navitus bay wind park - planning inspectorate... · 2.1.4 the project exceeds 100 mw and is...
TRANSCRIPT
NAVITUS BAY WIND PARK Response to Deadline VII
Appendix 17 Design and access statement v2
5 March 2015
Application Reference: EN10024
Navitus Bay Development Limited
navitusbaywindpark.co.uk
Navitus Bay Wind Park
Design and Access Statement v2
Appendix 17 (Document 8.2)
March 2015
Pursuant to Regulation 5(2)(q) of the Infrastructure Planning (Applications:
Prescribed Forms and Procedure) Regulations 2009
Navitus Bay Wind Park
DCO
Page ii Design and Access Statement
DOCUMENT CONTROL
DOCUMENT PROPERTIES
Author Navitus Bay Development Limited
Title Design and Access Statement v2
Document Reference
8.2
VERSION HISTORY
Date Version Status Description/Changes
4 March 2015 2.0 Final Issued at Deadline VII
Navitus Bay Wind Park
DCO
Design and Access Statement Page iii
TABLE OF CONTENTS
1. Introduction ........................................................................... 1
2. Policy Framework .................................................................... 4
3. Site Selection ......................................................................... 6
4. Site Description and Consenting Considerations ........................ 11
5. Project Design ...................................................................... 15
6. Access ................................................................................. 33
7. References ........................................................................... 38
8. Glossary .............................................................................. 39
9. Abbreviations ....................................................................... 44
Navitus Bay Wind Park
DCO
Page iv Design and Access Statement
LIST OF TABLES
Table 1.1 – Onshore Design Parameters .............................................. 3
Table 8.1 – Glossary ....................................................................... 39
Table 9.1 - Abbreviations ................................................................. 44
LIST OF FIGURES
Figure 5.1 - Indicative Landfall arrangement ...................................... 18
Figure 5.2 - A typical HDD compound at cable landfall (courtesy of Visser
Smit & Hanab) ............................................................. 19
Figure 5.3 - Typical HV cable configuration for a single circuit in both
trefoil and flat spaced formation ..................................... 21
Figure 5.4 - Indicative Onshore Cable Corridor working width ............... 22
Figure 5.5 - Indicative Onshore Substation Layout .............................. 27
Figure 5.6 - Indicative Onshore Substation Landscaping Scheme .......... 32
Figure 6.1 - Landfall access route ..................................................... 34
Navitus Bay Wind Park
DCO
Design and Access Statement Page 1
1. Introduction
1.1 Project Brief
1.1.1 Navitus Bay Development Limited (NBDL) is a joint venture
owned 50:50 by Eneco Wind UK Ltd (Eneco) and EDF Energy
(EDF). In January 2010, The Crown Estate awarded Eneco the
exclusive rights to develop an offshore wind park within Zone 7
(West of Isle of Wight), following Round 3 of its Offshore Wind
Programme. The development zone has a target capacity of up
to 970 MW.
1.1.2 Consent is being sought from the Secretary of State for Energy
and Climate Change. Subject to approval, it is anticipated that
the construction of the offshore wind farm and associated
onshore electrical infrastructure will take up to five years to
complete.
1.2 Purpose of the This Document
1.2.1 The purpose of this Design and Access Statement (DAS) is to
demonstrate the evolution and rationale of the design of the
onshore components of the Project within the Onshore
Development Area, comprising the Landfall, the Onshore Cable
Corridor and the Onshore Substation. It describes how the
design has been influenced by the technical and operational
requirements of the wind park electrical infrastructure. The
design approach incorporates comments received during pre-
application consultation under Section 42, 47 and 48 of the
Planning Act 2008, as well as outputs of environmental
assessments of the environment in which the infrastructure
would be located.
1.2.2 The DAS supports the Application for a Development Consent
Order (DCO) submitted to the Planning Inspectorate (PINS) by
NBDL. The DAS should be read in conjunction with the
Enviromental Statement (Document 6.1). The Application seeks
consent for the Navitus Bay Wind Park (‘the Project’).
1.2.3 Existing policy set out within the Overarching National Policy
Statement for Energy (NPS EN-1) makes clear the requirements
Navitus Bay Wind Park
DCO
Page 2 Design and Access Statement
for good design in energy projects. The DAS provides a tool to
communicate how the requirements for good design and access
provision have been considered.
1.2.4 There is no specific guidance provided for the preparation of
design and access statements in relation to Nationally Significant
Infrastructure Projects (NSIPs). NBDL has therefore decided to
prepare this DAS in line with the Commission for Architecture
and the Built Environment guidelines (CABE, 2007). The bullet
points below set out the key parameters set out in the CABE
guidelines:
use – what is the purpose of the development and how it will
fit within the surrounding environment;
amount – size and volume of the development and its
constitute elements;
layout – the relationship between the development, and
surrounding buildings;
scale – the physical size and shape of the proposed
development;
appearance – the physical look of the development specifically
the design and materials;
landscaping – how mitigation proposals will be applied to
screen the development from wider views; and
access – inclusive of construction and operational traffic and
how crossings over roads and watercourses will be achieved.
1.3 Project Description
1.3.1 The DAS focuses on the onshore elements of the Project
comprising the Onshore Development Area (as described above).
In order to bring electricity generated offshore by the wind
turbines offshore export cables will make Landfall at Taddiford
Gap, between Barton-on-Sea and Mildford-on-Sea and the
Onshore Cable Corridor would then head north-west, to the new
Onshore Substation at Three Legged-Cross, north of Ferndown in
East Dorset. The new Onshore Substation would then be
Navitus Bay Wind Park
DCO
Design and Access Statement Page 3
connected to the National Grid substation at Mannington, by
underground cable.
1.3.2 The proposed onshore electrical infrastructure is required in
order to connect the Navitus Bay Wind Park to the 400 kV
national electricity network. Table 1.1 below sets out the primary
infrastructure associated with the onshore Project components.
Table 1.1 – Onshore Design Parameters
Project component
Design Parameters
Landfall up to six offshore cables;
up to six transition joint bays; and
two temporary construction compounds.
Onshore Cable Corridor
working width of generally 40 m;
up to six cable circuits and fibre optics in six
trenches; and
four temporary construction compounds.
