professional studies report

Upload: prince-emmanuel-yemoh

Post on 05-Apr-2018

221 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/2/2019 Professional Studies Report

    1/35

    ARCHIPROFESSIONA

    This section describes how the design project would be delivered from

    inception through to completion, reecting on the roles undertaken by

    consultants, contractors and suppliers.

    SECTION 1

    SECTION 2

    SECTION 3

    SECTION 4

    APPENDIX

    INTRODUCTION

    ARCHITECTURAL MANAGEMENT

    BUILDING ECONOMICS

    LEGAL ISSUES

    About The ADA......

    Project Team /Roles & Responsibilities /Relationships......

    Construction&Use Risks......

    Project Planning /Stages of Work......

    Pre /Post Contractual Considerations......

    CDM Regulations /Health&Safety Issues......

    Procurement Strategies......

    Project Brieng /Cost Planning......

    Project Drivers&Objectives......

    Planning Legislation......

    Property Law......

    Adjoining Owners&Bouandaries......

    The Planning Process......

    Planning Appeals&Enforcement......

    Conservation Areas&Listed Buildings......

    Architects Legal Duties&Responsibilities......

    Project description&Programme......

    Project Setting&Client......

    contents BOO

  • 8/2/2019 Professional Studies Report

    2/35

  • 8/2/2019 Professional Studies Report

    3/35

    THE CLIEN

    THE CLIENT

    PARTNERSHIP

    THEIR VISION HOW IT WILL BE ACHIEVED

    A CULTURAL CENTER FOR THE

    COMMUNITY MADE BY THE

    COMMUNITY

    The Tower Hamlets Partnership is astrategic partnership that operatesin the borough of Tower Hamlets. Itwas established in November 2001by the police, the Council and localhealth, re services (the main publicsector organisations), local residentrepresentatives, businesses and vol-untary & faith groups. They workedtogether to ensure that the Partner-ship functioned as a local body thatprovided and improved services forthe borough local residents, visitorsand workers.

    The Partnership are responsible for the developmentand delivery of the Community Plan, which sets out andoutlines a series of strategic targets and priorities formaking Tower Hamlets a better borough for its resident,workers and visitors.

    The Core Strategy, is the primary document createdto support the ambitious long-term aspirations set outin the Community Plan for the development and re-

    generation in the area. The document strategizes andforcasts the boroughs spatial strategy for the next dec-ade (2025). Specifying on how, when and where futuredevelopments should occur and be delivered across theborough.

    The Cultural Center will be amongst the rst of theseredevelopment schemes taking place over the next dec-ade to reboost and re enrgise the borough.

    In September 2011 The Towr Hamlets Partnership ad-vertised a regional competition under the banner A

    cultural Center for the community by the communityIt was a competition open to all architects and design-ers whom could design and realise the vision of ThePartnerships Cultural Center. The Partnership wereadiment not to follow the conventional route of goingto a major Architectural practice. They wanted to givethis monumental opportunity to create the new iconof the borough to innovative presently unkown prac-tices.Advent Design Associates (ADA) were just that.

    ADA one the competition having been shortlisted from200 entries, and were immediately appointed by ThePartnership(The Client) as Design Team leader.

    The Tower Hamlets Partnership wish to create a new iconicMixed-Use Cultural center in the heart of the East Eand fol-lowing the legacy left behind after the London 2012 Olympicand Paralympic games. The mix use Cultural Center willbe the one of the great destinations and places to go in therichly diverse borough of Tower Hamlets . It must attractvisitors locally, regionally, nationally and globally. The centerwill reect and embody the ethos of the Olympic and Para-lympic games. The new center will comprise of a Cinema,

    Arts Pavilion, Crafts Workshop, Extreme Sports space anda place to eat and unwind. If proven a success the Centerwill be used as an exemplary template model for councilsnationwide to follow in their respective boroughs. Spa

    [Fig01]

    [Fig02]

    [Fig03]

  • 8/2/2019 Professional Studies Report

    4/35

    The LONDON CULTURAL IMPROVEMENT GROUP (LCIG) came into existence in

    2007, through the joint vision and belief of:

    THE LONDON CULTURAL IMPROVEMENT PROGRAMME

    is a cost effective operating model, well placed to support

    Local Authorities to respond to the rapidly changing politi-

    cal and scal environment and inevitable transformation of

    cultural services that resulted from the unprecedented pres-

    sure on public nance. The small core team had limited

    overheads and by fundraising for relatively small sums of

    project funding, effectively engaging local authorities and

    supporting networks of delivery partners, the capacity for

    delivering sustainable improvement and change was cre-

    ated from within the sector

    The LCIP has been funded by Capital Ambition and a con-

    sortium of partners in three phases. Phase one was fundedin January 2008, following a report to the Capital Ambition

    Programme Board on 26 November 2007 and subsequent

    support expressed for the programme by over half of Lon-

    dons Chief Executives. The total value of this phase was

    over 400,000, with 200,000 from Capital Ambition and the

    balance of the funding provided by a range of partners, in-

    cluding MLA, Arts Council, and Sport England and from Lo-

    cal Authorities. The programme combined a variety of work

    strands, designed to raise performance in individual Local

    Authorities, tackle the weakest areas of performance and

    raise standards in the cultural sector.

    LCIP has led London to outperform other regions and is

    now considered an example of good practice nationally,

    with many of its programmes and models being replicated

    by other regions and the LGA Group. Under CPA, Londonscultural services were the poorest performing service block

    in London and the worst of any other English Region. The

    LCIP effectively supported Local Authorities to improve their

    culture block scores and were the most improved region

    under CPA. Independent evaluation of Culture in the CAA

    showed that Londons Cultural Services performed con-

    siderably better than other regions and LCIP was cited as

    making a signicant contribution. Londons cultural services

    contributed to more green ags than all other regions and

    LCIP was cited as a contributing factor to Londons success.

    LCIP has attracted co

    able partnership fund

    cash and in kind, outper

    its phase one funding ta

    over 100%. Almost 100

    inward investment from

    sance funding has bee

    vided directly to London

    Authorities to deliver

    improvements in local a

    museums. The Cultural

    cies commitment to s

    ing London Boroughs

    LCIP is demonstrated byprioritisation of the prog

    following its reorganisati

    additional investment fr

    agencies in the program

    Strong leaders

    align a range of partners

    a strategic approach to

    improvement in local

    ity cultural services lea

    additional capacity and

    ment in the programme.

    Relatively sma

    incentives to local aut

    ensured high levels of e

    ment with the programm

    with partner authorities;levels of commitment; a

    projects were complet

    time and did not drift.

    The project tea

    credibility with local au

    because members of th

    team had extensive

    ence and knowledge of w

    within local authorities an

    able to build up trust.

    The organisations collaborated together to form the LONDON CULTURAL

    IMPROVEMENT PROGRAMME (LCIP), a strategic body that would strive to

    improve cultural services in London.

    The City of Londons 32 Boroughs

    Arts Coucil England

    MLA (Museums Libraries Archive) Council English Heritage

    Sports England

    London councils

    Capital Ambition

    R E G IO N A L

    CULTURALAGENCIES

    CORETEAM

    CLIENT FUNDERS

  • 8/2/2019 Professional Studies Report

    5/35

    LCIPTOWER

    HAMLETS

    PARTNERSHIP

    MAJOR

    GLOBAL

    SPONSOR

    COMMERCIAL

    SPONSORS

    OSBORN

    STREET

    ABANDONED

    WAREHOUSE

    SITE

    FIRS

    SPA

    STRA

    PI

    PRO

    FUNDING

    SEARCH FOR A SITE

    THAT IS NEED OF

    REDEVELOPMENT IN

    AND RE-USE IN THE

    BOROUGH

    FUNDING RAISED

    FOR THE SPATIAL THE

    STRATEGY PROJECT

    TO DESIGN AND

    DEVELOP AN ICONIC

    CULTURAL CENTER

    IN THE BOROUGH OF

    TOWERHAMLETS IN

    TIME FOR THE 2012

    OLYMPIC & PARALYM-

    PIC GAME LEGACY .

