pressure testing code requirements.pdf
TRANSCRIPT
7/28/2019 PRESSURE TESTING CODE REQUIREMENTS.pdf
http://slidepdf.com/reader/full/pressure-testing-code-requirementspdf 1/26N. Al-Khirdaji, AZTech Sr. Consultant
3.7 Pressure Testing – Code
Requirements and Best Practices• Hydrostatic testing
• Pneumatic testing
Pressure Testing• Pressure testing is used to determine the integrity of
pressure equipment and piping systems. It is based ondeterminin the abilit of a i in s stem to withstand ahydrostatic pressure that equals or exceeds the design pressure (test pressure depends on the type of test).
• The tests criteria are pressure history and leak detection.
• A test is conducted by isolating and pressurizing thevessel/piping, and then measuring the change in pressureover a specified time. At the same time, visual inspection
or ea s s con uc e .• The test pressure shall, unless otherwise specified, be in
accordance with applicable code (e.g., ASME BPVC,ASME B31.3, ASME B31.4, API 1110, etc.).
7/28/2019 PRESSURE TESTING CODE REQUIREMENTS.pdf
http://slidepdf.com/reader/full/pressure-testing-code-requirementspdf 2/26N. Al-Khirdaji, AZTech Sr. Consultant
Some Pressure Testing Requirements
• Accurate and precise temperature data are
essential to mathematicall reconcile tem erature
and pressure changes observed during testing of
buried pipelines and to certify absence of leakage.
• The API recommended practice applied by the
project specifications explicitly requires
temperature measurements to be made in
increments of 0.1°F (0.05°C) and that a
continuous-recording temperature measurementdevice be employed to provide a permanent record
of pipeline temperature versus time.
Some Pressure Testing Requirements
• During a typical pipeline hydrostatic test, pressuremeasurements are taken and recorded at 15 or 30-minute intervals using a dead weight test gaugecapable of precision of ± 0.5 psi, or better.
• Each set of measurements is reconciled and thecalculated net test volume is plotted on a timescale for each interval.
• Trends on the volume-time plot can indicate small
leaks after a short monitoring period.• After the elapse of the required test holding time,
typically specified as 8 to 24 hours, the presenceor absence of leaks is indicated with a high degreeof certainty.
7/28/2019 PRESSURE TESTING CODE REQUIREMENTS.pdf
http://slidepdf.com/reader/full/pressure-testing-code-requirementspdf 3/26N. Al-Khirdaji, AZTech Sr. Consultant
Pressure Testing of Buried Pipe
• Economic and construction considerations for pipeline projects typically require installation of pipe and back filling of the pipe trench before pressure testing.
• Since visual leak inspection of the buried pipe isnot possible during testing, it is necessary toreconcile observed changes in test pressure withchanges in temperature to verify the absence of
.
• A mathematical calculation is necessary to make
the reconciliation, and the temperature of the pipeand its contents are the most critical of severalelements to be considered.
Pressure Testing of Buried Pipe
• - -, , , pipeline 15,000 feet long, tested with water starting at 50°F, will lose about 9 pounds per square inch (psi) of pressure due to a 1°F cooling.
• The same pipeline tested at a starting temperatureof 70°F will lose about 23 psi for each 1°F of
.• Even more dramatically, this same pipeline, if leak
tested with diesel fuel or jet fuel, would lose about80 psi for each 1°F of cooling during a typical test
7/28/2019 PRESSURE TESTING CODE REQUIREMENTS.pdf
http://slidepdf.com/reader/full/pressure-testing-code-requirementspdf 4/26N. Al-Khirdaji, AZTech Sr. Consultant
Pressure Test Planning - 1
• To achieve an accurate and representative test,adequate planning is required.
• Some necessary information needs to be gathered prior to the test. The following information should be gathered days or weeks before the actual test: – presence of pressure relief devices,
– test medium information,
– delineation of individual pipeline test segments, and
– requ re es ns rumen accuracy.
• Just prior to test start-up, pre-test calculations
should be performed to detect the presence of entrained air.
Pressure Test Planning - 2
• The presence of pressure relief devices must
e e erm ne pr or o e es .
• Usually these devices have a set pressure at or
5 – 10 % above the maximum allowable
operating pressure.
• prior to conducting the test.
