republic of iraqal -ahbab al -aoul , capacity 10 0 m 3/h additionally, the intake structure...

48
REPUBLIC OF IRAQ Ministry of Construction, Housing, Municipalities, and Public Works Emergency Operation Development Projects (EODP) (P155732) Environmental and Social Management Checklist For Rehabilitation of Drinking Water Compact Units (Al-mzareea Althani, Aljameaya, Al-mzareea Alaoul, Al-Ahbab Al-Aoul) - Yathrib Sub District Salah El-Din Governorate W13-A. December 6, 2017

Upload: others

Post on 03-Jul-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: REPUBLIC OF IRAQAl -Ahbab Al -Aoul , capacity 10 0 m 3/h Additionally, the intake structure supplying the water to these units is to be refurbished also. The main objective of the

REPUBLIC OF IRAQ

Ministry of Construction, Housing, Municipalities,

and

Public Works

Emergency Operation Development Projects (EODP)

(P155732)

Environmental and Social Management Checklist

For

Rehabilitation of Drinking Water Compact Units (Al-mzareea

Althani, Aljameaya, Al-mzareea Alaoul, Al-Ahbab Al-Aoul) -

Yathrib Sub District Salah El-Din Governorate W13-A.

December 6, 2017

Page 2: REPUBLIC OF IRAQAl -Ahbab Al -Aoul , capacity 10 0 m 3/h Additionally, the intake structure supplying the water to these units is to be refurbished also. The main objective of the

IRAQ: Emergency Operation for Development Project

PART A: General Project and Site Information

INSTITUTIONAL & ADMINISTRATIVE

Country IRAQ

Project title

Rehabilitation of Drinking Water Compact Units (Al-mzareea Althani, aljameaya, Al-

mzareea Alaoul, Al-Ahbab Al-Aoul) - Yathrib Sub District Salah El-Din Governorate

W13-A.

Institutional

arrangements

Project Owner: MMPW

Person in Charge: SMO

Name: Eng . Salih Jabbar Abbas

Title: PMT Director

Contact: [email protected]

Local Counterpart(s): Salah El-din Governorate

Person in Charge: Salah El-din Water Directorate

Name: Mohammed Mahmud Husain

Title: : Salah El-din Water Director

Contact: [email protected]

Environmental

and Social

Management

Implementation

arrangements

Resident Engineer To be completed after awarding

Name:

Contact:

PMT Supervision:

Name: Usama hamudi

Title: follow up engineer

Contact: [email protected]

Local Site Supervision: To be completed after awarding

Page 3: REPUBLIC OF IRAQAl -Ahbab Al -Aoul , capacity 10 0 m 3/h Additionally, the intake structure supplying the water to these units is to be refurbished also. The main objective of the

Name:

Title:

Directorate:

Contact:

Local Counterpart Supervision:

Contractor: To be completed after awarding

Safeguard Supervision

Name:

Title:

Contact:

PROJECT LOCATION & SITE DESCRIPTION

Project

Location

The project is located in outskirts of the town of Yathrib, Salah Al-Din Governorate,

approximately 70km north of the capital city of Baghdad. The town is situated on the

bank of the Tigris River. Map below shows the project location.

Figure 1: Project Location

Aljameaya

Page 4: REPUBLIC OF IRAQAl -Ahbab Al -Aoul , capacity 10 0 m 3/h Additionally, the intake structure supplying the water to these units is to be refurbished also. The main objective of the

Project

Description

Four compact units are to be rehabilitated:

1. Al-mzareea Althani, capacity 200 m3/h;

2. Al jameaya, capacity 100 m3/h;

3. Al-mzareea Alaoul, capacity 100 m3/h;

4. Al-Ahbab Al-Aoul, capacity 100 m3/h

Additionally, the intake structure supplying the water to these units is to be refurbished

also.

The main objective of the project is the rehabilitation of the facilities is the provision of

the drinking water to the community of the residential settlements.

Compact unit consists of the following parts:

Intake structure.

Submersible pumps with raw water pipeline

Pipelines between the outlet pumps and clarifier tanks.

Intermediate Storage tank.

Steel clarifier tanks.

Pressure steel Filter tanks.

Alum system.

Air blowers.

Chlorine Sterilization system.

High lifting pumps.

Electric transformer.

Generator.

Main electrical board.

Cables.

Hydrophone system.

Page 5: REPUBLIC OF IRAQAl -Ahbab Al -Aoul , capacity 10 0 m 3/h Additionally, the intake structure supplying the water to these units is to be refurbished also. The main objective of the

Site Google Map

Page 6: REPUBLIC OF IRAQAl -Ahbab Al -Aoul , capacity 10 0 m 3/h Additionally, the intake structure supplying the water to these units is to be refurbished also. The main objective of the

Figure 2: Project Sites and Adjacent Areas

The area adjacent to the project sites is characterized as rural residential and agricultural.

The units are located in the residential part of the area. The predominant agriculture in the

area is the irrigated fruit plantations with limited vegetable cultivation.

Page 7: REPUBLIC OF IRAQAl -Ahbab Al -Aoul , capacity 10 0 m 3/h Additionally, the intake structure supplying the water to these units is to be refurbished also. The main objective of the

Current condition

of the facility

At present the units are not operational due to the damage during the combat operations in

the area. The damage can be described as severe and includes the following:

Structural damage to the existing operational facilities, such as partially damaged

walls, cracks in the walls and foundation base, removed doors and windows;

peeled of paint and plaster;

Damage to electrical network: electric wires torn out from the wall; destroyed

distribution circuit boards, damaged beyond repair automated systems, broken or

in very poor condition pumps;

Damage to mechanical parts: rusted and broken pipes; destroyed network

connections, destroyed sanitary facilities.

Figure 3: Damage to the Facilities

Figure 4: Standard Layout of the Facility

Alternative water

sources

At present the population relies on the water delivered by water tankers for drinking

purposes which imposes additional financial burden on the community, as well as severe

limitations on the water provision.

For irrigation, in areas close to the river bank, the water is pumped directly from the river.

Page 8: REPUBLIC OF IRAQAl -Ahbab Al -Aoul , capacity 10 0 m 3/h Additionally, the intake structure supplying the water to these units is to be refurbished also. The main objective of the

Project Duration

The expected project duration is 6 months.

Table 1: Duration of Construction Activities

# Activity Duration (man days)

1 Cleaning post-combat debris 75

2 Rehabilitation of Intake Structure 60

3 Rehabilitation of clarifier tank 60

4 Rehabilitation of filtration facilities 60

5 Rehabilitation of storage tank 60

6 Rehabilitation of MCC building 60

7 Rehabilitation of service building 60

8 Replacing of pipes 35

9 Repair and paving of roads within the facility 14

10 Installation of doors and windows 28

11 Painting 38

12 Electrical and mechanical works 42

Proposed Project

Activities

The project scope comprises the following components:

Cleaning post-combat debris;

Civil Works:

Structural rehabilitation of the damaged service facilities: intake, clarifier tank,

storage tank, filtration tank;

Installation of windows and doors;

Plastering and painting of the internal and external walls;

Replacing and renovating of unusable pipes within the perimeter of the facility;

Casting of the roads and surfaces within the facility perimeter;

Casting of the concrete base for the generator and other units as required;

Repair of transmission lines and network connections.

Building of fence around the facility.

Electrical and mechanical works include supply, installation and operation of the pumps,

electric transformers, electric generator, alum system, Chlorine system and the

replacement of cables and outdoor lightings.

Land Acquisition

The project comprises the rehabilitation of the existing facilities; add steel storage tanks

with intermediate pumps & pipes within the site area inside the surrounding fencing,

extended the existing intake structure 2.5 m. The project will not require any permanent

land acquisition.

The construction of the camp is envisioned to be located inside the surrounding fencing of

the existing unit of which the land matter is already settled. therefore,

The project will not require the temporary land acquisition.

The advantage from adding this new steel storage tank is:

To achieve smooth filtration by using low head pumps.

For a better control on the disinfection chlorine gas injection.

Page 9: REPUBLIC OF IRAQAl -Ahbab Al -Aoul , capacity 10 0 m 3/h Additionally, the intake structure supplying the water to these units is to be refurbished also. The main objective of the

Contactor’s Camp

The existing building comprises rooms as offices for the engineers and operators and

others for the guards.

The Contractor's main camp, will contain, the operational center, with prefabricated

offices and parking areas for administration and technical staff. This will also include

areas with sheds for materials testing storage, maintenance and equipment cleaning. The

need for residential accommodation is likely to be relatively minor, except for security

personnel and operators which they woks in 3 shifts, 3 persons for each shift.

It is to point out that the sub project and the compact unit run by three shifts, each shift is

setup of two operators and one guard

The total number of personnel including technical, administrative staff and skilled and

unskilled labor is expected not to exceed 45 persons on daily bases. The employed

personnel will be mostly from the neighborhood areas and Iraqi nationals.

The construction camp should have independent sources of water and electricity, and the

septic tank for the working teams effluent disposal.

PROJECT BASELIN CONDITIONS

Description of

Geographic

Conditions

The terrain is characterized as relatively flat with the elevations are ranging between 45-60

m asl. The area’s immediately adjacent to the units are rural residential, outside the

residential the land is agricultural.

