navitus bay wind park · 4a_29339951_1 4 1 introduction 1.1 this statement of common ground (socg)...
TRANSCRIPT
NAVITUS BAY WIND PARK Response to Deadline VI
Appendix 29 Updated Statement of Common Ground with Natural
England (ecology excluding fish and shellfish)
29 January 2015
Application Reference: EN10024
Navitus Bay Development Limited
navitusbaywindpark.co.uk
4A_29339951_1 1
Navitus Bay Wind Park Order
PINS Ref: EN010024
Statement of Common Ground
(1) Navitus Bay Development Limited
(2) Natural England
4A_29339951_1 2
Signed
Name Roger Covey
Position Principal Advisor
For Natural England
Date 28th
January 2015
Signed
Name Marlene Biessy
Position Environment Manager
For Navitus Bay Development Limited
Date 28th
January 2015
4A_29339951_1 3
Contents
1 Introduction
2 The Development
3 Application elements under Natural England remit
4 Consultation with Natural England
5 Matters agreed in relation to Physical processes
6 Matters agreed in relation to Benthic Ecology
7 Matters agreed in relation to Marine Mammals
8 Matters agreed in relation to Offshore Ornithology
9 Matters agreed in relation to Terrestrial and Freshwater Ecology
10 Matters agreed in relation to Onshore Ornithology
11 Matters agreed in relation to HRA
12 Matters under discussion
Appendices*
1 Clarification of assessment with regard to the Wight Barfleur SCI
2 Clarification of the assessment with regard to sandwave clearance
3 Clarification of the precautionary nature of the marine mammals and
Megafauna assessment
4 Clarification of the cumulative impact assessment for marine mammals
5 Clarification notes regarding the offshore ornithological assessment
* Appendices have not been included within this updated version of the Statement of Common Ground.
This is because these documents have not altered since their submission as Appendix 64 of the
Response to Deadline II.
4A_29339951_1 4
1 Introduction
1.1 This Statement of Common Ground (SOCG) has been prepared in respect of Navitus Bay
Development Limited’s (the Applicant) application for a development consent order (DCO) to
the Planning Inspectorate (PINS) under the Planning Act 2008 (the Application).
1.2 This SoCG with Natural England is a means of clearly stating any areas of agreement and
disagreement between two parties in relation to the Application. The SoCG has been structured
to reflect topics of interest to Natural England on the Application. Matters regarding the
Seascape, Landscape and Visual Assessment, the Onshore Landscape and Visual Assessment
and Fish and Shellfish Ecology are dealt with in separates SoCG.
1.3 This SoCG has been updated since its original submission at Deadline II. Where changes have
been made to the text these have been highlighted to enable comparision between the two
documents.
1.4 The structure of the SoCG is as follows:
Consultation with Natural England
Matters agreed in relation to Physical Processes
Matters agreed in relation to Benthic Ecology
Matters agreed in relation to Marine Mammals
Matters agreed in relation to Offshore Ornithology
Matters agreed in relation to Terrestrial and Freshwater Ecology
Matters agreed in relation to Onshore Ornithology
Matters agreed in relation to Habitat Regulations Assessment
Matters under discussion.
1.5 Throughout this SoCG the phrase “It is agreed…” is used as a precursor to any point of
agreement that has been specifically stated by agreement between the Applicant and Natural
England. The phrase “It is not agreed…” is used as a precursor to any point that the Applicant
and Natural England wish to clearly state as not yet agreed. Points that are “not agreed” will be
the subject of ongoing discussion wherever possible to resolve, or refine, the extent of
disagreement between the parties.
4A_29339951_1 5
2 The Development
2.1 The Application is for development consent to construct and operate the proposed Navitus Bay
Wind Park, which comprises up to 194 wind turbine generators and associated infrastructure,
with an installed capacity of up to 970 MW (the Project). The proposed wind farm will cover an
offshore area of approximately 153 km2 and will connect to the national grid via underground
cables to the 400 kV substation at Mannington in Dorset.
2.2 The DCO, if made, would be known as the Navitus Bay Wind Park Order. It will comprise the
following elements:
2.2.1 Offshore wind turbines and foundations (up to 194 wind turbines to provide an
installed capacity of up to 970 MW).
2.2.2 Up to one meteorological mast.
2.2.3 Up to three offshore substations.
2.2.4 Undersea cables between the wind turbines, meteorological mast and offshore
substations.
2.2.5 Up to six offshore undersea export cables to transmit electricity from the offshore
substations to the shore.
2.2.6 A landfall located at the Taddiford Gap between Barton-on-Sea and Milford-on-Sea
with onshore transition joint bays to connect the offshore and onshore cables.
2.2.7 Up to six onshore underground cable circuits with jointing bays to transmit electricity
to a new onshore substation.
2.2.8 An onshore substation on land in the vicinity of the existing National Grid substation
at Mannington, Dorset and up to two underground cable circuits to connect the
offshore wind farm to the national grid.
2.2.9 The permanent and/or temporary compulsory acquisition of land and/or rights for the
Project.
2.2.10 Overriding of easements and other rights over or affecting land for the Project.
2.2.11 The application and/or disapplication of legislation relevant to the Project including
inter alia legislation relating to compulsory purchase.
2.2.12 Such ancillary, incidental and consequential provisions, permits or consents as are
necessary and/or convenient.
2.3 The Application was submitted to the Planning Inspectorate on 10th April 2014 and accepted for
examination on 8th May 2014.
4A_29339951_1 6
3 Application elements under Natural England remit
3.1 Natural England is a non-departmental public body established under the Natural Environment
and Rural Communities Act 2006 (“NERC Act”). Natural England is the statutory adviser to
Government on nature conservation in England and promotes the conservation of England's
wildlife and natural features.1 Natural England’s remit extends to the territorial sea adjacent to
England, up to the 12 nautical mile limit from the coastline.2
3.2 Natural England is a statutory consultee:
In respect of environmental information submitted pursuant to the Infrastructure Planning
(Environmental Impact Assessment) Regulations 2009 (‘the EIA Regs’);3
in respect of plans or projects that are subject to the requirements of the Conservation of
Habitats and Species Regulations 2010 (as amended) (the “Habitats Regulations”) which are
likely to have a significant effect on European protected sites – that is, sites designated as
Special Areas of Conservation (“SACs”) and Special Protection Areas (“SPAs”) for the purposes
of the EU Habitats and Birds Directives;4
in respect of proposals likely to damage any of the flora, fauna or geological or physiographical
features for which a Site of Special Scientific Interest (“SSSI”) has been notified pursuant to the
Wildlife and Countryside Act 1981 (the “1981 Act”);5 and
in respect of all applications for consent for Nationally Significant Infrastructure Projects which
are likely to affect land in England.6
3.3 It is also the Government’s policy to consult Natural England in respect of sites listed for the
purposes of the Convention on Wetlands of International Importance especially as Waterfowl
Habitat signed at Ramsar on 2nd February 1971 (“Ramsar sites”) as if they were European
protected sites.7
3.4 Natural England is also the statutory advisor to Government on the conservation of England’s
landscape and biological and geological diversity and also on the promotion of access to the
countryside and open space for recreation. Natural England has statutory powers and duties to
support the conservation and enhancement of nationally protected areas, including advice to
Government on matters relating to nationally protected landscapes (section 84(1) Countryside
and Rights of Way Act 2000).
3.5 The Examining Authority should note that pursuant to an authorisation made on the 9th
December 2013 by the JNCC under paragraph 17(c) of Schedule 4 to the Natural Environment
1 NERC Act ss.1 (2), 2 and 4
2 NERC Act, s.1 (3)
3 Regs. 2(1), 8(6), 9(1), 13(2)(b), 17(3)(g), 18(3)(f), 19(3)(e) of the EIA Regs.
4 Regulation 61 of the Habitats Regulations
5 Section 28I of the 1981 Act
6Planning Act s.42; Infrastructure Planning (Applications: Prescribed Forms and Procedure) Regulations 2009, reg. 3
and sch.1. 7 National Planning Policy Framework (March 2012), para 118; PINS Advice Note 10: Habitats Regulation
Assessment for nationally significant infrastructure projects, p.4.
4A_29339951_1 7
and Rural Communities Act 2006, Natural England is authorised to exercise the JNCC‘s
functions as a statutory consultee in respect of applications for offshore renewable energy
installations in offshore waters (0-200nm) adjacent to England. This application was included in
that authorisation and therefore Natural England will be providing statutory advice in respect of
that delegated authority. However, JNCC retains responsibility as the statutory advisors for
European Protected sites that are located outside the territorial sea and UK internal waters (i.e.
more than 12 nautical miles offshore), in this instance the Wight Barfleur SCI and as such
continues to provide advice to Natural England on the significance of any potential impacts on
interest features of the site.