Onshore Substation
electrical footprint of approximately 3 ha (refer to the Works Plan (Document 2.4 of this Application)
which sets out the site boundary);
maximum height of electrical equipment – 11 m;
maximum height of GIS building – 14 m;
maximum height of lightning masts – 19 m;
ground raising above existing ground level – up to
1 m; and
one temporary construction compound.
Working hours generally, construction site working will be during normal working hours (08.00 – 18.00 Monday to
Friday and 08.00 – 13.00 Saturday), with no activity
on Sundays or bank holidays; and
exceptions will be required where seven days
working and/or 24 hours working is necessary for specific construction activities such as Horizontal
Directional Drilling (HDD) works.
Navitus Bay Wind Park
DCO
Page 4 Design and Access Statement
2. Policy Framework
2.1 Framework
2.1.1 This section provides a summary of the main planning policies
relevant to the Project and associated DCO documents. It
includes a summary of the national policy and guidance relevant
to the Project. A detailed appraisal of planning policy has been
carried out within the Planning Statement (Document 8.4).
a) National Policy
2.1.2 The UK Government has produced three National Policy
Statements (NPSs) under the Planning Act 2008 that relate to
renewable energy production, including offshore wind:
Overarching NPS for Energy EN-1, July 2011 (DECC, 2011a);
NPS for Renewable Energy Infrastructure (EN-3, July 2011)
(DECC, 2011b); and
NPS for Electricity Networks Infrastructure (EN-5, July 2011)
(DECC, 2011c).
2.1.3 NPSs establish the national need for a particular type of major
infrastructure, together with a series of criteria relating to the
benefits and impacts of a development. Potential benefits include
a development’s contribution to meeting the need for energy
infrastructure, job creation and any long-term or wider benefits.
Potential adverse impacts include any long-term and cumulative
adverse impacts, as well as any measures to avoid, reduce or
compensate for any adverse impacts.
2.1.4 The Project exceeds 100 MW and is therefore classified as a NISP
and will require development consent under the Planning Act
2008. Under the Planning Act 2008 it is possible to include
development associated with the generating station within the
boundaries of the DCO. NBDL has included all the offshore and
onshore infrastructure and grid connection elements of the
Project within the DCO.
Navitus Bay Wind Park
DCO
Design and Access Statement Page 5
2.2 Project Need and Justification
2.2.1 There is a clear need for the Project as set out in the
Overarching National Policy Statement for Energy (EN-1). EN-1
Paragraph 2.2.20 states that “it is critical that the UK continues
to have secure and reliable supplies of electricity as we make the
transition to a low carbon economy”.
2.2.2 In addition, EN-1 Paragraph 3.3.4 outlines the importance of
having a diverse mix of power generation and that renewables
offer a low carbon and proven (for example, onshore and
offshore wind) fuel source.
2.2.3 The UK has substantial renewable energy resources and EN-1
states that offshore wind is expected to provide the largest single
contribution towards the 2020 renewable energy generation
targets.
2.2.4 EN-1 sets out electricity demand forecasts for the year 2025,
stating that 59 GW of demand will need to be delivered by new
infrastructure. In order to meet renewable energy commitments,
some 33 GW of this has been identified as having to come from
renewable sources such as offshore wind.
2.2.5 EN-3 paragraph 2.1.2 provides that in the light of the statements
elsewhere in the NPS about the benefits of new renewable
infrastructure, the Secretary of State should act on the basis that
need for infrastructure covered by EN-3 has been demonstrated.
The document states that the decision-maker should give
substantial weight to the contribution that projects will make
towards satisfying the need for new infrastructure when
considering applications made under the Planning Act 2008.
Navitus Bay Wind Park
DCO
Page 6 Design and Access Statement
3. Site Selection
3.1 Description
3.1.1 Environmental, social and technical considerations have been
integral to informing the design development of the Project, and
as such, the design of the Project has been evolving over the last
two years following wide ranging consultation inputs from
statutory and non-statutory stakeholders. The key onshore
infrastructure elements of the Project has been listed in Table
1.1 of this DAS. As highlighted, the design of the infrastructure
cannot be achieved in isolation and must take account of the
environment in which it is placed. The criteria and approach to
the site selection strategy is set out below.
3.1.2 The site selection process included the Landfall, Onshore Cable
Corridor and Onshore Substation.
3.2 Site Selection Strategy
3.2.1 The site selection strategy consisted of the following:
initial investigations into electrical connection options to the
National Grid;
key Project decisions to install cables underground rather than
installing any new overhead lines;
desk-based constraints mapping process (identifying technical
and environmental constraints) in the proposed study area;
detailed surveys, studies and assessments to gather
information on the existing environment within the study
area;
environmental and engineering related site visits to confirm
the feasibility of the preferred Onshore Cable Corridor;
use of technical guidance for substation siting (e.g. National
Grid Holford and Horlock rules on siting of a substation);
consultation with a range of statutory consultees (through
meetings, site visits and correspondence);
Navitus Bay Wind Park
DCO
Design and Access Statement Page 7
discussions with landowners and tenants;
consultation with local communities (through public
exhibitions, newsletters and Project specific website); and
detailed analysis, assessment and route modifications to
identify the preferred Onshore Cable Corridor option, taking
into account environmental, technical, financial and risk
factors and any mitigation measures which may be required
to reduce or minimise environmental impacts.
3.3 Operational and Technical Requirements
3.3.1 The operational requirements for the Landfall, Onshore Cable
Corridor and Onshore Substation include:
safety by design;
risk identification and management;
dimensions and scale of the plant;
construction requirements;
maintenance requirements of plant; and
security.
3.3.2 The operational requirements provide the baseline to design,
build and operate the infrastructure safety in relation to existing
features of the site. The requirements dictate the minimum
spacing requirements to accommodate the plant for the works
e.g. proximity to the overhead lines.
3.4 Physical and Environmental Considerations
3.4.1 Physical and environmental considerations are those constraints
that inform the location and site selection process of the onshore
infrastructure. The physical and environmental considerations for
the Landfall, Onshore Cable Corridor and Onshore Substation
include:
the location of sensitive (human) receptors (i.e. residential
housing, schools, hospitals);
impacts to the terrestrial and river ecology and ornithology,
and impacts to designated sites for nature conservation;
Navitus Bay Wind Park
DCO
Page 8 Design and Access Statement
transport infrastructure;
visual appearance of the construction works and plant;
vhange to the existing landscape character;
impacts to the geology and hydrology, and surface water
management;
impacts to soils and agriculture;
the generation of noise and vibration;
impacts to the local air quality; and
impacts to archaeological and heritage assets.
