report: offsite groundwater monitoring plan tier 1 ... · the offsite ground water monitoring plan...

108
0000055 EPA Region 5 Records Ctr. 227917 OFFSITE GROUND WATER MONITORING PLAN TIER 1 BENNETT'S DUMP BLOOMINGTON, INDIANA Prepared For: Westinghouse Electric Corporation Environmental Services Division Waltz Mill Site Madison, Pennsylvania Prepared By: Westinghouse Environmental Services Post Office Box 1308 Gary, North Carolina 27512 and Blasland & Bouck Engineers, P.C. 6723 Towpath Road Syracuse, New York 13214 April 1989

Upload: others

Post on 17-Jul-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

0000055

EPA Region 5 Records Ctr.

227917

OFFSITE GROUND WATERMONITORING PLAN

TIER 1BENNETT'S DUMP

BLOOMINGTON, INDIANA

Prepared For:

Westinghouse Electric CorporationEnvironmental Services Division

Waltz Mill SiteMadison, Pennsylvania

Prepared By:

Westinghouse Environmental ServicesPost Office Box 1308

Gary, North Carolina 27512

and

Blasland & Bouck Engineers, P.C.6723 Towpath Road

Syracuse, New York 13214

April 1989

Page 2: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

Environmental Services MadlSDn

BP-WP-CD-89-033

• April 18, 1989

Mr. R. KarlUS EPARegion 5230 S. Dearborn Ave.Chicago, IL 60604

SUBJECT: Offsite Ground Water Monitoring Plan; Tier 1Winston-Thomas Facility, Bennett's Dump

Dear Mr. Karl:

The subject documents are enclosed for your review and approval. Thesedocuments fulfill the requirements set forth in Paragraph 74(b)(l) of theConsent Decree.

Unlike the previous submittal, the Consent Decree schedule necessitatesthat the Tier 1 Plans be submitted prior to the Onsite Plans for these twosites. While the Consent Decree allows an additional 60 days for OnsitePlan submittal, Westinghouse will endeavor to expedite delivery of theonsite plans to facilitate the review process.

Once the plans have been approved, Westinghouse will initiate discussionswith the offsite property owners to gain legal and physical access.

If you have any questions or comments regarding these documents, pleasecontact James Narkunas at 919-481-0397.

Sincerely,

Carl A. AndersonBloomington Project Manager

NJ/lel

ft division of Westinghouse Electric Corpoiation

Page 3: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

OFFSITE GROUND WATERMONITORING PLAN

TIER 1BENNETT'S DUMP

BLOOMINGTON, INDIANA

Prepared For:

Westinghouse Electric CorporationEnvironmental Services Division

Waltz Mill SiteMadison, Pennsylvania

Prepared By:

Westinghouse Environmental ServicesPost Office Box 1308

Gary, North Carolina 27512

and

Blasland & Bouck Engineers, P.C.6723 Towpath Road

Syracuse, New York 13214

April 19S9

Page 4: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

OFFSITE GROUND WATER MONITORING PLANTIER i

BENNETT'S DUMPBLOOMINGTON, INDIANA

Prepared for:

Westinghouse Electric CorporationEnvironmental Services Division

Waltz Mill SiteMadison, Pennsylvania

Prepared by:

Westinghouse Environmental ServicesP.O. Box 1308

Gary, North Carolina 27512

and

Blasland & Bouck Engineers, P.C.6723 Towpath Road

Syracuse, New York 13214

April 1989

Page 5: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

PREFACE

This Offsite Ground Water Monitoring Plan for Bennett's Dump was prepared

at: the conclusion of the site's Supplemental Hydrogeologic Investigation. As

specified in Paragraph 74 (b)(l) of the Consent Decree, a plan describing the

proposed Tier 1 wells is to be submitted within 30 days of completing the

Supplemental Hydrogeologic Investigation. The Offsite Ground Water Monitoring

Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due

90 days after completion of the Supplemental Hydrogeologic Investigation. Since

this sequence of plan submittal is contrary to earlier practice, this Offsite

%•/Ground Water Monitoring Plan is comprised of two volumes. The first volume is

the Data Evaluation. It provides the results of the Supplemental Hydrogeologic

Investigation and was prepared by Blasland & Bouck Engineers, P.C. of Syracuse,

Now York. The Data Evaluation includes the following information as proposed

Jin Task 3.2 of the Supplemental Hydrogeologic Investigation Plan for the Winston-

Thomas Facility and Bennett's Dump:

o A presentation of the work efforts performed during the SupplementalHydrogeologic Investigation.

% _, o Detailed logs of Phase 2 wells, borings, and corings.

o Geophysical logs.

o The results of permeability testing.

o Ground water analytical results.

o Ground water elevation contour maps.

o Geologic cross-sections.

Tine second volume is entitled Offsite Monitoring Well Network and was prepared

by Westinghouse Environmental Services of Gary, North Carolina. The Offsite

Page 6: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

Monitoring Well Network includes a description of the wells in the offsite

monitoring well network, reasons for selecting the wells, and a map showing the

proposed well locations.

11

Page 7: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

LEGEND

• GROUND-WATER MONITORING WELL

" S T R E A M GAUGE

(72341 ' ) GROUND-WATER ELEVATION 8/2?/67

726* ' GROUND-WATER CONTOUR LINE

o to1 no1

"

,,...4--

_ •-."•

. _

!_ - t fmj ta BENNETT'* DUMP

GROUND-WATER CONTOUR MAPAUGUST 22, 1987

5A

Page 8: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

s ' ^ , :.w ' '<;; ,;t^r: -•'-/,.

W T,-

^

^-e1

fi-<-

0.5 ACRE FILL AREA

Md

LEGEND

A APPROXIMATE SEEP LOCATIONS

/\ CROSS SECTION LOCATION

Mw"'* GROUND-WA ER MONITORING WELL

GS- IM STREAM GAUGE

! LIMITS OF FILL AREA (APPROXIMATE)

BENNETT'S DUMP

SITE LOCATION MAP

1

Page 9: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

Pi B - T n u l 0 . « 7 7.] 0.30 1.1Ii'i'bt

ND 0 .11

NO IE ND • NO DETECTIONNA - NOT APPLICABLE

iUtUND * 90UOL

BENNETT'S DUMP

PCB CONCENTRATIONSIN GROUND-WATER

Page 10: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

r-750

-740

-730

r - -720

680

-710

-700

-690

680

• iu"iZONTAL SCALE

v^ _ *p' IZ^O'

h*J Ai f» L*i(^( RH^ITID t'CtPTASWCMi 4fiUM4B S*Cf«>i '300 SUH^%*~M

Inchorgeof

Designed by __

Of own by

Checked by :

BENNETT'S DUMP

GEOLOGIC CROSS SECTION A-A1

^

File No

Dole

[ ) « ^ No

4A

Page 11: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

g

B

750-

740-

730-

720-

710-

700-

690-

680-

HONEf COHO

GRIT/ ,1

I '

GHADCS MICfUTIC

B1

-750

-740

-730

-720

-710

-700

-690

-680

HQF I/UN1AL SCALE

0 «0' I2O'

^ . E^sr"

In charge of

Designed by

[>awn by

Checked by

SLASLAND » IOUCKENOINEERS, P.O.

BENNETT'S DUMP

GEOLOGIC CROSS SECTION B-B'

File No

Dole

[>*U fJO

4B

Page 12: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

FIGURE 4C

UJUJ

zo

IUJ_lUJ

YELLOW/KED SILTYI—~-T_---^ CLAY

GRAY LIMESTONE(SALEM LIMESTONE)

710-

700-

690-

-700

-690

680 680

BENNETTS DUMP

GEOLOGIC CROSS SECTION C-C1

HORIZONTAL SCALE

0 60' 120'

BLASLAND fc BOUCKENGINEERS, P.O.

Page 13: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

LEGEND

• GROUND-WATER MONITORING WE'LL

H S T R E A M GAUGE

(720 73') GROUND-WATER ELEVATION 9/7/86

72Q1 GROUND-WATER CONTOUR LINE

BENNETT'S DUMP

GROUND-WATER CONTOUR MAPSEPTEMBER 7, 1988

5E

Page 14: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

VOLUME 2

OFFSITE MONITORING WELL NETWORKTIER 1

BENNETT'S DUMPBLOOMINGTON, INDIANA

Prepared for:

Westinghouse Electric CorporationEnvironmental Services Division

Waltz Mill SiteMadison, Pennsylvania

Prepared by:

Westinghouse Environmental ServicesP.O. Box 1308

Gary, North Carolina 27512

April 1989

Page 15: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

TABLE OF CONTENTS

Section No.

1

1.11.21.31.4

2

3

4

5

5.15.25.3

6

7

8

Title

INTRODUCTION

BACKGROUNDCONSENT DECREE REQUIREMENTSMONITORING FREQUENCYDOCUMENT OVERVIEW

TIER 1 DESCRIPTION

HYDROGEOLOGIC FRAMEWORK

PRIVATE WELL USE

TIER 1 OFFSITE MONITORING WELLS

WELL LOCATIONSBASES FOR WELL SELECTIONSHYDROLOGIC ZONE OF INFLUENCE

WELL INSTALLATION

WELL ABANDONMENT

WELL REPLACEMENT

Page No.

1

1123

4

6

8

10

101012

13

14

15

REFERENCESFIGURESAPPENDIXPLATE (In Pocket)

Page 16: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

SECTION 1

INTRODUCTION

1.1 BACKGROUND

This plan addresses the Tier 1 offsite ground water monitoring wells

selected for Bennett's Dump.

The objective of offsite ground water monitoring at Bennett's Dump is to

confirm the adequacy of the remediation and demonstrate the acceptability of

the final conditions such that active controls are no longer needed (Consent

Decree, Section XIII, Paragraph 69[c]).

Offsite ground water monitoring will be performed within a three-tiered

network of monitoring wells. The wells will be installed in an area between

Be'.nnett's Dump onsite boundary and an imaginary boundary circumscribed about

the facility at a distance of 5,000 feet from the onsite boundary. Tier 1 is

the area extending outward 1,000 feet beyond the onsite boundary; Tier 2

identifies the area located between 1,000 and 2,500 feet from the onsite

boundary; and Tier 3 includes the area located between 2,500 and 5,000 feet from

v.he onsite boundary (sse Plate 1) . Tier completion will occur successively,

beginning with Tier 1. All wells within a particular tier will be installed and

monitored before installation of the next tier of wells is initiated. Data

collected from the earlier tier(s) will be utilized in selecting well locations

for the subsequent tier.

1.2 CONSENT DECREE REQUIREMENTS

The bases for selecting the offsite monitoring well locations are specified

in Paragraph 74(b) of the Consent Decree (Section XIII). Specifically, "the

Page 17: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

locations of all offsite wells shall be selected based on the preferential flow

of ground water from each site, the lithologies representative of the ground

water system at each site, results of the private well user survey, and

monitoring completed to date at each site". For interpretive purposes,

preferential ground water flow paths are those flow lines demonstrated by

currently available data, such as, ground water levels, potentiometric surface

maps, existing wells with a history of rapid hydraulic response, lineaments, and

tracer test results, as applicable. Monitoring completed to date includes water

Ipvel measurements and PCB analytical results from wells installed onsJte and

from private wells to the extent those data are available and relevant.

In addition to specifying the bases for well selection, the Consent Decree

also specifies the number of offsite wells required for specific sites in Table

2 of Exhibit 13. The areas represented by the three tiers are described in

Paragraph 74 of the Consent Decree.

1.3 MONITORING FREQUENCY

The monitoring frequency for the offsite wells is specified in Table 1 of

Exhibit 13. However, in addition to performing monitoring according to the

schedule included in the Consent Decree, Westinghouse has agreed to monitor the

offsite wells as follows. Upon installing a well tier, Westinghouse will sample

ground water from the offsite monitoring wells in that tier following the

procedures specified in Paragraphs 71(a) and (b) of the Consent Decree. After

a.ll tiers have been completed, Westinghouse will sample all offsite monitoring

wells once in conjunction with scheduled onsite well sampling.

Page 18: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

1.4 DOCUMENT OVERVIEW

Volume 2 of the Tier 1 Offsite Ground Water Monitoring Plan is organized

into eight sections including this introduction which is Section 1. Section 2

provides a general description of the Tier 1 area around Bennett's Dump. An

interpretation of the hydrogeology based on the data evaluation provided in

Volume 1 of the plan is provided in Section 3. Section 4 presents a discussion

of private well use within 5,000 feet of the facility.

The wells selected for the Tier 1 offsite monitoring well network are

discussed in Section 5. In that section, the proposed locations of the wells

are described and data considered during the selection process are discussed.

The concept of the hydrologic zone of influence and its relation to the Tier 1

wells is also addressed. Section 6 provides an overview of the procedures for

installing the wells proposed for the Tier 1 monitoring well network. Section

7 specifies the procedures to be followed in abandoning the offsite wells.

Lastly, Section 8 discusses a well replacement protocol in the event a well is

damaged beyond repair or is otherwise rendered unusable for collection of a

representative sample.

Page 19: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

SECTION 2

TIER 1 DESCRIPTION

Plate 1 illustrates the Bennett's Dump site and the tier areas which

encircle it. Excavation at the site will occur in three areas, the main fill

area, the 1/2-acre fill area, and the satellite fill area as illustrated in the

E'ata Evaluation (volume 1). The shaded portion on Plate 1 represents the area

enclosed by a line which circumscribes the three areas scheduled for remediation.

The tier area around Bennett's Dump is illustrated by the innermost dashed line

circumscribed about the three proposed remediation areas at a distance of 1000

feet.

The Tier 1 area encompasses approximately 160 acres and is elongated in a

north-south direction reflecting the shape of the boundary enclosing the three

individual areas at Bennett's Dump scheduled for remediation. The Tier 1 area

is approximately 3600 feet long from north to south and about 2800 feet wide from

east to west.

Topography within the Tier 1 area is characterized by the north-south

trending floodplain and valley side slopes of Stout Creek. Elevations of the

floodplain range from about 705 feet above mean sea level (msl) at the northern

boundary of the Tier 1 area to about 745 feet above msl at the southern limit.

The valley sides exhibit slopes ranging from 2 to 18 percent and rise up from

the floodplain toward the east and west attaining maximum elevations within the

Tier 1 area of about 810 feet above msl and 790 feet above msl, respectively.

The side slopes within the Tier 1 area represent the lower portions of two

moderately broad north-south trending ridges located adjacent to Stout Creek.

Relief within the Tier 1 area is approximately 105 feet.

Page 20: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

Quarried areas are evident in the eastern and southern portions of the Tier

1 area. Abandoned open pits of various shapes and sizes are commonplace in these

areas with many of the deeper pits containing water. Waste rock and spoil

material from the former quarrying operations are also found in the quarried

areas.

The primary drainage feature in the Tier 1 area is Stout Creek which flows

from south to north past the western edge of Bennett's Dump. A number of

intermittent streams are tributary to Stout Creek along the segment which flows

through the Tier 1 area. Visual evidence of subsurface drainage in the Tier 1

area is minimal: two possible bedrock seeps were identified within the limits

of the main fill area during the Supplemental Hydrogeologic Investigation.

The Tier 1 area includes largely undeveloped land. Major cultural features

in the area include, in addition to the abandoned quarries, public and private

roadways and a small number of commercial buildings.

Page 21: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

SECTION 3

HYDROGEOLOGIC FRAMEWORK

The characterization of the carbonate aquifer present at Bennett's Dump is

dependent upon the degree of karstification which has occurred. Carbonate

aquifers which have undergone the least amount of solutional modification are

termed diffuse flow systems (White, 1969). Solutional cavities are limited in

size and distribution, often being mainly solution-widened joints and bedding

planes. There is a high degree of interconnection between these small solution

cavities. Associated karst landforms are subdued. The water table is well

defined and discharge is through a large number of small springs and seeps.

Diffuse flow aquifers occur where solutional activities ate retarded by

lithologic factors such as shaley limestones or coarsely crystalline dolomites.

Conduit flow systems are those where a high degree of solutional

modification has localized ground water flows into well integrated series of

conduit networks. Discharge is dendritic and convergent to large springs. Flows

reach velocities of feet per second and are often turbulent. These are largely

gravity flows which are governed mainly by the hydrostatic head, the hydraulic

characteristics of the conduit, and the volume of recharge. Karst landforms are

well developed and human-accessible caves occur.

As illustrated in the Figure 1 adapted from Quinlan and Ewers (1985), the

two flow systems may be thought of as composing the end members of a flow

continuum. Intermediate members may be termed mixed-flow aquifers. Most

carbonate aquifers are characterized by both types of flow and it is the relative

predominance of one type over the other which classifies the aquifer.

In this context the aquifer at Bennett's Dump would be classified as a

mixed-flow system but would fall toward the diffuse end between the Chicago

Page 22: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

dolomites and the Bluegrass aquifer. Karst landforms are subdued and few

sinkholes exist near the site. The water table is well defined and no springs

have been noted along Stout Creek as it flows through the site. Some shale beds

which might serve as lithologic impediments to solutional development were noted

in the geologic logs but the extent of these beds is not known. Reports of

previous quarrying activity indicate ground water seepage entering working pits

along joints and bedding planes; nevertheless, no large volumes of inflow were

reported which would have been indicative of conduits being intercepted.

However, upstream of the site along Stout Creek and its headwater tributaries,

numerous conduit springs have been noted, indicating an integrated system of

network drainage.

It is likely that water recharging at the site is entering a mainly diffuse

flow system and is discharging to Stout Creek as seepage via small, well

integrated, solutional-widened joints and bedding planes. It does not appear

likely that ground water is being conveyed any great distances by trunk conduits.

Page 23: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

SECTION 4

PRIVATE WELL USE

In December 1985, the Indiana University School of Public and Environmental

Affairs (SPEA), under contract to Westinghouse, completed a well water user

survey (Jones et al., 1985). The purpose of the survey was to identify the

location of private wells in use for commercial or residential purposes within

5,000 feet of the boundaries of four sites, including Bennett's Dump.

During the survey, SPEA identified 764 properties within the area of

investigation associated with the Bennett's Dump. Following the survey, SPEA

reported that 76 w%lls we're. in MSB at these properties; however, Table 2 of

their report lists only 74 wells and may reflect the actual number. The survey

did not include the map location of these wells; consequently, Westinghouse

performed a "windshield" survey to locate the wells on USGS topographic maps.

These well locations are illustrated on Plate 1 and labeled numerically from 1

to 73. Three wells were located at number 60 and number 15 was not assigned to

a. well. None of the wells were located within the Tier 1 area.

Table 2 from the SPEA report has been reproduced and the numerical

identifiers added to the respective addresses. A copy of the revised table is

included in the appendix of this document.

In plotting the wells on topographic maps, Westinghouse has determined that

five wells, numbers 27, 29, 35, 72, and 73 are located beyond Tier 3. Therefore,

only 69 of the wells identified in Table 2 of the SPEA report are located within

5,000 feet of the facility boundary.