    IMPLEMENTATION OF

    THE SPATIAL STRAT-

    EGY

    INTIATIVE>+

    &

    FUN

  • 8/2/2019 Professional Studies Report

    6/35

  • 8/2/2019 Professional Studies Report

    7/35

  • 8/2/2019 Professional Studies Report

    8/35

    OUR PEOPLE

    The ADA run by three young gifted co-di-rectors (founders) whom have considerably

    extensive experience between each other.

    Before starting up ADA they had all worked

    within respective sectors within Building De-

    sign Partnership(BDP), a leading and award-

    winning interdisciplinary practice of archi-

    tects, designers, engineers and urbanists.

    CO-DIRECTOR CO-DIRECTOR

    Prince.E.YemohBArch

    BA(Hons) Architecture

    Katie.J.Parkes(GDip) Landscape Design

    BA(Hons) Architecture

    3Specialisation / Specialisation /

    Experience/ Experience/

    Architect Landscape&Urban D

    I worked for BDP in Lon-don for two years, in theretail and regenerationstudio,where I played a keyrole in design for a series oflarge scale developmentsin the UK, Poland, Indiaand China.

    Ive been in BDP Llandscape and ustudio for 4 yearI was an extremelymember within thcomprising of urbaners, urban demasterplanners anscape architects.Ivalot from these disc

  • 8/2/2019 Professional Studies Report

    9/35

    OURVALUES

    1. BE HONEST AND ACT WITH INTEGRITY

    2. BE COMPETENT

    3. PROMOTE YOUR SERVICES HONESTLY AND RESPO

    4. MANAGE YOUR BUSINESS COMPETENTLY

    5. CONSIDER THE WIDER IMPACT OF YOUR WORK

    6. CARRY OUT YOUR WORK FAITHFULLY AND CONSC

    7. BE TRUSTWORTHY AND LOOK AFTER YOUR CLIEN

    8. HAVE APPROPRIATE INSURANCE ARRANGEMENTS

    9. MAINTAIN THE REPUTATION OF ARCHITECTS

    10. DEAL WITH DISPUTES OR COMPLAINTS APPROPR

    11. CO-OPERATE WITH REGULATORY REQUIREMENTS

    12. HAVE RESPECT FOR OTHERS.

    12(Taken from the The ArchitectsCode of Conduct)

  • 8/2/2019 Professional Studies Report

    10/35

  • 8/2/2019 Professional Studies Report

    11/35

    PROFESSIONALISM, ARCH

    ADA recomm

    Standard C

    large exper

    their own beproject. It is

    the project s

    Progressing

    appointmen

    tice (standa

    4.1). The ab

    change the

    position with

    To prevent

    continue to

    tential dispuhave agreed

    has been ag

  • 8/2/2019 Professional Studies Report

    12/35

    widerproje

    ROLES & FUN

    The Tower Hamlets Partnership is astrategic partnership that operates inthe borough of Tower Hamlets to provideimproved services for the borough localresidents, visitors and workers.

    The partnership are in charge of select-ing the potential site on which the newiconic Culture & Arts Centre is to bedesigned and built upon. If they do not

    posses the capability to do so they willoften instruct a consultant to carry outthe necessary work.

    The Partnership will select a representa -tive during the building design works,whom will ensure that the project runssmoothly with regards to cost and sched-uling. The Towerhamlets Partnershiprepresentative must be up to date withall matters in relation to the design pro -

    ject & provide regular feedback to ThePartnership.

    Their expertise in their respective eldsallows them to provide a substantial con -tribution to all aspects of the design &construction works.

    As Development Manager they are re -sponsible for co-ordinating and manag-ing all aspects in relation to the building

    procurement process.

    As the Lead Consultant/ Design TeamLeader Advent Design Associates areresponsible for the co-ordination of allworks by the Design Team (StructuralEngineers, Interior Designers, Landscap

    Architects, Consultants etc) ensuringthat the clients requirements are metwith regards to Time Schedule andBudgets.

