Remediation of Chernobyl NPP Site Vladimir Kholosha Valeriy Seyda Ukraine Vienna, 28-31 January, 2013, IAEA

Upload: others

Post on 16-Jul-2020

10 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Remediation of Chernobyl NPP Site - IAEA · Remediation of Chernobyl NPP Site Vladimir Kholosha Valeriy Seyda Ukraine Vienna, 28-31 January, 2013, IAEA. 2 Chernobyl NPP. Construction

Remediation of Chernobyl NPP Site

Vladimir KholoshaValeriy SeydaUkraine

Vienna, 28-31 January, 2013, IAEA

Page 2: Remediation of Chernobyl NPP Site - IAEA · Remediation of Chernobyl NPP Site Vladimir Kholosha Valeriy Seyda Ukraine Vienna, 28-31 January, 2013, IAEA. 2 Chernobyl NPP. Construction

2

Chernobyl NPP. Construction Start

Page 3: Remediation of Chernobyl NPP Site - IAEA · Remediation of Chernobyl NPP Site Vladimir Kholosha Valeriy Seyda Ukraine Vienna, 28-31 January, 2013, IAEA. 2 Chernobyl NPP. Construction

3

Commissioning

Turbine Hall. View of Turbine-Generators TG-1,2

Development of installed ChNPP capacities:

• September 26, 1977 – Unit 1 commissioned.

• December 21, 1978 – Unit 2 commissioned.

• December 3, 1981– Unit 3 commissioned.

• December 21, 1983 – Unit 4 commissioned.

Page 4: Remediation of Chernobyl NPP Site - IAEA · Remediation of Chernobyl NPP Site Vladimir Kholosha Valeriy Seyda Ukraine Vienna, 28-31 January, 2013, IAEA. 2 Chernobyl NPP. Construction

4

Accident

Accident at Chernobyl NPP Unit No.4 occurred on April, 26, 1986, at 01 o’clock 23 min. 40 sec. (Moscow time).

It was possible to stop active release of radioactivesubstances from the destroyed reactor only at the end ofMay 1986.

Page 5: Remediation of Chernobyl NPP Site - IAEA · Remediation of Chernobyl NPP Site Vladimir Kholosha Valeriy Seyda Ukraine Vienna, 28-31 January, 2013, IAEA. 2 Chernobyl NPP. Construction

5

Accident Elimination

Page 6: Remediation of Chernobyl NPP Site - IAEA · Remediation of Chernobyl NPP Site Vladimir Kholosha Valeriy Seyda Ukraine Vienna, 28-31 January, 2013, IAEA. 2 Chernobyl NPP. Construction

6

Evacuation of Population of Prypiat and Nearest Inhabited Settlements

Page 7: Remediation of Chernobyl NPP Site - IAEA · Remediation of Chernobyl NPP Site Vladimir Kholosha Valeriy Seyda Ukraine Vienna, 28-31 January, 2013, IAEA. 2 Chernobyl NPP. Construction

7

ChNPP Site Concreting, Dust Suppression

Page 8: Remediation of Chernobyl NPP Site - IAEA · Remediation of Chernobyl NPP Site Vladimir Kholosha Valeriy Seyda Ukraine Vienna, 28-31 January, 2013, IAEA. 2 Chernobyl NPP. Construction

8

Decontamination and Dust Fixation of Surrounding Area

Page 9: Remediation of Chernobyl NPP Site - IAEA · Remediation of Chernobyl NPP Site Vladimir Kholosha Valeriy Seyda Ukraine Vienna, 28-31 January, 2013, IAEA. 2 Chernobyl NPP. Construction

9

RAW Temporary Storage Facilities

Page 10: Remediation of Chernobyl NPP Site - IAEA · Remediation of Chernobyl NPP Site Vladimir Kholosha Valeriy Seyda Ukraine Vienna, 28-31 January, 2013, IAEA. 2 Chernobyl NPP. Construction

10

Activities on Reducing Precipitations

Aviation machinery used to run the clouds above the exclusion zone.

Page 11: Remediation of Chernobyl NPP Site - IAEA · Remediation of Chernobyl NPP Site Vladimir Kholosha Valeriy Seyda Ukraine Vienna, 28-31 January, 2013, IAEA. 2 Chernobyl NPP. Construction

11

Forest Planting (Reforestation) and Grass Planting (Grassing) of the Near Area

Page 12: Remediation of Chernobyl NPP Site - IAEA · Remediation of Chernobyl NPP Site Vladimir Kholosha Valeriy Seyda Ukraine Vienna, 28-31 January, 2013, IAEA. 2 Chernobyl NPP. Construction

12

Cleaning of ChNPP Roof

Page 13: Remediation of Chernobyl NPP Site - IAEA · Remediation of Chernobyl NPP Site Vladimir Kholosha Valeriy Seyda Ukraine Vienna, 28-31 January, 2013, IAEA. 2 Chernobyl NPP. Construction

13

Shelter Object Erection

In the middle of May 1986 the Governmental Commission made a Decision on long-term preservation of the destroyed Power Unit 4.