7/28/2019 PRESSURE TESTING CODE REQUIREMENTS.pdf
http://slidepdf.com/reader/full/pressure-testing-code-requirementspdf 5/26N. Al-Khirdaji, AZTech Sr. Consultant
Pressure Test Planning - 3
• The presence of a significant amount of
trappe a r w n e es e p pe ne can e
problematic to test accuracy.
• When testing a pipeline with water, trapped air
can be eliminated by filling the tested line at a
ra id enou h rate thereb creatin a
completely turbulent interface between the
incoming water and the displaced fluid.
Pressure Test Preparation
• Pressure, temperature and time recorders should be
.
recorders used to indicate and record test pressure
shall be dead weight tested for accuracy according to
a procedure, dependent of type of equipment.
• All piping should be adequately supported before the
.
should be blocked to prevent movement.
7/28/2019 PRESSURE TESTING CODE REQUIREMENTS.pdf
http://slidepdf.com/reader/full/pressure-testing-code-requirementspdf 6/26N. Al-Khirdaji, AZTech Sr. Consultant
Pressure Test Preparation
• If there is a deviation of more than 2% between gauge,
the equipment recalibrated.
• Piping joints and welds shall not be insulated or physically covered until satisfactory completion of testing in accordance with this specification, exceptfor painting of prefabricated welds.
• A p p ng s a e a equate y supporte e ore t e pressure test. Spring or other variable type supportsshall be blocked to prevent movement.
Pressure Test Preparation
• ,through body tested. First block valve for pressureinstruments shall be included in the test.
• Piping containing check valves shall have thesource of test pressure on the upstream side. If thisis not possible, the check valve disc shall be
.• Where the test pressure > the maximum allowable
test pressure for valves, the valves shall be blindedoff on the side to be tested, or removed andreplaced by dummy spools
7/28/2019 PRESSURE TESTING CODE REQUIREMENTS.pdf
http://slidepdf.com/reader/full/pressure-testing-code-requirementspdf 7/26N. Al-Khirdaji, AZTech Sr. Consultant
Pressure Test Preparation
• Turbines, pumps, compressors and vessels.
• A list shall be prepared for sensitive equipmentthat shall be removed, blocked off or isolatedduring testing, such as relief valves, inlineinstruments, turbines, pumps, compressors and
.
This list shall be a part of the test procedure
Pressure Test Preparation
• Piping joints and welds should not be insulated or
testing in accordance with this specification, exceptfor painting of prefabricated welds.
• Minimum of one gauge shall be positioned at thehighest point and one recorder to be positioned at thelowest point.
• ccuracy o pressure gauge s a e at east - atfull scale and 1-2% for the recorder. The test pressureshall be within 60% of the gauge range.
7/28/2019 PRESSURE TESTING CODE REQUIREMENTS.pdf
http://slidepdf.com/reader/full/pressure-testing-code-requirementspdf 8/26N. Al-Khirdaji, AZTech Sr. Consultant
Test Media
• For hydrostatic testing the test medium shall in,
suitable liquid may be used if:
– The piping or inline equipment would be adverselyaffected by water.
– If the liquid is flammable, its flash point shall be atleast 49°C and consideration shall be iven to the environment.
– The liquid is approved by the Owner
Test Media
• The chloride ion content of the water used for
100 ppm and the line shall be properly drained soonafter testing. The pH of the water shall be between6.5 and 7.5.
• For pneumatic testing, the test media shall be oil free,dry air or any inert gas. The extent of pneumatic
.and requirements generally apply.
7/28/2019 PRESSURE TESTING CODE REQUIREMENTS.pdf
http://slidepdf.com/reader/full/pressure-testing-code-requirementspdf 9/26N. Al-Khirdaji, AZTech Sr. Consultant
Duration of Test Pressure
•sufficient length of time to permit visualexamination to be made of all surfaces, welds andconnections, but not less than thirty minutes.
• A one hour test duration shall apply for pipingsystems with pressure rating class 600# and above.
• are s a e ta en to ensure t at over-pressur ngdue to static head does not take place.
• The piping systems shall not show any sign of plastic deformation or leakage.
After Completion of Test
• The tested systems shall be depressurized by opening
.
• After depressurization, all vents and low point drain
valves shall be opened and the system shall be
thoroughly drained where the test medium is water.
