precision mechanics / systems aspects case examples from lhc trackers 1st eiroforum school on...
TRANSCRIPT
Precision Mechanics / Precision Mechanics / Systems AspectsSystems Aspects
Case examples from LHC TrackersCase examples from LHC Trackers
1st EIROforum School on Instrumentation1st EIROforum School on Instrumentation 11-15 May 200911-15 May 2009
A. Onnela and A. Catinaccio A. Onnela and A. Catinaccio CERN – PH/DTCERN – PH/DT
http://indico.cern.ch/conferenceOtherViews.py?view=standard&confId=43007
ESI 2009, 11-15 May 2009 Precision Mechanics and Systems Aspects. A.Onnela, A.Catinaccio, CERN-PH/DT 2
Intro: LHC Trackers and ‘precision’
Design
Materials
Analysis
Manufacture, Assembly
Transport, Installation
Summary: Lessons learned
Intro: LHC Trackers
Tracker in the heart of the experiment, next to the beam interaction point
ESI 2009, 11-15 May 2009 3Precision Mechanics and Systems Aspects. A.Onnela, A.Catinaccio, CERN-PH/DT
Intro: LHC Trackers
Tracker: Measurement of particle track space points with 10-50 um precision
ESI 2009, 11-15 May 2009 4Precision Mechanics and Systems Aspects. A.Onnela, A.Catinaccio, CERN-PH/DT
Intro: LHC trackers
ESI 2009, 11-15 May 2009 Precision Mechanics and Systems Aspects. A.Onnela, A.Catinaccio, CERN-PH/DT 6
Find 4 straight tracks.
40 million times per second
Find 4 straight tracks!
ESI 2009, 11-15 May 2009 Precision Mechanics and Systems Aspects. A.Onnela, A.Catinaccio, CERN-PH/DT 7
Intro: LHC trackers
Here the 4 straight tracks+ few other high momentum tracks
Intro: LHC Trackers
ESI 2009, 11-15 May 2009 Precision Mechanics and Systems Aspects. A.Onnela, A.Catinaccio, CERN-PH/DT 8
From individual sensor units (modules) via sub-assemblies up to the final Experiment
ESI 2009, 11-15 May 2009 Precision Mechanics and Systems Aspects. A.Onnela, A.Catinaccio, CERN-PH/DT 9
Intro: LHC Trackers and precision
Design
Materials
Analysis
Manufacture, Assembly
Transport, Installation
Summary: Lessons learned
ESI 2009, 11-15 May 2009 Precision Mechanics and Systems Aspects. A.Onnela, A.Catinaccio, CERN-PH/DT 10
To design correctly clarify:
What is really needed?What ‘precision’ is needed?
Establishing the requirements may be difficult and take many iterations, possibly late in the project, too
Design: requirements
ESI 2009, 11-15 May 2009 Precision Mechanics and Systems Aspects. A.Onnela, A.Catinaccio, CERN-PH/DT 11
Design: What is really needed?
• Light weight, minimum material, “transparency” to particles
• Tight mechanical tolerances (high initial accuracy) (a few tens of microns are required for the correct positioning of the detecting modules).
• High stability, high stiffness high natural frequencies
• Short and Long term dimensional stability under load (low CTE, CME, creep)
• High radiation resistance
• Magnetic field: non-magnetic materials
• Low out-gassing and low gas permeability
Example requirements from the LHC trackers:
But as it may be too difficult / too costly / too slow to reach, therefore try to get
the real requirements on:Precision, Accuracy and Stability
Yes, this is the preferred result!
ESI 2009, 11-15 May 2009 12Precision Mechanics and Systems Aspects. A.Onnela, A.Catinaccio, CERN-PH/DT
Design: Requirements on Precision
Accuracy vs. Precision
High accuracy but low precision
High precision but low accuracy
Graph: Pekaje
Both influenced by the quality of manufacture and assembly, and by static loads
ESI 2009, 11-15 May 2009 13Precision Mechanics and Systems Aspects. A.Onnela, A.Catinaccio, CERN-PH/DT
Stability
High momentary precision but low stability
Stability influenced by dynamic loads, creep, vibration, temperature-, pressure-, humidity change, changing magnetic field, etc.
