normal street promenade + eastern hillcrest bikeways
TRANSCRIPT
Normal Street Promenade + Eastern Hillcrest Bikeways
Uptown PlannersUpdate PresentationNovember 5, 2019
1
Project Context
2
Project Context
3
Outreach – Community Meetings
Meeting 1January 24, 2019
Workshop• Gather input
on initial draft concept
• Gather input on features
• Discuss desires and concerns
Meeting 2February 20, 2019
Workshop• Present
updated draft concept
• Gather input on anchor options
• Discuss programming
Meeting 3March 5, 2019
Presentation• Present final
concept• Request
approval from Uptown Planners
4
Outreach – Community Meetings
100+ Participants
300+ Priority Votes
20+Written Comments
60+ Participants
170+Individual Comments
Uptown PlannersApproval
Meeting 1 Meeting 2 Meeting 3
5
What We Heard – Design Features
Plaza String Lighting
Brick Surface Treatment
Seating
Outreach – Results
6
Design – Plan Concept
N
7
Design
Plaza String Lighting
Brick Surface TreatmentSeating
8
Update: Other Key Stakeholder Requests
9
Address drainage issue on University and Normal Street
Add elements such as bioswales
Incorporate elements celebrating historic context
Expand Pride Plaza
Enhance landscaping
Include extra lighting conduits and receptacles
Replace existing sidewalk / incorporate into plaza
Include additional furniture
Update: Design – DRAFT Working Concept
10
Normal St
Harvey Milk St
Lincoln Ave
NDRAFT
Update: Pride Plaza Design – DRAFT Working Concept
11
NDRAFT
Update: Normal Street Tree Palette
12
Ulmus parvifoliaTrue Green Chinese Elm
Tipuana tipuTipu Tree
Senna carnivalCrown of Gold Tree
Quercus ilexHolly Oak
Quercus agrifoliaCoast Live Oak
Update: Space Programming
13
Maintenance Assessment District (MAD)
Programming
Placemaking
Update: Eastern Hillcrest + Park Boulevard Bikeways
14
Update: Park Boulevard Bikeway
15
N
Next Steps
Spring 2019
Outreach
Summer 2019 –Winter 2019
Finalize Design
Spring 2020 –Spring 2021
City Review
Spring 2021
Out to Bid
Summer 2021 –Winter 2022
Construction
Winter2022
Open to Public
16
Policy Advisor
Office of Councilmember Chris Ward
Third Council District, City of San Diego
E-mail: [email protected]
Brittany BaileyAssociate Active Transportation Planner
San Diego Association of Governments
E-mail: [email protected]
Chris Romano
Project Representatives
Tanner FrenchSenior Traffic Engineer
City of San Diego
Economic Development Department
E-mail: [email protected]
17
KeepSanDiegoMoving.com/EasternHillcrestBikeways