rfp09498 p2 pres_t05

45
PURDUE UNIVERSITY BASEBALL FACILITY Phase 2: Design-Build Response CE 498 -Senior Design - 2009 Team 5 Virtual Tour

Upload: rplaughl

Post on 13-Nov-2014

901 views

Category:

Documents


2 download

DESCRIPTION

 

TRANSCRIPT

Page 1: Rfp09498 p2 pres_t05

PURDUE UNIVERSITY BASEBALL FACILITY

Phase 2: Design-Build Response

CE 498 -Senior Design - 2009

Team 5

Virtual Tour

Page 2: Rfp09498 p2 pres_t05

2

ENGINEERING TEAM

PROJECT MANAGER: Alice Madjani

TRANSPORTATION ENGINEER: Eric Hulme

STRUCTURAL ENGINEER: Matt Murray

ENVIRONMENTAL ENGINEER: Mike Broyles

STRUCTURAL ENGINEER: Ryan Laughlin

Introduction

Facility

Drainage

Structural

Construction

LEEDAccess

Page 3: Rfp09498 p2 pres_t05

3

Presentation Overview

Baseball FacilitySoccer FacilitySite LayoutDrainage

Site AccessStructural AspectsLEED CredentialsConstruction and

Cost

Introduction

Facility

Drainage

Structural

Construction

LEEDAccess

Page 4: Rfp09498 p2 pres_t05

4

Time for a New FacilityOther Big Ten Facilities

Current Purdue Facility

Introduction

Facility

Drainage

Structural

Construction

LEEDAccess

Page 5: Rfp09498 p2 pres_t05

5

The Facility

Introduction

Facility

Drainage

Structural

Construction

LEEDAccess

1,800 Permanent Seats2 Green SpacesState of the art Press

BoxHigh Definition Lighting

Grass Berme SeatingHome & Away LockersIndoor Batting CagesUnique Architecture

Page 6: Rfp09498 p2 pres_t05

6

Soccer FacilityContinue using the eastern

field for competitionOption of using the west

field for a future men’s team

Expanded SeatingSupport Facilities

Concessions StandRestroomsLocker Room

H.D. LightingOpportunities to share

facilities

Introduction

Facility

Drainage

Structural

Construction

LEEDAccess

Page 7: Rfp09498 p2 pres_t05

7

Facility Location

Introduction

Facility

Drainage

Structural

Construction

LEEDAccess

Page 8: Rfp09498 p2 pres_t05

8

Drainage and GradingStorm Water Management Overview

Stream running through the center of the siteDetention Basin on the west end of the siteDrainage system for the baseball field

Grading SummaryBuildings are elevated 1-2 ft to prevent

infiltration during heavy storms.The stream is the low point of the site, allowing

the site to drain to it.

Introduction

Facility

Drainage

Structural

Construction

LEEDAccess

Page 9: Rfp09498 p2 pres_t05

9

Stream DesignTrapezoidal Channel

Designed for 100-year, 12 hour duration rain event4:1 side slopes for stabilityLined with cobbles to prevent erosionSide slopes lined with native grasses

Prevent erosion Remove sediment (TSS) and nutrients from runoff

3 connected sectionsConnector from east drainage basin to the siteEast Channel (about 1/2 of developed site

drainage)West Channel (all of developed site drainage)