3.6 In determining this application, the Secretary of State will be acting as the competent authority
for the purposes of the Habitats Regulations and the 2007 Regulations. The Secretary of State is
also a section 28G authority with specific duties under the 1981 Wildlife and Countryside Act in
respect of SSSIs.
3.7 Natural England defers to the following bodies in relation to specified matters:
3.7.1 The Marine Management Organisation (MMO) on matters related to water quality
3.7.2 The MMO and the Southern Inshore Fisheries Conservation Authority (SIFCA) on matters related to commercial fisheries
3.7.3 The Local Planning Authority on matters related to in-Air and onshore noise
3.8 With regard to the assessment of air quality Natural England confirm there are no matters
outstanding.
4A_29339951_1 8
4 Consultation with Natural England
Pre-Application
4.1 The Applicant engaged with Natural England on the Project during the pre-application process,
both in terms of informal non-statutory engagement and formal consultation carried out pursuant
to section 42 of the Planning Act 2008 (as amended).
4.2 During formal consultation, Natural England provided comments on the draft Environmental
Statement (ES) by way of letter dated 11th October 2013 (the Consultation Response). The
Applicant addressed these comments in its Application submitted to the Planning Inspectorate
on 10th April 2014.
4.3 Specific consultation with regard to the Conservation of Habitats and Species Regulations 2010
(as amended) was undertaken by following the Defra guidance “Habitats Regulations – Evidence
plans for Nationally Significant Infrastructure Projects (2012)”. This process is outlined in the
Evidence Plan Report (an Appendix to the Applicant’s response to Deadline II).
Post-Application
4.4 Natural England made a relevant representation on the Application to the Planning Inspectorate
on 23rd
June 2014 (the Relevant Representation).
4.5 A summary of the communications undertaken following the submission of the Application are
set out in the table below.
Activity Date Subject
Meeting 29/05/2014 Statement of Common Ground
process and updates on
Offshore Ornithology, Onshore
Ornithology and Terrestrial and
Freshwater Ecology
Tele-conference 05/06/2014 General biodiversity update
Tele-conference 11/07/2014 Relevant Representation for
Offshore Ornithology
Meeting 14/07/2014 Relevant Representation for
Terrestrial and Freshwater
Ecology and Onshore Birds
Tele-conference 16/07/2014 Relevant Representation for
Physical Processes
4A_29339951_1 9
Tele-conference 16/07/2014 Relevant Representation for
Benthic Ecology
Meeting 21/07/2014 Relevant Representation for
Offshore Ornithology
Tele-conference 28/07/2014 Relevant Representation for
Marine Mammals
Meeting 27/08/2014 Relevant Representation for
Terrestrial and Freshwater
Ecology and Onshore
Ornithology
Meeting 28/08/2014 Relevant Representation for
Offshore Ornithology
Meeting (joint meeting with
LPAs and Wildlife Trusts)
02/09/2014 Statement of Common Ground
for Terrestrial and Freshwater
Ecology and Onshore
Ornithology
Meeting 15/09/2014 Statement of Common Ground
for all matters excluding
Seascape, Landscape and
Visual.
Tele-conference 29/09/2014 Statement of Common Ground
for ornithology and terrestrial
ecology.
Tele-conference 13/10/2014 Statement of Common Ground
for all matters excluding
Seascape, Landscape and
Visual.
Tele-conference 22/10/2014 Updates and ongoing task
discussions for all topics within
Natural England remit.
Tele-conference 13/11/2014 Updates and ongoing task
discussions for all Terrestrial
4A_29339951_1 10
and Freshwater Ecology,
Onshore Ornithology and
Offshore Ornithology.
Tele-conference 09/12/2014 Updates and ongoing task
discussion for all ecological
topics.
4.6 Following meetings listed in the table above and subsequent communication with Natural
England, agreement was reached on certain matters previously raised by Natural England in
their Relevant Representation. These are outlined in the sections below.
4A_29339951_1 11
5 Matters Agreed in relation to Physical processes
5.1 The following paragraphs of this SoCG set out those aspects of the Environmental Impact
Assessment of physical processes that are agreed.
5.2 Where the agreements set out in the following paragraphs refer to sections of the ES, it is
agreed that those statements apply equally to all application documents. Unless otherwise
indicated, all paragraph references in this section are to Volume B, Chapter 5 of the ES.
Legislation, Policy and Guidance
5.3 It is agreed that the assessment methodology is appropriate and follows standard practice in
relation to the Overarching National Policy Statement (NPS) for Energy (EN-1) and the National
Policy Statement for Renewable Energy Infrastructure (EN-3) and that specific considerations
with regards to physical processes as have been considered. In addition specific regard to
paragraphs 2.6.81, 2.6.113 and 2.6.194 of EN-3 has been given.
5.4 It is agreed that the ES has considered and referred to all appropriate legislation, policy and
guidance in relation to the potential impacts on physical processes in preparing the impact
assessment undertaken.
5.5 It is agreed that Volume B, Chapter 5 of the ES, and subsequent clarification notes still under
discussion (see Section 12 ‘matters under discussion’), contains a complete assessment of all
the issues relevant to physical processes that should be included for this type of development in
this location and as defined by the NPS and any other policy or guidance considered relevant.
Study Area
5.6 It is agreed that an appropriate study area for the consideration of physical processes has been
assessed, in accordance to the agreed scope of work discussed at the Project outset and agreed
in writing on 15th August 2013.
Assessment Methodology
5.7 It is agreed that the methodology employed and set out in Section 5.3 provides an appropriate
description of the approach to defining the assessment criteria and assignment of significance
that has subsequently been used in the impact assessment undertaken.
Baseline conditions
5.8 It is agreed that the surveys and modelling undertaken, including sediment dispersion modelling,
and methodology employed were appropriate and of sufficient scale and timing to characterise
the area in relation to the physical processes environment, in accordance to the agreed scope of
work discussed at the Project outset and agreed in writing on 15th August 2013.
5.9 It is agreed that the information presented to describe the baseline conditions within Volume B,
Chapter 5 of the ES and supporting characterisation and assessment reports at Appendices 5.1
and 5.2, provide an accurate representation of the physical processes environment of the study
4A_29339951_1 12
area and utilises best available information, as confirmed in writing with Natural England on 15th
August 2013.
5.10 It is agreed that the information presented to describe the microclimate conditions within Volume
B, Chapter 5 of the ES and supporting micro climate reports at Appendices 5.3 to 5.5, provide an
accurate representation of the microclimate conditions of the study area.
Parameters for assessment and Realistic Worst Case Scenario (RWCS)
5.11 It is agreed that the key parameters for assessment and the RWCS, as defined in table 5.13.
Clarification was provided to Natural England to enable the agreement that the key parameters
for assessment of the RWCS are appropriate for assessing the potential maximum impacts upon
physical processes during construction, operation and decommissioning phases of the Project
and allows the full impacts of the proposals to be assessed.
5.12 It is agreed that a RWCS for the development has been established according to the Design
(Rochdale) Envelope principles.
5.13 It is agreed that the rationale for the RWCS of chalk release from pin pile installation and gravity
base bed preparation are appropriate and allows the full impacts of both scenarios to be
assessed.
5.14 It is agreed that the cable protection requirements are provided in sufficient detail to allow
potential impacts to be assessed. Further consideration will be undertaken once data from pre-
construction benthic surveys and likely areas of cable protection are identified in more detail as
part of the Scour Protection Management and Cable Armouring Plan.
5.15 It is agreed that there are no other design permutations, when considering the project details as
set out the Project Description Chapters (Volume A and Volume B, Chapter 2), which could lead
to any greater effect on physical processes than the RWCS as set out in Table 5.13.
Impact Assessment
5.16 It is agreed that for all physical processes pathways, effects and receptors identified, the ES
presents a detailed and adequate assessment of potential impacts, arising from all phases of
development. Clarification has been provided to Natural England to enable this agreement to be
reached.
5.17 It is agreed that the level of sensitivity assigned to each physical processes receptor is
appropriate and takes into account previous advice received from Natural England as part of the
Section 42 process in October 2013.
5.18 It is agreed that the use of Horizontal Directional Drilling will remove the potential for cabling
impacts arising in the intertidal area. Clarification has been provided to Natural England in order
to reach this agreement, which is based on no scour protection being placed at the cable exit pit
in the shallow offshore zone.
