register of comments:interested and affected parties …jomela.co.za/downloads/appendix 11-comments...
TRANSCRIPT
-
24 October 2016
REGISTER OF COMMENTS:INTERESTED AND AFFECTED PARTIES (I&AP’s)
UNIVERSAL COAL DEVELOPMENT II (PTY) LTD
NO. Name Date of
Received
Comment Respond
1 Cath Vise 27-09-16 I saw your notice about a Scoping Report for an open cast
coal mine within the Vhembe Biosphere Reserve, Makhado
Municipality, Limpopo, in the Zoutpansberger newspaper.
Please could you send me a copy of the scoping report?
Please also register me as an I&AP, my details are below. I
am also resident in Makhado.
You have been added as an interested and affected party. Please find
attached the scoping report and the drop box link for the rest of the studies.
https://www.dropbox.com/sh/dq24i49q79sfvxq/AADeCT4bAGMKzmzw-
XNdFIm-a?dl=0
Cath Vise 04-10-16 Thank you for sending through these documents. However, I
see you have a meeting for 8th September, which has
already passed. Could you please let me know of the
corrected date?
Also, please remind me if there is there a deadline for
response from I&APs?
The meeting will be held on the 08th of October 2016 at Waterpoort Farms
Association Hall.
I already sent new email with the correct date of the meeting.
Vhutshilo Theo
Muthurwana
04-10-16 Good I think there is an error about the month’s
08th/September /2016 instead of October. Please verify.
The meeting will be held on the 08th of October 2016 at Waterpoort Farms
Association Hall.
I already sent new email with the correct date of the meeting.
A B BURGER
ATTORNEYS
04-10-2016 You mentioned a Public Meeting will be held on 8th
SEPTEMBER 2016?? At Waterpoort Farms
Sure that is not correct.
The meeting is on the 08th of October 2016 at Waterpoort Farms
Association hall, the date of 08th of September was incorrect.
Deon Van Heerden 05-10-2016 Please also sort out your mailing list as I have not received
any of the previous 3 mails that were sent by you. I used to
be on the mailing list as I am an affected party, but seemed to
have fallen off along the way.
Sorry for that, all email is forwarded to you.
Juanita De Beer 23-09-2016 Bokamoso Landscape Architects and Environmental Your offices are registered as interested and affected parties for this project.
-
Consultants would hereby like to register as an Interested
and Affected Party on behalf of surrounding
landowners/tenants/farmers.
Our contact details are as follows: Lizelle Gregory / Anè
Agenbacht / Juanita de Beer
E-mail: [email protected] / [email protected] /
Landline: 012 346 3810
Cell phones: 083 255 8384 / 083 533 0420
Fax: 086 570 5659
It would be appreciated if you could clarify the process being
followed as a Scoping Report was published for public review
from 5 January 2016 to 4 February 2016.
Too our knowledge a new application for integrated
Environmental Authorisation was submitted to DMR on 2
September 2016.
If this is a new application i.e. previous application lapsed,
was the public afforded 30 days to Register as I&APs?
If not, could you please provide proof of exemption obtained
not to comply with Chapter 6, Section 41 of the 2014 NEMA
EIA Regulations.
It is furthermore requested that you keep our office informed
of all new information, reports, meetings etc. throughout the
remainder of this project.
Due to difficulties experienced during compilation of the water studies the
previous application 10121MR lapsed as interested and affected parties
would not have been given a minimum of 30 days to review the reports.
As such the new application was lodged and interested and affected parties
where notified of the status of the project. Following the NEMA process we
advertised in the local papers and via email to registered parties. Due to the
timeframe restrictions we made note of the status of the previous application
as well as availability of the new applications scoping report and as such
requested parties to register.
I hope all is in order. A public meeting will be held on the 8th of October
2016 at the Waterpoort farmers Association Hall,
-
Cath Vise 11-10-2016 In addition to the many impacts that your team has already
identified, I wanted to add the following considerations that
need to be addressed in any application going forward.
Zonation and International Conventions:
The proposed site is located within a Critical Biodiversity Area
(CBA) 1 and 2 according to the Limpopo Government's
Conservation Plan.
CBA1, under the guidelines, are irreplaceable sites where no
alternate sites are available to meet biodiversity targets.
Incompatible Land-Use practices include Mining and
associated infrastructure. Please see attached plan.
It is also worth noting the motion passed at the IUCN
congress regarding mining and areas importance for
biodiversity conservation:
https://portals.iucn.org/congress/motion/026
The proposed mine also falls within the UNESCO Vhembe
Biosphere Reserve. Biosphere Reserves are places where
SUSTAINABLE development is encouraged, with particular
regard to implementing global agreements such as the
Convention on Biological Diversity, Sustainable Development
Goals and in particular the UNFCCC COP21 Paris Climate
Agreement
https://www.environment.gov.za/mediarelease/southafricasig
nsparisagreementonclimate. Here, a statement for South
Africa to transition to a low carbon economy is made.
These comments have been noted and will be further addressed in the EIA.
We also refer to the specialist report for more information regarding the
social impacts.
-
Open cast coal mining, with associated carbon emissions and
impacts on climate change, water resources and biodiversity
would not be in line with achieving these international targets
and agreements which South Africa has signed.
Additional Environmental and Social Impacts to Address:
• concern over the removal of baobab trees, which
are a protected species
• cumulative impacts of the various mining and other
development applications in the region - especially with
regards to water security
• secondary impacts of the mining activities - i.e. the
coal that is transported to a different region (such a
Mpumalanga or further afield) will have a secondary impact
when burnt for power production in terms of both air quality in
that region, as well as associated carbon emmissions
• There is no mention of potential climate change
impacts in the scoping presentation (especially with regards
to CO2 emissions) for both local operations as well as end
use operations.