Description of

Physical

Conditions

The climate in the project area is characterized as hot desert climate. The average

temperature is 22.2°C. The warmest month, on average, is July with an average

temperature of 34.6°C. The coolest month on average is January, with an average

temperature of 4°C. The average amount of precipitation per year is 180 mm. The

predominant wind direction is Northeast in the months November through to April, and

predominantly north-west in the months May-October. The mean average wind speed is

10-12 km/h with the wind gusts reaching up to 26-28 km/h.

The main sources of the air pollution is dust generated by moving of the passenger

vehicles on unpaved surfaces, in dry condition and natural dusty conditions, especially

with the wind gusts.

The area is rural residential and noise is limited to the passenger vehicle movement.

Description of

Geological

Conditions

In the project location the geological formation is composed of thin-bedded, black

bituminous limestone, dolomitic limestone and black papery shale with streaks of thin

black chert.

The project area is located in the minor damage zone with the seismic activity of II on

Richter scale.

The area consists of potentially fertile soils characterized as heavy alluvial soils, with

some organic content and a high proportion of clays: about 75 silty loam, and the rest silty

clay loam and clay soil..

Description of According to the hydro-geological classification of Iraq, the project area is located in the

Page 10: REPUBLIC OF IRAQAl -Ahbab Al -Aoul , capacity 10 0 m 3/h Additionally, the intake structure supplying the water to these units is to be refurbished also. The main objective of the

Hydrogeology

Conditions

Low Fold hydro-geological zone. The Low Fold zone is filled by sedimentary formations

that range in age from Late Miocene to Recent: Fatha, Injana, Mukdadiyah and Bai

Hassan, and Quaternary cover. These formations represent the main aquifers in this zone.

The general trend of the groundwater movement is mainly from north and northwest

towards south and southeast.

The groundwater quality in the project area is slightly brackish with the salinity of 1000-

3000 ppm.

Description of

Surface water

The project is located in the watershed of Northern Tigris River on the territory of Iraq. At

Mosul the average, maximum and minimum discharge of the river is 668 m3/s, 7740 m3/s

(2/5/1972) and 85 m3/s (October, 1935) respectively.

The surface water is characterized as intermittent run-off streams with negligible amount

of water in winter rainy season and dry in summer. The majority of these streams

discharge the water into Tigris River with the contribution to the river flow negligible. Due

to the desert conditions, the stream are prone to flash floods in the event of the strong

rains.

Description of

Ecology

Conditions

The project area is located in the Mesopotamian shrub desert terrestrial eco-region1

considered as a transitional zone between the Syrian Desert and steppe region further

north. This terrestrial eco-zone is categorized as vulnerable and due to the security

concerns have received little focused study.

Vegetation reflects the Mesopotamian province of the Irano-Turanian eco-region and is

characterized by the dominance of the drought-tolerant low shrubs with a variety of

grasses and legumes.

Large mammals that are associated with this ecoregion include: Red fox (Vulpes vulpes);

wildcats (Felis silvestris); Greater Horseshoe Bat (Rhinolophus ferrumequinum). Other

mammalian species include: Long-eared hedgehog (Hemiechinus auritus), Asian house

shrew (Suncus murinus), Euphrates jerboa (Allactaga euphratica), black rat (Rattus

rattus).

Reptilian and amphibians associated with this eco-region include: Green Toad (Bufo

viridis), Green Frog (Pelophylax ridibunda), Keeled Rock Gecko (Cyrtopodion scaber).

Persian Gecko (Asaccus elisae), Snake-eyed lizard (Ophisops elegans), Desert monitor

(Varanus griseus).

The area of the project is located in a general area identified as a fly-way route for

migratory birds from Eastern Europe and West Siberia to Mesopotamia and Africa.

The riparian vegetation predominantly comprises reeds and rushes. The fauna of the

freshwater eco-systems is dominated by cyprinids, approximately 75% of the eco-region’s

species and native fauna is represented by genus Barbus considered as economically

important species.

1 National Report on Biodiversity in Iraq, July 2010

Page 11: REPUBLIC OF IRAQAl -Ahbab Al -Aoul , capacity 10 0 m 3/h Additionally, the intake structure supplying the water to these units is to be refurbished also. The main objective of the

The project area does not contain any globally important habitats or ecosystems. There are

no Nature Reserves or other legally protected areas in the vicinity of the project or in a

close proximity. No conservation practices are exercised in the project area apart from the

control of hunting to the extent they are controlled and monitored throughout the country.

Description of

Physical Cultural

Resources

There are no known sites of historical and archeological importance within the immediate

vicinity of the project.

Description of

Socio-Economic

Context

The total population of the Salaheddin Governorate is 1.5 million people. The population

of project area is approximately 6000 residents. The main demographic indicators are:

Population growth rate is 2.6%, according to the available statistics until 2014;

Age category of less than 15 years is 40% in 2012; the category of 15- 64 years of

age is %56.9 in 2012.

Population percentage in the urban areas is 69%, rural population was 31% for

2014.

Economic activity in governorate is centered around agriculture. 44% of the

governorate’s workforce is employed in the agricultural sector, the highest

percentage among all 18 provinces.

Salaheddin has 18% unemployment rate, and 39.9% live below the poverty line of

$2.20 per day.

Illiteracy rate is 15.7% with the school enrollment: 78.3% primary education;

14.7% secondary education.

Education: One university (Tikrit University, 2900 students), 269 secondary

schools, 16 vocational schools (commercial, industrial and technical), 11 teacher

training institutes.

Health: Salaheddin has 9 hospitals and 13 public medical clinics.

Access to drinking water: 72.5%.

Access to sanitary network: 82.4%.

No sanitary landfills in the area, only authorized dumping sites; municipal waste

collection rate is 43.1%

Access to electricity grid: 89.6%

LEGISLATION & POLICIES

National & Local

Legislation and

World Bank

Policies that

Apply to the

Project

The applicable national legislation is as following:

The Law for the Protection and Improvement of Environment No. 27, 2009;

Forests and Woodlands Law No. 30 of 2009;

Protection of Wild Animals and Birds No. 21 of 1979;

Regulating Exploitation and Protection of Aquatic Life No. 46 of 1976;

Ministry of Water Resources Law No. 50 of 2008;

Public Health Law No. 89 of 1981, amended by Resolution No.54 of 2001;

Page 12: REPUBLIC OF IRAQAl -Ahbab Al -Aoul , capacity 10 0 m 3/h Additionally, the intake structure supplying the water to these units is to be refurbished also. The main objective of the

Iraqi Drinking Water Standard No. (417)-2001;

Regulation for the Provision of Water Resources, No. 2, 2001;

Regulation for the Protection of Rivers No. 25, 1967;

Law No. 27 of 1999 concerning the establishment of the General Authority for

Water and Sewage;

Instructions No. 2 of 2014 on Environmental Protection from Municipal Waste;

Directive No. (67) of 1986 Regulating the Debris Collection Areas;

Clean Air Act No. 1 of 2004;

Noise Prevention Law No. 21 of 1966;

Directive No. 4 of 1993 concerning occupational health, protection of workers

against vibration;

Instructions No. 3/1985 Concerning Occupational Safety;

Law No. 6 of 1988 concerning the National Commission for Occupational

Hygiene and Safety;

Law No. 55 of 2002 for The Antiquities & Heritage of Iraq;

Acquisition Law No.12. of 1981

At present, there is no national Building Code in Iraq and the most commonly used are the

ACI 318 codes.

The main WB safeguard policies triggered are:

OP/BP 4.01 Environmental Assessment

OP/BP 4.11 Physical Cultural Resources

BP 17.50 Disclosure Policies

OP 4.12 Involuntary Resettlement.

Since there is no impact on cultural sites and no involuntary taking of land, therefore, OP

4.11 and OP 4.12 do not apply for this project.

The EHS Guidelines applicable to the project are:

Environmental, Health, and Safety General Guidelines

EHS Guidelines for Water and Sanitation

When host country regulations differ from the levels and measures presented in the EHS

Guidelines, projects will be required to achieve whichever is more stringent.

In case of the difference between the National Legislation and WB Safeguard Guidelines,

it has been agreed that the WB instructions will prevail over the national legislation

provisions.

Air quality standard and the drinking water standard are presented in Annex 1.

Page 13: REPUBLIC OF IRAQAl -Ahbab Al -Aoul , capacity 10 0 m 3/h Additionally, the intake structure supplying the water to these units is to be refurbished also. The main objective of the

PUBLIC CONSULTATION

Public

Consultation

Process

Due to the security concerns, it is not possible to conduct the public consultation meeting

with the affected parties, therefore, interviews were held with the residents on individual

basis. There are no active local NGOs currently in the area.

The PMT team has conducted individual interviews with the residents of the area passing

by the project site on 22 December, 2016. Accordingly, a questionnaire was prepared in

order to cover the key environmental and social aspects related to the project. The

questionnaire was then addressed to the local individuals in the surrounding community

randomly to have their opinions and thoughts regarding the rehabilitation activities. The

questionnaire was also conducted with women to take their opinions freely. The total

number of people interviewed 6 men. Please refer to annex 2 below for more details.

During the interview the team presented the description of the project and discussed the

issues of concern of the stakeholders. The main results of the discussion are:

1- All questioned local stakeholders agreed that the reconstruction activities will

have a strong positive impact from the social perspectives on the local residents.

2- No claims from any local population were recorded or alleged regarding the

ownership of the land where the rehabilitation activities to take place; all agreed

that is governmental land property.

3- No vegetation covers, crops, plants, trees…etc. will be removed in order to

execute the rehabilitation activities.

4- No infrastructure will be affected negatively due the reconstruction activities.

