30th August 2017 Retail Markets Co-Ordination Design ServiceReMCoDS
ReMCoWG Agenda
All participants are kindly requested to mute their phones when dialled into the forum conference call
Agenda Item Presenter Time
Introduction Carl Murphy, ReMCoDS 12:30 – 12:35
ReMCoSG Meeting Feedback Carl Murphy, ReMCoDS 12:35 – 12:45
ReMCoWG Action Items Carl Murphy, ReMCoDS 12:45 – 12:50
Tibco Hub/EMMA Update John Bracken, ESBN 12:50 – 13:00
Smart Metering Update CER 13:00 – 13:10
Market Design Update Carl Murphy, ReMCoDS 13:10 – 13:20
ReMCoWG To-Do List Review Carl Murphy, ReMCoDS 13:20 – 13:25
AOB & Closing Carl Murphy, ReMCoDS 13:25 – 13:30
30th August 2017 Retail Markets Co-Ordination Design ServiceReMCoDS
Approval of Minutes
Minutes (v1.0) from ReMCoWG meeting
28th June 2017
For Approval Today
30th August 2017 Retail Markets Co-Ordination Design ServiceReMCoDS
ReMCoSG Update
SG Meeting held on 23rd August 2017 – Next SG 22nd November 2017.
ReMCoSG Actions Summary New Action items:143 & 144,
Closed Action items:105, 135, 137, 139 & 141
Carried Forward Action items: 140 & 142
TIBCO HUB/EMMA update TIBCO is performant
SMART Metering Program
update
CER has been evaluating the proposal and is close to making a decision that this
is the way to proceed.
I-SEM update No update.
Retail Market Program update • The Retail Market Program was approved up to Q1/2019.
• New action 143 was logged: Prioritisation process for post Q1/2019 to be
agreed.
• The Retail Market Program will be a standing item on the ReMCoSG Agenda
going forward.
De-harmonisation • UR is minded to de-harmonise.
• Discussions ensued about potential impacts of de-harmonisation.
• UR will emphasise internally the importance of making a decision on de-
harmonisation as early as possible.
• New action 144 was logged: ESBN/NIE Networks to provide a date at
which if a decision was not made it would put the delivery of post
Q1//2019 Retail Market Program at risk.
• De-harmonisation will be a standing item on the ReMCoSG Agenda going
forward.
30th August 2017 Retail Markets Co-Ordination Design ServiceReMCoDS
ReMCoWG Action Items – Closed
2 Action were closed at last ReMCoWG meeting
AP No. Title Org. Assigned to Date Closed
151
Retail Program Update – ESBN/NIE Networks to circulate the Retail
Programme update ESBN/NIE Networks 28/06/2017
152
Retail Programme Update – NIE Networks to brief the UR on the Networks
Retail Program Update provided by ESBN NIE Networks 28/06/2017
30th August 2017 Retail Markets Co-Ordination Design ServiceReMCoDS
ReMCoWG Action Items – Open
1 Action was opened at the last ReMCoWG
AP No. Title Org. Assigned to Date Due
154
Secure Meters DR - ESBN/NIE Networks to review contingency plans to
determine if a co-ordinated plan could apply in certain scenarios ESBN/NIE Networks 30/08/2017
1 Action was carried forward at the last ReMCoWG
AP No. Title Org. Assigned to Date Due
153
Supplier Release 2.3.4 – Suppliers to respond with a generic Email Address to
Capita and/or NIE Networks Suppliers 30/08/2017
ReMCoWG
30th August 2017
7 esbnetworks.ie
Tibco Hub/Emma
Unplanned Outages
8 esbnetworks.ie
Retail Market Programme
Business As Usual
I-SEM
NIE SAP IS-U SPs / ES Infrastructure
Meter Reading Replacement/
QH remote modems pilot
Smart Enablers Smart Implementation
MCR 1187
– Eircodes
interim
MCR1184 – Cooling off
Release to be agreed
Non Schema MCR1179 -
Eligible customer files
on extranet
I-SEM go live 23.05.2018
Eircodes – MCR1140, MCR0175, MCR1169
Vulnerable Customers – MCR1173
Public Lighting – MCR1167
New Unmetered Tariff (NI) - MCR1154
010 Customer Validation (NI) - MCR1183
Provide MP Business Reference for reading (Non Schema) – MCR1175
New Registration Default – MCR1180
Market Webservice – MCR1135
Non Schema MCR1176 -
Extranet Message
reordering
9 esbnetworks.ie
Retail Market Programme
