 501RSTP (STP Regional): Federal

0 0 0 0 0 0 100RSTP (STP Regional): State Match

-9 0 0 0 0 0 0 626Total

MPO Area

RichmondUrban

PROGRAM/SYSTEM

BELVIDERE ST - REPLACE DECK

PROJECT

UPC NO.:

ROUTE:

102961

NFO

Underway

SCHEDULE

3

ESTIMATED COST (000's)

JURISDICTION:

BELVIDERE STREETSTREET NAME:

PERichmond

FY2015 2,197CN

BRIDGE OVER CSXDESCRIPTION: RW

PROJECT LENGTH: _SCOPE OF WORK: Bridge Replacement w/o Added Capacity TO 2,200

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 1,100Revenue Sharing Funds: Local Match

0 0 0 0 0 0 1,100Revenue Sharing Funds: State Match

0 0 0 0 0 0 0 2,200Total

MPO Area

RichmondUrban

PROGRAM/SYSTEM

7TH ST - REPLACE BRIDGE

PROJECT

UPC NO.:

ROUTE:

102962

NFO

Underway

SCHEDULE

150

ESTIMATED COST (000's)

JURISDICTION:

7TH STREETSTREET NAME:

PERichmond

FY2015 1,200CN

AT LEIGH STDESCRIPTION: RW

PROJECT LENGTH: _SCOPE OF WORK: Bridge Replacement w/o Added Capacity TO 1,350

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 675Revenue Sharing Funds: Local Match

0 0 0 0 0 0 675Revenue Sharing Funds: State Match

0 0 0 0 0 0 0 1,350Total

822 11/12/2014

Page 125: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Urban

MPO Area

RichmondUrban

PROGRAM/SYSTEM

MULTIMODAL IMPROVEMENT TO FRANKLIN

ST

PROJECT

UPC NO.:

ROUTE:

103899

NFO

MPO Project. Locally administered. Administered by DRPT.REPORT NOTE:

FY2013

SCHEDULE

225

ESTIMATED COST (000's)

JURISDICTION:

FRANKLIN STREETSTREET NAME:

PERichmond

FY2013 2,275CN

FROM: 14TH STREET TO: 18TH STREETDESCRIPTION: RW

PROJECT LENGTH: _SCOPE OF WORK: Reconstruction w/o Added Capacity TO 2,500

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 2,000RSTP (STP Regional): Federal

0 0 0 0 0 0 500RSTP (STP Regional): State Match

0 0 0 0 0 0 0 2,500Total

MPO Area

RichmondUrban

PROGRAM/SYSTEM

SIGNAL SYSTEM - EAST, NORTH AND WEST

OF CITY

PROJECT

UPC NO.:

ROUTE:

105890

NFO

MPO Project. Locally administered. Balance to be provided by MPO.REPORT NOTE:

FY2017

SCHEDULE

1,000

ESTIMATED COST (000's)

JURISDICTION:

VARIOUSSTREET NAME:

PERichmond

FY2018 5,312CN

VARIOUSDESCRIPTION: RW

PROJECT LENGTH: _SCOPE OF WORK: Safety TO 6,312

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 1,770 1,200 1,200 400 0 0CMAQ: MPO - Federal

0 442 300 300 100 0 0CMAQ: MPO - State Match

600 2,212 1,500 1,500 500 0 0 0Total

MPO Area

RichmondUrban

PROGRAM/SYSTEM

GRACE ST - TRAFFIC SIGNAL

MODERNIZATION PROJECT

PROJECT

UPC NO.:

ROUTE:

86556

NFO0000

Locally Administered.REPORT NOTE:

Complete

SCHEDULE

31

ESTIMATED COST (000's)

JURISDICTION:

Grace StreetSTREET NAME:

PERichmond

Underway 207CN

FROM: 200ft W of 1st St TO: 200ft E of 2nd StDESCRIPTION: RW

PROJECT LENGTH: 0.0000 MISCOPE OF WORK: Safety TO 238

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 304Highway Safety Improvements: Federal

0 0 0 0 0 0 34Highway Safety Improvements: State Match

-100 0 0 0 0 0 0 338Total

11/12/2014 823

Page 126: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Urban

MPO Area

RichmondUrban

PROGRAM/SYSTEM

HSIP PROACTIVE SAFETY PROJECTS CITY OF

RICHMOND

PROJECT

UPC NO.: 86733

NFODistrict-wide

City of Richmond Safety ImprovementsDESCRIPTION:

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 55Accounts Receivable: Local

0 0 0 0 0 0 1,332Highway Safety Improvements: Federal

0 0 0 0 0 0 155Highway Safety Improvements: State Match

0 0 0 0 0 0 43Local Project Contributions: Local

0 0 0 0 0 0 1,585Total

MPO Area

RichmondUrban

PROGRAM/SYSTEM

DOWNTOWN (VCU MAIN CAMPUS) - PED

COUNTDOWN INDICATORS

PROJECT

UPC NO.:

ROUTE:

96731

NFO0000

Locally Administered.REPORT NOTE:

Complete

SCHEDULE

54

ESTIMATED COST (000's)

JURISDICTION:

Various StreetsSTREET NAME:

PERichmond

Underway 321CN

VARIOUS LOCATIONS ON VCU MAIN CAMPUSDESCRIPTION: RW

PROJECT LENGTH: _SCOPE OF WORK: Safety TO 375

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 338Highway Safety Improvements: Federal

0 0 0 0 0 0 38Highway Safety Improvements: State Match

0 0 0 0 0 0 0 375Total

MPO Area

RichmondUrban

PROGRAM/SYSTEM

CITY OF RICHMOND - UPGRADE SIGNALS

PROJECT

UPC NO.:

ROUTE:

100564

NFO0000

Locally administered.REPORT NOTE:

Complete

SCHEDULE

134

ESTIMATED COST (000's)

JURISDICTION:

6 LOCATIONSSTREET NAME:

PERichmond

Underway 1,020CN

6 LOCATIONSDESCRIPTION: RW

PROJECT LENGTH: _SCOPE OF WORK: Safety TO 1,154

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 1,047Highway Safety Improvements: Federal

0 0 0 0 0 0 116Highway Safety Improvements: State Match

-10 0 0 0 0 0 0 1,164Total

824 11/12/2014

Page 127: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Urban

MPO Area

RichmondUrban

PROGRAM/SYSTEM

CITYWIDE - INSTALL SIDEWALK

PROJECT

UPC NO.:

ROUTE:

104215

NFO0000

Revised schedule required.REPORT NOTE:

FY2014

SCHEDULE

50

ESTIMATED COST (000's)

JURISDICTION:

CITYWIDESTREET NAME:

PERichmond

FY2015 1,250CN

FROM: VARIOUS TO: VARIOUSDESCRIPTION: RW

PROJECT LENGTH: _SCOPE OF WORK: Safety TO 1,300

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 650Revenue Sharing Funds: Local Match

0 0 0 0 0 0 650Revenue Sharing Funds: State Match

0 0 0 0 0 0 0 1,300Total

MPO Area

RichmondUrban

PROGRAM/SYSTEM

LOMBARDY ST - BRIDGE IMPROVEMENTS

PROJECT

UPC NO.:

ROUTE:

104216

NFO0000

Revised schedule required.REPORT NOTE:

FY2014

SCHEDULE

150

ESTIMATED COST (000's)

JURISDICTION:

LOMBARDYSTREET NAME:

PERichmond

FY2015 1,350CN

LOMBARDY OVER CSX RAILROADDESCRIPTION: RW

PROJECT LENGTH: _SCOPE OF WORK: Bridge Rehab w/o Added Capacity TO 1,500

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 750 0Revenue Sharing Funds: Local Match

0 0 0 0 0 750 0Revenue Sharing Funds: State Match

0 0 0 0 0 0 1,500 0Total

MPO Area

RichmondUrban

PROGRAM/SYSTEM

LYNNHAVEN ST - BRIDGE IMPROVEMENTS

PROJECT

UPC NO.:

ROUTE:

104217

NFO0000

Revised schedule required.REPORT NOTE:

Underway

SCHEDULE

50

ESTIMATED COST (000's)

JURISDICTION:

STREET NAME:

PERichmond

FY2014 550CN

LYNHAVEN OVER BROAD ROCK CREEKDESCRIPTION: RW

PROJECT LENGTH: _SCOPE OF WORK: Bridge Rehab w/o Added Capacity TO 600

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 300Revenue Sharing Funds: Local Match

0 0 0 0 0 0 300Revenue Sharing Funds: State Match

0 0 0 0 0 0 0 600Total

11/12/2014 825

Page 128: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Urban

MPO Area

RichmondUrban

PROGRAM/SYSTEM

INSTALL SIDEWALK & CROSSWALK -

CITYWIDE

PROJECT

UPC NO.:

ROUTE:

104218

NFO0000

Revised schedule required.REPORT NOTE:

Underway

SCHEDULE

200

ESTIMATED COST (000's)

JURISDICTION:

CITYWIDESTREET NAME:

PERichmond

FY2014 1,740CN

FROM: VARIOUS TO: VARIOUSDESCRIPTION: RW

PROJECT LENGTH: _SCOPE OF WORK: Safety TO 1,940

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 970Revenue Sharing Funds: Local Match

0 0 0 0 0 0 970Revenue Sharing Funds: State Match

0 0 0 0 0 0 0 1,940Total

MPO Area

RichmondUrban

PROGRAM/SYSTEM

CITYWIDE - TRAFFIC CALMING

PROJECT

UPC NO.:

ROUTE:

104279

NFO0000

Underway

SCHEDULE

75

ESTIMATED COST (000's)

JURISDICTION:

VARIOUSSTREET NAME:

PERichmond

FY2015 325CN

VARIOUS LOCATIONSDESCRIPTION: RW

PROJECT LENGTH: _SCOPE OF WORK: Traffic Management/Engineering TO 400

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 200Revenue Sharing Funds: Local Match

0 0 0 0 0 0 200Revenue Sharing Funds: State Match

0 0 0 0 0 0 0 400Total

MPO Area

RichmondUrban

PROGRAM/SYSTEM

CITYWIDE - INSTALL TRAFFIC CONTROL

PROJECT

UPC NO.:

ROUTE:

104280

NFO0000

Revised schedule required.REPORT NOTE:

Underway

SCHEDULE

75

ESTIMATED COST (000's)

JURISDICTION:

VARIOUSSTREET NAME:

PERichmond

FY2014 325CN

VARIOUS LOCATIONSDESCRIPTION: RW

PROJECT LENGTH: _SCOPE OF WORK: Traffic Management/Engineering TO 400

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 200Revenue Sharing Funds: Local Match

0 0 0 0 0 0 200Revenue Sharing Funds: State Match

0 0 0 0 0 0 0 400Total

826 11/12/2014

Page 129: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Urban

MPO Area

RichmondUrban

PROGRAM/SYSTEM

DEEPWATER TERMINAL RD - EXTEND

EXISTING ROADWAY

PROJECT

UPC NO.:

ROUTE:

104281

NFO0000

Underway

SCHEDULE

250

ESTIMATED COST (000's)

JURISDICTION:

DEEPWATER TERMINAL ROADSTREET NAME:

PERichmond

FY2016 1,600CN

FY2015FROM: END EXISTING DEEPWATER TERMINAL RD TO:

GOODES ST (0.6900 MI)

DESCRIPTION: 150RW

PROJECT LENGTH: 0.6900 MISCOPE OF WORK: New Construction Roadway TO 2,000

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 1,450Local Project Contributions: Local

0 0 0 0 0 0 250Revenue Sharing Funds: Local Match

0 0 0 0 0 0 250Revenue Sharing Funds: State Match

50 0 0 0 0 0 0 1,950Total

MPO Area

RichmondUrban

PROGRAM/SYSTEM

SOUTH KINSLEY - IMPROVE DRAINAGE

PROJECT

UPC NO.:

ROUTE:

104282

NFO0000

Revised schedule required.REPORT NOTE:

FY2014

SCHEDULE

5

ESTIMATED COST (000's)

JURISDICTION:

KINSLEYSTREET NAME:

PERichmond

FY2015 1,195CN

VARIOUS LOCATIONSDESCRIPTION: RW

PROJECT LENGTH: _SCOPE OF WORK: Reconstruction w/o Added Capacity TO 1,200

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 600Revenue Sharing Funds: Local Match

0 0 0 0 0 0 600Revenue Sharing Funds: State Match

0 0 0 0 0 0 0 1,200Total

MPO Area

RichmondUrban

PROGRAM/SYSTEM

WILLOW OAKS - IMPROVE DRAINAGE

PROJECT

UPC NO.:

ROUTE:

104283

NFO0000

Underway

SCHEDULE

5

ESTIMATED COST (000's)

JURISDICTION:

