project planning latest

Upload: zishan-mallik

Post on 06-Apr-2018

217 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/3/2019 Project Planning Latest

    1/27

    Planning a Project

  • 8/3/2019 Project Planning Latest

    2/27

    2

    Project Planning Process

    1. Clearly define project objective (scope)

    2. Develop a Work Breakdown Structure (WBS)

    3. Estimate time needed for each task

    4. Determine resources needed for each task

    5. Estimate cost needed for each task

    6. Develop project schedule and budget (adjust

    as needed)

  • 8/3/2019 Project Planning Latest

    3/27

    3

    Project Scope

    A clear project scope definition provides the guidelinesthat are used to develop your project plan.

    Project Scope Checklist:

    Project objectives (purpose, due date, budget) Deliverables (at each major phase of project)

    Milestones (significant events in the project)

    Technical requirements

    Limits and exclusions (who, what, how) Review with customer (agreement on expectations)

  • 8/3/2019 Project Planning Latest

    4/27

    4

    Identifying Necessary Activities

    Start by identifying major-level activities or tasks

    Then each major task can be broken down into

    subtasks

    Project team members can be responsible for

    breaking down different major activities

    Then each subtask is broken down to lower-

    level tasks, and so on until you have basic work-unit levels (work packages) that will be assigned

    Result: Work Breakdown Structure (WBS)

  • 8/3/2019 Project Planning Latest

    5/27

    5

    Mind Maps

    Mind maps are a tool to help identify all the

    necessary activities in a project

    Its a type of brainstorming tool

    The mind mapping process can bring out more

    ideas than simply making a list

    It engages the team and generates enthusiasm

    It brings out quieter team members Mind mapping can be fast, compared to an

    outlining or listing approach

  • 8/3/2019 Project Planning Latest

    6/27

    6

    Mind Map for Project Planning

    10K run toRaise 50K

    for homeless

    shelter

    Transportation

    Promotion

    Prizes/recognition

    FacilitiesSafetyRefreshments

    Clean-up

    Route

    Registration

  • 8/3/2019 Project Planning Latest

    7/27

    7

    Mind Map for WBS

    Promotion

    Investigatepast events

    Interviewrunning

    club

    members

    Print Design

    To schools To sportsretailers

    Preparemailing

    Acquire

    addresslists

    Mailpromo

    Monitorairings

    Purchase

    air time

    Produceads

    TV and

    radio ads

    Mailings

    Flyers

    Research

    Distribute

  • 8/3/2019 Project Planning Latest

    8/27

    8

    Work Breakdown Structure

    Either shown graphically in a tree structure, or

    as index numbers listed beside activities

    Entire project is Level 0; the major-level activities

    are Level 1; and so on

    Index numbers identify level of the task in thetree structure

  • 8/3/2019 Project Planning Latest

    9/27

    9

    WBS Tree Structure

    Carnival

    GamesPromotionVolunteers Rides Entertain. Food

    NewspaperPosters Tickets Grandstand Performers

    SoundStage Seating

    Level

    0

    1

    2

    3

    3

    5.1.2

    21 4 5 6

    2.1 2.2 2.3 5.1 5.2

    5.1.35.1.1

  • 8/3/2019 Project Planning Latest

    10/27

    10

    WBS Activity List

    WBS ActivityCarnival

    1 Volunteers

    2 Promotion

    2.1 Posters

    2.2 Newspaper

    2.3 Tickets3 Games

    4 Rides

    5 Entertainment

    5.1 Grandstand

    5.1.1 Stage

    5.1.2 Sound

    5.1.3 Seating

    5.2 Performers

    6 Food

  • 8/3/2019 Project Planning Latest

    11/27

    11

    WBS for Promotion Example

    Level 1 Task Level 2 Tasks Level 3 Tasks

    1. Promotion 1.1 Research 1.1.1 Investigate past events

    1.1.2 Interview running club members

    1.2 TV and radio ads 1.2.1 Produce ads

    1.2.2 Purchase air time

    1.2.3 Monitor airings

    1.3 Mailings 1.3.1 Acquire mailing lists

    1.3.2 Prepare mailings

    1.3.3 Mail promotional materials

    1.4 Flyers 1.4.1 Design flyers

    1.4.2 Print

    1.4.3 Distribute to schools

    1.4.4 Distribute to sports retailers

  • 8/3/2019 Project Planning Latest

    12/27

    12

    Responsibility Chart

    Often called Linear Responsibility Chartor

    Responsibility Matrix

    Shows who has primary responsibility for each

    task

    Can also show who provides support, who must

    be notified upon completion, who must give final

    approval, who is the backup person, etc. It lets everyone see their roles throughout the

    project

  • 8/3/2019 Project Planning Latest

    13/27

    13

    Responsibility ChartWBS Activity A B C D E F G H I

    Carnival P S S S S S

    1 Volunteers P S

    2 Promotion P S S

    2.1 Posters P S

    2.2 Newspaper P S

    2.3 Tickets S P3 Games P S

    4 Rides S P

    5 Entertainment S S P

    5.1 Grandstand P S

    5.1.1 Stage P S

    5.1.2 Sound S P

    5.1.3 Seating P S S

    5.2 Performers S P

    6 Food S P

    P = Primary responsibility; S = Support responsibility

  • 8/3/2019 Project Planning Latest

    14/27

    14

    Estimating Activity Durations

    Two Approaches

    1. Bottom-up estimate: Ask the person

    responsible for each low-level task how long

    they think it will take. This assumes a givenamount of resources.