Introduction

Facility

Drainage

Structural

Construction

LEEDAccess

Page 10: Rfp09498 p2 pres_t05

10

Stream DimensionsConnector from east drainage

basinDepth: 3 ftBottom Width: 2 ftTop Width: 10 ft

East ChannelDepth: 4 ftBottom Width: 1 ftTop Width: 33 ft

West ChannelDepth: 4 ftBottom Width: 6 ftTop Width: 38 ft

Introduction

Facility

Drainage

Structural

Construction

LEEDAccess

Page 11: Rfp09498 p2 pres_t05

11

Stream Layout

Introduction

Facility

Drainage

Structural

Construction

LEEDAccess

Page 12: Rfp09498 p2 pres_t05

12

Steam Cross Section

Introduction

Facility

Drainage

Structural

Construction

LEEDAccess

Page 13: Rfp09498 p2 pres_t05

13

Detention Basin DesignDesign storm: 100-year, 12 hr duration rain

eventRequired Storage Volume: 16.64 acre-ftDesign Characteristics

Overflow weir: 45 ft wide x 1 ft high4 outflow pipes

2 – 12” diameter pipes at invert elevation of 670.1 ft

2 – 15” diameter pipes at invert elevation of 672.2 ft

Depth of 8 feet and bottom elevation of 667.4 ft

Top elevation of 675.4 ft

Introduction

Facility

Drainage

Structural

Construction

LEEDAccess

Page 14: Rfp09498 p2 pres_t05

14

Baseball Field DrainageHydraway 2000 drainage system

Geotextile drainage mat 12” wide x 1” thick Strong, able to withstand heavy loading

Placed every 20 feetDrain to a central drainage pipeInstallation

After field is graded appropriately Smaller trencher creates a 6” wide x 12” deep Backfill with granular fill to promote drainage

Introduction

Facility

Drainage

Structural

Construction

LEEDAccess

Page 15: Rfp09498 p2 pres_t05

15

Baseball Field Drainage Layout

• Blue Lines = Hydraway 2000 Mats

• Pink Line = Central Drainage Collector

Source: Hydraway website

Introduction

Facility

Drainage

Structural

Construction

LEEDAccess

Page 16: Rfp09498 p2 pres_t05

16

Pavement Systems

Surface AsphaltBinder Asphalt

Type #53Sub-base

1 ½ inch

4 ½ inch

8 inch

Surface AsphaltBinder Asphalt

Type #53 Sub-base

1 ½ inch

3 inch

8 inch

Concrete

Type #53Sub-base

6 inch

8 inch

Pervious Concrete

Sand

Type #53Sub-base

9 inch

2 inch

9 inch

Introduction

Facility

Drainage

Structural

Construction

LEEDAccess

Page 17: Rfp09498 p2 pres_t05

17

Pedestrian AccessUpper Pedestrian

Corridor

Lower Pedestrian Corridor

Central Pathway

Eastern Pathway

Western Pathway

Bike Path Extension

Page 18: Rfp09498 p2 pres_t05

18

Site Access: Existing Traffic Volumes

LOS ANALYSIS

McCormick & Cherry (AWSC) A.M. Peak Hour:

LOS E 41 sec Delay

McCormick & Tennis Center (TWSC) A.M. Peak Hour:

LOS B 15 sec Delay

P.M. Peak Hour:

• LOS F • 330 sec Delay

– P.M. Peak Hour:

• LOS C• 18 sec Delay

Introduction

Facility

Drainage

Structural

Construction

LEEDAccess

Page 19: Rfp09498 p2 pres_t05

19

Site Access: 2010 Background Volumes

LOS ANALYSIS

McCormick & Cherry (AWSC) A.M. Peak Hour:

• LOS F• 95 sec Delay

McCormick & Tennis Center (TWSC) A.M. Peak Hour:

• LOS C• 16 sec Delay

P.M. Peak Hour:

• LOS F • 492 sec Delay

P.M. Peak Hour:

• LOS C• 20 sec Delay

Introduction

Facility

Drainage

Structural

Construction

LEEDAccess

Page 20: Rfp09498 p2 pres_t05

20

Site Access: 2010 Total Volumes

LOS ANALYSIS

McCormick & Cherry (RDBT) A.M. Peak Hour:

• LOS C• 18 sec Delay

McCormick & Tennis Center (TWSC) A.M. Peak Hour:

• LOS C• 17 sec Delay

McCormick & Perimeter Pkwy (TWSC) A.M. Peak Hour:

• LOS A• 0 sec Delay

P.M. Peak Hour:

• LOS C • 19 sec Delay

P.M. Peak Hour:

• LOS C• 21 sec Delay

P.M. Peak Hour:

• LOS A• 0 sec Delay

Introduction

Facility

Drainage

Structural

Construction

LEEDAccess

Page 21: Rfp09498 p2 pres_t05

21

Traffic Maintenance PlanConstruction Access

Baseball Stadium: Proposed AlignmentPerimeter ParkwaySoccer Stadium: Existing gravel access north of Tennis parking

Lot

McCormick Road ImprovementsLong-Term Stationary Work Zone

Work Zone Type Intermittent Closure (off-peak hours only) Use of shoulder

Construction Phasing Reconstruction by Halves (sides)

Work Zone Speed limit: 40 mph

As prescribed by INDOT Design Manual, Part VII - Work Zone Traffic Control

Introduction

Facility

Drainage

Structural

Construction

LEEDAccess

Page 22: Rfp09498 p2 pres_t05

22

Live Load 60.0 psf for stadium seating 50.0 psf for rooms 20.0 psf roof live load 0.54 psf live load reduction

factor

Seismic Load 60 kip base shear Lateral Loads

First Story = 17.4 kip Second Story = 21.0 kip Third Story = 21.6 kip

Dead Load 63.0 psf roof load 74.0 psf for other floors

Wind Load 10.7 psf lateral load 13.4 psf uplift

Environmental Load 22.0 psf snow load 11.9 psf ice load

Structural Design: Loads

Introduction

Facility

Drainage

Structural

Construction

LEEDAccess

Page 23: Rfp09498 p2 pres_t05

23

SAP2000 AnalysisPlacing columns & beamsModel of main stadium

structureApplication of loadsComputer analysis

Approximate AnalysisAxial forces in columns of

the critical sectionPortal method for lateral

load

Structural Design: Stadium Frame Analysis

Introduction

Facility

Drainage

Structural

Construction

LEEDAccess

Page 24: Rfp09498 p2 pres_t05

24

Structural Design: Sizing Stadium Components

First Floor Column Sizes

First Floor Beam Sizes

Introduction

Facility

Drainage

Structural

Construction

LEEDAccess

Page 25: Rfp09498 p2 pres_t05

25

Structural Design: Sizing Stadium Components

4” concrete decking 18K5 joists spaced at 5’ for third story 12K3 joists spaced at 5’ for lower stories

Additional Structural Components:

Introduction

Facility

Drainage

Structural

Construction

LEEDAccess

Page 26: Rfp09498 p2 pres_t05

26

Structural Design: Concrete Stadium Seating

Seating Structure: Reinforced

ConcreteBeams,

Girders, Columns

Masonry on Backstop

Introduction

Facility

Drainage

Structural

Construction

LEEDAccess

Page 27: Rfp09498 p2 pres_t05

27

Structural Design: Concrete Stadium Seating

Design: Isolate Beams, Girders, and Columns

Assume no moment TransferReduction to a

determinate structure

Load Path for Structure

Beams

24 ft spanSimply supported2.5 ft widePCI Design

Handbook

Load Path

Introduction

Facility

Drainage

Structural

Construction

LEEDAccess

Page 28: Rfp09498 p2 pres_t05

28

29.5 ft spanSimply supportedApply distributed

beam loadsNeglect compressionFlexure controlsPCI Design Handbook

Structural Design: Concrete Stadium Seating

Design: Isolate beams, Girders, and Columns

Assume no moment Transfer

Reduction to a determinate structure

Girders

Introduction

Facility

Drainage

Structural

Construction

LEEDAccess

Page 29: Rfp09498 p2 pres_t05

29

No moments – No interaction diagrams

Tributary area of girders for total loads

Detail the section – Check strength

PCI Design Handbook

Design: Isolate beams, Girders, and Columns

Assume no moment Transfer

Reduction to a determinate structure

Columns

Introduction

Facility

Drainage

Structural

Construction

LEEDAccess

Structural Design: Concrete Stadium Seating

Page 30: Rfp09498 p2 pres_t05

30

Complicated Moment Resistant FrameTruss remove

indeterminacyConsider tributary

areaApply joint loadsJoint analysis

member forcesCheck Stresses

Reality

Model

Introduction

Facility

Drainage

Structural

Construction

LEEDAccess

Structural Design: Awning Support Structure

Support Section

Page 31: Rfp09498 p2 pres_t05

31

Foundation DesignSoil Capacity

Gross soil bearing capacity of 6,400 psf

2,000 psf net allowable bearing pressure used in design

Shallow Foundations Combined Footings

3 columns per footing Eleven 5-ft x 35-ft

reinforced concrete footings

Design Considerations Soil bearing capacity Immediate settlement Consolidation settlement

Introduction

Facility

Drainage

Structural

Construction

LEEDAccess

Page 32: Rfp09498 p2 pres_t05

32

L.E.E.D.LEED Certification and Benefits

CE 498 Ratings

LEED Rating PointsCertified 14-17

Silver 18-20Gold 21-27

Platinum 28-37

Introduction

Facility

Drainage

Structural

Construction

LEEDAccess

Page 33: Rfp09498 p2 pres_t05

33

L.E.E.DLEED Reviews

Reviewer 1: 12 points - not certifiedReviewer 2: 17 points - LEED Certified

LEED re-submittalsRequesting Silver certificationSubmitted documents (22 points)

Sustainable Site Credits: 10 Water Efficiency Credits: 4 Materials and Resources Credits: 6 Innovation & Design Process Credits: 2

Gold Certification Potential

Introduction

Facility

Drainage

Structural

Construction

LEEDAccess

Page 34: Rfp09498 p2 pres_t05

34

Project ControlsProject Organization/communication

Design-Build firm advantagesSite ManagementLines of communication

Introduction

Facility

Drainage

Structural

Construction

LEEDAccess

Page 35: Rfp09498 p2 pres_t05

35

Quality, Materials and SafetyQuality

ZEAL’s Quality Control and Quality Assurance Manual Monitoring of all products, materials, and work Inspections

MaterialBuilding : Steel framing, reinforced concrete, masonryParking lot: Pervious concreteAccess road: Asphalt pavement

SafetyZEAL’s Safety ManagerSubcontractor’s safety requirements

Introduction

Facility

Drainage

Structural

Construction

LEEDAccess

Page 36: Rfp09498 p2 pres_t05

36

Cost EstimatePrice Proposal

Schedule of valuesRequest for payment due the 1st of every month and

payment received by the 15th of the next month5% retainage on all payments

PRICE PROPOSAL

Basic Facility Proposal Price $6,458,182

Optional Facilities Proposal Price $3,160,805

Parking and Transportation Facility Proposal price $3,545,865

Total Project Price Proposal $13,164,853

Introduction

Facility

Drainage

Structural

Construction

LEEDAccess

Page 37: Rfp09498 p2 pres_t05

37

Cost EstimateBasic Facility

CSI division Total CostDirect cost

Division 3 - Concrete $433,181Division 4 - Masonry $180,063Division 5 -Metals $483,996Division 7 -Thermal & Moisture protection $62,603Division 8 - Openings $28,930Division 9 - Finishes $308,803Division 10 - Specialties $41,392Division 11 - Equipments $133,642Division 31 - Earthwork $213,827Division 32 - Exterior Improvement $828,657Division 33 - Utilities $1,993,004Total Direct Cost $4,708,098

Indirect Cost Fees $1,155,338Insurance $245,002Allowance $1,131,676Total indirect Cost $2,532,016

Total Facility cost (89.2% reduction factor) $6,458,182

Introduction

Facility

Drainage

Structural

Construction

LEEDAccess

Page 38: Rfp09498 p2 pres_t05

38

Cost EstimateParking and Transportation Facility

CSI division Total CostDirect cost

Division 31 - Earthwork $144,271.58Division 32 - Exterior Improvement $2,320,927.91Division 33 - Utilities $275,384.21Total Direct Cost $2,740,583.70