• there will also be light pollution which could affect
tourism operations/ sense of place/ cultural ecosystem
services with regards to 'enjoying the African skies' and star
gazing attraction of the area
• You will also need to address impacts on
biodiversity (roadkill etc) of increased traffic on both roads
and railway
• Increased traffic (especially heavy vehicles with
restricted speed limits) may impact on other road users
-
operations
• Influx of people (construction workers, mine
workers) can also have an associated impact on local
communities. Of particular concern (which has been picked
up in developments elsewhere) is the increase in violent
crimes against women.
With regards the to water use licence, the quantity of water
required - a total of 4542 cubic metres per day as per the
presentation - seems extremely excessive in an already
water stressed area - in particular with the associated impact
this will have on water availability to existing agricultural
operations, which as noted by one of the attendees will also
affect existing local employment.
Of particular concern too will be the impact of climate change
on these water resources - what is already a stressed supply
now may become even more stressed in future as climate
change takes its toll on local environments.
I hope this helps to bring further depth and consideration to
your Environmental Impact Assessment.
Please do keep me informed of any further updates regarding
this project.
Erika 11-10-2016 The Waterpoort Farmers Union wishes to be registered as an
Interested and Affected Party with reference to the above
project. The reason for our registration is to be informed of
information that could have an effect on our members.
Thank you for the comments. Please supply me with your P.O Box so I can
send you a C.D with the specialist studies.
And as previously discussed, if you can supply us with other I&AP's who
weren't at the meeting but interested in the project.
-
Contact details are as follows:
Contact Person : Erika Helm
Cell phone : 0796996032
Email : [email protected]
Postal address : PO Box 26, Waterpoort, 0905
With reference to the public meeting as been set forth on the
8th of October 2016, we wish to furnish our
comments/questions as follows.
1. We wish to inform you of an Extraordinary Provincial
Gazette, dated 13 November 2015 Notice 344 of 2015 signed
and promulgated by the premier of Limpopo Province
whereby the area has been declared the area as disaster
area due to persisting drought according to the Disaster
Management Act 57 of 2002. This fact has again been
confirmed in the Parlement during the second quarter of this
year. According to this information it is therefor a very
sensitive area especially with reference to the water situation.
It is by this information that the farmers union wishes to
demand an Integrated Regional Water Study integrating all
mining projects in the area to be done. We take note that this
is not an obligation according to legislation – however it is the
opinion of this union that the project can have detrimental
effect on the livelihood and existence of each resident in the
area. Copy of the Provincial Gazette handed to the
Environmental Practitioner during the meeting.
-
2. We take note the life of mine for the Block OC 1 is
expected 20 years. We also take note according to the
information as being supplied during the meeting that the OC
2 and OC 3 blocks is situated within the 100 year floodline
and the Life of Mine on this blocks cannot be supplied. We
wish to enquire when will this information be available to the
Interested and Affected Parties.
3. We wish to request that the Safety and Security
impacts also be addressed during the assessment studies as
the influx of workers will have an influence on the current
situation as being experienced.
4. We refer to the existence of 4 graves within the
project area. Could the deceased be determined and what is
the age of these graves? In which block is this graves
situated?
5. Stockpiles – we take note of the sides being
vegetated to prevent erosion. The concern exist for the
invasive and non-indigenous plants which could invade these
stockpiles. What will the actions be to manage this situation?
6. We take note of the blasting that will occur with
reference to mining operations. The concern is that the
structures in the area was originally not build to endure the
stress of such operations. Please indicate the financial
guarantee be set in place for rehabilitation in respect of
damanges to the structures.
-
7. We take note of million tons of coal to be produced
per month. What is the quality of the coal and who is the
customers of Universal Coal?
8. We refer to the presentation of Mr Mandla Masango
with reference to the WULA application. We need to be
informed of the distance of the municipal sewerage treatment
plants from the proposed project as this is one of the water
sources as been specified in the presentation.
9. We take note the possible usage of the Brakriver in
the project. We wish to inform you to take note the Brakriver
is a river with a non-permanent waterflow. There will be an
impact on the water users downstream as well as the
environment which are supported by the water of this river
when it is flowing during the rainy season.
10. We take note of the pollution control dam – where
will this dam be constructed? It is our concern of the
possibility of pollution during overflow of this dam. This need
to be addressed.
11. In the documentation and presentation of Mr
Masango the Life of Mine is stated as 33 years and the
WULA application also in respect of this. It is however stated
in the MPRDA section 23 (6) that a mining licence can only
be approved for a maximum of 30 years. OC 1 is also
expected for only 20 years, whereby OC 2 and OC 3 is yet
-
not been established. Please explain the 33 years as this is
not clear with reference to the timeframes as set out above.
Thank you for the presentation as been conducted on 8
October 2016. We look forward in receiving the Draft EIA.
Juanita De Beer 07-10-2016 Our former e-mails in which Bokamoso raised various
concerns regarding the new EIA Application process for the
Universal Coal Mining Development known as the Berenice
Mining Application Refer
Take note: !!!!!!!!!!! This is a very important e-mail and all
I&APs must take cognizance of this correspondence,
because it also affects the rights of the registered interested
and affected parties and the parties that were not afforded an
opportunity to register as I&APs in this new application
process. We are of the opinion that the EAP is no
transparent, not independent and that they are once again
hiding important information from all the I&APs. This can
simply not be tolerated any longer.