Following completion of the survey, owners of 65 of the wells allowed SPEA

staff to sample and analyze water from the wells for PCBs. PCBs were not

8

Page 24: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

detected in 58 of the samples (Hites et al., 1986). Water sampled from wells

12, 18, 19, 22, 45, 59, and 68 were reported to contain PCBs at concentrations

oE 0.003, 0.004, 0.005, 0.007, 0.002, 0.003, and 0.402 parts per billion (ppb),

respectively. The residence associated with well number 68 is served by

municipal water, not the well; therefore, Westinghouse requested the owner's

authorization to cap the well, but was denied permission. The reported

concentrations of the other six samples were very low relative to a detection

level of 0.1 ppb referenced in the Consent Decree and to a detection limit, in

the absence of interferences, of 0.065 ppb cited in EPA method SW 846-8080.

Duplicate samples were collected from all wells; however, only samples showing

PCB concentrations greater than 0.1 ppb had duplicates analyzed to confirm the

occurrence of PCBs.

Page 25: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

SECTION 5

TIER 1 OFFSITE MONITORING WELLS

5.1 WELL LOCATIONS

The Consent Decree (Exhibit 13, Table) requires that a total of 15 wells

be installed throughout the Tier 1, 2, and 3 areas. However, the Consent Decree

does not specify how the number of wells is to be distributed among the three

tiers. Therefore, Westinghouse has elected to install six offsite wells in Tier

1. The proposed wells have been temporarily identified as BD-A through BD-F and

their locations are illustrated on Plate 1. Following installation, the wells

wJ.il be numbered sequentially based on their order of completion, continuing thfc

well numbering previously established at Bennett's Dump.

The proposed sites for wells BD-A through BD-C are located along the north

side of an east-west trending road that is located north of Bennett's Dump. The

proposed sites for wells BD-D and BD-E are located on the west side of a farm

road which crosses an open field west of Bennett's Dump. The proposed site for

well BD-F is located in the area currently occupied by a stone-cutting operation.

5.2 BASES FOR WELL SELECTIONS

As described in the Data Evaluation (Blasland and Bouck Engineers, 1989),

the direction of ground water flow within the bedrock is toward the west and

northwest. Therefore, offsite wells BD-A, BD-B, BD-D, BD-E, and BD-F, located

west and northwest of Bennett's Dump , will monitor ground water within the

bedrock that may be flowing beneath Stout Creek. Well BD-C is located in a more

northerly direction with respect to Bennett's Dump in order to monitor ground

water flowing within bedrock underlying the areas east of Stout Creek.

10

Page 26: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

According to the Data Evaluation, the Salem Limestone comprises the bedrock

aquifer in the area of Bennett's Dump. Therefore, offsite wells BD-A through

ED-F will be installed as open-hole wells in the Salem Formation. The wells will

be terminated at elevations approximately equivalent to the total-depth

elevations of the wells currently onsite.

The results of ground water monitoring at Bennett's Dump indicate the

occurrence of PCBs in four of the seven wells drilled onsite during the

Supplemental Hydrogeologic Investigation. The Data Evaluation reports that PCBs

were detected in wells MW-3, MW-5, MW-6I, and MW-6D. All of the wells are

downgardient of Bennett's Dump as interpreted in the Data Evaluation.

Consequently, offsite welis BD-D through ED-F have been proposed in the apparent

downgradient direction of documented PCS occurrence.

The occurrence of PCBs was also reported in seven private wells as described

in the preceding section. All of the wells were within Tier 3 at least 2500

feet from Bennett's Dump. One well, number 22, was located north of the site;

another, number 12, was located southeast of the site; and, the remainder were

located southwest of the site. However, based on the wells' locations relative

to the direction of ground water flow at Bennett's Dump, the reported occurrence

of PCBs at these locations did not influence the selection of offsite wells.

Nevertheless, wells BD-E and BD-F, are located, coincidentally, between Bennett's

Dump and a relatively large distribution of private wells located on Vernal Pike

and Woodyard Road.

Six private wells, numbers 16 and 30 through 34, were located west and

7iorthwest of Bennett's Dump. Well 16 was located in Tier 2 and the remainder

were in Tier 3. Water from four of the wells, numbers 16, 30, 32, and 33 was

sampled and analyzed for PCBs. No PCBs were detected in any of the wells.

11

Page 27: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

Nevertheless, the locations of these private wells influenced the selection of

the proposed sites for the Tier 1 monitoring wells, particularly wells BD-A

through BD-D.

5.3 HYDROLOGIC ZONES OF INFLUENCE

The Consent Decree requires that the hydrologic zone of influence (ZOI) of

each tier well be described. However, the Consent Decree does not define the

term. In common hydrologic terminology, the ZOI refers to the spatial lowering

of the water table or potentiometric surface around the pumping well. In this

context, the ZOI is a dynamic concept in that it represents an area which varies

with the duration of pumping and with changes in the pumping rate. Consequently,

the standard definition of the ZOI is not applicable to a monitoring well which

is pumped only prior to sample collection to remove "stagnant" water in the well.

For the purposes of this plan only, the ZOI of each tier well will be an

area of the following dimensions surrounding each tier well. The length of the

Z'.OI will extend upgradient from the Tier 1 well to the site boundary and

clowngradient to the Tier 1 boundary. The width of the ZOI will be defined as

t:he distance between the pair of ground water flow lines that pass through the

points midway between the Tier 1 well and the two adjoining Tier 1 wells (see

Figure 2). In those cases where only one well is adjoining, the width of the

ZOI will be established as twice the distance between the Tier 1 well and the

midpoint with the single adjoining well (see Figure 3).

12

Page 28: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

SECTION 6

WELL INSTALLATION

All of the Tier 1 wells at the Bennett's Dump will initially be advanced

through the unconsolidated material to the top of the bedrock by hollow-stem

auger or roller bit. At each well site, a core of the bedrock will then be

collected using a core barrel. Subsequently, the corehole will be reamed to

approximately 5-1/2 inches. A four-inch ID steel casing will be seated into the

upper portion of the bedrock and grouted in place. After the grout cures, the

well will be deepened by continuous coring until the bottom of the well is of

an approximate elevation of 690 feet above msl which is comparable to the total

depth elevation of the wells installed onsite during the Supplemental

Hydrogeologic Investigation.

A field geologist will be present to observe the drilling, collect and

describe the samples, and log the test holes. In order to minimize any potential

for cross-contamination, the drilling equipment will be decontaminated by steam

cleaning between each well. Upon the completion of drilling, the well casing

will be fitted with a locking cover to preclude unauthorized access.

Following well completion, each well will be developed, if necessary, by

pumping to remove cuttings generated during drilling and to establish a good

hydraulic connection between the well and the bedrock. Water collected during

development will be analyzed for PCBs. Contaminated water will be transported

to a permitted, commercial disposal facility or treated to reduce PCB

concentrations to below 1.0 ppb prior to local disposal. Each well will also

be surveyed to document its location and the elevation of its measuring point.

13

Page 29: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

SECTION 7

WELL ABANDONMENT

If five years after closure of Bennett's Dump, the Tier 1 well monitoring

demonstrates compliance with the conditions of Paragraph 80 of the Consent

Decree, the offsite well monitoring at these locations can be terminated. When

these conditions are met, Westinghouse will implement well abandonment according

to the following procedures.

Prior to abandonment, each well will be checked from land surface to the

entire depth of the well to insure freedom from obstructions that may interfere

with sealing operations. A hole will be dug around the casing and the casing

will be cut off below the ground surface. Subsequently, a neat cement grout

mixture consisting of not more than six gallons of water to one 94-pound bag of

Portland Cement or a sand cement grout mixture consisting of not more than two

parts sand to one part cement and not more than six gallons of water to one 94-

pound bag of Portland Cement will be introduced into the well casing by means

of a tremie pipe. The tremie pipe will extend to the bottom of the well and will

be raised as the well is filled. The grout will then be allowed to overflow the

casing and fill the manhole to the level of the ground surface. The grout will

be slightly mounded to drain off surface water.

Because of the fractured nature of the limestone in some areas, a neat or

sand cement grout mixture may not be sufficient nor economical to abandon an open

hole well. Therefore, a concrete grout may be utilized in highly fractured

areas. The concrete grout will consist of not more than two parts gravel to one

part cement and not more than six gallons of water to one 94-pound bag of cement.

The abandoned wells will be checked after the grout has cured and

additional grout will be added if significant settlement occurs.

14

Page 30: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

SECTION 8

WELL REPLACEMENT

If during the monitoring period, any onsite monitoring well is damaged

beyond repair or cannot otherwise be used for its intended purpose, the well will

be replaced in its original location. If the well cannot be replaced in its

original location, Westinghouse will notify the parties of the Consent Decree

and mutually resolve a new location. The design and construction of the

replacement well will be as similar as possible to that of the original well.

15

Page 31: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

REFERENCES

Blasland & Bouck Engineers, P.C., August 1986, Supplemental hydrogeologicinvestigation plan, Wins ton- Thomas facility & Bennett's dump, Syracuse, NewYork.

Masland & Bouck Engineers, P.C. , 1987, Phase I progress report Winston-Thomasfacility & Bennett's dump, Syracuse, New York.

Blasland & Bouck, Engineers, P.C. , 1989, Data evaluation, Bennett's dump,Syracuse, New York.

Hites, R.A. et al., 1986, Collection and analysis of drinking water well samplesfor PCB content: Indiana University School of Public and EnvironmentalAffairs, Bloomington, Indiana.

Jones, W.W. et al . , 1985, Well water user survey around four PCB-contaminatedsites: Indiana University School of Public and Environmental Affairs,Bloomington, Indiana.

Quinlan, J.F. and Ewers, R.O. , 1985, Ground water flow in limestone terranes:strategy rationale and procedure for reliable, efficient monitoring ofground water quality in karst areas: National Symposium and Exposition onAquifer Restoration and Ground Water Monitoring (5th, Columbus, Ohio, 1985),Proceedings, NWA, Worthington, Ohio, 197-234.

U.S. District Court for the Southern District of Indiana, 1985, Consent decree;United States vs. Westinghouse, civil action no IP83-9-C; city ofBloomington vs. Westinghouse, civil action no. IP-81-448-C.

White, W.B. , 1969, Conceptual models for carbonate aquifers: Groundwater, Vol.7, No. 3.

Page 32: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

FIGURES

Page 33: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

1 1

TYPE OF FLOW

DIFFUSE MIXED CONDUIT

tCHALK

(England)

t t tBLUEGRASS MAMMOTH(Kentucky) CAVE

(Kentucky)

CASTLEGUARD(CanadianRockies)CAMBRIAN-ORDOVICIAN

DOLOMITE(Chicago)

Isolated Conduits Braided Conduits Branching Conduit Isolatedand Fissures and Fissures Networks and Caves Conduits

(Small) (Small) (Large) (Large)

FROM'QUINLAN AND EWERS, 1985.

P R O J E C T

BENNETT'S DUMP/OFFSITEGROUND WATER MONITORING PLANBLOOMfNGTON, IN.

SME-5

W) WestinghouseS C A L E : N /AJOB NO. 4 1 I 2 - 8 8 - I 0 7 G

FIG NO: i

Page 34: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

SITE

LEGEND

(7) TIER 1 WELL

• ADJACENT TIER 1 WELL

X MIDPOINT

-^ FLOWLINE

SHADED AREA REPRESENTS ZOI

TIER 1 BOUNDARY

P R O J E C T

FIGURE ILLUSTRATING ZOIAROUND TIER WELLCASE 1

SME-6

WestinghouseS C A L E . N/A

JOB NO! 4112-88-107G

FIG NO:

Page 35: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

T

LEGEND

TIER 1 WELL

• ADJACENT TIER 1 WELL

X MIDPOINT

^ FLOWLINE

SHADED AREA REPRESENTS Z01dl=d2

TIER 1 BOUNDARY

P R O J E C T

FIGURE ILLUSTRATING ZOI-AROUND TIER WELLCASE 2

SME-5

WestinghouseS C A L E : N/A

JOB NO! 4H2-88-107G

FIG NO:

Page 36: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

APPENDIX

Page 37: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

TABLE 2. Bennett's Dump -- Wells in Use1

V, State Rd. 46

1 1618/Flowers Charles D/332-3898

W. 17th St

2 Kill/Conrad Urban

Arlington Rd.

3 1604/Oliver Dora/332-41984 2320/Ayers Scott/339-4525 (now s. .Horton)5 3029/Brummett Ji«/6 3101/Bruinmett Jin/7 3260/Goodman Bernard & Violet/332-82598 3730/Bock Harion & Hargaret/339-5476 •'9 3800/Abee Paul & Virginia/332-7578

Gourley Pike

10 1315/Mitchell Anna/336-8827

Hickory Lane

11 1325/DeWeese Dennis/(Lovell Bourke/818 School Ln)12 1330/Snith Jessie W/334-338713 1411/Rogers Clovis W/332-997314 1419/Baugh/332-8902

15 Number Unassigned

Hunter Lane

16 2501/Blake Lloyd/332-5495

Lane Drive

17 1018/Simmons Ray«ond/336-8371is 1608/Bunch Terry/19 1613/Griffith Michael/339-056520 1615/Prince Ancel W/332-496921 1618/Allgood Lee R/339-0214

Maple Grove Rd

22 3450/Gustin Wa/336-661623 C»555/Shiner Vernon J/332-103224 0655/Carr Lennie/(Kitty Burkhart/1205 Pickwick PI)25 3808/Cobine A/332-118326 3888/Zellers H/332-6661

Page 38: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

TABLE 2 continued

Pioneer Lane

27 1850/Holmes Tony/(C. Wallace Holmes/103 S Johnson Ave)

Pro* Rd

28 3603/Herbin J/339-934429 3760/Trout Mrs Gail/336-7263

Siouta Creek Rd

30 3730/Johnson J/339-814631 3fl30/<James Krepps/3840 Stouts Creek Rd)32 3840/Krepps James/336-586833 4123/Creech Stephen W/334-329534 4131/Byrd Roger C/333-2457

Vernal Pike

35 1605/Hiller Albert L Jr/339-286036 2535/Sargent Dexter/332-735337 3401/Baldwin Larry E/332-383138 3415/Pierce Dennis/39 3506/Chadvick Ed W/332-439640 3602/Pennington James G/332-395941 3S33/S»ith Frank

Woodyard Rd

42 3100/Vaught Robert D/332-978343 3250/(Robert M Abram/4417 Tanglevood)44 3255/Walcott Shoff/332-890845 3260/Abram Robert W/332-997146 3401/May Lester L/339-624347 3500/Jonea Rufo/339-209648 3503/North Janes E/339-5228A9 3522/Deckard Randall/332-444750 3523/Baugh Wm R/332-863951 3534/SpinkB Estel/333-242052 3535/May Wm F/332-581453 :i600/Shipvash Verna/336-712554 3605/Smith Darvin/336-067755 3609/Brown Mary/332-3490 (confirmed by veil log, no response from ovner)56 3704/Taylor Steve

Page 39: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

TABLE 2 continued

Woodyard Rd continued57 3720/Bowmer Waiter/332-527158 3721/Goad Debbie/333-607059 372'2/Barlett Paul R/336-011860 3740/Nickie Kile/4935 W Woodward/876-6416 (3 wells)61 3755/Langwald Ralf R/336-358962 3780/Sinmons Dan/339-8930/ (Velma Flake/same address)63 3800/Farmer Harry A/336-246364 3801/Boruff Perry L/339-564965 3812/LaFon Donald E/334-152566 3815/Floyd Clarence Jr/332-957367 3818/English Terry (now Tony & Luann Sowder)

68 4005/Gardner V J69 4110/Arthur Billy P70 4131/Lowery Curtis L/339-396871 4141/Goodman Jeane F/332-919272 4203/Hay Bev73 4360/Sturgeon Wm/339-9038 -

Absentee Owners

Sec 19, Blgtn Twp/Haselaann, Robt, 4273 N. Hartstrait Rd/876-2686Sec 31, Blgtn Twp/Williams Wayne W, 2759 Delap Rd/876-2680Sec 20, Blgtn Twp/Biship Michael D, 5960 W St Rd 46Sec 20, Blgtn Tvp/Kevitt-Burns Ruth, 2036 Mystics Bay, Indianapolis, IH 46240

* Owner' s name and address given in parentheses if property not owneroccupied.

Page 40: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

/. ~7J? f ILASLAND li IOUCKJ?~) INOINJIRS, F.C.

SOIL DATA

PtItLUJQ

• o

. 5

•15

suTC

SA

MP

LES

SA

MP

LE

NO

1

2

3

4

RE

CO

VE

RY

(FT

)

1 , •'

1.9

.3'.

.2

UJ3_i5Z

r-5-

10

12

100

RFACE ELEVATIONP OF CAS NG ELEW

ROCK

oz

2.13ir

. ,_

1

i

XOau.

7.0

10. (

13. (

7?5.2

Oi-

0.0

3.0

27

DATA

%

RE

CO

VE

RY

92

103

99

T»,M 727.63

oOa;

.0

RA

TE I

MIN

/FT

)

'

tt

9*.

J5

DAT

U

1

3

(4

6

fi

7

7

i

it

SUBSURFACE LOG

SOIL/ROCK DESCRIPTION

SOIL /ROCK CLASSIFICATION

0-3 5' SILT, clayey, reddish gray (5/2) moist.

'35-4.25' SILTY CLAY and SAND Interssamed \reddiih yellow, (7/8) moist ind wet. Whit*clay s«am at 4.05'.4 25-6 0' SILT, clayey, dark gray (4/1) withblack mottles.

i 0-7.0' No recovery.

Soils Boring Terminated at 7.0'7.0-10.95' LIMESTONE. m«dium to light gtay.(7)l,lb

Fenestrata bryozoan and crinoid calcarenitasolution void at 10 95'.

(12)mb

10.95-14.53' LIMESTONE, bluaish grayV/Sty

medium crystalline, thin laminations, mudstained at 12 05'. styblitea at 12.25' and l/m12 85V Sty/m

(15)mbSty

1453-17.3 ' SHALE, dark gray dolomitic.

Iraclurej.

- 8/26/B7

ROCK

FE

ATU

RE

S

sr

GE

OLO

GIC

CO

LUM

N

~ /

_ _

,'-

'1_.

1

1 .-

, 11 ._

|

1 ~l

'1

I""1

WE

LL

CO

LUM

N

»c

•a0

"•

*to

*•TBEaa

ID

oi•oUc•a0

PR

PR

LO

CL

rviprr Tm F Supplemental Hydrucipolnt,112.15

n.lFPT AHIMRFR

Ic. Lo*£M-Lg4tU

rATinM Bennett's Dump

aqciFiFn RY JLJ rnFr«Fn RY CSS

GAMMA RAY

ELE

VA

TIO

N (F

T)

727.6

725.