STREET NAME:

PERichmond

FY2015 253CN

VARIOUS LOCATIONSDESCRIPTION: RW

PROJECT LENGTH: _SCOPE OF WORK: Reconstruction w/o Added Capacity TO 258

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 130Revenue Sharing Funds: Local Match

0 0 0 0 0 0 130Revenue Sharing Funds: State Match

-2 0 0 0 0 0 0 260Total

11/12/2014 827

Page 130: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Urban

MPO Area

RichmondUrban

PROGRAM/SYSTEM

FRANKLIN ST - STREETSCAPE

PROJECT

UPC NO.:

ROUTE:

104284

NFO0000

Underway

SCHEDULE

5

ESTIMATED COST (000's)

JURISDICTION:

FRANKLIN STREETSTREET NAME:

PERichmond

FY2015 2,493CN

FROM: 14TH ST TO: 18TH ST (0.3000 MI)DESCRIPTION: RW

PROJECT LENGTH: 0.3000 MISCOPE OF WORK: Safety TO 2,498

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 1,250Revenue Sharing Funds: Local Match

0 0 0 0 0 0 1,250Revenue Sharing Funds: State Match

-2 0 0 0 0 0 0 2,500Total

MPO Area

RichmondUrban

PROGRAM/SYSTEM

CITYWIDE - OVERLAY PAVEMENT

PROJECT

UPC NO.:

ROUTE:

104507

NFO0000

Underway

SCHEDULE

50

ESTIMATED COST (000's)

JURISDICTION:

VARIOUSSTREET NAME:

PERichmond

FY2015 9,950CN

VARIOUS LOCATIONSDESCRIPTION: RW

PROJECT LENGTH: _SCOPE OF WORK: Resurfacing TO 10,000

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 6,905Local Project Contributions: Local

0 0 0 0 0 0 1,548Revenue Sharing Funds: Local Match

0 0 0 0 0 0 1,548Revenue Sharing Funds: State Match

0 0 0 0 0 0 0 10,000Total

MPO Area

RichmondUrban

PROGRAM/SYSTEM

DEEPWATER TERMINAL RD - EXTEND

EXISTING ROADWAY

PROJECT

UPC NO.:

ROUTE:

104882

NFO0000

MPO Project. Complete estimate & schedule required. Locally AdministeredREPORT NOTE:

SCHEDULE ESTIMATED COST (000's)

JURISDICTION:

DEEPWATER TERMINAL ROADSTREET NAME:

PERichmond

CNFROM: END EXISTING DEEPWATER TERMINAL RD

TO: GOODES ST (0.6900 MI)

DESCRIPTION: RW

PROJECT LENGTH: 0.6900 MISCOPE OF WORK: New Construction Roadway TO 0

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 1,400 0 0 0 0 0RSTP (STP Regional): MPO - Federal

0 350 0 0 0 0 0RSTP (STP Regional): MPO - State Match

-1,750 1,750 0 0 0 0 0 0Total

828 11/12/2014

Page 131: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Urban

MPO Area

RichmondUrban

PROGRAM/SYSTEM

RTE 360 - REHAB MAYO BRIDGE

PROJECT

UPC NO.:

ROUTE:

104888

NFO0000

MPO Project. Revised schedule required. Locally AdministeredREPORT NOTE:

FY2019

SCHEDULE

500

ESTIMATED COST (000's)

JURISDICTION:

MAYO BRIDGESTREET NAME:

PERichmond

FY2020 2,000CN

EAST 14TH STREET @ JAMES RIVER (0.2600 MI)DESCRIPTION: RW

PROJECT LENGTH: 0.2600 MISCOPE OF WORK: Bridge Rehab w/o Added Capacity TO 2,500

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 1,600 0 0 0 0 0RSTP (STP Regional): MPO - Federal

0 400 0 0 0 0 0RSTP (STP Regional): MPO - State Match

500 2,000 0 0 0 0 0 0Total

MPO Area

RichmondUrban

PROGRAM/SYSTEM

HUGUENOT ROAD CORRIDOR

IMPROVEMENTS

PROJECT

UPC NO.:

ROUTE:

104959

NFO0000

MPO Project. Balance to be provided for by MPO.REPORT NOTE:

Underway

SCHEDULE

118

ESTIMATED COST (000's)

JURISDICTION:

HUGUENOT ROADSTREET NAME:

PERichmond

FY2017 666CN

FY2015FROM: 0.15 MILE WEST OF RIVER ROAD TO: 0.70

MILE EAST ON RIVER ROAD (0.2200 MI)

DESCRIPTION: 110RW

PROJECT LENGTH: 0.2200 MISCOPE OF WORK: Safety TO 894

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

320 0 0 0 0 320 56CMAQ: MPO - Federal

80 0 0 0 0 80 14CMAQ: MPO - State Match

24 0 0 0 0 400 400 70Total

MPO Area

RichmondUrban

PROGRAM/SYSTEM

CITY OF RICHMOND - SRTS - FOX

ES/MUNFORD ES - BIKE/PED IMP

PROJECT

UPC NO.:

ROUTE:

105235

NFO0000

Locally Administered.REPORT NOTE:

Underway

SCHEDULE

21

ESTIMATED COST (000's)

JURISDICTION:

VARIOUSSTREET NAME:

PERichmond

FY2017 139CN

FROM: N WILETTA DR TO: S WILETTA DR (0.1000 MI)DESCRIPTION: RW

PROJECT LENGTH: 0.1000 MISCOPE OF WORK: Safety TO 160

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 160Safe Routes to School: Federal 0

11/12/2014 829

Page 132: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Urban

MPO Area

RichmondUrban

PROGRAM/SYSTEM

RTE 1 - MAJOR WIDENING

PROJECT

UPC NO.:

ROUTE:

15955

NFO0001

PE and RW only, accruing funds for CN.REPORT NOTE:

Underway

SCHEDULE

2,540

ESTIMATED COST (000's)

JURISDICTION:

JEFF DAVIS HWYSTREET NAME:

PERichmond

FY2020 22,950CN

UnderwayFROM: 0.010 KM SOUTH OF CHESTERMAN AVENUE

TO: 0.016 KM NORTH OF DECATUR STREET (1.7250

KM)

DESCRIPTION: 4,039RW

PROJECT LENGTH: 1.7250 KMSCOPE OF WORK: Reconstruction w/ Added Capacity TO 29,529

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 1,138CMAQ: Federal

0 0 0 0 0 0 284CMAQ: State Match

0 0 0 0 0 0 118Local Project Contributions: Urban - Local

Match

0 0 0 0 0 0 4Residue Parcel Revenue: State

0 0 0 0 0 0 49State Formula: Urban - Local Match

0 0 0 0 0 0 4,202Urban Formula: Federal

0 0 0 0 0 0 979Urban Formula: State

0 0 0 0 0 0 1,117Urban Formula: State Match

21,637 0 0 0 0 0 0 7,892Total

MPO Area

RichmondUrban

PROGRAM/SYSTEM

5TH ST - REPLACE BRIDGE

PROJECT

UPC NO.:

ROUTE:

102963

NFO0005

Underway

SCHEDULE

150

ESTIMATED COST (000's)

JURISDICTION:

5TH STREETSTREET NAME:

PERichmond

FY2015 1,200CN

@ LEIGH STDESCRIPTION: RW

PROJECT LENGTH: _SCOPE OF WORK: Bridge Replacement w/o Added Capacity TO 1,350

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 675Revenue Sharing Funds: Local Match

0 0 0 0 0 0 675Revenue Sharing Funds: State Match

0 0 0 0 0 0 0 1,350Total

MPO Area

RichmondUrban

PROGRAM/SYSTEM

CONSTRUCT ROUNDABOUT AT NINE MILE RD,

25TH ST. AND FARIMOUNT

PROJECT

UPC NO.:

ROUTE:

93350

NFO0033

Locally Administered. Revised schedule required.REPORT NOTE:

Underway

SCHEDULE

152

ESTIMATED COST (000's)

JURISDICTION:

Nine Mile RoadSTREET NAME:

PERichmond

FY2014 1,003CN

UnderwayFROM: 250' West of 25th and S Street TO: 250' East of

25th and S Street

DESCRIPTION: 67RW

PROJECT LENGTH: _SCOPE OF WORK: Safety TO 1,222

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 1,100Highway Safety Improvements: Federal

0 0 0 0 0 0 122Highway Safety Improvements: State Match

0 0 0 0 0 0 0 1,222Total

830 11/12/2014

Page 133: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Urban

MPO Area

RichmondUrban

PROGRAM/SYSTEM

RTE 60 - RECONSTRUCTION

PROJECT

UPC NO.:

ROUTE:

15834

NFO0060

Complete

SCHEDULE

4,230

ESTIMATED COST (000's)

JURISDICTION:

MIDLOTHIAN TURNPIKESTREET NAME:

PERichmond

Underway 37,633CN

UnderwayFROM: 0.058 KILOMETER EAST OF WEST RICHMOND

CITY LIMITS TO: 2.850 KILOMETERS EAST OF WEST

RICHMOND CITY LIMITS (2.7900 KM)

DESCRIPTION: 7,051RW

PROJECT LENGTH: 2.7900 KMSCOPE OF WORK: Reconstruction w/ Added Capacity TO 48,915

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 481Accounts Receivable: Local

0 0 0 0 0 0 173Bond Match: State Bond Match

0 0 0 0 0 0 2,548Concession Funds: State

0 0 0 0 0 0 1,535Highway Safety Improvements: Federal

0 0 0 0 0 0 171Highway Safety Improvements: State Match

0 0 0 0 0 0 815Local Project Contributions: Local

0 0 0 0 0 0 405Local Project Contributions: Urban - Local

Match

0 0 0 0 0 0 6,094Minimum Guarantee: Federal

0 0 0 0 0 0 572NHPP: Statewide - Federal

0 0 0 0 0 0 143NHPP: Statewide - Soft Match

0 0 0 0 0 0 24Residue Parcel Revenue: State

0 0 0 0 0 0 1,351Soft Match: Federal

0 0 0 0 0 0 148State Formula: Urban - Local Match

0 0 0 0 0 0 24,113Urban Formula: Federal

0 0 0 0 0 0 3,475Urban Formula: Federal/State

0 0 0 0 0 0 810Urban Formula: State

0 0 0 0 0 0 5,085Urban Formula: State Match

974 0 0 0 0 0 0 47,941Total

MPO Area

RichmondUrban

PROGRAM/SYSTEM

RTE 60 - INTERCHANGE STUDY

PROJECT

UPC NO.:

ROUTE:

19001

NFO0060

MPO project. Locally AdministeredREPORT NOTE:

Underway

SCHEDULE

300

ESTIMATED COST (000's)

JURISDICTION:

MIDLOTHIAN TURNPSTREET NAME:

PERichmond

CN

AT BELT BOULEVARDDESCRIPTION: RW

PROJECT LENGTH: 0.0000 KMSCOPE OF WORK: Preliminary Engineering TO 300

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 240RSTP (STP Regional): Federal

0 0 0 0 0 0 60RSTP (STP Regional): State Match

0 0 0 0 0 0 0 300Total

11/12/2014 831

Page 134: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Urban

MPO Area

RichmondUrban

PROGRAM/SYSTEM

RTE 60 - BRIDGE REHABILITATION

PROJECT

UPC NO.:

ROUTE:

104887

NFO0060

MPO Project. Locally Administered. Revised schedule required.REPORT NOTE:

FY2014

SCHEDULE

300

ESTIMATED COST (000's)

JURISDICTION:

MIDLOTHIAN TURNPIKESTREET NAME:

PERichmond

FY2015 1,728CN

AT RTE 161 (BELT BLVD) (0.1900 MI)DESCRIPTION: RW

PROJECT LENGTH: 0.1900 MISCOPE OF WORK: Bridge Rehab w/o Added Capacity TO 2,028

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 80 1,542RSTP (STP Regional): MPO - Federal

0 0 0 0 0 20 386RSTP (STP Regional): MPO - State Match

0 0 0 0 0 0 100 1,928Total

MPO Area

RichmondUrban

PROGRAM/SYSTEM

RTE 147 - INSTALL PED X-WALKS, ADA

RAMPS AND PAVE MARKINGS

PROJECT

UPC NO.:

ROUTE:

100562

NFO0147

Locally administered.REPORT NOTE:

Complete

SCHEDULE

10

ESTIMATED COST (000's)

JURISDICTION:

Cary StreetSTREET NAME:

PERichmond

Underway 492CN

FROM: Nansemond Street TO: Colonial AvenueDESCRIPTION: RW

PROJECT LENGTH: _SCOPE OF WORK: Safety TO 502

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 585Highway Safety Improvements: Federal

0 0 0 0 0 0 65Highway Safety Improvements: State Match

-148 0 0 0 0 0 0 650Total

MPO Area

RichmondUrban

PROGRAM/SYSTEM

RTE 197 - UPGRADE SIGNAL DESIGN AND ADD

LEFT TURN LANE

PROJECT

UPC NO.:

ROUTE:

89940

NFO0197

Locally Administered.REPORT NOTE:

Complete

SCHEDULE

100

ESTIMATED COST (000's)

JURISDICTION:

Laburnum AveSTREET NAME:

PERichmond

Underway 513CN

FROM: 300' W of Brook Road TO: 300' S of Brook RoadDESCRIPTION: RW

PROJECT LENGTH: _SCOPE OF WORK: Safety TO 613

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 552Highway Safety Improvements: Federal

0 0 0 0 0 0 61Highway Safety Improvements: State Match

0 0 0 0 0 0 0 613Total

832 11/12/2014

Page 135: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Urban

MPO Area

RichmondUrban

PROGRAM/SYSTEM

RTE 360 - MAJOR WIDENING

PROJECT

UPC NO.:

ROUTE:

15959

NFO0360

Urban Construction Initiative Project - Matching funds provided in quarterly payment. PE only,

accruing funds for RW & CN. Complete schedule and estimate required from City.