As already stated in our former correspondence and
comments provided we represent (as environmental
consultants) various land-owners/ farmers in the area that are
totally against the proposed open cast coal mine which will
cover an area of more than 7 000ha.
We are extremely disappointed in the modus operandi of
Jomela, because Jomela failed to disclose (in the former EIA
process) to the I&APs that DMR closed their files before the
Dear Interested and Affected Party;
Regarding the previous application, we noted that due to the delays with the
water studies which where supplied two weeks late that I&AP’s would not
have adequate time to comment on these reports. We requested not forced
I&AP’s to submit their comments as we had submitted a request for
extension as the due date for final submission was the 9th of September.
The DMR could not grant a second extension and based on the fact that
I&AP’s would not have had 30 days to review all the reports, the application
was deemed as lapsed. We did not refuse to afford I&Aps extra time but
rather stated that we were waiting on the department to give us feedback as
we indicated in a letter sent to you. This was also explained in a project
status quoi letter sent to registered interested and affected parties. We
requested comments on the EIA/EMPr report because the information is still
the same, the project is still the same and we want to address these
comments so that when we send the EIA report for the new application we
would have amended and addressed the issues raised.
Regarding the new application, newspaper adverts where placed in the
Limpopo Mirror and Zoutpan Newspapers ( 23 September 2016) and site
Notices were placed. In your previous queries you requested that we
provide you with an exemption letter for not following the NEMA PP
regulations and we advised you that we were conducting the PP according
-
submission of the Final EIA Report. Jomela forced the I&APs
to supply comments before a specific date and expected that
the I&APs review and comment on an incomplete
Environmental Impact Assessment Report and submit the
comments to DMR after Jomela submitted their Final EA to
DMR. We received some of the specialist reports almost 2
weeks after we received the EIA report without the annexures
for comment. We requested an extension of time for the
submission of the comments for the former EIA Report, but
Jomela refused to afford the I&APs an extension of time.
Whilst we were compiling the comments and whilst we
waisted a significant amount of time on the compilation of the
comments, we were informed that DMR closed the project file
and that DMR instructed Jomela to start afresh with a new
application process. Jomela were already aware of the
closure of the file when they forced the I&APs to supply
comments within a limited timeframe. In fact, Jomela already
submitted the nee mining application to DMR whilst waiting
for the I&APs comments regarding the EEIAR. This is
regarded as unprofessional, rude, reckless and to say the
least arrogant, because Jomela waisted the precious time of
the I&APs on a process that no longer existed and Jomela
withheld important information form the I&APs.
After some of the I&APs notified Jomela of DMRs
confirmation of the closing of the file, Jomela suddenly
decided to notify all the registered I&APs of the fact that the
former EIA process was terminated and that the process will
to Chapter 6, Section 41 of the 2014 NEMA EIA Regulations. The scoping
report was updated and sent out to registered parties from the previous
application as you so “however’ mentioned that they should also be included
which we have done so. We put up notices and advertised and we have
been adding parties who are registering for this process.
The reason why we arranged the meeting during the scoping period (which
is not against regulation) was due to the fact the we are also doing the
MPRDA consultation and we are aware that some of the farms in the area
have changed ownership. The issues raised by I&AP’s from the previous
application are still valid and we would like to afford new parties to raise
their issues.
This “selfish time driven process” as you call it is based on the legislation.
The scoping report has been released and I&AP’s have been given 30 days.
As you well know that the scoping report needs to be submitted within 44
days of the submission of the application how do we then give I&AP’s 30
days to register and then another 30 days for the review of the draft report
and be still within the timeframes?.
We are not limiting comments from registered parties but to anyone
interested or affected by the project. Jomela appointed specialists who
compiled studies and the negative impacts identified have not been masked
or hidden to I&AP’s. Jomela has not downplayed comments from I&AP’s, we
have included objections in the consultation reports and made the
department aware of these. The issue that water is a problem in the area
has been noted and the request for a regional study from IAP’s was noted in
the minutes. And as part of the IWULA which we are undertaking the DWS
will either approve or reject the application for the water use license based
-
start afresh. Jomela undertook to handle the new process in
a transparent matter, but this is once again not the case.
Jomela decided, without any permission from the delegated
authority (Jomela could not provide any proof of permission)
to refrain from placing any new newspaper adverts and site
notices which made I&APs aware of the new process. Jomela
furthermore failed to distribute notices to the surrounding
land-owners and tenants and to the current occupants of the
land. We only recently received a BID document, which was
sent out to the registered I&APs after Bokamoso enquired
about the PP process that was followed for the new EIA
process.
Bokamoso furthermore requested in recent correspondence
that Jomela supply proof of the newspaper advertisements,
site notices ad notices that were distributed to the
surrounding land owners in terms of the new process, but
Jomela failed to respond to this request.
We are of the opinion that Jomela failed to follow due process
and that the Public Participation for this new application is
once again “fatally flawed” and that it needs to be repeated.
New I&APs could have moved into the area since the last
public participation and the refusal to re-advertise will most
definitely have a negative impacts on new land-owners and
tenants. The fact that the new process was not re-advertised
furthermore creates an enormous amount of confusion,
because many of the I&APs still think that that Jomela is
on the stressors and water availability of the catchment.
A final register plus issues and response report will be included in the final
scoping report will be made available to all interested and affected parties.
And continuous engagement is not limited to the 30 days of the scoping, if
I&AP”s request another meeting we will schedule it. It is your prerogative not
to attend the meeting but we will still hold the meeting and identify other
parties.