719.9

715.2

712 2

710.2

DATE

HANfiF I0 * TIMF CONSTANT I0sec

COUNTS/MINUTE

10 20 30 40 5O 60 70 BO 90

-

"""\

"~"" ^HO ^\

1

- )

7

.19/9/871 ^__— — -~^~~

\ -

1 ( \

\ ~ ^- <

1 1 1 1 | ' r'l 1 18/8/87

CALIPER

HOLE DIAUE IE»(INCHLSI

2 4 6

-

-

-

-

-

-

1

i 1 '

-

-

OATE_Jl/B/al

f -ERMEABlL ITY

O2

t-

H

O

01

1-

tnOZ

in

1-

0•

£u

o

K

o10

DArF H/6/87

BORING/CORING/WELL NO MW 3

NOlf S

June 23. 1987 - Soil lot B3 was dulled

rig. Soil »ampl*« war* taken Ihiuug'i

2.5' long split ipoon sampler driven bya 140 Ib hammei 30* until split spoon *felustil at 7 0'. The soils boring wasbackfil led (torn 7 0' lo ground su r face

July 25. 1987 - Bediock foi H-3 wtUcored using a Gardner Denver 15 W aitrig Bediock was cored with a 3* 'diameter, 3' long double bnnel coiei to •1 0' below ground sur face Ihe dullingtluid consisted of misted air

/ 7/8' tilcone air rotary bit lo seal a 6* ~diameter casing at 13 0' below giound •surface The casing was sealed using -a 5% benionite grout mtxtuie iteimedthrough the annulus The grout wf&allowed lo cuie for over 48 huurs

August 5. 1987 - Bedrock was cored •using a 3* diameter. 14' long, splil .battel corei f rom 13 0' to 41 0' belowground sur face

conducted

was conducted

October 1t. 1987 - Core hole was "reamed to 5 5/81 diameter

October 11. 1987 • Well was developedby flushing air and mist Into bore hold

November 8. 1987 - Caliper logging was 'conducted

Page 41: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

/ ~}ff J U.ASLAND k tOUCK~j/ ~y ENGINEERS, P.C.

SOIL D A T A

u.

X

a

Q

20

25

30

.10SU

TC

SA

MP

LE

S

O2

a2

-

-

RE

CO

VE

RY

[FT

I

UJ

z

-—

-

RF1CE ELEVATION

P OF CASING EtEW

ROCK D A T A

,1

- -

^

--.

Oa.u.

E

27

Ot-

41

%

RE

CO

VE

RY

97

7?V2

TION 7?7 '«>

QO

95

nnT

i

5

7"

"i

7

rj

•,

b

7

b

-5—

a

TV

i ,•

i :

1 1

13

6

f,

s-

6

SUBSURFACE LOG

SOIL/ROCK DESCRIPTION

SOIL /ROCK CLASSIFICATION

1 7 3 - 4 1 0 ' LIMESTONE, medium <>'«/. micrllic.jtylolittc. grading to medium gity, lanesualo

slyloliles al 2065' . 215 ' . 22.76', 2!) 9'.30. 421 . 30 71. 323 ' , 3429 ' . 35. S'. 3 6 V .36 28'. 37 r. 37 631. wilh alte nutinglunesliale coqmn« layeis. Mlcilllc slnngeo ,,„ol 39 Q-. y

Sty

Sty

Sty

(13)mb

Sty

Sty

Sty

Sty

Sty

Sty

F a /26/67

RO

CK

F

EA

TU

RE

S

.-

GE

OL

OG

IC

CO

LU

MN

1

1

1

1r, 11

1

1

1

1

1 .

1

1

WE

LL

CO

LUM

N

OI

<D

Ou

caa.0

PFtUJECT T ITLE __S !'Pl!:"!e!ltlJM! r ^M«ul<.«|i^lnv,^u .nun

PROJFCT NttMBEH l!L. ._ _ .Bennett's Dump

LOCATION

CLASS!FIFO HY J1J r.HFCKFn RY

GAMMA HAY

EL

EV

AT

ION

(F

T)

705.:

7oo.;

690.2

685. i!

DATE

10

-

-

:

--"

3E J!?J< TIME CONSTANT J9 «E.

COUNTS/MINUTE

\

f'""

I

\ :

\

/

^) 1 1 1 1 1 1 i

t'Sb

CAMPER

1101 E IHAMC

(INdlESI

-

-

-

-

j (

-

DATE . l1/8./H/

I ' f K M E A B L I T Y

7

o

oz

DA! E

e»-

m0z

t-

i-

BORmG/CORlNG/WEL L NO Mz* ._?_.J.r 9 '

N O T T S

Page 42: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

X "v ""7' •LASLANO A iOUCK

# ~~f ENGINEERS. P.C.

SOIL D A T A

£\~a.

Q

*0

,s

SL

Tr

SA

MP

LE

S

SA

MP

LE

N

O

——

RE

CO

VE

RY (

FT

)

32

RFAtlL E L t V A T I O N

P OF CAS NG El EVi

HOCK D A T A

2Da

--

-

iOor

O

%

RE

CO

VE

R'

/ )*1 1

TION 7"'69

ij

a.

D/VT

RA

TE

IMIN

/FT

)

- —

6

r

SUBSURFACE LOG

SOIL /ROCK DESCRIPTION

SOIL /ROCK CLASSIFICATION

17 3-41.0' LIMESTONE, medium guy. mlcntic.

Rock Coring Terminated at 41.0*.

r 8/26/t i /

RO

CK

FE

AT

UR

ES

GE

OL

OG

IC

CO

LU

MN

WE

LL

CO

LU

MN

PR

PR

LO

CL

O.JFrr F IT IF Supplement.,) llydro.jeolugic Inv.Mi. j

112. IS

CATION tiennc-Lfs Dump

AS<;iFiFn HY JLJ c.nrrkFn HY

GAMMA RAY

EL

EV

AT

ION

(F

T)

684.:

680.2

DATE

RANGE 10x TIME CONSTANT _lfl L,eC-

COUNTS/MINU1E

10 2O 30 4O SO KO to 9O 90

;-

-

-

-

-

-

-

-

1 1 1 1 1 1 1 1 18/8/87

CSb

C A L t l ' K R

HOLE PIAUF UK

(IN( III. SI

' '

-

-

-

-

-

1 1 'DATE. 1 l /B /«'

l 'Fl<ME ABILIT >

;•'

I JATf

2

tf/6/l

n

oz

ttf}Ult -

1__

BORlfJC./COHING/WfLl NO "lVV~3 (CON T )

N O T E S

Page 43: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

z/^y_~W J iLASLAND* 10UCK

jff_ ~J INOINHM. P.O.

SOIL DATA

u.

it-a.

n

0

10

•15

SU

TC

aI<ti/i

O7

a

i

3

a:

o

UJa

1.5

.8

.7

HFACE ELEVA

P OF CASING E

2

10

7

"i

Too

ROCK DAIA

oz

z

--

]

_ _ .

-^—

i

2oaLL

-

7

10.0

12.0

0

1

0.0

--

6.0

a:

oUJo:

s?

-

67

I—'

100

a0a:

23

85

RATE

(M

IN /F

T:

i

i

_3_

J_

b

6

~

fi

7

n

SUBSURFACE LOG

SOIL/ROCK DESCRIPTION

SOIL /ROCK CLASSIFICATION

0-4 0' SILT, clayey, reddish gray (6/2), [rocsgray mottles, t race line sand seams, moist,grades to reddish yellow (7/8)

4 0-6 5' SILT, clayey, dark gray, with seam

mottles, damp, at 5.9' weathered rock.

6 5-71 No Recovery «7Soils Boring Terminated at 7.0'7 0 - 1 4 5 6 ' LIMESTONE, light brownish gray,medium to coarse grained tenestratebiyoioan and ctmoidal celcarenite, btownHF' m

mud-stained f rac ture at 13.2'.

HF/ n

1 4 5 6 - 1 6 9 LIMESTONE, medium light flrfly. Styrmcntic, with slylolllei It 14.8'. 14 7',HF/ m

HF/ m

RO

CK

F

EA

TU

RE

S

GE

OL

OG

IC

CO

LU

MN

~,

' .'

J -r—

I

I

I

I

I

I

|

I

|

|

WE

LL

CO

LU

MN

ctcM«JU

CO

V

E•tQ

"oI

0oc

aO

ION HO.O nAlF 8 / 2 6 / 8 7

, FVATl , ,N 7"-_80

PROJECT

PROJFCT

LOCATION

riTI F Supp)ein«nLal Hydroyi uloyic 1 n ves t

NiJMnr K 112.13Bennett 's Dump

i<|,it 01,

ci ASsiFiFn m JLJ niFr-KFn nr cst

GAMMA RAY

LL

Zo

LI_JUJ

732. S

730

725. i,

725

720

715

DA1E

HANGE

10

r

-

-

-

-

;-

- ,

-

-

i

|0 x riMF rnN^iANr lOse^

COUN f S / M I N U T E

10 BO 40 50 60 TO SO 90

\

\

\

1 1 1 1 1 I I I

8/10/H7

CAl . iPER

HOLE PlAME. T[K

(iNriltSI

1 4 6

'

(

-

\

1

| ,

uAie I I /B/ b/

PEKMEABIL IT l

-

E

o

ID

1

E

g

UJ

o

t-

o *o ',r

ro ',

ft

JA if LLLWii

MW-AnORING/CORING/WELL NO I*'" *t

N O T E S

June 23. 1987 - Soil lor B-4 was drilledusing a hollow stem auger tiuck mountrig. Soil samples were taken through

a 140 Ib hammer 30' until split spoon _refusal at 7 0'. The soils boring wasbackfilled f rom 7 0' to ground sur face

July 25. 1967 - Bedrock for B-4 wascored using 9 Gnrdnof Denver 15-W anng. Bedrock was cored with a 3' .diameter. 3* long douDle barrtt l coier to1 0* below ground su r face The dullinglluid consis ted ol misted air

7 7 j' tricone air rotary btt to seat a 6* •diameter casing at 12 0' below ground .

d 5% bentonite grout mixture tremied

allowed to cure for 24 hours

July 26. 1987 - Bedrock was cored ubinga 3* d iameter. 14' long, split ba r re lcorer f rom 12 0' to 40 0' oelow groundsur face

July 27. 1987 - Packer test ing w6* -conducted

August 10. 1987 • Gamma ray logging

October 11. 1987 • Core ho/a *db -reamed to 5 5/8' diameter

by Mushing air and rmsl into bore notetor one hour

November 8. 1987 • Caliper logging was .conducted

Page 44: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

A_jfff>"'f 1LASLANO * iOUCKjf ~f ENGINEERS, P.O.

SOIL D4TA

X

aUJo

.'b

. ill

. 35

SL

TC

SA

MP

LE

S

SA

MP

LE

N

O

-

-

RE

CO

VE

RV [F

T)

N

VA

LU

E

E—

RFACE ELEVATION

P OF CASING E F V.

ROCK D A T A

I

-;—

-

_..

—730.

50Q

--

~

o

ML

%

RE

CO

VE

R*

101

Ooo:

^

—° DA

IT

--

3

(,

5

t,

5

5

_5_

fe

5

b

—i

SUBSURFACE LOG

SOIL/HOCK DESCRIPTION

SOIL /ROCK CLASSIFICATION

IB. 9 35 3' LIMESTONE, medium light gray,eneslrale bryu/roan calcaienile to calcuujite ty

Honey

Honey

(20)mb

Sty

Sty

Sty

St,

Sty

Sty

3 5 3 - 3 7 8 ' LIMESTONE, medium tiQnl giny. ivymedium crystal l ine, grading denser.

Sty37 8-40.0 ' LIMESTONE, light gray, coa rse

grained calcuionlte.

Coring Terminated al 40.0'. St»

RO

CK

F

EA

TU

RE

S

TOm

mm,Soffirx

VSSSSS

'•

3E

OL

OG

IC

CO

LU

MN

.1.

=^T

1

1

1

1

1

1

1

1

1

1

WE

LL

CO

LU

MN

"bT.

O

cVn.O

PROJE

PfiOJEC

LOCAT

CLASS

-r I|TLE ^uppjementa! llyjro.jeolo^ic In

112.15

nw Bennett's Pump

FIFII B* JU riiFr.KFn Hr

GAMMA HAV

EL

EV

AT

ION

(FT

)

710

705

700

695

690

3ATE

RANGE !P_Jt_ TIME CONS1AN 1 J9j??_ .

COIJN15/MINU1E

IO 70 JO 40 iO 6O ro 0O 90

:. \

-

-

\;

/'

)

;/

-\

i\

j:.-".M"'""\_ __

- css -• ' ~

CAI il'ER

HOLE IHAMf II X

(INI lltSI

-

DATE. I I/

-

aye

PI I.MEABILIII

.'

MAI f

^

E

o

CM

1

oz1If)

1

tii-

|

1

0;

f

i

, ' f /Qf

DORING/LUHING/WELL NO MW'4 (CONT.)

N O T E S

Page 45: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

/ ~ffi J ILASLAND & IOUCKjp ~T ENOINIERS. P.C.

SOIL D A T A

u.

I

• 0

1U

SA

MP

LE

S z

0.I

E

RE

CO

VE

R*

ICT

I

D_l

Z

-

--

-

E

WICK DA1A

o

2

a

^

~

\

-

-j-

J_

ioa:

O

U

0

IT

-

aoir

——

1 —

a

-

-

SUBSURFACE LOG

SOIL/ROCK DESCRIPTION

SOU /HOCK CLASSIFICATION

0-1 4' Gravel . (FILL), tailtoao1 bed malenal,damp, hard

1 4 - 3 0 ' Si l t , black, some cindais, moist,moist. (FILL)

3 0-8.5, CLAY, silty, brown, wet

a 5-9 0' LIMES'TONE7. "Tigh! bTownish g iay"(5y i6 / l ) calcarenite, weathered, tolt9 0 - 1 7 0 ' LIMESTONE, medium gray (N5),

Iragments

1 7 . 0 - 1 6 0 ' LIMESTONE, medium dark gray(N4) . t race yellowish gray (5Y6/1) ,calcarenila harder.

ROCK

FEA

TURE

S

GE

OL

OG

IC

CO

LU

MN

-

"r1

^1

11

r

11

IwE

LL

CO

LU

MN

r

6'

Dia

me

ter

Ste

el

Ca

sin

g

|

Rn tv i . . i -- f | F V A T i O w ' l?7.7 DflTF 1 1 / 1 7 / H 7727.61 topi uf .veil cas ing elevat ion 727.30

TOP OF CASING F L F V a T O N

PROJEC1 TITLE Supplemental llyilruijeoli.iji. 1 meil i.i .l_ion

PRO.IFCI NMMHFR 112'1b

lOCATIOn liennetl'b Etunp

CLASSIFY D BY "J OIH-KFn BY tVl

GAMMA RAY

EL

EV

AT

ION

(F

T)

7 27 .7

722 .7

717.7

712 .7

RANGF _!P_* TIME CONSTAN1 . I0s?9

CCHINTS/MINUlt

m to so «o 30 eo ?o en 90

-

-

-

-

-

-

-

HA1F N/A ....

CAI. I I ' tL

IIOI t OIAMI ILH

(irjr It '.

-

D/UE II/A _

H HMEABILI 1 Y

L.' O

ro

o

|i/U F H/A

BORIIhVCORlUG/WEl \ tit) mW D

N O T E S

Octoboi M, 1987 boung was dulled to

15-W on lolary fig Soil fcamplet. wmw

Oclobei 14. 1987 • Bedrock was drilledto 8 JH' diameter and sampled at 1'intervals using a sieve 15' below yidUw

Octobtf i 14. 1987 - Casing 6' ID -diu e(vi was Kaaied at 15' withbeniomiu grout Kenned in placa Thw

October 15. 1987 - Bedrock was drilledto 5 b/a' diameter. 15' lo 451 below •giada and sampled at r intervals u*.inya sieve

October 15. 1987 • MW 5 was developed

lolnry nj lor one huui (nut recovering •ve ry quickly)

October 15, 1987 - Packer testing wasconducted Packet tabling was Iwnninated

hole

Page 46: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

/./—y_~Tff t BLASIAND t IOUCK

^^ ~f fNGINHRS. P.C.

SOIL DATA

u.

rt-0.

o

•20

2b

50

35

40

SL

Tf

SA

MP

LE

S

SA

MP

LE

N

O

RE

CO

VE

RY [

FT

I

UJ3-J<

2

--

-

ROCK D A T A

oz

zDQ:

+

T\

T

±

1

\

V

>

~T~

\

--

sO

u.

O

%

RE

CO

VE

R!

Ootr

,,0

-

RA

TE

(W

IN /

FT

)

SUBSURFACE LOG

SOIL/HOCK DESCRIPTION

SOIL /ROCK CLASSIFICATION

18 0-19 O1 LIMESTONE, yellow gray (5Y8/1)calcaiemte

19 0-23.0' LIMESTONE, medium gray (N5)calcaiemte t race fossi l fragments. t racesty lo l i ts f ragments .

At 22 0' grades grayish black (N2)

23 0 - 2 5 0' L IMESTONE. light olive gray(5Y6 /1 ) l i t t le to t f ace fossihterous. t race

sty lohte f ragmentsAt 24 0' grades to olive gray (5Y4/1)

25.0-27 0' LIMESTONE, medium light gray(N6) calcaremte.

27 0-32.0' LIMESTONE, medium light graygrading to vuiy light gray ( N S N 7 ) ,lithographic. Ititle (oasit (ragmscUa

At 28 0' Styiolite fragments

32 0-35 0' LIMESTONE, medium gray (N5)

fragments.

abundant.

35.0-36 O1 LIMESTONE. light oltve gray

36 0-37 0' LIMESTONE, medium dark gray

37 0-38.0' LIMESTONE, light olive gray(5Y6/1) t race calcite Iragmentc and fossilf ragments .38 .0 -45 0' LIMESTONE, light gray (N6)mien tic. l itt le fossil f ragman ta ( bryozoans)

RO

CK

F

EA

TU

RE

S

GE

OL

OG

IC

CO

LU

MN

1

|

1

i

Ii

i

ii

i

i i

i^ j .. —

i

1

WE

LL

CO

LU

MN

oX

9OO

cVaO

RFAfF Fl FV/mnw '27 '7 nvF /17/B7

P OF CASINr, E L E V A T I O N '"•" T°P "' li«n C"ln9 Elevation 727.50

Pi

P(

LO

CL

niFPT I IT IF Supplemental Hydroyeolu^ic Inveil i ijot ",n

n.lFCT MUMRFR 112.15

CnrifM Bennett's Dump

ASSiFiFn By JLJ nirrkFt) fly css

GAMMA RAY

EL

EV

AT

ION

(FT

)

707.7

702. /

697. /

692.7

687. /

HANGE 'O" - TIME CONSTANT _ !P iec

COUNTS/MINUTE

10 ?u 10 40 30 co rn eo «o

-

"

-

1 1 1 . 1 1 1 1 L 1

DATE N/A

CAI If'ER

1101 [ IH.IMF IM<(INI i r t S I

2 ^ 6

-

-

-

-

, — 1 — 1,_ J —D A I E _ " / A _

PEttMEABILIT"!

o7

h-

i

ru0z

O

I-in

n

O3L

\f\

MMf N/A

wnRlfJG/CORlNG/WFl 1 NO MW'D \LUN 1 J

N O T E S

-

Page 47: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

/ ^J/f™ f BLASLANDA BOUCK

# ~~J ENGINEERS. P.C.

SOIL D A T A

It-Q.LJO

" SL

TC

5

O

-ia2

— -

E

RE

CO

VE

RY fF

T'

---

=

RFACE ELEVA

P Of CASING E

UJD

3

ROCK DAI A

a

\

- • -

-;-

--

- -

-I:

20QLLL

--

o

__

%

RE

CO

VE

RY

E

E

inn) 7i'r.O

.EWnON.y-" -

Q0a.