Assumptions
● Suppliers will be ready for Easter 2019
(Suppliers IT system changes with resourcing)
● De-harmonisation is not included in this
programme of work
● No change requests to I-SEM
● SMART will proceed as per alternative
proposal – Phase approach
● DRs (New Reg/Cooling Off) proceed to MCRs
Dependencies
● No impact of Data Centre move from Capita to
ATOS
● CER and UR will formally sign off plan in
timely manner
● Funding will be in place for Non-Smart Work
● A smooth I-SEM implementation in 2018
● Clear integration with Smart Program (role of
Smart and Retail Forums like IGG)
Risks
● Program Full Resourcing
● No serious operational event/s
● Cyber Attacks and impacts for Retail Market
● Regulatory/Mandatory change requests
Role of Suppliers
● Proactive Participation to meet Objectives and
Timelines
● A high level of Preparedness
● Web Service Design work to be completed by
Easter 2019 (if not earlier)
● Approach for future prioritising to be agreed (to
include scoping ..)
10 nienetworks.co.uk
IT Managed Service Provider Update
Transition plans are being finalised to maintain the effective operation of the
market systems during the transition period.
Suppliers will not be required to make any changes as part of these transition
activities, for example, IP addresses will remain unchanged
Communication has been issued regarding outages required as part of
transition activities. The next outage will be:
Friday 22 September 2017 at 8pm to Monday 25 September 2017 at 8am
Market Systems Impacted:
ROI & NI Suppliers: TIBCO
NI Suppliers Only: Market Website, SFTP webservice
A Supplier workshop will be held on 12 September 2017 to provide an
opportunity to meet the Atos team and review transition activities
CDA Board 30th August 2017
11
CER SMART Metering
Update
30.08.2017
30th August 2017 Retail Markets Co-Ordination Design ServiceReMCoDS
Co-ordinated Retail Market Design Update
Co-ordinated Retail Market Design update
Carl Murphy
ReMCoDS
Retail Markets Co-Ordination Design ServiceReMCoDS
At the IGG on 26th July 2017, following the briefing on a P1 incident, it was
identified that market documentation needed to be updated to reflect the as-is
process that is currently in place to cater for meter and/or service removal as
part of a de-energisation.
This DR raised to show the necessary documentation updates required.
At Today’s Meeting: For Classification as RoI Specific
DR1188 – Update MPD 09 to Reflect Actual Market
Process in relation to Meter and/or Service Removal
30th August 2017 Retail Markets Co-Ordination Design ServiceReMCoDS
Co-MMR 11.1
Co-MMR 11.1 Release date of Monday 2nd October 2017. (Joint Release
with MMR 11.1)
Co-MMR 11.1 – CoBL will be re-versioned to 3.1 to include new Supplier
Codes. All Message Guides will be re-versioned.
MPs will be notified of details on Monday 4th September 2017.
30th August 2017 Retail Markets Co-Ordination Design ServiceReMCoDS
Upcoming Outages
IT Service Provide Transition – Capita to Atos
There will be a TIBCO outage from Friday 22nd September to Sunday 24th
September 2017 for 52 hours – further details will issue shortly.
A workshop has been scheduled for Tuesday 12th September which will give
Suppliers the opportunity to meet the Atos team and answer any
technical/business questions they may have regarding the transition and service
from 01 October 2017.
http://rmdservice.com/outages-2017
30th August 2017 Retail Markets Co-Ordination Design ServiceReMCoDS
ReMCoWG Meeting
AOB
30th August 2017 Retail Markets Co-Ordination Design ServiceReMCoDS
Next Steps
Diary dates for next ReMCoWG meeting:
Wednesday 1st November 2017 - Belfast
Dates included on Calendar of Events on RMDS
website www.rmdservice.com
30th August 2017 Retail Markets Co-Ordination Design ServiceReMCoDS
ReMCoWG Meeting
Thank You