ESI 2009, 11-15 May 2009 14Precision Mechanics and Systems Aspects. A.Onnela, A.Catinaccio, CERN-PH/DT
ESI 2009, 11-15 May 2009 Precision Mechanics and Systems Aspects. A.Onnela, A.Catinaccio, CERN-PH/DT 15
Loads
In addition to the ‘normal’, expected loads (gravitation, thermal, etc.) study also failure scenarios and related loads.
Examples from the Atlas inner tracker:• Transports and installation: Non-ideal support conditions or accidental loads
(difficult to estimate!)• Loss of thermal isolation of the LAr cryostat: Sudden move of tracker supports
by 3 mm (far more than the displacements under normal conditions) • Malfunctioning of cooling systems: fast heating or fast cooling of detectors
(possibly severe thermal shocks)
Design for high precision
Think up to the smallest details, e.g. connections are very important, and the error chain can be long(Modules Sub-structures Full Tracker Installation into Experiment)
Some examples on precision of (metallic) couplings:
Illustrations: J. Huopana / U. Oulu
Elastic averaging:~5 um
Pinned joints: ~5 um
Kinematic coupling:~0.5 um
ESI 2009, 11-15 May 2009 16Precision Mechanics and Systems Aspects. A.Onnela, A.Catinaccio, CERN-PH/DT
ESI 2009, 11-15 May 2009 Precision Mechanics and Systems Aspects. A.Onnela, A.Catinaccio, CERN-PH/DT 17
More and less interesting design subjects
Modules & Layout
Cooling & Services
Structures& Interfaces
Tracker:
1. This is where the attention naturally goes
2. Some attention goes to this, too
3. Little and late attention Big problems
Pay attention also to the less interesting subjects, already early on in the design process.
Not fun, but very much necessary!
ESI 2009, 11-15 May 2009 Precision Mechanics and Systems Aspects. A.Onnela, A.Catinaccio, CERN-PH/DT 18
Intro: LHC Trackers and precision
Design
Materials
Analysis
Manufacture, Assembly
Transport, Installation
Summary: Lessons learned
ESI 2009, 11-15 May 2009 Precision Mechanics and Systems Aspects. A.Onnela, A.Catinaccio, CERN-PH/DT 19
Choice of materials
Correct understanding of the design requirementsenables
Correct choice of materials
Of the LHC tracker requirements…
…all have a direct impact on the material choices.
• Light weight, minimum material, “transparency” to particles• Tight mechanical tolerances (high initial accuracy) (a few tens of microns are
required for the correct positioning of the detecting modules).• High stability, high stiffness high natural frequencies• Short and Long term dimensional stability under load (low CTE, CME, creep) • High radiation resistance • Magnetic field: non-magnetic materials• Low out-gassing and low gas permeability
Materials for a LHC tracker
ESI 2009, 11-15 May 2009 Precision Mechanics and Systems Aspects. A.Onnela, A.Catinaccio, CERN-PH/DT 20
For trackers a hybrid solution: Structures in CFRP, small support / cooling inserts in aluminium
ESI 2009, 11-15 May 2009 Precision Mechanics and Systems Aspects. A.Onnela, A.Catinaccio, CERN-PH/DT 21
•
Materials for a LHC tracker
• Documentation exists, e.g. “CERN: Compilation of radiation damage data”
• However, the products change, some materials are no longer available – some new materials are not tested yet (or not known by us)
ESI 2009, 11-15 May 2009 Precision Mechanics and Systems Aspects. A.Onnela, A.Catinaccio, CERN-PH/DT 22
• CFRP (carbon-fibre reinforced polymers) much favoured as tailorable for high stiffness, good strength, low mass, near zero CTE, low CME, low creep
– Typical carbon fibres:• HT (high tensile e.g. T300) E = 200-255 GPa (235 for T300)• IM (intermediate modulus e.g. T800) E = 255-315 GPa• HM (high modulus e.g. M55J) E > 315 GPa• UHM (ultra-high modulus e.g. GY-70, P120) E > 395 GPa• (Note: Aluminum: 70 GPa, Steel: 210 GPa)
– Typical matrix materials (resins):• Epoxies• Cyanate ester (10 times lower CME but usually costly)
– Typical core materials:• Nomex (aramid fibres)• Aluminium
• New interesting possibilities with non-plastic matrices– Metal matrix composites (for thermal properties, but ‘heavy’)– Carbon-carbon composites (for thermal properties)
• Availability and (dis)continuity of commercial products can be a problem
Materials for a LHC tracker
ESI 2009, 11-15 May 2009 Precision Mechanics and Systems Aspects. A.Onnela, A.Catinaccio, CERN-PH/DT 23
Intro: LHC Trackers and precision
Design
Materials
Analysis
Manufacture, Assembly
Transport, Installation
Summary: Lessons learned
ESI 2009, 11-15 May 2009 Precision Mechanics and Systems Aspects. A.Onnela, A.Catinaccio, CERN-PH/DT 24
Analysis
• Stability: analyse for high stiffness, thermal behaviour, vibrations & natural frequencies, support configuration, stress levels
• All boundary conditions must be well known (by experience) or large multipliers must be introduced (or risks taken!)