• Where required, blowing by dry air or Pressurized
be performed.
7/28/2019 PRESSURE TESTING CODE REQUIREMENTS.pdf
http://slidepdf.com/reader/full/pressure-testing-code-requirementspdf 10/26N. Al-Khirdaji, AZTech Sr. Consultant
Pneumatic Testing
• Pneumatic testing is normally used in cases where
tolerated or when water of suitable quality is notavailable.
• Typically, Owner approval is required before pneumatic testing is to be performed. Additionally, because of the potential energy of the compressed air
,safety precautions and procedures have to be
implemented.
Stored EnergyIn Pressurized Gas Vessel or Piping
• When a gas is compressed, energy is stored in it. If the
energy s re ease n an un avora e way, w cause
damage.
• Stored energies in excess of 100 kJ are considered
high hazard.
• Sometimes it is helpful to think of stored energy in
terms o grams o tr n troto uene .One gram of TNT contains 4.62 kJ of energy
0.01 lb TNT = 14,240 ft-lb of stored energy
7/28/2019 PRESSURE TESTING CODE REQUIREMENTS.pdf
http://slidepdf.com/reader/full/pressure-testing-code-requirementspdf 11/26N. Al-Khirdaji, AZTech Sr. Consultant
Stored Energy
In Pressurized Gas Vessel or Piping
-1
Vh = The volume of the vessel.
Ph = The absolute pressure of the vessel.
U =h h
γ - 1{ 1 – (P1/Ph)
γ }
Pl = The absolute pressure to which the vessel would drop if it burst,
generally one atmosphere (14.696 psi or 101,300 Pascal). A Pascal
is a Newton per square meter.
γ = The adiabatic exponent or ratio of specific heats, Cp/Cv. (= 1.67
for monatomic gases; 1.4 for diatomic gases; 1.3 polyatomic gases)
Example: Consequences of Leakage or Rupture of Pressure Vessel and Piping
= .
Vh = 1.0 m3 (35.3 ft3)
Ph = 10 atm (150 psi) gage or 11 atm absolute or 1.1 MPa
Pl = 1 atmosphere or 100 kPa or 14.7 psi
U ={(1*105 N/m2)(1.0 m3)/(1.4-1)}{1-[1*105 N/m2/ (1*105 N/m2)]1.4 -11.4 }
The stored energy is 1.4 MJ (N-m is a joule), which is equivalent
to 0.3 kg of TNT (1 kg TNT = 4.62 MJ)
U = 1.4* 106 N-m
7/28/2019 PRESSURE TESTING CODE REQUIREMENTS.pdf
http://slidepdf.com/reader/full/pressure-testing-code-requirementspdf 12/26N. Al-Khirdaji, AZTech Sr. Consultant
Potential EnergyStored Volumes of Ideal Gas at 20° C
PRESSURE, psig TNT EQUIV., lbs. per ft3
10 0.001
100 0.02
1000 1.42
10000 6.53
TNT equiv. = 5 x 105 Calories/lb
Preparation for Pneumatic Testing
. ,w/mechanical seals, heat exchangers, etc. thatare incapable of withstanding the test pressureshall be blanked off before pressure testing. In-line components such as filters and strainers mayremain.
. the Test Pressure, or that are otherwisesusceptible to damage, shall be removed or
blanked from the Pipeline being tested, or shall be replaced with a pipeline spool.
7/28/2019 PRESSURE TESTING CODE REQUIREMENTS.pdf
http://slidepdf.com/reader/full/pressure-testing-code-requirementspdf 13/26N. Al-Khirdaji, AZTech Sr. Consultant
Preparation for Pneumatic Testing3. Suitable warning signs, barricades or other safety
during testing in the event of sudden release of pressure. Pneumatic pressure testing should be performed during off-shift hours, where possible, toreduce the potential for personnel injury.
4. Visual Examination of the piping systems shall be
pressure tests.
Preparation for Pneumatic Testing5. All joints and welds must be uninsulated, before
.
6. If the air supply used is moist, no testing will be
permitted unless ambient temperatures are expected
to be above 32 F during the full duration of the test.
7. This pressure test method is restricted to 12" NPS
, by the owner.