-9

___

DAI

RA

TE

[MIN

/F

T)

SUBSURFACE LOG

SOIL/ROCK DESCRIPTION

SOIL /ROCK CLASSIFICATION

38 0-45 0' LIMESTONE. light gray (N6)micntic lit 1 la tossil fragments (bryozoans).

At 43* some yellowish gray (SYS/1).

3onng Term mated at 45.0'.

f 11/17/87

Ul

|LL.

ooCL

GE

OL

OG

IC

CO

LU

MN

1 -

[,

I

I1

_ \ _

I1

UJ |

* 0

01oX

01O

CJ

c01Q.

O

PlUl.irCT NifMDtR 11^2.13

LnraTir*) llenm-tt's Dumu

CL ft^^lFlFn H¥ JLJ niFTKFn BY CSi

GAMMA HAV

EL

EV

AT

ION

(F

T)

CB2 . )

DATE

KANGE TIMF CONSIANI _.

COUN1S/MINIIIE

tO to 30 40 3O CO 10 00 90

-

-

-

J 1 1 1.1 _!.._! 1 1

N/A

CAI IPER

MOI e ni.iMf it i<[INtHI M

1 ^ 6

-

.._! 1

DATE _ " ' i

f ' E h M E A B I L I T Y

o

t-

O

Oz

O

O

Oz

o

to

"""• m —

BO«.N6A.«,HG/WE1L NO MW-5JCONT)

NOUS

Page 48: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

r"/ 11ASLAND 4 BOUCK~y ENCINIERS, P.C.

'•OIL O A T A

LL

I

aUJo

0

10

- IS

suT(

i0

X<4

N/A

-

[REC

OVER

V in

__

N/A

E

=>

-

_

H/A

E

——

KFACE E L E V A T I O N

r OF CAS NO ELEV

ROCK UATA

o

0

——

N/A

r—

0

1 ——

I /A

%

RE

CO

VE

R1

N/A

7 5 2 . 1 '

Tinu 731 -116

Q

Oor

.0

• I /A

OAT

5

•4a

^

--

-

H / A

SUBSURFACE LOG

SOIL/ROCK DESCRIPTION

SOIL /ROCK CLASSIFICATION

0 3 0 ' Gravbl. FILL, railroad bed materidl.moiil

3 0 - 7 0 ' CLAY , silly. 'blown, wet al < 0'

7 0 - 1 B O ' LIMESTONE/ light olivs gray tolight gray. with some dark yellowlithographic and fossil liagmenls.

F 10/21/87 ' I J 1 IB U'

"""*

RO

CK

F

EA

TU

RE

S

*-

GE

OL

OG

IC

CO

LU

MN

I

I

I

I

I

I

I

I

WE

LL

CO

LU

MN

'

«

=

1

\ \

'

PROJECT IITIF Suplilerin-iitdl Hydrcm-olu'jiCj! I;, vest . ! .J?t i\...

pnojrci NUMBER '.U-'5 - ..inrATlDN IkjnneU'b I'ump

n AsqiFirn BY CSb niFrkFn BY ' " ' •

GAMMA RAY

EL

EV

AT

ION

(F

T)

732 1

7 2 7 1

7 2 2 1

717 1

DATE

RANGE TIMF CONSTANT _

COUNTS/MINUTE

10 20 10 40 3(1 so ro ao 90

-

-

-

-

1 1 1 I 1 I I I IH ,.

CAI ii 'ER

1101 E L i iAUFTIK

(INI. M( SI

2 4 e

-

-

DATE N •

I 'EI 'UEABl l I T Y

o

i

i

i

>-

Wl

t-

< *Tl Ht+

n

0

LU1-

tiOHlNG/LONING/WEl '.. NO -™ " 9i

SHEET 1 OF 1

NOTf S

October 23, 1987Wall drilled t rom ground

surface to a dvpth of 18 leet using aGoidnui Denver tuf ro ta ry rig

PVC Well Conslruclion Details- 2' diameter. 01 slotted schedule 40 .

PVC screen, installed Irom 13 0 lo8 0' below grade2' diameter, schedule 40 PVC riserinstalled f rom 6.0' lo 0 04' belowgrade4 O sand pack Irom 18 0 to 6 3Bemomie pallets liom 63 lo 4 0'Benionne grout f r om 4 0' lo surlaceProtect ive &tee i casing do 1.2' tosurlace

December 9. 1987 - Well was devt 'lopedby surging and bailing until clear nlsilt

t tibliny was conducted

Page 49: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

S~Mr—r ILASLAND » »OUCKJF ~J IMr-INHRS, F.C.

SOIL O A T A

Q.UJQ

0

1U

- 15

f"LTC

UJ

a

|

SA

MP

LE

N

O

/A

OE

CO

VE

HY (F

TI

J/A

z

-

II/A

~~

ROCK DATA

0z

-

-

-

1

'-

2

3

Ioitu.

~-

10.!

n.'

o

10.5

13.5

77.6

c/o

S

EC

OV

ER

Y

96

105

100

0

-

RA

TE

(W

IN

/FT

)

;:h'

—.?'.'-

1.—

e

6

it

3

4

T

-*-

3

SUBSURFACE LOG

SOIL/ROCK DESCRIPTION

SOIL/ROCK CLASSIFICATION

0-3 0' Gravel. (FILL), railroad bad matenal.moist, musty odor

3 0-7 . 01 CLAY, silly, blown.

At 4.0 ' wet

7 0 - 1 2 4 5 " LIMESTONE. light olive 9'a^)mb

5Y6M) lithogiaphic. small vi;gs at 8.6'.

V

COmb NC

BKZN

1245-13.5 ' LIMESTONE, light gray (N7).

I 161mb

1 3 5 - 2 1 0 ' LIMESTONE, light gray (N7) withsome dark yellow orange (10YR6/6) lossilIragments.

w/

v/c

RO

CK

F

EA

TU

RE

S

GE

OL

OG

IC

CO

LU

MN

\

i

I

— [-1-

— 1

1

1r1-

1~l

f1

1

1

1

T

iRFflCE ELEVATION 75-'-° _. .- HAIT " / ' 7 /S7 _

751.99 lop of dell Cjiin.i E levat ion 731.73P OF CASING ELEVATIUfJ

It OO

1

I

I

I

PHUJECT T ITLE S^UmenL.! Hy,ir0, jeiJ]ogic hw,

PROJECT NUMBER 112,15 _.NenneVt'i Dump

LOCATION

n ASSIFIFH HY J'J oiFrkR) RY

GAMMA RAY

u,

0

\

IU

/32.0

727.0

/22 .0

71;. o

RANGE IOX TIME COfjqiANF I0 lcc

IO 20

:

-

-

-

(

•: \-

nATF 11/8/87

COUN 1 S/MINU1 f.

3D 40 5O SO 7O BO 90

\

\

\

-

CSS

CAL I I 'ER

HOI f ni.'.METEH

IINCnl SI

/-

-

DAIE JO/ . '2/87

J 'ERMF AB LIT Y

0

UJi

g

UJt-

TO

0z

UJ

BOHING/COHING/WH 1 NO . _ _ - - - " . . _ -

N O T E S

October 15. 1967 - Soil for 8-6 wasdrilled using a Gardner Denvei 15-W rigtram giound surface to 7 Q1 belowground surlece. Soil watt templed u*lnga sieve at the annulus ol tha wail

October IS. 1987 - Bedrock for C-6 wascoied using a Gardner Denver 15-W rigT he bedrock was cored with a 3'diameter. 3' long, double ba r re t _oi*( •Kom 7 5' la 13.5' The dolling lluidconsisted ol misled air

October 15. 1987 - Core hole wasteamed to 7 7/6* diametei with a meant*dir r o t a r y Dit to seat a 6* diamuieri,eis-ng at 13 5' below giound sudact* •

uentonne grout mixtufe tremied througn

cure for over 48 hours

using a 3' diametei. 14' long split spoon .sampler liom 13 5 lo 4V

October 21 1987 • Packet testing wasconducted

O^lodei 22. 1967 - Core hole wasi earned to 5 5/8* diameter

by f lushing air and mist into [he bur* *note lot one nout

October 22. 19B7 Caliper logging wasconCucltd

Nuvember a. 1987 Gamma ray logging/.as conducted

^VC WELL CONSTRUCTION DtlAILSInsialled October 22. 1987Benlontta pellets installed lor Dacht iMIrom 41 0' to 36 0'4 Q gram size sand back! ill Irom -36 0' to 34 6'

- 2* diameter Ol slot schedule 40 10'long PVC screen f rom 34 6' to 24 6'below grade

Irom 24 6' to 27' below grade• 4 Q grain size sand pack installed .

trom 34 6' 10 21 2' below grade

below grade- Bei .onita irout installed Irom 19 2' to

sur face- Flush mount protective steel casing .

installed 1* above arade

Page 50: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

•LASLAMD 1 1OUCKENGINEERS, P.C. SUBSURFACE LOG

PHOJECT TITLE_ Supplemental Hydruijeologlc Invest i^ j l

pnojcci iniMBEn_ "_U.5.__ .LOCATION Dennett'i Hump

CLASSIFIED BV_ CHECKED BY .5HEE! _i OF

SOIL/ROCK DESCRIPTION GAMMA RAY •EHMt ABIL ITY

SOIL/ROCK CLASSIFICATION

5 I3 5P o

^-J I-' DMl J? O

RANGE I0 " TIME CONSTANI . I0.SJC

COUNT S/MINU l£

?o 30 40 so co 70 ao toI I I I I

IOLE OIAMI TEF(INOU S)

13 5-21 0' LIMESTONE, light gray (N7) withsome dark yellow orange (10YR6/6) fossilIragments. caicarenila.

TT.

At 20' grades to t race lossililarous p I

At 21 0' slyloliie.21 0 - 2 4 Op LIMESTONE. light gray (N7). Stycoarser calcarenite. t race fossils, appearsporous

I

24 0-2B 0' grades less coarse calcaranitt.WJW

24 5 -24 65' with slight 'honeycomb*eaihenng | T

I

I rAt 27 6' sty lo l i te. St

28 0-31 6' LIMESTONE, medium gray (N5).fossilileious, cnnoidal

and fenest ra te bryozoan IragmenteAt 28 7-28 8' light olive gray zone lasscalcarani le

_i

II I

31 6 - 3 6 0 ' grading with more lenetlratebryozoan appeals more porous

T_zc

m/vf /c j h-'-

IC36 8-36 9 'SHALE, gray black (N2) calcareous. '. I I36 9-41.o 1 LIMESTONE. light olive gray I(5Y6/1). 1

E

11/17 /87Tup oi ht-ll Cdbiny E levd t ion : 7 3 1 . 7 3

December 9. 1987 Well was developedby surging and bailing until cleat ol!.lll.

December 9. 1987 - In-bilu permeabilityubtlng was conducted.

J |__J 1 i l L_l 1 LiSUITACE ELtVATION__?Ji

TOP OF CASING ELEVATION _

Page 51: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

^

P J ILASLANO » IOUCK~J ENOINIIRS, P.C.

SOIL DATA

Pit

X

aUJ£>

45

LUs

SA

MP

LE

S

SA

MP

LE

N

O

RE

CO

VE

RY (F

T)

D

sz

R F A C E ELEVATION

P of CASING ELEVJ

ROCK

Oz

2Ua

732,

3Otru.

(1

O

D A T A

>ctw>o

(Z

S5

ooa

N?

RA

TE

(W

IN /F

T)

=

SUBSURFACE LOG

SOIL/ROCK DESCRIPTION

SOIL /ROCK CLASSIFICATION

3 6 9 - 4 1 0 ' LIMESTONE. Nghl oliv« gray(5Y6/1)

Conng Terminated at 41.0V

n/iri 11/17/87

Tinn| 731-99 lup of Hel l Casing Elevation 731.73

RO

CK

F

EA

TU

RE

S

GE

OL

OG

IC

CO

LU

MN

I

WE

LL

CO

LU

MN

Ks>1fcsl

PR

PR

LO

CL

n.lFTT TITI F <lll[>|>b!WIl''*1 Hyrirng^^lngir Invent

112.15n.iprr N"MRFP

.UdLi Lin

rAnnw Bennett's Dump

A^iFirn nv n i CHFTRFD HY r-f.

GAMMA RAY

EL

EV

AT

ION (

FT

)

691.0

6B7

DATE

Riwr.F 10x TIME CONSTANT 10 »>•••

C O U N T S / M I N U T E

n 20 10 40 SO CO TO SO 4O

-

-

-

-

-

-

-

-

-

1 .1.. .1 1 1 1 . 1 . _l_...l

CALII'ER

MOLE DIAMETER

(INCHES)

2 4 S

-

_

-

-

~

-

J__ J I

D A T E . J Q / 2 2 / 8 7

PERMEABILITY

OZ i

t-VIUJ(-

ozt-10LUH

DATF 10/21/87

BnB,Nr,/COH,Nc,x«F,,NoMW-6D(CONT.)

NOTES

-

Page 52: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

\LEGEND

* (.HOUNH - WAT ER W . " v l 1 uT' l - j f^ W F L L

>i S T R E A M G4IIM'

17233'} ( . R O U N D - W A T E R E 1 T V 4 T I O N

•yg^'i CHOUNO-WATER CONTOUR LINE

HAIUNO t »OWC«

BENNETT'S DUMP

GROUND-WATER CONTOUR MAPDECEMBER 6, 1988

5F

Page 53: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

1 i"; Cts\ ' "l? x

-A i.H''.''. . 7«H?;v,^. -*\/\. -V

0' H

LEGEND

» GROUND-WATER MONITORING WELI

" STREAM GAUGE

(72580') GROUND-WATER ELEVATION 3/9/68

725* GROUND-WATER CONTOUR LINE

BENNETT'S DUMP

GROUND-WATER CONTOUR MAPMARCH 9, 1968

5C

Page 54: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

r

'Mr.

HAIUMO » MUCK1, ».C.

LEGEND

• GROUND-WATER MONITORINS WELL

H S T R E A M GAUGE

(722 98') GROUND-WATER ELEVATION 6/6/B8

722* GROUND-WATER CONTOUR LINE

BENNETT'S DUMP

GROUND-WATER CONTOUR MAPJUNE 6, 1988

5D

Page 55: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

(72875')

^-——4-1 ~ ( \ (73059'' ^*^vr=rrr*732'. L \ -, -^b'

' '-; tgf--:-^ , '-•• ~ ' "•_• - %- -' // .-•-V —'- «*»•' ' /

, LEGEND

» r.ROUND- W A T E R MONITORING WELL

» ' JTREAM GAUGE

(722 to') f .ROUHO-WATER ELEVATION 11 /8 /87

-~~ GROUND-WATER CONTOUR LINE

BENNETT'S DUMP

GROUND-WATER CONTOUR MAPNOVEMBER 8, 1987

5B

Page 56: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

liv/" • 4i-'(i" ^' Hi'-rSf-^^ifev^

A ffi^fi:'''''t*f>^ "' 'f\ WW.: A-.v -u'A

FIGURE I

LEGEND

SITE LOCATION

BENNETTS DUMP

REGIONAL SITE PLAN

' ILASLAND A iOUCKfNOINEERS. PC.

Page 57: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

VOLUME 1

DATA EVALUATIONBENNETT'S DUMP

WESTINGHOUSE ENVIRONMENTAL SERVICESWALTZ MILL SITE, PENNSYLVANIA

MARCH 1989

BLASLAND & BOUCK ENGINEERS, P.C.6723 TOWPATH ROAD

SYRACUSE, NEW YORK 13214

Page 58: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

TABLE OF CONTENTS

Page

SECTION I - INTRODUCTION 1

SECTION II - PHASE 2 SITE INVESTIGATIONS 4

A. Introduction 4B. Task 2.1 - Continuous Test Boring/Rock Coring 4C. Task 2.2 - Monitoring Well Installation/Rock 7D. Task 2.4 - Ground-Water Sampling 15

SECTION III - DATA EVALUATION 17

A. Topography and Geomorphology 17B. Unconsolidated Material 17C. Bedrock Geology 18D. Hydrogeology 20E. PCS Analytical Results 23

SECTION IV - SUMMARY 24

SECTION V - REFERENCES

TABLES

1 Monitoring Well Construction Details2 Hydraulic Conductivity Values, Packer Testing and Slug Testing3 Water Elevations4 Ground-Water Analytical Results

FIGURES

1 Regional Site Plan2 Site Location Map3 PCB Concentrations in Ground Water4A Geologic Cross-Section A-A'4B Geologic Cross-Section B-B'4C Geologic Cross-Sect ion C-C'5A Ground-Water Contour Map for August 22, 19875B Ground-Water Contour Map for November 8, 19875C Ground-Water Contour Map for March 9, 19885D Ground-Water Contour Map for June 6, 19885E Ground-Water Contour Map for September 7, 19885F Ground-Water Contour Map for December 6, 1988

APPENDICES

12

Phase 2 Site Investigation SummarySubsurface Logs

Page 59: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

SECTION I - INTRODUCTION

The Bennett's Dump Site is located in Monroe County, Indiana,

approximately 2.5 miles northwest of the City of Bloomington in all four

quarters of the northeast quarter of Sect ion 30, Township 9 North, Range 1

West (Figure 1). The site consists of three fill areas (Figure 2). The main

fill area is 3.5 acres in size and is located adjacent to Stout Creek. The

two other fi l l areas are a 0.5-acre area adjacent to the main fill area and

a very small satellite area (approximately 30 feet by 60 feet) 750 feet north

of the main fi l l area.

The site is located within an area known as Bennett's Quarry, an active

quarry operation. The quarry was privately owned and operated by Mr.

Edward Bennett until it was sold to the Star Stone Company in 1987. In the

1960s, a portion of the Bennett land was used as a landfill for industrial

wastes. These wastes included electrical capacitors, some of which contained

Inerteen, a dielectric fluid which is primarily composed of polychlorinated

biphenyls (PCBs).