The construction lasted for 206 days and nights from June to November, 1986. About 90 thousand builders participated directly in it. On November 30, 1986, the State Acceptance Commission accepted the preserved Chernobyl NPP Unit 4 for maintenance.

Page 14: Remediation of Chernobyl NPP Site - IAEA · Remediation of Chernobyl NPP Site Vladimir Kholosha Valeriy Seyda Ukraine Vienna, 28-31 January, 2013, IAEA. 2 Chernobyl NPP. Construction

14

Page 15: Remediation of Chernobyl NPP Site - IAEA · Remediation of Chernobyl NPP Site Vladimir Kholosha Valeriy Seyda Ukraine Vienna, 28-31 January, 2013, IAEA. 2 Chernobyl NPP. Construction

15

ChNPP Units Decommissioning

On March 22, 2002, the State Nuclear Regulation Committee of Ukraine issued to the Chernobyl NPP a License for performing all types of activity on shutdown and decommissioning.

SSE “Chernobyl NPP” was established for comprehensive solution of problems of Chernobyl NPP Units decommissioning and Shelter Object transformation into an ecologically safe system.The enterprise statute was registered on June 11, 2001.

Page 16: Remediation of Chernobyl NPP Site - IAEA · Remediation of Chernobyl NPP Site Vladimir Kholosha Valeriy Seyda Ukraine Vienna, 28-31 January, 2013, IAEA. 2 Chernobyl NPP. Construction

16

Page 17: Remediation of Chernobyl NPP Site - IAEA · Remediation of Chernobyl NPP Site Vladimir Kholosha Valeriy Seyda Ukraine Vienna, 28-31 January, 2013, IAEA. 2 Chernobyl NPP. Construction

17

Cost for ChNPP Decommissioning

Preliminary estimation of aggregate costs for ChNPP decommissioning is 19 678 mln. UAH or3 935.6 mln. US$ (according to average exchange rate 5 UAH/1$ as of 2007).

CSF amount is 1.54 billion euros. At the moment there are no reliable cost estimations for SO transformation into ESS, their amount – tens of US$ billions.

Page 18: Remediation of Chernobyl NPP Site - IAEA · Remediation of Chernobyl NPP Site Vladimir Kholosha Valeriy Seyda Ukraine Vienna, 28-31 January, 2013, IAEA. 2 Chernobyl NPP. Construction

18

9580

9051

47624359

41143816 3866

38343730

3465 34843362

2729

1000

2000

3000

4000

5000

6000

7000

8000

9000

10000

2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012

Чи

сл

ен

но

сть

пе

рсо

на

ла

, ч

ел

Динамика изменения численности персонала

ГСП ЧАЭС

Staff reduction for 5,000 people after establishing SSE ChNPP in 2001 on a base of Chernobyl NPP

Staff reduction for 650 people after separation of non-core functions from the SSE ChNPP

Social Problems

Page 19: Remediation of Chernobyl NPP Site - IAEA · Remediation of Chernobyl NPP Site Vladimir Kholosha Valeriy Seyda Ukraine Vienna, 28-31 January, 2013, IAEA. 2 Chernobyl NPP. Construction

19

Establishment of Chernobyl NPP Decommissioning Infrastructure

Industrial Complex for Solid Radioactive Waste Management – construction was completed, activities on preparation for testing and commissioning are underway.

Liquid Radioactive Waste Treatment Plant –construction activities were completed, “cold” tests are in progress, the scheduled commissioning – 2013.

Complex on Manufacturing Steel Drums and Reinforced Concrete Containers for RAW Storage/Disposal – facility was commissioned.

Page 20: Remediation of Chernobyl NPP Site - IAEA · Remediation of Chernobyl NPP Site Vladimir Kholosha Valeriy Seyda Ukraine Vienna, 28-31 January, 2013, IAEA. 2 Chernobyl NPP. Construction

20

Establishment of Chernobyl NPP Decommissioning Infrastructure

Interim Storage Facility for Spent Fuel (ISF-2)

• design for ISF-2 completion was approved;

• detailed design stage has been started;• physical activities at the site will be

commenced in 2013;• ISF-2 planned commissioning – 2015.