3.4.2 For further detail on these constraints please refer to Section 4
of the DAS or the relevant chapter of the Environmental
Statement (ES Document 6.1).
3.5 Landfall, Onshore Cable Corridor and Onshore Substation
Site Selection
3.5.1 This section provides the key considerations NBDL usd to identify
the preferred locations of the Landfall, Onshore Cable Corridor
and Onshore Substation.
a) Landfall
3.5.2 The Landfall site selection process involved a detailed search of
the adjacent coastline to the offshore development. The key
considerations were:
cliff height;
cliff stability;
cliff geology;
the site’s accessibility from the main highway network for
construction traffic;
the site’s remoteness from environmentally designated areas;
sufficient area for a construction and drilling compound;
sufficient laydown area; and
minimising overall environmental and social impact.
Navitus Bay Wind Park
DCO
Design and Access Statement Page 9
b) Onshore Cable Corridor
3.5.3 The selection of the Onshore Cable Corridor involved
identification of a wider corridor combined with further detailed
desk top and site specific studies. The key criteria that were
considered were:
use of agricultural land where feasible;
avoidance of sensitive receptors such as housing, schools,
churches etc;
avoidance of environmentally sensitive sites where feasible;
and
avoidance of areas of cultural heritage significance.
3.5.4 Section 4 of the DAS provides detail of the key environmental
considerations within the Onshore Cable Corridor search area.
c) Onshore Substation
3.5.5 The Onshore Substation site selection process involved initially
identifying a suitable search area from the proposed connection
point in which a feasible site could be identified. A long list of
potential sites was identified based on broad site feasibility
requirements. The number of potential sites was gradually
reduced as development constraints were identified. All potential
sites were assessed based on the following key criteria:
the engineering / technical suitability of the site;
the site’s accessibility from the main highway network for
construction traffic;
the site’s impact on environmentally designated areas;
minimise the potential to overall environmental and social
impact;
access for the Onshore Cable Corridor to the site;
the site’s proximity to sensitive receptors (i.e. housing); and
the availability of additional land, allowing for substantial
enhancement of the existing natural screening in the area.
Navitus Bay Wind Park
DCO
Page 10 Design and Access Statement
3.5.6 A detailed description of both the Onshore Cable Corridor
identification and Onshore Substation site can be found in
Volume C, Chapter 4 Alternatives of the ES (Document 6.1).
Navitus Bay Wind Park
DCO
Design and Access Statement Page 11
4. Site Description and Consenting
Considerations
4.1 Description
4.1.1 This section of the DAS describes the selected Onshore
Development Area (comprising the Landfall, Onshore Cable
Corridor and Onshore Substation) in the context of its
environment within which it is proposed to be located.
4.2 Landscape Character
4.2.1 Landscape character is recorded at both the national and local
levels. The character types / areas are also evaluated in terms of
their sensitivity.
4.2.2 The Landfall site currently comprises a gently rolling pastoral
landscape set on top of the elevated and heavily eroded coastal
fringe where there are panoramic views across Christchurch Bay
and the mouth of the Solent.
4.2.3 The Onshore Cable Corridor extends for an approximately 35 km
between the Landfall site, located at Taddiford Gap, between
Barton-on- Sea and Milford-on-Sea, and the grid connection
point at the Mannington substation. The route passes through a
predominantly rural and frequently rolling landscape comprising
mostly agricultural land and plantation forestry. The Onshore
Cable Corridor passes through the local administrative
boundaries of New Forest District, Christchurch District and East
Dorset District.
4.2.4 The Onshore Substation is situated within the East Dorset Green
Belt, which encompasses much of the surrounding rural
landscape within the East Dorset District. Small areas to the
north-east and south-east lie within the New Forest District and
Christchurch Boroughs respectively.
4.2.5 A number of small and medium sized settlements are located
within 3 km of the Onshore Substation and include Verwood to
the north, St. Leonards, St Ives and Ashley Heath to the east,
and West Moors and Ferndown to the south. Moreover, the
Navitus Bay Wind Park
DCO
Page 12 Design and Access Statement
proposed Onshore Substation currently forms part of an estate,
which comprises open fields used as grazing pasture.
4.2.6 A full Landscape and Visual Impact Assessment (LVIA) has been
undertaken as part of the Environmental Impact Assessment and
is described in more detail in Volume C, Chapter 12 Landscape
and Visual of the ES.
4.3 Nature Conservation and Ecology
4.3.1 The description below provides an overview of the key habitats
considered during the assessment.
4.3.2 There are nine designated sites of international importance
within 1.5 km of the Onshore Development Area; six of these
overlap with the DCO application boundary. These six
designations overlap considerably, with three of the designations
relating to the River Avon and associated habitats and three
relating to the Dorset Heaths. Fourteen Special Sites of Scientific
Interest were identified during the desk study, six of which
overlap with the Onshore Development Area. Of these six sites,
three are constituent components of the international
designations.
4.3.3 There were 81 non-statutory designated sites of county
importance that were identified as part of the desk-study; 15 of
these overlap with the Onshore Development Area. Several of
the habitats recorded within the DCO application boundary are
habitats of principal importance under Section 41 of the Natural
Environment and Rural Communities Act 2006. These include the
following:
broadleaved woodland;
dry heath/acid grassland and shrub heath;
ponds;
rivers and streams; and
hedgerows.
Navitus Bay Wind Park
DCO
Design and Access Statement Page 13
4.3.4 The environmental and ecological designations as well as results
of the Phase 1 habitats are available in more detail in Volume C,
Chapter 10 Terrestrial and Freshwater Ecology of the ES.
4.4 Historic Environment
4.4.1 The heritage baseline survey identified a total of 60 designated
sites within the study area approximately 500 m either side of
the Onshore Cable Corridor, including Scheduled Monuments and
Listed Buildings. No World Heritage Sites, Registered Parks and
Gardens or Registered Battlefields were identified within the
study area. The small numbers of scheduled monuments
identified within the broad study area are Bronze Age barrows,
which form part of a larger concentration of funerary sites
located in proximity to Hurn Forest.