In August 1985, Westinghouse entered into a Consent Decree with the

United States (represented by the Environmental Protection Agency [EPA]), the

State of Indiana, the City of Bloomington and the County of Monroe. As

required by this Consent Decree (Paragraph 74 [b]), Westinghouse performed

a Supplemental Hydrogeologic Investigation at the Bennett's Dump Site. Prior

to initiating the investigation, Westinghouse submitted a Supplemental

Hydrogeologic Investigation Plan (Supplemental Plan) for approval by the

parties of the Consent Decree. The f i rs t Supplemental Plan was submitted

in October 1985. In December 1985, Westinghouse met with the parties of

3/22/89289275G

Page 60: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

the Consent Decree to review this submittal. A formal response to the

submittal was then received f rom the EPA (letter to Mr. Carl Anderson from

M.V. Pearce, December 3, 1985). Westinghouse agreed to resubmit the Plan

and incorporate changes that would address the issues raised by the EPA

and other parties of the Consent Decree. A rev ised Supplemental Plan for

the Bennett 's Dump Site was submitted in February 1986. The revised Plan

was reviewed and formal comments were submitted to West inghouse by the

EPA (letter to Mr. Carl Anderson f rom M.V. Pearce, April 14, 1986) and by

the City of Bloomington ( le t ter to C.A. Anderson f rom J.V. Karaganis, Esq.,

May 13, 1986). A meeting was held on May 20, 1986 to fur ther discuss the

February 1986 Supplemental Plan. In August 1986, the final Supplemental

Hydrogeologic Investigation Plan (1) was submitted to the parties of the

Consent Decree; all parties approved the Plan in March 1987.

The work e f fo r ts of the Supplemental Investigation are separated into

three phases: Phase 1 - Data Collection and Review; Phase 2 - Site

Investigations; and Phase 3 - Evaluation of Data and Submission of the On-

Site Monitoring Well Plan. The work e f fo r t s for Phase 1 began in the fall

of 1986 and were completed by January 1987. The Phase 1 work e f fo r ts

were evaluated and compiled into a Phase 1 Progress Report (2) for the

Bennett's Dump Site. This report was completed in January 1987; it was

transmitted to the parties of the Consent Decree in March 1987 af ter Plan

approval was received f rom all part ies.

The Phase 2 Site Investigation e f fo r t s , excluding the ground-water

sampling, Task 2.4, were performed f rom July 1987 to December 1987. As

specified in the Supplemental Plan, Task 2.3, Westinghouse submitted a Data

Transmittal (3) document in May 1988 that included data obtained f rom the

3/22/89289275G

Page 61: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

bor ing/cor ing and monitoring well instal lat ions, Tasks 2.1 and 2.2. The

quarterly ground-water sampling, Task 2.4, began in March 1988 and was

completed in December 1988. Quarter ly sampling reports were submitted to

the parties of the Consent Decree by Westinghouse in August 1988, October

1988 and January 1989 (4, 5, 6).

The Phase 3 work e f fo r ts included an evaluation of the Phase 1 and 2

data to establ ish the hydrogeologic condit ions at the si te. This evaluat ion

entitled the Data Evaluation is Volume I. The Phase 1 data and preliminary

evaluations were included in the Phase 1 Progress Report (2) and are

addressed in Volume I, as applicable. An evaluat ion of the Phase 2 work

e f fo r t s are presented herein. The Phase 2 data are presented in the Data

Transmittal (3) document. The reader is directed throughout this volume to

the appropriate references for data and results.

The Data Evaluation is organized into four sections. Section I,

Introduction, includes introductory remarks regarding the site history and site

background information and a description of the contents of this report .

Section II, Phase 2 Site Investigations, is a detailed review of the

investigative work completed by Westinghouse in accordance with Task 2.1

through Task 2.4 of the Supplemental Plan (1). Section III, Data Evaluation,

sets for th an interpretat ion of the geology, hydrogeology and PCB analytical

results at the Bennett's Dump Site. Section IV, Summary, provides a synopsis

of the geology, hydrogeology and PCB distribution in the ground water at the

Bennett 's Dump Site.

3/22/89289275G

Page 62: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

SECTION II - PHASE 2 SITE INVESTIGATIONS

A. Introduction

As descr ibed in Tasks 2.1, 2.2 and 2.4 of the Supplemental Plan (1),

Westinghouse has performed four soil borings, four rock cor ings, four

monitoring well instal lat ions and four rounds of ground-water sampling.

Fur thermore, West inghouse advanced an additional bor ing/cor ing and installed

three additional monitoring wells as described in the Data Transmit ta l (3)

submi t ted in May 1988. These work e f f o r t s were completed f rom July 1987

through December 1988.

Each Phase 2 task set fo r th in the Supplemental Plan (1) is described

in this section. A summary of all investigative work tasks, in chronological

order, is provided in Appendix 1. A reference list of all studies, reports

and other reference sources applicable to this site is presented in Section V.

B. Task 2.1 - Continuous Test Boring/Rock Coring

The locations of the f ive borings/corings were selected to provide

compositional data on the unconsolidated material (soil and fill) and lithologic

and structural information on the bedrock at the site. Continuous sampling

of the unconsolidated material and the bedrock was per formed f rom the

ground sur face to an average depth of 42 fee t at f ive locat ions, which are

now designated as Wells MW-1, MW-2, MW-3, MW-4 and MW-6D (Figure 2).

The subsurface logs for the borings/corings are provided in Appendix 2.

The test borings and rock corings were performed during the months of June,

July, August and October of 1987. The exact dates of test boring and rock

3/22/89289275G

Page 63: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

coring are provided in Appendix 1.

Samples of the unconsolidated material were collected with a split-spoon

sampler according to ASTM Standards and Procedures as described in

Appendix A, Drilling/Sampling Protocol for Soil Borings, of the Supplemental

Plan (1). All test borings were dri l led with a hol low-stem auger rig except

at the location of Well MW-6D, where the boring was drilled with a Gardener

Denver 15W air rotary drill rig. Continuous rock coring was conducted

following ASTM Standards and Procedures outlined in Appendix B,

Drill ing/Sampling Protocol for Rock Coring, of the Supplemental Plan (1).

Rock cores were obtained using a 15- foo t long, 3-inch I.D. split barrel core

barrel and a 3-foot long, 3-inch I.D. double tube core barrel. The coreholes

were drilled with a Gardener Denver 15W air rotary drill rig. Permanent steel

casing was grouted a minimum of 5 feet into the bedrock to seal the

unconsolidated material from the lower bedrock during the coring. A

geologist was on-site to ensure that the drilling protocols were followed and

to describe the unconsolidated material and rock units encountered as

outlined in the Supplemental Plan (1).

The boring/coring at the location of Well MW-1 was completed on July

28, 1987, to a total depth of 44 feet. This boring/coring is located near the

southern end of the main f i l l area. At this location, 8.9 feet of clay and

silt were encountered above 35 feet of fossil i ferous limestone (biocalcarenite).

In the core obtained from this installation, three vertical f ractures were noted

from approximately 30 to 38 feet. Honeycombed weathering was noted at

depths of 26.5 feet and 28.4 to 29.6 feet. Solution features with brown mud

were encountered at a depth of 30.8 fee t . A broken rock zone was noted

at a depth of approximately 31 feet . Some sty lo l i tes were noted throughout

3/22/89289275G

Page 64: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

the core.

The boring/coring at the location of Well MW-2 was completed on August

4, 1987, to a depth of 42 feet . This boring/coring is located near the

eastern edge of the main fill area and is west of the 0.5 acre fill area. At

this location, 4.75 feet of s i l ty clay was encountered above 37.25 feet of

limestone and micritic limestone (calcarenite and calci lutite). A healed vertical

f rac tu re was encountered f rom approximately 40 to 42 fee t . A void was

noted f rom 6.5 to 6.7 feet . Only a few sty lo l i tes were noted in the core.

The boring/coring at the location of Well MW-3 was completed on August

5, 1987, to a total depth of 41 feet . This boring/coring is located north of

the main fill area. At this location, 7 feet of clayey silt and silty clay and

sand were encountered above 34 feet of fossi l i ferous limestone

(biocalcarenite), shale and micritic fossiliferous limestone (biocalcilutite). Many

stylolites were noted throughout the core.

The boring/coring at the location of Well MW-4 was completed on July

2(3, 1987, to a depth of 40 feet. This boring/coring is located adjacent to

the satellite fill area in the northern section of the site. At this location,

6.5 feet of clayey silt was encountered above 33.5 feet of fossi l i ferous

limestone (biocalcarenite) and micrit ic limestone (calci lutite) that became

coarser in grain size (calcarenite) with depth. Four horizontal f rac tures with

mud fi l l ing were encountered f rom approximately 8 to 16 feet . Honeycomb

weather ing was noted at depths of approximately 21 to 22 feet and 24.7 to

25.0 feet . Many sty lo l i tes were noted throughout the core.

The boring/coring at the location of Well MW-6D was completed on

October 21, 1987, to a total depth of 41 feet. This boring/coring is located

near the southwest section of the main f i l l area between the site and Stout

3/22/89289275G

Page 65: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

Creek. At this location, 3 feet of gravel fil l fol lowed by 4 feet of silty clay

.~". . . - • • ' was encountered above 34 feet of l imestone (calcarenite) with a trace amount

of fossils. Vugs were encountered at depths of 8.6 and 17 feet. A broken

rock zone at a depth of 11 feet , and a calci te fi l led ver t ica l f rac ture zone

from 34.5 to 36.5 feet were also noted in the cores. Honeycomb weathering

was noted at a depth of 24.5 to 24.65 feet. Only a few stylol i tes were

observed throughout the core.

As stated in the Supplemental Plan (1), packer test ing and gamma-ray

logging were conducted at each coreho le . Because these work e f f o r t s were

also conducted at the monitoring wells, they will be discussed jo int ly in the

following sect ion.