    ARUP engineers play a fundamental partin the Building process. The ability to de-sign Structure for Buildings makes thema key part to the Design Team.

    Team members have been selected on the

    basis of their merit and effeciency in their

    respective elds. The Client is satised

    with the fee and competence of all mem-

    bers of the Project Team.

    TOWER HAMLETS PARTNERSHIP CAPITA SYMONDS (transport)

    DRIVERS JONAS DELOITTE (planning)

    STANHOPE PLC ADVENT DESIGN ASSOCIATES ARUP

    DEVELOPMENT

    MANAGER

    ARCHITECT STRUCTURAL

    ENGINEER

    OTHER

    CONSULTANTS

    CLIENT

    Often a Specialist Trader(Roong,Cladding etc) they are able tocarry out design works on specic andspecialised parts of the constructionworks on behalf of the Contractor.

    Responsible for the supply of Materialsand Equipment but not its erection/con -struction on site. T hey can offer adviceservices to the Design Team.

    TBC??? TBC???

    SUB-

    CONTRACTOR

    SUPPLIER

  • 8/2/2019 Professional Studies Report

    13/35

    Succe

    clearly

    (Archit

    Disput

    within tion of

    work b

    team m

    To avo

    lowing

    Role

    Decis

    Chan

    ARC

    [Fig04]

  • 8/2/2019 Professional Studies Report

    14/35

    E

    A

    QS

    PO

    SC

    BC

    T1

    C

    CQ

    A+

    CO

    PS

    SA

    SF

    FTSS

    WORK STAGES. PEOPLE INVOLVED.

    A-B(15% of fees due)

    Appraisal

    E

    E / A

    C-D,E(further 30% of fees due)

    Design

    Final Proposals

    E / A / QS / PO

    E / A / QS / SC

    E / A / QS / SC / PO / BCO

    F-H(further 30% of fees due)

    Production

    E / A / QS / SC / T1+T

    2+T

    3+T

    4

    J-L(remaining 25% of fees due)

    Construction to PracticalCompletion

    Job Management

    Ofce Managemet

    E / A / QS / SC / C / CQS

    A+T COW PS / SA / SF / FT / SSC

    RIBA TRADITIONAL, PLAN OF WORK & T

  • 8/2/2019 Professional Studies Report

    15/35

    ARCHITECTS

    APPOINTMENT

    DEVELOPER

    APPOINTMENT

    PotentialSite:ensurepurchaseisco

    mpletedontime

    AppointSpecialistadvisors

    AppointFinancialadvisors

    Establishaninternaldecisionmakingsystemisinplacetoavoid

    designdelays.

    NominateClientrepresentattiveto

    keepwiderclientorganisa-

    tioninformed.

    ConrmappointmentofArchitect.

    Conrmbrief

    AdviceonConsultants

    DraProgramme

    AppointSurveyor

    Arrangeanin-housesiteinspection

    Ideas&Vision PotentialSite

    SetupFundingframeworktoensurepaymentsaremade

    DetectExistingSiteproperties

    Identifynames&Addresses

    EstablishBoundaries&Access

    Siteorientation&characteristics

    PhotographSite&makeSketchnotes

    Takebasicdimensionsofthesiteto

    enablepreliminaryanalysis

    &designworks

    InstructSurveyortopreparemoreaccurateanddetailedsurvey

    drawingsoftheSite.

    Establishexistingstructures(Plans,e

    levations,sec-

    tionsandselecteddetails)

    OwnershipofFence,andPartyAgreements.

    Plotaccuratelevels,boundariesandadjoining

    buildings.

    Services,Soiltest&Trialholes

    EstablishImprovementlines

    Scheduleofdefects.

    Comprehensiveinternalandextern

    alphotographs

    ofthesiteanditsimmediatecontex

    t.

    siteinspection/analysis

    survey

    THE CLIENT

    PROJECT PLA

  • 8/2/2019 Professional Studies Report

    16/35

    CONTRACTOR

    APPOINTMENT

    DESIGN

    PROPOSALS

    CONSTRUCTION

    DRAWINGS

    Createbasicdrawings,modelsand

    sketches

    Collectsamplesandillustrations

    Liasewithconsultantstodiscussdesign.