7/28/2019 PRESSURE TESTING CODE REQUIREMENTS.pdf
http://slidepdf.com/reader/full/pressure-testing-code-requirementspdf 14/26N. Al-Khirdaji, AZTech Sr. Consultant
Preparation for Pneumatic Testing• , ,
provided by a compressor, which is free from dirt,oil, weld slag, construction debris, and other foreignmatter, shall be used for the pneumatic test.
• Test Apparatus: All gauges used for field testingshall have a suitable range and a dial scale not less
" .so that the test pressure of the system falls between
40% and 80% of the gauge scale range. Gauges shall be out of "new" quality and in first class workingcondition.
Preparation for Pneumatic Testing
• A pressure relief device shall be installed in
e es oop an s a e se o re eve a e
greater of 25 psig or 10% above the defined
Test Pressure
• Test Pressure: The Test Pressure shall be
e ual to 110% of either the desi n ressure of
the piping system, or its weakest component.
7/28/2019 PRESSURE TESTING CODE REQUIREMENTS.pdf
http://slidepdf.com/reader/full/pressure-testing-code-requirementspdf 15/26N. Al-Khirdaji, AZTech Sr. Consultant
Test Procedure
• Test Procedure: The pressure source shall be.
necessary for the operator to leave the pressuresource, he should first relieve the pressure in the testloop.
• A preliminary check shall be made by pressurizingthe test loop to not more than 25 psig. At each
,for one minute before processing to a higher pressure
Test Procedure
The following typical procedure shall be used:
. ose a va ves n e ne an or an o a anges.
2. Open the valve supplying the test fluid to the pipe system
slowly until the pressure gauge indicates 25 psig.
3. Close the valve supplying pressure.
4. Observe the pressure gauge. If the pressure holds steady
for one minute, proceed to Step 5.
5. Open the valve supplying pressure.
7/28/2019 PRESSURE TESTING CODE REQUIREMENTS.pdf
http://slidepdf.com/reader/full/pressure-testing-code-requirementspdf 16/26N. Al-Khirdaji, AZTech Sr. Consultant
Test Procedure
6. Increase the test pressure in the line by 25 psi.
7. Close the valve su l in ressure.
8. Repeat Steps 4, 5, 6 and 7 until the Test Pressure isachieved.
9. Hold the Test Pressure for a period of time sufficient to permit a thorough inspection of all joints for leakage, butnot less than 10 minutes. The pneumatic pressure testresults are acceptable when there is no evidence of ea age or seepage an no ecrease n pressure s own on
the test gauge during the test.
10. Relieve the pressure in the test loop.
Test Procedure
• Repair any leaks found in the test loop. After
repa rs, re es e es oop per eps ru
above at the Test Pressure.
• Retesting also requires a stepwise pressure
increased in 25 psig increments.
7/28/2019 PRESSURE TESTING CODE REQUIREMENTS.pdf
http://slidepdf.com/reader/full/pressure-testing-code-requirementspdf 17/26N. Al-Khirdaji, AZTech Sr. Consultant
Test Record
• Test Record: The test shall be witnessed by the
required by regulations).
• Records of the pressure test shall be maintained bythe per company policies as identified on the PressureTest Record Form.
• Records should include the test date, identification of t e p pe ne teste an t e type o pressure test usewith reference to the appropriate project andmaintenance files.
Pressure Tests – Pressure Vessels130 Hydrostatic test pressure for pressure vessels
110
100
Pneumatic test pressure for pressure vessels
Maximum Allowable working Pressure, MAWPMaximum relief device settingRetest pressure for all vessels and systems
e n t o f M A W P
80
Maximum operating pressure, MOP*
* Recommended range is 10 to 20% below the MAWP
P e r
≈
7/28/2019 PRESSURE TESTING CODE REQUIREMENTS.pdf
http://slidepdf.com/reader/full/pressure-testing-code-requirementspdf 18/26N. Al-Khirdaji, AZTech Sr. Consultant
Pressure Testing of Liquid
Petroleum Pipelines• A pressure test is performed to test for pipeline
s reng an ea age, an o sa s y s a u ory
regulations.
• A pressure test includes: site preparation,
temperature measurement and monitoring,
time of events i eline ackin and
pressurization, strength testing, leak testing,
and pipeline test documentation.
Hydrostatic Testing of InternalPressure Piping (ASME B31.4)
•existing liquid petroleum pipelines.