Upgrades to Industrial Capacities on Long-Length Waste Cutting

• Technical design passed the expert review at SSTC NRS.

• Detailed engineering, procurement of equipment and materials are underway.

• Project completion date – 2013.

Page 21: Remediation of Chernobyl NPP Site - IAEA · Remediation of Chernobyl NPP Site Vladimir Kholosha Valeriy Seyda Ukraine Vienna, 28-31 January, 2013, IAEA. 2 Chernobyl NPP. Construction

21

Management of Spent Nuclear Fuel (SNF)

Release of Power Units from nuclear fuel is a primary factor, which defines duration of the shutdown stage.In August 2010 Unit 3 was completely released from fuel.In November 2011 a Decision on placing all conditioned SNF from Units 1, 2 at ISF-1 was agreed upon with the State Nuclear Regulatory Inspectorate of Ukraine.Works on SNF transfer from Units 1 and 2 into the 5th compartment of ISF-1 SP were commenced in December 2011.As of today all conditioned fuel was transferred from Unit 2 into ISF-1. 20.5 unconditioned SFAs remain.Unit 1 is planned to be released from conditioned SNF in 2013.

Page 22: Remediation of Chernobyl NPP Site - IAEA · Remediation of Chernobyl NPP Site Vladimir Kholosha Valeriy Seyda Ukraine Vienna, 28-31 January, 2013, IAEA. 2 Chernobyl NPP. Construction

22

Dismantling

Starting from 2004 the ChNPP has performed dismantling activities by own forces, mainly at external objects.From 2011 to accelerate the dismantling contracting organizations are involved into the works.

The dismantling of Power Unit 1 Turbine Hall equipment (13,900 tons of metal in total) is scheduled for 2012-2015. The activities on dismantling of equipment and structure elements, fragmentation, transportation for decontamination and release from regulatory control have been started.

Page 23: Remediation of Chernobyl NPP Site - IAEA · Remediation of Chernobyl NPP Site Vladimir Kholosha Valeriy Seyda Ukraine Vienna, 28-31 January, 2013, IAEA. 2 Chernobyl NPP. Construction

23

Shelter Implementation Plan

Basic stages:• stabilization;• construction of the confinement and

preparation for FCM and HLW retrieval;• retrieval of FCM and long-lived RAW,

their conditioning with subsequent storage and disposal in accordance with effective standards.

• Contract conclusion – August 10, 2007.• Contract work commencement - October 29, 2007.• Foundation construction completion – May 2013.• Assembling of the main Arch structure – November 2014.• NSC commissioning – October 2015.

Milestones of NSC creation:

Page 24: Remediation of Chernobyl NPP Site - IAEA · Remediation of Chernobyl NPP Site Vladimir Kholosha Valeriy Seyda Ukraine Vienna, 28-31 January, 2013, IAEA. 2 Chernobyl NPP. Construction

24

Construction of New Ventilation Stack (NVS)

NVS assembling was completed, including works on installation of external equipment and elimination of comments. Works on the NVS commissioning are underway. Contract work completion – 2012.

Contract SIP-09-1-003 “Design of Dismantling, Design Supervision for Dismantling Activities and Dismantling of ChNPP Generation II Ventilation Stack” was signed on April 23, 2012.

Page 25: Remediation of Chernobyl NPP Site - IAEA · Remediation of Chernobyl NPP Site Vladimir Kholosha Valeriy Seyda Ukraine Vienna, 28-31 January, 2013, IAEA. 2 Chernobyl NPP. Construction

25

Construction of New Safe Confinement (NSC)

Foundation activities in the confinement erection area were completed in November 2011. In total, 396 piles 1 m in diameter and 25 m in length were driven. Weight of the piles is about 5,000 tons.Concreting of foundations in erection and transport areas of the Arch is in progress.

On November 24, 2012, the first lift of the Eastern part of the Arch 5,300 tons in weight for 22 meters was performed at the Chernobyl NPP Shelter site. The lifting beams are under dismantling.

Page 26: Remediation of Chernobyl NPP Site - IAEA · Remediation of Chernobyl NPP Site Vladimir Kholosha Valeriy Seyda Ukraine Vienna, 28-31 January, 2013, IAEA. 2 Chernobyl NPP. Construction

26

There are no many sites in the world, where such large-scale and unique activities, as at ChNPP, are performed.

The Chernobyl NPP personnel have mastered new types of activity and have accumulated experience on elimination and containment of accident consequences, NPP decommissioning under the conditions of the severest industrial accident.

We are open for any proposals on interaction and cooperation, as well as ready to share our experience and demonstrate our procedures and achievements.

Conclusion