4A_29339951_1 13
5.19 It is agreed that the impacts on all physical process pathways, effects and receptors identified
and assessed, including the Wight Barfleur SCI (see Appendix 1) and with reference to potential
sandwave clearance (see Appendix 2), will be negligible or minor and therefore not significant.
5.20 Cumulative impact assessment
5.21 It is agreed that the projects and plans considered within the cumulative assessment are relevant
and appropriate to allow the potential cumulative impacts of the Project to be assessed.
5.22 It is agreed that the Applicant has sufficiently considered all potential cumulative impacts to
inform the assessment and that the cumulative impacts presented in Section 5.7 are appropriate,
which concludes that there are unlikely to be any significant impacts.
Agreed Mitigation Measures/DCO requirements
5.23 It is agreed that the Deemed Marine Licences (DMLs) for the Project contain a provision at
Condition 11(g) for a cable specification and installation plan and at Condition 11(e) for a scour
protection management and cable armouring plan, which will provide details of the need, type,
sources, quantity and installation methods for scour protection.
5.24 It is agreed that the DMLs for the Project have been updated at Condition 11(c), regarding
suspended sediment concentrations, and Condition 11(e), regarding scour protection, to allow
for consultation with Natural England, as requested by Natural England.
6 Matters Agreed in relation to Benthic Ecology
6.1 The following paragraphs of this SoCG set out those aspects of the Environmental Impact
Assessment of benthic ecology that are agreed.
6.2 Where the agreements set out in the following paragraphs refer to sections of the ES, it is
agreed that those statements apply equally to all application documents. Unless otherwise
indicated, all paragraph reference in this section are to Volume B, Chapter 9 of the ES.
Legislation, Policy and Guidance
6.3 It is agreed that the assessment methodology is appropriate and follows standard practice in
relation to the Overarching National Policy Statement (NPS) for Energy (EN-1) and the National
Policy Statement for Renewable Energy Infrastructure (EN-3) and that specific considerations
with regards to benthic ecology as set out in paragraphs 5.3.3 and 5.3.4 of EN-1 and paragraphs
2.6.64 – 2.6.67 and 2.6.13 and 2.6.14 of EN-3 has been given.
6.4 It is agreed that the ES has considered and referred to all appropriate legislation, policy and
guidance in relation to the potential impacts on benthic ecology in preparing the impact
assessment undertaken.
6.5 It is agreed that Volume B, Chapter 9 of the ES contains a complete assessment of all the
significant issues relevant to benthic ecology that should be included for this type of development
in this location and as defined by the NPS and any other policy or guidance considered relevant.
4A_29339951_1 14
Study Area
6.6 It is agreed that an appropriate study area for the consideration of potential effects on benthic
ecology receptors from the Project has been assessed, in accordance to the agreed scope of
work discussed and agreed with the MMO on 1st May 2012.
Assessment Methodology
6.7 It is agreed that the methodology employed and set out in Section 9.3 provides an appropriate
description of the approach to defining the assessment criteria and assignment of significance
that has subsequently been used in the impact assessment undertaken.
6.8 It is agreed that the intertidal survey undertaken, was appropriate and of sufficient scale and
timing to characterise the area in relation to benthic ecology.
6.9 It is agreed that the methodology used to characterise the level of reef resemblance to Annex I
stony (geogenic reef) is appropriate as advised by Natural England and presented within the
benthic ecology characterisation technical report (Appendix 9.1) and that no habitats of high
resemblance to the definitions of Annex I stony (geogenic) reef were identified within the
boundaries of the Offshore Development Area, as agreed with Natural England on 16th July
2014.
Baseline conditions
6.10 It is agreed that the benthic ecology survey undertaken, including beam trawl samples, sediment
samples and seabed video footage and photographs, was appropriate and of sufficient scale and
timing to characterise the area in relation to benthic ecology, in accordance to the scope of work
agreed in correspondence with the MMO and their advisors Cefas on 1st May 2012.
6.11 It is agreed that the offshore development area including the turbine array and export cable
corridor has been appropriately mapped with regards to biotope classification and valued
ecological components (VECs) using a combination of grab samples and acoustic data, following
advice from Natural England in response to PEI3 (October 2013).
6.12 It is agreed that the information presented to describe the baseline conditions within Volume B,
Chapter 9 of the ES and supporting benthic ecology characterisation technical report at
Appendix 9.1, provide an accurate representation of benthic ecology of the study area and
utilises best available information, as agreed in writing with Natural England on 15th August
2013.
Parameters for assessment and Realistic Worst Case Scenario (RWCS)
6.13 It is agreed that the key parameters for assessment and the RWCS, as defined in table 9.11 are
appropriate for assessing the potential maximum impacts upon benthic ecology receptors during
construction, operation and decommissioning phases of the Project and allows the full impacts of
the proposals to be assessed. This agreement has been reached following the provision of
clarification to Natural England.
4A_29339951_1 15
6.14 It is agreed that a RWCS for the development has been established according to the Design
(Rochdale) Envelope principles.
6.15 It is agreed that the RWCS for suspended sediment concentrations is based on a maximum of
two gravity base foundations being installed at any one time as presented within Volume B,
Chapter 5.
6.16 It is agreed that the cable protection requirements are provided in sufficient detail to allow
potential impacts to be assessed. Clarification has been provided to Natural England in order to
reach this agreement.
6.17 It is agreed that there are no other design permutations, when considering the Project details as
set out in the Project Description Chapters (Volume A and Volume B, Chapter 2), which could
lead to any greater effect on benthic ecology than the worst case scenarios as set out in Table
9.11. Clarification has been provided to Natural England to enable this agreement to be reached.
6.18 It is agreed that for all benthic ecology receptors identified, the ES presents a detailed and
adequate assessment of potential impacts, arising from all phases of development. However, the
Applicant notes Natural England’s comments raised within their Relevant Representation over
the use of Valued Ecological Components (VEC) to assign receptor sensitivity and Natural
England would wish to consult if the approach was to be used in future applications.
6.19 It is agreed that for all benthic ecology receptors identified, consideration of importance and the
assignment of sensitivity used within the assessment is appropriate.
6.20 It is agreed that the conclusions based on the methodologies used is appropriate to assess the
likely recovery (re-colonisation) rates of species and biotopes.
6.21 It is agreed that the impacts on all benthic ecology receptors identified and assessed, including
direct and indirect impacts, will be negligible or minor and therefore not significant.
Cumulative impact assessment
6.22 It is agreed that the projects and plans considered within the cumulative assessment are relevant
and appropriate to allow the potential cumulative impacts of the project to be assessed.
6.23 It is agreed that the Project has sufficiently considered all potential cumulative impacts to inform
the assessment and that the cumulative impacts presented in Section 9.7 are appropriate, which
concludes that there are unlikely to be any significant impacts.
Agreed Mitigation Measures/DCO requirements
6.24 It is agreed that the DMLs for the Project contain a provision at Condition 11(g) for a cable
specification and installation plan and at Condition 11(e) for a scour protection management and
cable armouring plan, which will provide details of the need, type, sources, quantity and
installation methods for scour protection.
4A_29339951_1 16
6.25 It is agreed that all export cables will be installed through the intertidal area using Horizontal
Directional Drilling and this forms a Requirement with the draft DCO for the Project (Requirement
10).
6.26 It is agreed that best practice will be followed and implemented and a Construction Method
Statement (CMS) and project Environmental Management Plan (PEMP) would be developed in
consultation with Natural England prior to the commencement of construction activity (Condition
11 (Pre-construction plans and documentation)).
7 Matters Agreed in relation to Marine Mammals and Megafauna
7.1 The following paragraphs of this SoCG set out those aspects of the Environmental Impact
Assessment for marine mammals and megafauna that are agreed.
7.2 Where the agreements set out in the following paragraphs refer to sections of the ES, it is
agreed that those statements apply equally to all Application documents. Unless otherwise
indicated, all paragraph reference in this section are to Volume B, Chapter 11 of the ES.
Legislation, Policy and Guidance
7.3 It is agreed that the assessment methodology is appropriate and follows standard practice in
relation to the Overarching National Policy Statement (NPS) for Energy (EN-1) and the National
Policy Statement for Renewable Energy Infrastructure (EN-3) and that specific considerations
with regards to marine mammals and megafauna as set out in paragraphs 5.3.3 and 5.3.4 of EN-
1 and paragraphs 2.6.92 and 2.6.93 of EN-3 has been given.
