overview of us contributions to the iter steady state electrical

15
Overview of US In-Kind Contributions to the ITER Steady State Electrical Network (SSEN) US ITER 1040100-AD0002-R01

Upload: haxuyen

Post on 04-Feb-2017

217 views

Category:

Documents


2 download

TRANSCRIPT

Overview of

US In-Kind Contributions to the ITER

Steady State Electrical Network (SSEN)

US ITER 1040100-AD0002-R01

US ITER 1040100-AD0002-R01 Page 2

TABLE OF CONTENTS

1   INTRODUCTION .................................................................................................................. 3  

2   BACKGROUND ..................................................................................................................... 4  

3   PROCUREMENT PLAN....................................................................................................... 6  

4   SCHEDULE........................................................................................................................... 15  

US ITER 1040100-AD0002-R01 Page 3

1 INTRODUCTION

The International Thermonuclear Experimental Reactor1 (ITER) is a project now underway in France to construct a device that will demonstrate nuclear fusion power at a powerplant-relevant scale. The international partners, including the US, are each responsible for contributions of resources and equipment to the project.

In the area of AC power distribution, two subsystems are defined, namely the Steady State Electrical Network (SSEN) providing power to the conventional plant loads, and the Pulse Power Electrical Network (PPEN) proving power to the pulsed experimental loads. The design of both the SSEN and PPEN is being developed by the “Domestic Agency” (DA) of the European Union (EU), managed by the “Fusion for Energy2”, (F4E) organization. The EU DA is also responsible for the emergency diesel generator power system, most of the power cabling, and the installation of the entire AC distribution system. The remaining SSEN materials and supplies are to be contributed by the DAs of the United States (US) and the EU and the PPEN materials and supplies by China (CN).

The final design of the SSEN components was completed in July 2012. The bill of materials assignments to the US and EU have been decided and follow the intent of the ITER Agreement whereby the US provides 75% and the EU 25%. The Procurement Arrangement (PA) document, a covenant between the central ITER International Organization (IO) and the US DA with respect to the equipment it supplies, was signed in September 2012, permitting the US DA SSEN procurement activities to commence.

The US DA is overseen by the US Department of Energy which has assigned management responsibility to the US ITER Project Office3 (USIPO) hosted by the Oak Ridge National Laboratory (ORNL). The work scope associated with the SSEN is assigned to the Princeton Plasma Physics Laboratory (PPPL) and is led by its Work Breakdown Structure (WBS) manager who is responsible for the work described herein.

1 http://www.iter.org/default.aspx

2 http://fusionforenergy.europa.eu/

3 https://www.usiter.org/

US ITER 1040100-AD0002-R01 Page 4

PPPL has issued a contract to the URS Corporation to provide Engineering Support Subcontractor (ESS) services related the specification, procurement, manufacturing oversight, and QC activities associated with the SSEN procurements.

The PPPL Procurement Division will issue solicitations, lead the evaluation of offers, negotiate with selected suppliers, and place and administer all contracts for the purchase of the subject equipment. The ESS will assist in this process.

The ITER IO will utilize a Global Transport and Logistics Service (GTLS) for transport of all equipment from the manufacturers’ facilities to the final destination. The US DA will engage and pay for the GLTS services for shipping and related items such as insurance, tariffs, etc., for each shipment.

The USIPO WBS Manager is responsible for the procurement of the equipment as described herein:

Mr. Charles Neumeyer

Princeton University, Plasma Physics Laboratory

P.O. Box 451

Princeton, NJ 08540

(609) 243-2159

[email protected]

2 BACKGROUND

ITER will receive AC power at 400kV, 50Hz from the French grid operator “Réseau de transport d’electricité” (RTE). A recent photograph of the new RTE substation called “Prionnet”, now energized, is given in Figure 1. The SSEN switchyard will be installed in the area immediately adjoining this substation.

US ITER 1040100-AD0002-R01 Page 5

Figure 1 – ITER Construction Site Showing RTE Substation “Prionnet”

A one-line diagram of the SSEN in given in the attached reference drawing4, and a simplified version is shown in Figure 2.

The SSEN is subdivided into four power feeds. Two of the feeds consist of a 400kV substation transformer, 22kV distribution, and 6.6kV distribution. The other two consist of a 400kV substation transformer, 22kV distribution to load centers (LC), and 22kV distribution, which is transformed to 400V distribution for safety relevant (SR) and investment protection (IP) loads, which can also be energized using diesel generators (G). The 22kV bus bars can be interconnected as indicated under contingency situations to improve reliability of service. Where Figure 2 differs from the reference drawing, the latter shall take precedence.

