Public Information Meeting New Champlain Bridge Corridor Project

Centre Elgar - November 5, 2015

Page 2: Public Information Meeting L’Île-des-Soeurs - New Champlain Bridge Corridor Project - November 5, 2015

New Champlain Bridge Corridor Project

To inform you about

the completed and upcoming work on the

new Champlain Bridge corridor project

on L’Île-des-Soeurs

-----------

including anticipated impacts

and mitigation measures

------------

and to answer your questions

Meeting Objective

2

Page 3: Public Information Meeting L’Île-des-Soeurs - New Champlain Bridge Corridor Project - November 5, 2015

New Champlain Bridge Corridor Project

Agenda

• Welcome

• Review of the project and our technical solution

• Context specific to L’Île-des-Soeurs

• Key activities

First 6 months

Next 12 months

• Impacts and mitigation measures

• Communications

• Question period

3

Page 4: Public Information Meeting L’Île-des-Soeurs - New Champlain Bridge Corridor Project - November 5, 2015

New Champlain Bridge Corridor Project

Jean-François Parenteau Mayor of the Borough of Verdun

Welcome

4

Page 5: Public Information Meeting L’Île-des-Soeurs - New Champlain Bridge Corridor Project - November 5, 2015

New Champlain Bridge Corridor Project

Daniel Genest Director Coordination Signature on the Saint-Laurent

Marthe Robitaille Director Environment Signature on the Saint-Laurent

5

Page 6: Public Information Meeting L’Île-des-Soeurs - New Champlain Bridge Corridor Project - November 5, 2015

New Champlain Bridge Corridor Project

Challenges of the Project

• Very large, complex site

Urban setting

Near residents

Over water

Winter conditions

Environmental considerations

• Numerous partners and stakeholders : importance of

providing information well ahead of time to ensure proper

collaboration and coordination

• Construction of Champlain Bridge : 42 months

(now 37 months remaining) 6

Page 7: Public Information Meeting L’Île-des-Soeurs - New Champlain Bridge Corridor Project - November 5, 2015

New Champlain Bridge Corridor Project

Bird’s Eye View

7

Page 8: Public Information Meeting L’Île-des-Soeurs - New Champlain Bridge Corridor Project - November 5, 2015

New Champlain Bridge Corridor Project

Sectors and Sequence of Construction

West Approach

26 spans : WA - W02

Cable-stayed Bridge

4 spans : W02 - E02

East Approach

9 spans : E02 - EA

1 W4 W3 W2 W1 MST E1 E2

3 2 1 1 2 1 2 4

8

Execution of works in three sectors, in parallel

Page 9: Public Information Meeting L’Île-des-Soeurs - New Champlain Bridge Corridor Project - November 5, 2015

New Champlain Bridge Corridor Project

Bridge Construction Strategy

Steel superstructure

Steel pier caps

Concrete pier

Concrete footing

Concrete deck

9

• Maximize pre-fabrication of concrete components, with the option of cast-in-

place when more practical :

Footings : West Jetty

Piers and deck : Drummondville

• Pre-assembly of steel pier caps and superstructure : three jetties

• Delivery, installation and assembly by barge and catamaran

Page 10: Public Information Meeting L’Île-des-Soeurs - New Champlain Bridge Corridor Project - November 5, 2015

New Champlain Bridge Corridor Project

Context Specific

to L’Île-des-Soeurs

• Gateway to one of the largest infrastructure projects in North America

• Construction of the new Champlain Bridge :

West Jetty : pre-fabrication of footings and pre-assembly of pier caps and

superstructure

West Approach : marine excavation, installation of footings, piers and pier caps, and

assembly of superstructure

• Reconfiguration of the road corridor :

Demolition and reconstruction of the Île-des-Sœurs bridge

Reconfiguration of Highway 15

• Presence of the Project Team office (8 Place du Commerce) and largest project

site facilities (Pointe-Nord)

10

Page 11: Public Information Meeting L’Île-des-Soeurs - New Champlain Bridge Corridor Project - November 5, 2015

Key Activities of the Last 6 Months

Page 12: Public Information Meeting L’Île-des-Soeurs - New Champlain Bridge Corridor Project - November 5, 2015

New Champlain Bridge Corridor Project

• Major communication efforts

• Detailed design

• Construction of large-scale temporary works : two large jetties completed and

a third underway

• Start of the construction of the main pylon of the new Champlain Bridge

• May Street demolition

• Site facilities in the Pointe-Nord sector of L’Île-des-Sœurs and south of the

Gaétan-Laberge interchange

• Transfer of responsibility for operation and maintenance of the A15 and A10

road links, from JCCBI to SSL

Major Project Activities Since Our Selection in mid-April

12

Page 13: Public Information Meeting L’Île-des-Soeurs - New Champlain Bridge Corridor Project - November 5, 2015

