NICMAR

NICMAR INSTITUTE OF CONSTRUCTION MANAGEMENT AND RESEARCH

SCHOOL OF DISTANCE EDUCATION

ASSIGNMENT

NICMAR/CODE OFFICE

1. Course No. : PGPM 33

2. Course title : Materials & Logistics Management

3. Assignment No. : 11

4. Date of Dispatch : 07-08-2012

5. Last Date of receipt : 15-08-2012

of Assignment at CODE office

Page 2: PGPM 33 _ NICMAR Assignments

ASSIGNMENT

You have been appointed as manager of materials management department of a construction

firm. The company is asking you to prepare a manual on procurement of materials. Prepare a

manual on procurement of materials by covering the following:

1. Factors to be considered for purchasing.

2. Source Selection.

3. Selection of Suppliers.

4. Scrutiny of offers.

5. Final purchase.

6. How to develop purchasing policies and procedures.

7. Formulate strategies for improving efficiency of procurement of materials department.

Page 3: PGPM 33 _ NICMAR Assignments

Name of the Project : Developing & Construction of an International

Airport 30km away from a city.

Project phases : Phase I - Landing strip of 100m width

Work Description is as follows

a) Cutting and dozing of 1,00,000cum of Earth. Average Height 0.75m.

b) Transportation of 20000cum of surplus earth from site to dumping place 3km

away from site (including spreading). Filling of 80000cum in landing strip.

c) Bringing in 3000cum of sand from 20km (Including spreading and leveling at

Site).

d) Procurement of 1,50,000Litres of Bitumen. Duration of work 30days from 60th

day of starting of work. Bitumen to be obtained from refinery at Bongaigon in

Assam. Lead time upto site is 45 days. Storage facility available at Site

50,000litres Tank.

Page 4: PGPM 33 _ NICMAR Assignments

SCOPE OF WORK & DESCRIPTION OF EQUIPMENTS CONSIDERED

SCOPE OF WORK

Work involves developing and constructing a new International Airport 30 K.M.

away from a city. This project is to be implemented in phases. In phase I, one strip of

landing of 100m width is to be constructed in 100 days. The scope of work is as

follows:

I. Earthwork

a) Cutting and Dozing of earth.

Quantity – 1,00,000 cum

Height – 0.75m

b) Filling of available soil from above

Quantity- 80,000 cum

c) Transporting, dumping, from spreading of soil at 3 km distance

Quantity- 20,000 cum

d) Filling by outside sand obtained from 20 km distance including spreading and

leveling at site.

Quantity- 3,000 cum

II. Procurement of Bitumen

a) Transport and unloading of Bitumen

Quantity- 1,50,000 litres

Page 5: PGPM 33 _ NICMAR Assignments

DESCRIPTION OF EQUIPMENTS CONSIDERED

EARTHWORK EQUIPMENTS

I) Excavators

Crawler Excavator

Crawler excavators are excavators mounted on chain crawlers which can be

used for almost all terrain and type of soil and are suitable for slushy areas also.

They have a long boom with a bucket and teeth arrangement at end for excavating

collecting and dumping/ filling earth.

These excavators have 360 degrees swing so can work in all four directions by

standing at one place only. These excavators are available in different capacity

normally used models are Ex 60, Ex 100/ Ck90/ PC 100, Ex 200/ PC 200 for

small medium and big size depending on bucket and engine capacity type.

Tyre Mounted Backhoe Excavator cum loader

These excavators have multipurpose uses like in excavation, loading,

unloading and shifting but they have limitation due to tyres and speed. These

excavators have legs which provide some grip on slopes and difcult terrains but it

can’t be used with same ease as in crawlers.

Secondly it doesn’t have swing and it can work from either front or back and as

per working side operator has to move his position. Lastly speed wise these

excavators are slower than Crawler mounted as crawler mounted models are

available in higher capacity models whereas only basic lower capacity model of

tyre mounted excavators are available.

Page 6: PGPM 33 _ NICMAR Assignments

II) DOZERS

Crawler Dozers

These are crawler mounted locomotive fitted with a dozing blade. Availability

of same is less than tractor dozers.

Tractor Dozers

These are dozers attached normal tractors easily available.

Motor Graders

These are tyre mounted special tractors with optional blade attachments

between front and rear wheels and are used mainly for finishing works after

dozing for final leveling and making super-elevation and camber etc.