5- No deportation, dislocation of any of the local community will be needed due to

these activities.

6- Information about a grievance mechanism was introduced to interviewed

individuals and a translated GRM form was also provided. All interviewed people

were informed that they can submit their complaint to either site engineer, or to

community leader or to PMT during construction.

GRIEVANCE REDRESS MECHANISEM (GRM)

GRM Process

Bank procedures require that Grievance Redress Mechanisms (GRMs) be established and

operational prior to commencement of the project, and that they continue to operate for

one year following completion of the works for third party settlement of disputes. This

GRM should take into account the availability of judicial recourse as well as traditional

and community dispute resolution mechanisms.

The project grievance redressed system should be developed in consultation with

communities, which might include the following for written complaints:

1. First, the affected person sends his/her grievance in writing to the

Page 14: REPUBLIC OF IRAQAl -Ahbab Al -Aoul , capacity 10 0 m 3/h Additionally, the intake structure supplying the water to these units is to be refurbished also. The main objective of the

communities’/community leaders. The grievance note should be signed and dated

by the aggrieved person. Where the affected person is unable to write, s/he should

obtain assistance from the community to write the note and mark the letter with

his/her thumbprint. The community should respond within 14 days.

2. Second, if the aggrieved person does not receive a response or is not satisfied with

the solution provided by the community, s/he lodges her or his grievance to PMT

which should respond within 14 days.

3. Third, if the aggrieved person is not satisfied with the solution of PMT, s/he can

go to the court.

In any case, the PMT must maintain records of grievances and complaints, including

minutes of discussions, recommendations and resolutions made. The contact information

of the designated GRM personnel will be also posted at the project site for any complaint

and redress. The contacts at the Ministry are:

# Name Job Title Phone Number E-mail

1 Fouad Abed Jameel Engineer, Ministry +96477010197

01

[email protected]

m

2 Saba Qasem Engineer, Ministry +96478130115

56

[email protected]

INSTITUTIONAL CAPACITY BUILDING

Will there be any

capacity building?

[ ] N or [X ]Y

Page 15: REPUBLIC OF IRAQAl -Ahbab Al -Aoul , capacity 10 0 m 3/h Additionally, the intake structure supplying the water to these units is to be refurbished also. The main objective of the

15

PART B: safeguards SCREENING AND Triggers

Will the site activity

include/involve any

of the following??

Activity/ Typology Status

1. Reconstruction of linear infrastructure, such as roads or transmission lines [X] Yes [] No

2. Reconstruction of private homes, housing estates, public buildings, or facilities and

installations for public services (e.g. substations, water treatment plants, pumping

stations or similar)

[ X] Yes [] No

3. Reconstruction of / impacts on surface drainage system [ ] Yes [ X] No

4. Activities in Historic building(s) and districts [ ] Yes [X ] No

5. Required acquisition of land2 or temporary / permanent impacts on livelihoods [ ] Yes [ X] No

6. Handling or presence of hazardous or toxic materials3 [ X] Yes [ ] No

7. Impacts on forests and/or protected areas [] Yes [ X] No

8. Risk of unexploded ordinance (UXO) [X ] Yes [ ] No

9. Traffic and Pedestrian Safety [ ] Yes [X ] No

2 Land acquisitions includes displacement of people, change of livelihood encroachment on private property this is to land that is purchased/transferred and affects people who are

living and/or squatters and/or operate a business (kiosks) on land that is being acquired. 3 Toxic / hazardous material includes but is not limited to asbestos, toxic paints, noxious solvents, removal of lead paint, etc.

Page 16: REPUBLIC OF IRAQAl -Ahbab Al -Aoul , capacity 10 0 m 3/h Additionally, the intake structure supplying the water to these units is to be refurbished also. The main objective of the

16

PART C: Mitigation measures

Construction Phase

No. Potential Impacts Mitigation Measures Monitoring

Responsibility Additional Cost in USD

Implementation Monitoring Mitigation

measures Monitoring

0 General

Conditions

(a) The local construction and environment inspectorates and

communities have been notified of upcoming activities

(b) The public has been notified of the works through

appropriate notification in the media and/or at publicly

accessible sites (including the site of the works)

(c) All legally required permits have been acquired for

construction and/or rehabilitation

(d) The Contractor formally agrees that all work will be carried

out in a safe and disciplined manner designed to minimize

impacts on neighboring residents and environment.

(e) Workers’ PPE will comply with international good practice

(always hardhats, as needed masks and safety glasses,

harnesses and safety boots)

(f) There is posted material indicating the nearest police station

and hospital (with accident and emergency facilities).

(g) The contractor must take reasonable steps to prevent

unauthorized people accessing the site.

(h) Training on handling of UXO/ERW

(i) Avoid the burning of materials on site.

(j) Provide a first aid kits in different places of the work site

with the appropriate number of materials given the number

of workers on site. The locations of the first aid kits will be

provided to all workers.

(k) Providing extinguishers on work site.

(l) If work involving the use of flammable materials is being

carried out, stop people smoking and do not allow other

work activities involving potential ignition sources to take

place nearby.

(m) Providing site boundaries by installing suitable physical

boundaries (barriers, tape or fence).

(n) Marking excavation holes with physical boundaries

(barriers, tape or fence)

(o) The contractor should put up barriers or covers in the area

of openings and excavations.

(p) Store building materials (such as pipes, manhole rings, and

cement bags) so that they cannot topple or roll over.

Bi-monthly: record of

all the licenses and

permits obtained;

Compliance with the

HSE requirements

Contractor Resident

engineer

PMT

No additional cost No additional cost

Page 17: REPUBLIC OF IRAQAl -Ahbab Al -Aoul , capacity 10 0 m 3/h Additionally, the intake structure supplying the water to these units is to be refurbished also. The main objective of the

17

No. Potential Impacts Mitigation Measures Monitoring

Responsibility Additional Cost in USD

Implementation Monitoring Mitigation

measures Monitoring

(q) Keep walkways and stairways free of tripping hazards such

as trailing cables, building materials, and debris.

(r) Everyone who works on any site must have access to

adequate toilet and washing facilities, a place for preparing

and consuming refreshments, and an area for storing and

drying clothing and personal protective equipment (PPE).

(s) Contractor to ensure PPE (personal protective equipment) is

used by all workers on site.

(t) Materials and equipment are tidily stacked, protected and

covered where necessary. Additionally, there is adequate

space for new materials to be stored in secured covered

areas to avoid damage, theft, and to protect these items

from weather conditions.

(u) Scaffolding for work in elevated areas such as ceiling

painting should comply with the OSHA “General

Requirements for Scaffolds §1926.451”

(v) Appropriate signposting of the sites will inform workers of

key rules and regulations to follow.

1

Generation,

storage, disposal

of construction

and domestic

waste

(w) Waste collection and disposal pathways and sites will be

identified for all major waste types expected from

demolition and construction activities.

(x) Mineral construction and demolition wastes will be

separated from general refuse, organic, liquid and chemical

wastes by on-site sorting and stored in appropriate

containers.

(y) Construction waste will be collected and disposed properly

by licensed collectors

(z) The records of waste disposal will be maintained as proof

for proper management as designed.

(aa) Whenever feasible Contractor will reuse and recycle

appropriate and viable materials (except when containing

asbestos)

Weekly site inspections

and verifying the

records on waste

disposal

Contractor Resident

engineer

PMT

No additional cost No additional cost

2 Deterioration of

air quality

(a) During excavation works dust control measures shall be

employed, e.g. by spraying and moistening the ground

(b) Demolition debris, excavated soil and aggregates shall be

kept in controlled area and sprayed with water mist to

reduce debris dust

(c) During pneumatic drilling or breaking of pavement and

foundations dust shall be suppressed by ongoing water

Ambient air quality

test, 1 time prior to

construction to obtain

the baseline

Air quality parameters:

PM10, PM2.5, SO2,

Contractor Resident

engineer

PMT

Additional cost of

water

2000

Testing done by

accredited

laboratories.

Additional cost

2000 US $

Page 18: REPUBLIC OF IRAQAl -Ahbab Al -Aoul , capacity 10 0 m 3/h Additionally, the intake structure supplying the water to these units is to be refurbished also. The main objective of the

18

No. Potential Impacts Mitigation Measures Monitoring

Responsibility Additional Cost in USD

Implementation Monitoring Mitigation

measures Monitoring

spraying and/or installing dust screen enclosures at site

(d) The surrounding environment (sidewalks, roads) shall be

kept free of soil and debris to minimize dust

(e) There will be no open burning of construction / waste

material at the site

(f) All machinery will comply with Iraqi emission regulations,

shall well maintained and serviced and there will be no

excessive idling of construction vehicles at sites

NOx, CO, Ozone and

HC

Compliance with dust

abatement measures

Camera: 250 US $

3 Increased level of

noise

(a) Construction noise will be limited to restricted times agreed

to in the permit

(b) During operations the engine covers of generators, air

compressors and other powered mechanical equipment shall

be closed, and equipment placed as far away from

residential areas as possible

Weekly site inspection:

Compliance with

the time

limitations;

Switching off the

equipment not in

use;