4.4.2 The majority of the designated sites identified within the study
area are Listed Buildings. These are primarily clustered around
the settlements of Hordle, Bashley, Hinton, North Bockhampton
and Avon, and are predominantly Grade II listed cottages and
farmhouses.
4.4.3 Full details of the heritage and archaeological assessment are
provided in Volume C, Chapter 13 Cultural Heritage and
Archaeology of the ES.
4.5 Transport and Infrastructure
4.5.1 The main vehicular access routes identified in relation to the
Onshore Development Area are described below. Further detail
on the assessment of relevant transport infrastructure can be
found in the associated ES chapter (Volume C, Chapter 14 Traffic
and Transportation).
4.5.2 The only strategic road that the Onshore Cable Corridor crosses
is the A31 dual carriageway which is a trunk road maintained by
the Highways Agency. To the east, the A31 connects to the
motorway network at the M27 near Cadnam. The A338 is the
only other section of dual carriageway that the Onshore Cable
Corridor crosses and is a north-south route connecting the A31
near Ringwood with Bournemouth. There are several other
Navitus Bay Wind Park
DCO
Page 14 Design and Access Statement
classified A roads within this area, the A35 which connects
Lyndhurst with Poole via Christchurch and Bournemouth; the
A337 which connects Lymington with Christchurch, via the
coastal settlements at Barton-on-Sea, New Milton and Highcliffe,
and the A348 which provides access from the A31 to
Bournemouth.
Navitus Bay Wind Park
DCO
Design and Access Statement Page 15
5. Project Design
5.1 Description
5.1.1 A full description of the onshore elements of the Project is
provided in Volume C Chapter 2, Project Description of the ES.
This section describes the, Landfall, Onshore Cable Corridor and
Onshore Substation. The requirements for access are detailed in
section 6 of this DAS. This section is structured in accordance
with the CABE guidelines and considers the use, amount, layout
and scale of each element.
5.2 Landfall
5.2.1 The Landfall is located to the east of Barton on Sea at Taddiford
Gap. The site is an open arable field above a cliff line where a
narrow beach sits below. The Landfall works will be carried out
over a period of approximately 6 months within the primary
construction period of 2 years. Pre-construction works and cable
installation may occur outside this period.
a) Use
5.2.2 The purpose of the landfall is to bring the subsea export cables
to shore and connect to the buried onshore cable system.
Landfall will be achieved through the use of the Horizontal
Directional Drill (HDD) technique. This involves directional
drilling from the onshore side under the cliff line. The purpose of
this is to install ducts through which the cables will be pulled by
a winch.
b) Amount
5.2.3 The Shoreline Management Plan (Royal Haskoning, 2011)
predicts that the rate of erosion along this stretch of coast is up
to 2.7 m per year, with an expected maximum of 135 m over 50
years. To prevent the cables becoming exposed through coastal
erosion the HDD profile will be designed for a minimum of 50
years erosion. The HDD will start at an appropriate distance, no
closer than 135 m from the cliff edge.
Navitus Bay Wind Park
DCO
Page 16 Design and Access Statement
5.2.4 The typical equipment required to carry out the HDD works at
the landfall includes, though is not limited to:
a Drilling Rig;
a Control Cabin;
a Power Pack;
a Hiab Flat Container;
up to two Bentonite Mud Pumps;
a Storage Container;
a mud Recycling Unit; and
ancillary plant and equipment.
5.2.5 Up to six cable circuits would be required and one HDD bore is
required for each circuit. A transition joint bay will be required to
connect the subsea cables to the onshore cables. A typical single
joint bay will be 12 m long, three metres wide and three m deep.
c) Layout
5.2.6 Figure 5.1 below shows the proposed location of the work and
red line boundary. The export cable will make Landfall at
Taddiford Gap, Barton on Sea and the Landfall will be within an
open pasture field, on the landward side of a minor drain and to
the west of the EA flood alleviation channel.
Navitus Bay Wind Park
DCO
Design and Access Statement Page 17
Page left intentionally blank
Navitus Bay Wind Park
DCO
Page 18 Design and Access Statement
Figure 5.1 - Indicative Landfall arrangement
Navitus Bay Wind Park
DCO
Design and Access Statement Page 19
d) Scale
5.2.7 During construction there will be a variety of plant machinery on
site, portacabins and laydown areas (See Figure 5.2). These will
be secured and site security will be used out of construction
hours.
5.2.8 There will be no permanent structures built at the Landfall. Once
construction is complete the only infrastructure visible will be a
manhole cover above the transition joint bay (if required) where
the offshore cables have connected to onshore cables.
Figure 5.2 - A typical HDD compound at cable landfall
(courtesy of Visser Smit & Hanab)
5.3 Onshore Cable Corridor
5.3.1 The Onshore Cable Corridor will be approximately 35 km in
length, travelling from the Landfall site to the new Onshore
Substation, and then from the Onshore Substation to its
connection at the National Grid’s Mannington Substation. The
Onshore Cable Corridor runs predominately within open farmland
in Hampshire and Dorset.
Navitus Bay Wind Park
DCO
Page 20 Design and Access Statement
a) Use
5.3.2 Onshore electricity cables will carry the power from the Landfall
to the proposed new Onshore Substation and will comprise the
following:
alternating Current (AC) operating at a voltage level of up to
275 kV;
the number of circuits required will be up to six, depending on
the final design and detailed cost analysis and will be identical
to the number of offshore cable circuits;
they will be armoured, single core cables with XLPE
insulation; and
the conductor will be either copper or aluminium with cross
sections up to 2000 mm2.
5.3.3 Cabling is also required to connect the new Onshore Substation
to the existing grid connection point at Mannington. It is
expected that these cables will comprise continuous underground
cabling from the Onshore Substation to the connection point, and
will be up to two circuits of 400 kV AC cables.
5.3.4 Ancillary fibre optic and telecommunications cables will also be
required.
b) Amount
5.3.5 There will be up to six trenches used, containing one circuit of
three cables in each trench. The total length of each trench is
approximately 35 km. Table 5.1 shows the indicative dimensions
at different voltages.
