offshore wind farms - can the industry deliver (again) bruce valpy october 2010
TRANSCRIPT
Offshore Wind Farms:
can the wind industry deliver (again)?
Bruce Valpy
Joseph Swan Memorial Lecture, 19 October 2010
2© BVG Associates 2010
All the below available online. BVG Associates
contactable via [email protected] to
request use of any material.
3© BVG Associates 2010
1. Wind industry introduction
• Facts and figures
2. History lesson
• Meet the ancestors
• Famous battles
3. Anatomy lesson
4. Geography lesson
5. The future: “Can do”
Today
4© BVG Associates 2010
1. Wind industry introduction
• Facts and figures
2. History lesson
• Meet the ancestors
• Famous battles
3. Anatomy lesson
4. Geography lesson
5. The future: “Can do”
Today
5© BVG Associates 2010
12
History Lesson 1:
meet the ancestors
13© BVG Associates 2010
History - Meet the Ancestors 1000BC
Nile Delta
First
windmills
© BVG Associates 2010 14
Meet the Ancestors
500BC
Persia
Panemones
common
Pumping
water
© BVG Associates 2010 15
Meet the Ancestors
Crete
Pumping water
and grinding
1000AD
© BVG Associates 2010 16
Meet the Ancestors
Jack & Jill
in Sussex
First UK windmill
in Weedly, Yorkshire
in 1185
1821
17© BVG Associates 2010
1800’s
US
Pumping
water
Meet the Ancestors
18© BVG Associates 2010
1941
US
Grampa’s
Knob
1st grid
connection
Meet the Ancestors
19
1982
UK
First
composite
blades
Meet the Ancestors
© BVG Associates 2010 20
Global
$80bn
business
Vestas
employs
25,000
2010
Meet the Ancestors
© BVG Associates 2010 21
Recent History: 1st Battle - Axis of Rotation
No longer a teenager...
10
100
1,000
10,000
100,000
1980 1985 1990 1995 2000 2005 2010 2015
Tu
rbin
e R
ati
ng
(kW
)
Year of Introduction
Historical
Extrapolation
Onshore Forecast
Offshore Forecast
22© BVG Associates 2010
History Lesson 2:
Famous battles
23© BVG Associates 2010
1st famous battle: 3 blades vs 2
Recent History: 2nd Battle – Number of Blades
© BVG Associates 2010 24
Recent History: 1st Battle - Axis of Rotation
2nd famous battle: horizontal axis vs vertical
25© BVG Associates 2010
Recent History: End of Dominance of Stall
3rd famous battle: stall vs pitch control
26© BVG Associates 2010
Recent History: Return of Downwind & Compliant Turbines?
4th famous battle: upwind vs downwind
27© BVG Associates 2010
Recent History: Return of Downwind & Compliant Turbines?
5th famous battle: fixed vs variable speed
28© BVG Associates 2010
Recent History: Return of Downwind & Compliant Turbines?
6th famous battle: geared vs direct-drive
Anatomy lesson
30© BVG Associates 2010
Blades
Hub
Gearbox
Yaw system
Generator
Control system,
converter & transformer
Tower
Anatomy of a Wind Turbine
€
V90-3MW
31© BVG Associates 2010
Blades
Hub
Gearbox
Yaw system
Generator
Control system,
converter & transformer
Tower
Tower
16%
Nacelle
& yaw
system
13%
Hub
9%
Gearbox
20%
Blades
23%
Electric
& control
system
19%
Anatomy of a Wind Turbine
€
32© BVG Associates 2010
Rotor
40-150T
Naelle
70-330T
Tower
200-400T
Rotor
Nacelle
Tower
Mass
Anatomy of a Wind Turbine
33© BVG Associates 2010
Blades
Anatomy of a Wind Turbine
0
5
10
15
20
25
010
2030
4050
60
Bla
de M
ass (
T)
Blade Length (m)
1996 Technology
2001 Technology
2005 Technology
34© BVG Associates 2010
Blades
Hub
Anatomy of a Wind Turbine
35© BVG Associates 2010
Blades
Hub
€
Anatomy of a Wind Turbine
36© BVG Associates 2010
Blades
Hub Nacelle
Yaw system
Anatomy of a Wind Turbine
37© BVG Associates 2010
Inside – Novel Nacelles (High Speed Generators)
38© BVG Associates 2010
Inside – Novel Nacelles (Mid Speed Generators)
39© BVG Associates 2010
Inside – Novel Nacelles (Direct-Drive Generators)
40© BVG Associates 2010
Blades
Hub
Gearbox
Yaw system
Generator
Control system,
converter & transformer
Tower
Anatomy of a Wind Turbine
© BVG Associates 200941© BVG Associates 2010
42© BVG Associates 2010
Geography lesson
>9m/s
8-9m/s
>7-8m/s
>5.5-7m/s
43© BVG Associates 2010
1990
Norgersund (SE)
1 x 220kW© BVG Associates 2010
1991
Vindeby (DK)
11 x 450kW© BVG Associates 2010
rest of 1990s
4 projects
26MW© BVG Associates 2010
2002
Horns Rev 1
80 x 2MW© BVG Associates 2010
2005
Kentish Flats (UK)
30 x 3MW© BVG Associates 2010
2007
Beatrice Demonstration (UK)
2 x 5MW© BVG Associates 2010
2010
Thanet (UK)
100 x 3MW© BVG Associates 2010
51© BVG Associates 2010
52© BVG Associates 2010
Development & Consent3.0%
Turbine29.0%
Balance of Plant22.5%
Installation & Commissioning19.5%
Operation & Maintenance26.0%
1.4%
1.4%
0.2%
5.9%
19.4%
3.8%
2.6%
17.8%2.0%
3.2%
14.6%
1.8%
9.1%
15.1%
1.8%
Offshore Wind Farm CAPEX Cost of Energy Breakdown
53© BVG Associates 2010
54© BVG Associates 2010
“Can do...” What?
1. Do Health & Safety excellently
55© BVG Associates 2010
“Can do...” What?
1. Do Health & Safety excellently
2. Massive supply chain growth
56© BVG Associates 2010
“Can do...” What?
1. Do Health & Safety excellently
2. Massive supply chain growth
3. Improve CAPEX costs significantly
57© BVG Associates 2010
“Can do...” What?
1. Do Health & Safety excellently
2. Massive supply chain growth
3. Improve CAPEX costs significantly
59© BVG Associates 2010
60© BVG Associates 2010
“Can do...” What?
1. Do Health & Safety excellently
2. Massive supply chain growth
3. Improve CAPEX costs significantly
4. Improve Installation & OPEX costs more
62© BVG Associates 2010