NPP I&C status In Brazil and
Recommendations to IAEA
26th Meeting of the IAEA TWG-NPPIC
24-26 May 2017 Vienna
Salomão Gonçalves O. Jr Eletrobras Eletronuclear
Fuad Kassab Junior University of São Paulo
1. Brazil data
2. NPP data
3. Fleet modernization – Angra unit 1 and 2.
4. Recommendations to IAEA programme (2018 to 2021)
Contents
1- Brazil data
Area: 8.515.767 km2
World´s 5th largest country
Population: 196.7 million
World´s 5th largest population
GDP: 1.98 trillion US$
World´s 8th economy
GDP Per Capita: US$ 10,3 Inh
77th
Electricity Production/yr:450 TWh
10th (Nuclear: 2.007 MW 1.49 %)
Elec. Consumption Per Capita:
90th 2.4 KWh
1- Brazil data
Hydro is the main source (>65%).
The prediction for renewables in 2017 will be very close to 2016.
Sources: ONS (National Electrical System Operator)
Ministry of Mines and Energy www.mme.gov.br
AHE BELO MONTE 11.000 MW now 3.2 MW
(Xingu River)
AHE MADEIRA 6.500 MW
(Madeira River)
1- Brazil data
Brazilian Nuclear Industry
There are currently two NPPs in operation(Angra 1 and Angra 2)
and one under construction (Angra 3).
ANGRA 1ANGRA 2
2- NPP data
Future plans
Six new NPPs
in the northeast
2- NPP data
Westinghouse PWR type, two loops, 657 MWe
• Analog I&C predominant
• Digital Turbine Control System (Electrical Overspeed Trip)
• Digital Feedwater and Heater Drain Control System
2- NPP data (Angra 1)
2- NPP data (Angra 2)
Areva (formerly KWU), PWR type, four loops, 1350 MWe
• Analog and digital hardwired I&C predominant
• Digital Reactor Control System (JS)
• Reactor Limitation System
Similarities:
Conventional Analog Human-Machine Interface
Plant Process Computer - HW PLC and SW PC based sys
Digital, hardwired Reactor Protection System.
2- NPP data (Angra 3 – under construction)
Areva PWR type, four loops, 1400 MWe
Base for HFE
Program
ANGRA 3 ANGRA 2
Standard NUREG 0711 NUREG 0711 covers
IEC 60964
Plant Pre-Konvoi Pre-Konvoi
Control Room Display Based Conventional
Procedures eOM Paper
PICS OM690 Operating and
Monitoring Sys Version 5
Hardware Panel
SICS Safety shut down /
and timely limited operation
Hardware Panel
Operating Crew 5 Person shift 5 Persons shift
Operating Manual Pre-Konvoi Pre-Konvoi
What we have done successfully regarding Monitoring?
Plant Process Computer – (Research Institute)
Vent Stack Computer – (Research Institute)
Sub-cooling Margin Monitor – (Research Institute)
Turbine Vibration Monitoring (Rovsing)
Leakage Monitoring System (Westinghouse)
Loose Parts Monitoring System (Areva)
What we are planning to do regarding Monitoring?
Replacement of Main Transformers (500Kv) new monitoring sys.
Replacement of Radiation Monitors (R11 & R12)
Upgrade of Reactor Coolant Pump Vibration Mon. Sys. (Rovsing)
Upgrade of Digital Rod Position Indication System (DRPI)
3- Fleet Modernization (Angra 1)
3- Fleet Modernization (Angra 1)
What we have done successfully regarding Control?
Replacement of transmitters (Emerson) and Foxboro Modules for NUS
Level Control System of Heater Exchangers (Yokogawa Sinlge Loop)
Pressure Control of the Biological Barrier Ventilation Sys (Siemens SL)
Upgrade of Reactor Protection System (replacement of electronic cards)
Upgrade of Control Rod Drive Mechanism (replacement of cards)
Upgrade of Turbine and Feed Water Ctrl Sys. (West./Emerson Ovation)
Full Scope Simulator System (Training Center new building)
What we are planning to do regarding Control?
NSSS upgrade – Pzr Level and Pressure, Chemical Volume Ctrl,
Reactor Ctrl (Average Temp., Overpower and Over temp. delta T loops),
Rod Insertion Limit (RIL), Steam Dump (SD), Rod Speed Ctrl, Safety
Injection and Accumulator (SA) loops.
3- Fleet Modernization (Angra 1)
3- Fleet Modernization (Angra 1)
COOPERATION WITH THE EUROPEAN COMMISSION
Eletronuclear developed a two year project with the EC to upgrade Safety
Related I&C of Angra 2.
The project aimed to define a strategy for the replacement of the existing
analogue I&C equipment currently used in Angra 2, mainly the systems
important to safety.
The project reached its conclusion in the beginning of 2013.
The results has been used to modernize Angra 2 safety related I&C.
3- Fleet Modernization (Angra 2)
What we have done successfully regarding Monitoring?
Upgrade of Plant Process Computer – SICA
Installation of Thermal Transient Monitoring System
Upgrade of LPMS and Vibration Monitoring System
Upgrade of Aeroball System
Upgrade of Reactor Vessel Level Instrumentation System
What we are planning to do regarding Monitoring?
Modernization of Gas Stack Monitoring (KLK)
Modernization of Radiation System (replacement SINUPERM M)
Modernization of Physical Protection System - (CZ)
3- Fleet Modernization (Angra 2)
What we have done successfully regarding Control?
Modernization of Chlorination System
Modernization of Turbine Building Crane Control
Modernization of Polar Bridge Crane Control
Modernization of Boiler Control Loops
Modernization of Reactor Control System (JS)
What we are planning to do regarding Control?
Modernization of Refueling Machine
3- Fleet Modernization (Angra 2)
• HFE – Angra unit 1 - Simplified guidance to aid in definition of MCR/MCB
“End Point Vision”. I&C digital upgrade for process control systems. Angra
unit 3 HFE requirements FSAR chapter 18;
• New technologies applied to digital I&C systems (Ex: Neural Network,
Fuzzy Inference Systems and Big Data) ;
• Tech Meeting topics to exchange informations – Control loops tuning for
non expected transients (Ex: 100% load rejection), System Health
Management, V&V of digital I&C upgrades and VDU based MCR design;
• Cyber Security – Managing external and internal security of digital
systems. Managing domain policies.
• Ageing management of electrical equipment and components (IGALL).
4- Recommendations to IAEA programme (2018 to 2021)
END
Contact Information
Salomão Gonçalves O. Jr [email protected]
Fuad Kassab Junior [email protected]
Thanks to:
Leonan dos Santos G. Eletronuclear Technical Director
Fernando Futuro Eletronuclear Superintendent
Renan Giese Eletronuclear Sup. Assistent
Antonio C. de O. Affonso Eletronuclear Manager
Leonard P. Eletronuclear Supervisor
and all the I&C team of GEI.T