• It recommends minimum procedures to befollowed, suggest equipment to be used, and
points out factors to be considered duringhydrostatic testing of liquid petroleum pipelines.
• s suggests proce ures t at are ase onsound engineering judgments, but certaingovernmental requirements may differ from this
procedure set forth in this RP. Such requirementssupersede the RP.
7/28/2019 PRESSURE TESTING CODE REQUIREMENTS.pdf
http://slidepdf.com/reader/full/pressure-testing-code-requirementspdf 19/26N. Al-Khirdaji, AZTech Sr. Consultant
Hydrostatic Testing of Internal
Pressure Piping (ASME B31.4)• Portions of i in s stems to be o erated at a hoo
stress of more than 20% of the specified minimumyield strength of the pipe shall be subjected at any
point to a hydrostatic proof test equivalent to not lessthan 1.25 times the internal design pressure at that
point (see para. 401.2.2) for not less than 4 hours.
•hoop stress, based on nominal wall thickness, in
excess of 90% of the specified minimum yieldstrength of the pipe, special care shall be used to
prevent overstrain of the pipe:
Hydrostatic Testing of Internal
Pressure Piping (ASME B31.4)
–
pressured components are visually inspected during
the proof test to determine that there is no leakage
require no further test. This can include lengths of
pipe which are pre-tested for use as replacement
sections.
– On those portions of piping systems not visuallyinspected while under test, the proof test shall be
followed by a reduced pressure leak test equivalent
to not less than 1.1 times the internal design
pressure for not less than 4 hours.
7/28/2019 PRESSURE TESTING CODE REQUIREMENTS.pdf
http://slidepdf.com/reader/full/pressure-testing-code-requirementspdf 20/26N. Al-Khirdaji, AZTech Sr. Consultant
Hydrostatic Testing of Internal
Pressure Piping (ASME B31.4)• ,
except liquid petroleum that does not vaporizerapidly may be used provided :
– The pipeline section under test is not offshore and isoutside of cities and other populated areas, and each building within 300 feet of the test section isunoccupied while the test pressure is equal to or greater than a pressure which produced a hoop stress of 50% of the specific minimum yield strength of the pipe.
– The test section is kept under surveillance by regular patrols during test; and
– Communication is maintained along the test section.
Hydrostatic Testing of Internal
Pressure Piping (ASME B31.4)• If the testing medium in the system will be subject to
,made for relief of excess pressure. Effects of temperature change shall be taken into account wheninterpretations are made of recorded test pressures.
• After completion of the hydrostatic test, it isimportant in cold weather that the lines, valves, and
damage due to freezing.
7/28/2019 PRESSURE TESTING CODE REQUIREMENTS.pdf
http://slidepdf.com/reader/full/pressure-testing-code-requirementspdf 21/26N. Al-Khirdaji, AZTech Sr. Consultant
Hydrostatic Testing - 1
• Hydrostatic testing is used to conduct strength tests on:
– new pipes while in the manufacturing process, as well as
– at the completion of pipeline installation in the field prior to being placed in service.
• Hydrostatic testing is also used, at times, for integrityassurance after a pipeline is in operation.
•assessment method when the pipeline is not capable of
being internally inspected or if defects are suspectedthat may not be detectable by internal inspection smart
pigs.
Hydrostatic Testing - 2
•capacity of a pipeline and may identify defects thatcould affect integrity during operation.
• Testing is done to a pressure that is greater than thenormal operating pressure of the pipeline. This
provides a margin of safety.
• e test stresses t e p pe ne to a pre eterm ne percentage of its specified minimum yield strength(SMYS). Typically pressures range from 93% to100% of SMYS, and the test is generally held for eight hours.
7/28/2019 PRESSURE TESTING CODE REQUIREMENTS.pdf
http://slidepdf.com/reader/full/pressure-testing-code-requirementspdf 22/26N. Al-Khirdaji, AZTech Sr. Consultant
Hydrostatic Testing - 3
• If stress corrosion cracking (SCC) is suspected, the
SMYS or higher for 30 minutes to an hour.
• Axial flaws such as stress corrosion cracking,
longitudinal seam cracking, selective seam corrosion,
long narrow axial (channel) corrosion and axial
Leakage (MFL) pigs and are better detected with a
hydrostatic test.