REPORT NOTE:

Underway

SCHEDULE

1,221

ESTIMATED COST (000's)

JURISDICTION:

HULL STREETSTREET NAME:

PERichmond

CNFROM: ELKHARDT ROAD TO: DIXON STREET (2.2400

MI)

DESCRIPTION: RW

PROJECT LENGTH: 2.2400 MISCOPE OF WORK: Reconstruction w/ Added Capacity TO 1,221

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 76Local Project Contributions: Local

0 0 0 0 0 0 683(X) Local Project Contributions: State Match

0 0 0 0 0 0 24State Formula: Urban - Local Match

0 0 0 0 0 0 3,035Urban Formula: Federal

0 0 0 0 0 0 1,197Urban Formula: State

-3,794 0 0 0 0 0 0 5,015Total

MPO Area

RichmondUrban

PROGRAM/SYSTEM

RTE 360 - IMPROVE INTERSECTION

PROJECT

UPC NO.:

ROUTE:

93395

NFO0360

Locally AdministeredREPORT NOTE:

Complete

SCHEDULE

143

ESTIMATED COST (000's)

JURISDICTION:

HULL STREET ROADSTREET NAME:

PERichmond

Underway 1,720CN

UnderwayFROM: 1288' W of Elkhardt Rd/Hull St. Rd Intersection

TO: 348' E of Orcutt Ln/Hull St. Rd Intersection (0.2100

MI)

DESCRIPTION: 137RW

PROJECT LENGTH: 0.2100 MISCOPE OF WORK: Safety TO 2,000

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 1,807Highway Safety Improvements: Federal

0 0 0 0 0 0 193Highway Safety Improvements: State Match

0 0 0 0 0 0 0 2,000Total

MPO Area

RichmondUrban

PROGRAM/SYSTEM

MAIN STREET STATION

PROJECT

UPC NO.:

ROUTE:

57008

NFO9999

Revised estimate requiredREPORT NOTE:

SCHEDULE ESTIMATED COST (000's)

JURISDICTION:

MAIN STREET STATIONSTREET NAME:

PERichmond

Underway 4,885CNFROM: MAIN STREET STATION TO: MAIN STREET

STATION

DESCRIPTION: RW

PROJECT LENGTH: _SCOPE OF WORK: Other TO 4,885

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 4,395State Formula: Urban - State 490

11/12/2014 833

Page 136: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Urban

MPO Area

RichmondUrban

PROGRAM/SYSTEM

SIGNALS & TRAFFIC SERVICES

PROJECT

UPC NO.:

ROUTE:

105652

NFO9999

N/A

SCHEDULE

0

ESTIMATED COST (000's)

JURISDICTION:

FULTON COMMERCIAL CORRIDOR IMPROVEMENTSSTREET NAME:

PERichmond

FY2016 200CNFROM: GOVERNMENT ROAD & NATIONAL STREET TO:

CREEDMORE STREET & CARLISLE AVENUE (0.1400

MI)

DESCRIPTION: RW

PROJECT LENGTH: 0.1400 MISCOPE OF WORK: Safety TO 200

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 100 0Revenue Sharing Funds: Local Match

0 0 0 0 0 100 0Revenue Sharing Funds: State Match

0 0 0 0 0 0 200 0Total

MPO Area

RichmondUrban

PROGRAM/SYSTEM

INTERSECTION IMPROVEMENT

PROJECT

UPC NO.:

ROUTE:

105653

NFO9999

FY2015

SCHEDULE

80

ESTIMATED COST (000's)

JURISDICTION:

MONUMENT AVE & ALLEN AVESTREET NAME:

PERichmond

FY2015 520CN

FROM: MONUMENT AVE & ALLEN AVE TO: 0DESCRIPTION: RW

PROJECT LENGTH: _SCOPE OF WORK: Reconstruction w/o Added Capacity TO 600

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 300 0Revenue Sharing Funds: Local Match

0 0 0 0 0 300 0Revenue Sharing Funds: State Match

0 0 0 0 0 0 600 0Total

MPO Area

RichmondUrban

PROGRAM/SYSTEM

DRAINAGE IMPROVEMENTS

PROJECT

UPC NO.:

ROUTE:

105684

NFO9999

N/A

SCHEDULE

0

ESTIMATED COST (000's)

JURISDICTION:

YORKTOWN AVENUESTREET NAME:

PERichmond

FY2015 370CN

FROM: 0 TO: 0DESCRIPTION: RW

PROJECT LENGTH: _SCOPE OF WORK: Reconstruction w/o Added Capacity TO 370

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 185 0Revenue Sharing Funds: Local Match

0 0 0 0 0 185 0Revenue Sharing Funds: State Match

0 0 0 0 0 0 370 0Total

834 11/12/2014

Page 137: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Urban

MPO Area

RichmondUrban

PROGRAM/SYSTEM

DRAINAGE IMPROVEMENTS

PROJECT

UPC NO.:

ROUTE:

105686

NFO9999

N/A

SCHEDULE

0

ESTIMATED COST (000's)

JURISDICTION:

YORKTOWN AVENUESTREET NAME:

PERichmond

FY2015 920CN

FROM: 0 TO: 0DESCRIPTION: RW

PROJECT LENGTH: _SCOPE OF WORK: Reconstruction w/o Added Capacity TO 920

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 460 0Revenue Sharing Funds: Local Match

0 0 0 0 0 460 0Revenue Sharing Funds: State Match

0 0 0 0 0 0 920 0Total

MPO Area

RichmondUrban

PROGRAM/SYSTEM

DRAINAGE IMPROVEMENTS

PROJECT

UPC NO.:

ROUTE:

105687

NFO9999

N/A

SCHEDULE

0

ESTIMATED COST (000's)

JURISDICTION:

YORKTOWN AVENUESTREET NAME:

PERichmond

FY2015 410CNFROM: BROAD ROCK CREEK (NORTH), LYNHAVEN

AVE (EAST) TO: LUMKIN AVE (SOUTH), JEFFERSON

DAVIS HIGHWAY (WEST)

DESCRIPTION: RW

PROJECT LENGTH: _SCOPE OF WORK: Reconstruction w/o Added Capacity TO 410

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 205 0Revenue Sharing Funds: Local Match

0 0 0 0 0 205 0Revenue Sharing Funds: State Match

0 0 0 0 0 0 410 0Total

MPO Area

RichmondUrban

PROGRAM/SYSTEM

RECONSTRUCTION

PROJECT

UPC NO.:

ROUTE:

105691

NFO9999

FY2015

SCHEDULE

25

ESTIMATED COST (000's)

JURISDICTION:

EAST 37TH STREETSTREET NAME:

PERichmond

FY2016 475CN

FROM: McRAND STREET TO: HULL STREET (0.2500 MI)DESCRIPTION: RW

PROJECT LENGTH: 0.2500 MISCOPE OF WORK: Reconstruction w/o Added Capacity TO 500

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 250 0Revenue Sharing Funds: Local Match

0 0 0 0 0 250 0Revenue Sharing Funds: State Match

0 0 0 0 0 0 500 0Total

11/12/2014 835

Page 138: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Urban

MPO Area

RichmondUrban

PROGRAM/SYSTEM

GUARDRAIL

PROJECT

UPC NO.:

ROUTE:

105693

NFO9999

Underway

SCHEDULE

0

ESTIMATED COST (000's)

JURISDICTION:

RIVERSIDE DRIVESTREET NAME:

PERichmond

FY2015 540CNFROM: WESTOVER HILLS BOULEVARD TO: REEDY

CREEK PARK ENTRANCE (1.0500 MI)

DESCRIPTION: RW

PROJECT LENGTH: 1.0500 MISCOPE OF WORK: Safety TO 540

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 270 0Revenue Sharing Funds: Local Match

0 0 0 0 0 270 0Revenue Sharing Funds: State Match

0 0 0 0 0 0 540 0Total

MPO Area

RichmondUrban

PROGRAM/SYSTEM

MAIN STREET STATION SITE IMPROVEMENTS

PROJECT

UPC NO.:

ROUTE:

105701

NFO9999

SCHEDULE ESTIMATED COST (000's)

JURISDICTION:

MAIN STREET STATIONSTREET NAME:

PERichmond

FY2015 3,500CNFROM: MAIN STREET STATION TO: MAIN STREET

STATION

DESCRIPTION: RW

PROJECT LENGTH: _SCOPE OF WORK: Other TO 3,500

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 1,500Bond Proceeds: CPR Bonds

2,000 0 0 0 0 0 0CTB Formula: High Priority - State

0 0 0 0 0 2,000 0 1,500Total

MPO Area

RichmondUrban

PROGRAM/SYSTEM

SIDEWALK (NEW CONSTRUCTION)

PROJECT

UPC NO.:

ROUTE:

105709

NFO9999

FY2015

SCHEDULE

25

ESTIMATED COST (000's)

JURISDICTION:

TERMINAL AVENUE/EAST BELT BOULEVARD SIDEWALKSTREET NAME:

PERichmond

FY2016 375CNFROM: 3000 BLOCK OF EAST BELT BOULEVARD TO:

2801 TERMINAL AVENUE (0.7500 MI)

DESCRIPTION: RW

PROJECT LENGTH: 0.7500 MISCOPE OF WORK: Facilities for Pedestrians and Bicycles TO 400

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 200 0Revenue Sharing Funds: Local Match

0 0 0 0 0 200 0Revenue Sharing Funds: State Match

0 0 0 0 0 0 400 0Total

836 11/12/2014

Page 139: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Urban

MPO Area

RichmondUrban

PROGRAM/SYSTEM

CITYWIDE - RECONSTRUCTION

PROJECT

UPC NO.:

ROUTE:

105649

NFOU000

FY2015

SCHEDULE

50

ESTIMATED COST (000's)

JURISDICTION:

CITYWIDESTREET NAME:

PERichmond

FY2016 1,150CN

FROM: VARIOUS TO: VARIOUSDESCRIPTION: RW

PROJECT LENGTH: _SCOPE OF WORK: Reconstruction w/o Added Capacity TO 1,200

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 600 0Revenue Sharing Funds: Local Match

0 0 0 0 0 600 0Revenue Sharing Funds: State Match

0 0 0 0 0 0 1,200 0Total

MPO Area

RichmondUrban

PROGRAM/SYSTEM

CITYWIDE - PAVEMENT OVERLAY

PROJECT

UPC NO.:

ROUTE:

105666

NFOU000

FY2015

SCHEDULE

50

ESTIMATED COST (000's)

JURISDICTION:

CITYWIDESTREET NAME:

PERichmond

FY2016 5,450CN

FROM: VARIOUS TO: VARIOUSDESCRIPTION: RW

PROJECT LENGTH: _SCOPE OF WORK: Resurfacing TO 5,500

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 2,750 0Revenue Sharing Funds: Local Match

0 0 0 0 0 2,750 0Revenue Sharing Funds: State Match

0 0 0 0 0 0 5,500 0Total

MPO Area

RichmondUrban

PROGRAM/SYSTEM

CITYWIDE - SIGNALS/TRAFFIC SERVICES

PROJECT

UPC NO.:

ROUTE:

105668

NFOU000

N/A

SCHEDULE

0

ESTIMATED COST (000's)

JURISDICTION:

CITYWIDESTREET NAME:

PERichmond

FY2015 400CN

FROM: VARIOUS TO: VARIOUSDESCRIPTION: RW

PROJECT LENGTH: _SCOPE OF WORK: Safety TO 400

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 200 0Revenue Sharing Funds: Local Match