Table 5.1 – Typical dimensions of AC onshore cables
Voltage Conductor
Cross-
Section
132 kV 1200
mm²
132 kV 2000
mm²
220 kV 1200
mm²
220 kV 2000
mm²
400 kV 800 mm²
400 kV 1200
mm²
Conductor type
Aluminium Aluminium Aluminium Aluminium Aluminium Aluminium
Navitus Bay Wind Park
DCO
Design and Access Statement Page 21
Table 5.1 – Typical dimensions of AC onshore cables
Voltage Conductor
Cross-
Section
132 kV 1200
mm²
132 kV 2000
mm²
220 kV 1200
mm²
220 kV 2000
mm²
400 kV 800 mm²
400 kV 1200
mm²
Outer
diameter (mm)
94 106 112 124.2 116.3 120.4
Cable weight
(kg/m)
8.7 11.8 12 15.4 12.1 13.4
c) Layout
5.3.6 The configuration of the onshore cables will be established during
detailed design but will comprise up to a maximum of six
circuits, each made up of three, single core cables. Within each
circuit, the onshore cables will be installed in either a trefoil or
flat formation, as shown in Figure 5.3.
5.3.7 The final spacing and cable arrangement will be dependent upon
the voltage of the cables, including the available space and the
thermal properties of the soil.
Figure 5.3 - Typical HV cable configuration for a single
circuit in both trefoil and flat spaced formation
5.3.8 The typical burial depth will be 1,200 mm to the top tile, in line
with landowner agreements. However, in some locations the
depth may vary as shown in Table 5.1. The final depth will be
Navitus Bay Wind Park
DCO
Page 22 Design and Access Statement
dependent upon local conditions and include factors such as the
road construction, the presence of other utilities and also the
ground conditions and topography.
d) Scale
5.3.9 All construction activities will take place within the working
width. Figure 5.4 shows a cross section of the working width,
which will generally be up to 40 m wide.
The working width will principally contain the cable trenches, a
temporary access track and storage area for soil and plant.
Figure 5.4 - Indicative Onshore Cable Corridor working width
5.3.10 Where landowner agreements permit or engineering
requirements dictate, the working width may be wider. These
areas are limited to the Landfall, the route through the West
Moors Ministry of Defence base and where there are both
incoming and outgoing cables from the Onshore Substation.
5.3.11 Temporary construction compounds will be required during
construction. A total of seven temporary construction facility
locations have been identified for the onshore construction (two
to be located at the Landfall, four along the Onshore Cable
Corridor and one at the Onshore Substation). The locations have
been selected based on a number of parameters, including their
close proximity to the working width, ensuring sufficient
coverage of the full length of the route, suitable transport access
and sufficient land area.
5.3.12 Trenchless installation working areas will also be required at
certain locations along the Onshore Cable Corridor. These have
been identified specifically to provide sufficient working area to
complete trenchless cable installation operations. Once the
Stockpile Stockpile
Navitus Bay Wind Park
DCO
Design and Access Statement Page 23
trenchless installation is complete these compounds will be
reinstated.
5.3.13 The exact installation methods for the cables will only be
confirmed during detailed design, post-consent, and will be
developed to suit the requirements of the respective
stakeholders and landowners, where feasible. The construction
methods will also be subject to several other factors, such as the
ground conditions and any environmental constraints.
5.3.14 Temporary accesses will be taken from the public highway at
regular points along the Onshore Cable Corridor. Design of the
accesses will be suitable for both light and heavy goods vehicles
and will include passing places where required. A total of 73 site
accesses have been identified for the Project. Wherever possible,
the site accesses are based upon using the nearest suitable point
from the public highway.
5.4 Onshore Substation
5.4.1 The Onshore Substation is proposed to be sited to the south of
the substation site, adjacent to the Ministry of Defence fuel
depot and providing sufficient separation from residential
properties to the north. A new access road would come through
the plantation woodland to the west of the site.
a) Use
5.4.2 The use will be for an onshore substation facility accommodated
within a compound containing electrical equipment including
power transformers, switchgear, reactive compensation
equipment, harmonic filters, cables, lightning protection masts,
control buildings, communications masts, back-up generators,
fuel storage, access roads, car parking and hard standing,
fencing and other associated equipment and structures.
b) Amount
5.4.3 The detailed design of the Onshore Substation will be determined
post-consent and would be influenced by factors including the
export voltage, number of cables and the turbine type.
Navitus Bay Wind Park
DCO
Page 24 Design and Access Statement
5.4.4 The substation will require a compound within which will be
located electrical equipment to transform the power generated
by the offshore wind park up to 400 kV. The compound will be
approximately 3 hectares in area, with a maximum height of
infrastructure of up to 14 m for the GIS building, 19 m for the
lightning towers (if required) and up to 11 m high for other
electrical equipment and infrastructure.
5.4.5 The existing ground level could be raised by up to 1000 mm at
the Onshore Substation in order to provide suitable foundations
and facilitate drainage.
5.4.6 These maximum dimensions represent a realistic worst case. As
such, the ES accompanying the DCO has assessed the impact of
the new Onshore Substation on this basis.
c) Layout
5.4.7 The Onshore Substation compound will contain:
transformers;
GIS (gas insulated switchgear) housed in a building;
reactive compensation equipment;
harmonic filters;
control building;
car parking;
access roads;
security fencing;
lightning towers, if required; and
drainage and flood attenuation.
5.4.8 Outside of this compound the Onshore Substation is likely to
have:
hard landscaping;
access tracks;
Navitus Bay Wind Park
DCO
Design and Access Statement Page 25
planting;
fencing; and
utility connections.
5.4.9 An indicative Onshore Substation layout is shown in Figure 5.5.
The Onshore Substation design will be in accordance with
applicable Engineering Recommendations and European and
British Standards and will be carried out during the detailed
design phase. It will consider the following design principles:
substation design will pay due regard to the Green Belt
designation and, within the constraints of procurement, will
ensure that the built form associated with the development
represents only what is reasonably necessary to safely
construct, maintain and operate the onshore substation to
ensure that the impact on the openness of the Green Belt is
kept to a minimum
the height of structures will take into account the heights of
existing screening and will seek to limit the impact of the
development on the surrounding area
landscaping will seek to maximise the screening of the site
from surrounding properties, particularly those from the north
and north-west, in addition to the existing mature screening.
buildings required will be of simple, utilitarian design to
minimise the built form in the Green Belt
areas of hardstanding and vehicle car parking will be kept to a
minimum and will relate to the function of the site.