New Champlain Bridge Corridor Project

West Jetty : Pre-fabrication and Pre-assembly Facilities

13

Page 14: Public Information Meeting L’Île-des-Soeurs - New Champlain Bridge Corridor Project - November 5, 2015

New Champlain Bridge Corridor Project

West Jetty : Look Back at the Construction

• Work :

Jetty: June 15 to August 19, 2015

Pre-fabrication and pre-assembly facilities: underway since August 20, 2015

• Trucking related to jetty construction :

212,000 m³ / 435,780 tons of rock

13,017 truck trips

277 trips per day, on average

• Limited impact on traffic

• No incidents with cyclists or pedestrians

• Noise management and air quality : prescribed thresholds respected

• Rapid reaction to residents’ complaints : calls returned and corrective

measures taken

14

Page 15: Public Information Meeting L’Île-des-Soeurs - New Champlain Bridge Corridor Project - November 5, 2015

New Champlain Bridge Corridor Project

Site Facilities

15

Page 16: Public Information Meeting L’Île-des-Soeurs - New Champlain Bridge Corridor Project - November 5, 2015

New Champlain Bridge Corridor Project

Site Office

16

Page 17: Public Information Meeting L’Île-des-Soeurs - New Champlain Bridge Corridor Project - November 5, 2015

New Champlain Bridge Corridor Project

Key Activities for Next 12 Months :

West Approach

Design and planning underway

therefore modifications are possible

Page 18: Public Information Meeting L’Île-des-Soeurs - New Champlain Bridge Corridor Project - November 5, 2015

New Champlain Bridge Corridor Project

Underway : Construction of pre-fabrication and pre-assembly facilities

Next :

• Step 1 : Pre-fabrication of footings and pre-assembly of pier caps and

superstructure - November 2015 to April 2018

• Step 2 : Marine excavation - November 2015 to September 2016

• Step 3 : Installation of footings - April 2016 to July 2017

• Step 4 : Installation of piers and pier caps - May 2016 to August 2017

• Step 5 : Assembly of superstructure and deck - August 2016 to July 2018

• Step 6 : Finishing work - June 2017 to October 2018

Approach :

• Work done mainly during the day, except for pre-fabrication, which will take

place day and night

West Approach : Key Activities

18

Page 19: Public Information Meeting L’Île-des-Soeurs - New Champlain Bridge Corridor Project - November 5, 2015

New Champlain Bridge Corridor Project

Nov

2015 May Nov

2016

May Nov

2017

Nov

2018

May

Pre-fabrication and pre-assembly

Marine excavation

Installation of footings

Installation of piers and pier caps

Assembly of superstructure and deck

Finishing work

West Approach : Schedule

19

Feb

2016 Aug Feb

2017

Aug Feb

2018 Aug

Page 20: Public Information Meeting L’Île-des-Soeurs - New Champlain Bridge Corridor Project - November 5, 2015

New Champlain Bridge Corridor Project 20

Pre-assembly area

for steel superstructure

Pre-assembly area

for steel pier caps

Pre-fabrication area

for concrete footings

Loading facilities

Pre-fabrication and Pre-assembly Facilities

Page 21: Public Information Meeting L’Île-des-Soeurs - New Champlain Bridge Corridor Project - November 5, 2015

New Champlain Bridge Corridor Project

Concrete Footing and Pier Starter Segment

21

Concrete pier

starter segment

Concrete footing

Work platform

Page 22: Public Information Meeting L’Île-des-Soeurs - New Champlain Bridge Corridor Project - November 5, 2015

New Champlain Bridge Corridor Project

Marine Excavation

22

Page 23: Public Information Meeting L’Île-des-Soeurs - New Champlain Bridge Corridor Project - November 5, 2015

New Champlain Bridge Corridor Project

Installation of Deflector with Transport Gantry

23

Page 24: Public Information Meeting L’Île-des-Soeurs - New Champlain Bridge Corridor Project - November 5, 2015

New Champlain Bridge Corridor Project

Footing Loaded with Transport Gantry

24

Page 25: Public Information Meeting L’Île-des-Soeurs - New Champlain Bridge Corridor Project - November 5, 2015

New Champlain Bridge Corridor Project

Complementary Cleaning of Marine Excavation

25

Page 26: Public Information Meeting L’Île-des-Soeurs - New Champlain Bridge Corridor Project - November 5, 2015

New Champlain Bridge Corridor Project

Alignment of Footing with Cofferdam

26

Page 27: Public Information Meeting L’Île-des-Soeurs - New Champlain Bridge Corridor Project - November 5, 2015

