powerpoint presentation · stormwater engineer city of lubbock r. paul mcmillen, p.e., cfm project...
TRANSCRIPT
6/9/2014
1
2014 TFMA Annual Spring Conference
Project Team
Michael Keenum, P.E., CFM
Stormwater Engineer
City of Lubbock
R. Paul McMillen, P.E., CFM
Project Manager
Parkhill, Smith & Cooper, Inc.
Jason L. Swofford, P.E.
V.P. Engineering
Hugo Reed and Associates, Inc.
What is a playa lake?
Naturally occurring, broad, shallow,
roughly circular depression
Approximately 1 per square mile
Non-riverine
6/9/2014
2
How do playa lakes function?
Catch runoff that collects in low spots
Naturally restore capacity by
evaporation or infiltration – slow process
Some overflow to the next downstream
playa in larger rainfall events
Some lakes do not overflow even in a
0.2% chance annual rainfall event
City of Lubbock Storm Sewer
Projects
South Central Lubbock Drainage
Improvements Project (SCLDIP) – 1995-
2003
South Lubbock Drainage Improvements
Project (SLDIP) – 1999-2009
Northwest Lubbock Drainage
Improvements Project (NWLDIP) –
2006-present
South Central and South
Lubbock Drainage Projects
6/9/2014
3
Northwest Lubbock Study Area
Northwest Lubbock Drainage Project
Catalyst for “recent” projects
October 1983 Storm Event
6/9/2014
4
Catalyst for “recent” projects
June 1999 Storm Event
Catalyst for “recent” projects
September 2008 Storm Event
Catalyst for “recent” projects
July 2010 Storm Event
6/9/2014
5
Storage Restoration
Install storm sewer networks to drain down lakes
to pre-rain condition
Migrate from reliance on evaporation and
percolation to restore lake storage
Establish initial Water Surface Elevation (WSE) at
lakes
Evaluate draindown times and recovery process
for each lake
Design appropriate pipe network to meet goals
Design Considerations
Based on recovery of playa lake storage
within a reasonable time period to
prepare for the next rainfall event
Design basis – single day (24 hour)
event precipitation, “official” and
accepted method
Design Considerations
Basis for single-event precipitation is the
Flood Insurance Study 24-hour
precipitation depths based on probability
of occurrence in any given year:
• 10% probable event (10 Year) 4.60 inches
• 4% probable event (25 Year) 5.30 inches
• 2% probable event (50 Year) 6.00 inches
• 1% probable event (100 Year) 6.80 inches
• 0.2% probable event (500 Year) 8.38 inches
6/9/2014
6
Design concept for projects
Infeasible to capture and collect storm event to
offer significant protection
Evaluated draindown time concept vs. standard
design storm
Ensured available storage and draindown times
Utilized 30-day draindown time for ultimate
designs for largest storage-capacity lakes
Most lakes recover 90% of available storage in 10
days or less
Other design considerations
Route (right-of-way) availability
Available grades to outlet point
Existing utilities
Subsurface obstacles (i.e., drill shaft retaining wall
at IH-27 for SCLDIP)
Archaeology at outlets
Environmental sites (i.e., LPST)
Corps of Engineers Permit (all projects under
NWP 26)
Draindown Effects April-June 1999 SCLDIP
L019 (Casey/K-Mart)April - June 1999
3195
3200
3205
3210
3215
3220
24-Apr 24-May 23-Jun 23-Jul 22-Aug 21-Sep
Date
Sta
ge (
ft)
Overflow Low Floor No Project Alt 2E Int 1 Int 2 Alt 2A
Estimated Low Floor Elev. = 3215.5
Lake Overflow Elev. = 3214
6/9/2014
7
Draindown Effects April-June 1999 SCLDIP
L021 (Clapp)April - June 1999
3185
3190
3195
3200
3205
3210
24-Apr 24-May 23-Jun 23-Jul 22-Aug 21-Sep
Date
Sta
ge (
ft)
Overflow Low Floor No Project Alt 2E Int 1 Int 2 Alt 2A
Estimated Low Floor Elev. = 3200
Lake Overflow Elev. = 3208.6
Draindown Effects April-June 1999 SCLDIP
L023N (Trinity)April - June 1999
3214
3215
3216
3217
3218
3219
3220
3221
3222
3223
3224
24-Apr 24-May 23-Jun 23-Jul 22-Aug 21-Sep
Date
Sta
ge (
ft)
Overflow Low Floor No Project Alt 2E Int 1 Int 2 Alt 2A
Estimated Low Floor Elev. = 3223
Lake Overflow Elev. = 3221.7
Draindown Effects April-June 1999 SCLDIP