0 0 0 0 0 200 0Revenue Sharing Funds: State Match

0 0 0 0 0 0 400 0Total

11/12/2014 837

Page 140: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Urban

MPO Area

RichmondUrban

PROGRAM/SYSTEM

BRIDGE REPLACEMENT - RECONSTRUCTION

PROJECT

UPC NO.:

ROUTE:

105678

NFOU000

N/A

SCHEDULE

0

ESTIMATED COST (000's)

JURISDICTION:

STREET NAME:

PERichmond

FY2015 1,900CN

FROM: 0 TO: 0DESCRIPTION: RW

PROJECT LENGTH: _SCOPE OF WORK: Bridge Replacement w/o Added Capacity TO 1,900

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 550 0Revenue Sharing Funds: Local Match

0 0 0 0 0 550 0Revenue Sharing Funds: State Match

800 0 0 0 0 0 1,100 0Total

MPO Area

RichmondUrban

PROGRAM/SYSTEM

BIKEWAY/TRAILS

PROJECT

UPC NO.:

ROUTE:

105680

NFOU000

Underway

SCHEDULE

0

ESTIMATED COST (000's)

JURISDICTION:

RICHMOND RIVER FRONTSTREET NAME:

PERichmond

FY2015 5,000CNFROM: SOUTH 5TH AND TREDEGAR STREET TO:

WEST 12TH STREET AND RIVERSIDE PARKWAY

(0.5000 MI)

DESCRIPTION: RW

PROJECT LENGTH: 0.5000 MISCOPE OF WORK: Safety and Education of Pedestrians /Bicyclisits TO 5,000

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 2,500 0Revenue Sharing Funds: Local Match

0 0 0 0 0 2,500 0Revenue Sharing Funds: State Match

0 0 0 0 0 0 5,000 0Total

MPO Area

RichmondUrban

PROGRAM/SYSTEM

FRANKLIN STREET - RECONSTRUCTION

PROJECT

UPC NO.:

ROUTE:

105682

NFOU000

N/A

SCHEDULE

0

ESTIMATED COST (000's)

JURISDICTION:

FRANKLIN STREETSTREET NAME:

PERichmond

FY2015 1,000CNDESCRIPTION: RW

PROJECT LENGTH: _SCOPE OF WORK: Reconstruction w/o Added Capacity TO 1,000

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 500 0Revenue Sharing Funds: Local Match

0 0 0 0 0 500 0Revenue Sharing Funds: State Match

0 0 0 0 0 0 1,000 0Total

838 11/12/2014

Page 141: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Enhancement

MPO Area

RichmondEnhancement

PROGRAM/SYSTEM

LANDSCAPING ON VARIOUS SITES

PROJECT

UPC NO.:

ROUTE:

13791

NFO

Complete

SCHEDULE

307

ESTIMATED COST (000's)

JURISDICTION:

STREET NAME:

PERichmond

Underway 629CNVARIOUS LOCATIONS WITHIN THE CITY OF

RICHMOND

DESCRIPTION: RW

PROJECT LENGTH: 0.0000 MISCOPE OF WORK: Landscaping/Beautification TO 937

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 195TAP: MPO - Federal

0 0 0 0 0 0 915Transportation Enhancement Funds:

Federal

0 0 0 0 0 0 277(X) Transportation Enhancement Funds:

Local

-451 0 0 0 0 0 0 1,387Total

MPO Area

RichmondEnhancement

PROGRAM/SYSTEM

LOWER FALLING CREEK GREENWAY

ENHANCEMENT

PROJECT

UPC NO.:

ROUTE:

16086

NFO

Complete

SCHEDULE

148

ESTIMATED COST (000's)

JURISDICTION:

STREET NAME:

PEChesterfield County

Underway 569CN

UnderwayFROM: CONSTRUCT A PEDESTRIAN PARK WITH

MULTI-PURPOSE TRAILS AND TO: HISTORICAL

INTERPRETIVE AREAS.

DESCRIPTION: 105RW

PROJECT LENGTH: _SCOPE OF WORK: Scenic or Historic Highway Programs TO 823

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 216Project Contributions: Various Sources

0 0 0 0 0 0 545Transportation Enhancement Funds:

Federal

0 0 0 0 0 0 136(X) Transportation Enhancement Funds:

Local

-74 0 0 0 0 0 0 897Total

MPO Area

NonMPOEnhancement

PROGRAM/SYSTEM

BATTLE OF REAM'S STATION

PROJECT

UPC NO.:

ROUTE:

70326

NFO

Underway

SCHEDULE

2

ESTIMATED COST (000's)

JURISDICTION:

N/ASTREET NAME:

PEDinwiddie County

CN

UnderwayFROM: 0 TO: 0DESCRIPTION: 239RW

PROJECT LENGTH: 0.0000 MISCOPE OF WORK: Rehabilitation of Historic Bldgs/Facilities TO 241

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 22Project Contributions: Various Sources

0 0 0 0 0 0 175Transportation Enhancement Funds:

Federal

0 0 0 0 0 0 44(X) Transportation Enhancement Funds:

Local

0 0 0 0 0 0 0 241Total

11/12/2014 839

Page 142: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Enhancement

MPO Area

NonMPOEnhancement

PROGRAM/SYSTEM

SOUTH HILL DOWNTOWN REVITALIZATION -

PHASE I

PROJECT

UPC NO.:

ROUTE:

75264

NFO

Complete

SCHEDULE

104

ESTIMATED COST (000's)

JURISDICTION:

STREET NAME:

PESouth Hill

Underway 1,075CN

UnderwayFROM: THREE PHASE IMPROVEMENT PROJECT -

REMOVE OVERHEAD UTILITIES, TO: INSTALL

STREETLIGHTS & LANDSCAPE FOR PED. &

BICYCLIST

DESCRIPTION: 448RW

PROJECT LENGTH: 0.0000 MISCOPE OF WORK: Facilities for Pedestrians and Bicycles TO 1,626

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 33Project Contributions: Various Sources

0 0 0 0 0 0 1,355Transportation Enhancement Funds:

Federal

0 0 0 0 0 0 339(X) Transportation Enhancement Funds:

Local

-100 0 0 0 0 0 0 1,726Total

MPO Area

Tri-CitiesEnhancement

PROGRAM/SYSTEM

CITY OF COLONIAL HEIGHTS - STREETSCAPE

AT GOVERNMENT CENTER

PROJECT

UPC NO.:

ROUTE:

78222

NFO

Underway

SCHEDULE

47

ESTIMATED COST (000's)

JURISDICTION:

BoulevardSTREET NAME:

PEColonial Heights

FY2011 274CN

FROM: A Avenue TO: Charlotte Aveune (0.2800 MI)DESCRIPTION: RW

PROJECT LENGTH: 0.2800 MISCOPE OF WORK: Landscaping/Beautification TO 321

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 325TAP: MPO - Federal

0 0 0 0 0 0 43TAP: Statewide - Federal

0 0 0 0 0 0 225Transportation Enhancement Funds:

Federal

0 0 0 0 0 0 148(X) Transportation Enhancement Funds:

Local

-421 0 0 0 0 0 0 741Total

840 11/12/2014

Page 143: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Enhancement

MPO Area

NonMPOEnhancement

PROGRAM/SYSTEM

TOWN OF LA CROSSE - LACROSSE HOTEL

RENOVATION

PROJECT

UPC NO.:

ROUTE:

78226

NFO

Complete

SCHEDULE

186

ESTIMATED COST (000's)

JURISDICTION:

STREET NAME:

PELa Crosse

Underway 1,373CNFROM: RENOVATION OF HISTORIC HOTEL FOR USE

AS A TRAILHEAD TO: FACILITY, VISITOR CENTER AND

TRANSPORTATION MUSEUM

DESCRIPTION: RW

PROJECT LENGTH: 0.0000 MISCOPE OF WORK: Facilities for Pedestrians and Bicycles TO 1,559

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 77Project Contributions: Various Sources

0 0 0 0 0 0 155TAP: Statewide - Federal

0 0 0 0 0 0 1,026Transportation Enhancement Funds:

Federal

0 0 0 0 0 0 295(X) Transportation Enhancement Funds:

Local

5 0 0 0 0 0 0 1,554Total

MPO Area

NonMPOEnhancement

PROGRAM/SYSTEM

TOBACCO HERITAGE TRAIL (PHASE ONE,

TRAIL 1 AND 2A)

PROJECT

UPC NO.:

ROUTE:

78247

NFO

Complete

SCHEDULE

950

ESTIMATED COST (000's)

JURISDICTION:

STREET NAME:

PELawrenceville

Underway 2,451CNFROM: Trail 1: Brodnax to Lacrosse/Centennial Park (3.27

Miles) TO: Trail 2A: L'ville Public Works to Sta. 95+85.29

(1.01 Mi) (5.0900 MI)

DESCRIPTION: RW

PROJECT LENGTH: 5.0900 MISCOPE OF WORK: Facilities for Pedestrians and Bicycles TO 3,401

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 125Local Project Contributions: Local

0 0 0 0 0 0 787TAP: Statewide - Federal

0 0 0 0 0 0 1,716Transportation Enhancement Funds:

Federal

0 0 0 0 0 0 626(X) Transportation Enhancement Funds:

Local

147 0 0 0 0 0 0 3,254Total

11/12/2014 841

Page 144: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Enhancement

MPO Area

NonMPOEnhancement

PROGRAM/SYSTEM

AMELIA COUNTY - SIDEWALKS, PARKING,

STREETLIGHTS, BIKE RACKS

PROJECT

UPC NO.:

ROUTE:

81760

NFO

Complete

SCHEDULE

39

ESTIMATED COST (000's)

JURISDICTION:

VARIOUS LOCATIONSSTREET NAME:

PEAmelia County

Underway 137CNDESCRIPTION: RW

PROJECT LENGTH: 0.0000 MISCOPE OF WORK: Facilities for Pedestrians and Bicycles TO 176

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 40Open Container Funds: Bike/Ped

0 0 0 0 0 0 75Transportation Enhancement Funds:

Federal

0 0 0 0 0 0 118(X) Transportation Enhancement Funds:

Local

-57 0 0 0 0 0 0 233Total

MPO Area

RichmondEnhancement

PROGRAM/SYSTEM

NEW KENT COUNTY - SIGNAGE FOR 7

BICYCLE RTES

PROJECT

UPC NO.:

ROUTE:

81762

NFO

Complete

SCHEDULE

1

ESTIMATED COST (000's)

JURISDICTION:

STREET NAME:

PENew Kent County

Underway 34CNFROM: NEAR TALLEYSVILLE TO: VARIOUS

LOCATIONS

DESCRIPTION: RW

PROJECT LENGTH: 0.0000 MISCOPE OF WORK: Safety and Education of Pedestrians /Bicyclisits TO 34

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 5Non-Formula: State Match

0 0 0 0 0 0 20RSTP (STP Regional): Federal

0 0 0 0 0 0 10Transportation Enhancement Funds:

Federal

0 0 0 0 0 0 3(X) Transportation Enhancement Funds:

Local

-3 0 0 0 0 0 0 38Total

MPO Area

RichmondEnhancement

PROGRAM/SYSTEM

PATRICK HENRY- ROAD TO REVOLUTION

TRAIL, SIGNAGE & BROCHURES

PROJECT

UPC NO.:

ROUTE:

91207

NFO

Complete

SCHEDULE

20

ESTIMATED COST (000's)

JURISDICTION:

STREET NAME:

PEHanover County

Underway 240CN

FROM: Hanover County TO: Hanover CountyDESCRIPTION: RW

PROJECT LENGTH: _SCOPE OF WORK: Facilities for Pedestrians and Bicycles TO 260

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 43Project Contributions: Various Sources

0 0 0 0 0 0 150Transportation Enhancement Funds:

Federal

0 0 0 0 0 0 37(X) Transportation Enhancement Funds:

Local

29 0 0 0 0 0 0 231Total

842 11/12/2014

Page 145: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Enhancement

MPO Area

Tri-CitiesEnhancement

PROGRAM/SYSTEM

APPOMATTOX RIVER GREENWAY TRAIL

PROJECT

UPC NO.:

ROUTE:

91208

NFO

Complete

SCHEDULE

90

ESTIMATED COST (000's)

JURISDICTION:

STREET NAME:

PEColonial Heights

Underway 932CN

FROM: 2175 feet from Roslyn Park TO: I-95 BridgeDESCRIPTION: RW

PROJECT LENGTH: _SCOPE OF WORK: Facilities for Pedestrians and Bicycles TO 1,022

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 228TAP: Statewide - Federal

0 0 0 0 0 0 831Transportation Enhancement Funds:

Federal

0 0 0 0 0 0 265(X) Transportation Enhancement Funds:

Local

-301 0 0 0 0 0 0 1,323Total

MPO Area

RichmondEnhancement

PROGRAM/SYSTEM

ARRA CHARLES CITY/HENRICO 5 VA CAPITAL

TRAIL CONSTRUCTION

PROJECT

UPC NO.: 93199

NFOARRA09

PE & RW on UPC 86279.REPORT NOTE:

FROM: Long Bridge Road TO: Rte 658 - Kimages Rd.