C. Task 2.2 - Monitoring Well Installation/Rock

~~~s

/ 1. Monitoring Well Installation

Seven monitoring wells were installed in October 1987 around

the perimeter of the fil l areas of the Bennett's Dump Site. The

monitoring wells were designated as MW-1, MW-2, MW-3, MW-4, MW-5,

MW-6I and MW-6D. All of the monitoring wells were installed with the

Gardener Denver 15W air rotary drill rig using a tr icone roller bit.

Monitoring well specif ications are provided in Appendix 2 and Table 1.

Monitoring Wells MW-1, MW-2, MW-3 and MW-4 were constructed

as open-hole wells as descr ibed in Appendix E, Drill ing Protocol for

Open-Hole Monitor ing Well Completion, of the Supplemental Plan (1).

These wells were completed by reaming the 3-inch diameter coreholes

previously completed at these locations to a 5-5/8 inch diameter. Steel

casing (6-inch inner diameter) was previously set during the coring

3/22/89289275G

Page 66: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

operat ions to seal the bedrock f rom the unconsol idated material .

Monitoring Well MW-1 was completed on October 10, 1987, to a

total depth of 44 feet. The casing in this well extends to 17.5 feet ;

the re fo re , the open port ion of the well is f rom 17.5 to 44 feet (719 to

692.5 feet above mean sea level [amsl]) .

Monitoring Well MW-2 was completed on October 11, 1987, to a

total depth of 42 fee t . The casing in this well extends to 11.0 f ee t ;

therefore, the open portion of the well is f rom 11 to 42 feet (731.2 to

700.2 feet amsl).

Monitoring Well MW-3 was installed on October 11, 1987, to a

total depth of 41 fee t . The casing in this well extends to 13 feet ;

therefore, the open portion of the well is f rom 13 to 41 feet (712.2 to

684.2 feet amsl).

On October 11, 1987, Monitoring Well MW-4 was installed to a

total depth of 40 feet. The casing in this well extends to 12 feet ;

therefore, the open portion of the well is f rom 12 to 40 feet (718 to

690 feet amsl).

Monitoring Well MW-5 was constructed as an open-hole well on

October 15, 1987. The procedures used for this installation are

described in Appendix E, Drilling Protocol for Open-Hole Monitoring Well

Completion, of the Supplemental Plan (1). This well was completed to

a total depth of 45 feet near the western edge of the main fi l l area.

The casing in this well extends to a depth of 15 fee t ; there fo re , the

open portion of the well is f rom 15 to 45 feet (712.7 to 682.7 feet

amsl). During the installation of this well, no split-spoon or core

samples were obtained; however, drill cuttings were sampled at one-foot

3/22/89289275G

Page 67: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

intervals. At this location, 3.0 feet of gravel f i l l and silt f i l l fo l lowed

^ by 5.5 feet of silty clay were encountered above 36.5 feet of

fossi l i ferous limestone (biocalcarenite).

Monitoring Wells MW-6D and MW-61 form a well nest near the

southwestern portion of the main fill area. Both wells were completed

as screened and cased wells. On October 22, 1987, Well MW-6D was

completed by reaming the corehole at this location, adding bentonite

pellets for backf i l l f rom 36 to 41 fee t and install ing two-inch diameter

PVC screen and casing. The screened interval at Well MW-6D extends

from 24.6 to 34.6 feet (707.4 to 697.4 feet amsl). Well MW-6I was""•»•

installed adjacent to Well MW-6D. During the installation of this well,

no split-spoon or core samples were obtained; however, drill cutt ings

were sampled at one-foot intervals. At this location, 7.0 feet of gravel

j fill and silty clay were encountered above 11.0 feet of olive-grey<-..>'

limestone. Monitoring Well MW-6I was completed as a two-inch diameter

PVC screened and cased well on October 23, 1987. The screened

interval at this well extends f rom 8 to 18 feet (724.1 to 714.1 feet

amsl).

Af ter each open-hole well was completed (Wells MW-1, MW-2,

MW-3, MW-4 and MW-5), it was developed for approximately one hour

by flushing air and water into the well until the water appeared free of

fine sediments as speci f ied in Appendix E, Drilling Protocol for Open-

Hole Monitoring Well Complet ion, of the Supplemental Plan (1). In

addition, Wells MW-6I and MW-6D were developed by surging and bailing

for one hour until the water appeared f ree of fine sediments.

3/22/89289275G

Page 68: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

Upon completion of the coring and monitoring well installation in

August and November 1987, the well locations, the elevations ol the

ground surface adjacent to the well and the elevations of the top of the

inner (if applicable) and outer well casings were surveyed by standard

surveying methods. All elevations are based on the National Geodetic

Ver t ica l Datum of 1929 and repor ted as fee t above mean sea level

(amsl).

2. Packer Test ing

Westinghouse performed packer tests at the locat ions of Wells

MW-1, MW-2, MW-3, MW-4, MW-5 and MW-6D (Table 2), as described

in Appendix D, Packer Testing Protocol , of the Supplemental Plan (1).

Packer testing was conducted at the coreholes which were subsequently

completed as Wells MW-1, MW-2, MW-3, MW-4 and MW-6D. At Well

MW-5, packer testing was terminated when an oil film was noted on the

test apparatus. The packer test data are provided in the Data

Transmittal (3). Packer testing was performed after the development of

each corehole or well to provide an estimate of the hydraulic

conductivity (K) of the tested section of the well. Double or single

packer tests were performed depending on the zone tested within the

corehole or well. The packers were set at zones within the corehole

or well that were believed to be the most permeable due to solut ion

fea tu res , f rac tu res or other secondary porosi ty fea tu res . At least two

intervals were packer tested in each well.

The K values ranged f rom 9.1 x 10~6 cent imeters per second

(cm/sec) to 2.5 x 10~3 cm/sec. Most K valuer, were approximately 10~4

10 3/22/89289275G

Page 69: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

to 10~5 cm/sec, and the average K value calculated was 2.7 x 10"4

~Ncm/sec. For certain tests, the K values could not be calculated because

either there was no flow into the formation or the test was determined

to be invalid due to leakage above the packers.

3. Slug Test ing

Slug tests were performed at Wells MW-6I and MW-6D to estimate

a K value for the fo rmat ion adjacent to the screened sect ion in each

well in December 1987. The tes ts were pe r fo rmed by causing an

instantaneous change in the ground-water level in each well through the

introduction of a solid cylinder ("slug") of a known volume beneath the

static water level in the well. The change in water level during recovery

to the original water level was measured and timed. Water levels were

, measured as quickly as possible for the first 5 minutes of the test and

at longer intervals as the test progressed. The test was terminated

when the water level in the well reached the static level or when the

test had been conducted for about 30 minutes. The f ield data are

provided in the Data Transmittal (3).«r

The K values were calculated using the Hvorslev Method (7). The

K values calculated are 1.3 x 10'4 for Well MW-6I and 1.5 x 10'4

cm/sec for Well MW-6D (Table 2). This range of values is consistent

with K values obtained during the packer test ing.

4. Down-Hole Geophysical Logging

At the completion of the bor ing/cor ing and well installation

activit ies at the locations of Wells MW-1, MW-2, MW-3 and MW-4, the

11 3/22/89289275G

Page 70: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

coreholes/wells were caliper logged and gamma-ray logged according to

procedures described in Appendix C, Gamma-Ray Logging Protocol, and

Appendix F, Caliper Logging Protocol , of the Supplemental Plan (1).

Well MW-6D was caliper and gamma-ray logged prior to the installation

of the casing and screen. No geophysical logging was conducted at

Wells MW-6I and MW-5.

Caliper logging was performed with a Keck HC-84 caliper logging

system. The caliper probe was cal ibrated before insert ing it into the

well. The probe was lowered to the bot tom of the well and slowly

raised in 1-foot increments. As the caliper probe was raised, the depth

of the probe was recorded in feet , and the diameter of the well was

recorded in inches. If a change in the well diameter was detected, the

diameter of the well was then measured at 0.25-foot intervals. The

caliper logs are plotted on the subsurface logs provided in Appendix 2.

The caliper log field data are included in the Data Transmittal (3).

No large voids were measured at the wells caliper logged. In

general, only small changes (+_ 0.5 inches) in the well diameter were

measured in each of the wells logged. A 0.9-inch increase in the well

diameter was measured at a depth of 13.3 fee t at Well MW-2. This

increase could not be correlated to f ractures or other features observed

in the cores. A one-inch increase in the well diameter was measured

at a depth of 15.3 fee t at Well MW-3 in a shale layer. A 1.1-inch

increase in the well diameter at a depth of 14.4 fee t and a 0.7-inch

increase at a depth of 12 feet were measured at Well MW-4. These

increases were at t r ibuted to f rac tu re zones at these depths.

12 3/22/89289275G

Page 71: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

Gamma-ray logging was performed with a Keck GR-81 natural

gamma-ray logger at the locat ions of Wells MW-1. MW-2, MW-3, MW-4

and MW-6D. In general, clay, silt and shale emit larger concentrat ions

of natural gamma-ray radiation than limestone. A background natural

gamma-ray count was obtained; the probe was then lowered into the

well and slowly raised in 1- foot intervals. As the probe was raised, the

depth of the probe was recorded in fee t and the gamma-ray counts of

the format ion were recorded. The gamma-ray logs are plotted on the

subsur face logs provided in Appendix 2. The f ie ld data f rom the

gamma-ray logging are included in the Data Transmi t ta l (3).

At Well MW-1, small gamma-ray peaks were recorded at a depth

of 30.5 feet in an area of mud-fi l led solution features and at a depth

of 38.5 feet in the limestone bedrock in an area of mud-filled fractures.

At Well MW-2, small gamma-ray peaks were measured in the limestone

bedrock at depths of 13.5 feet, 16.5 feet and 33.5 feet. These peaks

were attr ibuted to micritic l imestone streaks noted in the core samples.

At Well MW-3, a large gamma-ray peak was recorded in a fractured

dolomitic shale f rom 14.6 to 18.6 feet. In addition, at this well, two

small gamma-ray peaks were recorded at depths of 20.5 feet and 40

feet in a micritic limestone. A small gamma-ray peak was measured at

a depth of 16 feet in the limestone bedrock at Well MW-4. This peak

was attributed to mud fil led f ractures at depths of 15 and 16 feet. At

Well MW-6D, a large gamma-ray peak was measured from 21 to 22 feet

in the limestone bedrock. This peak was attributed to the bentonite

pellet seal installed above the sand pack around the well screen.

13 3/22/89289275G

Page 72: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

The bottom of the unconsolidated material was also confirmed via

the gamma-ray logging conducted at Wells MW-1, MW-2. MW-3, MW-4

and MW-6 by noting the change f rom higher gamma-ray counts in the

clay soil to the lower gamma-ray counts associated with the limestone

bedrock.

5. Ground-Water Elevat ion Measurement

Three rounds of ground-water elevations were obtained on August

9, August 22 and September 9, 1987, f rom the coreholes that became

Wells MW-1, MW-2, MW-3 and MW-4 (Table 3). In addition, the ground-

water elevations were measured during the coring; however, because

water was added into the corehole, the data obtained could not be

evaluated. On November 8, 1987, ground-water elevations were obtained

from Wells MW-1, MW-2, MW-3, MW-4, MW-5, MW-6I and MW-6D. Stream

elevations were also obtained from Gauge Stations GS-1, GS-2, GS-3 and

GS-4 on this date. In addition, ground-water elevations were obtained

at all monitoring wells during the quarterly ground-water sampling events

in March, June, September and December 1988. During two of the four

events, water elevations were also measured at the gauge stations.

Water elevation measurements were measured to the nearest 0.01 foot

with an Acta t Olympic Well Probe and an engineer 's ruler.

Ground-water f low direct ions and gradients are discussed in

Sect ion III D, Hydrogeology.

14 3/22/89289275G

Page 73: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

D. Task 2.4 - Ground-Water Sampling

^ Af te r installation, each monitoring well was sampled lour times on a

quarterly basis. The monitoring schedule was set for th in the Data

Transmit ta l (3). Ground water was sampled according to the Ground-Watej^

Sampling Protocol provided in Appendix H of the Supplemental Plan (1). All

ground water was analyzed for PCBs in accordance with the requirements of

the EPA document, "Test Methods for Evaluat ing Solid Waste:

Physical/Chemical Methods" (8).

For each of the four rounds of g round-wa te r sampl ing, West inghouse

submitted to the part ies of the Consent Decree the fol lowing data for each

well sampled:

a. Ground-water elevation measurements

b. Temperature measurements

,i c. pH measurements

d. Specific conductance measurements

e. PCB analytical results (to a detect ion level of 0.01 ppb)

f. Ground-water elevation contour map

•wThese data were compiled into three reports previously sent to the

p;arties of the Consent Decree in August and September 1987 and January

1989 (4, 5, 6). The details regarding each ground-water sampling event,

including quality assurance results, are provided in these reports. Herein, the

temperature, pH and speci f ic conductance f ield measurements and the PCB

analytical results are presented on Table 4. The ground-water elevations are

included on Table 3. The ground-water elevation contour maps are presented

in Section III D, Hydrogeology.

15 3/22/89289275G

Page 74: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

In the four sampling events, PCBs were not detected in all four events

in the ground-water samples obtained f rom Wells MW-1, MW-2 and MW-4;

PCBs were detected once in the ground-water samples obtained from Well

MW-3; and PCBs were detected in all four events in the ground-water

samples obtained f rom Wells MW-6I and MW-6D. Because an oil was

encountered in Well MW-5 during the f i rs t sampling event, and the PCB

analytical resul ts f rom this well (1,100,000 to 430,000 ppb) indicated the

presence of PCB oil, this well was not sampled in the last three quarter ly

sampling events. It is a standard pract ice not to sample the ground water

f iom a well with a non-aqueous phase product present, but to record the

presence of the product through a visual inspection. In two of the three last

quarterly events, an oily sheen was present on top of the water column at

Well MW-5. A summary of the PCB concentrations in ground water is

depicted on Figure 3.

16 3/22/89289275G

Page 75: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

SECTION III - DATA EVALUATION

A. Topography and Geomorpholoqy

The Bennett's Dump Site lies at elevations ranging from 710 feet to

750 feet amsl. The topography near the site is character ized by numerous

rectangular wa te r - f i l l ed pits due to quarrying the building stone unit of the

Salem Limestone. The main f i l l area is on a gently westward sloping hillside

east of Stout Creek. To the south of the si te, two st reams join forming

Stout Creek, which f lows north from the site area. The site is located along

the eastern margin of the Mitchell Plain physiographic region, a low plateau

developed on limestones of the Mississippian Blue River and Sanders Groups

(9).

B. Unconsolidated Material

The unconsolidated material at the Bennett 's Dump Site consists of soil

and fill. The predominant soil is a yellow/red/brown, s t i f f silty clay that

ranges in thickness from 2.65 to 5.5 feet. This soil was encountered during

the installations of Wells MW-1, MW-2, MW-5 and MW-6D (Figures 4A. 4B and

4C), in the 60 shallow test borings throughout the main fill area, and in the

15 shallow test borings on the per imeter of the main fill area in April 1983

and May 1984, respectively (2). A red/grey, st i f f clayey silt was encountered

during the installation of Wells MW-1, MW-3 and MW-4 (Figures 4A and 4B)

and in f ive shallow borings on the perimeter of the main fil l area obtained

in May 1984 (2). This soil is gradational with the clayey silt and ranges in

thickness f rom 1.6 feet to 4.0 feet .

17 3/22/89289275G

Page 76: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

Fill consisting of a very compact gravel (railroad bed material) was

encountered in the upper three feet of unconsolidated material in the western

portion of the site along the old railroad bed. This gravel f i l l , ranging in

thickness f rom 1.4 feet to 3.0 feet, was encountered during the instal lat ion

of Wells MW-5, MW-6I and MW-6D (Figures 4A and 4C), and in nine shallow

test borings obtained by the EPA between the main fill area and Stout Creek

in June 1983 (2). Other f i l l mater ia l consist ing of a mix of c lay, l imestone

and coal was encountered during the instal lat ion of Well MW-1 (Figures 4A

and 4B). Information on the fi l l associated with the dump areas is provided

in the Phase I Progress Report (2).

C. Bedrock Geology

1. Stratigraphy

The bedrock unit encountered at the site is the Salem Limestone

of the Sanders Group. This unit is of Mississippian Age. In the core

obtained, the Salem Limestone is primarily a light brownish/grey/olive

limestone (calcarenite and calcilutite) (Figures 4A through 4C). The

average th ickness of the rock cored was approximately 35 feet.

Lithologic character ist ics, fossi l density, and structural and solution

features vary in the cores examined from the site; however, no significant

strat igraphic changes could be corre lated and no useful marker beds

were identi f ied. A 0.25 to 1.6-foot thick, white, weathered and

fragmented l imestone (Figures 4A, 4B and 4C) was encountered during

the installation of Wells MW-1 and MW-2. A grey/black shale ranging

in thickness from 0.1 to 2.77 feet was encountered during the installation

of Wells MW-3 and MW-6D (Figure 4A); however, this unit was only

18 3/22/89289275G

Page 77: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

encountered at these two locations and could not be correlated

throughout the site. This shale may represent the Somerset Shale

member that separates the Salem Limestone f rom the underlying

Harrodsburg Limestone. Fossil f ragments consist ing of fenest ra te

bryozoans and crinoids were noted in all cores. Honeycomb weathering

was noted in the cores obtained at the locations of Wells MW-1, MW-4

and MW-6D (Figures 4A and 4B). This weathering feature was correlated

between Wells MW-1 and MW-6D. At three of the six well locations, the