New Champlain Bridge Corridor Project

Lowering and Positioning of the Footing at the Bottom of the River

27

Page 28: Public Information Meeting L’Île-des-Soeurs - New Champlain Bridge Corridor Project - November 5, 2015

New Champlain Bridge Corridor Project

Retrieval of the Work Platform and Deflector

28

Page 29: Public Information Meeting L’Île-des-Soeurs - New Champlain Bridge Corridor Project - November 5, 2015

New Champlain Bridge Corridor Project

Installation of the Piers

29

Page 30: Public Information Meeting L’Île-des-Soeurs - New Champlain Bridge Corridor Project - November 5, 2015

New Champlain Bridge Corridor Project

Transition from Piers to Pier Caps

30

Page 31: Public Information Meeting L’Île-des-Soeurs - New Champlain Bridge Corridor Project - November 5, 2015

New Champlain Bridge Corridor Project

Steel Pier Caps

31

Page 32: Public Information Meeting L’Île-des-Soeurs - New Champlain Bridge Corridor Project - November 5, 2015

New Champlain Bridge Corridor Project

Installation of Pier Caps, Superstructure and Deck

32

Page 33: Public Information Meeting L’Île-des-Soeurs - New Champlain Bridge Corridor Project - November 5, 2015

New Champlain Bridge Corridor Project

Key Activities for Next 12 Months :

A15 Corridor

Design and planning underway

therefore modifications are possible

Page 34: Public Information Meeting L’Île-des-Soeurs - New Champlain Bridge Corridor Project - November 5, 2015

New Champlain Bridge Corridor Project

Underway : Preparatory work for demolition of Île-des-Sœurs Bridge, including

construction of a jetty from the west bank of the channel

Next :

• Demolition of Île-des-Sœurs Bridge - November 2015 to April 2016

• Construction of new Île-des-Sœurs Bridge - March 2016 to September 2017

• Demolition of south-bound direction of existing overpass over Boul. de L’Île-des-

Sœurs - April to May 2016

• Construction of south-bound direction of new overpass over Boul. de L’Île-des-

Sœurs - May 2016 to April 2017

Approach :

• Demolition work during the day only, with debris collection activities in the

evening and at night

• Construction work during the day and night

A15 Corridor : Key Activities

34

Page 35: Public Information Meeting L’Île-des-Soeurs - New Champlain Bridge Corridor Project - November 5, 2015

New Champlain Bridge Corridor Project

Demolition of Île-des-Sœurs Bridge and Boul. de L’Île-des-Sœurs Overpass

35

Phase 1 : Demolition of

the bridge superstructure

Phase 2 : Demolition

of the piers

Phase 3 : Demolition of

the overpass

Page 36: Public Information Meeting L’Île-des-Soeurs - New Champlain Bridge Corridor Project - November 5, 2015

New Champlain Bridge Corridor Project

Construction of new Île-des-Sœurs Bridge

• Construction from a jetty and barges

• Construction period : March 2016 to September 2017

• Construction priority : south-bound direction, which will be open

to traffic in July 2017

36

Page 37: Public Information Meeting L’Île-des-Soeurs - New Champlain Bridge Corridor Project - November 5, 2015

New Champlain Bridge Corridor Project

Gaétan-Laberge Boulevard

• Vision : an urban boulevard leading to downtown

• Desire expressed to not create a « highway-type » interchange

37

Page 38: Public Information Meeting L’Île-des-Soeurs - New Champlain Bridge Corridor Project - November 5, 2015

New Champlain Bridge Corridor Project

Anticipated Impacts

and Mitigation Measures

Page 39: Public Information Meeting L’Île-des-Soeurs - New Champlain Bridge Corridor Project - November 5, 2015

New Champlain Bridge Corridor Project

Anticipated Impacts and Mitigation Measures

• Traffic

• Noise

• Air quality

39

Page 40: Public Information Meeting L’Île-des-Soeurs - New Champlain Bridge Corridor Project - November 5, 2015

New Champlain Bridge Corridor Project

Traffic Management

• Create and maintain safe conditions for

all users of the road network, cyclists

and pedestrians

• Minimize impact on users of the road

network, cyclists and pedestrians

• Continue the approach already in place

40

Page 41: Public Information Meeting L’Île-des-Soeurs - New Champlain Bridge Corridor Project - November 5, 2015