    Preparereport.

    ereportshouldstatetheClients

    originalbrief.

    esiteconditions&Analysisrelatedtothebrief.

    Attitude&approachtodesignprob

    lems.

    Consulatantsrecommendations.

    assessmentofcostandfees.

    Submitreporttoclientforfurtherdiscussion.

    SetupofanappropriateDrawingP

    rogramme.

    LiasewithConsultantstosetupan

    eecientschedulereference

    system.

    DevelopConstructionDrawings.

    contractorinstructsArchitecttodevelopthebuilding

    designdrawingfurtherintoacoherentdetailedcon-

    struction/productiondrawings

    ProduceasetofKeydrawings-GA

    Plans/Sections&Elevations

    P

    d

    h

    f C

    i

    D

    i l

    ConsultantsmeetingswithClient

    Discussdesignpolicy,structure,materials,servicing

    Cost&Contractoptions

    Designdevelopment.

    designreport

    approvalsfromc

    lient

    handovertocontractor

    architectisnovated&

    now

    worksforthecontractor

    PROJECT PLANNING, STAG

  • 8/2/2019 Professional Studies Report

    17/35

    CONSIDERATIONS

    DELAY OF F

    It is importan

    involved in th

    appointment

    TIME_

    It is importan

    sign and ove

    tender inform

    for Stage 2 T

    CLIENT DEC

    Experienced

    experience w

    detriment of t

    can have dra

    PROCUREM

    This needs a

    responsibilitie

    CONTRACT_

    If the procure

    become inco

    the contract v

    [Fig07]

  • 8/2/2019 Professional Studies Report

    18/35

    CONSTRUCTION D

    INTER-RELATIONSHIPS DESIGNING FOR HEALTH & S

    [Fig05] [Fig06]

  • 8/2/2019 Professional Studies Report

    19/35

    CLIENT DUTIES DESIGNER DUTIES

    [Fig07]

  • 8/2/2019 Professional Studies Report

    20/35

  • 8/2/2019 Professional Studies Report

    21/35

    COMPARIS

    ONOFPROCUREM

    ENTMETHOD

    [Fig08]

  • 8/2/2019 Professional Studies Report

    22/35

    Which contract Choosing the appropriate building contract. 4th edition[Fig09]

    For further deatils on procurement

    comparisons please refer to the Pro-

    curement section in Appendix 03)

  • 8/2/2019 Professional Studies Report

    23/35

    ORIGINAL PROCUREMENT& EV

  • 8/2/2019 Professional Studies Report

    24/35

    FUNDING

    Public Funders co

    Ofcial Partner co

    Ofcial Supporter

    TOTAL

    CLIENT D Tower Hamlets Partnership

    ARCHITECT Advent Design Associates

    COST 4,000,000

    PROCUREMENT Design & Build

    START/COMPLETION Jan 2012/Sept 2012

    This Report recommends that th

    Old Truman Brewery. The Capi

    ing a Design & Build approach.