-
continuing with the former EIA process.
Jomela should have followed the following steps with the new
Application:
Option 1: Follow a complete new process with full Public
Participation (PP)
Such a process will require that at least the following PP
be done:
- Placement of advertisements in newspapers in line with
the requirements of the MPRDA/ NEMA, the NWA and
NEM:WA;
- Placement of site notices at prominent points on the
site;
- The distribution of notices to the surrounding land-
owners, tenants. Occupants of land etc. (not only to I&APs
registered in terms of the former PP process, which was also
“fatally flawed”);
- Affording the I&APs a period of 30 days to register as
I&APs and to raise issues and concerns before compiling the
Draft Scoping Report and before making the Draft Scoping
Report available to I&APs;
- Creation of revised I&AP data base; and
- The compilation of a Scoping Phase Issues and
Response Report
None of this was done!!!!
The EAP simply used the I&AP database compiled during the
former EIA process, which is no longer valid and made no
effort whatsoever to comply with the steps as listed above.
-
The EAP had the arrogance to supply the I&APs registered in
the former EIA process with a copy of the same Draft
Scoping Report compiled for the former process and
requested that the I&APs supply comments within 30 days.
This is unfair and the I&APs and surrounding land-owners
and tenants are being prejudiced by this time driven and
selfish process of the applicant and the EAP. This clearly
indicated that he EAP is bias.
What is even more concerning is the fact that the EAP even
went as far as to arrange a public meeting in the SR
comment period. The public meeting was arranged less than
2 weeks in advance and during a school holiday. It is
regarded as reasonable if a public meeting is arranged at
least 2 weeks in advance.
Option 2: Apply for Exemption from PP
If the EAP wanted to make use of the PP process followed in
the previous application for which the file was closed. The
EAP should have applied to DMR in a formal exemption
application for exemption from public participation.
Unfortunately an exemption process also requires Public
Participation and it is therefore often just better to repeat the
public participation process when a file is closed and when
the EIA process needs to start afresh. As EAPs with many
years of experience in EIA applications, we had similar
situation in Limpopo Province with files that were closed and
PP processes that we wanted to carry over to the new EIA
processes. The delegated authority simply refused to allow
-
the usage of the previous PP process without an exemption
application and we eventually had to repeat the entire pp
process for the new applications.
Based on the above, we are of the opinion that the public
meeting cannot take place without proper advertising and
notification of the I&APs. We are furthermore of the opinion
that the request to provide comments regarding the Draft
Scoping Report is premature, because the EAP simply
accepted that no new I&APs will register in the mining
application process and simply decided to limited the I&APs
for the new process to the I&APs that were identified and
registered in the former EIA process.
This mining application will have a devastating and
irreversible impact on all environmental associated with the
study area and its surroundings and many of the I&APs are
getting the impression that the applicant plans to down-play
their comments in order to achieve the results as prematurely
promised to the investors.
The proposed open cast mining activity will amongst others
include the following impacts/ “fatal flaws”:
- The proposed mining activities will lead to the total
exploitation and destruction of the limited water resources in
the area, which is mainly associated with the river bed area
(the applicant’s own specialist confirmed this statement
during the former EIA application which lapsed). At present
-
the game farms and other vegetable farmers are already
struggling to irrigate their crops and feed game during
drought periods and the proposed new mine will utilize every
drop of available ground water. This is not in line with the
reserve determination allocations of the National department
of Water and Sanitation (DWS);
- The current ecological systems associated with the
river system in which the coal mining will take pace will be
destroyed completely (the applicant’s own specialist
confirmed this in his fauna and flora report attached as part of
the former EIA report compiled for the application which
lapsed);
- The relative flat landscape with the scattered Boabad
trees create a unique “Sense of Place” ad this will be
destroyed completely;
- The area have a very tranquil atmosphere and most of
the farmers purchased farms in this area in order to enjoy the
tranquil atmosphere with starlit evenings without any lighting
pollution. The proposed open cast mine will destroy this
valuable asset of the area;
- The road infrastructure in the area and the available
accommodation and social facilities in the area will not be
able to cater in the needs of the new employees at the mine;
- The surrounding roads are sub-standard roads and
cannot accommodate heavy vehicles and machinery that
travel to and from the mining areas.
Way Forward:
- If the EAP decide to continue with the process without
complying with the Public Participation requirements of the
-
applicable Regulations and Acts, the EAP must supply proof
that DMR exempted the EAP from new public participation;
- If the EAP received exemption from DMR for PP, all
I&APs have the right to peruse such exemption that was
granted, because exemption applications usually require
public participation;
- The EAP must give I&APs at least a 30 day period to
register as I&APs before making the Draft Scoping Report
available for comment. Surely the I&APs must be afforded
opportunities to raise new comments and issues of concern;
- If the public meeting takes place, the I&APs will
demand another public meeting after all the surrounding
farmers have been afforded a fair opportunity to register as
I&APs in the prescribed 30 day period. The meeting of 8
October 2016 will not be regarded as a proper public
meeting. This preliminary meeting can at most be regarded
as an introduction and first round data collection meeting that
will supplement data and information collected during a
proper public meeting;
- We will only supply comments regarding the Draft
Scoping Report after the 30 day I&AP registering period has
lapsed and once the Scoping Report has been updated in
order to accommodate the new list of I&APs and the new
issues and comments raised by the newly registered I&APs.
- It is however also recommended that the EAP also add
the I&APs registered in the previous application process as
I&APs of the new application process.
