project overview - microsoft · project overview . 2 proposed project improvements 2 . 3 3 project...

18
1 LAX Guest Experience Partners Council June 3, 2019 Project Overview

Upload: others

Post on 24-Aug-2020

5 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Project Overview - Microsoft · Project Overview . 2 Proposed Project Improvements 2 . 3 3 Project Elements Terminal Improvements Terminal 9 (T9) - 12 gate facility (12 new gates)

1

LAX Guest Experience Partners Council

June 3, 2019

Project Overview

Page 2: Project Overview - Microsoft · Project Overview . 2 Proposed Project Improvements 2 . 3 3 Project Elements Terminal Improvements Terminal 9 (T9) - 12 gate facility (12 new gates)

2

Proposed Project Improvements

2

Page 3: Project Overview - Microsoft · Project Overview . 2 Proposed Project Improvements 2 . 3 3 Project Elements Terminal Improvements Terminal 9 (T9) - 12 gate facility (12 new gates)

3 3

Project Elements Terminal Improvements

Terminal 9 (T9) - 12 gate

facility (12 new gates)

Concourse 0 (C0) - 11 gate facility (9 new gates)

All full-service international capabilities

Better guest experience (extra

seating, check-in areas, security screening, charging stations, etc.)

Gates at T9 and C0 will replace

West Remote Gates

Landside Improvements Will serve Terminal 9

Improve CTA access & reduce

congestion on nearby public roads

New APM station at Terminal 9 & pedestrian connector to Terminal 8

Airfield Improvements

Relocate runway exits

Extension and improvement of taxiways

Enhances safety, efficiency and helps reduce delays

Page 4: Project Overview - Microsoft · Project Overview . 2 Proposed Project Improvements 2 . 3 3 Project Elements Terminal Improvements Terminal 9 (T9) - 12 gate facility (12 new gates)

4 4

Airfield Improvements

Page 5: Project Overview - Microsoft · Project Overview . 2 Proposed Project Improvements 2 . 3 3 Project Elements Terminal Improvements Terminal 9 (T9) - 12 gate facility (12 new gates)

5

Reconfiguration of taxiways/runways to

meet current FAA design standards Improved runway exit configurations

that enhance pilot visibility Decommissioning of taxiways that cross

the runway “high-energy zone” Westerly extension of Taxiway D at ADG

VI standards for operational efficiency and to meet FAA standards Improvements to Taxiways C & D for new

Terminals Relocation of Vehicle Service Roads

Taxiway Improvements – West End

Exit Taxiway Improvements

Airfield Improvements

Page 6: Project Overview - Microsoft · Project Overview . 2 Proposed Project Improvements 2 . 3 3 Project Elements Terminal Improvements Terminal 9 (T9) - 12 gate facility (12 new gates)

6 6

Terminal Improvements

Page 7: Project Overview - Microsoft · Project Overview . 2 Proposed Project Improvements 2 . 3 3 Project Elements Terminal Improvements Terminal 9 (T9) - 12 gate facility (12 new gates)

7

11 Gates (9 new) for narrowbody planes

Accommodates up to 5 widebody planes

2 Remain-Overnight Aircraft parking

positions Up to 1.2 million sf* (750,000 sf base) International (FIS) capability

4 levels (Ticketing, Concourse, Apron &

Arrivals) Pedestrian corridor to new APM station

No landside access –Passengers

processed through Terminal 1

* With option for an Offices Levels and 20% design contingency

Concourse 0 Conceptual Site Plan

Page 8: Project Overview - Microsoft · Project Overview . 2 Proposed Project Improvements 2 . 3 3 Project Elements Terminal Improvements Terminal 9 (T9) - 12 gate facility (12 new gates)

8

Proposed C0 Conceptual View

Proposed T0 Conceptual View

Page 9: Project Overview - Microsoft · Project Overview . 2 Proposed Project Improvements 2 . 3 3 Project Elements Terminal Improvements Terminal 9 (T9) - 12 gate facility (12 new gates)

9

12 New Gates for widebody planes

Up to 1.5 million sf* (1.2 million sf base)

International (FIS) capability

4 levels (Ticketing, Concourse, Apron & Arrivals)

Taxiway C improvement and easterly extension – ADG VI FAA design standards with 4-lane VSR

Pedestrian corridor to new APM station

Pedestrian corridor to Central Terminal Area (CTA) over Sepulveda

Landside access to/from roadway system

* With pedestrian corridors and 20% design contingency

Terminal 9 Conceptual Site Plan

Page 10: Project Overview - Microsoft · Project Overview . 2 Proposed Project Improvements 2 . 3 3 Project Elements Terminal Improvements Terminal 9 (T9) - 12 gate facility (12 new gates)

10

Proposed T9 Conceptual View

Page 11: Project Overview - Microsoft · Project Overview . 2 Proposed Project Improvements 2 . 3 3 Project Elements Terminal Improvements Terminal 9 (T9) - 12 gate facility (12 new gates)

11 11

Landside Improvements

Page 12: Project Overview - Microsoft · Project Overview . 2 Proposed Project Improvements 2 . 3 3 Project Elements Terminal Improvements Terminal 9 (T9) - 12 gate facility (12 new gates)

12

Landside Improvements

Page 13: Project Overview - Microsoft · Project Overview . 2 Proposed Project Improvements 2 . 3 3 Project Elements Terminal Improvements Terminal 9 (T9) - 12 gate facility (12 new gates)

13

Looking South across roads T9 & C0

Page 14: Project Overview - Microsoft · Project Overview . 2 Proposed Project Improvements 2 . 3 3 Project Elements Terminal Improvements Terminal 9 (T9) - 12 gate facility (12 new gates)

14

Looking East Exiting the CTA

Page 15: Project Overview - Microsoft · Project Overview . 2 Proposed Project Improvements 2 . 3 3 Project Elements Terminal Improvements Terminal 9 (T9) - 12 gate facility (12 new gates)

15 15

Project Benefits

Page 16: Project Overview - Microsoft · Project Overview . 2 Proposed Project Improvements 2 . 3 3 Project Elements Terminal Improvements Terminal 9 (T9) - 12 gate facility (12 new gates)

16

Benefits – Overall Project

Improves Passenger Experience

Improves Community Experience

Enhances Safety & Carrier

Experience

Increases Business

Opportunities

Reduced wait times on tarmac Seamless transition between

international & domestic flights Reduces on-ground travel by

busing from remote gates Contact gates provide better

passenger experience than busing from remote gates

More seating, concessions & retail

Reduced traffic congestion on neighborhood streets

Promotes sustainable practices - minimum LEED Silver certification

Less aircraft idling reduces air pollutant emissions

Connection to the APM & regional mass transit

Increases safety & efficiency

Reduced tarmac wait times Removes remote gates –

less busing Improves taxiways Enhances aircraft movement

New Concessionaires (restaurants & shops)

SBE & job opportunities during construction

Local jobs & local business opportunities

Page 17: Project Overview - Microsoft · Project Overview . 2 Proposed Project Improvements 2 . 3 3 Project Elements Terminal Improvements Terminal 9 (T9) - 12 gate facility (12 new gates)

17 17

Next Steps & Proposed Schedule

Page 18: Project Overview - Microsoft · Project Overview . 2 Proposed Project Improvements 2 . 3 3 Project Elements Terminal Improvements Terminal 9 (T9) - 12 gate facility (12 new gates)

18

CEQA Process

Q1 Q2 Q1 - Q4 Q1 Q3/Q4 Q4

2019 2019 2019 2019 2020 2020 2020