7.4 It is agreed that the ES has considered and referred to all appropriate international and national
legislation, policy and guidance in relation to the potential impacts on marine mammals and
megafauna in preparing the impact assessment undertaken.
7.5 It is agreed that Volume B, Chapter 11 of the ES contains a complete assessment of all the
issues relevant to marine mammals and megafauna that should be included for this type of
development in this location and as defined by the NPS and any other policy or guidance
considered relevant.
Study Area
7.6 It is agreed that an appropriate study area for the consideration of marine mammals and
megafauna has been assessed, in accordance with available information and datasets, as
agreed in writing with Natural England on 7th and 11
th June 2013.
Assessment Methodology
7.7 It is agreed that the methodology employed and set out in Section 11.3 provides an appropriate
description of the approach to defining the assessment criteria and assignment of significance
that has subsequently been used in the impact assessment undertaken.
4A_29339951_1 17
7.8 It is agreed that the method of assessment, using a quantitative approach to assigning effect
magnitude and sensitivity of receptors is clear and reasonable and that necessary limitations and
assumptions are recorded appropriately.
Baseline conditions
7.9 It is agreed that the data sources used and marine mammal surveys undertaken, including aerial
and boat based surveys and static passive acoustic surveys, were appropriate and of sufficient
scale and timing to characterise the area in relation to marine mammals and megafauna, as
discussed and agreed with Natural England on 28th July 2014.
7.10 It is agreed that that the information presented to describe the baseline conditions within Volume
B, Chapter 11 of the ES and supporting technical reports at Appendices 11.1 to 11.3 provide an
accurate representation of marine mammal and megafauna within the study area and utilises
best available information, as agreed in writing with Natural England on 7th and 11
th June 2013.
Parameters for assessment and Realistic Worst Case Scenario (RWCS)
7.11 It is agreed that the key parameters for assessment and the RWCS, as defined in table 11.18
are appropriate for assessing the potential maximum impacts upon marine mammal and
megafauna during construction, operation and decommissioning phases of the Project and
allows the full impacts of the proposals to be assessed.
7.12 It is agreed that a RWCS for the development has been established according to the Design
(Rochdale) Envelope principles and that this provides a suitable basis for undertaking the impact
assessment, as discussed and agreed with Natural England on 28th July 2014.
7.13 It is agreed that the survey area and data collected for the previous PEI3 layout remain
appropriate and assessment using this information is likely to be more precautionary as a result
of the layout change which resulted in movement of the turbine array away from the coast.
7.14 It is agreed that there are no other design permutations, when considering the project details as
set out the Project Description Chapters (Volume A and Volume B, Chapter 2), which could lead
to any greater effect on marine mammals and megafauna than the worst case scenarios as set
out in Table 11.18. This follows clarification provided to Natural England and agreed on 28h July
2014.
Impact Assessment
7.15 It is agreed that for all marine mammal and megafauna receptors identified, the ES presents a
detailed and adequate assessment of potential impacts, arising from all phases of development.
Although it is acknowledged there are uncertainties associated with understanding the impact
significance of noise on marine mammals and a precautionary approach has been undertaken
as appropriate.
7.16 It is agreed that for all marine mammal and megafauna receptors identified, consideration of
importance and the assignment of sensitivity used within the assessment is appropriate.
4A_29339951_1 18
7.17 It is agreed that the most significant potential impact would arise from pile driving noise during
construction and that the assessment correctly focuses on this impact.
7.18 It is agreed that the impacts on all marine mammals and megafauna receptors identified and
assessed, including direct and indirect impacts, will be negligible or minor and therefore not
significant. This follows provision of a clarification note issued on the 14th August 2014 (see
Appendix 3).
Cumulative impact assessment
7.19 It is agreed that the projects and plans considered within the cumulative assessment are relevant
and appropriate to allow the potential cumulative impacts of the project to be assessed.
7.20 It is agreed that the Project has sufficiently considered all potential cumulative impacts to inform
the assessment and that the cumulative impacts presented in Section 6.7 are appropriate, which
concludes that there are unlikely to be any significant impacts. This follows provision of a
clarification note issued on the 14th August 2014.
Agreed Mitigation Measures/DCO requirements
7.21 It is agreed that an area within the Turbine Area has been demarcated for the exclusion of
monopile foundations, reducing the total number of monopile foundations used. This forms a
condition within the transmission assets DML for the Project (Condition 1 (Design parameters)).
7.22 It is agreed that best practice will be followed and implemented and a Marine Mammal Mitigation
Protocol (MMMP) will be developed in consultation with Natural England and the MMO prior to
the commencement of construction works (as per Condition 11(f) (Pre-construction plans and
documentation) of the DMLs. This will include provision for a soft start procedure for pile driving,
and will include a qualitative assessment of potential collision risk of seals with construction
vessels, should a construction port other than Portland or Poole be selected.
7.23 It is agreed that the DMLs for the Project includes a provision at Condition 11(c)(v) and (vi) (Pre-
construction plans and documentation) with respect to vessel routeing and the production of a
vessel routeing protocol which will have the impact of reducing potential collision risk.
7.24 It is agreed that the Applicant will continue to consult with oil and gas operators in the area and
will enter into an agreement and if necessary programming arrangement, to ensure that piling
does not occur concurrently with seismic surveys for oil and gas exploration.
7.25 It is agreed that Rampion and Navitus Bay wind farms have entered into a an agreement to
ensure that both projects work together to propose a joint approach to mitigation measures as
required, to be taken during the construction of each individual wind farm.
7.26 It is agreed that the Applicant will continue to consult with French wind farm developers, to
enable projects to work together to coordinate activities to develop mitigation measures, as
required.
4A_29339951_1 19
7.27 It is agreed that provided the design envelope for the Project remains the same and no material
changes are made to the Application, an EPS licence would be granted prior to construction, this
conclusion based on further clarification provided with regard to cumulative impact assessment
(Appendix 4).
8 Matters Agreed in relation to Offshore Ornithology
8.1 The following paragraphs of this SoCG set out those aspects of the Environmental Impact
Assessment of offshore ornithology that are agreed.
8.2 Where the agreements set out in the following paragraphs refer to sections of the ES, it is
agreed that those statements apply equally to all Application documents. Unless otherwise
indicated, all section and paragraph references in this section of the SoCG are to Volume B,
Chapter 12 of the ES. All references to appendices made are to those accompanying Volume B,
Chapter 12 of the ES.
8.3 The offshore ornithology chapter includes an assessment of the potential impacts on seabirds,
seaducks and birds that may pass through the Turbine Area when migrating between different
land masses (e.g. the British Isles and continental Europe). Birds wintering or breeding within or
adjacent to the Onshore Development Area are considered separately in section 10 of this
SoCG.
Legislation, Policy and Guidance
8.4 It is agreed that the relevant international, national and local legislation and policy is identified
within Section 12.2, and that the relevant aspects of these documents are addressed in the
information provided within the chapter. This includes, but is not restricted to, part 5.3 of the
Overarching National Policy Statement for Energy (EN-1) and part 2.6 of the National Policy
Statement for Renewable Energy Infrastructure (EN-3).
8.5 It is agreed that the guidance documents identified within Section 12.2 are those most relevant to
the assessment of impacts of offshore wind farm on birds.
8.6 It is agreed that Volume B, Chapter 12 of the ES and subsequent information provided post-
application (Appendix 5 sections 5.1 to 5.10) provide a complete assessment of the issues
relevant to offshore ornithology that should be included for this type of development in this
location as defined by the NPS and any other policy or guidance considered relevant.
Study Area
8.7 It is agreed that the definition of the study area, comprising the Turbine Area, a 4 km buffer zone
and Zone 7 (see Section 12.3), provides a suitable scale across which to describe the baseline
(Appendix 12.1 of the ES) and on which to determine the potential impacts on offshore
ornithology due to the Project.
8.8 It is agreed that the use of the PEI3 boundary to determine the densities of individual bird
species (as outlined in paragraphs 12.1.6 and 12.3.3) is suitable as the basis of the general
assessment as there is no pattern regarding distribution of birds noticeable within the data (in
4A_29339951_1 20
comparison between the PEI3 and Application boundary), except for guillemot and razorbill
where further information has been provided (see Appendix 5.4 and 5.5).
8.9 It is agreed that the updating of the density figures for guillemot and razorbill used within the
displacement matrices, to reflect the Application boundary, is both required and reasonable
given the changes in design parameters (e.g. reduction in the maximum number of wind
turbines).
