![Page 1: Phase 1- Progress Report - Hub6 6-Progress_Report.pdf · Phase 1- Progress Report ... The site leveling & grading works has been completed. ... GSB & WMM layers are completed in A1,CC1,DD1&](https://reader031.vdocuments.us/reader031/viewer/2022021901/5b87f20a7f8b9a3d028c2d19/html5/thumbnails/1.jpg)
Hub 6 Chennai
Phase 1- Progress Report
Status as on 06-May-2013
![Page 2: Phase 1- Progress Report - Hub6 6-Progress_Report.pdf · Phase 1- Progress Report ... The site leveling & grading works has been completed. ... GSB & WMM layers are completed in A1,CC1,DD1&](https://reader031.vdocuments.us/reader031/viewer/2022021901/5b87f20a7f8b9a3d028c2d19/html5/thumbnails/2.jpg)
Hub 6 Chennai
CONTENT
General Project Information Project brief Design status of project Procurement Packages
Packages Plumbing Electrical
Progress of works
Status of civil works
Progress Photographs
![Page 3: Phase 1- Progress Report - Hub6 6-Progress_Report.pdf · Phase 1- Progress Report ... The site leveling & grading works has been completed. ... GSB & WMM layers are completed in A1,CC1,DD1&](https://reader031.vdocuments.us/reader031/viewer/2022021901/5b87f20a7f8b9a3d028c2d19/html5/thumbnails/3.jpg)
Hub 6 Chennai
GENERAL
1.1 Project information :
Project Name : HUB 6
Developers : Fortune Estate Developers Pvt. Ltd
Architect : M/s Sajith & Vivek Architects
Structural & Service consultants : M/s. Potential Semac Consultants (P)
Ltd Bangalore
Landscape Consultant : M/s WAHO Designs Pvt Ltd
PCB & MOEF Consultants : Hubert Enviro Care systems Pvt Ltd
Traffic Management consultants : Consortia of Infrastructure Engineers
![Page 4: Phase 1- Progress Report - Hub6 6-Progress_Report.pdf · Phase 1- Progress Report ... The site leveling & grading works has been completed. ... GSB & WMM layers are completed in A1,CC1,DD1&](https://reader031.vdocuments.us/reader031/viewer/2022021901/5b87f20a7f8b9a3d028c2d19/html5/thumbnails/4.jpg)
Hub 6 Chennai
1.2 Project Brief:
Classification of Project : Integrated Township
Location : OMR, Thiruporur , Kelambakkam,Chennai
Area in Acres : 175 acres (approx.)
Phase 1 area in acres : 10.53 acres ( Road pattern Sanctioned Extent )
Project Start Date : July 2012
![Page 5: Phase 1- Progress Report - Hub6 6-Progress_Report.pdf · Phase 1- Progress Report ... The site leveling & grading works has been completed. ... GSB & WMM layers are completed in A1,CC1,DD1&](https://reader031.vdocuments.us/reader031/viewer/2022021901/5b87f20a7f8b9a3d028c2d19/html5/thumbnails/5.jpg)
Hub 6 Chennai
1.3 Current Design status of project:
Architectural Concept : Phase 2 , The initial concept Plan has been shared by S & V.
Entrance Gateway :The concept Plan has been circulated for approval by WAHO designs .
Landscaping Concept : Phase 1 & Master Plan shared by WAHO
designs is approved.
Approval Plan of 10.53 acres : The Road Pattern approval from DTCP received on 22.06.12.
Layout Approval from DTCP received on 08.01.2013
![Page 6: Phase 1- Progress Report - Hub6 6-Progress_Report.pdf · Phase 1- Progress Report ... The site leveling & grading works has been completed. ... GSB & WMM layers are completed in A1,CC1,DD1&](https://reader031.vdocuments.us/reader031/viewer/2022021901/5b87f20a7f8b9a3d028c2d19/html5/thumbnails/6.jpg)
Hub 6 Chennai
1.4 Procurement Packages:
Package Activity Agency
Civil Works Compound wall Sri Ganesh Cement works
Back Filling & well Barrication works
Dhandapani Civil Contractor
Site Grading & Levelling works
YKR Transport
Culvert works
Parimala Construction & agencies Pvt Ltd
Water Testing & Yield Geonix
Security Services Dass security services
Survey Works Apex Topo Mappers
Road Works Sathyam Engineers & Contractors
![Page 7: Phase 1- Progress Report - Hub6 6-Progress_Report.pdf · Phase 1- Progress Report ... The site leveling & grading works has been completed. ... GSB & WMM layers are completed in A1,CC1,DD1&](https://reader031.vdocuments.us/reader031/viewer/2022021901/5b87f20a7f8b9a3d028c2d19/html5/thumbnails/7.jpg)
Hub 6 Chennai
2. SERVICE PACKAGES :
Name of Package Name of Vendor
Plumbing Package Techmek Engineers
Electrical Package Tecsol Engineers Pvt. Ltd
Landscape Package Jesam Irrigation Systems -SC
Civil Package Vinayaga Engineers & Contractors Ltd.