Juanita De Beer 08-10-2016 Thank you for your response. Please find attached consultation documents for Universal Coal
-
First of all you failed to provide us with proof of the
advertisements that were placed after we specifically
requested the proof. You only supplied it yesterday evening.
The proof of public participation should have been attached
as part of the Draft Scoping Report that was made available
to the public for review. This was not done. The applicable
regulations specifically require that proof of the public
participation process be attached as part of the Draft Scoping
Report. The new EIA Process
You already made the Draft Scoping Report available for
review on 13 September 2016, but you only placed the
advertisements and site notice 10 days after the Draft
Scoping Report was made available for review. In the
newspaper notice you mentioned to the new I&APs that the
Draft Scoping Report is available for review and that they
only have until 13 October 2016 for comments (less than
30days were afforded to newly registered I&APs for
comment). You once again failed to afford the I&APs a
minimum of 30 days for comments and you are once again
not complying with the timeframes as set in the legislation.
In your previous e-mails and notices forwarded to the I&APs
you explained that the former EIA process lapsed, because
you failed to supply the I&APs a minimum of 30 days to
supply comments regarding the report that was made
available. You decided to repeat this mistake again in the
new process. The new I&APs (the I&APs who registered after
Development II (Pty) Ltd as requested.
Your comments have been noted. For compliance purposes we will submit
the scoping report on the 14th but we will receive comments until the 23rd of
October and update the consultation report which we will submit to the
department.
We also have the Mining Right application commenting period open until the
2nd of November 12p.m.
We will send out the scoping report to registered parties on the 14th and we
will keep the registration process of any I&AP’s open. The reason why we
had the meeting during the scoping period is due to the fact that from the
previous consultation I&AP’s had concerns that we had held the meeting
outside the scoping period.
We do however are not limiting I&AP’s to one meeting. If I&AP’s do however
request a meeting we will be more than happy to arrange.
-
the advertisements and site notices were placed and the
I&APs who can still register until 23 October 2016) are once
again prejudiced, because they have less than 30 days to
supply comments and the public meeting is held before the
lapsing of the 30 day registration period. The people who
register after the public meeting will not even have an
opportunity to attend a Scoping Phase public meeting,
because the public meeting is held before the registration
period ends on 23 October 2016. This is a very sensitive
project and the proposed mine will have a devastating impact
on the environment and it is therefore crucial that you follow
the correct procedures and processes. Your own specialists
emphasized the irreversible and significant negative impacts
on the water resources, ecological environment and various
other environments and you are fully aware of the
controversy around this project.
Are you going to give the newly registered I&APs an
extension of time for the submission of comments regarding
the Draft Scoping Report? Are you going to make an
amended scoping report available which includes the public
participation details and which includes the comments and
issues raised by the new I&APs? Please clarify the way
forward.
We will also appreciate it if you could supply us with minutes
and attendance register of the first public meeting that will be
held today. We will also appreciate it if you could furnish us
with a copy of the power point presentation presented at the
-
meeting. We need copies of the minutes and the presentation
by Monday 10 October 2016, because you only afforded
I&APs until 13 October 2016 to supply their comments
regarding the Draft Scoping Report.
Naas Grové
11-10-2016 Kindly forward information to be registered as an IA&P
President: Dendrological Society of South Africa
082 575 4244
Constance
Ndavhedi Mbali
(Mudau
10-10-2016 Good day Yvonne
My name is Constance Ndavhedi Mbali (Mudau) I hereby
respond to the below mentioned notice and likewise declare
my interest in the matter.
NOTICE OF A COAL MINING RIGHT APPLICATION AND
A SCPOING REPORT ON THE FARMS
BERENICE 548MS, CELINE 54 PORTION 1
DOORVAAEDT 355MS, REMAINDER DOORVAARDT
355MS, MATSURI 358 MS, LONGFORD 354MS AND
GEZELS 395MS LOCATED IN MAKHADO, LIMPOPO BY
UNIVERSAL COAL DEVELOPMENT II (PTY) LTD.
I deem myself as one of the affected parties in respect of the
above mentioned matter. I am the daughter of the late
Moyanalo Annah Mudau whom was a daughter to Jacob
Maano Motau and Moshasawe Sophi Motau who are my
grandparents. My grandparents own a portion of the farm’s
land. They had children and raised them on the very same
farm who are now my aunts and uncles. I too was born and
You have been registered as an interested and affected party. You will
receive any and all communication regarding the project. We are
independent environmental consultants and only deal with the
environmental issues. Compensation issues can only be discussed with
Universal Coal after such a time the mining right has been granted. But the
issues that you have raised will be noted. Since we did not have your details
previously that is why we submitted hard copies to the actual farm to allow
the residents an opportunity to share the information with other members.
-
grew on the farm. I spent most of my childhood upbringing on
the farm and I was raised by my grandparents following the
passing of my mother. I am currently based in Gauteng and
when I go to my homelands during holidays I go to the farm.
The farm is a home to me and holds a precious place in my
heart as it contains rich history of my family and our heritage
as the Badau clan.
Sadly the head of our family Mr J M Motau( Mudau) passed
on and he was buried on the farm. We have a very big family
and we hold our annual family gatherings on the farm. I am
convinced that with the information I have declared to you I
am truly and deeply affected by the changes to take place on
our homeland.
I therefore would like to find out more information about how
will I benefit from the compensation and what plans are put in
place for the affected individuals going forward.
Should you require further clarity you may contact me on my
cell: 071 595 7019 or email: [email protected]
In addition to the above, kindly note that the following will
also be part of the affected parties. I have CC’d them to ease
your reference.