4 ITER Drawing entitled “ONE-LINE GENERAL SSEN”, filename “SSEN_One_Line_1.pdf””

US ITER 1040100-AD0002-R01 Page 6

Figure 2 - Steady State Electrical Network (SSEN)

All of the SSEN equipment will be built to IEC standards for 50Hz operation.

3 PROCUREMENT PLAN

As shown in Table 3-1 a total of sixteen (16) procurement groups have been identified based on the full list of items specified in the bill of materials (B/M) given Table 3-2. It is planned that each of the procurement groups will be procured via an individual contract to an individual supplier, although some bundling is possible.

PPPL will prepare, in conjunction with the ESS, purchasing specifications for each of the procurement actions listed in Table 3-1. Each procurement action will be initiated by the issuance of a Pre-Solicitation Notice, followed by a Request for Proposal. Both of these notices will be issued on the Federal Business Opportunities (http://www.fedbizopps.gov) web site. Related information is also available at the PPPL Procurement web site (http://procurement.pppl.gov/Procurement%20Opportunities.HTM). PPPL will follow US DOE Procedures in the bid evaluation and contract award process.

US ITER 1040100-AD0002-R01 Page 7

Table 3-1 – Procurement Groups

Group No. Title B/M Item(s)

1 HV Circuit Breakers 1.1

2 HV Switches 1.2,1.3

3 HV Surge Arresters 1.4

4 HV Current Transformers 1.5

5 HV Potential Transformers 1.6

6 HV Control & Protection 1.7,1.8

7 HV Substation Hardware 1.9

8 HV Substation Transformers 2.1,2.2

9 22kV Switchgear 3.1 through 3.7

10 6.6kV Switchgear 4.1 through 4.19, 8.2,8.3

11 Reactive Power Compensators 3.8,4.20 through 4.26

12 Power Transformers 5.1 through 5.3, 8.4

13 UPS 8.6

14 LV Distribution & Sub-distribution Panels 8.5,8.7

15 DC Distribution 8.8,8.9

16 Earthing Resistors 2.3,5.4

US ITER 1040100-AD0002-R01 Page 8

Table 3-2 - Bill of Materials for US Contribution to SSEN

No. Components Basic parameters Total Base + Spares

Quantity

Procurement Group

1 High Voltage Switchyard

Description

1.1 Main Incomer Circuit breaker SF6 technology, 420kV rated voltage, 4 kA / 40 kA / 100 kA, (operating/breaking/making current), outdoor, one (1) pole

12 1

1.2 Line Disconnector 420kV rated voltage, 4 kA operating current, outdoor

12 2

1.3 Earthing Switch 420kV rated voltage, 63kA withstand short-circuit current, outdoor

24 2

1.4 Surge Arrester 378kV rated voltage, 20 kA peak, outdoor

12 3

1.5 Current Transformer

420kV rated voltage, outdoor, ratio, burden and accuracy: 1000 / 5-5 A, 50-50 VA, 5P40; 3000/5 A, 50 VA, 5P20; 120/5 A, 20VA, Cl0.2; 120/5 A, 20VA, Cl0.2s

12 4

1.6 Voltage Transformer

Outdoor, ratio: 400/sqrt(3) : 0.1/ sqrt(3) -0.1/ sqrt(3) kV-0.1/ sqrt(3) 3 kV, Burden: 30-30-30 VA Accuracy: 0.2-0.5 3P-0.5 3P

12 5

1.7 Control & Protection cubicle

Transformer and bay protection panel, bay control and monitoring panels, control panels, protective relays and communication equipment, Automatic Voltage Regulator (AVR) and tap changer controller step down transformer

4 6

US ITER 1040100-AD0002-R01 Page 9

No. Components Basic parameters Total Base + Spares

Quantity

Procurement Group

1.8 Auxiliary services 400/230 VAC and 230 VAC UPS Distribution Systems, 110 VDC and 48 VDC Distribution Systems

4

1.9 Electrical connection

420 kV rated voltage insulators, cable link, OHL conductors, ancillary connection equipment

12 7

2 Main Step-Down Transformers

2.1 Step-Down Transformer

400 ± 10 x 1.5%/23.1 kV,Oil immersed type, 60/75 MVA (ONAN/ONAF), Zcc=17 % (BASE 75 MVA), YNyn0

4 8

2.2 Voltage Tap Changer

On-load tap changer, 21 steps, ±15% voltage regulation, primary winding operation

