progress to date progress remains on track. effort and % complete within expectation
DESCRIPTION
Project Progress Summary - Week 18. Progress to date Progress remains on track. Effort and % complete within expectation. Milestones 41 completed to date against planned target of 45. Some milestones are running late awaiting sign off from user management. Deliverables - PowerPoint PPT PresentationTRANSCRIPT
Progress to dateProgress remains on track. Effort and % complete within expectation.
DeliverablesSigned off deliverables running behind schedule due to lack of availability of key user management. Recommend review and encouragement by sponsors.
Projected delivery timelineProjected delivery date remains on target.
IssuesNo adequate training facility is available internally for end-user training. Recommend review of priorities with internal training and/or evaluation of external facilities
Change requestsNo change request requiring Steering Committee review this period. Two minor changes approved.
Risk assessmentNo change in risk profile or risk avoidance. Risk analysis remains within expectations.
Quality ReviewReviews conducted as scheduled. No issues requiring Steering Committee attention.
Milestones41 completed to date against planned target of 45. Some milestones are running late awaiting sign off from user management.
ResourcingAvailability of resources from the business units remains an issue. Hours contributed remains significantly below planned targets. Recommend attention from sponsors.
Projected benefitProjected benefit remains on target.
Project Progress Summary - Week 18