Use of protective

gear

Contractor Resident

engineer

PMT

No additional cost No additional cost

4

Disruption of the

runoff water and

drainage systems

(a) Drainage / canalization systems will be reconstructed

according to good engineering practice, including

appropriate dimensions, clarifier basins, and connection to

treatment facilities as required

(b) Storm water drainage systems will be designed and

constructed as not to silt, pollute, block or otherwise

negatively impact natural streams, rivers, ponds and lakes;

including during construction activities

(c) There will be procedures in place for prevention of and

rapid response to accidental spills of fuels, lubricants and

other toxic or noxious substances, and for their recovery

and appropriate disposal

(d) Construction vehicles and machinery will be washed only

in designated areas where runoff will not pollute natural

surface water bodies

(e) There will be no unregulated extraction of groundwater, nor

uncontrolled discharge of process waters, cement slurries,

or any other contaminated waters into the ground or

adjacent streams or rivers;

(f) Contractor will obtain all necessary licenses and permits for

Weekly site inspection

during rainy season;

Bi-weekly site

inspection during dry

seasons:

debris

accumulation in

water drainage

areas;

Alteration of water

courses;

Signs of spillage of

hazardous

materials

Testing in case of

accidental spills of

hazardous

Contractor Resident

engineer

PMT

additional cost:

contingency for

removal of

accidental

hazardous spills

1000 US $

No additional cost

Page 19: REPUBLIC OF IRAQAl -Ahbab Al -Aoul , capacity 10 0 m 3/h Additionally, the intake structure supplying the water to these units is to be refurbished also. The main objective of the

19

No. Potential Impacts Mitigation Measures Monitoring

Responsibility Additional Cost in USD

Implementation Monitoring Mitigation

measures Monitoring

water extraction and regulated discharge into the public

wastewater system.

materials

5

Deterioration of

groundwater

quality

(a) The site will establish appropriate erosion and sediment

control measures such as e.g. hay bales and / or silt fences

to prevent sediment from moving off site and causing

excessive turbidity in canalization and nearby streams and

rivers

(b) Sewage from construction offices and rest areas will be

collected and transferred by trucks to the nearest sewage

treatment plant

Weekly site inspection

during rainy season;

Bi-weekly site

inspection during dry

seasons

Water testing: in case

of accidental spills of

hazardous materials:

pH, Turbidity,

Electrical Conductivity

(EC), Color, Total

Suspended Solids

(TSS), Total Dissolved

Solids (TDS),

Chemical Oxygen

Demand (COD),

Biological Oxygen

Demand (BOD),

Polychlorinated

Biphenyls (PCBs)

Contractor Resident

engineer

PMT

No additional cost Testing done by

accredited

laboratories.

Additional cost

3000 US $

6 Damage to fauna,

flora

(a) A survey and an inventory shall be made of large trees in

the vicinity of the construction activity, large trees shall be

marked and cordoned off with fencing, their root system

protected, and any damage to the trees avoided

(b) Adjacent streams shall be protected from site run-off and

siltation with appropriate measures

(c) There will be no unlicensed borrow pits, quarries or waste

dumps in adjacent areas, especially not in protected areas.

Bi-weekly site

inspections:

Degree of habitat

disruption due to

construction

activities

Site restoration after

work completion

Contractor Resident

engineer

PMT

No additional cost No additional cost

Page 20: REPUBLIC OF IRAQAl -Ahbab Al -Aoul , capacity 10 0 m 3/h Additionally, the intake structure supplying the water to these units is to be refurbished also. The main objective of the

20

No. Potential Impacts Mitigation Measures Monitoring

Responsibility Additional Cost in USD

Implementation Monitoring Mitigation

measures Monitoring

7 Disruption of

traffic

(a) In compliance with national regulations the Contractor will

insure that the construction site is properly secured and

construction related traffic regulated.

(b) The site will be clearly visible and the public warned of all

potential hazards by signposting and barriers / fencing

(c) Traffic management system and staff training, especially

for site access and near-site heavy traffic. Provision of safe

passages and crossings for pedestrians where construction

traffic interferes.

(d) Adjustment of working hours to local traffic patterns, e.g.

avoiding major transport activities during rush hours or

times of livestock movement

(e) If required, active traffic management by trained and visible

staff at the site for safe passage for the public

(f) Ensuring safe and continuous access to all adjacent office

facilities, shops and residences during construction

Monthly site

surveillance for the

presence of

fencing/barriers and

warning signs, and

traffic speed limitations

Contractor Resident

engineer

PMT

No additional cost No additional cost

8

Deterioration of

health & safety

conditions

(a) Provide adequate signage to prevent accidental falling into

open areas

(b) Fencing of the work areas

(c) Deployment of HSE procedures for the construction

personnel (Annex 3)

Inspection and photo

evidence

Maintaining records of

injuries and accidents

with cause and location

Contractor Resident

engineer

PMT

No additional cost No additional cost

9 Social Impacts

(a) Reducing impacts on the community through community

and neighbour engagement.

(b) In cases of where there are minority communities speaking

a different language in the area or working on site, notices

are printed in the common local language.

(c) Provide the proper GRM for handling complaints

Bi-weekly monitoring

of response to

complaints

Contractor Resident

engineer

PMT

No additional cost No additional cost

Expected additional mitigation costs: USD 8 450

Expected monitoring costs: USD 5 250 per year

Page 21: REPUBLIC OF IRAQAl -Ahbab Al -Aoul , capacity 10 0 m 3/h Additionally, the intake structure supplying the water to these units is to be refurbished also. The main objective of the

21

PART D: Monitoring Plan

Table (1) Summary of ESMP during Maintenance Phase

No. Potential Impacts Mitigation Measures Monitoring

Responsibility Additional Cost in USD

Implementation Monitoring Mitigation measures Monitoring

1

Generation,

storage, disposal

of construction

and domestic

waste

(a) Use of non-toxic paints for repairs of the

buildings;

(b) Storage of hazardous materials used for repairs in

sealed containers;

(c) Disposal of waste to authorized disposal sites;

(d) Avoid disposal of effluent into the river

Monthly

surveillance;

Maintaining

records of

quantities of waste

and location of its

disposal

Operator Yathrib Water

Directorate No additional costs No additional cost

2 Deterioration of

air quality

(a) Water spraying for dust control in maintenance

areas;

(b) Draining of ponds to prevent stagnation;

(c) Timely disposal of effluent from sanitary facilities

in office buildings;

(d) Timely disposal of domestic waste

Once a year testing

during the dry

season:

Air quality

Parameters:

PM10, PM2.5,

SO2, NOx, CO,

Ozone and HC

Operator Yathrib Water

Directorate No additional costs 2000 US $ for air quality

monitoring

3 Increased level of

noise

(a) Advance warning to public ahead of planned

maintenance and repair activities;

(b) Restriction on working hours to 8.00-19.00 during

working days and avoidance of works during

holidays unless needed on emergency basis

Ensure the noise

levels are within

the acceptable

limits during

maintenance and

repairs

Operator Yathrib Water

Directorate No additional costs No additional costs

4

Deterioration of

groundwater

quality

(a) Timely and adequate disposal of debris generated

by maintenance activities and solid and liquid

waste from office building;

Water quality

testing in case of

accidental spills of

hazardous

materials:

pH, Turbidity,

Electrical

Conductivity (EC),

Color, Total

Suspended Solids

(TSS), Total

Dissolved Solids

(TDS), Chemical

Operator Yathrib Water

Directorate No additional costs 500 for water testing

Page 22: REPUBLIC OF IRAQAl -Ahbab Al -Aoul , capacity 10 0 m 3/h Additionally, the intake structure supplying the water to these units is to be refurbished also. The main objective of the

22

No. Potential Impacts Mitigation Measures Monitoring

Responsibility Additional Cost in USD

Implementation Monitoring Mitigation measures Monitoring

Oxygen Demand

(COD), Biological

Oxygen Demand

(BOD),

Polychlorinated

Biphenyls (PCBs)

5 Damage to fauna,

flora

(a) Adequate waste disposal;

(b) Draining of ponds;

(c) Re-vegetation with the plants native to the area

Monthly

inspection:

Condition of

the manholes

and ditches;

Level of re-

vegetation;

Absence of

ponds

Operator Yathrib Water

Directorate No additional costs No additional costs

6

Drinking water

quality issues

during operation

(a) Regular checking for the condition of the storm

water and sewerage networks for the presence of

leaking;

(b) Adequate waste disposal;

(c) Timely draining of ponds to avoid breeding of

insects

Regular water

quality testing

Operator Yathrib Water

Directorate No additional costs No additional costs

Expected additional mitigation costs: No additional costs

Expected monitoring costs: USD 3000

Page 23: REPUBLIC OF IRAQAl -Ahbab Al -Aoul , capacity 10 0 m 3/h Additionally, the intake structure supplying the water to these units is to be refurbished also. The main objective of the

23

Annexes:

Annex 1:

Drinking Water Quality Standard:

Characteristic Maximum Allowable Limit

Natural Characteristics

Color 10 units

Turbidity (NTU) 5 units

Smell acceptable

Taste acceptable

pH value 6.5-8.5

Chemical Characteristics (mg/L)

Arsenic 0.01

Cadmium 0.003

Chrome 0.05

Cyanide 0.02

Fluoride 1

Lead 0.01

Mercury 0.001

Nitrate (NO3) 50

Nitrite (NO2) 3

Selenium 0.01

Aluminium 0.2

Chloride (Cl) 250

Copper 1

Total Hardness (as CaCO3) 500

Iron 0.3

Manganese 0.1

Sodium 200

T.D.S 1000

Sulphate (SO4) 250

Zinc 3

Calcium 50

Magnesium 50

Barium 0.7

Nickel 0.02

Dissolved H.C 0.01

Carbon-chloroform Extracted 0.3

Industrial Detergents 0.3

Phenolic compounds 0.002

Biological Characteristics

Page 24: REPUBLIC OF IRAQAl -Ahbab Al -Aoul , capacity 10 0 m 3/h Additionally, the intake structure supplying the water to these units is to be refurbished also. The main objective of the