    PROJECT

  • 8/2/2019 Professional Studies Report

    25/35

    LAN

  • 8/2/2019 Professional Studies Report

    26/35

    LAN

    OW

    OS

    BORNSTREET

    WHITE

    CHAPEL

    ROAD

    Conservatio

    Conservatio

    Conservatio

    Statutory Li

    Building

    Statutory Li

    Building

    Listed Build

    Land Owne

    Land Owne

    Land Owne

    THE SITE

    ELECTRIC

    SUBSTATIO

    WHITECHA

    GALLERY

  • 8/2/2019 Professional Studies Report

    27/35

    PLANNING APPLICATION HISTORY OF TH

    2001 20032001 2

    ADDRESS /

    APPLICATION NUMBER /

    PROPOSAL /

    DESCISION DATE /

    DESCISION /

    Demolition of main buildings and develop-

    ment of a six storey building facing Osborn

    Street providing retail, showroom, light in-

    dustrial and ofce with ats above. 02

    Use of ground oor and part rst oor as

    entertainment venue including function /

    performance hall, restaurant and four bars

    with ancillary ofces. 04

    Demolition of 15-23 Osborn Street and

    partial demolition of no. 25 Osborn Street

    to enable redevelopment. 03

    Demolition o

    change of us

    WITHDRAWN - RETURNED TO APPLICANT WITHDRAWN - RETURNED TO APPLICANTWITHDRAWN - RETURNED TO APPLICANT WITHD

    15 To 25, Osborn Street, London, E1 15 To 25, Osborn Street, London, E115 To 25, Osborn Street, London, E1 15 To 25, Os

    25/09/2001 29/10/200325/09/2001

    PA/00 /00639 PA/02/ 01542PA/00 /00640

    APPEN

  • 8/2/2019 Professional Studies Report

    28/35

    APPEN

  • 8/2/2019 Professional Studies Report

    29/35

    NOTE:ALL PAGES IN THIS SECTION HAVE BEEN EXTR

    THE ARCHITECTS FEES 2005 & WHICH CONTRA

    THE APPROPRIATE BUILDING CONTRACT. 4TH ED

    COST P

    FEE RANGE

  • 8/2/2019 Professional Studies Report

    30/35

    FEE RANGE

    COMPARISONS

    There is, of course, variation in the fees reported in

    this survey. The averages reported in the tables and

    the lines of best t presented in the charts disguise

    variations between individual jobs. The charts, right,

    show the distribution of fees, analysing new build

    and refurbishment separately for jobs undertaken

    using the traditional contract types.On each fees chart below, the solid line shows the

    average fees - the line of best t. The grey lines

    show lower and upper quartiles. It is clear that there

    is a greater variation in fees from the average for

    refurbishment jobs than for new build jobs. Fees re-

    ported using the design & buil d contract show less

    variation than traditional contract jobs.

    ArchitectsFees2005

  • 8/2/2019 Professional Studies Report

    31/35

  • 8/2/2019 Professional Studies Report

    32/35

    DESIGN & BUILD PROCUREMENT

    CONTRACTUAL

    RELATIONSHIPS /

    With design and build, it is likely that in

    the absence of in-house professional staff,

    the client will wish to engage outside con -sultants to advise on the preparation of

    requirements and to evaluate and select

    tenders etc. Often one or more of these

    consultants will switch from being ap-

    pointed by the client to being appointed

    by the contractor at the time the contractor

    is engaged. The main contractual link is

    between the client and the contractor and

    if the clients agent or representative has

    only a limited role. The contractor might

    also have a contractual link with his own

    design consultants, and with sub-contrac-

    tors and suppliers. As the contractor is

    wholly

    Which contract Choosing the appropriate build-

    ing contract. 4th edition

  • 8/2/2019 Professional Studies Report

    33/35

    DESIGN & BUILD PROCUREMENTPLAN OF WORK STAGES

    The

    requ

    in-ho

    desi

    cons

    tion,

    sche

    Wh

    LONDON CULTURAL IMPROVEMENT PROGRAMME

  • 8/2/2019 Professional Studies Report

    34/35

    LONDON CULTURAL IMPROVEMENT PROGRAMME

    FUNDING

    CASH FUNDING SUMMARY

    In each nancial year that LCIP

    ran it attracted funding from Capi-tal Ambition and match funding

    from partner organisations. In

    total, the funding provided has

    been nearly evenly split between

    Capital Ambition and the cross-or-

    ganisational match-funding: Capi-

    tal Ambition has provided 57.82%

    of the monetary funding to deliver

    LCIP compared with 42.18% from

    partner organisations. The total

    value of monetary funding since

    LCIP inception is 1,598,200. The

    graph demonstrates the funding

    levels, by nancial year, broken

    down into contributing organisa-

    tions

    SUMMARY OF MATCH-FUNDING

  • 8/2/2019 Professional Studies Report

    35/35

    SUMMARY OF MATCH FUNDING

    STRANDS