deeper bedrock is composed of f iner-gra in ca lc i te part ic les as noted by

the "grades micr i t ic" notat ion in the c ross-sec t ions (Figures 4A, 4B and

4C). The micritic limestone was tentatively correlated between some well

locations.

2. Structure

Bedrock in southern Indiana generally dips west to southwest at

approximately 30 feet per mile. In the Salem Limestone, at the

Bennett's Dump Site, no useful marker beds were encountered that could

be used to prepare bedrock structure maps.

Fractures were noted in the rock cores obtained at the locations

of Wells MW-1, MW-2, MW-4 and MW-6D. The f rac tu res noted at the

locations of Wells MW-1, MW-2 and MW-6D were ver t ica l and those at

the location of Well MW-4 were horizontal. The horizontal f ractures were

noted in the upper portion of the cores while the vert ical f ractures were

noted in the lower portion of the cores. Most of the f rac tu res were

fil led with either calcite or mud. Based on the K values determined

from the packer tests conducted in these f . a c t u r e zones and the zones

19 3/22/89289275G

Page 78: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

with few f rac tures , the presence of f rac tures does not appear to be

directly correlated to the magnitude of the K value. A vertical f racture

was also noted on the eastern wall of the quarry opposite Gauge Station

GS-1 (2). In addition, several vert ical weathered jo :nts were observed

in this quarry.

3. Subsur face Solution Features

Few subsurface solution features were noted in the cores obtained

at the Bennett 's Dump Site. Small solution voids (0.2 inches and less)

were noted in the cores obtained at the locations of Wells MW-1, MW-2

and MW-3. The solution voids in the cores from Wells MW-2 and MW-3

were shallow, 6.5 and 10.95 feet , respectively, while the solution voids

in the core from Well MW-1 were lower, 30.8 feet in depth. A few

small vugs, some calcite filled, were noted in the upper 10 feet of core

obtained at the location of Well MW-6D. As discussed previously,

honeycomb weathered zones were noted in the cores obtained at the

locations of Wells MW-1, MW-4 and MW-6D.

D. HvdrogeoloQV

The ground-water flow system at the Bennett 's Dump Site consists of

three components: recharge areas, f low areas and discharge areas. Based

on the topography near the s i te , recharge to the f low system occurs in the

topographical ly higher areas east of the site and closer to the site through

the open water - f i l led quarries and old quarries which have been backfi l led

with quarry rubble. During quarrying, ground-water seepage was noted in the

bot tom two f l oo rs . Each f loor is approximately 10 feet and three to four

20 3/22/89289275G

Page 79: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

f loors were quarried depending on the location. From this information, the

predominant origin of the water in the quarr ies is ground water. However,

the elevations of the water sur face measured in the quarry east of the site

at Gauge Station GS-1, are higher than would be expected for the ground-

water table at this area; therefore surface water runoff is likely an additional

source of water in this quarry.

The ground-water f low system exists in the Salem Limestone and in the

unconsolidated material that is hydraulically connected to the bedrock beneath

the si te. During the Phase 2 drilling, sa tura ted condi t ions were not noted

in the unconsolidated material; however, during previous subsurface

investigations, saturated soil and fill material were noted throughout the area

of the main site, especially in the central and southwestern portions of this

area. In the bedrock, ground-water flow occurs in fractures, joints and

solution-enlarged features, and to a lesser degree in bedding planes.

Ground-water flow may also occur in the primary pore space of the

calcarenite (estimated to be approximately 5 percent [11]), although f low in

solution enlarged features is likely predominant (11).

Based on the ground-water elevation data col lected f rom the monitoring

wells in August and November 1987, and March, June, September and

December 1988, ground-water flow is to the west-northwest towards Stout

Creek for all measurement periods (Figures 5A through 5F). In the southern

portion of the site, the ground-water f low direction trends more direct ly west

toward Stout Creek while in the centra l and nor thern areas of the site, the

ground-water f low direction trends west -nor thwest toward Stout Creek.

Horizontal ground-water gradients varied f rom approximately 0.05 feet / foot to

0.03 feet / foot in the southern port ion of the site and f rom approximately

21 3/22/89289275G

Page 80: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

0.03 feet/foot to 0.02 feet/foot in the central and northern portions of the

7

•-'----" site.

Precipitation data was collected and compared to the ground-water

elevations measured during the sampling events. A total of 1.4 inches of

precipitation was measured prior to the March 1988 sampling event, and a

trace amount of precipitation was recorded during the March 1988 event (10).

The highest ground-water elevations were measured in March 1988. Beginning

in early to mid-April through May 1988, very little precipitation was measured

in the Bloomington area (10). During the June 1988 sampling event, a t race

amount of precipitat ion was recorded (10). A few signi f icant precipitat ion

events (greater than 1.0 inches) occurred in July, August and early September

1988. However, the amount of precipitation was less than normal; the

Bloomington area was considered to be in drought conditions. Thus, an

vy^ overall decrease in ground-water elevations was observed from the March

1988 sampling event to the September 1988 sampling event. The lowest

ground-water elevations were measured in September 1988. Throughout the

fall of 1988, the amount of precipitation increased; an increase was observed

in the ground-water elevations measured during the December 1988 sampling

event.

The ground-water discharge area of the flow system is Stout Creek. The

water levels measured at Wells MW-6I and MW-6D, as well as at Well MW-

5 and Gauge Station GS-2, indicate that the hydraulic potential in the lower

bedrock is higher than the hydraulic potential in upper bedrock at the

bedrock/unconsolidated material in ter face and Stout Creek, respectively.

Therefore, vertical ground-water flow is upward in this area, indicating ground-

water discharge into the c reek .

22 3/22/89289275G

Page 81: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

The two seeps delineated in Phase 1 (2), within the limit of the main

fill area, also may be ground-water discharge points (Figure 2). Ground

water seeping from the bedrock in this area then f lows toward Stout Creek.

Stout Creek f lows north f rom the Bennett 's Dump Site. A tr ibutary

stream enters the creek to the west near the northwestern portion of the site.

Water f rom the quarry operat ions is also added to the creek discharge near

the southwest end of the main f i l l area.

E. PCB Analy t ica l Resu l ts

The ground water at the Bennett's Dump Site was sampled from six wells

four times in 1988 (Table 4, Figure 3). PCBs were detected in the ground

water sampled from the wells that are hydraulically downgradient of the main

fill area, Wells MW-3, MW-6I and MW-6D. In addition, a PCB oil was

observed at Well MW-5 which is also hydraulically downgradient of the main

fill area. No PCBs were detected in the ground water sampled from Well

MW-2 which is hydraulically upgradient of the main f i l l area and hydraulically

downgradient of the 0.5 acre fill area. Well MW-4 monitors the ground water

near the sate l l i te f i l l area, and no PCBs were detected at this well. Well

MW-1 is hydraulically upgradient of the main fill area, and no PCBs were

detected at this well. At the Bennett 's Dump Site, the areas where PCBs

were detected and the hydraulically downgradient areas are coincident,

indicating PCB migration in the ground-water f low system.

23 3/22/89289275G

Page 82: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

SECTION IV - SUMMARY

The following discussion summarizes the principal site conditions relative

to the geology, hydrogeology, and distribution of PCBs in ground water at the

Bennett 's Dump Site.

Subsurface conditions beneath Bennett 's Dump are character ized by a

relatively thin layer of unconsol idated material overlying bedrock. The

unconsolidated material consists primarily of silty clay that grades to clayey

silt at some locat ions. Along the wes te rn port ion of the s i te, approximately

1.5 to 3 feet of gravel f i l l , former ly a railroad bed, overl ies the silty clay.

The uppermost bedrock unit underlying the site is primarily light

biownish/grey/olive limestone of the Salem Limestone. Bedrock in southern

Indiana dips to the west and southwest at approximately 30 feet per mile.

However, no useful marker beds were encountered in bedrock underlying the

site. The Salem Limestone exhibits both horizontal and vertical fractures filled

with calcite or mud. Solution features in the form of small voids, vugs and

honeycombed weathered zones were also evident in the bedrock.

Ground water at the site is present within the bedrock and, at some

locations, within the overlying unconsolidated material. Ground water in the

bedrock is transmitted primarily through fractures, joints, solution features and,

to a lesser degree, through bedding planes. Ground-water f lows from the

Bennett 's Dump Site to the west -nor thwest toward Stout Creek under a

hydraulic gradient of between 0.02 and 0.05 fee t / foo t . A comparison of the

hydraulic head measurements at the stream and within the bedrock indicates

that Stout Creek is the discharge area for the f low system underlying

Bennett 's Dump. Seasonal ground water f luctuat ions in the bedrock were

24 3/22/89289275G

Page 83: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

typical; maximum water levels were experienced in the spring and minimum

levels in the fa l l . Nevertheless, no s ign i f i cant changes in the direction of

ground-water f low were noted for data obtained through the period of the

investigation.

No PCBs were detected in ground-water samples col lected at Wells

MW-1. MW-2 and MW-4 in four sampling events. However, PCBs were

detected in the ground-water samples obtained f rom four wells downgradient

of the site, Wells MW-3, MW-5, MW-6I and MW-6D.

25 3/22/89289275G

Page 84: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

SECTION V - REFERENCES

1. Blasland & Bouck Engineers, P.C. (or Westinghouse Electric Corporation.Supplemental Hvdrogeologic Investigation Plan. Winston Thomas Facil i tyand Bennett 's Dump. August 1986.

2. Blasland & Bouck Engineers, P.C. for Westinghouse Electr ic Corporation.Phase I Progress Report Winston Thomas Faci l i ty and Bennett 's Dump.January 1987.

3. Blasland & Bouck Engineers, P.C. for Westinghouse Electric Corporation.Data Transmi t ta l Winston Thomas Faci l i ty and Bennett 's Dump. May1988.

4. Blasland & Bouck Engineers, P.C. for West inghouse EnvironmentalServices. Quarter ly Ground-Water Sampling Resu l ts , Quarter ly SamplingEvents 1 and 2 of 4, March 8-10 and June 6-9. 1988. Bennett's Dumpand Winston Thomas Facil i ty. Supplemental Hvdrogeologic Investigation.Bloomington. Indiana. August 1988.

5. Blasland & Bouck Engineers, P.C. for West inghouse EnvironmentalServices. Quarterly Ground-Water Sampling Results. Quarter ly SamplingEvent 3 of 4. September 5-8. 1988. Bennett's Dump and WinstonThomas Facility. Supplemental Hvdrogeologic Investigation. Bloomington.Indiana. October 1988.

6. Blasland & Bouck Engineers, P.C. for Westinghouse EnvironmentalServices. Quarterly Ground-Water Sampling Results, Quarterly SamplingEvent 4 of 4. December 5-7. 1988, Bennett's Dump and Winston ThomasFacility, Supplemental Hvdrogeologic Investigation, Bloomington. Indiana.January 1989.

7. Hvorslev, J.M., Time Lag and Soil Permeability in Ground WaterObservations. Bulletin 36 of U.S. Corps of Engineers Waterways Exp.Station, V icksburg, 1951.

8. U.S. Environmental Protection Agency. Test Methods for Evaluating SolidWaste: Physical/Chemical Methods. EPA SW-846. 2d ed. July, 1982.

9. Gates, G.R. Geologic Considerations in Urban Planning for Bloomington,Indiana. Indiana Department of Conservation, Geological Survey, Reportof Progress 25, 1962.

10. Blasland & Bouck Engineers, P.C. for Westinghouse EnvironmentalServices Phase 1 Report , Supplemental Hvdrogeologic Investigat ion,Lemon Lane Landfi l l . Draft , November 1988.

11. Palmer, A.N. A Hvdrologic Study of Indiana Karst. Ph.D. Thesis, IndianaUniversity 1969.

3/23/890688317P

Page 85: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

00

m

TABLES

Page 86: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

TABLE 1

MONITORING WELL CONSTRUCTION DETAILSBENNETTS DUMP

BLOOMINQTON, INDIANA

WeiNo,

MW-1

MW-2

MW-3

MW4

MW-5

MW6I

MW-60

Top ol Depth ctProtective Protective Protective Screen Gravel GroutCasing Ground Casing In Coring Well Wet! Casing Interval Pack Interval

Elevation1 Elevation1 Subsurface Depth Depth Diameter Diameter Type of Elevation1 Elevation1 Elevation1

(H)_ (K.I _ (It ) _ (HI flU (inches) (Inches) Construction (IU (HI (til

73869 7365 17.5 44.0 44.0 5-5/B 6 ID Open N/A N/A 7365-719

74467 7422 11.0 420 42.0 5-5/B 6 ID Open N/A N/A 7422-7312

72769 7252 130 41.0 41.0 5-5/8 6 ID Open N/A N/A 7252-712.2

732 80 730.0 120 400 40.0 5-5/8 610 Open N/A N/A 730-718

72761 727.7 150 N/A 45.0 5-5/8 6 ID Open N/A N/A 727.7-712.7

73206 732.1 1.2 N/A 18.0 2.0 6 ID Screened 724.1-714.1 725.8-714.1 732.1-728.1

73199 7320 135 41.0 34.6 20 610 Screened 707.4-«97.4 71086960 7327128

BentoniteSeal Elevation1 General

(HI Geologic Log

N/A 0-5454-8989-10.5105-1111-44

N/A 0-484.842

N/A 0-353.5-4.34 3 66^77-14514.5-17.317.3-41

N/A 0-44 6 565-77-40

N/A 0-141.4-303.0-858 5 9 09.0-450

7281-7258 0-3030-707.0-18

7128-7108 0-3030-7.070-36836836936941.0

Red-Brown ClayGrey Cloyey S*WliitP Iwrtr'ipNo RproveryBrownish-Grey Limeslone

Yelowish-Red Sdty ClayGiey Umeslone

Red-Grey Clayey Sr»Red-Yellow Clay & SandDark Grey Clayey SiftNo RecoveryGrey 1 'nwsfoneDark Grey ShaleGrey Limestone

Red Grey Clayey SitGrey Clayey SitNo RecoveryGrey Brown Limeslone

Gravel FitBlack S*Blown ClayWeathered LimestoneGrey Bcown Limestone

Gravel FrlBrown Silly ClayOlrve Grey Limeslone

Gravel FinBlown Si«y ClayOlrve Giey LimestoneBlack ShaleOlive Grey Limestone

Note: 1 Elevations are based on National Geodetic Vertical Datum at 1929 and expressed as (eet above mean eea level.

0688317C

Page 87: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

TABLE 2

HYDRAULIC CONDUCTIVITY VALUESPACKER TESTING AND SLUG TESTING

BENNETT'S DUMPBLOOMINGTON, INDIANA

Pressure Test IntervalWell # (psi) (ft. from ground level)

MW-1 10 24.5-3120 24.5-3130 24.5-3110 20-4420 20-4430 20-44

HydraulicConductivity(cm/sec)

8.0 x 10'5

1.5x 10'4

1.7x 10'4

3.1 x 10'4

2.6 x 10'4

2.5 x 10'4

TestDate

7/29/87N •

H H

W U

H H

• H

Notes

Test from 25-44 notvalid.

MW-2 112030102030

25.5-3225.5-3225.5-3214-4214-4214-42

4.9 x 10'5

1.3x ID'4

1.8 x 10'4

3.2 x 10'5

1.4 x 10'5

8.2 x 10'5

8/4/87• I

M •

8/5/87

MW-3 102030102030

13-14.413-14.413-14.422.5-2922.5-2922.5-29

6.0 x 10'4

1.0 x 1Q-3

2.5 x 1Q-3

No Flow9.1 x 10"6

2.1 x 10'5

8/6/87

MW-4 102030102030102030

12-15.512-15.512-15.519-25.519-25.519-25.512-4012-4012-40

6.4 x 10'5

6.7 X 10'4

6.5 X 10'4

2.4 x 10'4

4.1 x 10'4

4.3 x 10'4

9.3 x 10'5

9.6 x 10'5

1.8x 1Q-4

7/26/87

2189199C2/24/89

Page 88: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

TABLE 3

WATER ELEVATIONSBENNETTS DUMP

BLOOMINGTON, INDIANA

Well No

MW 1

MW-2

MW3

MW-4

MW5

MW6O

MW6I

GS-1

GS 2

GS 3

GS-44

GroundElevalion

7365

7422

7252

7300

7277

7320

732.1

74609

N/A

N/A

75592

Steel Casing(Outer)Elevation1

73869

74467

72769

73280

727.61

731.99

73206

N/A

N/A

N/A

N/A

PVC Casing(Inner)

Elevation1

N/A2

N/A

N/A

N/A

N/A

73173

731.46

N/A

N/A

N/A

N/A

Stream GaugeStationElevation1

N/A

N/A

N/A

N/A

N/A

N/A

N/A

74609

724.18

73087

755.92

B/9/B7

734.59

731.10

72034

725.10

Nl3

Nl

Nl

Nl

Nl

Nl

Nl

B/22/87

73422

73099

720.13

723.41

Nl

Nl

Nl

Nl

Nl

Nl

Nl

9/9/B7

73348

73084

71997

72248

Nl

Nl

Nl

Nl

Nl

Nl

Nl

Water Elevations1

11/B/87

73358

73059

71996

72335

72260

72753

72703

73826

72206

72875

746«4

3/9/BB

73R21

73361

72144

72580

72451

73021

72730

_ 5

-

6/6/B8

73430

73083

72004

72386

72298

72830

72743

73865

721 88

72904

74650

9/7/88

732.50

7?910

71953

72073

72238

72723

72670

_

_

73554

73057

72057

71940

72330

73030

72781

73845

722 Of)6

73052

Notes: 1 All elevations in leet above mean sea level and based on National Geodetic Vertical Datum of 1929.

2 N/A - Not applicable.

3 Nl - Well or gauge station not installed at this time.

4 GS-4 is located east ol GS-1 but is not shown on Figure BD-2. The exact location of GS-4 was not surveyed.

5 -- - Not measured.

6 Elevation represents a ponded water elevation rather than a true stream elevation.

3/21/B90188317P

Page 89: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

TABLE 2 (Cont'd.)

Well #

MW-5

Pressure(psi)

102030102030

Test Interval(ft. from ground levul)

40-4540-4540-4535-4535-4535-45

HydraulicConductivity(cm/sec)

No FlowNo FlowNo FlowNo FlowNo FlowNo Flow

TestDale

10/15/87U b

M H

10/15/87H h

U N

MW-6D

MW-6I

MW-6D

102030102030102030

N/A

N/A

13.5-2113.5-2113.5-2121-35.721-35.721-35.736-41.536-41.536-41 .5

1.2x 10'5

3.4 x 10'5

4.3 x 10'5

1.3 x 10'4

1.3 x 10'4

1.0x 10'4

No Flow5.5 x 10'5

5.8 x 10'5

8-18

24.6-34.6

1.3x 10'4

1.5 x 10'4

10/22/67

• H

II •

10/21/87• ft

10/22/8710/21/87

12/9/87

12/9/87

Notes

Packer Testterminated when oilwas detected inWell MW-5.

Packer Testperformed priorto well materialinstallation.

Slug Test

Slug Test

2189199C2/24/89

Page 90: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

GROUND-WATEFTATOLYriCAL RESULTSBENNETTS DUMP

BLOOMINGTON, INDIANA

Well No/Sample

MW 1MW 2MW3MW4MW 5MW 5 DuplicateMW 61MW 61 DuplicateMW6D

Temperalure

Match1988

165150138130135135110N/A119

fdegfe

June1988

15014014.1

n°N/AJ

N/A150N/A150

es C)

September1988

145160150130N/AN/A150N/A130

December1988

13.9

130120130N/AN/A13.0

N/A120

March1988

7.8108838.110410.4

78N/ABO

June1988

7.27.35

827.6N/AN/A8.5N/A85

pH(PH unlit)

September1988

707.07.47.2N/AN/A7.0N/A7.1

December1988

697.17.07.0N/AN/A7.0N/A68

SpecificConductance

March1988

400359352510248248360N/A418

fumhos)

June Sept ember Decem1988 1988 1988

429420370560N/AN/A430N/A430

390 400420 390380 330520 550N/A N/AN/A N/A450 450N/A N/A425 420

PCB Concentration[ppb]1

March1988

ND2

NONDND

1,100.000430,000

30N/A042

June1988

NDNDNDNDN/AN/A1931597.3

Sep|embet

1988

NDND

014ND

N/AN/A1 71.10.3

1988

NDNDNDND

N/AN/A

21027322

Notes

1 ppb - Parts per billion2 ND - Not detected to a Detection Level ol 0.1 ppb3 N/A - Not applicable

02B8317P1/30/89

