ppt on high level bridge
TRANSCRIPT
APresentation
onPractical Training
taken at
DURATION: 04/06/2014 to 04/07/2014SESSION: 2014-2015
SUBMITTED BY : LOKESH KUMAR MEENA
Final Year B.Tech (Civil)
SUBMITTED TO :SHIVANSHI SINGHANKUSH JAINAVI MAHERISHI
DEPARTMENT OF CIVIL ENGINEERINGR.N MODI ENGINEERING COLLEGE
RANPUR., KOTA
HIGH LEVEL BRIDGE ACROSSKALISIND RIVER
NEED FOR CONSTRUCTION
To improve traffic management system.
To reduce hindrance to traffic flow.
By increase the volume of road, chances of accidents get reduced hence it will act as a life saving drug.
Elevated Road
FOUNDATION
SUBSTRUCTURE
SUPERSTRUCTURE
APPROACHES
WEARING COAT
CRASH BARRIERS
RAILINGS
SHIFTING OF UTILITIES
SERVICE ROAD
1. Overall length of elevated road2. Carriage way of elevated road 3. Crash Barriers
4. Embankment Slope5. Approaches
Salient features of Elevated Road Bridge1250meter
Two lane divided bridge
R.C.C. Crash Barriers1 in 30 Solid approaches beyond via duct spans with R.C.C. Retaining Wall
7. Structure Details Of Viaduct
6. Wearing Coat 40 mm BC Followed by 25mm mastic asphalt
i. PSC Box Girder 52.600 meter span (7No.), 47.600 meter span (3No.)
ii. PSC Girder With RCC Decking16.700 meter span (7 No.)with 4 girder arrangement
iii. Box Pier 1 No. (26 meter span)
Wall type pier with Semi-Circular Ends
v. Foundation Open foundation
8. Seismic Zone Zone II
9. Bearings Elastomeric Bearing & POT PIT
iv. Sub-structure for viaduct span
10.Expansion Joint Strip Seal Expansion Joint
11. Estimated Quantity of steel Reinforcement
3041 MT
12. Estimated Quantity of High Tension Steel
147.54 MT
13. Estimated Quantity of Cement Concrete
20619 cubic meter
14. Climate & Rainfall climate is hot & humid & catchment
The primary components of the project include: 1. Site clearance. 2. Earth Work and Excavation . 3. Shifting of utilities. 4. Construction of Open foundation for pier & abutments. 5. Construction of RCC T Beam & PSC Girders & Deck Slab type superstructure . 6. Construction of retaining wall. 7. Construction of embankment and subgrade in approaches. 8. Construction of service road. 9. Construction of roadside unlined drain.10. Construction of diversion road including culvert.11.Providing road sign & markings.12. Providing road illumination required.
TEST PERFORMED AT SITE AND SITE LABORATORY
(a) At site of work:- Slump test for measurement of workability of concrete. (b) At site laboratory:- (i) Compressive strength test of concrete . (ii) Grading of aggregates-Sieve Analysis Test.
SLUMP TEST FOR WORKABILITY OF CONCRETE
Most common method for measuring the consistency & uniformity of concrete. APPARATUS REQUIRED FOR TEST:• Cast iron mould in the form of frustum of cone having internal dimension:- Bottom diameter : 20cm Top diameter : 10cm Height : 30cm• Tamping Rod of 16mm diameter.
Foundation For piers and abutments • Types of bridge foundations- 1. Open foundation2. Well foundation3. Block foundation
Open foundation & Block foundation are come under shallow foundations . well foundation are come under deep foundations.
Open foundation
• Types of open foundation-Isolated , combined, and strip footings.Raft foundations.
CURING OF OPEN FOUNDATION
WELL FOUNDATION
Pre-Stressing Pre-stress
concrete is the one in which there have been introduced internal stresses of such a magnitude and distribution that the stresses resulting from given external loading counteracted to a desired degree.
Pre-Stressing
SUBSTRUCTURE PIERS & ABUTMENTS
Piers and abutments are the vertical structures supporting deck,girders,bearings providing for transmitting their load along with live load coming over bridge to the bed/earth through foundation.
Formwork on pier Lifting of formwork on pier
Concreting and curing
SUPER STRUCTUREBOX GIDER
Progress of Kalisind Bridge in GAD - 1
Progress of Kalisindl Bridge in GAD - 2
River Portion
Progress of Kalisind Bridge in GAD - 3
THANK
YOU
QUERIES
???