• Analyses must feedback to design at early stage• Analyse carefully most stressed areas (local supports and connections)• Allow time for analysis verification by extensive testing and prototype
qualification (CFRP assemblies are often difficult to predict due to manufacturing and hybrid components)
Typical analyses:
Composite layup characterisationStatic analysis (gravity loads, loads during transports)Sub modelling, local areas, supports and connections where the real problems can be.BucklingThermalModal analysisRandom vibrationShock Analysis (transport and installation)
ESI 2009, 11-15 May 2009 Precision Mechanics and Systems Aspects. A.Onnela, A.Catinaccio, CERN-PH/DT 25
Examples of FEM calculations
Rigid structures high local stresses
ESI 2009, 11-15 May 2009 Precision Mechanics and Systems Aspects. A.Onnela, A.Catinaccio, CERN-PH/DT 26
Examples of FEM calculations
ASIC power 5.3 WFEA
Loads during handling can be much higher than the nominal operation loads
ESI 2009, 11-15 May 2009 Precision Mechanics and Systems Aspects. A.Onnela, A.Catinaccio, CERN-PH/DT 27
Examples of FEM calculations
Vibration measurements for different accelerators
Random vibration analysis on Atlas TRT barrel structure:Input power spectral density (PSD) 110-8 g2/Hz and 5% damping ratio (frequency independent) results in 11 um displacements.10x lower PSD results in 2x smaller displacement, still significant!‘Fortunately’, finally a lot of cables, so a lot of damping too...
Vibration measurements in different accelerators
1.E-15
1.E-14
1.E-13
1.E-12
1.E-11
1.E-10
1.E-09
1.E-08
1.E-07
0 20 40 60 80 100
Frequency [Hz]
PS
D a
ccel
erat
ion
[g2/
Hz]
LEP (Aleph worst case) Strasburg
Ruthe (GE) SSC
US standard
ESI 2009, 11-15 May 2009 Precision Mechanics and Systems Aspects. A.Onnela, A.Catinaccio, CERN-PH/DT 28
Intro: LHC Trackers and precision
Design
Materials
Analysis
Manufacture, Assembly
Transport, Installation
Summary: Lessons learned
Manufacture
Example:Manufacture of this silicon module support frame
ESI 2009, 11-15 May 2009 29Precision Mechanics and Systems Aspects. A.Onnela, A.Catinaccio, CERN-PH/DT
Detector supports inserts (e.g. 11, 12, 13, and 14)Detector supports inserts (e.g. 11, 12, 13, and 14)• Define parallel planes on which the detectors Define parallel planes on which the detectors
are mountedare mounted• Planarity requirement 0.05 mmPlanarity requirement 0.05 mm
1.2 m
ESI 2009, 11-15 May 2009 30Precision Mechanics and Systems Aspects. A.Onnela, A.Catinaccio, CERN-PH/DT
Manufacture
Metallic inserts
Carbon fibre piecesin ‘1 mm precision’
Accurate gluing jig
Applied concept: From modest accuracy components to assemblies of high accuracy
ESI 2009, 11-15 May 2009 31Precision Mechanics and Systems Aspects. A.Onnela, A.Catinaccio, CERN-PH/DT
Assembly
756x756x
ESI 2009, 11-15 May 2009 32Precision Mechanics and Systems Aspects. A.Onnela, A.Catinaccio, CERN-PH/DT
Measurements
Geometrical precision of the module supports and positioning dowel pins measured to be better than 50 m over the whole area. 4% of assemblies found out of tolerances, and corrected.