Fire Damage Zones (FDZ) for equipment containing oil will be
considered when producing the layout to ensure there is
adequate spacing between substation components;
equipment containing oil will have a bund type foundation
with sufficient internal clearance at ground level between the
equipment and the bund wall;
the layout will look to optimise the use of space in order to
minimise the overall Onshore Substation footprint; and
Navitus Bay Wind Park
DCO
Page 26 Design and Access Statement
the Onshore Substation will be designed to mitigate noise
pollution and where possible, locate the largest noise sources
away from noise receptors. Noise mitigation/suppression will
be installed where necessary.
d) Scale
5.4.10 The exact size and scale of each of the elements within the
Onshore Substation are not yet known. However the footprint of
the site is fixed (refer to Works Plan, Document 2.4) along with
the maximum height for any element under the DCO (see
Requirement 10 (Detailed design approval onshore)). The details
of details of its layout, design, scale and external appearance will
be agreed with the relevant planning authority pursuant to
Requirement 10.
5.4.11 The design parameters for the Onshore Substation and
associated equipment have been informed by the surrounding
height of onsite vegetation. This will act as natural screening of
the development to surrounding receptors. Figure 5.5 below
shows the zoning of the Onshore Substation site for each activity
relative to the site boundary.
Navitus Bay Wind Park
DCO
Design and Access Statement Page 27
Figure 5.5 - Indicative Onshore Substation Layout
Navitus Bay Wind Park
DCO
Page 28 Design and Access Statement
5.5 Lighting
a) Landfall and Onshore Cable Corridor
5.5.1 No fixed lighting will be required along the Onshore Cable
Corridor during construction.
5.5.2 At construction compounds and along the Onshore Cable
Corridor, temporary lighting may be required during working
hours in the winter months.
5.5.3 External lighting would be designed and positioned to:
provide the necessary levels for safe working;
minimise risk of accident or injury; and
avoid disturbance to residents and occupiers in the vicinity.
5.5.4 Lighting may be required for 24 hour working at trenchless
installation working areas. As far as is reasonable, appropriate
lighting will be used to direct light towards the working areas.
Lighting would be designed to balance the requirements for safe
access and specific tasks against minimising light pollution and
impact on amenity.
b) Onshore Substation
5.5.5 As a principally unmanned substation there will be two distinct
conditions of lighting for the compound:
unmanned; and
attended site.
5.5.6 The outline lighting requirements for each condition are
discussed below.
i Unmanned
5.5.7 There will be no requirement to provide lighting across the
Onshore Substation compound or plant areas when no personnel
are on site. This is in accordance with the requirements set out
in the National Electrical Safety Code.
Navitus Bay Wind Park
DCO
Design and Access Statement Page 29
ii Attended Site
5.5.8 Switchable lighting for all external and internal areas of the
Onshore Substation will be provided for periods where work is
carried out on site. This switching could consist of manual and/or
movement sensors.
5.5.9 Site attendance for maintenance will be planned to be completed
during daytime hours where possible. Night time working is
expected to be required for reactive and infrequent maintenance
tasks.
5.5.10 In general, external lighting will be floor, building or pole
mounted and internal lighting will be wall and ceiling mounted.
5.6 Landscaping
a) Landfall and Onshore Cable Corridor
5.6.1 Along the Onshore Cable Corridor the excavated trench will be
backfilled and soil compacted to the equivalent density as the
pre-excavated material. Where the soil type varies over the
depth of the trench, the excavated material will be back-filled
and replaced in the same order and to the same thickness as the
existing ground conditions.
5.6.2 Topsoil replacement and final reinstatement will be undertaken
once construction works have completed. Specific reinstatement
measures may need to be implemented in environmentally
sensitive areas and this will be settled after discussions with
landowners and statutory bodies. The reinstatement works will
include, though are not limited to:
removal of the access and haul roads, temporary fencing and
construction compounds;
removal of any temporary drainage; and
replanting as appropriate.
5.6.3 Where the cable corridor goes through hedgerows, rivers and
woodlands specific reinstatement is described in the Ecological
Mitigation Plan (draft) attached to the Code of Construction
Practice (Document 8.5).
Navitus Bay Wind Park
DCO
Page 30 Design and Access Statement
5.6.4 Where applicable, post-construction drainage may be installed to
ensure water does not drain along cable trench lines and that
land is returned to its previous draining state. These drains are
typically laid parallel to the cable trenches.
b) Onshore Substation
5.6.5 The Onshore Substation site was selected partially for its high
level of natural screening. The design seeks to utilise this
screening and to enhance it by including planting and
landscaping (Figure 5.6) to ensure that any residual visibility of
the site is reduced as far as is practicable. The Onshore
Substation compound has been sited at least 20 metres from the
East, West and South sides of the site boundary to enable
landscaping and planting. This reduces to a potential minimum of
10m for a short length at the South East boundary.
5.6.6 The proposed curved access road limits visibility of the site from
the road by removing a clear line of site through the wooded
area.
5.6.7 Heights of the substation buildings and electrical infrastructure
have been determined so as to be below existing screening.
5.6.8 The final Onshore Substation landscape design and management
plan will be determined through consultation with landowners
and stakeholders, and agreed with the relevant planning
authorities (see Requirement 21 (Landscaping design and
management plan)).
Navitus Bay Wind Park
DCO
Design and Access Statement Page 31
Page Left Intentionally Blank
Navitus Bay Wind Park
DCO
Page 32 Design and Access Statement
Figure 5.6 - Indicative Onshore Substation Landscaping Scheme
Navitus Bay Wind Park
DCO
Design and Access Statement Page 33
6. Access
6.1 Access
6.1.1 The following section of the DAS describes the access
requirements and arrangements for the proposed onshore
elements of the Project development during the construction and
operational phases.
6.1.2 Typical vehicles travelling to and from the site during the
construction period will include:
flat bed trucks;
tipper trucks;
low loaders;
excavators;
mobile cranes;
mobile mixers;
delivery vans; and
labour transport (vans and cars).