1. Maropeng Daphey Sithole ( Mudau) - 851008 034
2082 – 072 123 8347
2. Refilwe Paulete Duba ( Mudau ) – 881125 037 2085 –
072 145 2180
I trust you find the above in order and I hope to hear from
you soon.
tel:071%C2%A0595%207019mailto:[email protected]:072%C2%A0123%208347tel:072%C2%A0145%202180
-
Bokamoso 1) INTRODUCTION
It was requested that Bokamoso, on behalf of some the
surrounding landowners/tenants/farmers to peruse the Draft
Scoping Report for the above mentioned project and submit
comments regarding the report to Jomela Consulting (Pty)
Ltd. A copy of this comment document will also be forwarded
to the Limpopo Department of Economic Development,
Environment and Tourism (LDEDET).
To follow now are the preliminary comments regarding the
Draft Scoping Report for the new application for the proposed
open cast coal mine, which will be developed on the above
mentioned farms.
2) COMMENTS REGARDING THE DRAFT SCOPING
REPORT WHICH WAS MADE AVAILABLE ON 13
SEPTEMBER 2016
2.1) SUMMARY OF BACKGROUND INFORMATION AS
SUPPLIED IN THE DSR
Universal Coal Development ll (Pty) Lt had been appointed
by Jomela Consulting (Pty) Ltd to conduct an Environmental
Impact Assessment (EIA) to evaluate the potential
environmental and social impacts of the proposed project.
The applicant intends to establish an opencast coal mining
operation, located in the Limpopo Province of South Africa,
some 120 kilometres (km) to the North of Polokwane and to
the east of the settlement of Alldays. The project may
be REACHED via an all-weather gravel road that branches
off from the tar road. The R584, between Alldays and
Waterpoort.
-
The farms covered by the Berenice Project is 7761.0950
hectares in extent, is held under Prospecting Right (PR) (No.
LP30/5/1/1/2/378PR); granted to Universal Coal
Development lI (Pty) Ltd that expires on 19 March 2016. The
'Boreholes drilled in the prospecting area indicates that the
area of interest lies on the farms Berenice 548 MS, Celine
547 MS, Doorvaart 355 MS, Matsuri 358 MS and Longford
355 MS, with no coal on the Farm Gezelschap 395 MS.
Apparently the Berenice Project has a JORC compliant coal
resource of 1.358t (gross tonnes in situ) of which 424.91 Mt
are measured, 800.92MT indicated and 124.29MT inferred.
The Proposed site location (Berenice project), is located
within the B-block of the Mopane
Sub-Basin sector of the Soutpansberg coalfield.
In order to assess the potential impacts, it was stated that the
following specialist studies will be conducted and included as
part of the EIA:
0 Air Quality impact assessment
Hydrological assessment (Surface water)
0 Geohydrological assessment
Ecological assessment
Soil and land capability
Social impact assessment
0 Visual impact assessment
-
0 Noise assessment
Traffic impact assessment
Heritage impact assessment
In the Scoping Report the EAP referred to the public
participation process that was followed.
The EAP however only included detail of the PP process
followed as part of the former EIA process application for
which the file was closed due to the fact that the EAP failed to
afford the l&APs 30 days to supply comments regarding the
reports that were made available.
The I&AP database as supplied in the Scoping Report also
refers to the I&APs that registered in the former EIA process
for an application which is no longer applicable.
2.2) COMMENTS REGARDING THE DRAFT SCOPING
REPORT AND THE PROCESS
FOLLOWED UP TO DATE:
GENERAL:
As qualified environmental consultants with many year’s
experience in the compilation of EIA applications, we are of
the opinion that the EAP appointed for the mining application,
failed to act as independent consultant. The independence of
the EAP will be challenged.
The EAP is well aware of the time constraints associated with
an application once an application has been submitted to the
delegated authority, but due to fact that the mining application
is subject to serious time constraints, the EAP forces the
I&AP’s where supplied with the relevant documents via email, including the
minutes from the public meeting.
Comment has been noted
-
I&APs to participate in a flawed PP process.
The EAP is also well aware of the fact that the 2014 EIA
Regulations make provision for the compilation of specialist
reports and extensive PP prior to the submission of an
application to the competent authority, because such pre-
application procedures actually allow for the EAP to address
and consider all issues raised by the I&APs before embarking
into a process with strict timeframes.
PUBLIC PARTICIPATION:
The Public Participation process that was followed in the
Scoping Phase is once again regarded as insufficient and
“Fatally Flawed”;
The advertisements for the new EIA process were only
placed on 23 September 2016. In the advertisement it is
stated that all l&APs have an opportunity to register as
I&APs until 23 October 2016, but in the same advertisement
it is mentioned that the Scoping Report is available for
review, but only until 13 October 2016. How is this possible?
This is very irregular and arrogant and will without any doubt
prejudice any new I&APs that wish to register during the
public participation process for the new application. In the
EAP’s own notices that were distributed (after the closure of
the file for the former application) and in this scoping report,
the EAP stated that the former application file was closed due
tot the fact that they failed to allow the l&APs 30 days to
supply comments regarding the EIA Reports;
Comment Noted
This objection has been noted. We have kept the commenting period open.
Please do note that we are re-advertising and as requested in the email
received from Bokamoso, we will keep the registration and commenting
period open for another 30 days. These comments will be continuously
updated in the comments and response report.