New Champlain Bridge Corridor Project

Noise Management

NOISE CRITERIA

• Day (7 a.m. to 7 p.m.) : 75 decibels or 5 decibels above

ambient noise level

• Evening and night (7 p.m. to 7 a.m.) : 5 decibels above

ambient noise level

Source: MTQ Turcot Project Presentation of November 18, 2014 41

A few basic concepts

Audibility

threshold

Sleep

threshold

Disturbing

noise

Irritating

noise

Harmful

noise

Pain

threshold

55 dBA and -

change barely perceptible

change perceptible

doubles or halves the audio intensity

recognized as an acceptable sound level

Sound levels do not compound in a linear fashion

Doubling the sources of noise doubling the noise level

Page 42: Public Information Meeting L’Île-des-Soeurs - New Champlain Bridge Corridor Project - November 5, 2015

New Champlain Bridge Corridor Project

Noise Management

42

Noise-sensitive Zones

West

Approach

Île-des-Sœurs

Bridge

Page 43: Public Information Meeting L’Île-des-Soeurs - New Champlain Bridge Corridor Project - November 5, 2015

New Champlain Bridge Corridor Project

Activity Work

period

Most

exposed

sensitive

zone

Ambient

noise

in dba

(May 2015)

Criterion

in dba

Estimated

noise in dba

(October

2015)

Specific

mitigation

measures

West Approach -

Construction

of loading facilities

D I2 / I3 64 / 57 75 65 No

West Approach -

Pre-fabrication of footings

D

E

N

I2 / I3

64 / 57

59 / 52

57 / 52

75

64 / 57

62 / 57

60

57

57

No

West Approach -

Marine excavation D I2 / I3 64 / 57 75 64 No

L’Île-des-Sœurs -

Construction of West Jetty D I1 57 75 66 No

L’Île-des-Sœurs -

Demolition of existing bridge D I1 57 75 73 No

L’Île-des-Sœurs -

Demolition of overpass D I1 57 75 69 No

Sound Management Plan

(up to end March 2016)

43

I1 : Sax

I2 : Evolo

I3 : Cours des Fougères

No specific mitigation measure required

Follow-up required

Page 44: Public Information Meeting L’Île-des-Soeurs - New Champlain Bridge Corridor Project - November 5, 2015

New Champlain Bridge Corridor Project

• Main mitigation measures for the entire work site:

Use variable-intensity back-up alarms

Organize traffic to minimize backing up

Control production of impact noise (truck tailgates)

Make site supervisors and workers aware of the need to comply with noise

mitigation measures

• Monitor noise levels during construction

At the beginning of critical activities, for verification purposes

Once or twice every two weeks

Check when there are complaints

Noise Management

44

Page 45: Public Information Meeting L’Île-des-Soeurs - New Champlain Bridge Corridor Project - November 5, 2015

New Champlain Bridge Corridor Project

Air Quality Management

Regulatory framework

Contractual environmental obligations

Clean Air Regulation (CAR)

Applicable MDDELCC Standards

MDDELCC CAR

PMT PM2.5

120 ug/m3 30 ug/m3

45

Page 46: Public Information Meeting L’Île-des-Soeurs - New Champlain Bridge Corridor Project - November 5, 2015

New Champlain Bridge Corridor Project

Air Quality Management

• No expected impact on sensitive zones

• Main mitigation measures for the entire work site:

Transport of materials in dump trucks with tarp covers

Appropriate maximum speed for vehicles, to reduce dust emissions on access roads

or jetty

Spraying water on surfaces

Regular cleaning of the streets used by vehicles and machinery in order to remove

any accumulation of movable material and other debris

If necessary, application of dust suppressant

• Monitoring to be done mainly for demolition activities

46

Page 47: Public Information Meeting L’Île-des-Soeurs - New Champlain Bridge Corridor Project - November 5, 2015

New Champlain Bridge Corridor Project

• Public information meetings : One per year, on average, per sector

L’Île-des-Sœurs (June 8), Verdun / Sud-Ouest (September 14) and Brossard (October 14)

• CINPA : Verdun / Sud-Ouest

Selection process underway

Kick-off meeting by the end of November

First CINPA “open session” meeting in January

• Newsletter available soon : suscribe through our web site

• Door delivered notices to residents, when needed, and local newspaper notices

• Site visit planned for this fall, has been postponed to May / June 2016

• Subscribe / contact us at :

Website : www.newchamplain.ca

Email : [email protected]

Phone : (514) 876-1020

Twitter : @NOUV_CHAMPLAIN

Communications

47

Page 48: Public Information Meeting L’Île-des-Soeurs - New Champlain Bridge Corridor Project - November 5, 2015

New Champlain Bridge Corridor Project

Blitz : 6 to 9 November 2015 (A15N Closure)

48

Detour

through Verdun

Autoroute Bonaventure

open

Page 49: Public Information Meeting L’Île-des-Soeurs - New Champlain Bridge Corridor Project - November 5, 2015

New Champlain Bridge Corridor Project