24

Characteristic Maximum Allowable Limit

Coliform (100 ml after 24hr at 35oC) <1.1

E.coli (100 ml after 24hr at 44oC) <1.1

Escherichia coli (250 ml after 24hr at

35oC) Zero

Plate count (1ml after 24hr at 35oC) Zero

Pesticides (mg/L)

Organic chloro (chlorinated) 0.7

Organic Phosphorous 0.000005

Multi chloro-diphenolic 0.001

Radiation (Becquerel/litre)

Total Alfa radiation 0.1

Total Beta radiation 1

Air Quality Standard

Pollutant Concentration Averaging Time

CO 10 ppm 8 hours

35 ppm 1 hour

SO2 0.1 ppm 1 hour

0.04 ppm 24 hours

0.018 ppm 1 year

NO2 0.05 ppm 24 hours

0.04 ppm 1 year

O3 0.06 ppm 1 hour

PM10 150 μg/m3 24 hours

PM2.5 65 μg/m3 24 hours

15 μg/m3 1 year

Total Suspended Particles 350 μg/m3 24 hours

150 μg/m3 1 year

Flling Dust 10 t/km2/month -residential zone 30 days

20 t/km2/month - industrial zone 30 days

Hydrocarbons 0.24 ppm 3 hours

Pb 2 μg/m3 24 hours

1.5 μg/m3 3 months

1 μg/m3 1 year

Benzene 0.003 μg/m3 1 year

Dioxin 0.6 pico g/m3 1 year

Page 25: REPUBLIC OF IRAQAl -Ahbab Al -Aoul , capacity 10 0 m 3/h Additionally, the intake structure supplying the water to these units is to be refurbished also. The main objective of the

25

Annex 2: Occupational HSE

There is posted material indicating the nearest police station and hospital (with accident and emergency

facilities).

The contractor must take reasonable steps to prevent unauthorized people accessing the site.

Training on handling of UXO/ERW

Avoid the burning of materials on site.

Provide a first aid kits in different places of the work site with the appropriate number of materials given the

number of workers on site. The locations of the first aid kits will be provided to all workers.

Providing extinguishers on work site.

If work involving the use of flammable materials is being carried out, stop people smoking and do not allow

other work activities involving potential ignition sources to take place nearby.

Providing site boundaries by installing suitable physical boundaries (barriers, tape or fence).

Marking excavation holes with physical boundaries (barriers, tape or fence)

The contractor should put up barriers or covers in the area of openings and excavations.

Store building materials (such as pipes, manhole rings, and cement bags) so that they cannot topple or roll over.

Keep walkways and stairways free of tripping hazards such as trailing cables, building materials, and debris.

Everyone who works on any site must have access to adequate toilet and washing facilities, a place for

preparing and consuming refreshments, and an area for storing and drying clothing and personal protective

equipment (PPE).

Contractor to ensure PPE (personal protective equipment) is used by all workers on site.

Materials and equipment are tidily stacked, protected and covered where necessary. Additionally, there is

adequate space for new materials to be stored in secured covered areas to avoid damage, theft, and to protect

these items from weather conditions.

Scaffolding for work in elevated areas such as ceiling painting should comply with the OSHA “General

Requirements for Scaffolds §1926.451”

Page 26: REPUBLIC OF IRAQAl -Ahbab Al -Aoul , capacity 10 0 m 3/h Additionally, the intake structure supplying the water to these units is to be refurbished also. The main objective of the

26

Annex 3: Chance Find Procedure

Chance find procedures will be used as follows:

Stop the construction activities in the area of the chance find;

Delineate the discovered site or area;

Secure the site to prevent any damage or loss of removable objects. In cases of removable

antiquities or sensitive remains, a night guard shall be present until the responsible local

authorities and the Ministry of Culture take over;

Notify the supervisory Engineer who in turn will notify the responsible local authorities and the

Ministry of Culture immediately (within 24 hours or less);

Responsible local authorities and the Ministry of Culture would be in charge of protecting and

preserving the site before deciding on subsequent appropriate procedures. This would require a

preliminary evaluation of the findings to be performed by the archeologists from the Department

of Antiquities and the Ministry of Culture (within 72 hours). The significance and importance of

the findings should be assessed according to the various criteria relevant to cultural heritage;

those include the aesthetic, historic, scientific or research, social and economic values;

Decisions on how to handle the finding shall be taken by the responsible authorities from DA and

the Ministry of Culture. This could include changes in the layout (such as when finding an

irremovable remain of cultural or archeological importance) conservation, preservation,

restoration and salvage;

Implementation for the authority decision concerning the management of the finding shall be

communicated in writing by the Ministry of Culture; and

Construction work could resume only after permission is given from the responsible local

authorities and the Ministry of Culture concerning safeguard of the heritage.

These procedures must be referred to as standard provisions in construction contracts, when applicable.

During project supervision, the Site Engineer shall monitor the above regulations relating to the treatment

of any chance find encountered are observed.

Page 27: REPUBLIC OF IRAQAl -Ahbab Al -Aoul , capacity 10 0 m 3/h Additionally, the intake structure supplying the water to these units is to be refurbished also. The main objective of the

27

Annex 4: Public Consultations

Questionnaire Form in English:

Name of the project:

Location of the project:

Name of the respondent:

Occupation of the respondent:

Date of visit:

1 In your opinion, would the rehabilitation of water/sanitation facilities have positive impact

on the residents of the area?

yes no

2 Are there any claims on private land ownership in the project area? yes no

3 Would there be any damages to income generating crops, trees, and vegetation due to the

rehabilitation activities?

yes no

4 Would there be any losses of income of local residents due to the rehabilitation activities? yes no

5 Would there be any damages whether permanent or temporary which would affect the

livelihood of the residents due to the rehabilitation activities?

yes no

6 Would the rehabilitation activities require relocation of the residents of the area, whether

permanent or temporary?

yes no

7 Is there any usage by local residents of the facilities or land of the facilities by the local

residents?

yes no

8 In your opinion, would there be any negative social impacts due to the rehabilitation

activities?

yes no

9 Would there be any changes to the demographics or social structure in the project area

induced by the rehabilitation activities?

yes no

10 Would there be any damages to the structures or houses induced by the rehabilitation

activities?

yes no

11 Would there be any disturbance to traffic during the rehabilitation activities? yes no

12 Is there any need for warning and directional signage during the rehabilitation activities? yes no

Name and signature of the interviewer:

Page 28: REPUBLIC OF IRAQAl -Ahbab Al -Aoul , capacity 10 0 m 3/h Additionally, the intake structure supplying the water to these units is to be refurbished also. The main objective of the

28

Photos of Interviews

Page 29: REPUBLIC OF IRAQAl -Ahbab Al -Aoul , capacity 10 0 m 3/h Additionally, the intake structure supplying the water to these units is to be refurbished also. The main objective of the

29

Arabic Questionnaire with Responses

Page 30: REPUBLIC OF IRAQAl -Ahbab Al -Aoul , capacity 10 0 m 3/h Additionally, the intake structure supplying the water to these units is to be refurbished also. The main objective of the

30

Page 31: REPUBLIC OF IRAQAl -Ahbab Al -Aoul , capacity 10 0 m 3/h Additionally, the intake structure supplying the water to these units is to be refurbished also. The main objective of the

31

Page 32: REPUBLIC OF IRAQAl -Ahbab Al -Aoul , capacity 10 0 m 3/h Additionally, the intake structure supplying the water to these units is to be refurbished also. The main objective of the

32

Page 33: REPUBLIC OF IRAQAl -Ahbab Al -Aoul , capacity 10 0 m 3/h Additionally, the intake structure supplying the water to these units is to be refurbished also. The main objective of the

33

Page 34: REPUBLIC OF IRAQAl -Ahbab Al -Aoul , capacity 10 0 m 3/h Additionally, the intake structure supplying the water to these units is to be refurbished also. The main objective of the

34

Page 35: REPUBLIC OF IRAQAl -Ahbab Al -Aoul , capacity 10 0 m 3/h Additionally, the intake structure supplying the water to these units is to be refurbished also. The main objective of the

35

Page 36: REPUBLIC OF IRAQAl -Ahbab Al -Aoul , capacity 10 0 m 3/h Additionally, the intake structure supplying the water to these units is to be refurbished also. The main objective of the

36

Page 37: REPUBLIC OF IRAQAl -Ahbab Al -Aoul , capacity 10 0 m 3/h Additionally, the intake structure supplying the water to these units is to be refurbished also. The main objective of the

37

Page 38: REPUBLIC OF IRAQAl -Ahbab Al -Aoul , capacity 10 0 m 3/h Additionally, the intake structure supplying the water to these units is to be refurbished also. The main objective of the

38

Page 39: REPUBLIC OF IRAQAl -Ahbab Al -Aoul , capacity 10 0 m 3/h Additionally, the intake structure supplying the water to these units is to be refurbished also. The main objective of the

39

Page 40: REPUBLIC OF IRAQAl -Ahbab Al -Aoul , capacity 10 0 m 3/h Additionally, the intake structure supplying the water to these units is to be refurbished also. The main objective of the

40

Page 41: REPUBLIC OF IRAQAl -Ahbab Al -Aoul , capacity 10 0 m 3/h Additionally, the intake structure supplying the water to these units is to be refurbished also. The main objective of the

41

Responses to the Questionnaire

#

Na

me

of

the R

esp

on

den

t

Occ

up

ati

on

Gen

der

In y

ou

r o

pin

ion

, w

ou

ld t

he

reh

ab

ilit

ati

on

of

wa

ter/

san

ita

tio

n f

aci

liti

es

hav

e p

osi

tive i

mp

act

on

the r

esi

den

ts o

f th

e a

rea

?

