Page 1: Amelia and Dinwiddie Co. & Phase 1 Progress Report

Wireless Broadband Project

Amelia and Dinwiddie Co. & Tobacco Commission Grants

Phase 1 Progress Report

Page 2: Amelia and Dinwiddie Co. & Phase 1 Progress Report

March 2021 Phase 1 - Status Overview

Amelia

Upstream VA DatacenterFiber Interconnect / CoLocationRedundant Link to DinwiddieGBC/IDA Water TankMain Water TankFeatherstone SiloMannboro 190’ Tower (new)Fiber Infrastructure (Phase 1)Routing and Redundancy

Phase 2 Planning

Dinwiddie

Upstream VA DatacenterFiber Interconnect / CoLocationRedundant Link to AmeliaUnico Rd Water TankDinwiddie Landfill TowerNorthside 190’ Tower (new)Subcarrier Darvills Tower (CoLo)Fiber Infrastructure (Phase 1)Routing and Redundancy

Phase 2 Planning

Page 3: Amelia and Dinwiddie Co. & Phase 1 Progress Report

Dinwiddie:Interconnect & Upstream Fiber

Live: Q3 2020Pixel Factory and MBC

Page 4: Amelia and Dinwiddie Co. & Phase 1 Progress Report

Upstream and Redundant PathsBGP and OSPF to create failover network paths

Page 5: Amelia and Dinwiddie Co. & Phase 1 Progress Report

Dinwiddie: Fiber Leasing and Construction Complete

Fiber Constructed / Leased:

Landfill Segment: 17,734 ft Completed

Unico Segment: Leased Completed

Northside Segment: 3,346 ft Completed

Leased Fiber: 34.84 miles

Wireless Backhauls current and future noted with dark blue lines.

Page 6: Amelia and Dinwiddie Co. & Phase 1 Progress Report

Dinwiddie:Unico Rd Tank

Live: February 2021Status: Live, Customer Beta Testing

Remaining Construction Tasks:- None

Page 7: Amelia and Dinwiddie Co. & Phase 1 Progress Report

Unico PtMP Sectors

Page 8: Amelia and Dinwiddie Co. & Phase 1 Progress Report

Dinwiddie:Landfill Tower CoLocation

Live: March 2021Status: Live, Customer Beta Testing

Remaining Construction Tasks:- None

Antennas and Transmitters

County Compound

Page 9: Amelia and Dinwiddie Co. & Phase 1 Progress Report

Landfill PtMP Sectors

Page 10: Amelia and Dinwiddie Co. & Phase 1 Progress Report

Dinwiddie:Northside School New Tower

190’ New Built TowerDonated Steel

Est Live: June-July 2021

Current Status:Fiber Constructed Driveway ConstructedNTP AccomplishedTower Construction Starting

Simulation Photo

Driveway

Fiber

Page 11: Amelia and Dinwiddie Co. & Phase 1 Progress Report

Dinwiddie:Subcarrier Darvills CoLo

Live: Q3 2021

Status: Delayed awaiting construction

Structural Failed owner building new tower

Lease Negotiation and DrawingsAwaiting Asset Construction

Tower to be Replaced

Page 12: Amelia and Dinwiddie Co. & Phase 1 Progress Report

Dinwiddie Projected Coverage Area(Active)

Install Heights up to 60’ (may require pole installation or tree mounted CPE)

Coverages are projected software models. Need to be fine tuned based on field data and ground clutter density.

Page 13: Amelia and Dinwiddie Co. & Phase 1 Progress Report

Dinwiddie Projected Coverage Area(Phase 1 All)

Install Heights up to 60’ (may require pole installation or tree mounted CPE)

Coverages are projected software models. Need to be fine tuned based on field data and ground clutter density.

Page 14: Amelia and Dinwiddie Co. & Phase 1 Progress Report

Dinwiddie Projected Coverage Area(Phase 1 All with Survey Overlay)

Install Heights up to 60’ (may require pole installation or tree mounted CPE)

Coverages are projected software models. Need to be fine tuned based on field data and ground clutter density.

Page 15: Amelia and Dinwiddie Co. & Phase 1 Progress Report

Thank You!