![Page 8: Phase 1- Progress Report - Hub6 6-Progress_Report.pdf · Phase 1- Progress Report ... The site leveling & grading works has been completed. ... GSB & WMM layers are completed in A1,CC1,DD1&](https://reader031.vdocuments.us/reader031/viewer/2022021901/5b87f20a7f8b9a3d028c2d19/html5/thumbnails/8.jpg)
Hub 6 Chennai
3. Progress of Civil work - Status
Culvert Works : The culvert works for the channel which passes through the
layout has been completed. Road works : 1. The site leveling & grading works has been completed. 2. The filling of Hill earth to the required level is completed. 3. The leveling & trimming of road from culvert to Illalur road is
completed. 4. 12 & 9mts Road : GSB & WMM layers are completed in A1,CC1,DD1&
EE1. WMM layer completed in FF,GG & HH.
Plumbing Works :Pipe laying on 12mts ,9 mts & 7.2mts road :
1. Laying of storm water pipes – 100% completed
2. Laying of sewer pipe – 100% completed
3. Manhole construction – 95% completed
![Page 9: Phase 1- Progress Report - Hub6 6-Progress_Report.pdf · Phase 1- Progress Report ... The site leveling & grading works has been completed. ... GSB & WMM layers are completed in A1,CC1,DD1&](https://reader031.vdocuments.us/reader031/viewer/2022021901/5b87f20a7f8b9a3d028c2d19/html5/thumbnails/9.jpg)
Hub 6 Chennai
Progress Photographs
![Page 10: Phase 1- Progress Report - Hub6 6-Progress_Report.pdf · Phase 1- Progress Report ... The site leveling & grading works has been completed. ... GSB & WMM layers are completed in A1,CC1,DD1&](https://reader031.vdocuments.us/reader031/viewer/2022021901/5b87f20a7f8b9a3d028c2d19/html5/thumbnails/10.jpg)
Hub 6 Chennai
Right side of Front compound wall –
Final lift to be completed by tomorrow
Front Compound Wall – Retaining wall works in progress
![Page 11: Phase 1- Progress Report - Hub6 6-Progress_Report.pdf · Phase 1- Progress Report ... The site leveling & grading works has been completed. ... GSB & WMM layers are completed in A1,CC1,DD1&](https://reader031.vdocuments.us/reader031/viewer/2022021901/5b87f20a7f8b9a3d028c2d19/html5/thumbnails/11.jpg)
Hub 6 Chennai
Front Compound Wall –Retaining wall works in progress
Left side of Front compound wall-
Final lift reinforcement works under progress
![Page 12: Phase 1- Progress Report - Hub6 6-Progress_Report.pdf · Phase 1- Progress Report ... The site leveling & grading works has been completed. ... GSB & WMM layers are completed in A1,CC1,DD1&](https://reader031.vdocuments.us/reader031/viewer/2022021901/5b87f20a7f8b9a3d028c2d19/html5/thumbnails/12.jpg)
Hub 6 Chennai
Bund cleaning in front of Phase -1 – 80% completed
![Page 13: Phase 1- Progress Report - Hub6 6-Progress_Report.pdf · Phase 1- Progress Report ... The site leveling & grading works has been completed. ... GSB & WMM layers are completed in A1,CC1,DD1&](https://reader031.vdocuments.us/reader031/viewer/2022021901/5b87f20a7f8b9a3d028c2d19/html5/thumbnails/13.jpg)
Hub 6 Chennai
Guard Room works – Shuttering and concreting under progress
![Page 14: Phase 1- Progress Report - Hub6 6-Progress_Report.pdf · Phase 1- Progress Report ... The site leveling & grading works has been completed. ... GSB & WMM layers are completed in A1,CC1,DD1&](https://reader031.vdocuments.us/reader031/viewer/2022021901/5b87f20a7f8b9a3d028c2d19/html5/thumbnails/14.jpg)
Hub 6 Chennai
7.2m road to Road – Connectivity of plumbing works connectivity in progress
ROAD - HH
RO
AD
- II