rfp09498 p1 pres_t05

25
PURDUE UNIVERSITY BASEBALL FACILITY Phase 1 : Conceptual Design and Alternatives Analysis CE 498 -Senior Design - 2009 Team 5

Upload: rplaughl

Post on 05-Dec-2014

285 views

Category:

Documents


1 download

DESCRIPTION

 

TRANSCRIPT

Page 1: Rfp09498 p1 pres_t05

PURDUE UNIVERSITY BASEBALL FACILITY

Phase 1 : Conceptual Design and Alternatives Analysis

CE 498 -Senior Design - 2009

Team 5

Page 2: Rfp09498 p1 pres_t05

ENGINEERING TEAMPROJECT MANAGER: Alice MadjaniTRANSPORTATION ENGINEER: Eric HulmeSTRUCTURAL ENGINEER: Matt MurrayENVIRONMENTAL ENGINEER: Mike BroylesSTRUCTURAL ENGINEER: Ryan Laughlin

2

Page 3: Rfp09498 p1 pres_t05

3

Presentation OverviewSite LayoutBaseball FacilitySoccer FacilitySite master planSite AccessWater management

Engineering considerations

Environmental considerations

LEED AccreditationConstructionCost EstimateProject Schedule

Page 4: Rfp09498 p1 pres_t05

4

Time for a New FacilityOther Big Ten Facilities

Current Purdue Facility

Page 5: Rfp09498 p1 pres_t05

5

Site Layout

Page 6: Rfp09498 p1 pres_t05

6

Baseball FacilityUnique Features

SeatingGreen SpacesPress BoxHD LightingBerme SeatingOutfield Wall

LayoutGround LevelConcourse LevelPress Box

Page 7: Rfp09498 p1 pres_t05

7

Soccer FacilityContinue using the eastern

field for competitionOption of using the west

field for a future men’s teamExpanded SeatingSupport Facilities

Concessions StandRestroomsLocker Room

H.D. LightingOpportunities to share

facilities

Opportunities to share facilities

Page 8: Rfp09498 p1 pres_t05

8

Site Master Plan

Page 9: Rfp09498 p1 pres_t05

9

Existing Access

Page 10: Rfp09498 p1 pres_t05

10

Construction Access

Construction Route from S.R. 26

Construction Route from S.R. 126

Construction Route to US 231

Construction Route to S.R. 26

Construction Exit Route from S.R. 526 to S.R. 126

Construction Route into Site

Construction Route from Site

Construction Route from US 231

Page 11: Rfp09498 p1 pres_t05

11

Vehicle Access Intersection Improvements

Intersection Improvements

New Parking Field

New Parking Field

New Parking Field

Perimeter Parkway

Page 12: Rfp09498 p1 pres_t05

12

Pedestrian AccessUpper Pedestrian

Corridor

Lower Pedestrian Corridor

Central Pathway

Eastern Pathway

Western Pathway

Bike Path Extension

Page 13: Rfp09498 p1 pres_t05

13

Water ManagementStream through the middle of the site

Central Drainage Channel through siteRiparian zone = Storm water pollution prevention

BMP to remove fertilizers and suspended solidsCentral detention basin

Control release rate to Jordan CreekHarvest rain water from basin

Flushing toilets Site irrigation Electronic controls (Supervisory Controls and Data

Acquisition)

Page 14: Rfp09498 p1 pres_t05

14

Water Management

Page 15: Rfp09498 p1 pres_t05

15

Environmental ConsiderationsWetlands

U.S. Fish and Wildlife Service

PEMA: temporary wetlandContamination

US-231 Relocation StudyPreviously undeveloped

siteNot classified as a historic

site by DNRNo formal study

Page 16: Rfp09498 p1 pres_t05

16

Engineering ConsiderationsFoundation System

Shallow spread footing and continuous wall foundations

Structural SystemSteel frameReinforced concrete slabs and seating structureSteel columns for Press Box supportAwning covering half the seatsCable suspension system for awning and

backstop

Page 17: Rfp09498 p1 pres_t05

17

L.E.E.D.LEED Certification and Benefits

Anticipated Certification: Silver (20 points)Sustainable Site Credits: 9Water Efficiency Credits: 3Materials and Resources Credits: 6Innovation & Design Process Credits: 2