-
The EAP is now repeating this mistake. The EAP supplied
the I&APs that registered in the former EIA process (which is
no longer applicable) with a Scoping Report for review on 13
September 2016 and requested that their comments be
submitted to Jomela on 13 October 2016, because the Final
Scoping Report will be submitted to DMR on 14 October
2016. This just illustrates that it was never the EAP’s intention
to incorporate and address the issues raised by the l&APs on
13 October 2016 as part of the Final Scoping to be submitted,
because it is impossible to thoroughly address the issues
raised by the formerly registered I&APs (in an amended
report), especially with regards to a controversial application
such as this one, in only one day.
The EAP simply ignored that fact that they have to follow a
new PP process for the new application and that the new
process must allow l&APs 30 days to register as l&APs and
only after the l&APs are registered in terms of the new EIA
process are they allowed to make the Draft Scoping Report
available for a further 30 days for review to all parties that
registered.
The EAP is now furthermore going to submit the Final
Scoping Report to DMR without the comments of the newly
registered l&APs and l&APs that can still register until 23
October 2016. The public meeting was also held prior to the
lapsing of the registration period for the l&APs and this selfish
and time-driven action also prejudiced the l&Aps who still
have an opportunity to register between 8 October 2016 (the
day of the public meeting) and 23 October 2016 (the last day
The public meeting was held during the scoping phase as we had noted
objections not to hold the meeting outside the scoping phase. We are
however prepared to have another meeting for the scoping phase at the
request of I&AP’s/
-
afforded for registration).
As stated in our e-mails that were sent to Jomela prior to the
public meeting, they should have applied for exemption from
public participation if they intended to submit the Final
Scoping Report before the new registration period/
advertisement period for the l&APs lapsed and if they wanted
to rely on the PP of the former application (for which the file
has been closed due to insufficient PP) in the new
application. l&Aps are now very confused, especially due to
the fact that the EAP requested that the l&APs who
registered in the former EIA process for the mine, now also
submit their comments regarding the Jomela EIA report that
was made available in the former process.
It is also important to note that we were recently contacted by
land-owners, workers and tenants in the area who only
recently became aware of the proposed mine in the area.
Some of the PDls are extremely upset about the limited
efforts that were made to notify them of the proposed mine,
which will have a devastating effect. Apparently some of the
l&APs could not understand the language on the notices and
they are furthermore not equipped with technology to register
by means of faxes/ e-mails.
How are you going to deal with l&APs that register after you
submitted the Final Scoping Report? Will you withdraw the
Scoping Report at DMR in order to afford them the required
30-day period to comment on the Draft Scoping Report?
-
Certainly you are not again going to submit your final report
and as an afterthought file the submissions and comments of
such I&APs who lawfully has time to lodge their submissions
until :23 November 2016.
If DMR decide to accept this flawed PP process it will create
an untenable precedent and applicants for similar
applications will be able to use advertisements and
comments supplied by I&APs in former processes, without an
application for exemption in an endeavor to comply with the
PP requirements for the new EIA process. It shall indeed
make a mockery of the entire PP process to the detriment of
I&APS
The I&APs were once again not afforded 30 days for the
submission of comments;
The EAP will not be able to attach an updated I&AP data
base to the Final Scoping Report, which is unacceptable;
The EAP failed to notify all the organs of state that could
have an interest in the matter;
The low attendance figures at the public meeting held on 8
October 2016, which was arranged with less than 2 weeks
notice and before all the I&AP had the opportunity to register,
once again confirms the “non-transparent” and flawed public
participation process that was followed up to date. The EAP
clearly only pays lip services to the statutory requirements in
that regard and with undue haste to the detriment of the
The comments received will be submitted to the DMR and in addition to that
these comments will also feed into the EIA report.
-
entire process endeavors to bulldose the process to
finalization;
The EAP failed to apply for an extension of time for the
submission of the Final Scoping Report and the time limits
associated with the application will without any doubt
prejudice the I&APs. The inevitable result of the aforegoing
would be that this process shall again be nullified as a result
of non-compliance with the timeframes imposed by applicable
legislation.
2.3) DETAILED COMMENTS
The proof of PP attached as part of the DBAR is not in line
with the applicable
legislation;
The DBAR lists the specialist studies to be conducted during
the EIA process. We are of the opinion that it will be
necessary to conduct the following additional studies:
4» A detailed wetland delineation, because most of the
mining activities will take place within a very sensitive
watercourse. In the former EIA it was stated that
it was not possible to do a wetland delineation due to limited
access to the properties;
4. An aquatic assessment;
4:- A red data fauna and flora study;
Noted and these will be done during the EIA
-
1L A certification of the pre- and post-construction 1:100 year
floodline, because mining activities will have a significant
impact on the flood line, even outside the boundaries of the
mining area;
4» The technology problems and language problems of the
PDI l&APs must be taken into consideration and dealt with in
line with the applicable PP Regulations and guidelines;
«L An updated geo-hydrological assessment will be required,
because the geo-hydrological report compiled as part of the
former application process was incomplete and sub-standard.
3) CONCLUSION AND RECOMMENDATIONS
Bokamoso is of the opinion that the PP process followed for
the new application is “fatally flawed”. The EAP once again
failed to afford l&APs 30 days to supply comments regarding
a Draft Report and the public meeting was held before all
l&APs had the opportunity to register for the new process.
The EAP had to apply for an exemption if they wanted to
deviate for the PP requirements as set out the applicable
regulations and DEA guidelines.
Based on the above, we regard the process followed up to
date as invalid and it is recommended that the EAP rather
terminate the current application process and start afresh
Adverts will be published in Venda, Afrkaans and English.