6.2 Construction Access
a) Landfall
6.2.1 Proposed temporary access and egress arrangements will be
arranged from the B3058 (Milford Road), situated immediately to
the north of the Landfall location and using the existing access
into the car park. There will be two temporary construction
compounds at the Landfall area. A temporary access track will be
constructed to the Landfall compound. This will be for the sole
use of construction vehicles and will be removed upon the
completion of construction activities. Figure 6.1 shows the
proposed Landfall access route.
Navitus Bay Wind Park
DCO
Page 34 Design and Access Statement
Figure 6.1 - Landfall access route
b) Onshore Cable Corridor
6.2.2 Access to the Onshore Cable Corridor will be from temporary
construction compounds. These contain:
construction management offices, car parking and welfare
facilities;
containers for material and equipment storage;
fuel storage and wheel wash facilities;
storage areas for plant and materials; and
waste management facilities.
6.2.3 A total of four temporary construction compounds have been
identified for construction of the onshore cable. The locations
have been selected based on a number of parameters, including
their close proximity to the working width, suitable transport
FF
FF
Def
Def
Pond
Drain
House
Drain
11.6m
Dra
in
Drain
Issues
Cottage
Car Park
Taddiford
Path
(um
)
Legend
Temporary Construction Compound
Proposed Temporary Access Route
This map is the copyright of Navitus Bay Development Ltd. The accuracy, reliability, or completeness of the information is not guaranteed or warranted in any way and Navitus Bay Development Ltd and its
representatives disclaim liability of any kind whatsoever, including, without limitation, liability for quality, performance, merchantability and fitness for a particular purpose arising out of the use, or inability to use the data.
Contains Ordnance Survey data © Crown copyright and database right 2013; © Crown copyright, All rights reserved. 2013 Licence number 0100031673
Navitus Bay Wind Park
DCO
Design and Access Statement Page 35
access and sufficient land area. The construction compounds
where possible have been sited at equal points along the
Onshore Cable Corridor.
6.2.4 Temporary site access will also be required, to provide entry to
and from the working width from the public highway.
6.2.5 A total of 73 site accesses have been identified for the Project.
Wherever possible, the site accesses are based upon using the
nearest suitable point from the public highway. Locations have
been chosen to minimise the environmental implications (e.g.
hedgerow removal has been kept to a minimum).
c) Onshore Substation
6.2.6 Traffic to site will comprise of three types of movements:
daily workforce movements;
deliveries and HGVs; and
abnormal loads.
6.2.7 Construction workforce numbers will vary and suitable temporary
parking will provided within the contractors Construction, Design
and Management (CDM) compound, typically up to 50 spaces.
6.2.8 General deliveries, typically vans and flatbed trucks, will vary
depending on the stage of construction, with peak transport
movements likely during civil construction. HGV movements will
be for the delivery of key components including:
reactors;
steelwork for buildings;
Gas Insulated Switchgear (GIS) electrical equipment;
cable drums;
Static VAR Compensator (SVC) electrical equipment; and
concrete deliveries.
6.2.9 It is anticipated that the only abnormal load deliveries (as
defined by the Road Vehicles (Construction and Use) Regulations
1986) will be for up to three high-voltage transformers. The
Navitus Bay Wind Park
DCO
Page 36 Design and Access Statement
delivery of these items will be coordinated with the local
highways authority and the Highways Agency. The abornmal
loadvehicles used will be multi-axle specialist vehicles with total
lengths over 30 m with a project specific trailer arrangement;
they will be subject to a special abnormal load licence.
6.2.10 All construction access will be obtained from the B3072 (West
Moors Road), through the Mill Nursery plantation and directly
into the site compound. The new access road will allow sufficient
lines of sight along the road for safe access and egress.
Vegetation clearance may be required to create a bell-mouth
entrance during construction. The proposed access road is
designed to minimise direct views into the substation compound.
6.3 Operational access
a) Landfall
6.3.1 Once operational there will be no requirement to have
permanent access to the Landfall. There will be a requirement for
planned maintenance inspections of the Landfall transition joint
bay which will be accessed via a manhole cover. It is not
expected that any plant will be required to carry out the
maintenance.
b) Onshore Cable Corridor
6.3.2 The Onshore Cable Corridor will be monitored throughout
operation and will include a full check on a yearly basis, including
all the joint bays. Access to the Onshore Cable Corridor will
normally be by foot and apart from routine tests the cable will
remain maintenance free. In the event of a cable failure during
operation, a fault finding system will determine if it is mechanical
or electrical, and the fault will be repaired.
Access for inspections and maintenance would be taken from
existing accesses.
c) Onshore Substation
6.3.3 During operation, the Onshore Substation is likely to be
unmanned, requiring only infrequent visits for routine inspection
Navitus Bay Wind Park
DCO
Design and Access Statement Page 37
and maintenance. Such activities would be undertaken by a
small team of technicians for most works.
6.4 Public access
a) Landfall
6.4.1 Public Rights of Way (PRoW) at the Landfall will be managed
during construction with temporary closures and discussions with
the relevant PRoW officer at the Local Planning Authority. The
affected PRoWs are detailed with the PRoW Strategy (Document
8.3). There will be no disruption to access during the operation
and maintenance phase of the Project.
b) Onshore Cable Corridor
6.4.2 PRoW and open access land along the Onshore Cable Corridor
will be managed during construction with temporary closures and
discussions with the relevant PRoW officer at the Local Planning
Authority. The affected PRoWs are detailed with the PRoW
Strategy (Document 8.3). There will be no disruption to access
during the operation and maintenance phase of the Project.
c) Onshore Substation
6.4.3 There are no PRoW within the development footprint of the
Onshore Substation. The Onshore Substation site will be securely
fenced and there will be no public access during the construction
or operational phases of the Project.
Navitus Bay Wind Park
DCO
Page 38 Design and Access Statement
7. References
CABE (2007) Design and Access Statement: How to Read, Write and Use
Them. London. CABE
DCLG (2004) Circular 01/2006 – Guidance on Changes to the
Development Control System. London. CABE
DECC (2011a) Overarching National Policy Statement for Energy (EN-1).
Department for Energy and Climate Change. London. HMSO.
DECC (2011b) National Policy Statement for Renewable Energy
Infrastructure (EN-3). Department for Energy and Climate Change.