Gold Certification Potential

Page 18: Rfp09498 p1 pres_t05

18

ConstructionSite management

ZEAL as the constructionmanager

Construction equipment1. Rollers 7. Bobcats2. Lifts 8. Grader3. Concrete pumps

9. Excavator

4. Cranes 10. Pavers5. Front-end loader

11. Compactor

6. Dump Trucks 12. Fort lift

Page 19: Rfp09498 p1 pres_t05

19

Construction cont’dMaterial

Building Steel framing Reinforced concrete

Parking lot Pervious concrete

Page 20: Rfp09498 p1 pres_t05

20

Cost EstimateConceptual cost estimate

Soccer addition

Facility CostBaseball field $1,894,089Building Construction $4,929,922Site work $5,471,713

Total (89.2% cost reduction) $10,967,786

Administrative $4,240,563

Total project cost $15,208,349

Facility Cost

Soccer addition $592,330

Administrative cost $191,915

Total $784,245

Page 21: Rfp09498 p1 pres_t05

21

Construction Scheduling

Page 22: Rfp09498 p1 pres_t05

22

SummaryThe FacilitySite LayoutEngineering ConsiderationEnvironmental ConsiderationL.E.E.D. Accreditation Cost EstimateProject Schedule

Page 23: Rfp09498 p1 pres_t05

23

References Ashley, Erin. "Using Pervious Concrete to achieve LEED credits." 2008.

Pervious Concrete Pavement. 02 February 2009 <http://www.perviouspavement.org/benefits_LEEDcredit.htm>.

B4UBUILD. A Sample Residential Construction Schedule. 1998 - 2008. 19 February 2009 <http://www.b4ubuild.com/resources/schedule/6kproj.shtml>.

CE 498 - CE Design Project. January 2009. 02 February 2009 <https://engineering.purdue.edu/Courses/CE498>.

Corporation, The Schneider. "Storm Water Analysis." 2007. Google. Google Earth. West Lafayette, February 2009. HNTB. Purdue University - Athletic Facilities Master Plan. Conceptual master

plan. Indianapolis: HNTB, 2007. J&M Equipment Specialist & Salvage Recovery. 2008. 2 February 2009

<jmequipmentspecialist.com/id7.html>. Michigan, University of. Michigan Go Blue. February 2009. February 2009

<http://www.mgoblue.com/facilities/article.aspx?id=28646#>.

Page 24: Rfp09498 p1 pres_t05

24

References cont’d Microsoft. Live Search Maps. February 2009. February 2009

<http://maps.live.com/>. Office of the University Architect. "Consultant's Handbook." 2006. Office of

University Architect. 20 January 2009 <http://www.purdue.edu/architect/resources/handbook/index.html>.

Qualite. Design Soccer. 2008. 12 February 2009 <http://www.qualite.com/DesignSoccer.html>.

RS Means. Builiding Construction Cost Data. Kingston, MA: R.S. Means Company, 2009.

The Schneider Corporation. "Report of Geotechnical Engineering Study." 2008. The Schneider Corporation. "Storm Water Analysis." 2007. U.S. Fish and Wildlife Service. "Viewing Wetland with Google Earth (Plug-in for

Google Earth)." July 2008. U.S. Green Building Council. New Construction Version 2.2 Reference Guide.

Washington, DC: U.S. Green Building Council, 2006. US Green Building Council. 2009. 20 January 2009 <http://www.usgbc.org/>.

Page 25: Rfp09498 p1 pres_t05

25

Questions!