Methodology
Desk-study and Field Survey
8.10 It is agreed that the desk-study information gathered from the scientific and grey literature and
locally gathered historical ornithological data (as described in paragraphs 12.4.1 to 12.4.3)
provides a suitable context within which to frame the impact assessment provided in Section
12.4 and Appendix 12.1 of the ES.
8.11 It is agreed that the methodology used to undertake the field survey programme (including level
of survey effort) was discussed and regularly reviewed by Natural England resulting in the
baseline data (Appendix 12.1 of the ES) being considered suitable for informing the assessment
on 13th June 2013.
8.12 It is agreed that the boat-based transect surveys (both in method and level of survey effort)
undertaken within the Turbine Area, buffer zone and Zone 7 provide suitable baseline
information on which to base an assessment of the impacts of the Project on offshore ornithology
when combined with the desk-study information, other field survey data and modelling outputs
described in Volume B, Chapter 12 and accompanying appendices. This includes providing
adequate data to undertake collision risk modelling (following the basic Band model) and the
derivation of displacement matrices (as per JNCC / Natural England interim guidance).
8.13 It is agreed that the aerial transect surveys (both in method and survey effort) undertaken within
the Turbine Area, buffer zone and Zone 7 provide suitable additional information in order to
provide context to the assessment.
8.14 It is agreed that the migration surveys (land and boat-based surveys run concurrently) did not
provide sufficient information on which to provide an assessment of this aspect of the offshore
ornithology. It is also agreed that the options for gathering suitable field data on migrating birds is
limited and that this has resulted in the necessity to determine impacts on migratory birds
following a modelling approach.
Modelling
8.15 It is agreed that Migropath modelling (as described in Appendices 12.2 and 12.5 of the ES) is
suitable for providing baseline information on which to base a collision risk assessment of the
following species; common scoter, little egret, avocet, golden plover, grey plover, knot, black-
tailed godwit and bar-tailed godwit (UK non-breeding population). It is agreed that further
corroboration of the Migropath model outputs for common tern, Sandwich tern, great skua, Arctic
4A_29339951_1 21
skua, Dark-bellied brent goose and bar-tailed godwit (Taymyrensis sub-species) was required, in
the form of an apportionment exercise, and has been completed to Natural England’s
satisfaction (Appendix 5.1).
8.16 It is agreed that the method used to determine which migratory birds should be assessed is
adequate and that modelling of all migratory species listed in Appendix 12.9 is not necessary.
8.17 It is agreed that the method for the apportionment exercise (see Appendix 5.1) for common tern,
Sandwich tern, great skua, Arctic skua, Dark-bellied brent goose and bar-tailed godwit
(Taymyrensis sub-species) enables conclusions on the likely level of impact on these species to
be drawn.
8.18 It is agreed that the use of the JNCC / Natural England interim guidance for determining losses
to displacement is appropriate following further input post submission (Appendix 5.9).
8.19 It is agreed that the approach to collision risk modelling used to inform the assessment is
suitable following the provision of clarification. Use of Option 1 of the Band model (see Appendix
12.4 of the ES) is appropriate and precautionary for the key seabirds and migratory birds listed in
Tables 12.31 and 12.41 and Option 2 for migratory seabirds (Appendix 5.1 and 5.8). It is also
agreed that the range of avoidance rates presented are appropriate.
8.20 It is agreed that the collision risk modelling scenarios undertaken for nightjar (see Appendix 12.8
of the ES) provide a range of scenarios that are highly precautionary. The highly precautionary
outputs account for the lack of information on the migratory behaviour of this species.
8.21 It is agreed that the collision risk modelling of linnet (used as an exemplar passerine), as
described in paragraph 12.4.111, provides a precautionary basis for the assessment of collision
risk for passerine species.
Impact Assessment Methodology
8.22 It is agreed that the impact assessment methodology outlined in paragraphs 12.3.15 to 12.3.48,
although it is not supported by Natural England, results in valid conclusions being drawn.
8.23 It is agreed that the thresholds for determining significance at the regional, national and
international population for the assessment of displacement and collision risk (see Table 12.30)
are appropriate (i.e. the use of changes relative to background mortality rates of 1% or greater
being associated with potential significant impacts).
Baseline Environment
8.24 It is agreed that the desk-study and field survey information presented within Appendix 12.1
provide a suitable baseline to inform the impact assessment of the Project. It is noted that this
baseline was agreed as suitable by Natural England as part of the Evidence Plan process on
13th June 2013.
8.25 It is agreed that the Migropath model outputs described in paragraphs 12.4.53 and 12.4.111,
when allied with the outputs of the apportionment exercise (Appendix 5.1), adequately describe
4A_29339951_1 22
the baseline for migrating birds. Central to this agreement is the understanding that the
practicable collection of robust field data that could be used to parameterise the impact
assessment of migratory birds was not possible.
8.26 It is agreed that the Applicant and Natural England discussed the potential methods for the
recording of migratory bird movements on a number of occasions during the data collection
period, and that the conclusion of these discussions (following a review of the data collected
during concurrent migration boat and land based surveys) was the recognition that a modelling
approach was the best way to enable quantification of the baseline.
8.27 It is agreed that the baseline environment described by field survey, desk-based research and
estimates of migration movements through the Turbine Area (using Migropath and / or
apportionment) provides adequate information on which to base an assessment of the Project on
offshore ornithology.
Parameters for assessment and Realistic Worst Case Scenario (RWCS)
8.28 It is agreed that Table 12.19 provides the RWCS for the Project with regard to the potential
ornithological impacts at the construction, operation and maintenance and decommissioning
phases of the Project.
8.29 It is agreed that the scenario that presents the greatest potential collision risk for the Project is
that which specifies the installation of 194 turbines, each with an output of 5 MW (see Appendix
12.4, Volume B, Chapter 12).
8.30 It is agreed that there are no other design permutations, when considering the Project details as
set out the Project Description Chapters (Volume A and Volume B, Chapter 2), which could lead
to any greater effect on offshore ornithology than the RWCS as set out in Table 12.19.
Assessment of impacts
8.31 It is agreed that the following species that were noted within the survey area, but did not occur
either in large numbers or frequently or were judged to be of limited nature conservation
importance, should remain scoped out of the assessment:
Red-breasted merganser
Black-throated diver
Storm petrel
Manx shearwater
Cormorant
Shag
Merlin
Coot
4A_29339951_1 23
Whimbrel
Pormarine skua
Black-headed gull
Common gull
Little gull
Yellow-legged gull
Arctic tern
Feral pigeon
Passerines noted at sea.
8.32 It is agreed that the potential impacts on the key seabird species during the construction and
decommissioning phases of the Project of disturbance and displacement and habitat
loss/change would not result in an impact on the populations of these species that would be
deemed Significant in EIA terms.
8.33 It is agreed that the potential impacts on the key seabird species, during the construction and
operation phases of the Project of disturbance and displacement, losses due to collision and the
barrier effect would not result in an impact on the populations of these species that would be
deemed Significant in EIA terms.
8.34 It is agreed that the migratory species considered (dark-bellied brent goose, common scoter,
little egret, avocet, golden plover, grey plover, knot, black-tailed godwit, bar-tailed godwit (UK
non-breeding population and Taymyrensis sub-species), common tern, Sandwich tern, great
skua, Arctic skua, nightjar and linnet) within the impact assessment provide the information
necessary (alongside that provided in Appendix 12.9 of the ES and Appendix 5.1) to conclude
that there will be No Significant Impacts, in EIA terms, on any population of migratory birds due
to the potential passage through the Navitus Bay Wind Park.
Agreed mitigation measures / DCO requirements
8.35 It is agreed that the measures adopted as part of the Project (see paragraphs 12.3.52 to
12.3.55), implemented through Project design and the adoption of best practice measures (e.g.
pollution control measures), reduce or eliminate any identified potential impacts as none are
judged to be Significant in EIA terms.
8.36 It is agreed that there is no requirement for ornithological monitoring for areas under Natural
England’s remit during the construction and operation of the Navitus Bay Wind Park as no
significant impacts on any birds within the marine environment have been predicted.
Inter-relationships
4A_29339951_1 24
8.37 It is agreed that the inter-relationships identified within Volume B, Chapter 12 and Volume D,
Chapter 6 are appropriate and all potential impacts relevant to the Project have been identified
and assessed.
8.38 There is ongoing discussion to agree that none of the inter-relationships identified result in a
significant impact on any receptor. Further information on this point is outlined within Section 12
‘Matters under discussion’
Cumulative Impacts
8.39 It is agreed that the Project makes no significant contribution to cumulative impacts to birds at
any relevant population scale.