III) COMPACTION EQUIPMENT

Rollers

Tandem Roller

This is a smooth wheeled roller with two rolling wheels of approximately the

same width.

Smooth Wheeled Roller

It is most commonly used roller and compaction is achieved by the weight of

the roller.

Vibro Roller

These rollers exert both static and dynamic pressures. It gives almost double

compaction of its size of non-vibratory type.

Page 7: PGPM 33 _ NICMAR Assignments

IV) TRANSPORTING EQUIPMENT

Dump Trucks

These trucks are available in different capacity and are hydraulically operated

for dumping material from rear body.

Tractor with Hydraulic Trolley

Tractors with hydraulically operated trailers are also a good options but

capacity is less so more numbers are required.

Tankers

Tankers are trucks mounted with tanks to carry liquids, gases etc. This will be

used in transporting water and bitumen to worksite. Bitumen carriers have thermal

insulation.

Page 8: PGPM 33 _ NICMAR Assignments

CALCULATION OF PER DAY WORK

Equipment Output

Main Equipment output in this type of work depends mainly on availability of

supporting equipments and dumping areas. Faster the loading, faster the transporting

and faster the unloading can be easily seen and the same cycle is repeated.

Each set of equipment shall consist of one excavator, at least three dump

trucks. Water tanker, dozer and roller can be shared with each two set of equipments.

No. of these sets can be further decided on the basis of sequence, number of days

required to complete each activity and constraints if any.

As 100m wide strip is to be constructed in 100days which include following

activities and quantities:

As 83000 cum of earth and sand, together, will cover approximately 1107 m

length of 100m wide strip considering average depth of filling as 0.75m. All this

work is to be completed in 100 days.

Excavation and dumping shall be planned to be completed in 80 days. So

required excavation per day is 1250 Cum and same is to be transported to site or

outside same day. Theoretically for this one no. excavator with 100 cum/ hour output

for 12.5 hours working seems sufficient but practically, considering cycle time of

dump trucks including time required for positioning loading etc., average output

reduces to 60 Cum / hour. In this case 2 nos. excavators for 10.41 hours will be

required which can be easily achieved even after time lapses for daily fuel filling,

maintenance, lunch and tea breaks etc.. Each excavator is to be supported by 3 dump

trucks of 10-15 cum capacity.

Page 9: PGPM 33 _ NICMAR Assignments

Cost of each equipment per day of work

a) Excavator

As per present market we can get excavator @ Rs 2,25,000/- per month

excluding cost of fuel but including operating and maintenance cost

So per day cost of hire = (Rs 225000/260 hours) x 10.41 Hours x 2 nos.

= Rs 18018/-

Per day HSD (fuel cost) = 2 no. x15 litre / hourx10.41 hourx Rs 40/ litre

= Rs 12,492/-

The total operating and fuel cost together for excavators (18018+12492)

= Rs 30510 including all charges. (a)

b) Dump Trucks

Total 6 nos. dump trucks have been considered for two sets of excavators.

Hire charges of Dump trucks = 4,000/- x 6 nos.(per day) = 24,000/-

HSD cost considering two trips of each dump truck to and fro 3km each distance will

be calculated as follows:

Distance traveled per hour = 2 Trips x (3+3) km = 12 kms

Per hour fuel consumption = 12/2.75km per litre = 4.36 liter per hour

Total HSD cost = 6 nos. x 10.41 hours x 4.36 lit/ hour x Rs 40/ litre

= Rs 10893/-

The total operating and fuel cost together for Dump trucks will be (24000+10893)

= Rs 34893 including all charges.(b)

Page 10: PGPM 33 _ NICMAR Assignments

c) Dozer

Hire charges of Dozer = 1,50,000 /260 Hours x 10.41 Hours

= Rs 6,006/-

Per day HSD (fuel cost) = 15 litre / hourx10.41 hourx Rs 40/ litre

= Rs 6,246/-

The total operating and fuel cost together for Dozer will be (6006+6246)

= Rs 12252 including all charges.(c)

d) Grader

Per day cost of hire = (Rs 225000/260 hours) x 10.41 Hours x 1 nos.

= Rs 9009/-

Per day HSD cost = 1 no. x13 litre / hourx10.41 hourx Rs 40/ litre

= Rs 5,413/-

The total operating and fuel cost together for grader will be (9009+5413)

= Rs 14422 including all charges(d)

e) Roller

Per day cost of hire = (Rs 120000/260 hours) x 10.41 Hours x 1 nos.