(10.0000 MI)

DESCRIPTION:

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 8,184American Recovery and Reinvestment Act:

Enhancement

0 0 0 0 0 0 2,841Bond Proceeds: CPR Bonds

0 0 0 0 0 0 11,025Total

MPO Area

NonMPOEnhancement

PROGRAM/SYSTEM

ARRA - TOBACCO HERITAGE TRAIL

PROJECT

UPC NO.: 93204

NFOARRA09

DESCRIPTION:

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 6,000American Recovery and Reinvestment Act:

Enhancement

11/12/2014 843

Page 146: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Enhancement

MPO Area

NonMPOEnhancement

PROGRAM/SYSTEM

LAWRENCEVILLE DOWNTOWN STREETSCAPE

ENHANCEMENT

PROJECT

UPC NO.:

ROUTE:

97815

NFO

Complete

SCHEDULE

29

ESTIMATED COST (000's)

JURISDICTION:

STREET NAME:

PELawrenceville

Underway 197CNFROM: SOUTH & NEW STREETS TO: SHARP & HICKS

STREETS

DESCRIPTION: RW

PROJECT LENGTH: _SCOPE OF WORK: Landscaping/Beautification TO 226

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 13Project Contributions: Various Sources

0 0 0 0 0 0 307TAP: Statewide - Federal

0 0 0 0 0 0 150Transportation Enhancement Funds:

Federal

0 0 0 0 0 0 114(X) Transportation Enhancement Funds:

Local

-359 0 0 0 0 0 0 584Total

MPO Area

RichmondEnhancement

PROGRAM/SYSTEM

LANDSCAPE INTERSTATE I-95 GATEWAYS

INTO THE CITY OF RICHMOND

PROJECT

UPC NO.:

ROUTE:

97840

NFO

Complete

SCHEDULE

91

ESTIMATED COST (000's)

JURISDICTION:

STREET NAME:

PERichmond

Underway 2,722CNFROM: Franklin Street TO: Martin Luther King Bridge

(0.4600 MI)

DESCRIPTION: RW

PROJECT LENGTH: 0.4600 MISCOPE OF WORK: Landscaping/Beautification TO 2,813

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 88State: State Match

0 0 0 0 0 0 283TAP: MPO - Federal

0 0 0 0 0 0 421TAP: Statewide - Federal

0 0 0 0 0 0 1,350Transportation Enhancement Funds:

Federal

0 0 0 0 0 0 566(X) Transportation Enhancement Funds:

Local

105 0 0 0 0 0 0 2,708Total

MPO Area

NonMPOEnhancement

PROGRAM/SYSTEM

BRUNSWICK BYWAYS VISITOR AND

INTERPRETIVE CENTER

PROJECT

UPC NO.:

ROUTE:

101588

NFO

Underway

SCHEDULE

250

ESTIMATED COST (000's)

JURISDICTION:

STREET NAME:

PEBrunswick County

FY2014 548CNDESCRIPTION: RW

PROJECT LENGTH: _SCOPE OF WORK: Scenic or Historic Highway Programs TO 798

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 160Local Project Contributions: Local

0 0 0 0 0 0 638Scenic Byway Grants: Federal

0 0 0 0 0 0 0 798Total

844 11/12/2014

Page 147: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Enhancement

MPO Area

RichmondEnhancement

PROGRAM/SYSTEM

RTE 638 (COGBILL ROAD) - PROVIDE

SIDEWALK

PROJECT

UPC NO.:

ROUTE:

103608

NFO

SCHEDULE ESTIMATED COST (000's)

JURISDICTION:

Cogbill RoadSTREET NAME:

PEChesterfield County

FY2016 440CN

UnderwayFROM: Rt. 639 (HOWELL DR) TO: EXISTING SIDEWALK

AT MEADOWBROOK HS (0.2000 MI)

DESCRIPTION: 35RW

PROJECT LENGTH: 0.2000 MISCOPE OF WORK: Facilities for Pedestrians and Bicycles TO 475

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 380TAP: MPO - Federal

0 0 0 0 0 0 95(X) Transportation Enhancement Funds:

Local

0 0 0 0 0 0 0 475Total

MPO Area

Tri-CitiesEnhancement

PROGRAM/SYSTEM

CITY OF PETERSBURG, SOUTHSIDE DEPOT

RESTORATION

PROJECT

UPC NO.:

ROUTE:

104036

NFO

Underway

SCHEDULE

68

ESTIMATED COST (000's)

JURISDICTION:

STREET NAME:

PEPetersburg

FY2015 433CNDESCRIPTION: RW

PROJECT LENGTH: _SCOPE OF WORK: Restoration and Rehabilitation TO 500

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 200TAP: MPO - Federal

0 0 0 0 0 0 400TAP: Statewide - Federal

0 0 0 0 0 0 152(X) Transportation Enhancement Funds:

Local

-252 0 0 0 0 0 0 752Total

MPO Area

RichmondEnhancement

PROGRAM/SYSTEM

RTE 2770 - ADD SIDEWALK

PROJECT

UPC NO.:

ROUTE:

105192

NFO

Underway

SCHEDULE

80

ESTIMATED COST (000's)

JURISDICTION:

SMOKETREE DRIVE (RT 2770)STREET NAME:

PEChesterfield County

FY2015 483CN

FY2015FROM: YARROW LANE (RTE 3400) TO: 500 FT W RTE

653 (COURTHOUSE RD) (0.3700 MI)

DESCRIPTION: 40RW

PROJECT LENGTH: _SCOPE OF WORK: Facilities for Pedestrians and Bicycles TO 603

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 470TAP: MPO - Federal

0 0 0 0 0 0 118(X) Transportation Enhancement Funds:

Local

15 0 0 0 0 0 0 588Total

11/12/2014 845

Page 148: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Enhancement

MPO Area

RichmondEnhancement

PROGRAM/SYSTEM

FLOYD AVE BIKE BOULEVARD - PE ONLY

PROJECT

UPC NO.:

ROUTE:

105209

NFO

Underway

SCHEDULE

50

ESTIMATED COST (000's)

JURISDICTION:

FLOYD AVESTREET NAME:

PERichmond

N/A 0CNFROM: VARIOUS LOCATIONS TO: VARIOUS

LOCATIONS

DESCRIPTION: RW

PROJECT LENGTH: _SCOPE OF WORK: Facilities for Pedestrians and Bicycles TO 50

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 457TAP: MPO - Federal

0 0 0 0 0 104 10(X) Transportation Enhancement Funds:

Local

-522 0 0 0 0 0 104 467Total

MPO Area

RichmondEnhancement

PROGRAM/SYSTEM

RTE 5 - SCENIC BYWAYS - INTERPRETIVE SITE

PROJECT

UPC NO.:

ROUTE:

54758

NFO0005

Balance of funds to be provided by Henrico County.REPORT NOTE:

Complete

SCHEDULE

150

ESTIMATED COST (000's)

JURISDICTION:

STREET NAME:

PEHenrico County

Underway 425CNFROM: SPOT LOCATION, NORTH SIDE OF RTE 5 EAST

OF I-295 TO: AT FOUR MILE CREEK PARK

DESCRIPTION: RW

PROJECT LENGTH: 0.0000 MISCOPE OF WORK: New Construction Roadway TO 575

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 94Local Match: Local Match

0 0 0 0 0 0 375Scenic Byway Grants: Federal

106 0 0 0 0 0 0 469Total

MPO Area

RichmondEnhancement

PROGRAM/SYSTEM

MAIN ST & FRANKLIN ST - CYCLE TRACK

PROJECT

UPC NO.:

ROUTE:

106182

NFOEN14

FY2015

SCHEDULE

60

ESTIMATED COST (000's)

JURISDICTION:

STREET NAME:

PERichmond

FY2017 240CN

FROM: 9TH STREET TO: LAUREL STREETDESCRIPTION: RW

PROJECT LENGTH: _SCOPE OF WORK: Facilities for Pedestrians and Bicycles TO 300

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 240 0TAP: Statewide - Federal

0 0 0 0 0 60 0(X) Transportation Enhancement Funds:

Local

0 0 0 0 0 0 300 0Total

846 11/12/2014

Page 149: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Enhancement

MPO Area

RichmondEnhancement

PROGRAM/SYSTEM

VIRGINIA CAPITAL TRAIL - DOREY PARK

CONNECTION

PROJECT

UPC NO.:

ROUTE:

106184

NFOEN14

FY2015

SCHEDULE

15

ESTIMATED COST (000's)

JURISDICTION:

STREET NAME:

PEHenrico County

FY2017 114CNFROM: DOREY PARK LOWER PARKING LOT TO:

VIRGINIA CAPITAL TRAIL, PARK PHASE

DESCRIPTION: RW

PROJECT LENGTH: _SCOPE OF WORK: Facilities for Pedestrians and Bicycles TO 130

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 104 0TAP: Statewide - Federal

0 0 0 0 0 26 0(X) Transportation Enhancement Funds:

Local

0 0 0 0 0 0 129 0Total

MPO Area

Tri-CitiesEnhancement

PROGRAM/SYSTEM

NORTH ES - SIDEWALKS

PROJECT

UPC NO.:

ROUTE:

106188

NFOEN14

FY2015

SCHEDULE

40

ESTIMATED COST (000's)

JURISDICTION:

STREET NAME:

PEColonial Heights

FY2018 356CN

FY2017FROM: VARIOUS TO: VARIOUSDESCRIPTION: 36RW

PROJECT LENGTH: _SCOPE OF WORK: Facilities for Pedestrians and Bicycles TO 433

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 151 0TAP: MPO - Federal

0 0 0 0 0 195 0TAP: Statewide - Federal

0 0 0 0 0 87 0(X) Transportation Enhancement Funds:

Local

0 0 0 0 0 0 433 0Total

MPO Area

RichmondEnhancement

PROGRAM/SYSTEM

LEGORDON DR - SIDEWALKS

PROJECT

UPC NO.:

ROUTE:

106201

NFOEN14

FY2015

SCHEDULE

85

ESTIMATED COST (000's)

JURISDICTION:

STREET NAME:

PEChesterfield County

FY2018 275CN

FY2017FROM: CHARTER COLONY PARKWAY TO:

MIDLOTHIAN WOOD BLVD (0.1900 MI)

DESCRIPTION: 15RW

PROJECT LENGTH: _SCOPE OF WORK: Facilities for Pedestrians and Bicycles TO 375

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 300 0TAP: MPO - Federal

0 0 0 0 0 75 0(X) Transportation Enhancement Funds:

Local

0 0 0 0 0 0 375 0Total

11/12/2014 847

Page 150: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Enhancement

MPO Area

RichmondEnhancement

PROGRAM/SYSTEM

CANNON CREEK GREENWAY

PROJECT

UPC NO.:

ROUTE:

106246

NFOEN14

FY2015

SCHEDULE

210

ESTIMATED COST (000's)

JURISDICTION:

STREET NAME:

PERichmond

FY2017 490CNFROM: VALLEY ROAD TO: HOSPITAL ROAD (AT

OLIVER HILL WY)

DESCRIPTION: RW

PROJECT LENGTH: _SCOPE OF WORK: Facilities for Pedestrians and Bicycles TO 700

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 180 0Revenue Sharing Funds: Local Match

0 0 0 0 0 180 0Revenue Sharing Funds: State Match

0 0 0 0 0 160 0TAP: MPO - Federal

0 0 0 0 0 160 0TAP: Statewide - Federal

0 0 0 0 0 80 0(X) Transportation Enhancement Funds:

Local

-60 0 0 0 0 0 760 0Total

MPO Area

RichmondEnhancement

PROGRAM/SYSTEM

MUNFORD ES & FOX ES - SIDEWALKS

PROJECT

UPC NO.:

ROUTE:

106247

NFOEN14

FY2015

SCHEDULE

15

ESTIMATED COST (000's)

JURISDICTION:

STREET NAME:

PERichmond

FY2017 209CN

FROM: VARIOUS TO: VARIOUSDESCRIPTION: RW

PROJECT LENGTH: _SCOPE OF WORK: Facilities for Pedestrians and Bicycles TO 223

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 19 0TAP: MPO - Federal

0 0 0 0 0 301 0TAP: Statewide - Federal

0 0 0 0 0 80 0(X) Transportation Enhancement Funds:

Local

-177 0 0 0 0 0 400 0Total

848 11/12/2014

Page 151: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Public Transportation