Transboundary Impacts
8.40 It is agreed that transboundary impacts are dealt with through the assessment of impacts at the
regional (including British and French waters), national and international levels.
8.41 It is agreed that as there are no impacts identified as Significant in EIA terms, there are no
significant transboundary issues.
9 Matters Agreed in relation to Terrestrial and Freshwater Ecology
Introduction
9.1 The following paragraphs of this SoCG set out those aspects of the Environmental Impact
Assessment of terrestrial and freshwater ecology that are agreed.
9.2 Where the agreements set out in the following paragraphs refer to sections of the ES, it is
agreed that those statements apply equally to all Application documents. Unless otherwise
indicated, all section and paragraph references in this section of the SoCG are to Volume C,
Chapter 10 of the ES. All references to appendices made are to those accompanying Volume C,
Chapter 10 of the ES.
9.3 The terrestrial and freshwater ecology chapter includes an assessment of the potential impacts
of habitats and species that may interact with the construction, operation and maintenance and
decommissioning of the onshore infrastructure. The exception to this is with regard to migrating
bats and Lepidoptera which are considered with regard to the offshore infrastructure.
9.4 Migratory fish when in the freshwater environment are considered within a separate SoCG.
9.5 This section is focused on terrestrial and freshwater ecology receptors with regard to the EIA
Regulations. Section 11 of this SoCG lists the agreements with regard to terrestrial and
freshwater ecology and the Habitat Regulations.
Legislation, Policy and Guidance
9.6 It is agreed that the relevant international, national and local legislation and policy is identified
within Section 10.2, and that the relevant aspects of these documents are addressed in the
4A_29339951_1 25
information provided within the chapter. This includes, but is not restricted to, part 5.3 of the
Overarching National Policy Statement for Energy (EN-1), part 2.6 of the National Policy
Statement for Renewable Energy Infrastructure (EN-3) and part 2.7 of the National Policy
Statement for Electrical Networks Infrastructure (EN-5).
9.7 It is agreed that the guidance documents identified within Section 10.2 are those most relevant to
the assessment of impacts of onshore infrastructure projects (e.g. the installation of onshore
electrical transmission cables) on terrestrial and freshwater ecology receptors.
9.8 It is agreed that Volume C, Chapter 10 of the ES and subsequent information provided post-
application (an Appendix to the Applicant’s response to Deadline II) provide a complete
assessment of the issues relevant to terrestrial and freshwater ecology that should be included
for this type of development in this location as defined by the NPS and any other policy or
guidance considered relevant.
Study Area
9.9 It is agreed that the definition of the study area described in Section 10.3 is of a suitable scale to
enable the determination of the potential impacts of temporary habitat loss, degradation of
adjacent habitats and disturbance of fauna due to the construction, operation and maintenance
and decommissioning of the Project. This position having been confirmed with Natural England
originally on 14th June 2013.
9.10 It is agreed and acknowledged that full access to the study area was not available for terrestrial
ecology surveys until October 2013 (i.e. seasonally dependent surveys could not be completed
until after the submission of the application for development consent). It is agreed that the
surveys undertaken in late 2013 and 2014 (an Appendix to the Applicant’s response to Deadline
II) ensure full coverage of the study area has been achieved.
Assessment Methodology
9.11 It is agreed that the Ecological Impact Assessment guidance provided by the Chartered Institute
of Ecology and Environmental Management provides a suitable framework within which to carry
out the impact assessment for the Project. It is agreed that this guidance has been interpreted
correctly and implemented accordingly within Volume C, Chapter 10.
9.12 It is agreed that species, within the study area, that have been determined as having a nature
conservation value of ‘local’ or lower do not require detailed impact assessment. This is because
there is no potential for the Project to result in a significant impact, in EIA terms, on the
populations of these species.
Baseline Environment
9.13 It is agreed that the desk-study information gathered from the local biological record centres
(based in Hampshire and Dorset), internet based databases and through consultation with
relevant bodies (as described in Tables 10.2 and 10.4) provides a suitable context within which
to frame the impact assessment provided in Volume C, Chapter 10.
4A_29339951_1 26
9.14 It is agreed that the use of the extended Phase 1 habitat survey method to classify habitats
within and adjacent to the Onshore Development Area was appropriate.
9.15 It is agreed that the hedgerow survey methodology used to classify hedgerows within and
adjacent to the Onshore Development Area were appropriate for determining the value of this
habitat.
9.16 It is agreed that the use of the National Vegetation Classification survey methodology within the
Onshore Development Area as it passes through the Dorset Heaths Special Area of
Conservation (SAC) was appropriate to provide a detailed description of the types of habitats
present.
9.17 It is agreed that the arboriculture survey used to identify individual trees and groups of trees
within and adjacent to the Onshore Development Area was appropriate for providing a baseline
for this resource.
9.18 It is agreed that the great crested newt survey methodology employed within suitable habitats
within and adjacent to the Onshore Development Area was appropriate for identifying the
presence of this species.
9.19 It is agreed that the reptile survey methods employed within suitable habitats within the Onshore
Development Area were appropriate for identifying the presence of reptile populations.
9.20 It is agreed that the bat survey methods (tree climbing, emergence surveys, transect surveys
and static detector surveys) within and adjacent to the Onshore Development Area were suitable
for identifying the bat species present and their relative levels of activity.
9.21 It is agreed that the dormouse survey methodology employed within suitable habitats within and
adjacent to the Onshore Development Area was appropriate for identifying the presence of this
species.
9.22 It is agreed that the badger survey method employed within suitable habitats within and adjacent
to the Onshore Development Area was appropriate for identifying the presence of badger
activity.
9.23 It is agreed that the otter survey methodology employed within suitable habitats within and
adjacent to the Onshore Development Area was appropriate for identifying the presence of this
species.
9.24 It is agreed that the water vole survey methodology employed within suitable habitats within and
adjacent to the Onshore Development Area was appropriate for identifying the presence of this
species.
9.25 It is agreed that the aquatic invertebrate survey methodology employed within suitable habitats
within and adjacent to the Onshore Development Area was appropriate for identifying the type of
species present.
4A_29339951_1 27
9.26 It is agreed that the baseline environment, derived from field survey and desk-based study is
adequately described in Section 10.4, in Appendices 10.1 through 10.6 of the ES and in the
Ecology Survey Report 2014 Appended to the Applicant’s response to Deadline II.
9.27 It is agreed that the results from the surveys undertaken in 2014 do not alter the baseline
situation assessed within Volume C, Chapter 10, as the types of habitats and species present
were in keeping with those in adjacent parts of the study area.
Parameters for assessment and Realistic Worst Case Scenario (RWCS)
9.28 It is agreed that the impact assessment is based on the RWCS – i.e. all habitat is lost within the
Onshore Development Area during the construction period, apart from that where cable
installation will be undertaken using trenchless techniques (see Volume C, Chapter 2 and the
updated trenchless crossing plan).
Assessment of impacts
9.29 It is agreed that the following potential impacts on ecological receptors determined to be of
‘county’ conservation value or greater (see Table 10.8) can be scoped out of detailed
assessment due to the implementation of the measures adopted as part of the Project in
paragraph 10.3.43 and 10.3.44 and in the updated trenchless crossing plan (see Appendices to
the Applicant’s response to Deadline II):
Statutory and non-statutory designated sites outside of the Onshore Development
Area;
Statutory and non-statutory designated sites crossed using trenchless crossing
techniques;
Bats migrating or feeding within the marine environment;
Butterflies and moths migrating across the Turbine Area;
Marsh/marshy grassland;
Soft cliff and intertidal shingle/cobbles;
Migratory fish reacting to electro-magnetic fields.
9.30 It is agreed that the impacts that required assessment for the Project, in relation to terrestrial and
freshwater ecology, once all measures adopted as part of the project are considered, were:
Statutory and non-statutory designated sites to be crossed using open trenching
techniques;
Temporary loss of broad-leaved and mixed woodland, hedgerows, lowland heath and
rivers and streams;
Disturbance of badger and destruction of their resting places;
Disturbance of bats and temporary loss of foraging and commuting habitats;
4A_29339951_1 28
Killing or injury of common reptiles and temporary loss of habitat;
Killing, injury or disturbance of rare reptiles and temporary loss of habitat;
Loss of aquatic invertebrates through pollution and sedimentation;
Loss of migratory fish through pollution and sedimentation or blocking of freshwater
channels.
