ppt on high level bridge

22
A Presentation on Practical Training taken at DURATION: 04/06/2014 to 04/07/2014 SESSION: 2014- 2015 SUBMITTED BY : LOKESH KUMAR MEENA Final Year B.Tech (Civil) SUBMITTED TO : SHIVANSHI SINGH ANKUSH JAIN AVI MAHERISHI DEPARTMENT OF CIVIL ENGINEERING R.N MODI ENGINEERING COLLEGE RANPUR., KOTA HIGH LEVEL BRIDGE ACROSS KALISIND RIVER

Upload: lokesh

Post on 14-Apr-2017

434 views

Category:

Engineering


6 download

TRANSCRIPT

Page 1: PPT On High level bridge

APresentation

onPractical Training

taken at

DURATION: 04/06/2014 to 04/07/2014SESSION: 2014-2015

SUBMITTED BY : LOKESH KUMAR MEENA

Final Year B.Tech (Civil)

SUBMITTED TO :SHIVANSHI SINGHANKUSH JAINAVI MAHERISHI

DEPARTMENT OF CIVIL ENGINEERINGR.N MODI ENGINEERING COLLEGE

RANPUR., KOTA

HIGH LEVEL BRIDGE ACROSSKALISIND RIVER

Page 2: PPT On High level bridge

NEED FOR CONSTRUCTION

To improve traffic management system.

To reduce hindrance to traffic flow.

By increase the volume of road, chances of accidents get reduced hence it will act as a life saving drug.

Page 3: PPT On High level bridge

Elevated Road

FOUNDATION

SUBSTRUCTURE

SUPERSTRUCTURE

APPROACHES

WEARING COAT

CRASH BARRIERS

RAILINGS

SHIFTING OF UTILITIES

SERVICE ROAD

Page 4: PPT On High level bridge

1. Overall length of elevated road2. Carriage way of elevated road 3. Crash Barriers

4. Embankment Slope5. Approaches

Salient features of Elevated Road Bridge1250meter

Two lane divided bridge

R.C.C. Crash Barriers1 in 30 Solid approaches beyond via duct spans with R.C.C. Retaining Wall

7. Structure Details Of Viaduct

6. Wearing Coat 40 mm BC Followed by 25mm mastic asphalt

i. PSC Box Girder 52.600 meter span (7No.), 47.600 meter span (3No.)

ii. PSC Girder With RCC Decking16.700 meter span (7 No.)with 4 girder arrangement

iii. Box Pier 1 No. (26 meter span)

Page 5: PPT On High level bridge

Wall type pier with Semi-Circular Ends

v. Foundation Open foundation

8. Seismic Zone Zone II

9. Bearings Elastomeric Bearing & POT PIT

iv. Sub-structure for viaduct span

10.Expansion Joint Strip Seal Expansion Joint

11. Estimated Quantity of steel Reinforcement

3041 MT

12. Estimated Quantity of High Tension Steel

147.54 MT

13. Estimated Quantity of Cement Concrete

20619 cubic meter

14. Climate & Rainfall climate is hot & humid & catchment

Page 6: PPT On High level bridge

The primary components of the project include: 1. Site clearance. 2. Earth Work and Excavation . 3. Shifting of utilities. 4. Construction of Open foundation for pier & abutments. 5. Construction of RCC T Beam & PSC Girders & Deck Slab type superstructure . 6. Construction of retaining wall. 7. Construction of embankment and subgrade in approaches. 8. Construction of service road. 9. Construction of roadside unlined drain.10. Construction of diversion road including culvert.11.Providing road sign & markings.12. Providing road illumination required.

Page 7: PPT On High level bridge

TEST PERFORMED AT SITE AND SITE LABORATORY

(a) At site of work:- Slump test for measurement of workability of concrete. (b) At site laboratory:- (i) Compressive strength test of concrete . (ii) Grading of aggregates-Sieve Analysis Test.

Page 8: PPT On High level bridge

SLUMP TEST FOR WORKABILITY OF CONCRETE

Most common method for measuring the consistency & uniformity of concrete. APPARATUS REQUIRED FOR TEST:• Cast iron mould in the form of frustum of cone having internal dimension:- Bottom diameter : 20cm Top diameter : 10cm Height : 30cm• Tamping Rod of 16mm diameter.

Page 9: PPT On High level bridge

Foundation For piers and abutments • Types of bridge foundations- 1. Open foundation2. Well foundation3. Block foundation

Open foundation & Block foundation are come under shallow foundations . well foundation are come under deep foundations.

Page 10: PPT On High level bridge

Open foundation

• Types of open foundation-Isolated , combined, and strip footings.Raft foundations.

Page 11: PPT On High level bridge

CURING OF OPEN FOUNDATION

Page 12: PPT On High level bridge

WELL FOUNDATION

Page 13: PPT On High level bridge
Page 14: PPT On High level bridge

Pre-Stressing Pre-stress

concrete is the one in which there have been introduced internal stresses of such a magnitude and distribution that the stresses resulting from given external loading counteracted to a desired degree.

Pre-Stressing

Page 15: PPT On High level bridge

SUBSTRUCTURE PIERS & ABUTMENTS

Piers and abutments are the vertical structures supporting deck,girders,bearings providing for transmitting their load along with live load coming over bridge to the bed/earth through foundation.

Page 16: PPT On High level bridge

Formwork on pier Lifting of formwork on pier

Concreting and curing

Page 17: PPT On High level bridge

SUPER STRUCTUREBOX GIDER

Page 18: PPT On High level bridge

Progress of Kalisind Bridge in GAD - 1

Page 19: PPT On High level bridge

Progress of Kalisindl Bridge in GAD - 2

River Portion

Page 20: PPT On High level bridge

Progress of Kalisind Bridge in GAD - 3

Page 21: PPT On High level bridge

THANK

YOU

Page 22: PPT On High level bridge

QUERIES

???