Page 91: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

•noc3Dm

FIGURES

Page 92: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

APPENDICES

•oTJmzoomCO

Page 93: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

/7&ry *•>»"»«> « »ooctt— "2r ~~j INOINUM, ».c.

SOIL DATA

t-b.UJ

f.

SA

MP

LE

S

1

SA

MP

LE

N

O

RE

CO

VE

R* (f

T)

- S| lit 5

:ffl• -• Air ro

— -

UJ

5Z

ROCK DATA

o

a

Io0:i*.

g%

R

EC

OV

ER

Y

Q0cc

o5

RA

TE

W

IN /

FT

)" ! R

n-j1 1— IB nilies of sp itspoun pcnetr

I

N, A

1

-1t a ryed dt

dr lilt

1

A\ ~

1c

Not

d sariiurla

,„„

dpph

nples

r Ihj

able

SUBSURFACE LOG KEY

SOIL/ROCK DESCRIPTION

SOIL /ROCK CLASSIFICATION

QO Ruck Quality Degree - thesum of the lengths of pieceslour inches long or greaterdivided by the length ofthe core.

tion .

Soil/Rock Classif ications

(SYR 3 / 2 ) Color of soils using Munsell ColorChart(5CY 6/1) Color of rock using Geological

RO

CK

F

EA

TU

RE

S

H

t\

mn

Ce

1GE

OLO

GIC

CO

LUM

N

Rock

MB-n{7MBf -

- Irf -

Hf -— If -

- vr -- haf

BR2

o -

1 - 1s -P -

gmgl -c -

- — he -

Hit> st -

Sty

olugic CoIW

EL

LC

OLU

MN

Feature

ractureIrregulilow anthoiizonnc linedvert icalhigh a

M - brokvuggy

wedlhertjxidued

amlneasolutionsolutionmud in

greenglaucon

calcitehoneyccnot rechi/died

stringer- sty lo 1

lumn Sy

' //

~_~

•V" • "t,

; -;v o

T^—T—

Clay

Si l t

Sand

PROJECT TITLF

PHOJFCT MilURFR

LOCATION

Cl ASSiFlFn RY rut

ELE

VA

TIO

N (F

T)

CKFD BY

GAMMA RAY

RAN

;;Symbol*. I

ber of MB

r fracturele fractureal fracturefracturefracture

igle fractu

d

ned

enlargeenlargepenlng

nud intic

nib weoveredfract i rse

nbols

menmen

ope

iihe

e

E

IGF TIUF CHM^TANT

COUNTS/MINUTE

\ DASHEO LINE INUICATtS A SCALE) CHANCE FROM O - IOO c/m TO IOO I

Abbreviations

n a runCondition <jf Fr.,

1 - in

3 - r , ,L

e

t wt lh Mdlma

Ting

-

JocA

-

k

.jli

-

-

-

-

-

-

-

Gravel

Fill

Do lomite

Limestone

Shale

Si 1 tstone

IF OF CAS NG E L E V A T I O N

1 1 U_J 1 1 '

-

-

CALIPER

IOLE luAMETth

(INCHt'S)

-

-

-

-

UATF

PERMEABILITY

o2

UJ

0Z

H

UJ

X

K)

Oz

<nu

4

i

)ATE

NOTES

at 10 pai .

Page 94: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

/ ~J# J UASLAND* iOUCK

~/f ~J INGINKRS, PC.

rD(L D A T A

i

aUJn

in

St.

rc

•q

O

•I

-

-

^

fl

--

U.

ct

oo

- L

;.u

i .1.

1 .S

U. 2

_ -

\

--

1

~

~

._

ROCK D A T A

o

z

--

,'

-i

6Q.

-

-

1 1

Tt

-

17

0

I

I

-

!0~

%

RE

CO

VE

RY

• •

_..

::115

170

~ta

n

--

I

13

92

5

•Jcr

;-

f—

—4

5

3

it

SUBSURFACE LOG

SOIL/ROCK DESCRIPTION

SOIL/ROCK CLASSIFICATION

0-2 75' CLAY, limestone, coal, wet at 2.7',

(F ILL)

2 75' -5. 4' CLAY, ailty. reddish-brown (4/4).moist

5 4' 8 9' SILT, clayey, dark gray (4/1).earniy. wet at 8.9'.

8 9 - 1 0 . 5 ' LIMESTONE. while (8/1).

fragmented, weathered

Soils Boring Terminated at 10.51 0 5 - 1 1 0 ' No Recovery

1 1 0 - 1 3 6 " LIMESTONE, light brownish 9'«y. (B, [|lb

1 3 6 - 2 3 6 ' Credea to light gray LIMESTONE

RO

CK

F

EA

TU

RE

S

I G

EO

LO

GIC

1 C

OL

UM

N

-.

"-

^=f1

1

RFA'.E E L E V A T I O N _7 36i ^ _£l_, DAT £_£/ 2tL/&7)P C* CASING E L E V A 1 H - N ? 3 8 . 6 9 tt

IW

EL

LC

OL

UM

N

V

cto10

O

1 '. i

;1

6*

Dia

me

ter

Ste

e

prvn.ifrT

NUMBER ' ' 2 . 1 5•--- .... .. 1

LOCATinN Bennett's Dump

CIA^IFIFDHY JLJ r i l^^nRV ( SS/SI 'S

GAMMA RAY

EL

EV

AT

ION

(F

T.)

E738.ffl_

736.5

733.116

731.5

726.5

721.5

RANGE

'O

-

-

_J9*_ TIME CONSTANI _[°_Sf r

COUNTS/MINUTE

20 10 40 50 60 TO BO au

\ -

(979/87) ^x

; /;

:

v

_J — 1 — 1 — t — 1 1 1 ,

CAI 'PER

lOLt MIME Tth

(IH1 ' IKS)

2 ' 6

-

-

i

1 1

hrtl E ] ' dl/_7

•EHMEABILITr

0

t-

O oz

t-

i -Arc 7 /29 /8

BOR1NG/CORING/WEL 1 NO

SHFFT 1 OF.

NOTES

June 22. 1987 • Soil boring B 1 wa^drilled using a hollow stem auger. IIUCK

through hollow stem augers using a 2 t

a 140 Ib hammer until spoon re fusa l at10 5'

July 24. 1987 - Bedrock at B 1 wascored using a Gardner Denver 15-W ait

d iameter . 3' long, double barre l core i *The drilling tluid consisted at misiud anThe boring was reamed with a 7 7/b'tncone air rotary bit to seal a 6'diameter casing at 17 5 below grade

bentoriut) grout mixture iramied (hrougnthe annulus The grout was allowed tucure lor over 48 hours

July 28. 1987 - Beo/och was cored usinga 3' diameter. 14' long, split barrui

surface

July 29. 19B7 - Packer tes t ing wa*

August 22. 1987 - Gamma ray lugging

October 10. 1987 - Core holu waareamed trom 3* diameter to 5 5/bdiameter

October 10. 1987 • Well was devbiopeaby flushing air and mist mio bora holt*

November 8. 1987 - C flipper logging we*conducted

Page 95: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

/_"J/r~~~7 BIASIAND 1 BOUCKjp ~f ENCINttBS. P.C.

5i.lt [>-•.! A

It

iu

• i S

SU

TO

22•j

:__

--

It

-

-

::

--

_~

1

-

-

~

--'

~

*<JCK DA 1 A

1'

-

irr o

-

Z

a

--

-

-

-

L

0

IT

._.

-

"

_.

I

I

a

!

5 ~

5

--

b

b

\"

- -

1

y

SUBSURFACE LOG

SOIL/ROCK DESCRIPTION

SOU /HOCK ClASSIF ICATION

Sty

23 6 -24 81 Giddes to light brownish grayL IMESTONE

24 8-26 1' Grades to light gray LIMESTONE

26 1 30 81 LIMESTONE, light brownish gray, Honeypredominantly crinoid f ragments ,•honeycombed weathering' at 26.5' and 28 4-29 6'. solution fea tures with brown mud at30 a1

Money

»fHf/mA

JO 831 7' Grades to lignt gray LIMESTONE. WZ(15) Mb

31 7 - 3 4 5' Grades to light brownish gray BRZNLIMESTONE.

Vh

35 5 -37 0' Grades to light gray LIMESTONE. VF

37 0 -44 .0 ' LIMESTONE, light gray, micntlcver t i ca l F r a c t u r e 35 .8-381 ' .

Sty

ROCK

FEA

TURE

S

llmh

am

tfwSxTOW?

$8?

i

1GE

OL

OG

IC

CO

LU

MN

-p1'

i

i

i

I

i

i

i

R F A f F F I F V A T K 1 N ""• ' "• • n/UF O ' - 'WB/

P OF CAS NG F L E / A torj / J 'a -6 9 fu

(W

EL

L

CO

LU

MN

ao.C

o0

CttdO

PROJECT NUMBER "L'.M

LOCATION Bennett's Dump

CLASSIFIED nv JLJ rnri-KEo py Cb ./bl^b

GAMMA RAY

ELE

VA

TIO

N (F

Ti

'16.5

711.5

706.5

701.5

B36.5

IIANGF 101< _ TIME COriSTANI ]°._5" •

COUNTS/MINUTF

10 20 30 40 Sp 60 TO BO 1*0

:'

-

!— L

ii

i

-

V

\ :

CAL 1'FR

i«)l E [i .'.ME T i l .

(INC MI S)

2 - 1 6

-

i 1 nut /.Bil llr

!;;

Ia-'-

1

y

f .

O > ;

S*'

1

1f3i

0

t-

HORING/..ORING/WEL, NO MW_- MCON T )

N O T E S

Page 96: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

/ ~J$" J IIASLAND i flOUCKjjf ~J ENGINEERS. P.C.

•,fjiL LJAIA

iQ

SL

K

i

l

-

-

Lt

-

--

k

-

ROCK DflTfl

'-'

~

1o

0

:

-

-

-

QUi

a

-

--

-

-

it

7

^

--

SUBSURFACE LOG

PROJECT T I T L E Supplemental Hvdrun.'L-lu.ji L I n v i - s t i ;rti . ,.n

PROJFC 1 NUMB^ R _ _M? • 1^_ .

L O C A T I O N nennelt'i Hump

ci A<;<-,iriFn BY JLJ r,,t rkEt> BY ' ^''jl '

SOU /ROCK DESCRIPTION

Still /ROCK CLASSIFICATION

Sty

Co'ing Tdf mindlod at 44 0*.

cr

u.

(icrll

I1

ii

p HF CflS Nn Fl F /.il ION 7^.:6- f t L-

* 0

GAMMA HAY

EL

EV

AT

ION

(F

T)

692.5

RANGf !OX _ TIMF rt tN^TANr_ '° jric

COUN 1 S /MINUTE

10 ?0 SO 40 30 6O 7O SO aO

i

: 1

— i — i — i i i

-

J 1 L_

Cfll II'ER

'01 f 1 lAMf II 1

(IN: MIS)

? 4 6

1 1 -

,J / U En/»/b7

El iMEAB ITY

or

O

u

O

•..•uE'/i^57

MVA/- i frOMT )BORING/CORING/WE1 I NO I V I" . . ' V^WIM I /

••nFE T ^ f>F 3

NOTE S

Page 97: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

/ ~J# y ilASLAND* iOUCK~jy ~J ENGINEIRS, P.C.

•jt.ll DA! A

li

1 1

51

T

SA

MP

LE

S

1

z

1-J

5

t<

i-

00

-

i •'

i . ii

Nk

~

-

-

UJ-)_J*1>

Z

1

-

-

KuCK D A T A

,f

i

RFACE E L E V A T I O N .jP fif CAS iNG p 1 E Vil i- >H

^

-

-

-

1 1

1 I.1

-

O\-

-

-

.-

a

'-'.b

_

1 1

ii.1.

^7.5

r . .' r i ./Mi .f,7

tcLJ

>

0

cc

-

._.

— .

/b

1 .' i

_••'

•J/

QOcc

-

-

-

_.

1 1

11 10

'iH

',3

^y

Z.|

•4

-

-

(~

"-

i,

3_

SUBSURFACE LOG

SOIL /HOCK DESCNIPTION

SOU /ROCK Cl ASSIFICATION

0-4 .75 ' CLAY, si l ty. yellowish ted (5/6) withroo t l e t s , slid, moist.

5 0-5 55' LIMESTONE, medium light gray^™^tenestrate bryozoan and cnnoidal calcarenite. w^weathered Vuid5 5 5 - 1 6 9 ' LIMESTONE. medium light i,Drowmsh gray, micnlic streaK at 17 5'6 5-6 7' Bit Dfop - void

(4 )mb

('i )mb

( 'J)mb

ROCK

FEA

TURE

S

GE

OLO

GIC ^

5-j

0

1

1— r

1

rz:—J--LI

1~3—-—1

— rL__

1!

1DA IE H/2b/«/

i 1 .

IW

EL

LC

OL

UM

N

o>cMaO

[ 4.

6*

D

iam

eter

S

tee

"' 'PROJFCT H

LOCATION.

CLASSfflED

,,, s.,.,,.,™,.,,,, H. .™.. , ....... ,:.,,: .... _

IMBfR !!2_l!.L . .. ___ .. _HcllllL-tt1!, Uuni|.

HY..i'J. CHfCKED BY __V' ' '

GAMMA RAY

ELEV

ATIO

N (F

T;

7l|it.6

IJ 7 4 2 . 2

1

/ 3 7 . 2

752.2

730.8

728.2

7 2 7 . 2

RANGE

-

_ I IWE CONS IAN I _

COUN 1 S/MINII 1 f

50 4O 3O to /o 80 9.

i 1 ~\ 1 1 1 1

110 120 130

/

- //

• W/9.'en\

- I. 1

: /- (•/

PAIE^/-'^1 1 _l_ I i i ,

CAl Ifl H

K)l L lnAMt T E I -

iHJi lit S)

2 ^ 6

'

; i ;

i

i .iii

/

.

n.-it "."-..'

r»Mi / .e iL i iY

b 1;;

Q

E

0

mOz

.iE._»/'j/e^_

HuHifJG/CORlNG/ WELL fjO _. _ „ .

' ,MF£1 .] Oi L.

N f d E S

June 23. 1987 - Soil lor B 2 wa» drilludusing e hollow »lem auget t ruck mountrlrj Soil tarn pie* were taken throughhollow stem augers using a 2* diameter.2 5' long tpllt tpoon sampler driven bya 140 Ib hammer 30' until split spoon -refusal at 5 0'. The soils boring wnbbackfi l led f rom 5 0' lo ground iuilece

July 24. 19B7 - Bedrock (or B 2 wascored using a Gar drier Denver 15 W UK

diameter. 3' long double bar re l corer lo11 0' below ground burface Ihe drillingfluid consisted of misted air

July 24. 1987 • B 2 was laanied with a7 7/B* trlcone all ro tary bit lo teat a 61 •d iameter cas ing at 1 1 0 ' below ground

a 5% benlonite gruut m ix tu re t re inmdihtough the onnulus 1 he ytoul v-osallowed lo cuie for over 48 hours

August 4. 19EJ7 - Bedrock was coimlusing a 3' diameter. 14' long. & | l > lba r re l co te r f rom 13 b' to 42 0

August 5. 1987 - Packet t es t i ng wabconduclbU

September 27. 19U7 - Gamma ruylogging was conducted

October 1 1, 1987 - Core hole waslearned lo 5 b/9' diametbi

O c t o b e r 11. 1987 • Well was developedby (lushing en and mist into bore hulafor one hour

November 8. 1987 - Callper logging wab -conducted

Page 98: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

/ ffi f BLASLANO i BOUCK^ ~y ENGINEERS. P.C.

• , ( ' i IM la

T

. ill

' S'j

' suTO

•1

• I

-

-

Q

-

-•

-

-

_ .

.

E

UJ

-

-

-

--

--

ROCK DAI A

I

-

--

,r-

- - -

-

5

-

O

E"t2

-

-

%

RE

CO

VE

OT

-

-

101

00a

66

-

-

-

E

IL-

1_

i

i

i

4

s

7"

n

SUBSURFACE LOG

SOIL /HOCK DESCRIPTION

SOU /ROCK U ASSIFICAT ION

1 8 9 4 2 0 ' LIMESTONE, lighl gray

2 5 . 1 - 2 5 9 5 ' Mlcnlic streaks

28 02-2B 9' Micillic.23mb

30 4' More rudaceous.

33 78-35 6' Slylulile

34 Ob' Sly lohtes St.y

Sty

35 75-36 75' Mlcnlic.

VI

0

\

in

CO

LU

MN

~ T

r1—

J

1

Y-

"r1"!— r 1-

ii

RFAC.F F 1 f Vfi ION / • > . . ' H A T F H /2b /H /

P OF f ASi fJT, Fl FvillGN

:\

oc

0)

oocwQ.O

t O C A T

T NUMHt'H "2- 1 5

ON._!fc"."!.U>_"

C L A S S F FD BY H J _. _ _ _, nECKfcU BY ' ' '^

GAMMA KAY

u.

o

•q

m.2

' 1 2 . 2

707.2

702.2

RANGE _.. ... TIMF COWMAN 1

CHUN 1 *-, /MIND 1 [

-

L 1 1 1 1 1 1 L ,DATE 'V27/67

( Al irl R

HOli DIAUI. Til.

-

-

rauii/a/"/

i LI.MI ABILI lr

u

i{•

o

m

&

r"i

C1

U)

"1IF -&*2-

OOKlN.VroRING/WEll ,,.,MW'2 1'CONT.)

N ' • U '.,

Page 99: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

z'"~y___Jjy J iLASlANO 1 iOUCK// —f ENGINEERS, f.C.

SO I [J/UA

I

a

o

j SL

SA

MP

LES 7

i

-

-

tt

6UJa

_.

UJ

<

-

-

ROCK D A T A

o

-

-

~

-

OttM.

-

-

O

-

•-

a.

o

a

aoa.

-

-

——

RiT

E

[MIN

/FT

)10

-

-

--

SUBSURFACE LOG

SOIL /ROCK DESCRIPTION

SOIL/HOCK CLASSIFICATION

4 0 0 - 4 2 0 ' Healed ver t ica l liaclure v f

41 6-42 0' Micilllc

Coring Teimlnaled at 420 ' .

IROC

K FE

ATUR

ES

IGE

OL

OG

IC

CO

LU

MN

I

I

rwE

LL

CO

LU

MN

P OF CASING Fl FVATlON 7 ' t4.£7 l

PNO.IFrT TIT 1 F Suiiplemer

PROJECT NUMBER '12.15

IOCATION lte

CLASSIFIED BY

-"' "il"-'.' "' ' -!!'. ^ti.

met t ' b Dump

JLJCHECKED BY . C

GAMMA HAY

u,

O1-

_j

/oo.;

RANGE TIME CON'.IANT..

COUNT S /MINN I E

IO ZO SO 4O 50 60 7O flO 90

-

-

-

-

-

-

-

1 1 1

\

I 1 1 1

-

-

1 1 L

"

CA1 IPER

HOI E IHAMI IEI,

|IN(.HI SI

2 4 6

-

-

-

-

HRMEAU.L.TY

^I

0>

E

0

(M

n

O7.

BORING/CORING/WELL NO """ ^ \COM1.)

NUIES

Page 100: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

APPENDIX 1

PHASE 2 SITE INVESTIGATION SUMMARYBENNETTS DUMP

BLOOMINGTON. INDIANA

Task

o Soil Borings

o Steel CasingInstallationfor Coreholes(lower bedrock)

o Rock Coring(lower bedrock)

o Packer Tests

o Steel CasingInstallationfor Air RotaryHoles

o Air Rotary Wells

Task Description

Continuous split-spoon sampling from ground surfaceto top of bedrock.

Air rotary drill 7-7/8' diameter hole from ground surfaceto top of bedrock. Core 3' diameter/ock sample from topof bedrock to 6' or to the bottom of weathered bedrock.Ream out the 3* diameter rock corehote to 7-7/8' diameterrock corehole to 7-7/8" diameter and set 6" diameter steelcasing with bentonite grout.

Continuous rock coring from top of bedrock toapproximately 30' below top of water table.

Measure permeability of bedrock and detect fractures.

No. ofTasksCompleted

5 soil borings

5 holeswithcasing

5 coreholes

6 holespacker tested

Air rotary drill 8-3/4' diameter hole from ground surface 1 hole withto bottom of weathered bedrock. Install 6* diameter steel casingcasing and seal from ground surface to bottom of weatheredbedrock with cement grout tremied in place.

Air rotary 5-5/8 diameter bedrock from bottom of weathered 1 open holebedrock to 30' below water table. Obtain drill cutting wellsamples at one-foot intervals.

CompletedWellI.D.

MW-1MW-2MW-3MW-4

MW-1MW-2MW-3MW-4MW-6D

StartDate

6/22/876/23/876/23/876/23/87

7/24/877/24/877/25/877/25/8710/15/87

CompletionDate

6/22/876/23/876/23/876/23/87

7/25/877/25/877/26/877/26/8710/16/87

MW-1MW-2MW-3MW-4MW-60

MW-1MW-2MW-3MW-4MW-5MW-6D

7/28/878/3/878/5/877/26/8710/20/87

7/29/878/4/878/6/877/26/8710/15/8710/21/87

7/28/878/4/878/5/877/26/8710/21/87

7/29/878/5/878/6/877/27/8710/15/8710/21/87

MW-5

MW-5

10/14/87

10/15/87

10/14/87

10/15/87

3/21/890188317S

Page 101: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

APPENDIX 1 (Cont'd.)

Task Task Description

o Corehole Ream corehole diameter from 3.41 to 5-5/8' with air rotaryReaming drill bit.

o Open Hole Well Flush air and water into borehole after reaming.Development

o Caliper Logging Measure open air rotary well diameters for fracture andcavity detection.

o PVC WellInstallation(lower bedrock)

o PVC WellInstallation(upper bedrock)

o PVC Cased WellDevelopment

o Gamma RayLogging

o In-SituPermeabilityTests

Install 2" diameter, .01' slot, 10' PVC screen in existingopen hole at a zone of ground-water flow.

Air rotary 5-5/8* diameter hole from ground surface to 10'below top of bedrock and install 2" diameter 10' of .01slot PVC screen.

Surge and bail wells until clear of silt.

Measure natural gamma radiation for stratigraphiccorrelation.

Measure hydraulic conductivity of bedrock.

No. ofTasksCompleted

5 open holewells

Swellsdeveloped

5 wells caliperlogged

1 PVC well

1 PVC well

2 PVC wellsdevelopment

5 wells gamma raylogged

2 wellstested

CompietedWellI.D.

MW-1MW-2MW-3MW-4MW-6D

MW-1MW-2MW-3MW-4MW-6D

MW-1MW-2MW-3MW-4MW-6D

MW-6D

MW-6I

MW-6IMW-6D

MW-1MW-2MW-3MW-4MW-6D

MW-6DMW-6I

StartDate

10/10/8710/11/8710/11/8710/11/8710/22/87

10/10/8710/11/8710/11/8710/11/8710/22/87

11/8/8711/8/B711/8/B711/8/8710/22/87

10/22/87

10/23/87

12/9/8712/9/87

8/22/879/27/878/8/878/10/8711/8/B7

12/9/8712/9/87

CompletionDate

10/10/8710/11/8710/11/8710/11/8710/22/87

10/10/8710/11/8710/11/8710/11/8710/22/87

11/8/8711/8/8711/8/6711/8/8710/22/87

10/22/87

10/23/87

12/9/8712/9/87

8/22/879/27/878/8/878/10/8711/B/87

12/9/8712/9/87

3/22/890188317S

Page 102: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

APPENDIX 1 (Cont'd.)

Task

Water LevelMonitoring

Task Description

Measure depths to water in wells, quarries and streamgauging stations.

Rain GaugeInstallation &Monitoring

Install manual rain gauge.

No. ofTasksCompleted

3 rounds ofwater levels

1 round ofwater levels

1 rain gaugeinstallation

CompletedWellI.D.

MW-1throughMW-4

GS-1 throughGS-4MW-1 throughMW-5, MW-6I,MW-6D

RG-1BD

StartDate

8/9/87,8/22/S7&9/9/87

11/8/87

12/9/87

CompletionDate

8/9/87,8/22/8749/9/87

11/8/87

12/9/87

o Survey Elevations and locations measured.

QuarterlyGround-WaterSampling

Sample ground water and analyze for PCBs using Method8080 of EPA SW-846.

5 pointssurveyed

6 pointssurveyed

4 sampling rounds

MW-1 through 8/5/87 8/26/87MW-4GS-1

GS-2 through 11/18/87 11/20/87GS-4MW-5,MW-6D.MW-6I

MW-1 through 3/8/88 12/6/88MW-6D

3/21/890188317S

Page 103: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

APPENDIX 2SUBSURFACE LOGS

Page 104: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

1 V^/I

\>»>.^C)&

•^^mR^&ifRyZ^^vt i^ ^V-- II' •c-^ --^->T,// sr-%v^-\ \ #/ ??Mli4^MJIP^^^

ii:?ilft P«

BENNETTS QUARRY DUMPOFFSITE GROUND WATER MONITORING

WestinghouseTIER BOUNDARYPRIVATE USE WEL1

Page 105: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

Cff\

i , • , IO.J\ ' . - ' / I /V

\ i((i 1(1

i/x. / y / •-%£\i k , - .+. :.-.,. ^ - ; ,-..ij-jV.fei-,i i; fc.1IL: A- >" r^r

a^sop ft*?p£ r^ / fTEp- i^il-•^' i tii*s -

j-. (ii,4 ^TS| i : 'J|»}j

fC/H x/i!i:|P,j M • N3 1!$'; \-r^^\ f^m A:IM.H

H"-"- S24»J \-^ ' * U i ^I )^ / ^X: \ s *\\ i l&

\K

fater

m^\ /' "X o/• *

>*;** >K,

!)<•• «*« « *«ji

Page 106: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

;*-.:•> /' -L

*T~- -:'V.«"~V ...• ' T V

2500.* "*" "-VMt i,.-; :T\ Vj .«;,«*^6£d£ , 4ttuJ|

•>-v- M- )•> •/, -v . ••' \ r "/

y^ \.

^^^^f^ -(t>;y •' ^v r \ f . . ' \; ,-M' v^fi

/'"- • ' • ' ' ' : '-^t ^^If^l>t •- ,,•"' ' :•- ••^y" vfe ' » "••?>: ' ''^^?Jf

/• 'i*i i>e*;. - ; • ••• fpif#'*<\ r /*L' ''«^*:4i^w^fj -' •- •-. -.._ ' ^flr ' ••' • *"' ';/. . •' '/ fr%V

1000;

'/ ///.; ^v ! >aM\ GA A

|

!

fi... \ --»

-N ;V\ v* -'V

-" lx / ^' m T-l r ^<v : *:-W'r^ ^ — —//14\\

I /ilKcJ' Jt''/«iifw

./•\\\YC !?'~::-s*'"%^ :

A^P S^2l ^

y^: > ] y- "^ )W*t •f | ^^^ n )^ r

^^^^ i ^ jm^^^^^^L <&*r*&&iP~^ ^ :z%W

Page 107: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

•m-t ••-&•&*-<&

•#i#mi*v#$f&*\li! Mi•{,',( If ^1^

- -'X'3 \y \3 \ ; •><?"

-:? -i ),>..... "u'*

-

/ /-j;. f r ' ,• ,•«

» 9* *'*..* «,

^

..•<'

«..=•^ • y- :\j,/r•*.*

1

I

"^';'r'""""'''' - ' ' • : '•/•.~|:r.:v4w:;'./ '.'•'

s . '

fi n ' - ' • . . . ' " '

—^ ,\»*' ;

?

o

/">-4irt• ..-•- '.• ••• **• -i . • - • •• " ^ - . • . . . .

/- r./i - . :-

Page 108: REPORT: OFFSITE GROUNDWATER MONITORING PLAN TIER 1 ... · The Offsite Ground Water Monitoring Plan is to be followed by the Onsite Ground Water Monitoring Plan that is due 90 days

;r\" " '

- ' -

/ . . . - • , • • ; ,^'7'' : '"r "';upK00u If. <<<•&

~~*r*t!£j£jlf:*M:~^ .,,..?. ,.•: ' BP-A ,%•:' ., :. 9>""."' \ ,7

• ...,. ..,-•-.„.,.'' ;-' ,•'*!

,....,-/-'-•''

7I\ ro-E«

•iiV ) f i - f; •: t-:::::,-\rs*s=» |.- "s~, , ,.;,. '^ / „•• - .., --. X-. ifH,.""-. - -- '*'V

frfeUB \. i, ^ \\\ >! ! V-^ ^u^ .. x^»V^J :,;~

• ^>, (V / .

<^ /T-* ..

( 2^ ^

V\V

BO-F«