1 May 2014 Construction Update

TRANSCRIPT

1

May 2014 Construction Update

2

May 2014 Construction Update

3

May 2014 Construction Update

4

May 2014 Construction Update

Change House

Environmental

Enclosure #1

Environmental

Enclosure #3

Laboratory

PCAPP EDS Site Overview

5

PCAPP EDS Safety

As of April 30, the PCAPP EDS project staff has accomplished:

20 Safe Work Days

2,497 Safe Work Hours

6

Workers smooth concrete on May 8 after the first concrete slab pour for Environmental Enclosure #1.

PCAPP EDS ConstructionStaffing –26 employees

Construction

Workers: 6

–Subcontractor personnel – 20

A worker sets screws for the forms in preparation for the concrete slab pour for Environmental Enclosure #2

7

NOT STARTED

IN PROGRESS (POTENTIAL ISSUES)

IN PROGRESS (NO ISSUES)

COMPLETE

Key Milestone

DESIGN START (DEC 2013)

SITE DESIGN COMPLETE (MAR 2014)

CONSTRUCTION STARTS (27 MAR 2014)

CONSTRUCTION COMPLETE (OCT 2014)

E-DAY – EDS START OF

AGENT OPERATIONS (OCT 2014)

CONSTRUCTION CONTRACT AWARD (NOV 2013)

PEO ACWA PROGRAMMATIC DECISION TO SELECT EDS TECHNOLOGY (APR 2013)

PCAPP EDS Schedule(JPME-P Working Schedule)

CONCRETE POURS BEGIN (17 APR 2014)

MODULES (COMMAND POST, CHANGE HOUSE, TREATY TRAILER, ETC.)

BEGIN TO ARRIVE (MAY 2014)

MILITARY FABRIC STRUCTURES FOR EDS ENVIRONMENTAL

ENCLOSURES ARRIVE (JUN 2014)

ARRIVAL OF FIRST EDS UNIT (AUGUST 2014)

8

PCAPP EDS Permitting Progress

NOT STARTED

IN PROGRESS (POTENTIAL ISSUES)

IN PROGRESS (NO ISSUES)

COMPLETE

Key Milestone

CLASS III PERMIT MODIFICATION SUBMITTED TO CDPHE (24 OCT 2013)

STATE APPROVAL OF TEMPORARY AUTHORIZATION

FOR CONSTRUCTION (7 MAR 2014)

SITE CONSTRUCTION START (27MAR 2014)

APPROVAL OF CLASS III MODIFICATION

FOR OPERATIONS (SEP 2014)

E-DAY – EDS START OF AGENT

OPERATIONS (OCT 2014)

PCD RCRA PERMIT RENEWED (JAN 2014)

SUBMIT CERTIFICATE OF DESIGNATION (CD) (DEC 2013)

PEO ACWA PROGRAMMATIC DECISION TO SELECT EDS TECHNOLOGY (APR 2013)

APPROVAL OF CD FOR OPERATIONS

(OCT 2014)

COUNTY APPROVAL OF TEMPORARY AUTHORIZATION

FOR CONSTRUCTION (26 MAR 2014)

RECORD OF ENVIRONMENTAL CONSIDERATION (DEC 2013)

9

Site Progress

10

Processing dirt, the job of mixing the fill with water under the weight of heavy equipment, makes for better compaction when it’s later moved into the enclosures as a base for the slabs that will be poured.

Site Progress

11

Measure twice, dig once. A worker confirms the depth of the trench being carved out. This for the pipes that will be part of the fire line that will serve the EDS site when complete.

Questions?

12

Acting Principal Deputy Assistant Secretary of Defense Dr. A. Tom Hopkins (third from left), Program Executive Officer ACWA Conrad Whyne (second from left) and PCAPP Project Manager Rick Holmes, listen to Jake Torres explain the munition process in the Vapor Containment Room.