pcapp update 28 may 2014

8
PCAPP Update 28 May 2014 Presented to: Citizens’ Advisory Commission Presented by: Paul Dent Operational Readiness Review (ORR) Manager

TRANSCRIPT

Page 1: PCAPP Update 28 May 2014

PCAPP Update

28 May 2014

Presented to:

Citizens’ Advisory Commission

Presented by:

Paul DentOperational Readiness Review (ORR) Manager

Page 2: PCAPP Update 28 May 2014

What is an ORR?

Per ACWA Policy Statement 26, “ORRs will be conducted to verify the readiness of the ACWA Pilot Plants to safely begin operations involving chemical agents, explosives, or other highly hazardous materials.” The ORR process is used to validate

that PCAPP “plant, paper, and people” collectively meet the required criteria to allow a new operation to begin.

PCAPP ORR process is led by the system-contractor (SC) to support a declaration of readiness.

ACWA provides ORR oversight; independent validation is used to support the SC’s declaration of readiness.

Stakeholders are invited to observe the ORR process.

2

Plant

People Paper

Achieve Readiness – by Responsible Managers

Validate Readiness – by ORR Board

Declare Readiness – by Project Manager

Accept Readiness – by ACWA

Page 3: PCAPP Update 28 May 2014

5

ORR Major Milestones

NOT YET STARTED

IN PROGRESS

COMPLETE

* Major Milestones per the PCAPP Baseline IMS.

PCAPP goal is to declare readiness 60 days sooner

* Incremental Readiness Assessments will overlap –

they are not strictly sequential

1

7

9

8

4

3

2

6

14

15

16

Lab Dilute Agent Operations Mini-ORR OCT 2013 – 52 Criteria

Boiler Ignition Readiness Assessment DEC 2012 – 19 Criteria

* Mile

stones

for Incre

mental R

eadiness

Assessm

ents

Leading to

Initia

l Agen

t Opera

tions

Integrated Operations Demonstrations (IODs) JUN 2015 – 11 Criteria

Agent Entry Readiness and Agent Containment and Confinement Controls SEP 2014 – 49 Criteria

ERB Provisional Operations SEP-2014 – 75 Criteria

APB Provisional Operations NOV 2014 – 32 Criteria

Contingency Training Readiness/Crew Certification JAN 2015 – 59 Criteria

Security/Surety (Soft-Lockdown) Readiness Review FEB 2015 – 16 Criteria

BTA Provisional Operations NOV 2014 – 13 Criteria

Yard Provisional Operations JUL-2014 – 111 Criteria

Initial Agent Operations - Readiness Declared JUL 2015 – 6 Criteria

ACWA Readiness Endorsement SEP 2015

Training Facility Available for Practical Factors – Readiness Check JUN 2014 Forecast

Pre-Systemization Complete NOV 2013

Training Facility Available for TAT – Readiness Check JAN 2014

10

11

13

12Environmental Readiness FEB 2015 – 14 Criteria

3

Page 4: PCAPP Update 28 May 2014

Scope of ORR for Initial Agent Operations

Criteria are defined in the Initial Agent Operations ORR procedure

― Defines ORR criteria that reflect project requirements

― Summarizes proposed Integrated Operations Demonstrations (IODs)

― Include normal and off-normal exercises to be performed

― Evaluation teams will observe and critique each demonstration

4

# Functional Area # of criteria

1 Acquisitions 102 Emergency Preparedness 143 Engineering 264 Environmental 145 Government Interfaces 136 Human Resources 37 Information Systems & Technology 58 Laboratory 219 Maintenance 11

10 Medical 2111 Office and Administrative Services 612 Operations 4913 Operations Support 2214 Pilot Test Preparedness 315 Plant Support (Treaty) 816 Project and Plant Management 1517 Quality Assurance/Quality Control 718 Safety 3819 Security 1320 Start-up/ Systemization 5021 Surety 722 Training 1523 Work Control 15

386

Each of the four shifts will perform IODs for readiness validation.

Upon successful completion of IODs and closeout of required findings, System Contractor will declare readiness.

Page 5: PCAPP Update 28 May 2014

Criteria Review Resources Engaged

Chris Midgett – Chair of Executive Board:― Brings extensive experience in managing chem-demil work

― Liaison to ACWA and stakeholder executive functions

Sierra Lobo, Inc. – Independent engineering resource― Testing & evaluation expertise

― Clients include NASA & Department of Defense

Blue Grass Subject Matter Experts (SMEs): ― Will use BGCAPP SMEs for independent review

― Bring an excellent understanding of standards & recent operating experience

― ORR experience provides benefits to both projects

5

Page 6: PCAPP Update 28 May 2014

IAO ORR Status

ORR work will be paced by Systemization work.

Data as of 22-May-2014

ORR Documents TotalRequired

Issued for Completion

Board Reviewed Board Accepted

Affidavits 386 135 55 34

CRADS 386 15 0 0

6

Page 7: PCAPP Update 28 May 2014

ORR Oversight

Review ORR documents, attend Board meetings, and observe demonstrations

Provide immediate feedback on ORR issues, process, and documentation

Provide independent validation of 20% of ORR criteria in accordance with their oversight procedure

Coordinate stakeholder involvement in ORR process

Lead a monthly meeting with representatives from the Blue Grass project, Pueblo Chemical Depot, and stakeholders to communicate ORR status, schedule, issues, and lessons learned

ACWA representatives also assess the System Contractor’s readiness for initial agent operations:

7

Page 8: PCAPP Update 28 May 2014

Questions?

8