4 8

2.3 Earthing Neutral Resistor

Rated voltage 23.1/ sqrt(3) kV, rated s.c. current 500 A (10 s), outdoor

4 16

3 22kV Distribution

3.1 Main incomer Rated Voltage: 24 kV Vacuum/SF6 circuit breaker 2.5 kA/25 kA/63 kA (operating/breaking/making capacity)

4 9

3.2 Main Busbars Rated Voltage: 24 kV, current ratings: 2.5 kA/25 kA/63 kA (operating/breaking/making capacity)

8 9

3.3 Couplers (for Main Busbars)

Rated Voltage: 24 kV Vacuum/SF6 circuit breaker 2.5 kA/25 kA/63 kA (operating/breaking/making capacity)

8 9

US ITER 1040100-AD0002-R01 Page 10

No. Components Basic parameters Total Base + Spares

Quantity

Procurement Group

3.4 Feeder (for Main Busbars)

Rated Voltage: 24 kV Vacuum/SF6 circuit breaker 1250 A/25 kA /63 kA (operating/breaking/making capacity)

4 9

3.5 Feeder (for Main Busbars)

Rated Voltage: 24 kV Vacuum/SF6 circuit breaker 630 A/25 kA /63 kA (operating/breaking/making capacity)

36 9

3.6 Feeder (reactive compensation) (for Main Busbars)

Rated Voltage: 24 kV Vacuum/SF6 circuit breaker 630 A/25 kA /63 kA (operating/breaking/making capacity)

4 9

3.7 Feeder (spare) (for Main Busbars)

Rated Voltage: 24 kV Vacuum/SF6 circuit breaker

15 9

3.8 Reactive power compensation (for Main Busbars)

24 kV, 2400 kVar 4 11

4 Medium Voltage Power Centres (Class IV)

4.1 Main Busbars (type 1)

Rated Voltage: 7.2 kV, current ratings:3.15kA/ 50kA/125kA, (operating/breaking/making current)

4 10

4.2 Main incomer (for main Busbars type 1)

Rated Voltage: 7.2 kV Vacuum/SF6 circuit breaker: 3.15 kA/50 kA/ 125 kA (operating/breaking/making current)

4 10

4.3 Couplers (for main Busbars type 1)

Rated Voltage: 7.2 kV Vacuum/SF6 circuit breaker: 3.15 kA/50 kA/ 125 kA (operating/breaking/making current)

3 10

4.4 Motor (for main Busbars type 1)

Rated Voltage: 7.2 kV Vacuum/SF6 circuit breaker: 630 A/50 kA/ 125

40 10

US ITER 1040100-AD0002-R01 Page 11

No. Components Basic parameters Total Base + Spares

Quantity

Procurement Group

kA (operating/breaking/making current)

4.5 Feeder (for main Busbars type 1)

Rated Voltage: 7.2 kV Vacuum/SF6 circuit breaker: 1250 A/50 kA/ 125 kA (operating/breaking/making current)

1 10

4.6 Feeder (for main Busbars type 1)

Rated Voltage: 7.2 kV Vacuum/SF6 circuit breaker: 1600 A/50 kA/ 125 kA (operating/breaking/making current)

3 10

4.7 Feeder spare (for main Busbars type 1)

Rated Voltage: 7.2 kV Vacuum/SF6 circuit breaker

16 10

4.8 Main Busbars (type 2)

Rated Voltage: 7.2 kV, current ratings: 2kA/31.5kA/ 80kA, (operating/breaking/making current)

4 10

4.9 Main incomer (for main Busbars type 2)

Rated Voltage: 7.2 kV Vacuum/SF6 circuit breaker: 2 kA/31.5 kA/ 80 kA (operating/breaking/making current)

4 10

4.10 Couplers (for main Busbars type 2)

Rated Voltage: 7.2 kV Vacuum/SF6 circuit breaker: 2 kA/31.5 kA/ 80 kA (operating/breaking/making current)

2 10

4.11 Motor (for main Busbars type 2)

Rated Voltage: 7.2 kV Vacuum/SF6 circuit breaker: 630 A/31.5 kA/ 80 kA (operating/breaking/making current)

30 10

4.12 Feeder (for main Busbars type 2)

Rated Voltage: 7.2 kV Vacuum/SF6 circuit breaker: 800 A/31.5 kA/ 80 kA (operating/breaking/making current)

2 10

US ITER 1040100-AD0002-R01 Page 12

No. Components Basic parameters Total Base + Spares

Quantity

Procurement Group

4.13 Feeder (for main Busbars type 2)

Rated Voltage: 7.2 kV Vacuum/SF6 circuit breaker: 1000 A/31.5 kA/ 80 kA (operating/breaking/making current)

2 10

4.14 Feeder spare (for main Busbars type 2)

Rated Voltage: 7.2 kV Vacuum/SF6 circuit breaker

12 10

4.15 Main Busbars (type 3)

Rated Voltage: 7.2 kV, current ratings: 630 A/16 kA/40 kA, (operating/breaking/making current)