-
Rikus Myburgh 17 October
2016
Wie dit mag aangaan,
Hiermee gee ek aan Universal Coal Development II (Pty) Ltd
kennis dat ek;
‘n Geaffekteerde person is as verteenwoordiger en
proxy vir die plase Renfrew, Thurso en Andromeda
aangrensend tot die projek
Ten sterkste beswaar maak teen die beoogde
mynprojek aangesien:
o Daar bloot nie naastenby genoeg water in
die gebied is vir mynboubedrywighede nie,
veral oopgroef steenkoolmyne
o Die beoogde projek die migrasieroete van
luiperds van/na die Soutpansberg afgesny
en/of erg beperkend sal maak, met
gepaardgaande eskalering van skade vir
wildboer wat in die gebied boer;
o Besoedeling van ondergrondse water ‘n
ernstige negatiewe invloed op die
verbouing van ‘n verskeidenheid van
groente in die gebied sal he
o Die padinfrastruktuur is glad nie in staat om
die addisionele swaarvoertuie te
akkommodeer nie.
Thank you for registering as an affected party. Your objection has been
noted. We will address the issues in the EIA report.
Dr Ian Little 14 October,
2016
RESPONSE TO: DMR REF NO. LP 30/5/1/2/3/2/1 (10131)
Your comments and objections have been received.
-
EM, application for mining rights (Berenice project), Makhado
local municipality Limpopo.
The Endangered Wildlife Trust (EWT) is a non-governmental,
non-profit, conservation organisation, founded in 1973 and
operating throughout southern Africa. The EWT conserves
threatened species and ecosystems in southern Africa by
initiating research and conservation action programmes,
implementing projects which mitigate threats facing species
diversity and supporting sustainable natural resource
management. The EWT furthermore communicates the
principles of sustainable living through awareness
programmes to the broadest possible constituency for the
benefit of the region. The EWT has developed a unique
operational structure through which the mission and
objectives of the EWT can be achieved. The EWT achieves
its conservation goals through specialist, thematic Working
Groups, designed to maximise effectiveness in the field and
enhance the development of skills and capacity.
The EWT strives to conserve biodiversity assets, ecosystem
services and our natural heritage in general to the benefit of
all people in South Africa.
The proposed mining project is situated in a highly sensitive
and biologically important area. This is supported by the fact
that 90% of the area is identified as Critical Biodiversity Area
1 or 2 and the remainder as Ecosystem Support Areas 1.
Cumulative impacts including road networks, air, soil and
water pollution in the region will have further knock-on effects
on associated critical biodiversity areas including the Langjan
Provincial Nature Reserve (17km from proposed site). It is
Noted
-
important to note that there are No alternative sites available
to meet the proposed targets, especially because this whole
region falls within the within the proposed buffer zone of
Vhembe Biosphere Reserve (2016 SEMP). On top of this are
the water issues that will be associated with this proposed
mining activity. The proposed area is on the Brak River which
is a Class B river (Largely Natural under NFEPA
classification). The impacts on the river and its riparian zone
will be impossible to rehabilitate and this on top of the fact
that the proposed water consumption exceeds the annual
rainfall in the area and that the area is a drought catastrophe
area means that this proposal should not even be considered
from a Water Use Licence perspective.
Given the overall biodiversity value of the area, the
cumulative impacts of the proposed activity, the inability to
rehabilitate such a sensitive area and the extreme water use
issues we strongly oppose this application.
It has been noted that the buffer has been proposed and not implemented
yet. This has been noted and will be taken into consideration by the DMR as
they evaluate the feasibility of the project.
Due to the sensitive nature of the Brak River, the applicant has amended
their layout cutting out areas of the proposed OC2 and OC3 mining areas.
This was done so as to avoid mining within 100m of the river and floodlines.
Noted.
Bokamoso These l&APs requested our office to register them on your
data basis as some of them do not have access to emails.
Therefore we would like to inform you of additional l&APs
whom we would like add on your l&APs Database. Take note
that all correspondence regarding
this project should be forwarded to both the l&APs and
Bokamoso in the future.
We are also under the impression that the comments on the
Draft Scoping Report had to be submitted on the 13th of
October 2016, however the registration period for l&APs is
Noted
-
accepted until today 23 October 2016 (which falls on a
Sunday therefore the actual date will be Monday, 24 October
2016). These l&APs would also like an opportunity to
comment on the Scoping Report and they are allowed to
have a 30 day comment period to peruse the available
documents and supply your office with comments. The 30
day comment period should commence on Monday, 24
October 2016 until Tuesday, 22 October 2016. It is therefore
requested that your office make the Draft Scoping Report
available to them at a public facility in close proximity to them
in order for them to peruse the documents (Draft Scoping
Report). Unfortunately our offices are not close to them and
therefore we cannot assist them in this regard. As mentioned
before, please ensure to inform the people without any email
addresses by means of sms communication.
A list with the additional people to add to your database is
attached as Annexure A to this.
Kindly keep our office as well as these individuals updated
regarding any other available information, meetings, reports
etc. regarding the project throughout the remainder of the
process. Please note that some of these affected parties do
not have access to emails and it is requested yet again that
your office inform them by means of sending them a sms. It
should also be considered to arrange for an interpreter to
attend any future public meetings as some of the people do
not understand English and should be given the opportunity
to fully grasp what is being said in their own home language.
The common home language in the area is Pedi and Venda.
We have received the list of I&AP’s and we will contact them and find the
nearest area where we can send the reports for them.
-
Bokamoso furthermore would like to know if the Final
Scoping Report for this project had been submitted to the
relevant authorities for consideration. Please provide our
office with written confirmation in this regard as well as proof
that the additional l&APs were registered and given an
opportunity to peruse the Draft Scoping Report.