Indirect Cost Fees $426,129Insurance $143,881Allowance $664,592Total indirect Cost $1,234,602 Total Facility cost (89.2% reduction factor) $3,545,865

Introduction

Facility

Drainage

Structural

Construction

LEEDAccess

Page 39: Rfp09498 p2 pres_t05

39

Cost EstimateOptional Facility

Direct cost Total CostSoccer $664,047Seat expansion $105,000Other Roadways and parking facility $1,666,245Total Direct cost $2,435,292

Indirect Cost Fees $389,800Insurance $127,853Allowance $590,558Total indirect Cost $1,108,211 Total Facility cost (89.2% reduction factor) $3,160,805

Introduction

Facility

Drainage

Structural

Construction

LEEDAccess

Page 40: Rfp09498 p2 pres_t05

40

Project ScheduleProject duration: 462 days; ~ 20 monthsDesign schedule

Conceptual Design: Jan 13,09 –May 5, 09Final Design: May 1, 09 – Aug 12, 09

Construction scheduleSite preparation and mobilization: Aug 3, 09Construction starts: Aug 17, 09 Scheduled completion date: Oct 20, 2010Latest construction completion date : Nov 30, 2010

Introduction

Facility

Drainage

Structural

Construction

LEEDAccess

Page 41: Rfp09498 p2 pres_t05

41

Construction Scheduling

Introduction

Facility

Drainage

Structural

Construction

LEEDAccess

Page 42: Rfp09498 p2 pres_t05

42

Summary

Purdue’s needBaseball FacilitySoccer FacilityDrainageSite AccessStructural AspectsLEED CredentialsConstruction and Cost

Page 43: Rfp09498 p2 pres_t05

43

Questions!

Page 44: Rfp09498 p2 pres_t05

44

References Ashley, Erin. "Using Pervious Concrete to achieve LEED credits." 2008.

Pervious Concrete Pavement. 02 February 2009 <http://www.perviouspavement.org/benefits_LEEDcredit.htm>.

B4UBUILD. A Sample Residential Construction Schedule. 1998 - 2008. 19 February 2009 <http://www.b4ubuild.com/resources/schedule/6kproj.shtml>.

CE 498 - CE Design Project. January 2009. 02 February 2009 <https://engineering.purdue.edu/Courses/CE498>.

Corporation, The Schneider. "Storm Water Analysis." 2007. Google. Google Earth. West Lafayette, February 2009. Hydraway Drainage Systems. “Hydraway 2000.” 2007.

<http://www.hydraway.net/hydraway_2000.php> HNTB. Purdue University - Athletic Facilities Master Plan. Conceptual master

plan. Indianapolis: HNTB, 2007. J&M Equipment Specialist & Salvage Recovery. 2008. 2 February 2009

<jmequipmentspecialist.com/id7.html>. Michigan, University of. Michigan Go Blue. February 2009. February 2009

<http://www.mgoblue.com/facilities/article.aspx?id=28646#>.

Page 45: Rfp09498 p2 pres_t05

45

References cont’d Microsoft. Live Search Maps. February 2009. February 2009

<http://maps.live.com/>. Office of the University Architect. "Consultant's Handbook." 2006. Office of

University Architect. 20 January 2009 <http://www.purdue.edu/architect/resources/handbook/index.html>.

Qualite. Design Soccer. 2008. 12 February 2009 <http://www.qualite.com/DesignSoccer.html>.

RS Means. Building Construction Cost Data. Kingston, MA: R.S. Means Company, 2009.

The Schneider Corporation. "Report of Geotechnical Engineering Study." 2008.

The Schneider Corporation. "Storm Water Analysis." 2007. U.S. Fish and Wildlife Service. "Viewing Wetland with Google Earth (Plug-in for

Google Earth)." July 2008. U.S. Green Building Council. New Construction Version 2.2 Reference Guide.

Washington, DC: U.S. Green Building Council, 2006. US Green Building Council. 2009. 20 January 2009 <http://www.usgbc.org/>.