Are t

her

e a

ny

cla

ims

on

priv

ate

la

nd

ow

ner

ship

in

the p

ro

ject

are

a?

Wo

uld

th

ere

be

an

y d

am

ag

es

to i

nco

me g

en

era

tin

g

cro

ps,

tre

es,

an

d v

egeta

tio

n d

ue t

o t

he

reh

ab

ilit

ati

on

acti

vit

ies?

Wo

uld

th

ere

be

an

y l

oss

es

of

incom

e o

f lo

cal

resi

den

ts d

ue t

o t

he

reh

ab

ilit

ati

on

acti

vit

ies?

Wo

uld

th

ere

be

an

y d

am

ag

es

wh

eth

er p

erm

an

en

t

or t

em

po

rary

wh

ich

wo

uld

aff

ect

the l

iveli

hoo

d o

f

the r

esi

den

ts d

ue

to t

he r

eh

ab

ilit

ati

on

acti

vit

ies?

Wo

uld

th

e r

eh

ab

ilit

ati

on

acti

vit

ies

req

uir

e

relo

cati

on

of

the r

esi

den

ts o

f th

e area

, w

heth

er

perm

an

en

t o

r te

mp

ora

ry?

Is t

here

an

y u

sag

e b

y l

ocal

resi

den

ts o

f th

e fa

cili

ties

or l

an

d o

f th

e f

acil

itie

s b

y t

he

loca

l resi

den

ts?

In y

ou

r o

pin

ion

, w

ou

ld t

her

e b

e a

ny n

ega

tiv

e so

cia

l

imp

acts

du

e to

th

e r

eh

ab

ilit

ati

on

act

ivit

ies?

Wo

uld

th

ere

be

an

y c

ha

ng

es

to t

he

dem

ogra

ph

ics

or s

ocia

l st

ru

ctu

re i

n t

he p

roje

ct

are

a i

nd

uced

by

the r

eh

ab

ilit

ati

on

acti

vit

ies?

Wo

uld

th

ere

be

an

y d

am

ag

es

to t

he

stru

ctu

res

or

ho

use

s in

du

ced

by t

he r

eh

ab

ilit

ati

on

acti

vit

ies?

Wo

uld

th

ere

be

an

y d

istu

rb

an

ce t

o t

ra

ffic

du

rin

g

the r

eh

ab

ilit

ati

on

acti

vit

ies?

Is t

here

an

y n

eed

fo

r w

arn

ing a

nd

dir

ecti

on

al

sig

na

ge d

uri

ng t

he r

eh

ab

ilit

ati

on

act

ivit

ies?

Recom

men

da

tio

ns

Yes

NO

Yes

NO

Yes

NO

Yes

NO

Yes

NO

Yes

NO

Yes

NO

Yes

NO

Yes

NO

Yes

NO

Yes

NO

Yes

NO

1 Hameed Qasim Hussein Scholl teacher Male X X X X X X X X X X X X

2 Amer Hashem Hussein Military Male X X X X X X X X X X X X

3 Asaad Geroun Majeed Freelancer Male X X X X X X X X X X X X

4 Mohammad Hashem Hussein Freelancer Male X X X X X X X X X X X X

5 Nashwan Shaker Hashem Student Male X X X X X X X X X X X X

6 Ahmed Taha Hashem Freelancer Male X X X X X X X X X X X X

Page 42: REPUBLIC OF IRAQAl -Ahbab Al -Aoul , capacity 10 0 m 3/h Additionally, the intake structure supplying the water to these units is to be refurbished also. The main objective of the

42

Annex 5: List of Mitigation Measures during Rehabilitation Phase

General Conditions (a) The local construction and environment inspectorates and communities have been notified of upcoming activities

(b) The public has been notified of the works through appropriate notification in the media and/or at publicly accessible sites

(including the site of the works)

(c) All legally required permits have been acquired for construction and/or rehabilitation

(d) The Contractor formally agrees that all work will be carried out in a safe and disciplined manner designed to minimize

impacts on neighboring residents and environment.

(e) Workers’ PPE will comply with international good practice (always hardhats, as needed masks and safety glasses, harnesses

and safety boots)

(f) There is posted material indicating the nearest police station and hospital (with accident and emergency facilities).

(g) The contractor must take reasonable steps to prevent unauthorized people accessing the site.

(h) Training on handling of UXO/ERW

(i) Avoid the burning of materials on site.

(j) Provide a first aid kits in different places of the work site with the appropriate number of materials given the number of

workers on site. The locations of the first aid kits will be provided to all workers.

(k) Providing extinguishers on work site.

(l) If work involving the use of flammable materials is being carried out, stop people smoking and do not allow other work

activities involving potential ignition sources to take place nearby.

(m) Providing site boundaries by installing suitable physical boundaries (barriers, tape or fence).

(n) Marking excavation holes with physical boundaries (barriers, tape or fence)

(o) The contractor should put up barriers or covers in the area of openings and excavations.

(p) Store building materials (such as pipes, manhole rings, and cement bags) so that they cannot topple or roll over.

(q) Keep walkways and stairways free of tripping hazards such as trailing cables, building materials, and debris.

(r) Everyone who works on any site must have access to adequate toilet and washing facilities, a place for preparing and

consuming refreshments, and an area for storing and drying clothing and personal protective equipment (PPE).

(s) Contractor to ensure PPE (personal protective equipment) is used by all workers on site.

(t) Materials and equipment are tidily stacked, protected and covered where necessary. Additionally, there is adequate space for

new materials to be stored in secured covered areas to avoid damage, theft, and to protect these items from weather

conditions.

(u) Scaffolding for work in elevated areas such as ceiling painting should comply with the OSHA “General Requirements for

Scaffolds §1926.451”

(v) Appropriate signposting of the sites will inform workers of key rules and regulations to follow.

Generation, storage, disposal of construction and domestic waste

(a) Waste collection and disposal pathways and sites will be identified for all major waste types expected from excavation,

demolition and construction activities.

(b) Mineral construction and demolition wastes will be separated from general refuse, organic, liquid and chemical wastes by

on-site sorting and stored in appropriate containers.

(c) Construction waste will be collected and disposed properly by licensed collectors

(d) The records of waste disposal will be maintained as proof for proper management as designed.

(e) Whenever feasible Contractor will reuse and recycle appropriate and viable materials (except when containing asbestos)

Deterioration of air quality

(a) During excavation works dust control measures shall be employed, e.g. by spraying and moistening the ground

(b) Demolition debris, excavated soil and aggregates shall be kept in controlled area and sprayed with water mist to reduce

debris dust

(c) During pneumatic drilling or breaking of pavement and foundations dust shall be suppressed by ongoing water spraying

and/or installing dust screen enclosures at site

(d) The surrounding environment (sidewalks, roads) shall be kept free of soil and debris to minimize dust

(e) There will be no open burning of construction / waste material at the site

(f) All machinery will comply with Iraqi emission regulations, shall well maintained and serviced and there will be no

excessive idling of construction vehicles at sites

Increased level of noise

(a) Construction noise will be limited to restricted times agreed to in the permit

(b) During operations the engine covers of generators, air compressors and other powered mechanical equipment shall be

closed, and equipment placed as far away from residential areas as possible

Page 43: REPUBLIC OF IRAQAl -Ahbab Al -Aoul , capacity 10 0 m 3/h Additionally, the intake structure supplying the water to these units is to be refurbished also. The main objective of the

43

Disruption of the runoff water and drainage systems

(a) Drainage / canalization systems will be reconstructed according to good engineering practice, including appropriate

dimensions, clarifier basins, and connection to treatment facilities as required

(b) Storm water drainage systems will be designed and constructed as not to silt, pollute, block or otherwise negatively impact

natural streams, rivers, ponds and lakes; including during construction activities

(c) There will be procedures in place for prevention of and rapid response to accidental spills of fuels, lubricants and other toxic

or noxious substances, and for their recovery and appropriate disposal

(d) Construction vehicles and machinery will be washed only in designated areas where runoff will not pollute natural surface

water bodies

(e) The site will establish appropriate erosion and sediment control measures such as e.g. hay bales and / or silt fences to

prevent sediment from moving off site and causing excessive turbidity in canalization and nearby streams and rivers

Deterioration of groundwater quality

(a) Sewage from construction offices and rest areas will be collected and transferred by trucks to the nearest sewage treatment

plant

(b) There will be no unregulated extraction of groundwater, nor uncontrolled discharge of process waters, cement slurries, or

any other contaminated waters into the ground or adjacent streams or rivers;

(c) the Contractor will obtain all necessary licenses and permits for water extraction and regulated discharge into the public

wastewater system.