Hydrostatic Testing - 4
•large quantities of test water, which in some areasmay be difficult.
• Once used, the test water may contain trace quantitiesof petroleum products, which may require treatmentof the water prior to discharging or disposal.
• y rostat c test ng requ res t e p pe ne to e out oservice for a period of time thus potentially curtailingthe availability of gasoline, jet fuel, diesel fuel, crudeoil, and/or home heating oil at the delivery point.
7/28/2019 PRESSURE TESTING CODE REQUIREMENTS.pdf
http://slidepdf.com/reader/full/pressure-testing-code-requirementspdf 23/26N. Al-Khirdaji, AZTech Sr. Consultant
Leak Testing
• Leak testing may be used to find leaks in a newly
,
established system where an apparent loss of integrity
has been experienced.
• If they exist, leaks typically occur at joints (or from
through wall defects).
,
operating pressure.
Leak Testing
• Leak testing does not verify pressure rating or - .
and the pressure ratings of the installed componentsare the sole determinants of system pressure ratingand long-term performance.
• Safety is of paramount importance. Leak tests canapply high stress to untried joints and parts in the
.catastrophic rupture. In some cases, leakage mayimmediately precede catastrophic rupture.
7/28/2019 PRESSURE TESTING CODE REQUIREMENTS.pdf
http://slidepdf.com/reader/full/pressure-testing-code-requirementspdf 24/26N. Al-Khirdaji, AZTech Sr. Consultant
Some US Regulations
• § 192.507 Test requirements for pipelines tooperate at a hoop stress less than 30 percent of SMYS and at or above 100 psi. (689 kPa).
• Except for service lines and plastic pipelines, eachsegment of a pipeline that is to be operated at ahoop stress less than 30 percent of SMYS and ator above 100 si 689 kPa must be tested inaccordance with the following:
(a) The pipeline operator must use a test procedurethat will ensure discovery of all potentiallyhazardous leaks in the segment being tested
Some US Regulations
, ,
20 % or more of SMYS and natural gas, inert gas, or
air is the test medium:
(1) A leak test must be made at a pressure between 100 psi.
(689 kPa) gage and the pressure required to produce a
hoop stress of 20 % of SMYS; or
(2) The line must be walked to check for leaks while thehoop stress is held at approximately 20 % of SMYS.
(c) The pressure must be maintained at or above the
test pressure for at least 1 hour.
7/28/2019 PRESSURE TESTING CODE REQUIREMENTS.pdf
http://slidepdf.com/reader/full/pressure-testing-code-requirementspdf 25/26N. Al-Khirdaji, AZTech Sr. Consultant
Pressure Test Preparation
• Each test loop should be provided with a low pointi in connection for h drotest water su l .
High point vents shall be provided to permit theventing of air from the test loop--to ensure that the
pipeline is completely filled with water.
• Test Pressure: The Test Pressure shall be equal to
– 150% of either the design pressure of the piping, .
– 130% of either the design pressure of the pressure
vessel, or its weakest component.(adjusted to new and cold conditions)
Service Tests
• Service tests are usually applied to non-critical
-
hazardous services. Illustrative examples:
(1) Non-flammable and non-toxic fluids
(2) Design pressures less than 150 psig
(3) Operating temperatures range: -20 to 366o F.
• The criteria for application of service tests should beclearly established in the owner specifications.
7/28/2019 PRESSURE TESTING CODE REQUIREMENTS.pdf
http://slidepdf.com/reader/full/pressure-testing-code-requirementspdf 26/26
Pneumatic Tests
• Pneumatic testing is normally used in cases where
tolerated or when water of suitable quality is notavailable.
• Typically, Owner approval is required before pneumatic testing is to be performed.
• Additionally, because of the potential energy of t e compresse a r gas) n t e system un er
pneumatic testing, special safety precautions and procedures have to be implemented.
• Test pressure for pressure vessels = 110% X DP
Leak Detection
• Technology is available to detect leaks from gas.
• One approach involves the use of sensitive sensors on board low- flying surveillance airplanes that fly alonghe pipe route.
• Another approach entails the use of methods basedon analysis of time series of pressure and/or flow
m a ance ecause t ese present some we nownreaction to leaks. A software-based system istypically used for such application.