Agreed mitigation measures / DCO requirements
9.31 It is agreed that the implementation of the measures adopted as part of the Project outlined in
paragraphs 10.3.43 and 10.3.44 and described within the draft Landscape and Ecological
Management Plan (LEMP - see the Applicant’s response to Deadline II) would ensure that
relevant legislation aimed at the protection of flora and fauna would be complied with. There is
ongoing discussion as to how these should be secured within the DCO.
9.32 It is agreed that the implementation of the measures adopted as part of the Project outlined in
paragraphs 10.3.43 and 10.3.44 and additional mitigation described in Section 10.6 and the
LEMP (Appended to the Applicant’s response to Deadline II) ensure that the potential to reduce
the extent and quality of habitats or suppress the populations of the species listed in this SoCG
listed in Section 13.7 of this SoCG in the medium to long term is negligible.
9.33 It is agreed that the implementation of the additional mitigation outlined in Section 10.6 and the
LEMP (Appended to the Applicant’s response to Deadline II) would ensure that the Project
provides biodiversity gain in the medium to long-term.
Inter-relationships
9.34 It is agreed that the inter-relationships identified within Volume C, Chapter 10 and Volume D,
Chapter 6 are appropriate and all potential impacts relevant to the Project have been identified
and assessed.
Cumulative Impacts
It is agreed that as the information available at the date of the preliminary meeting (11th
September 2014) on the St Leonards Hospital re-development has not altered since the
submission of the application for development consent then the assessment within the ES
remains valid.
It is agreed that the mitigation measures outlined within the LEMP (Appended to the Applicant’s
response to Deadline II) provide the necessary management tools to ensure that displacement of
recreational users will not result in increased impacts on habitats and species in Hurn Forest or
surrounding areas.
Transboundary Impacts
9.35 It is agreed that transboundary impacts are not relevant to the consideration of terrestrial and
freshwater ecology for this Project.
4A_29339951_1 29
10 Matters Agreed in relation to Onshore Ornithology
Introduction
10.1 The following paragraphs of this SoCG set out those aspects of the Environmental Impact
Assessment of Onshore Ornithology that are agreed.
10.2 Where the agreements set out in the following paragraphs refer to sections of the ES, it is
agreed that those statements apply equally to all Application documents. Unless otherwise
indicated, all section and paragraph references in this section of the SoCG are to Volume C,
Chapter 11 of the ES. All references to appendices made are to those accompanying Volume C,
Chapter 11 of the ES.
10.3 The Onshore Ornithology chapter includes consideration of resident birds, breeding birds and
wintering birds within or in close proximity to the Onshore Development Area. Impacts on birds
whilst on migration are dealt with in the Offshore Ornithology section of this SoCG.
10.4 This section is focused on onshore ornithological aspects with regard to the EIA Regulations.
Section 11 of this SoCG lists the agreements with regard to onshore ornithology and the Habitat
Regulations.
Legislation, Policy and Guidance
10.5 It is agreed that the relevant international, national and local legislation and policy is identified
within Section 11.2, and that the relevant aspects of these documents are addressed in the
information provided within the chapter. This includes, but is not restricted to, part 5.3 of the
Overarching National Policy Statement for Energy (EN-1), part 2.6 of the National Policy
Statement for Renewable Energy Infrastructure (EN-3) and part 2.7 of the National Policy
Statement for Electrical Networks Infrastructure (EN-5).
10.6 It is agreed that the guidance documents identified within Section 11.2 are those most relevant to
the assessment of impacts of onshore infrastructure projects (e.g. the installation of onshore
electrical transmission cables) on onshore ornithological receptors. Agreements with regard to
suitable implementation of guidance documents are provided in Section 13.4 of this SoCG.
10.7 It is agreed that Volume C, Chapter 11 of the ES and subsequent information provided post-
application (Ornithology Survey Report 2014 appended to the Applicant’s response to Deadline
II) provide a complete assessment of the issues relevant to onshore ornithology that should be
included for this type of development in this location as defined by the NPS and any other policy
or guidance considered relevant.
Study Area
10.8 It is agreed that the definition of the study area described in Section 11.3 is of a suitable scale to
enable the determination of the potential impacts of temporary habitat loss and disturbance on
onshore ornithological receptors due to the Project. This position having been confirmed
originally on 14th June 2013.
4A_29339951_1 30
10.9 It is acknowledged that full access to the study area was not available for breeding bird surveys
until spring / summer 2014 (i.e. after the submission of the application for development consent).
It is agreed that the surveys undertaken in 2014 (appended to the Applicant’s response to
Deadline II) ensure full coverage of the study area has been achieved.
Methodology
Impact Assessment Methodology
10.10 It is agreed that the Ecological Impact Assessment guidance provided by the Chartered Institute
of Ecology and Environmental Management provides a suitable framework within which to carry
out the impact assessment for the Project. It is agreed that this guidance has been interpreted
correctly and implemented accordingly within Volume C, Chapter 11.
10.11 It is agreed that species, within the study area, that have been determined as having a nature
conservation value of ‘local’ or lower do not require detailed impact assessment. This is because
there is no potential for the Project to result in a significant impact, in EIA terms, on the
populations of these species.
Baseline Environment
10.12 It is agreed that the desk-study information gathered from the local biological record centres
(based in Hampshire and Dorset), ornithological literature and locally gathered historical
ornithological data (as described in Table 11.4) provides a suitable context within which to frame
the impact assessment provided in Volume C, Chapter 11.
10.13 It is agreed that the breeding bird survey programme undertaken using a methodology based on
that of the Common Bird Census (CBC) provides suitable baseline information, when used
alongside the data gathered during the desk-study, to determine the nature conservation value of
each breeding species within the context of the Onshore Development Area.
10.14 It is agreed that the breeding bird survey programme provides suitable baseline data on which to
base an assessment of the impacts of the Project on breeding birds when within the terrestrial
environment.
10.15 It is agreed that the winter bird surveys undertaken provided an overview of the types and
distribution of species commonly wintering within the Onshore Development Area and provides
suitable baseline information, when used alongside the data gathered during the desk-study, to
determine their nature conservation value.
10.16 It is agreed that the wintering bird survey programme provides suitable baseline data on which to
base an assessment of the impacts of the Project on wintering birds when within the terrestrial
environment.
10.17 It is agreed that the baseline environment, derived from field survey and desk-based study is
adequately described in Section 11.4, Appendices 11.1, 11.2, 11.3 and 11.4 of the ES and in the
Applicant’s response to Deadline II.
4A_29339951_1 31
10.18 It is agreed that the reports within Appendix 11.2 and 11.3 of the ES were agreed as suitable by
Natural England on 14th June 2013 as part of the Evidence Plan process. It is also agreed that a
further survey report (Volume C, Chapter 11, Appendix 11.4) was provided to Natural England
on 4th November 2013 and it was confirmed as adequate within a meeting on 18th November
2013.
Parameters for assessment and Realistic Worst Case Scenario (RWCS)
10.19 It is agreed that the impact assessment is based on the RWCS – i.e. all habitat is lost within the
Onshore Development Area during the construction period, apart from that where cable
installation will be undertaken using trenchless techniques (see Volume C, Chapter 2).
Assessment of impacts
10.20 It is agreed that the majority of potential impacts on onshore ornithological receptors determined
to be of ‘county’ conservation value or greater can be scoped out of detailed assessment due to
the implementation of measures adopted as part of the project outlined in paragraphs 11.3.30
and 11.3.31. These species are listed below:
Dark-bellied brent goose
Shelduck
Wigeon
Teal
Grey partridge
Quail
Marsh harrier
Hen harrier
Merlin
Peregrine
Lapwing
Green sandpiper
Mediterranean gull
Black-headed gull
Lesser black-backed gull
Turtle dove
Skylark
Tree pipit
4A_29339951_1 32
Yellow wagtail
Redstart
Winchat
Mistle thrush
Grasshopper warbler
Marsh tit
Eurasian tree sparrow
Linnet
Lesser redpoll
Crossbill.
10.21 It is agreed that the impacts that required assessment for the Project, in relation to onshore
ornithology and once all measures adopted as part of the project (paragraph 11.3.30 and
11.3.31, Volume C, Chapter 11) are considered, are:
The disturbance of wintering birds within the Avon Valley;
The disturbance of birds breeding on heathlands;
Temporary habitat loss for birds breeding on heathlands.
10.22 It is agreed that the impacts outlined above are addressed within Volume C, Chapter 11.
Agreed mitigation measures / DCO requirements
10.23 It is agreed that the implementation of the measures adopted as part of the Project outlined in
paragraphs 11.3.30 and 11.3.31 would ensure that relevant legislation aimed at protecting
individual birds, their eggs, young and active nests would be complied with. Provision of the
Landscape and Ecological Management Plan is secured in the DCO at Requirement 18
(Landscape and ecological management plan).