MPO Area

RichmondPublic Transportation

PROGRAM/SYSTEM

GRTC REPLACEMENT BUSES

PROJECT

UPC NO.:

ROUTE:

T11907

NFO

MPO Project.REPORT NOTE:

SCHEDULE ESTIMATED COST (000's)

JURISDICTION:

STREET NAME:

PERichmond

FY2013 4,219CNDESCRIPTION: RW

PROJECT LENGTH: _SCOPE OF WORK: Transit TO 4,219

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 3,375RSTP (STP Regional): MPO - Federal

0 0 0 0 0 0 844RSTP (STP Regional): MPO - State Match

0 0 0 0 0 0 0 4,219Total

MPO Area

RichmondPublic Transportation

PROGRAM/SYSTEM

ARRA - GRTC BUS REPLACEMENT

PROJECT

UPC NO.: T9879

NFOARRA09

DESCRIPTION:

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 3,120American Recovery and Reinvestment Act:

Urbanized Area > 200K

MPO Area

RichmondPublic Transportation

PROGRAM/SYSTEM

MECHANICSVILLE COMMUTER TRANSIT

SERVICE

PROJECT

UPC NO.:

ROUTE:

T9717

NFO

MPO Project. Balance to be provided by MPO.REPORT NOTE:

SCHEDULE ESTIMATED COST (000's)

JURISDICTION:

STREET NAME:

PEMulti-jurisdictional: Richmond MPO

FY2012 639CNDESCRIPTION: RW

PROJECT LENGTH: _SCOPE OF WORK: Transit TO 639

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 315CMAQ: Federal

0 0 0 0 0 0 68CMAQ: MPO - Federal

0 0 0 0 0 0 17CMAQ: MPO - State Match

239 0 0 0 0 0 0 400Total

11/12/2014 849

Page 152: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Public Transportation

MPO Area

RichmondPublic Transportation

PROGRAM/SYSTEM

GRTC BUS REPLACEMENT

PROJECT

UPC NO.:

ROUTE:

T9678

NFO

MPO Project.REPORT NOTE:

SCHEDULE ESTIMATED COST (000's)

JURISDICTION:

STREET NAME:

PEMulti-jurisdictional: Richmond MPO

FY2011 2,100CNDESCRIPTION: RW

PROJECT LENGTH: _SCOPE OF WORK: Transit TO 2,100

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 1,680RSTP (STP Regional): Federal

0 0 0 0 0 0 420RSTP (STP Regional): State Match

0 0 0 0 0 0 0 2,100Total

MPO Area

Tri-CitiesPublic Transportation

PROGRAM/SYSTEM

HOPEWELL CIRCULATOR BUS ROUTE

PROJECT

UPC NO.:

ROUTE:

T9443

NFO

SCHEDULE ESTIMATED COST (000's)

JURISDICTION:

STREET NAME:

PEHopewell

FY2011 1,394CNDESCRIPTION: RW

PROJECT LENGTH: _SCOPE OF WORK: Transit TO 1,394

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 988CMAQ: Federal

0 0 0 0 0 0 406CMAQ: State Match

0 0 0 0 0 0 22Local Project Contributions: Local

-22 0 0 0 0 0 0 1,416Total

MPO Area

RichmondPublic Transportation

PROGRAM/SYSTEM

TELEWORK!VA

PROJECT

UPC NO.: T3406

NFOProject Report Req'd

Telework!VADESCRIPTION:

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 400CMAQ TERMS: Federal

0 0 0 0 0 0 100CMAQ TERMS: State Match

0 0 0 0 0 0 500Total

MPO Area

RichmondPublic Transportation

PROGRAM/SYSTEM

GLOBAL POSITIONING SYSTEM/AUTO

VEHICLE LOCATION/AUTO PASSENG

PROJECT

UPC NO.: T998

NFOPublic Transportation

MPO ProjectREPORT NOTE:

FROM: GPS Auto Vehicle Location TO: Auto Passenger

Counting

DESCRIPTION:

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 3,726CMAQ: Federal

0 0 0 0 0 0 868CMAQ: State Match

0 0 0 0 0 0 4,594Total

850 11/12/2014

Page 153: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Public Transportation

MPO Area

Tri-CitiesPublic Transportation

PROGRAM/SYSTEM

NONATTAINMENT AREA

PROJECT

UPC NO.: T204

NFOPublic Transportation

Tri-Cities MPO Air Quality Maintenance AreaDESCRIPTION:

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 178CMAQ: Federal

28 28 28 28 28 28 29CMAQ: MPO - Federal

7 7 7 7 7 7 3CMAQ: MPO - State Match

0 0 0 0 0 0 10Non-Formula: Statewide

0 0 0 0 0 0 40RSTP (STP Regional): Statewide

35 35 35 35 35 35 260Total

MPO Area

RichmondPublic Transportation

PROGRAM/SYSTEM

REGIONWIDE AIR POLLUTION REDUCTION

PROGRAM - RIDEFINDERS

PROJECT

UPC NO.: T203

NFOPublic Transportation

Regionwide Air Pollution Reduction ProgramDESCRIPTION:

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 9,796CMAQ: Federal

400 0 0 0 400 400 1,153CMAQ: MPO - Federal

100 0 0 0 100 100 288CMAQ: MPO - State Match

0 0 0 0 0 0 174CMAQ: State Match

0 0 0 0 0 0 141Non-Formula: Statewide

0 0 0 0 0 0 563RSTP (STP Regional): Statewide

0 0 0 500 500 500 12,115Total

MPO Area

RichmondPublic Transportation

PROGRAM/SYSTEM

VANPOOL FLEET EXPANSION

PROJECT

UPC NO.: T201

NFOPublic Transportation

DESCRIPTION:

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 50CMAQ: Federal

MPO Area

NonMPOPublic Transportation

PROGRAM/SYSTEM

RENOVATION

PROJECT

UPC NO.: T43

NFOPublic Transportation

DESCRIPTION:

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 6,058TEA-21 High Priority Funds: Statewide

MPO Area

RichmondPublic Transportation

PROGRAM/SYSTEM

RENOVATION OF TRANSPORTATION FACILITY

PROJECT

UPC NO.: T41

NFOPublic Transportation

DESCRIPTION:

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 3,786TEA-21 High Priority Funds: Statewide

11/12/2014 851

Page 154: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Public Transportation

MPO Area

RichmondPublic Transportation

PROGRAM/SYSTEM

EXPANSION OF CURRENT MAINTENANCE

FACILITY

PROJECT

UPC NO.: T40

NFOPublic Transportation

Administered by DRPTREPORT NOTE:

GRTC Service AreaDESCRIPTION:

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 1,437Non-Formula: Statewide

0 0 0 0 0 0 11,828RSTP (STP Regional): Federal

0 0 0 0 0 0 1,520RSTP (STP Regional): State Match

0 0 0 0 0 0 14,785Total

MPO Area

Tri-CitiesPublic Transportation

PROGRAM/SYSTEM

CONSTRUCTION OF MULTI-MODAL CENTER

PROJECT

UPC NO.: 76618

NFOPublic Transportation

DRPT administered.REPORT NOTE:

FROM: SOUTH UNION STREET TO: WEST

WASHINGTON STREET

DESCRIPTION:

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 455Non-Formula: State

0 0 0 0 0 0 82Non-Formula: Statewide

0 0 0 0 0 0 2,146RSTP (STP Regional): Federal

0 0 0 0 0 0 2,683Total

MPO Area

RichmondPublic Transportation

PROGRAM/SYSTEM

BIKE SHARE SYSTEM - CITYWIDE

PROJECT

UPC NO.:

ROUTE:

105889

NFO

MPO Project.REPORT NOTE:

FY2014

SCHEDULE

200

ESTIMATED COST (000's)

JURISDICTION:

VARIOUSSTREET NAME:

PERichmond

FY2016 2,800CN

VARIOUSDESCRIPTION: RW

PROJECT LENGTH: _SCOPE OF WORK: Facilities for Pedestrians and Bicycles TO 3,000

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 314 538CMAQ: MPO - Federal

0 0 0 0 0 78 134CMAQ: MPO - State Match

0 0 0 0 0 0 1,936Local Project Contributions: Local

0 0 0 0 0 0 392 2,608Total

MPO Area

RichmondPublic Transportation

PROGRAM/SYSTEM

RICHMOND GRTC - PURCHASE 15 TRANSIT

BUSES

PROJECT

UPC NO.: T4314

NFOPublic Transportation

RICHMOND GRTC - PURCHASE 15 TRANSIT BUSESDESCRIPTION:

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 1,060Project Contributions: Various Sources

0 0 0 0 0 0 4,240RSTP (STP Regional): Federal

0 0 0 0 0 0 5,300Total

852 11/12/2014

Page 155: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Public Transportation

MPO Area

RichmondPublic Transportation

PROGRAM/SYSTEM

EXPANSION OF BUS SERVICE

PROJECT

UPC NO.: T2131

NFOProject Report Req'd

Complete schedule & estimate required.REPORT NOTE:

Expansion of Bus ServiceDESCRIPTION:

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 828CMAQ TERMS: Federal

0 0 0 0 0 0 207CMAQ TERMS: State Match

0 0 0 0 0 0 1,560Primary Formula: State

0 0 0 0 0 0 2,596Total

MPO Area

RichmondPublic Transportation

PROGRAM/SYSTEM

NEW MARKING CAMPAIGN: EDUCATE USERS

ABOUT TRANSIT TECHNOLOGY

PROJECT

UPC NO.: T1806

NFOPublic Transportation

DESCRIPTION:

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 215CMAQ: Federal

0 0 0 0 0 0 54CMAQ: State Match

0 0 0 0 0 0 269Total

MPO Area

RichmondPublic Transportation

PROGRAM/SYSTEM

TRANSIT INFORMATION SOFTWARE

PROJECT

UPC NO.: T240

NFOPublic Transportation

DESCRIPTION:

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 300CMAQ: Federal

MPO Area

RichmondPublic Transportation

PROGRAM/SYSTEM

ALTERNATIVE FUEL TROLLEY VEHICLE

REPLACEMENT

PROJECT

UPC NO.: T206

NFOPublic Transportation

DESCRIPTION:

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 180CMAQ: Federal

MPO Area

RichmondPublic Transportation

PROGRAM/SYSTEM

MARKETING CAMPAIGN TO ATTRACT CHOICE

RIDERS

PROJECT

UPC NO.: T198

NFOPublic Transportation

DESCRIPTION:

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 817CMAQ: Federal

0 0 0 0 0 0 40Non-Formula: Statewide

0 0 0 0 0 0 160RSTP (STP Regional): Statewide

0 0 0 0 0 0 1,017Total

11/12/2014 853

Page 156: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Public Transportation

MPO Area

RichmondPublic Transportation

PROGRAM/SYSTEM

BUS TRANSFER STATION ON BROAD STREET

BETWEEN 7TH AND 8TH ST

PROJECT

UPC NO.: T39

NFOPublic Transportation

DESCRIPTION:

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 20Non-Formula: Statewide

0 0 0 0 0 0 80RSTP (STP Regional): Statewide

0 0 0 0 0 0 100Total

MPO Area

RichmondPublic Transportation

PROGRAM/SYSTEM

GASKINS ROAD PARK AND RIDE FACILITY -

RESURFACE

PROJECT

UPC NO.:

ROUTE:

104511

NFO9999

SCHEDULE ESTIMATED COST (000's)

JURISDICTION:

GASKINS RDSTREET NAME:

PEHenrico County

Underway 228CN

AT 2900 GASKINS RDDESCRIPTION: RW

PROJECT LENGTH: _SCOPE OF WORK: Resurfacing TO 228

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 118Local Project Contributions: Local

0 0 0 0 0 0 55Revenue Sharing Funds: Local Match

0 0 0 0 0 0 55Revenue Sharing Funds: State Match

0 0 0 0 0 0 0 228Total

854 11/12/2014

Page 157: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Rail

MPO Area

Tri-CitiesRail

PROGRAM/SYSTEM

NEPA STUDY - MULTIMODAL FACILITY

PROJECT

UPC NO.:

ROUTE:

105462

FO9999

FY2014

SCHEDULE

500

ESTIMATED COST (000's)

JURISDICTION:

STREET NAME:

PEMulti-jurisdictional: Tri-Cities MPO

CNFROM: VARIOUS LOCATIONS TO: VARIOUS

LOCATIONS

DESCRIPTION: RW

PROJECT LENGTH: _SCOPE OF WORK: Transit TO 500

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 200Local Project Contributions: Local

0 0 0 0 0 0 6Local Project Contributions: Urban - Local

Match

0 0 0 0 0 0 240Urban Formula: Federal

0 0 0 0 0 0 54Urban Formula: State Match

0 0 0 0 0 0 0 500Total

11/12/2014 855

Page 158: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Miscellaneous

MPO Area

RichmondMiscellaneous

PROGRAM/SYSTEM

RICHMOND MPO CMAQ BALANCE ENTRY

PROJECT

UPC NO.: 70719

NFOBalance Entry

DESCRIPTION:

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 171CMAQ: Federal

0 0 0 0 0 0 418CMAQ: State Match

0 0 0 0 0 0 589Total

MPO Area

RichmondMiscellaneous

PROGRAM/SYSTEM

RICHMOND MPO REGIONAL STP (RSTP)

BALANCE ENTRY

PROJECT

UPC NO.: 70721

NFOBalance Entry

DESCRIPTION:

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 150Non-Formula: State Match

0 0 0 0 0 0 589RSTP (STP Regional): Federal

0 0 0 0 0 0 65RSTP (STP Regional): State Match

0 0 0 0 0 0 804Total

MPO Area

Tri-CitiesMiscellaneous

PROGRAM/SYSTEM

RSTP TRANSPORTATN PLANNING

SUPPLMENTL FUNDING FOR CRATER PDC

PROJECT

UPC NO.: 72904

NFODistrict-wide

MPO Project.REPORT NOTE:

DESCRIPTION:

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 413RSTP (STP Regional): Federal

0 20 20 0 0 0 57RSTP (STP Regional): MPO - Federal

0 5 5 0 0 0 14RSTP (STP Regional): MPO - State Match

0 0 0 0 0 0 103RSTP (STP Regional): State Match

25 25 0 0 0 0 588Total

MPO Area

RichmondMiscellaneous

PROGRAM/SYSTEM

ASHLAND TROLLEY LINE TRAIL SECTION 2

PROJECT

UPC NO.:

ROUTE:

97689

NFO

MPO Project.REPORT NOTE:

Underway

SCHEDULE

5

ESTIMATED COST (000's)

JURISDICTION:

STREET NAME:

PEAshland

CNFROM: End of Pavement on Walder Road TO: End of

Town Limits (0.2400 MI)

DESCRIPTION: RW

PROJECT LENGTH: 0.2400 MISCOPE OF WORK: Facilities for Pedestrians and Bicycles TO 5

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 53RSTP (STP Regional): Federal

0 0 0 0 0 0 13RSTP (STP Regional): State Match

-62 0 0 0 0 0 0 66Total

856 11/12/2014

Page 159: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Miscellaneous

MPO Area

RichmondMiscellaneous

PROGRAM/SYSTEM

PROJECT PRESCOPING - RICHMOND

PROJECT

UPC NO.: 99581

NFOBalance Entry

FROM: Various TO: VariousDESCRIPTION:

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

1,035 1,130 1,105 1,082 1,058 919 3,023Prescoping Funds: State

MPO Area

RichmondMiscellaneous

PROGRAM/SYSTEM

CITY OF RICHMOND: EMPLOYEE

TRIPREDUCTION PROGRAM

PROJECT

UPC NO.: T1811

NFOPublic Transportation

MPO Project.REPORT NOTE:

DESCRIPTION:

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 1,677CMAQ: Federal

0 0 0 0 0 0 480CMAQ: MPO - Federal

0 0 0 0 0 0 120CMAQ: MPO - State Match

0 0 0 0 0 0 419CMAQ: State Match

0 0 0 0 0 0 2,696Total

MPO Area

RichmondMiscellaneous

PROGRAM/SYSTEM

RIDEFINDERS - REGIONWIDE

PROJECT

UPC NO.: 50650

FOProject Report Req'd

RIDEFINDERS - RICHMOND REGIONWIDEDESCRIPTION:

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 3,558CMAQ TERMS: Federal

0 0 0 0 0 0 888CMAQ TERMS: State Match

0 0 0 0 0 0 4,446Total

MPO Area

RichmondMiscellaneous

PROGRAM/SYSTEM

HSIP DISTRICTWIDE ROADWAY SAFETY

ASSESSMENT

PROJECT

UPC NO.: 81373

NFODistrict-wide

VARIOUS LOCATIONSDESCRIPTION:

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

428 0 0 0 0 0 1,202Highway Safety Improvements: Federal

48 0 0 0 0 0 32Highway Safety Improvements: Soft Match

0 0 0 0 0 0 101Highway Safety Improvements: State Match

0 0 0 0 476 0 1,335Total

11/12/2014 857

Page 160: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Miscellaneous

MPO Area

RichmondMiscellaneous

PROGRAM/SYSTEM

HSIP DISTRICTWIDE TRAFFIC SIGNALS AND

ITS

PROJECT

UPC NO.: 81388

NFODistrict-wide

VARIOUS LOCATIONSDESCRIPTION:

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 3,144Highway Safety Improvements: Federal

0 0 0 0 0 0 349Highway Safety Improvements: State Match

0 0 0 0 0 142 143(X) Maintenance Funds: Statewide

0 0 0 0 0 142 3,637Total

MPO Area

RichmondMiscellaneous

PROGRAM/SYSTEM

HSIP DISTRICTWIDE HIGH RISK RURAL

ROADS - RICHMOND

PROJECT

UPC NO.: 86684

NFODistrict-wide

FROM: To be detemined TO: To be determinedDESCRIPTION:

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 828High Risk Rural: Federal

0 0 0 0 0 0 92High Risk Rural: State Match

0 0 0 0 0 0 920Total

MPO Area

RichmondMiscellaneous

PROGRAM/SYSTEM

BERKLEY PROJECT

PROJECT

UPC NO.:

ROUTE:

88477

NFO0000

Underway

SCHEDULE

786

ESTIMATED COST (000's)

JURISDICTION:

STREET NAME:

PERichmond

CNDESCRIPTION: RW

PROJECT LENGTH: _SCOPE OF WORK: Preliminary Engineering TO 786

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

784 0 0 0 0 0 0Prescoping Funds: State 3

MPO Area

RichmondMiscellaneous

PROGRAM/SYSTEM

TOWN OF ASHLAND - SRTS - HENRY CLAY ES

- ADD SIDEWALK

PROJECT

UPC NO.:

ROUTE:

102834

NFO0000

Underway

SCHEDULE

64

ESTIMATED COST (000's)

JURISDICTION:

DUNCAN ST, EARLY ST, STEBBINS STSTREET NAME:

PEAshland

FY2015 396CNFROM: 3 LOCATIONS - TO: DUNCAN ST, EARLY ST,

STEBBINS ST (0.9000 MI)

DESCRIPTION: RW

PROJECT LENGTH: 0.9000 MISCOPE OF WORK: Safety TO 460

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 7Local Project Contributions: Local

0 0 0 0 0 0 519Safe Routes to School: Federal

-66 0 0 0 0 0 0 527Total

858 11/12/2014

Page 161: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Miscellaneous

MPO Area

Tri-CitiesMiscellaneous

PROGRAM/SYSTEM

CITY OF COLONIAL HEIGHTS - SRTS - COL

HTS MS - ADD SIDEWALK

PROJECT

UPC NO.:

ROUTE:

102836

NFO0000

Revised schedule requiredREPORT NOTE:

Underway

SCHEDULE

14

ESTIMATED COST (000's)

JURISDICTION:

Conduit Road and Colonial/Lafayette/Elko AvesSTREET NAME:

PEColonial Heights

FY2014 160CN

FY2014FROM: 500 Conduit Road TO: VariousDESCRIPTION: 6RW

PROJECT LENGTH: _SCOPE OF WORK: Safety TO 179

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 221Safe Routes to School: Federal -42

MPO Area

RichmondMiscellaneous

PROGRAM/SYSTEM

ASHLAND TROLLEY LINE TRAIL/PARK

PROJECT

UPC NO.:

ROUTE:

103393

NFO0000

MPO Project. Revised estimate & schedule required. Excess funds to be redistributed by MPO.REPORT NOTE:

SCHEDULE ESTIMATED COST (000's)

JURISDICTION:

STREET NAME:

PEAshland

FY2014 179CNFROM: Maple Street Extended TO: Trolley Line Trail Park

(0.2700 MI)

DESCRIPTION: RW

PROJECT LENGTH: 0.2700 MISCOPE OF WORK: Facilities for Pedestrians and Bicycles TO 179

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

400 0 0 0 480 0 0RSTP (STP Regional): MPO - Federal

100 0 0 0 120 0 0RSTP (STP Regional): MPO - State Match

-921 0 0 0 600 500 0 0Total

MPO Area

Tri-CitiesMiscellaneous

PROGRAM/SYSTEM

RETIMING SIGNALS - VARIOUS LOCATIONS

PROJECT

UPC NO.:

ROUTE:

104877

NFO0000

MPO Project. Revised schedule required.REPORT NOTE:

FY2019

SCHEDULE

45

ESTIMATED COST (000's)

JURISDICTION:

VARIOUSSTREET NAME:

PEPetersburg

FY2020 135CNFROM: VARIOUS LOCATIONS TO: VARIOUS

LOCATIONS

DESCRIPTION: RW

PROJECT LENGTH: _SCOPE OF WORK: Traffic Management/Engineering TO 180

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 37 107 0 0 0CMAQ: MPO - Federal

0 0 9 27 0 0 0CMAQ: MPO - State Match

0 0 46 134 0 0 0 0Total

11/12/2014 859

Page 162: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Miscellaneous

MPO Area

RichmondMiscellaneous

PROGRAM/SYSTEM

VIRGINIA PORT AUTHORITY - CRANE

PROCUREMENT

PROJECT

UPC NO.:

ROUTE:

104891

NFO0000

MPO Project.REPORT NOTE:

SCHEDULE ESTIMATED COST (000's)

JURISDICTION:

PORT OF RICHMONDSTREET NAME:

PERichmond

FY2015 4,184CNDESCRIPTION: RW

PROJECT LENGTH: _SCOPE OF WORK: Other TO 4,184

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 2,056 1,292CMAQ: MPO - Federal

0 0 0 0 0 514 323CMAQ: MPO - State Match

0 0 0 0 0 0 2,570 1,615Total

MPO Area

RichmondMiscellaneous

PROGRAM/SYSTEM

GREEN OPERATOR (GO) RICHMOND DRAYAGE

TRUCK REPLACEMENT PROG

PROJECT

UPC NO.:

ROUTE:

104892

NFO0000

MPO Project.REPORT NOTE:

SCHEDULE ESTIMATED COST (000's)

JURISDICTION:

PORT OF RICHMONDSTREET NAME:

PERichmond

FY2015 1,543CNDESCRIPTION: RW

PROJECT LENGTH: _SCOPE OF WORK: Other TO 1,543

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 400 0 400 434CMAQ: MPO - Federal

0 0 0 100 0 100 109CMAQ: MPO - State Match

0 0 0 500 0 0 500 543Total

MPO Area

RichmondMiscellaneous

PROGRAM/SYSTEM

PARK AND RIDE LOTS AT PRIORITY

LOCATIONS - PE ONLY

PROJECT

UPC NO.:

ROUTE:

106304

NFO0000

FY2016

SCHEDULE

125

ESTIMATED COST (000's)

JURISDICTION:

STREET NAME:

PEMulti-jurisdictional: Richmond MPO

CNFROM: VARIOUS LOCATIONS TO: VARIOUS

LOCATIONS

DESCRIPTION: RW

PROJECT LENGTH: _SCOPE OF WORK: Preliminary Engineering TO 125

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

100 0 0 0 0 0 0CMAQ: MPO - Federal

25 0 0 0 0 0 0CMAQ: MPO - State Match

0 0 0 0 0 125 0 0Total

860 11/12/2014

Page 163: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Miscellaneous

MPO Area

NonMPOMiscellaneous

PROGRAM/SYSTEM

COMMITTED SAFETY PROJECTS-RICHMOND

PROJECT

UPC NO.:

ROUTE:

106554

NFO0000

NEW PROJECT

SCHEDULE ESTIMATED COST (000's)

JURISDICTION:

STREET NAME:

PERichmond District-wide

N/A 0CN

FROM: various TO: variousDESCRIPTION: RW

PROJECT LENGTH: 0.0000 MISCOPE OF WORK: Safety TO 0

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 4,453 3,116 2,489 2,477 0 0Highway Safety Improvements: Federal

0 495 346 277 275 0 0Highway Safety Improvements: Soft Match

-13,927 4,947 3,463 2,765 2,752 0 0 0Total

MPO Area

NonMPOMiscellaneous

PROGRAM/SYSTEM

I95 CORR TECH ADV US1 SIGNAL COMM CAM

- CAROL TO COL HGTS

PROJECT

UPC NO.:

ROUTE:

105369

NFO0001

Underway

SCHEDULE

525

ESTIMATED COST (000's)

JURISDICTION:

STREET NAME:

PERichmond District-wide

CNFROM: Caroline CL TO: Colonial Heights Corp Limits

(42.9700 MI)