24 module supports
12 dowel pins
ESI 2009, 11-15 May 2009 33Precision Mechanics and Systems Aspects. A.Onnela, A.Catinaccio, CERN-PH/DT
ESI 2009, 11-15 May 2009 Precision Mechanics and Systems Aspects. A.Onnela, A.Catinaccio, CERN-PH/DT 34
Manufacture
ESI 2009, 11-15 May 2009 Precision Mechanics and Systems Aspects. A.Onnela, A.Catinaccio, CERN-PH/DT 35
Measurements
ASIC power 5.3 WFEA
PhotogrammetryPhotogrammetry ‘‘Robotic’ armRobotic’ arm
Measurements
ESI 2009, 11-15 May 2009 Precision Mechanics and Systems Aspects. A.Onnela, A.Catinaccio, CERN-PH/DT 36
ESI 2009, 11-15 May 2009 Precision Mechanics and Systems Aspects. A.Onnela, A.Catinaccio, CERN-PH/DT 37
Example: Barrel Support Structure
ASIC power 5.3 WFEA
Measurements
And then the structures are loaded
ESI 2009, 11-15 May 2009 Precision Mechanics and Systems Aspects. A.Onnela, A.Catinaccio, CERN-PH/DT 38
Design hint: Choose carefully the color of the cables!
ESI 2009, 11-15 May 2009 Precision Mechanics and Systems Aspects. A.Onnela, A.Catinaccio, CERN-PH/DT 39
ESI 2009, 11-15 May 2009 Precision Mechanics and Systems Aspects. A.Onnela, A.Catinaccio, CERN-PH/DT 40
Intro: LHC Trackers and precision
Design
Materials
Analysis
Manufacture, Assembly
Transport, Installation
Summary: Lessons learned
ESI 2009, 11-15 May 2009 Precision Mechanics and Systems Aspects. A.Onnela, A.Catinaccio, CERN-PH/DT 41
Transport and installation
ESI 2009, 11-15 May 2009 Precision Mechanics and Systems Aspects. A.Onnela, A.Catinaccio, CERN-PH/DT 42
Transport and installation
ESI 2009, 11-15 May 2009 Precision Mechanics and Systems Aspects. A.Onnela, A.Catinaccio, CERN-PH/DT 43
Collision predicted from 3D measurementsInstallation adjusted accordingly
Measurements up to the end
ESI 2009, 11-15 May 2009 Precision Mechanics and Systems Aspects. A.Onnela, A.Catinaccio, CERN-PH/DT 44
Intro: LHC Trackers and precision
Design
Materials
Analysis
Manufacture, Assembly
Transport, Installation
Summary: Lessons learned
ESI 2009, 11-15 May 2009 Precision Mechanics and Systems Aspects. A.Onnela, A.Catinaccio, CERN-PH/DT 45
Summary: Lessons learned• Put effort into establishing clear specifications,
be prepared to do many iterations and late modifications– Accuracy, precision, stability requirements– Load conditions– Electrical, magnetic, radiation, fluids, etc.
• Aim for simplicity and clarity in the design (e.g. supports). Enough of complications will come anyways!
• Do analysis early on to direct the design choices– Back-up with prototypes and tests where suitable data not available
• Plan and ‘design’ geometry measurements right from the beginning– References, survey targets, etc.
• And last, but not at all least: Take ‘services’ = Pipework and cabling into the main design effort right from the beginning
– Remember to plan and design their testing too (leak tests, connectivity, etc.)
The end