10.24 It is agreed that the implementation of the measures adopted as part of the Project outlined in
paragraphs 11.3.30 and 11.3.31 and the LEMP (appended to the Applicant’s response to
Deadline II) ensure that the potential to suppress the populations of birds in the Onshore
Development Area in the short, medium and long term is negligible and there is the potential for
bird populations to expand in habitats created as part of the Project in the medium to long term.
10.25 It is agreed that the implementation of the additional mitigation outlined in paragraphs 11.6.2 to
11.6.4 and the LEMP (appended to the Applicant’s response to Deadline II) would ensure that
the populations of species associated with the Avon Valley would not be challenged by the
Project and therefore the impact is Not Significant.
4A_29339951_1 33
10.26 It is agreed that the implementation of the additional mitigation outlined in paragraphs 11.6.6 to
11.6.13 and the LEMP (appended to the Applicant’s response to Deadline II) would ensure that
the populations of species associated with the Dorset Heathlands would not be challenged by
the Project and therefore the impact is Not Significant.
10.27 It is agreed that Requirement 27 of the draft Development Consent Order has been updated to
allow for consultation with Natural England, as requested by Natural England.
Inter-relationships
10.28 It is agreed that the inter-relationships identified within Volume C, Chapter 11 and Volume D,
Chapter 6 are appropriate and all potential impacts relevant to the Project have been identified
and assessed.
Cumulative Impacts
It is agreed that as the information available at the date of the preliminary meeting (11th
September 2014) on the St Leonards Hospital re-development has not altered since the
submission of the application for development consent then the assessment within the ES
remains valid.
It is agreed that the mitigation measures outlined within the LEMP (appended to the Applicant’s
response to Deadline II) provide the necessary management tools to ensure that displacement of
recreational users will not result in increased impacts on birds in Hurn Forest or surrounding
areas. This is supported by the clarification of the assessment of recreational disturbance
provided in an appendix to the Applicant’s response to Deadline II.
Transboundary Impacts
10.29 It is agreed that transboundary impacts are not relevant to the consideration of birds resident,
breeding or wintering within or in close proximity to the Onshore Development Area. This is on
the understanding that birds on migration are considered separately within Volume B, Chapter
12 Offshore Ornithology.
11 Matters Agreed in relation to Habitats Regulation Assessment
Introduction
11.1 This section outlines the areas of agreement between the Applicant and Natural England in
relation to the Habitat Regulations Assessment (Document references 5.2 and 5.3). This
includes consideration of the potential impacts of the Project on all European sites and their
designated features.
11.2 Where the agreements set out in the following sections refer to sections of the HRA Screening
Report or the HRA Assessment Report, it is agreed that those statements apply equally to all
application documents. Unless otherwise indicated, all section and paragraph references in this
section of the SoCG are to HRA Screening Report (in the relevant titled section) or the HRA
4A_29339951_1 34
Assessment Report. All references to appendices made are to those accompanying HRA
Screening Report.
11.3 The agreement of survey methodology, analytical processes (e.g. mathematical modelling) and
baseline information is covered in the topic specific sections is dealt with within the relevant
sections of this SoCG and not repeated. However, it is agreed that these are equally applicable
to the HRA process unless otherwise stated.
11.4 It is agreed that the definition of European sites provided in footnote 1 of the HRA Screening
Report is a suitable basis on which to base the assessment. This was agreed during the
Evidence Plan process on 15th August 2013.
11.5 It is agreed that the European Commission guidance, that provides a basis for the screening
process (see Section 2.1), provides a framework for the assessment. This was agreed during the
Evidence Plan process on 15th August 2013.
11.6 It is agreed that the HRA screening methodology employed for the Project provides a logical
basis, as described in Section 2.2, for identification of European sites that could be subject to
Likely Significant Effects. This was agreed during the Evidence Plan process on 15th August
2013.
11.7 It is agreed that the methodology for determining which plans and projects to include within the
in-combination assessment, as described in Section 2.3. This was agreed during the Evidence
Plan process on 15th August 2013.
11.8 The Applicant and Natural England acknowledge that the threshold for determining whether or
not a potential impact is judged to be a Likely Significant Effect differs between the two parties.
Due to PINS advice on the structure of the HRA document, consideration of mathematical
modelling outputs and other analytical processes was considered with regard to the
determination of Likely Significant Effects. Natural England would prefer that this assessment
was undertaken at the consideration of Adverse Effects stage (i.e. that detailed in the HRA
report).
11.9 It is agreed that there will be no adverse effects on the following Special Protection Areas (as
identified in Natural England’s Relevant Representation):
Avon Valley SPA;
Dorset Heathlands SPA;
Alde-Ore Estuary SPA;
Flamborough and Filey Coast pSPA;
Flamborough and Bempton Cliffs SPA
Poole Harbour SPA;
Solent and Southampton Water SPA;
Chichester and Langstone Harbours SPA.
4A_29339951_1 35
11.10 There is ongoing discussion regarding the level of effects on the following Special Protection
Areas (as identified in Natural England’s Relevant Representation) with regard to various
species of tern (see matters under discussion in Section 12):
Poole Harbour SPA;
Solent and Southampton Water SPA;
Chichester and Langstone Harbours SPA.
11.11 It is agreed that there will be no adverse effects on the following Special Areas of
Conservation(as identified in Natural England’s Relevant Representation):
Dorset Heaths SAC.
11.12 There is ongoing discussion regarding the level of effects on the following Special Areas of
Conservation (as identified in Natural England’s Relevant Representation) with regard to Atlantic
salmon (see matters under discussion in Section 12):
River Avon SAC;
River Itchen SAC.
11.13 It is agreed that there will be no adverse effects on the following Ramsar sites(as identified in
Natural England’s Relevant Representation):
Avon Valley Ramsar Site;
Dorset Heathlands Ramsar Site;
Poole Harbour Ramsar Site;
Solent and Southampton Water Ramsar Site;
Alderney West Coast and the Burhou Islands Ramsar Site
Chichester and Langstone Harbour Ramsar site.
11.14 It is agreed that Natural England have provided advice and appraisal of the Applicant’s
assessment of the gannet colony on the Alderney and West Coast and the Burhou Islands
Ramsar Site. However, it is acknowledged that this site is outside the remit of Natural England.
11.15 It is agreed that there will be no likely significant effects on any of the other European sites within
the UK or other EEA member states identified within the HRA Screening Report (Document
reference 5.2).
4A_29339951_1 36
12 Matters under discussion
12.1 The following section sets out a summary of those issues where Natural England and the
Applicant have not yet reached agreement.
Matters under discussion in relation to Physical Processes
12.2 There are no matters outstanding with regard to the assessment of Physical Processes.
Matters under discussion in relation to Benthic Ecology
12.3 There are no matters outstanding with regard to the assessment of Benthic Ecology.
Matters under discussion in relation to marine mammals
12.4 There are no outstanding points of discussion between the Applicant and Natural England with
regard to the assessment of marine mammals.
Matters under discussion in relation to Offshore Ornithology
12.5 There are no outstanding points of discussion between the Applicant and Natural England with
regard to the assessment of offshore ornithology.
12.6 The following table sets out a summary of those issues where Natural England and the Applicant
have not yet reached agreement and issues are therefore under discussion.
Topic Comment/Status Response/Action
Clarifications as
raised by Natural
England with regard
to terns
Natural England have requested further
assessment of the potential for subsea noise
created during the construction phase to
displace the prey (small fish etc.) of terns
associated with breeding colonies on the south
coast.
Natural England and the Applicant are
awaiting conclusion of discussions
between the parties with regard to
subsea noise (see separate SoCG
with Natural England on fish) prior to
concluding discussions regarding
impacts on terns.
12.7 Matters under discussion in relation to Habitat Regulations Assessment
12.8 The following table sets out a summary of those issues where Natural England and the
Applicant have not yet reached agreement and issues are therefore under discussion
Topic Comment/Status Response/Action
4A_29339951_1 37
Determination of
no adverse effects
For a number of European sites further receptor
specific discussions (described above) need to
be concluded prior to a determination of no
adverse effects being drawn for a number of
designations.
These receptor specific discussions cover:
Terns;
Atlantic salmon.
See above and the
SoCG with Natural
England with regard to
fish.
Appendices
Appendices have not been included within this updated version of the Statement of Common Ground.
This is because these documents have not altered since their submission as Appendix 64 of the
Response to Deadline II.