DESCRIPTION: RW

PROJECT LENGTH: 42.9700 MISCOPE OF WORK: Safety TO 525

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

375 0 0 0 0 150 0CTB Formula: ITS - State 0

MPO Area

RichmondMiscellaneous

PROGRAM/SYSTEM

RTE 604 PARK AND RIDE AT I-64 (EXIT 214)

PROJECT

UPC NO.:

ROUTE:

106300

NFO0604

Complete estimate and schedule requiredREPORT NOTE:

N/A

SCHEDULE

0

ESTIMATED COST (000's)

JURISDICTION:

POINDEXTER ROADSTREET NAME:

PENew Kent County

FY2015 325CNFROM: IN FRONT OF COUNTY BUILDING TO: IN FRONT

OF COUNTY BUILDING

DESCRIPTION: RW

PROJECT LENGTH: _SCOPE OF WORK: Other TO 325

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 320 0RSTP (STP Regional): MPO - Federal

0 0 0 0 0 80 0RSTP (STP Regional): MPO - State Match

-75 0 0 0 0 0 400 0Total

11/12/2014 861

Page 164: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Miscellaneous

MPO Area

RichmondMiscellaneous

PROGRAM/SYSTEM

RTE 638 - ADD SIDEWALK

PROJECT

UPC NO.:

ROUTE:

86561

NFO0638

Complete

SCHEDULE

257

ESTIMATED COST (000's)

JURISDICTION:

COGBILL ROADSTREET NAME:

PEChesterfield County

Underway 250CN

UnderwayFROM: RTE 847 (LIVINGSTONE AVE) TO: RTE 770

(CHESTERWOOD DR) (0.2940 MI)

DESCRIPTION: 40RW

PROJECT LENGTH: 0.2940 MISCOPE OF WORK: Safety TO 547

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 576Highway Safety Improvements: Federal

0 0 0 0 0 0 64Highway Safety Improvements: State Match

-93 0 0 0 0 0 0 640Total

MPO Area

RichmondMiscellaneous

PROGRAM/SYSTEM

HSIP RICHMOND DISTRICTWIDE

PROJECT

UPC NO.: T6521

NFODistrict-wide

Various locationsDESCRIPTION:

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 1,893Highway Safety Improvements: Federal

0 0 0 0 0 0 210Highway Safety Improvements: State Match

0 0 0 0 0 0 64Local Project Contributions: Local

0 0 0 0 0 0 2,168Total

MPO Area

RichmondMiscellaneous

PROGRAM/SYSTEM

CRAC "CELL LOTS"

PROJECT

UPC NO.:

ROUTE:

84348

NFO9999

MPO Project - Match to be provided by Capitol Region Area Commission.REPORT NOTE:

Underway

SCHEDULE

4

ESTIMATED COST (000's)

JURISDICTION:

CRAC "Cell Phone Parking Lot"STREET NAME:

PEHenrico County

CN

FROM: Parking lots - RIC TO: Parking lots - RICDESCRIPTION: RW

PROJECT LENGTH: _SCOPE OF WORK: New Construction Roadway TO 4

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 307CMAQ: Federal

0 0 0 0 0 0 1Local Project Contributions: Local

-304 0 0 0 0 0 0 308Total

862 11/12/2014

Page 165: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Miscellaneous

MPO Area

RichmondMiscellaneous

PROGRAM/SYSTEM

RICHMOND MPO MULITMODAL LRP

PROJECT

UPC NO.:

ROUTE:

86357

FO9999

MPO project - balance to be provided by MPO.REPORT NOTE:

FY2010

SCHEDULE

1,300

ESTIMATED COST (000's)

JURISDICTION:

STREET NAME:

PEMulti-jurisdictional: Richmond MPO

CNDESCRIPTION: RW

PROJECT LENGTH: 0.0000 MISCOPE OF WORK: Safety TO 1,300

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 240RSTP (STP Regional): Federal

0 0 0 0 0 0 60RSTP (STP Regional): State Match

1,000 0 0 0 0 0 0 300Total

MPO Area

RichmondMiscellaneous

PROGRAM/SYSTEM

HSIP PROACTIVE SAFETY - HENRICO COUNTY

PROJECT

UPC NO.: 86683

NFODistrict-wide

HSIP Proactive Safety Projects Henrico CountyDESCRIPTION:

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 2,237Highway Safety Improvements: Federal

0 0 0 0 0 0 46Highway Safety Improvements: Soft Match

0 0 0 0 0 0 202Highway Safety Improvements: State Match

0 0 0 0 0 0 1Primary Formula: State

0 0 0 0 0 0 11Safety Funds: Hazard Elimination

0 0 0 0 0 0 2,498Total

MPO Area

RichmondMiscellaneous

PROGRAM/SYSTEM

MARINE HWY PROGRAM:

RICHMOND-HAMPTON ROADS BARGE

SERVICE

PROJECT

UPC NO.:

ROUTE:

90354

NFO9999

To be administered by Virginia Port Authority;REPORT NOTE:

Underway

SCHEDULE

3,915

ESTIMATED COST (000's)

JURISDICTION:

STREET NAME:

PERichmond District-wide

CNDESCRIPTION: RW

PROJECT LENGTH: _SCOPE OF WORK: Historic Preservation TO 3,915

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 2,857CMAQ: Federal

0 0 0 0 0 0 1,057CMAQ: State Match

0 0 0 0 0 0 0 3,915Total

11/12/2014 863

Page 166: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Miscellaneous

MPO Area

RichmondMiscellaneous

PROGRAM/SYSTEM

RICHMOND REGION-WIDE

TRAFFIC/OPERATIONS IMPROVEMENTS

PROJECT

UPC NO.:

ROUTE:

101492

NFO9999

MPO Project. Revised schedule required. Balance to be provided by MPO.REPORT NOTE:

FY2014

SCHEDULE

1,000

ESTIMATED COST (000's)

JURISDICTION:

STREET NAME:

PEMulti-jurisdictional: Richmond MPO

FY2015 18,312CN

FROM: N/A TO: N/ADESCRIPTION: RW

PROJECT LENGTH: _SCOPE OF WORK: Safety TO 19,312

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

355 1,346 701 455 450 105 0CMAQ: MPO - Federal

89 336 175 114 112 26 0CMAQ: MPO - State Match

746 4,402 922 922 1,830 168 0RSTP (STP Regional): MPO - Federal

187 1,101 231 231 458 42 0RSTP (STP Regional): MPO - State Match

3,809 7,185 2,029 1,722 2,850 1,376 341 0Total

MPO Area

NonMPOMiscellaneous

PROGRAM/SYSTEM

TRAFFIC SIGNAL CLEARANCE INTERVALS

EVALUATIONS (PE ONLY)

PROJECT

UPC NO.:

ROUTE:

104663

NFO9999

Underway

SCHEDULE

1,800

ESTIMATED COST (000's)

JURISDICTION:

VARIOUSSTREET NAME:

PERichmond District-wide

CN

FROM: VARIOUS LOCATIONS TO: VariousDESCRIPTION: RW

PROJECT LENGTH: _SCOPE OF WORK: Safety TO 1,800

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

540 0 0 0 0 540 540Highway Safety Improvements: Federal

60 0 0 0 0 60 60Highway Safety Improvements: Soft Match

0 0 0 0 0 600 600 600Total

MPO Area

RichmondMiscellaneous

PROGRAM/SYSTEM

REPLACE SIGNALS - VARIOUS

INTERSECTIONS

PROJECT

UPC NO.:

ROUTE:

104664

NFO9999

Underway

SCHEDULE

1,050

ESTIMATED COST (000's)

JURISDICTION:

VARIOUSSTREET NAME:

PERichmond District-wide

FY2016 3,270CN

UnderwayFROM: VARIOUS LOCATIONS TO: VARIOUS

LOCATIONS

DESCRIPTION: 2,170RW

PROJECT LENGTH: 0.0000 MISCOPE OF WORK: Safety TO 6,490

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

1,890 0 0 0 1,890 1,116 945Highway Safety Improvements: Federal

210 0 0 0 210 124 105Highway Safety Improvements: Soft Match

0 0 0 0 2,100 2,100 1,240 1,050Total

864 11/12/2014

Page 167: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Miscellaneous

MPO Area

NonMPOMiscellaneous

PROGRAM/SYSTEM

I64 CORR TECH ADV US 250 - SIGNAL COMM

CAM - RICH TO LOUISA

PROJECT

UPC NO.:

ROUTE:

105366

NFO9999

HB2 ADJUSTMENT

FY2016

SCHEDULE

645

ESTIMATED COST (000's)

JURISDICTION:

STREET NAME:

PERichmond District-wide

CN

FROM: Richmond Corp Limits TO: Lousia CL (25.2200 MI)DESCRIPTION: RW

PROJECT LENGTH: 25.2200 MISCOPE OF WORK: Safety TO 645

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 0Accounts Receivable: Local 645

MPO Area

RichmondMiscellaneous

PROGRAM/SYSTEM

INSTALL SIGNALS - VARIOUS

INTERSECTIONS

PROJECT

UPC NO.:

ROUTE:

106238

NFO9999

Revised schedule requiredREPORT NOTE:

FY2014

SCHEDULE

100

ESTIMATED COST (000's)

JURISDICTION:

STREET NAME:

PERichmond District-wide

FY2016 400CN

FROM: VARIOUS TO: VARIOUSDESCRIPTION: RW

PROJECT LENGTH: _SCOPE OF WORK: Safety TO 500

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

450 0 0 0 0 0 0Highway Safety Improvements: Federal

50 0 0 0 0 0 0Highway Safety Improvements: Soft Match

0 0 0 0 0 500 0 0Total

MPO Area

RichmondMiscellaneous

PROGRAM/SYSTEM

DISTRICTWIDE - PROVIDE PEDESTRIAN

ACCOMODATIONS

PROJECT

UPC NO.:

ROUTE:

106240

NFO9999

FY2016

SCHEDULE

450

ESTIMATED COST (000's)

JURISDICTION:

STREET NAME:

PERichmond District-wide

FY2017 1,000CN

FROM: VARIOUS TO: VARIOUSDESCRIPTION: RW

PROJECT LENGTH: _SCOPE OF WORK: Safety TO 1,450

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

405 0 0 0 900 0 0Highway Safety Improvements: Federal

45 0 0 0 100 0 0Highway Safety Improvements: Soft Match

0 0 0 0 1,000 450 0 0Total

11/12/2014 865

Page 168: RICHMOND - Virginia Department of Transportationsyip.virginiadot.org/reports/213/07-FY15-REVISED-FINAL... · 2014. 11. 5. · FY15 REVISED FINAL FY2015-2020 Six-Year Improvement Program

RICHMOND DISTRICTFY2015-2020 Six-Year Improvement Program

FY15 REVISED FINAL Miscellaneous

MPO Area

RichmondMiscellaneous

PROGRAM/SYSTEM

VA CAPITAL TRAIL - HENRICO RIVERFRONT

PROJECT

UPC NO.:

ROUTE:

106468

NFO9999

FY2015

SCHEDULE

92

ESTIMATED COST (000's)

JURISDICTION:

STREET NAME:

PEHenrico County

FY2015 308CN

N/AFROM: RICHMOND CITY LIMITS TO: 0.36 MI S

RICHMOND CITY LIMITS (0.3600 MI)

DESCRIPTION: 0RW

PROJECT LENGTH: 0.3600 MISCOPE OF WORK: Facilities for Pedestrians and Bicycles TO 400

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 400Open Container Funds: Statewide 0

MPO Area

Tri-CitiesMiscellaneous

PROGRAM/SYSTEM

RICHMOND TRI-CITIES CMAQ BALANCE

ENTRY

PROJECT

UPC NO.: 70722

NFOBalance Entry

DESCRIPTION:

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

16 15 19 16 16 0 0CMAQ: MPO - Federal

4 4 5 4 4 0 0CMAQ: MPO - State Match

18 24 20 20 19 0 0Total

MPO Area

Tri-CitiesMiscellaneous

PROGRAM/SYSTEM

RICHMOND TRI-CITIES REGIONAL STP (RSTP)

BALANCE ENTRY

PROJECT

UPC NO.: 70725

NFOBalance Entry

DESCRIPTION:

REQ'D AFTER

2020FY2020 FY2019FY2018FY2017FY2016FY2015Prev. AllocFund Sources

REQUIRED ALLOCATIONS (000's)

0 0 0 0 0 0 1,434RSTP (STP Regional): Federal

57 110 108 96 100 0 0RSTP (STP Regional): MPO - Federal

14 27 27 24 25 0 0RSTP (STP Regional): MPO - State Match

0 0 0 0 0 0 359RSTP (STP Regional): State Match

137 135 120 125 71 0 1,793Total

866 11/12/2014