L037 (McAlister)April - June 1999
3252
3254
3256
3258
3260
3262
3264
3266
3268
24-Apr 24-May 23-Jun 23-Jul 22-Aug 21-Sep
Date
Sta
ge (
ft)
Overflow Low Floor No Project Alt 2E Int 1 Int 2 Alt 2A
Estimated Low Floor Elev. = 3266
Lake Overflow Elev. = 3264.1
6/9/2014
8
Maxey Park Draindown Single Event NWLDIP
Rush Park Lake Draindown Single Event NWLDIP
Project Costs
South Central Drainage Project (SCLDIP)
$39 million
South Lubbock Drainage Project (SLDIP)
$55 million
Northwest Lubbock Drainage Project (NWLDIP)
$80 million (estimated)
Total Costs
$174 million
Feasibility Study preceded each project
6/9/2014
9
Financing Approach
Stormwater Utility Fee – created in 1993
Currently flat fee based on number of water meters
City Council elected to fund all of the projects with utility fee
20 and 30 year bonds to fund projects
Additional debt service added through 2018
First debt roll-off scheduled in 2021
Remapping Efforts
SCLDIP – Playa Lake System E
SLDIP – Playa Lake System G
NWLDIP – Playa Lake Systems B,C,D
SCLDIP Remapping
Playa System E
Reduction of Base Flood Elevations at all
lakes except Lakes 20, 23N, 31
665 structures removed from SFHA
98 structures added to SFHA
567 net structures removed from SFHA
Estimated structure removal value - $76.5
million
6/9/2014
10
SCLDIP Remapping Lakes 23, 24,
and 25 Playa System E
SCLDIP Remapping Lakes 27 and 31
Playa System E
SLDIP Remapping
Playa System G
Reduction of Base Flood Elevations at all
lakes except Lakes 84, 87, 91 and 92
465 structures removed from SFHA
86 structures added to SFHA
379 net structures removed from SFHA
Estimated structure removal value - $71
million
6/9/2014
11
SLDIP Remapping Lakes 94, 95 and 133
Playa System G
NWLDIP Anticipated Remap Structure
Removal Arnett-Benson Area
NWLDIP Anticipated Remap
Structure Removal
Structure Removal Count at Arnett-Benson
Structures to be Removed from Special Flood Hazard Area
Residential 770
Business 43
Church 6
Education 9
Municipal 1
Total Structures 829
6/9/2014
12
NWLDIP Anticipated Remap Structure
Removal Maxey Park
NWLDIP Anticipated Remap
Structure Removal
Structure Removal Count at Maxey Park
Structures to be Removed from Special Flood Hazard Area
Residential 400
Business 33
Total Structures 433
Conclusion
Remapping completed and FEMA
accepted for System E
Remapping efforts for System G
awaiting FEMA approval – anticipate
Draft maps in summer 2014
Capital Project to remap systems
impacted by Phase 1 of NWLDIP
scheduled for FY 2014-15
6/9/2014
13
2014 TFMA Annual Spring Conference
Project Team
Michael Keenum, P.E., CFM
Stormwater Engineer
City of Lubbock
R. Paul McMillen, P.E., CFM
Project Manager
Parkhill, Smith & Cooper, Inc.
Jason L. Swofford, P.E.
V.P. Engineering
Hugo Reed and Associates, Inc.
6/9/2014
14
Playa Lakes
Naturally occurring, broad, shallow,
roughly circular depression
95% of the world’s playas are located on
the South Plains
There are approximately 22,000 playas
located across the Llano Estacado
Playa Lakes
The Construction Process
Three major projects
South Central Lubbock Drainage Improvements Project (SCLDIP)
South Lubbock Drainage Improvements Project (SLDIP)
Northwest Lubbock Drainage Improvements Project (NWLDIP)
All are deep Installations
Up to 55 feet below grade to storm sewer invert
6/9/2014
15
Project Costs
South Central Drainage Project (SCLDIP)
$39 million
South Lubbock Drainage Project (SLDIP)
$55 million
Northwest Lubbock Drainage Project (NWLDIP)
$80 million (estimated)
Total Costs
$174 million
SCLDIP Statistics
Connects 12 playa lakes
13.6 miles of storm sewer pipeline
Depths ranging from 15 to 50 feet
Over 32,000 linear feet of tunnel
Pipe diameters from 24 – 72 inch
Retrofit through urban area
SCLDIP Permissible Materials
Precast reinforced concrete pipe (RCP)
Fiberglass reinforced mortar pipe
(FRMP)
Cast-in-place non-reinforced concrete
pipe (CIPNRCP)
6/9/2014
16
SCLDIP at Outlet 72” RCP
SCLDIP CIPNRCP 72” Dia.