= Rs 4805/-

Per day HSD cost = 1 no. x 8 litre / hourx10.41 hourx Rs 40/ litre

= Rs 3331/-

The total operating and fuel cost together for roller will be (4805+3331)

= Rs 9136 including all charges(e)

Page 11: PGPM 33 _ NICMAR Assignments

f) Water Tanker

Water Tankers can be either hired or direct water quantity can be paid to supplier.

Considering MDD as 1.9 and 11% OMC and natural moisture content as 6%

we need balance 5% water quantity per day as follows:

= 1250 cum x 1.9 x (11-6)%x 1000 litres

= 1,18,750/-

Considering cost of water as 7 paise per litre including filling at source ,

transport and unloading at site cost of water required per day= 118750 x 0.07

= 8313/- including all charges(f)

So total cost of excavation and filling in landing strip/ disposing in 3km away

work per day will be (a)+(b)+(c)+(d)+(e)+(f)= Rs 1,09,526/-

Per unit cost will be = 109526/1250 Cum = Rs 88 per cum

Similarly for bringing in 3000 cum sand combination of excavator and tippers to be

worked out as follows:

Considering time for positioning dumper = 2 minutes

Filling by excavator = 6 minutes

Turning and moving out = 2 minutes

Total time consumed in filling one dumper = 10 minutes

Minimum required dumpers 6 nos. per hour and first dumper should come back

after 50 minutes.

Distance of 20 km in loaded condition will be traveled in 40 minutes at a speed

of 30km/ hour and same distance will be covered in 30 minutes at a speed of 40km/

hour while returning. Say 10 minutes more will be spent in turning and unloading. So

Page 12: PGPM 33 _ NICMAR Assignments

first dumper will be returning back to excavator in 80 minutes whereas excavator will

be free after 60 minutes it means it can also load two more dumpers before starting

second cycle of loading.

It is obvious from above that 8 dumpers will be required with an excavator.

Cost of excavator per day = Rs 15255 including all charges. (a)Dumpers

Cost of Dumpers per day

Hire charges of Dump trucks per day = 4,000/- x 8 nos.

= 32,000/-

HSD cost considering Nine trips of each dump truck to and fro 20km each distance

will be calculated as follows:

Distance traveled per hour = 9 Trips x (20+20) km

= 360 kms

Per dumper fuel consumption = 360/2.75km per litre

= 131 liter per day

So total HSD cost for Dump trucks = 8 nos. x 131 litre x Rs 40/ litre

= Rs 41920/-

The total operating and fuel cost together for Dump trucks will be (30000+41920)

= Rs 71920 including all charges (a)

(b) Dozer

Hire charges of Dozer = 1,50,000 /260 Hours x 10.41 Hours

= Rs 6,006/-

Per day HSD (fuel cost) = 15 litre / hourx10.41 hourx Rs 40/ litre

= Rs 6,246/-

Page 13: PGPM 33 _ NICMAR Assignments

The total operating and fuel cost together for Dozer will be (6006+6246)

= Rs 12252 including all charges (b)

(c) Grader

Per day cost of hire = (Rs 225000/260 hours) x 10.41 Hours x 1 nos.

= Rs 9009/-

Per day HSD (fuel cost) = 1 no. x13 litre / hourx10.41 hourx Rs 40/ litre

= Rs 5,413/-

The total operating and fuel cost together for grader will be (9009+5413)

= Rs 14422 including all charges (c)

(d) Roller

Per day cost of hire = (Rs 120000/260 hours) x 10.41 Hours x 1 nos.

= Rs 4805/-

Per day HSD (fuel cost) = 1 no. x 8 litre / hourx10.41 hour x Rs 40/ litre

= Rs 3331/-

The total operating and fuel cost together for roller will be (4805+3331)

= Rs 9136 including all charges (d)

So total cost of bringing and filling sand in landing strip from 20km distance

away work per day will be (a)+(b)+(c)+(d) = Rs 1,22,985/-

Per unit cost will be = 122985/625 Cum = Rs 197 per cum

Page 14: PGPM 33 _ NICMAR Assignments

SECOND BEST ALTERNATIVE

Second best alternative is use of J.C.B. tyre mounted backhoe loader cum

excavators and tractor levelers and tractor dozers but in this case J.C.B. has less

bucket capacity and ultimately almost half the speed of work. Similarly tractors have

less speed and capacity . It will be advisable to use combination of crawler and tyre

mounted excavators. But in no case speed of work as achieved in alternative one can

be achieved.