Damage to fauna, flora

(a) Adjacent wetlands and streams shall be protected from site run-off and siltation with appropriate measures

(b) There will be no unlicensed borrow pits, quarries or waste dumps in adjacent areas;

(c) Monitor the construction crew and provide punitive measures for illegal hunting and/or fishing;

(d) Provide the crew with fuel for cooking to avoid burning of natural materials;

(e) Apply waste management plan

(f) Provide regular dredging around the cofferdams for the intake structure to ensure sufficient depth and avoid creation of

whirlpools around the cofferdam which will cause increased turbidity of the water.

Disruption of traffic

(a) In compliance with national regulations the Contractor will insure that the construction site is properly secured and

construction related traffic regulated.

(b) The site will be clearly visible and the public warned of all potential hazards by signposting and barriers / fencing

(c) Traffic management system and staff training, especially for site access and near-site heavy traffic. Provision of safe

passages and crossings for pedestrians where construction traffic interferes.

(d) Adjustment of working hours to local traffic patterns, e.g. avoiding major transport activities during rush hours or times of

livestock movement

(e) If required, active traffic management by trained and visible staff at the site for safe passage for the public

(f) Ensuring safe and continuous access to all adjacent office facilities, shops and residences during construction

Deterioration of health & safety conditions (a) Provide adequate signage to prevent accidental falling into open areas

(b) Fencing of the work areas

(c) Provision of safe crossing rumps over the excavated trenches for residence access and for livestock crossing;

(d) Keep walkways free of tripping hazards such as trailing cables, building materials, and debris.

(e) Deployment of HSE procedures for the construction personnel as described in point: General Conditions.

Social Impacts (a) Reducing impacts on the community through community and neighbour engagement.

(b) In cases of where there are minority communities speaking a different language in the area or working on site, notices are in

the common local language.

(c) Provide the proper GRM for handling complaints

Page 44: REPUBLIC OF IRAQAl -Ahbab Al -Aoul , capacity 10 0 m 3/h Additionally, the intake structure supplying the water to these units is to be refurbished also. The main objective of the

44

Annex 6: List of Mitigation Measures during Construction Phase in Arabic

: قائمة بإجراءات تخفيف المخاطر خالل أعمال إعادة التأهيل:5ترجمة الملحق

الشروط العامـــــة: الجهات الرقابية المسؤولة عن أعمال التشييد والبيئة بالنشاط المرتقب للمشروع.لقد أبلغت .أ

باألعمال المرتقبة من خالل الوسائط اإلعالمية وكذلك / أو المواقع اإللكترونية ومن لقد أبلغ الجمهور .ب

ضمنها موقع رب العمل.

بناء و/ أو إعادة التأهيل.إصدار كافة الرخص القانونية واألصولية إلجازة أعمال ال استكمالتم .ت

وافق المقاول رسميا على أن ينجز األعمال وفق ضوابط السالمة لتقليل المؤثرات على المقيمين .ث

بالجوار وعلى البيئة.

مع التطبيقات العالمية )دائما بقبعة صلبة، أقنعة حسب الحاجة، نظارة قأن تكون وقاية العاملين تتطاب .ج

للسالمة(.السالمة، طاقم العمل ، وجزم

والحوادث(. الطوارئلوحات معلقة لبيان أقرب مركز شرطة وأقرب مستشفى )مع توفير تسهيالت .ح

أن يتخذ الخطوات المعقولة لمنع دخول غير المخولين إلى موقع العمل. لالمقاوعلى .خ

وتلك غير المنفلقة. لالنفجارالتدريب على التعامل مع المواد الحربية القابلة .د

اد داخل موقع العمل.تجنب حرق المو .ذ

تجهيز مناطق مختلفة من موقع العمل بأطقم )اإلسعافات األولية( ومجهزة بعدد مالئم من المحتويات .ر

تتناسب مع عدد العاملين. ينبغي إعالم كافة العاملين في الموقع بأمكنة أطقم )اإلسعافات األولية(.

الحريق. بمطافئتجهيز موقع العمل .ز

في األعمال باالستمراريجب منع التدخين وعدم السماح لالشتعالمواد قابلة استعمالفي حالة .س

قدحات نارية. انبعاث الموقعية المجاورة األخرى ذات الصلة بمصادر

تحديد حدود الموقع بنصب مواد محددة )حواجز، أشرطة أو أسيجة(. .ش

تأشير مواقع الحفر بنصب مواد محددة )حواجز، أشرطة أو أسيجة(. .ص

المقاول أن يضع حواجز أو أغطية لمساحات الفتحات والحفريات.على .ض

انقالبها خزن مواد البناء )كاألنابيب، إطارات أغطية المجاري، وأكياس السمنت( بشكل يمنع .ط

ودحرجتها(.

تصان المماشي والساللم خاوية من العواثر الخطرة كاألسالك المسحوبة والمواد اإلنشائية واألنقاض. .ظ

، واالغتسالالعاملين وفي أية منطقة عمل سهولة الوصول إلى مرافق قضاء الحاجة تكون لكافة .ع

وحيز لتحضير وتناول المرطبات ومساحة لخزن وتجفيف المالبس وعدة الوقاية الشخصية.

وعدة الوقاية الشخصية من جميع العاملين في الموقع. باستخدامعلى المقاول التأكد .غ

والحماية من التلف وتغطى أينما كان ضروريا، باإلضافة تحدد أمكنة تكدس المواد والمعدات بعناية .ف

خزن مغطاة لمواد جديدة لتجنب تلفها، وسرقتها وكذلك لحمايتها من الظروف المناخية.

يجب أن تذعن صالحية السقاالت )اإلسكالت( المستعملة للوصول إلى مناطق العمل المرتفعة كصبغ .ق

(.1926.451للسقاالت )العامة المتطلباتالسقوف لنشرة

العاملين بالقواعد الرئيسية والتعليمات الواجب إتباعها. إلبالغلوائح مالئمة ومعلقة في مناطق العمل .ك

Page 45: REPUBLIC OF IRAQAl -Ahbab Al -Aoul , capacity 10 0 m 3/h Additionally, the intake structure supplying the water to these units is to be refurbished also. The main objective of the

45

جودة الهواء:

انبعاثات المركبات . على المقاول أن يستخدم اآلليات و المعدات بشكل سليم و يتأكد من صيانتها

المركبات الغير ضروري .على المقاول أن يقلل من تشغيل

. أن يطفئ المحركات بعد استخدامها

الغبار أن يقلل من انبعاث الغبار من المواد )مثل الرمل و اإلسمنت( و أنشطة البناء باستخدام أغطية أو

تخزين أو معدات تحكم و زيادة محتوى الرطوبة

حصى, رمل, اسمنت( اذا كان تحضير اإلسمنت قبل الذهاب الى الموقع للحد من عملية نقل المواد(

ذلك ممكنا

تقليل الغبار الناتج عن حركة المركبات باستخدام رش المياه حسب الحاجة

تجنب حرق المواد في الموقع

اطفاء المحركات بمجرد االنتهاء من استخدامها

االنبعاثات الخطرة تجنب تخزين المواد الخطرة في األماكن المفتوحة بدون غطاء الئق

تهوية كافية في مناطق العمل توفير

إدارة الضوضاء و االهتزازات تجنب أو التقليل من التنقل في المناطق المجتمعية

اطفاء المحركات بمجرد االنتهاء من استخدامها

على المقاول أن يقلل من تشغيل المركبات الغير ضروري

تقليل ضوضاء المعدات

ون مع معدات اهتزازية أو صاخبةفحوصات طبية اضافية للموظفين الذين يتعامل

إدارة مجاري المياه الموسمية )خطة تصريف المياه( على المواد األولية المستخدمة في البناء و التي ممكن انجرافها بمجرى المياه الموسمية أن يتم

تواجدها و تخزينها في أماكن بعيدة عن مجاري المياه الموسمية

عمال بحيث تتجنب المواسم المطرية )مثال في المواسم الجافة( و ان كان مناسبا أو ممكنا جدولة األ

تعديل النشاطات أثناء األمطار الغزيرة و الرياح العاتية

التربة التخلص من التربة الملوثة بنقلها بالشاحنات الى أقرب مكب مخول

و أكياس الرمل اذا كان الصرف السطحي يعيق عمليات البناء, ممكن استخدام الخنادق و السدود و / أ

لتحويل مسار المياه عن مواقع الحفر

على مهندس الموقع أن يراقب عن كثب األحوال الجوية يوميا. لن يكون هناك أي اعمال انشائية في

أجواء يسودها المطر الشديد أو الرياح القوية

النفايات الصلبة و الخطرة الحفاظ على الموقع نظيفا و منظما

مواد أو حطام ملقاة بشكل عشوائي في الموقع أو في محيط الموقع التأكد من عدم وجود .أ

يجب فحص نظافة المركبات بشكل دوري )فحص شامل و التأكد من عدم التسريب( .ب

حرق النفايات ممنوع كليا

التقليل من نفايات البناء ذات الصلة بالبناء داخل الموقع و نفايات التصنيع خارج الموقع

Page 46: REPUBLIC OF IRAQAl -Ahbab Al -Aoul , capacity 10 0 m 3/h Additionally, the intake structure supplying the water to these units is to be refurbished also. The main objective of the

46

المواد في الموقع متى أمكن ذلكاعادة استخدام

متابعة كمية النفايات اإلنشائية في الموقع للتأكد من عدم تأثيرها على الموقع و المنطقة المحيطة

المخلفات ال تعيق الطرق .أ

يتم جمع المخلفات اإلنشائية في مكان محدد في الموقع .ب

رح لتفادي تجمع النفايات داخل على المقاول ازالة المخلفات اإلنشائية بشكل دوري ألقرب مكب مص