SCLDIP CIPNRCP 72” Dia.
6/9/2014
17
SCLDIP Rock Trencher on Avenue W
SCLDIP TBM Retrieval 50’ Below Grade
40th Street at IH-27
SCLDIP “Stair Step” Lake Inlet
6/9/2014
18
SCLDIP “Stair Step” Lake Inlet
SCLDIP “Tower” Inlet
Cofferdam protected
construction at Lake 31
Completed tower inlet at Lake 24
SCLDIP 72” Diameter Outlet
6/9/2014
19
SLDIP Statistics
Connects 12 playa lakes
19 miles of storm sewer pipeline
Depths ranging from 15 to 55 feet
Over 10,000 linear feet of tunnel
Pipe diameters from 24 – 54 inch
SLDIP Permissible Materials
Precast reinforced concrete pipe (RCP)
Fiberglass reinforced mortar pipe
(FRMP)
SLDIP Construction Train
In unpaved right-of-way
In paved thoroughfare
6/9/2014
20
SLDIP Deep Installation
Construction in thoroughfare
Deadweight prevents FRMP flotation
when installing cement stabilized
backfill
SLDIP Lake Inlet Under Construction
SLDIP FRMP Stockpile
6/9/2014
21
SLDIP Outlet 54” Diameter
NWLDIP Statistics
Connects 6 playa lakes and 1 retention
basin
8 miles of storm sewer pipeline
Depths ranging from 15 to 55 feet
Over 8,200 feet of tunnel
Pipe sizes from 24-inch diameter to
10’x10’ box with short segment of 15’x7’
box
NWLDIP Permissible Materials
Precast reinforced concrete box (RCB)
Precast reinforced concrete pipe (RCP)
Fiberglass reinforced mortar pipe
(FRMP)
6/9/2014
22
NWLDIP Plan & Profile at Outfall - Why it
gets deep so quickly
NWLDIP Precast Box Manufacture
10 x 10 box reinforcement cage
and post-casting touchup
NWLDIP 15’ x 7’ RCB Stockpile
6/9/2014
23
NWLDIP 10’ x 10’ RCB Stockpile
NWLDIP Placing 15’ x 7’ Boxes at Outlet
NWLDIP Placing Articulated Block
6/9/2014
24
NWLDIP Placing Articulated Block
NWLDIP RCB Cast-in-place Transition
15’ x 7’ to 10’ x 10’
NWLDIP Trenching Uphill from Outlet
6/9/2014
25
NWLDIP First Major Bend 10’ x 10’ RCB
Prior to Trench Box Reset
NWLDIP Screening Operation
NWLDIP Tunnel Shaft at Railroad
6/9/2014
26
NWLDIP Tunnel Shaft at Railroad
NWLDIP Tunnel Liner Plate Under Railroad for
10’ x 10’ RCB – 230 linear foot drive
NWLDIP Tunnel Jacking Machine
6/9/2014
27
NWLDIP Lowering 10’ x 10’ Box at Railroad
Tunnel Shaft
NWLDIP Construction Train in Residential
Neighborhood
NWLDIP Gantry Crane Operation
6/9/2014
28
NWLDIP Cement Stabilized Backfill
NWLDIP Density-Controlled Backfill Compaction
NWLDIP Work Zone in Residential Area
6/9/2014
29
NWLDIP 10’ x 10’ One-Pass Tunnel in
Knoxville Avenue – 330 Linear Feet Run
NWLDIP Lake 52 Inlet Structure
NWLDIP Paving Operations in Residential
Neighborhood
6/9/2014
30
Conclusion
2 Major projects already completed
SCLDIP in 2003
SLDIP in 2009
Phase 1 of third project completed
NWLDIP in May 2014
Projects tested by record rainfall events
in 2008 and 2010
Most recent test of systems May 2014