Hence in all respect second best alternative is use of combination of crawler

and tyre mounted excavators and dump trucks even of smaller capacity but numbers

to increase to maintain speed of work.

Page 15: PGPM 33 _ NICMAR Assignments

PROCUREMENT OF BITUMEN

Total requirement of Material = 1,50,000 litres

Duration of work = 30 days from 60th day of starting of work

Source = Maharastra

Lead time = 45 Days

Storage facility = 50,000 litres

Total consumption in 30days will be 150000 litres. Hence considering 5000

litres per day after 59th day.

Consider cost of each litre of bitumen is Rs 20/- and each cost of ordering is Rs

1000/- and cost of storage per day per litre is Rs 1/-.

EOQ =Under root ( (2AS)/(Ph))=Under root ((2x 150000x1000)/(20x0.05))= 17321L

So there should be 8 orders of 17321 litres and 1 order of 11432 litres.

Check for economic order quantity

Consider as above cost of material = 30,00,000/-

Ordering cost = 9000/-

Inventory cost assuming minimum 8500 litres = 8500/-

Total cost = 3017500/-

Page 16: PGPM 33 _ NICMAR Assignments

Consider another case with 10 orders of 15000 litres

Consider as above cost of material = 30,00,000/-

Ordering cost = 15000/-

Inventory cost assuming minimum 7500 litres = 7500/-

Total cost = 30,22,500/-

Consider another case with 5 orders of 30000 litres

Consider as above cost of material = 30,00,000/-

Ordering cost = 5000/-

Inventory cost assuming minimum 15000 litres = 15000/-

Total cost = 30,20,000/-

1st order date at start of work = 0 and date of last order shall be such that there is no

shortage of bitumen at end.

Safety level to be maintained is as follows:

1st order 0-45 days = 17321 litres

2nd order 1-46 days = 17321 litres

3rd order 2-47 days =11432 litres

Total stock on 59th day = 46074 litres

Page 17: PGPM 33 _ NICMAR Assignments

This can be easily understood by following table.

OrderNo.

OrderDay

WorkDay

OpeningStock Received Consumed

ClosingStock

1 0 45 0 17321 0 173212 1 46 17321 17321 0 346423 2 47 34642 11432 0 46074

60 46074 0 5000 4107461 41074 0 5000 3607462 36074 0 5000 31074

4 18 63 31074 17321 5000 4339564 43395 5000 3839565 38395 5000 33395

5 21 66 33395 17321 5000 4571667 45716 5000 4071668 40716 5000 3571669 35716 5000 30716

6 25 70 30716 17321 5000 4303771 43037 5000 3803772 38037 5000 33037

7 28 73 33037 17321 5000 4535874 45358 5000 4035875 40358 5000 3535876 35358 5000 30358

8 32 77 30358 17321 5000 4267978 42679 5000 3767979 37679 5000 3267980 32679 5000 27679

9 36 81 27679 17321 5000 4000082 40000 5000 3500083 35000 5000 3000084 30000 5000 2500085 25000 5000 2000086 20000 5000 1500087 15000 5000 1000088 10000 5000 500089 5000 5000 090 0 0

Page 18: PGPM 33 _ NICMAR Assignments

Proper arrangement of required size of tankers with heating facilities shall be

ensured. Storage tanks shall have proper insulation and heating facility also.

Total cost of transportation will be @ 1.6 per MT per Kilometer and considering 2500

km distance from one side to and fro cost as per oil industry norms shall be Rs 3.2 per

MT per KM.

Hence total cost of Bitumen material = 150000 litre x 20/-

= Rs 30,00,000/-

Cost of transportation = 150000 litre x 2500x (2 x1.6/1000)x 1.04 Kg/cum

= Rs 6,24,000/-

Ordering cost = 9000/-

Inventory cost assuming minimum 8500 litres = 8500/-

Total cost = 3642000/-

Hence Total cost of Project will be as follows:

Earthwork cost = 109526x 80 days = Rs 87,62,080/-

Sand filling cost = 1,22,985 x 5 days = Rs 6,14,925/-

Bitumen procurement = Rs 36,42,000/-

Total = Rs 1,30,19,005/-

Contractor’s Profit = (13019005*15%) = 1952851/-

Therefore Total Project Cost = 14971856/-

As per above plan work shall be completed in given time schedule however

some standby and back-up equipment will be required which will incur additional

cost.