الموقع

على جميع العاملين التقيد بعدم رمي النفايات

وجود خزان للصرف الصحي للنفايات السائلة السكنية من معسكر الموقع و التي يجب التخلص منها

دوريا الى محطات المعالجة

المواد الخطرة مثل زيوت التشحيم و الزيوت الهيدروليكية تزويد الموقع بحاويات لحفظ الوقود و المواد األخرى

استخدام أرضية منيعة )غير قابلة للتسريب( في مناطق تزويد الوقود و التحويل

تزويد آليات لمكافحة التسرب و أعمال التنظيف و تدريب فريق العمل على استخدامها بشكل آمن

كما هو مذكور في تزويد مرافق الصرف الصحي المناسبة لخدمة جميع العاملين في الم( وقعHSE)

لن تستخدم الدهانات التي تحتوي على المواد السامة أو مذوبات أو دهانات ذات قاعدة الرصاص

التنوع البيولوجي تدريب فريق العمل على التأثير الناتج عن خلخلة أو تدمير البيئة

بشكل غير قانوني مراقبة فريق العمل و توفير تدابير عقابية ضد الصيد و / أو صيد السمك

الى حرق مواد طبيعية اتوفير وقود لفريق العمل ليتمكنوا من الطهي و حتى ال يلجؤو

تطبيق خطة ادارة النفايات

أعمال التجريف الدورية في مناطق السحب حول السدود المؤقتة لضمان العمق الكافي لمنع الدوامات

حول السدود و التي تتسبب بعكر الماء

المنع منعا باتا من التخلص من أي من النفايات بإلقائها في النهر

لحماية الطبيعة و األحياء الهشة في مناطق السحب, على أعمال البناء أن تبدأ في الموسم الجاف حيث

منسوب مياه النهر في أدنى مستواها و موسم التكاثر قد قضى

قل متر واحد تحت سطح الماء و سرعة التدفق ال يجب على بناء السحب تحت الماء أن يكون على األ

متر/الثانية لتجنب سحب األسماك الصغيرة 1.5تزيد عن

الطبوغرافيا و التدفق السطحي مناطق لتخزين مواد البناء يجب أن تتواجد في الموقع و يجب أن ال تكون في مسار المياه لمنع

%1.5االنجرافات و يجب أن تكون على أرضيات بميول أقل من

يجب تحديد ساعات العمل في األجواء الممطرة

يجب صيانة المعدات و اآلالت بشكل دوري للتأكد من عدم انسكاب المواد الخطرة

يجب اعادة زراعة المناطق التي انتهى بها العمل

يجب التخلص من النفايات الصلبة و السائلة و بشكل دوري في األماكن المخصصة لذلك

حركة المرور اشارات تحذيرية في الموقع وضع

تعليم ممرات المشاة اآلمنة بحيث ال يعترضها مواد البناء .أ

Page 47: REPUBLIC OF IRAQAl -Ahbab Al -Aoul , capacity 10 0 m 3/h Additionally, the intake structure supplying the water to these units is to be refurbished also. The main objective of the

47

مدخل و مخرج الموقع معلمين بشكل واضح للزوار و لسائقي التوصيل .ب

مكتب استعالمات الموقع واضحة و ارشادية و اذا لم توجد فيجب اصطحاب الزوار شخصيا .ج

لمكتب االستعالمات

مركبات الزوار و العاملين خارج منطقة العمل تحديد أماكن اصطفاف

تجنب أو قلل من السياقة عبر المناطق السكنية

نظام ادارة السير و تدريب العمال و خصوصا عند مداخل الموقع و عند اختناق السير قرب الموقع

ساعات تعديل ساعات العمل لتناسب حركة المرور المحلية )مثل تجنب عمليات النقل الثقيلة أثناء

الذروة أو عند تحرك الماشية

الصحة و السالمة وضع اشارات تحذيرية كافية لمنع حوادث مثل السقوط الفجائي في المناطق المفتوحة

( تسييج منطقة العملHSE)

وضع اشارات واضحة لإلدالل على أقرب مركز أمني و مشفى به قسم حوادث و طوارئ

على المقاول اتخاذ التدابير االزمة لمنع الزوار الغير مصرح لهم بالدخول للموقع

التدريب على معالجة أسلحة الحرب الغير منفجرة

تجنب حرق المواد في الموقع

وضع حقائب اسعافات أولية في أماكن مختلفة في الموقع بكميات تتناسب مع عدد العاملين في الموقع

ين في الموقع عن مواقع حقائب االسعافات األولية . يجب اعالم العامل

وضع طفايات حريق في الموقع

اذا استوجب العمل على استخدام مواد سريعة االشتعال يجب منع التدخين في المنطقة و العمل على

عزل المنطقة من كل ما قد يحدث شرارة

صق أو السور(تحديد مناطق المشروع بحدود ملموسة )مثل الحواجز أو الشريط الال

)تحديد مناطق الحفر بحدود ملموسة )مثل الحواجز أو الشريط الالصق أو السور

على المقاول أن يضع عالمات تحذيرية أو أغطية على األماكن المفتوحة و أماكن الحفر

تخزين مواد البناء )أنابيب, أغطية مناهل, أكياس أسمنت( بشكل عملي حتى ال تنزلق المواد و تتبعثر

بقاء ممرات المشاة و الدرج خالية من مواد البناء و الحطام ا

كل من يعمل في الموقع له الحق باستخدام حمامات و مغاسل كافية, و مكان للشرب و مكان لتغيير و

(PPEتجفيف المالبس و لتخزين أدوات الحماية الشخصية )

على المقاول العمل على جعل العمال استخدام أدوات الحماية الشخ( صيةPPEفي الموقع )

يجب تخزين المواد و اآلليات بشكل منظم و حمايتها و تغطيتها ان لزم األمر. و كذلك يجب التأكد من

وجود أماكن كافية لتخزين المواد الجديدة و حمايتها من التلف و السرقة و عوامل الطقس

ء األسقف أن تمتثل لشروط يجب على السقاالت المعلقة و المستخدمة في األماكن المرتفعة مثل طال

OSHA (1926.451)المتطلبات األساسية للسقاالت

التعامل مع الشكاوي .تقليل الضرر على المجتمع المحلي من خالل التفاعل مع المجتمع و الجار

,في حال وجود أقليات في المجتمع المحلي المجاور أو يعملون في المشروع ممن يتكلمون لغة أخرى

م كتابيا بلغتهم المحليةيجب مخاطبته

الموارد العينية و الثقافية في حال االكتشاف العرضي , أوقف جميع األعمال في الموقع و تواصل مع األجهزة المعنية خالل

ساعة 24

Page 48: REPUBLIC OF IRAQAl -Ahbab Al -Aoul , capacity 10 0 m 3/h Additionally, the intake structure supplying the water to these units is to be refurbished also. The main objective of the

48

مع االلتزام قم بتدريب الكادر على طريقة التعامل المثلى في حال االكتشافات العرضية

باالشتراطات التالية:

الصدفة طريق عن األثرية االكتشافات على الخاصة بالعثوراإلجراءات

على النحو التالي: الصدفة طريق عن األثرية االكتشافات على يتم استخدام اإلجراءات الخاصة بالعثور

وقف أنشطة البناء في منطقة العثور على اكتشافات أثرية عن طريق الصدفة .أ

المكتشفةتحديد الموقع المكتشف أو المنطقة .ب

تأمين الموقع لمنع وقوع أية أضرار أو فقدان األشياء المنقولة. وبالنسبة لآلثار القديمة المنقولة أو .ج

اآلثار الحساسة، سيتم تعيين حارس ليلي لحيين قيدوم السيلطات المحليية المسيؤولة ووزارة الثقافية

الستالمها

السييلطات المحلييية المسييؤولة إخطييار المهنييدس المشييرف الييذي يقييوم بييدوره علييى الفييور بإخطييار .د

ساعة أو أقل( 24ووزارة الثقافة )في خالل

تكيون السييلطات المحليية المختصيية ووزارة الثقافية مسييؤولة عيين حمايية وحفييظ الموقيع قبييل اتخيياذ .ه

قرار بشأن اإلجراءات المالئمة الحقا. ويتطلب ذلك إجراء تقييم أولي للمكتشيفات مين قبيل خبيراء

سياعة(. ويجيب تقيييم أهميية المكتشيفات طبقيا للمعيايير المختلفية 72فية )خيالل اآلثار بوزارة الثقا

التيييي تشيييمل القيمييية الجماليييية والتاريخيييية والعلميييية والبحثيييية واالجتماعيييية للتيييراث الحضييياري

واالقتصادية

يتم اتخاذ القرارات المعنية بكيفية التصيرف فيي المكتشيفات مين قبيل السيلطات المختصية ووزارة .و

ويمكن أن يتضمن ذلك تغييرات في الشكل والتصيميم )مثلميا هيو الحيال عنيد العثيور عليى الثقافة.

آثار ثقافية غير قابلة للنقل أو ذات أهمية أثرية( والحفظ والصيانة واالستعادة واإلنقاذ

تقوم وزارة الثقافة بتقديم بييان كتيابي حيول تنفييذ القيرار المتخيذ مين قبيل السيلطة المختصية بشيأن .ز

كتشافات التي تم العثور عليهاإدارة اال

ال يمكن استئناف أعمال البناء إال بعد الحصول على تصريح بذلك من السلطات المحلية المختصة ووزارة

الثقافة من أجل حماية التراث.