4 10

4.16 Main incomer (for main Busbars type 3)

Rated Voltage: 7.2 kV Vacuum/SF6 circuit breaker: 630 A/16 kA/40 kA (operating/breaking/making current)

4 10

4.17 Couplers (for main Busbars type 3)

Rated Voltage: 7.2 kV Vacuum/SF6 circuit breaker: 630 A/16 kA/40 kA (operating/breaking/making current)

4 10

4.18 Feeder (for main Busbars type 3)

Rated Voltage: 7.2 kV Vacuum/SF6 circuit breaker: 630 A/16 kA/40 kA (operating/breaking/making current)

4 10

4.19 Feeder spare (for main Busbars type 3)

Rated Voltage: 7.2 kV Vacuum/SF6 circuit breaker

4 10

4.20 Power factor correction units

Rated Voltage: 7.2 kV, Rated Reactive Power 5.2Mvar, automatic voltage controller.

1 11

4.21 Power factor correction units

Rated Voltage: 7.2 kV, Rated Reactive Power 10Mvar, automatic voltage controller.

2 11

4.22 Power factor correction units

Rated Voltage: 7.2 kV, Rated Reactive Power 2.3Mvar, automatic voltage controller.

2 11

US ITER 1040100-AD0002-R01 Page 13

No. Components Basic parameters Total Base + Spares

Quantity

Procurement Group

4.23 Power factor correction units

Rated Voltage: 7.2 kV, Rated Reactive Power 1.5Mvar, automatic voltage controller.

2 11

4.24 Power factor correction units

Rated Voltage: 7.2 kV, Rated Reactive Power 8.4Mvar, automatic voltage controller.

1 11

4.25 Power factor correction units

Rated Voltage: 7.2 kV, Rated Reactive Power 4.8Mvar, automatic voltage controller.

1 11

4.26 Power factor correction units

Rated Voltage: 7.2 kV, Rated Reactive Power 7.1Mvar, automatic voltage controller.

1 11

5 Power Transformers (Class IV)

5.1 Main power transformer (type 1)

22±2.5±5%/6.6 kV, Oil immersed, 30/35 MVA (ONAN/ONAF), Zcc= 10 %, Dyn11

4 12

5.2 Main power transformer (type 2)

22±2.5±5%/6.6 kV, Oil immersed, 16/20 MVA (ONAN/ONAF), Zcc= 10 %

4 12

5.3 Emergency distribution transformers

22±2.5±5%/6.6 kV, Oil immersed, 3.75/5 MVA (ONAN/ONAF), Zcc= 7 %, Dyn11

4 12

5.4 Earthing Neutral Resistor

Rated voltage 6.6/Ö3kV, rated s.c. current 500 A (10 seconds), outdoor

12 16

8 Investment Protection Emergency Distribution

US ITER 1040100-AD0002-R01 Page 14

No. Components Basic parameters Total Base + Spares

Quantity

Procurement Group

8.2 MV Feeder Rated Voltage: 7.2 kV, Vacuum/SF6 circuit breaker, ratings 0.63/16/40kA (operating/breaking/making current), current transformer 630/1A-10VA-5P20, 3 voltage transformers, protective relays

14 10

8.3 MV Distribution Busbars

Rated Voltage: 7.2 kV, current ratings:630/16/40kA

2 10

8.4 Distribution transformer

22/0.4kV – 1.6 MVA Dry transformer, indoor, Short circuit impedance: 6%

8 12

8.5 LV Distribution board

LV distribution board, 2500 nominal current, with a main incomer, a coupling and all distribution feeders (circuit breakers). Short circuit rated current 65 Ka

8 14

8.6 UPS Rated total power 260kVA, batteries autonomy 1h, static by-pass, long life batteries (10 years) N+1 redundancy

8 13

8.7 LV Sub-Distribution panel

LV sub-distribution panel, nominal current 120 A, equipped with feeders, indoors, Short circuit rated current 25kA

100 14

8.8 DC distribution DC distribution cubicle including AC/DC converters, batteries (4h autonomy) and DC distribution. DC voltage output 110V, rated DC current 3300Ah

4 15

8.9 DC distribution DC distribution cubicle including AC/DC converters, batteries (4h autonomy) and DC distribution. DC voltage output 48V

4 15

US ITER 1040100-AD0002-R01 Page 15

4 SCHEDULE

Although the ITER 1st plasma milestone is not scheduled until 2020, parts of the SSEN are needed much earlier to support the need for site power as the construction, installation, and commissioning activities progress. For this reason the US plans to issue “Request for Proposals” (RFP) for all of the procurement actions during calendar year 2012.