    2. Top-down estimate: Based on the project due

    date, tell the person responsible for each low-

    level task how much time they are allotted to do

    the task. They must then determine how much

    resources are needed to meet the deadline.

  • 8/3/2019 Project Planning Latest

    15/27

    15

    Estimating Activity Durations

    For a given amount of resources, how can you

    estimate a task duration?

    use the experts best guess (person doing task)

    use past data, if task has been done before

    use engineering standards or work standards

    dissect task into different elements and estimate

    time needed for each elementThe task time estimate should reflect the most

    likelytime needed to do the task.

  • 8/3/2019 Project Planning Latest

    16/27

    16

    Identifying Necessary Resources

    To complete a task within a given amount of time,

    what resources will be required?

    How many and what types of employees

    What facilities

    What equipment

    What materials and supplies

    What services

    What information and technologies

  • 8/3/2019 Project Planning Latest

    17/27

    17

    Top-Down vs. Bottom-Up Budgets

    Top-DownBudgeting: Senior management

    decides how much they think the project should

    cost, and that becomes the total project budget.

    The budget is then divided among the activities.

    Bottom-Up Budgeting: Cost estimates for

    each task are solicited from those responsible

    for the tasks. These estimates are rolled up for

    all activities to get the total project budget.

  • 8/3/2019 Project Planning Latest

    18/27

    18

    Estimating Activity Costs

    Estimates for both time and cost of activitiesshould be done with same approach, either top-down or bottom-up (or somewhere in between)

    Two initial budget estimates may be developedfor some projects, a top-down and a bottom-up.Which will most likely be higher? Why?

    The project manager must then negotiate with

    senior management to finalize the budget Tradeoffs may be necessary between the cost,

    due date, and the extent and quality of outputs

  • 8/3/2019 Project Planning Latest

    19/27

    19

    Baseline Plan

    The finalized budget, time estimates, and

    resulting project schedule are the basis for the

    baseline plan.

    The baseline plan lays out the target levels ofprogress and performance at the outset of the

    project execution phase.

    It is the basis for assessing project performance

    throughout the project

    Project trackingutilizes the baseline plan to

    provide the project manager with a control tool

  • 8/3/2019 Project Planning Latest

    20/27

    20

    Project Action Plan

    For each activity, action plan should at least show

    Activity name

    Time duration estimate

    Start date

    Immediate predecessor activity

    Resources needed

    Optionally, it might also show finish date, WBS

    index, cost, slack time, latest finish date, etc.

  • 8/3/2019 Project Planning Latest

    21/27

    21

    Action Plan

    ID Task Name Duration Start Finish Predec. Resourc

    1 Proj. approval 0 days

    2 Script writing 14 days 1

    3 Sched. shoots 17

    days 14 Script approval 8 days 2

    5 Revise script 5 days 4

    6 Shooting 10 days 3,5

    7 Editing 7 days 6

    8 Final approval 2 days 7

    9 Deliver to client 0 days 8

    C=client, E=editor, ER=editing room, P=producer, S=secretary, SW=scriptwriter

  • 8/3/2019 Project Planning Latest

    22/27

    22

    Project Charter(or Project Master Plan)

    Agreed-upon, legally binding project plan (the final plan)

    1. Overview

    2. Objectives

    3. General approach4. Contractual aspects

    5. Schedules

    6. Resources and budgets

    7. Personnel

    8. Evaluation methods

    9. Potential problems

  • 8/3/2019 Project Planning Latest

    23/27

    2

    3

    Project Charter

    1. Overview

    Intended for senior management

    Brief description of project & deliverables

    List of major milestones Likely profitability & competitive impacts

    2. Objectives

    Purpose of project

    More detailed description of deliverables

    Could be in the form of a project mission statement

  • 8/3/2019 Project Planning Latest

    24/27

    2

    4

    Project Charter

    3. General Approach

    Technical and managerial approaches

    Relationship with other projects

    4. Contractual Aspects

    Description of all agreements (client, others)

    Reporting requirements, technical specs, delivery

    dates, penalties, process for changes

  • 8/3/2019 Project Planning Latest

    25/27

    25

    Project Charter

    5. Schedules

    Outline of all schedules and milestones

    Project action plan, WBS

    6. Resource Requirements

    All capital and operating expenses

    Cost monitoring and control procedures

  • 8/3/2019 Project Planning Latest

    26/27

    26

    Project Charter

    7. Personnel

    What types of personnel are needed and when

    Skill requirements, necessary training, securityclearances, nondisclosure agreements

    8. Evaluation Methods

    Descriptions of all procedures and standards forevaluating projecthow information will be

    collected, stored, monitored

  • 8/3/2019 Project Planning Latest

    27/27

    27

    Project Charter

    9. Potential Problems

    List of potential risks to project progress

    Contingency planning may prevent or soften theimpacts of some problems

    Small or routine projects may not need all 9 of theseelements in the project charter, but larger projects

    should have them.