London. HMSO.
DECC (2011c) National Policy Statement for Electricity Networks
Infrastructure (EN-5). Department for Energy and Climate Change.
London. HMSO.
Royal Haskoning (2011) Poole and Christchurch Bays Shoreline
Management Plan 2 Sub-cell 5f: Hurst Spit to Durlston Head
Navitus Bay Wind Park
DCO
Design and Access Statement Page 39
8. Glossary
Table 8.1 – Glossary
Term Definition
Alternating Current (AC) The flow of electric charge for which
the direction of flow reverses periodically.
Application The application for development consent for the Project submitted to
the Secretary of State for Energy and Climate Change (formerly the
Infrastructure Planning Commission)
for determination.
Boundary Onshore or Offshore geographical
limits to the Project development area.
Onshore cable A single-core cable
Cable circuit Each cable circuit is made up of 3 single-core onshore cables
Cable route The route of the cables from the Landfall to the Onshore Substation
and onto the grid connection at
Manninton, Dorset.
Development Consent Order (DCO) An order made by the Secretary of
State under the Planning Act 2008 (as amended) granting development
consent for a Nationally Significant
Infrastructure Project.
Environment For the purpose of this document,
environment covers physical, biological and human aspects of the
EIA process.
Environmental Impact Assessment
(EIA)
The process defined in the
Infrastructure Planning (Environmental Impact Assessment)
Regulations 2009 (as amended) [the
EIA Regulations] through which
environmental information on the
Navitus Bay Wind Park
DCO
Page 40 Design and Access Statement
Table 8.1 – Glossary
Term Definition
likely significant environmental
impacts of a proposed development
is collected and assessed to inform the determination of an application
for development consent. The
Secretary of State is required to
take into account the environmental
information in the determination of an application for development
consent.
Environmental Information The information obtained during the
EIA process and including the ES and representations from statutory
consultees and third parties.
Environmental Statement (ES) The document submitted by the developer that contains the
information referred to in Part 1 of Schedule 4 to the EIA Regulations,
as is reasonably required to assess
the environmental effects of the
Project and of any associate development and which the
applicant can, having regard to
particular current knowledge and
methods of assessment, reasonably
be required to compile; and includes at least the information referred to
in Part 2 of Schedule 4 to the EIA
Regulations.
Export cable The electrical connection from an Offshore Substation to the Landfall
location.
Geographic Information System (GIS)
GIS integrates hardware, software, and data for capturing, managing,
analyzing, and displaying all forms of geographically referenced
information.
Navitus Bay Wind Park
DCO
Design and Access Statement Page 41
Table 8.1 – Glossary
Term Definition
Horizontal Directional Drilling (HDD) HDD is a steerable trenchless method of installing underground
pipes, conduits and cables along a
prescribed bore path by using a
surface-launched drilling rig.
Impact The net change to a sensitive receptor as a result of the proposed
Project activities, which could be
positive, negative or neutral.
Joint Bay Where two onshore cable circuits are
joined together in a buried concrete pit.
Landfall The site where the offshore cable joins the onshore cable at Taddiford
Gap, Barton-on-Sea, Hampshire, comprising a construction compound
and access track.
Mean Low Water (MLW) The mean surface water elevation as determined by averaging the heights
of the water at equal intervals of time and the jurisdiction of the local
planning authorities.
Navitus Bay Wind Park The entire Project including the
proposed Offshore Development Area and the Onshore Development
Area. The terms Navitus Bay Wind
Park or Project can be used
interchangeably.
Onshore Cable Corridor The working width, temporary accesses and temporary construction
compounds from the Landfall to the
Onshore Substation and on to the
grid connection point at Mannington.
Onshore Development Area This includes all onshore infrastructure including the Landfall,
the Onshore Cable Corridor and
Navitus Bay Wind Park
DCO
Page 42 Design and Access Statement
Table 8.1 – Glossary
Term Definition
Onshore Substation.
Onshore Substation A new Onshore Substation located near Three Legged Cross containing
switchgear and transformers for collecting electricity from the export
cables and transmitting to the
National Grid 400 kV Substation at
Mannington.
Ramsar Site Area comprising wetlands of international importance, notified
under the Ramsar convention.
Public Rights of Way (PRoW) Paths on which the public have a
legally protected right to pass and re-pass.
Sites of Special Scientific Interest (SSSI)
A wildlife or geological conservation designation denoting a protected
area in the United Kingdom
identified by the Nature Conservancy Council for protection under the
Wildlife and Countryside Act 1981
(as amended).
Source The origin of an impact, such as an activity associated with project
construction, operation, and/or
decommissioning.
Special Areas of Conservation (SAC) Protected sites designated under the
EC Habitats Directive.
Special Protected Areas (SPA) Sites classified in accordance with the EC Directive on the Conservation
of Wild Birds.
Temporary access Accesses taken onto the working
width for construction purposes
Temporary construction compounds Areas outside of the cable working width identified to provide greater
working area (e.g. for trenchless
crossings).
Navitus Bay Wind Park
DCO
Design and Access Statement Page 43
Table 8.1 – Glossary
Term Definition
Wind Turbine Wind Turbine Generator - offshore electricity generating structure
comprising the tower, hub, nacelle
and rotor blades.
Working Width Temporary width required for the
installation of cables during construction, generally 40 m.
Zone Area of seabed demarcated by The Crown Estate for wind farm
development under the Round 3
Offshore Wind Programme.
Navitus Bay Wind Park
DCO
Page 44 Design and Access Statement
9. Abbreviations
Table 9.1 - Abbreviations
Term Definition
AC Alternating current
CDM Construction Design Management
DCO Development Consent Order
EA Environment Agency
EIA Environmental Impact Assessment
EGL Existing ground level
ES Environmental Statement
GIS Gas Insulated Switchgear
Ha Hectare
HDD Horizontal directional drilling
kV Kilovolt (a unit of electromotive force equal to 1000 volts)
m Meter
MHWS Mean High Water Spring
MLW Mean Low Water mark
MOD Ministry of Defence
MW Megawatt
NBDL Navitus Bay Development Limited
OFTO Offshore Transmission Operator
PRoW Public Rights of Ways
SAC Special Area of Conservation
SPA Special Protection Area